ML21082A085: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:April 9, 2021 MEMORANDUM TO: | {{#Wiki_filter:April 9, 2021 MEMORANDUM TO: | ||
Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | Joshua Borromeo, Chief Containment, Thermal, Chemical, and Fire Protection Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards FROM: | ||
Leslie Perkins, Project Manager /RA/ | |||
Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF MARCH 9, 2021, CLOSED MEETING WITH HOLTEC INTERNATIONAL AND U.S. NUCLEAR REGULATORY COMMISSION REGARDING TOPICAL REPORT FOR ALLOWANCE OF HEAT LOAD PATTERNS IN HI-STORM 100 AND HI-STORM FW SYSTEMS On March 9, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives from Holtec International (Holtec). The purpose of this meeting was for Holtec and NRC staff to discuss the draft safety evaluation (SE) with open items for the Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems. The meeting was noticed on February 26, 2021, and is available at the Agencywide Documents Access and Management System (ADAMS) Accession No. ML21057A313. | OF MARCH 9, 2021, CLOSED MEETING WITH HOLTEC INTERNATIONAL AND U.S. NUCLEAR REGULATORY COMMISSION REGARDING TOPICAL REPORT FOR ALLOWANCE OF HEAT LOAD PATTERNS IN HI-STORM 100 AND HI-STORM FW SYSTEMS On March 9, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives from Holtec International (Holtec). The purpose of this meeting was for Holtec and NRC staff to discuss the draft safety evaluation (SE) with open items for the Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems. The meeting was noticed on February 26, 2021, and is available at the Agencywide Documents Access and Management System (ADAMS) Accession No. ML21057A313. | ||
| Line 29: | Line 30: | ||
As a result of the discussion, there was alignment regarding the path forward for closing out the open items identified. Holtec will formally submit its responses to the open items for the NRC staff review to resolve the open items. Holtec representatives indicated that they would let the NRC staff know when they plan to submit the responses to the open items. | As a result of the discussion, there was alignment regarding the path forward for closing out the open items identified. Holtec will formally submit its responses to the open items for the NRC staff review to resolve the open items. Holtec representatives indicated that they would let the NRC staff know when they plan to submit the responses to the open items. | ||
A list of the attendees is enclosed. | A list of the attendees is enclosed. | ||
Docket Nos. 72-1014 and 72-1032 | Docket Nos. 72-1014 and 72-1032 | ||
==Enclosure:== | ==Enclosure:== | ||
As stated CONTACT: | As stated CONTACT: | ||
Leslie Perkins, NRR/DORL 301-415-2375 | |||
MEETING LIST OF ATTENDEES March 9, 2021 NAME | Enclosure MEETING LIST OF ATTENDEES March 9, 2021 NAME ORGANIZATION Debu Mitra-Majumdar Holtec International (Holtec) | ||
Abrar Mohammad | Abrar Mohammad Holtec Chris Bajwa U.S. Nuclear Regulatory Commission (NRC) | ||
Jason Piotter | Jason Piotter NRC JoAnn Ireland NRC Leslie Perkins NRC | ||
* All Attendees Participated Remotely by Microsoft Teams/Telephone | * All Attendees Participated Remotely by Microsoft Teams/Telephone | ||
Package: ML21082A247 Notice: ML21057A313 Summary: ML21082A085 | Package: ML21082A247 Notice: ML21057A313 Summary: ML21082A085 | ||
NAME | *via email OFFICE NRR/DORL/LLPB/PM* | ||
NRR/DORL/LLPB/LA* | |||
NMSS/DFM/LLPB/BC* | |||
NRR/DORL/LLPB/PM* | |||
NAME LPerkins DHarrison JBorromeo LPerkins DATE 3/22/2021 3/23/2021 4/9/2021 4/9/2021}} | |||
Latest revision as of 10:05, 29 November 2024
| ML21082A085 | |
| Person / Time | |
|---|---|
| Site: | 07201032, Holtec |
| Issue date: | 04/09/2021 |
| From: | Leslie Perkins Licensing Processes Branch |
| To: | Joshua Borromeo NRC/NMSS/DFM/CTCFB |
| Perkins L | |
| Shared Package | |
| ML21082A247 | List: |
| References | |
| EPID L-2020-TOP-0018 | |
| Download: ML21082A085 (3) | |
Text
April 9, 2021 MEMORANDUM TO:
Joshua Borromeo, Chief Containment, Thermal, Chemical, and Fire Protection Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards FROM:
Leslie Perkins, Project Manager /RA/
Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF MARCH 9, 2021, CLOSED MEETING WITH HOLTEC INTERNATIONAL AND U.S. NUCLEAR REGULATORY COMMISSION REGARDING TOPICAL REPORT FOR ALLOWANCE OF HEAT LOAD PATTERNS IN HI-STORM 100 AND HI-STORM FW SYSTEMS On March 9, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives from Holtec International (Holtec). The purpose of this meeting was for Holtec and NRC staff to discuss the draft safety evaluation (SE) with open items for the Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems. The meeting was noticed on February 26, 2021, and is available at the Agencywide Documents Access and Management System (ADAMS) Accession No. ML21057A313.
During the meeting, Holtec representatives and NRC staff discussed the open items identified in the NRC staffs draft SE with open items. Holtec representatives discussed how they planned to address each open item to confirm their understanding of what was needed to close each open item. The NRC staff provided clarification on a couple of the open items in the draft SE.
As a result of the discussion, there was alignment regarding the path forward for closing out the open items identified. Holtec will formally submit its responses to the open items for the NRC staff review to resolve the open items. Holtec representatives indicated that they would let the NRC staff know when they plan to submit the responses to the open items.
A list of the attendees is enclosed.
Docket Nos. 72-1014 and 72-1032
Enclosure:
As stated CONTACT:
Leslie Perkins, NRR/DORL 301-415-2375
Enclosure MEETING LIST OF ATTENDEES March 9, 2021 NAME ORGANIZATION Debu Mitra-Majumdar Holtec International (Holtec)
Abrar Mohammad Holtec Chris Bajwa U.S. Nuclear Regulatory Commission (NRC)
Jason Piotter NRC JoAnn Ireland NRC Leslie Perkins NRC
- All Attendees Participated Remotely by Microsoft Teams/Telephone
Package: ML21082A247 Notice: ML21057A313 Summary: ML21082A085
- via email OFFICE NRR/DORL/LLPB/PM*
NRR/DORL/LLPB/LA*
NMSS/DFM/LLPB/BC*
NRR/DORL/LLPB/PM*
NAME LPerkins DHarrison JBorromeo LPerkins DATE 3/22/2021 3/23/2021 4/9/2021 4/9/2021