{{#Wiki_filter:Exelon Generation Company, LLC Braidwood Station 35100 South Route 53, Suite 84 Braceville, IL 60407-9619 www.exeloncorp.com January 31, 2022 BW220011 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Unit 2 Renewed Facility Operating License No. NPF-77 NRC Docket No. STN 50-457
{{#Wiki_filter:Exelon Generation Company, LLC Braidwood Station 35100 South Route 53, Suite 84 Braceville, IL 60407-9619
 
www.exeloncorp.com
 
January 31, 2022 BW220011
 
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
 
Braidwood Station, Unit 2 Renewed Facility Operating License No. NPF-77 NRC Docket No. STN 50-457


==Subject:==
==Subject:==
Braidwood Station, Unit 2 Inservice Inspection Summary Report Enclosed please find the post-outage summary report for Inservice Inspection (lSI) examinations conducted prior to and during Braidwood Station, Unit 2 Refueling Outage 22 (A2R22). This report is submitted in accordance with the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for the Inservice Inspection of Nuclear Power Plant Components," and ASME Code Case N-532-5, "Repair/Replacement Activity Documentation Requirements and Inservice Inspection Summary Report Preparation and Submission - Section XI, Division 1." provides the Owner's Activity Report (OAR) for lSI activities conducted prior to and during A2R22 including a list of items with flaws or relevant conditions that required evaluation for continued service, and an abstract of repair/replacement activities required for continued service.
Braidwood Station, Unit 2 Inservice Inspection Summary Report
Please direct any questions you may have regarding this submittal to Mr. Richard Schliessmann, acting Regulatory Assurance Manager, at (815) 417-2820.
 
Digitally signed by Keenan, John P.
Enclosed please find the post-outage summary report for Inservice Inspection (lSI) examinations conducted prior to and d uring Braidwood Station, Unit 2 Refueling Outage 2 2 (A2R22). This report is submitted in accordance with the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for the Inservice Inspection of Nuclear Power Plant Components," and ASME Code Case N-532-5, "Repair/Replacement Activity Documentation Requirements and Inservice Inspection Summary Report Preparation and Submission - Section XI, Division 1."
Keenan, John P. DN:        cn=Keenan, John P.
provides the Owner's Activity Report (OAR) for lSI activities conducted prior to and during A2R22 including a list of items with flaws or relevant conditions that required evaluation for continued service, and an abstract of repair/replacement activities required for continued service.
Date: 2022.01.28 09:42:10 -06'00' John P Keenan Site Vice President Braidwood Station Attachments:
 
: 1. Owner's Activity Report (OAR) for refueling outage A2R22 cc:     Regional Administrator - NRC Region III NRC Senior Resident Inspector - Braidwood Station NRR Project Manager - Braidwood Station Illinois Emergency Management Agency - Division of Nuclear Safety}}
Please direct any questions you may have regarding t his submittal to Mr. Richard Schliessmann, acting Regulatory Assurance Manager, at (815) 417-2820.
 
John P Keenan Site Vice President Braidwood Station
 
Attachments:
: 1. Owner's Activity Report (OAR) for r e f u e l i n g o u t a g e A2R22
 
cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Braidwood Station NRR Project Manager - Braidwood Station Illinois Emergency Management Agency - Division of Nuclear Safety}}

Revision as of 19:04, 18 November 2024

Inservice Inspection Summary Report
ML22031A043
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 01/31/2022
From: Keenan J
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML22031A042 List:
References
BW220011
Download: ML22031A043 (1)


Text

Exelon Generation Company, LLC Braidwood Station 35100 South Route 53, Suite 84 Braceville, IL 60407-9619

www.exeloncorp.com

January 31, 2022 BW220011

U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Braidwood Station, Unit 2 Renewed Facility Operating License No. NPF-77 NRC Docket No. STN 50-457

Subject:

Braidwood Station, Unit 2 Inservice Inspection Summary Report

Enclosed please find the post-outage summary report for Inservice Inspection (lSI) examinations conducted prior to and d uring Braidwood Station, Unit 2 Refueling Outage 2 2 (A2R22). This report is submitted in accordance with the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, "Rules for the Inservice Inspection of Nuclear Power Plant Components," and ASME Code Case N-532-5, "Repair/Replacement Activity Documentation Requirements and Inservice Inspection Summary Report Preparation and Submission - Section XI, Division 1."

provides the Owner's Activity Report (OAR) for lSI activities conducted prior to and during A2R22 including a list of items with flaws or relevant conditions that required evaluation for continued service, and an abstract of repair/replacement activities required for continued service.

Please direct any questions you may have regarding t his submittal to Mr. Richard Schliessmann, acting Regulatory Assurance Manager, at (815) 417-2820.

John P Keenan Site Vice President Braidwood Station

Attachments:

1. Owner's Activity Report (OAR) for r e f u e l i n g o u t a g e A2R22

cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Braidwood Station NRR Project Manager - Braidwood Station Illinois Emergency Management Agency - Division of Nuclear Safety