{{#Wiki_filter:V. Cusumano                                                                              January 15, 2021 MEMORANDUM TO:             Victor G. Cusumano, Branch Chief Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation FROM:                     Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch /RA/
{{#Wiki_filter:
Division of Safety Systems Office of Nuclear Reactor Regulation
January 15, 2021 MEMORANDUM TO:
Victor G. Cusumano, Branch Chief Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation FROM:
Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch /RA/
Division of Safety Systems Office of Nuclear Reactor Regulation  


==SUBJECT:==
==SUBJECT:==
==SUMMARY==
==SUMMARY==
OF JANUARY 7, 2021, MEETING WITH THE TECHNICAL SPECIFICATIONS TASK FORCE RE: TSTF-577, REVISED FREQUENCIES FOR STEAM GENERATOR TUBE INSPECTIONS On January 7, 2021, a Category 2 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Technical Specifications Task Force (TSTF). The purpose of the meeting was for the NRC staff to provide feedback on their review findings regarding traveler TSTF-577, Revised Frequencies for Steam Generator Tube Inspections (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20160A359). The discussion included key issues and staff position following the audit on Alloy 600TT steam generator tubing. The meeting notice is available in the ADAMS at Accession No. ML21007A036. The NRC staffs presentation is available in ADAMS at Accession No. ML21007A111. A list of attendees is enclosed.
OF JANUARY 7, 2021, MEETING WITH THE TECHNICAL SPECIFICATIONS TASK FORCE RE: TSTF-577, REVISED FREQUENCIES FOR STEAM GENERATOR TUBE INSPECTIONS On January 7, 2021, a Category 2 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Technical Specifications Task Force (TSTF). The purpose of the meeting was for the NRC staff to provide feedback on their review findings regarding traveler TSTF-577, Revised Frequencies for Steam Generator Tube Inspections (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20160A359). The discussion included key issues and staff position following the audit on Alloy 600TT steam generator tubing. The meeting notice is available in the ADAMS at Accession No. ML21007A036. The NRC staffs presentation is available in ADAMS at Accession No. ML21007A111. A list of attendees is enclosed.
No members of the public had comments.
No members of the public had comments.
Project No. 753
Project No. 753  


==Enclosure:==
==Enclosure:==
As stated cc: See next page CONTACT: Michelle C. Honcharik, NRR/DSS 301-415-1774


As stated cc: See next page CONTACT: Michelle C. Honcharik, NRR/DSS 301-415-1774
Package: ML21007A115, Meeting summary: ML21012A322; Meeting notice: ML21007A036; Meeting handout ML21007A111 *via E-mail NRR-106 OFFICE NRR/DSS/STSB*
NRR/DSS/STSB/BC*
NRR/DSS/STSB*
NAME MHoncharik VCusumano MHoncharik DATE 1/14/2021 1/14/2021 1/15/2021


Package: ML21007A115, Meeting summary: ML21012A322; Meeting notice: ML21007A036; Meeting handout ML21007A111 *via E-mail    NRR-106 OFFICE    NRR/DSS/STSB*          NRR/DSS/STSB/BC*        NRR/DSS/STSB*
Enclosure LIST OF ATTENDEES NRC Staff Honcharik, Michelle Purtscher, Pat Terry, Leslie Bloom, Steven Hiser, Allen Makar, Gregory Klein, Paul Johnson, Andrew Tilton, Caroline Hon, Andrew Industry/Public Joyce, Ryan M.
NAME      MHoncharik              VCusumano              MHoncharik DATE      1/14/2021              1/14/2021              1/15/2021 LIST OF ATTENDEES NRC Staff Honcharik, Michelle Purtscher, Pat Terry, Leslie Bloom, Steven Hiser, Allen Makar, Gregory Klein, Paul Johnson, Andrew Tilton, Caroline Hon, Andrew Industry/Public Joyce, Ryan M.
Kusumawatimurray, Putri Moyer, Carol Mann, Brian Vaughan, Jordan L Bakhtiari, Sasan Cothron, Helen Thomas, Brian J.
Kusumawatimurray, Putri Moyer, Carol Mann, Brian Vaughan, Jordan L Bakhtiari, Sasan Cothron, Helen Thomas, Brian J.
Bergman, Jana Enclosure
Bergman, Jana  


Technical Specifications Task Force Project No. 753 cc:
Technical Specifications Task Force Project No. 753 cc:
Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E mail: brian.mann@excelservices.com James P. Miksa Entergy Nuclear Operations, Inc.
Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E mail: brian.mann@excelservices.com James P. Miksa Entergy Nuclear Operations, Inc.
Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E mail: jmiksa@entergy.com Jordan L. Vaughan Duke Energy EC07C / P.O. Box 1006 Charlotte, NC 28202 E mail: jordan.vaughan@duke energy.com Ryan M. Joyce Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-274-EC Birmingham, AL 35243 E mail: rmjoyce@southernco.com David M. Gullott Exelon Generation 4300 Winfield Road Warrenville IL 60555 E mail: David.Gullott@exeloncorp.com Wesley Sparkman Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-226-EC Birmingham, AL 35242 E mail: wasparkm@southernco.com}}
Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E mail: jmiksa@entergy.com Jordan L. Vaughan Duke Energy EC07C / P.O. Box 1006 Charlotte, NC 28202 E mail: jordan.vaughan@duke energy.com Ryan M. Joyce Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-274-EC Birmingham, AL 35243 E mail: rmjoyce@southernco.com David M. Gullott Exelon Generation 4300 Winfield Road Warrenville IL 60555 E mail: David.Gullott@exeloncorp.com Wesley Sparkman Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-226-EC Birmingham, AL 35242 E mail: wasparkm@southernco.com}}

Latest revision as of 11:36, 29 November 2024

Summary of January 7, 2021, Meeting with the Technical Specifications Task Force Re TSTF-577, Revised Frequencies for Steam Generator Tube Inspections
ML21012A322
Person / Time
Site: Technical Specifications Task Force
Issue date: 01/15/2021
From: Michelle Honcharik
NRC/NRR/DSS/STSB
To: Victor Cusumano
NRC/NRR/DSS/STSB
Honcharik, M., NRR/DSS, 301-415-1774
Shared Package
ML21007A115 List:
References
Download: ML21012A322 (4)


Text

January 15, 2021 MEMORANDUM TO:

Victor G. Cusumano, Branch Chief Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation FROM:

Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch /RA/

Division of Safety Systems Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF JANUARY 7, 2021, MEETING WITH THE TECHNICAL SPECIFICATIONS TASK FORCE RE: TSTF-577, REVISED FREQUENCIES FOR STEAM GENERATOR TUBE INSPECTIONS On January 7, 2021, a Category 2 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Technical Specifications Task Force (TSTF). The purpose of the meeting was for the NRC staff to provide feedback on their review findings regarding traveler TSTF-577, Revised Frequencies for Steam Generator Tube Inspections (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20160A359). The discussion included key issues and staff position following the audit on Alloy 600TT steam generator tubing. The meeting notice is available in the ADAMS at Accession No. ML21007A036. The NRC staffs presentation is available in ADAMS at Accession No. ML21007A111. A list of attendees is enclosed.

No members of the public had comments.

Project No. 753

Enclosure:

As stated cc: See next page CONTACT: Michelle C. Honcharik, NRR/DSS 301-415-1774

Package: ML21007A115, Meeting summary: ML21012A322; Meeting notice: ML21007A036; Meeting handout ML21007A111 *via E-mail NRR-106 OFFICE NRR/DSS/STSB*

NRR/DSS/STSB/BC*

NRR/DSS/STSB*

NAME MHoncharik VCusumano MHoncharik DATE 1/14/2021 1/14/2021 1/15/2021

Enclosure LIST OF ATTENDEES NRC Staff Honcharik, Michelle Purtscher, Pat Terry, Leslie Bloom, Steven Hiser, Allen Makar, Gregory Klein, Paul Johnson, Andrew Tilton, Caroline Hon, Andrew Industry/Public Joyce, Ryan M.

Kusumawatimurray, Putri Moyer, Carol Mann, Brian Vaughan, Jordan L Bakhtiari, Sasan Cothron, Helen Thomas, Brian J.

Bergman, Jana

Technical Specifications Task Force Project No. 753 cc:

Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E mail: brian.mann@excelservices.com James P. Miksa Entergy Nuclear Operations, Inc.

Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E mail: jmiksa@entergy.com Jordan L. Vaughan Duke Energy EC07C / P.O. Box 1006 Charlotte, NC 28202 E mail: jordan.vaughan@duke energy.com Ryan M. Joyce Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-274-EC Birmingham, AL 35243 E mail: rmjoyce@southernco.com David M. Gullott Exelon Generation 4300 Winfield Road Warrenville IL 60555 E mail: David.Gullott@exeloncorp.com Wesley Sparkman Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-226-EC Birmingham, AL 35242 E mail: wasparkm@southernco.com