IR 05000255/2019011: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:ber 27, 2019
{{#Wiki_filter:November 27, 2019


==SUBJECT:==
==SUBJECT:==
Line 31: Line 31:


Sincerely,
Sincerely,
/RA/
/RA/  
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 05000255 License No. DPR-20
 
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety  
 
Docket No. 05000255 License No. DPR-20  


===Enclosure:===
===Enclosure:===
As stated
As stated  


==Inspection Report==
==Inspection Report==
Docket Number: 05000255 License Number: DPR-20 Report Number: 05000255/2019011 Enterprise Identifier: I-2019-011-0048 Licensee: Entergy Nuclear Operations, Inc.
Docket Number:
05000255  
 
License Number:
DPR-20  
 
Report Number:
05000255/2019011  
 
Enterprise Identifier: I-2019-011-0048  
 
Licensee:
Entergy Nuclear Operations, Inc.  
 
Facility:
Palisades Nuclear Plant
 
Location:
Covert, MI
 
Inspection Dates:
October 28, 2019 to November 01, 2019
 
Inspectors:
J. Neurauter, Senior Reactor Inspector
 
G. O'Dwyer, Reactor Engineer


Facility: Palisades Nuclear Plant Location: Covert, MI Inspection Dates: October 28, 2019 to November 01, 2019 Inspectors: J. Neurauter, Senior Reactor Inspector G. O'Dwyer, Reactor Engineer D. Szwarc, Senior Reactor Inspector Approved By: Robert C. Daley, Branch Chief Engineering Branch 3 Division of Reactor Safety Enclosure
D. Szwarc, Senior Reactor Inspector  
 
Approved By:
Robert C. Daley, Branch Chief  
 
Engineering Branch 3  
 
Division of Reactor Safety  


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Palisades Nuclear Plant in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Palisades Nuclear Plant in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.


List of Findings and Violations No findings or violations of more than minor significance were identified.
===List of Findings and Violations===
No findings or violations of more than minor significance were identified.


Additional Tracking Items None.
===Additional Tracking Items===
None.


=INSPECTION SCOPES=
=INSPECTION SCOPES=
Line 54: Line 92:


==REACTOR SAFETY==
==REACTOR SAFETY==
===71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)===
{{IP sample|IP=IP 71111.17|count=26}}


===71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01) ===
{{IP sample|IP=IP 71111.17|count=26}}
The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for Title 10 of the Code of Federal Regulations (10 CFR) 50.59 from 2016 to 2019.
The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for Title 10 of the Code of Federal Regulations (10 CFR) 50.59 from 2016 to 2019.
: (1) 17-0122, Changes to Technical Specification Bases 3.8.3 Concerning the Fuel Oil Transfer System, Revision 0
 
: (2) 19-021, EC 76687 / V24A/B/C/D Emergency Diesel Generator Room Ventilation Fans Modify Control Circuit to Resolve CR-PLP-2016-03456, Revision 0
(1)17-0122, Changes to Technical Specification Bases 3.8.3 Concerning the Fuel Oil Transfer System, Revision 0 (2)19-021, EC 76687 / V24A/B/C/D Emergency Diesel Generator Room Ventilation Fans Modify Control Circuit to Resolve CR-PLP-2016-03456, Revision 0 (3)19-022, EC 76688 / V-27A/B/C/D Engineering Safeguards Room Ventilation Fans Modify Circuit to Resolve CR-PLP_2016-03456, Revision 0 (4)17-0030, EC 44749 - Calculation Spent Fuel Pool Dilation Analysis (Calculation EA-WJB-00-01 Revision 2), Revision 0 (5)16-0230, MSM-M-29, Lifting Equipment, Rigging and Tackle Inspection, Revision 0 (6)17-0060, EN-QV-137, Supplier Commercial Grade Survey Procedure, Revision 0 (7)17-0193, EN-DC-214, Freeze Seal Evaluations, Revision 0 (8)18-0191, EN-MA-159, Concrete Anchor Bolt Installation, Revision 0 (9)19-0093, EC 82734 - Temporary Modification to Block CV-3223, Shutdown Cooling Heat Exchanger Inlet Valve, Open during VOP-3223 Removal for Overhaul, Revision 1 (10)16-0201, Licensing Basis Document Change Request (LBDCR 16-048) for Final Safety Analysis Report Section 5.5, Revision 0 (11)18-0090, Technical Specifications Bases Limiting Condition for Operation 3.7.6, Revision 0 (12)17-0094, EC [Engineering Change] 72434: TSR [Temporary Shielding Request]
: (3) 19-022, EC 76688 / V-27A/B/C/D Engineering Safeguards Room Ventilation Fans Modify Circuit to Resolve CR-PLP_2016-03456, Revision 0
2017-095 "P-55B Charging Pump Discharge Line (Elbow on South End and Support Bracket Above FE-0212):, Revision 0 (13)19-028, EC 81574 Evaluate Station Battery Remaining Life Capacity Relative to Ambient Temperature, Revision 0 (14)16-0248, Revise RT-35, Inservice Inspection of Safety Related Components, Revision 0 (15)17-0081, EC 1743, 1R25 Flow Accelerated Corrosion Evaluations, Revision 0 (16)17-0089, Long Term Scaffold 17-026 in 607 Component Cooling Water, Revision 0 (17)17-0139, ACADIA 4 Software Application, Revision 0 (18)18-0135, EC 78263, Revise Calculation EA-GL-8910-02 Torque Loss Calculation for Motor Operated Valves at Elevated Temperatures, Revision 0 (19)18-0143, EC 78472, Temporary Leak Repair of Two 2 Elbow Fittings on Steam Trap Drain Line Upstream of MV-CD190, Isolation Valve for Condensate Return from Main Steam Lines Steam Traps, Revision 0 (20)19-0018, EN-CS-S-008-MULTI, Pipe Wall Thinning Structural Evaluation, Revision 0 (21)19-0046, EC 82059, MO-3010 Spring Hanger, Reconcile Setting, Revision 0 (22)16-0110, EAR [Engineering Assistance Request] 199-0081, "Chemical and Volume Control Declassification", Revision 0 (23)19-0010, Revision of EN-DC-315, Rev 15, Flow Accelerated Corrosion Program; Revision 0 (24)19-0034, change to FSAR Section 9.4.2.1, System Description, to add floating filter used to clear spent fuel pool water; Revision 0 (25)19-0056, COP-2, Chemical and Volume Control System Chemistry, Revision 67; Revision 0 (26)19-0113; Procedure Change SOP-24, Ventilation and Air Conditioning System; Revision
: (4) 17-0030, EC 44749 - Calculation Spent Fuel Pool Dilation Analysis (Calculation EA-WJB-00-01 Revision 2), Revision 0
: (5) 16-0230, MSM-M-29, Lifting Equipment, Rigging and Tackle Inspection, Revision 0
: (6) 17-0060, EN-QV-137, Supplier Commercial Grade Survey Procedure, Revision 0
: (7) 17-0193, EN-DC-214, Freeze Seal Evaluations, Revision 0
: (8) 18-0191, EN-MA-159, Concrete Anchor Bolt Installation, Revision 0
: (9) 19-0093, EC 82734 - Temporary Modification to Block CV-3223, Shutdown Cooling Heat Exchanger Inlet Valve, Open during VOP-3223 Removal for Overhaul, Revision 1
: (10) 16-0201, Licensing Basis Document Change Request (LBDCR 16-048) for Final Safety Analysis Report Section 5.5, Revision 0
: (11) 18-0090, Technical Specifications Bases Limiting Condition for Operation 3.7.6, Revision 0
: (12) 17-0094, EC [Engineering Change] 72434: TSR [Temporary Shielding Request]
2017-095 "P-55B Charging Pump Discharge Line (Elbow on South End and Support Bracket Above FE-0212):, Revision 0
: (13) 19-028, EC 81574 Evaluate Station Battery Remaining Life Capacity Relative to Ambient Temperature, Revision 0
: (14) 16-0248, Revise RT-35, Inservice Inspection of Safety Related Components, Revision 0
: (15) 17-0081, EC 1743, 1R25 Flow Accelerated Corrosion Evaluations, Revision 0
: (16) 17-0089, Long Term Scaffold 17-026 in 607 Component Cooling Water, Revision 0
: (17) 17-0139, ACADIA 4 Software Application, Revision 0
: (18) 18-0135, EC 78263, Revise Calculation EA-GL-8910-02 Torque Loss Calculation for Motor Operated Valves at Elevated Temperatures, Revision 0
: (19) 18-0143, EC 78472, Temporary Leak Repair of Two 2 Elbow Fittings on Steam Trap Drain Line Upstream of MV-CD190, Isolation Valve for Condensate Return from Main Steam Lines Steam Traps, Revision 0
: (20) 19-0018, EN-CS-S-008-MULTI, Pipe Wall Thinning Structural Evaluation, Revision 0
: (21) 19-0046, EC 82059, MO-3010 Spring Hanger, Reconcile Setting, Revision 0
: (22) 16-0110, EAR [Engineering Assistance Request] 199-0081, "Chemical and Volume Control Declassification", Revision 0
: (23) 19-0010, Revision of EN-DC-315, Rev 15, Flow Accelerated Corrosion Program; Revision 0
: (24) 19-0034, change to FSAR Section 9.4.2.1, System Description, to add floating filter used to clear spent fuel pool water; Revision 0
: (25) 19-0056, COP-2, Chemical and Volume Control System Chemistry, Revision 67; Revision 0
: (26) 19-0113; Procedure Change SOP-24, Ventilation and Air Conditioning System; Revision


==INSPECTION RESULTS==
==INSPECTION RESULTS==
Line 95: Line 109:
=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


Inspection Type             Designation   Description or Title                                     Revision or
Inspection
Procedure                                                                                            Date
Procedure
71111.17T Calculations       EA-EC171743-01 Flow Accelerated Corrosion, 1R25 Non-Safety Related Wall 0
Type
Designation
Description or Title
Revision or
Date
71111.17T Calculations
EA-EC171743-01
Flow Accelerated Corrosion, 1R25 Non-Safety Related Wall
Thinning Evaluations
Thinning Evaluations
EA-EC171743-02 Flow Accelerated Corrosion, 1R25 Safety Related Wall     0
EA-EC171743-02
Flow Accelerated Corrosion, 1R25 Safety Related Wall
Thinning Evaluations
Thinning Evaluations
EA-EC171743-03 Engineering Analysis of Component ES-GB-2-E023           0
EA-EC171743-03
EA-WJB-00-01   Spent Fuel Pool Dilution Analysis                         2
Engineering Analysis of Component ES-GB-2-E023
Corrective Action CR-PLP-2016-   Licensing Review of the NRC 4th Quarter 2015 Integrated   03/07/2016
EA-WJB-00-01
Documents        01143          Inspection Report
Spent Fuel Pool Dilution Analysis
CR-PLP-2016-   Temporary Shield Requests for the Charging Pump Cubicles 10/21/2016
Corrective Action
05054          Beyond Allowed Installation Time
Documents
CR-PLP-2017-   Documentation Deficiencies in Process Applicability       01/30/2017
CR-PLP-2016-
00364          Determination Forms
01143
CR-PLP-2017-   Legacy Shielding Installed in Evaporator Concentrate Tank 09/14/2017
Licensing Review of the NRC 4th Quarter 2015 Integrated
225          and Pump Rooms
Inspection Report
CR-PLP-2019-   Remove Temporary Measuring and Test Equipment within     01/24/2019
03/07/2016
00387          90 Days of Installation Or Perform 50.59 Screening for
CR-PLP-2016-
05054
Temporary Shield Requests for the Charging Pump Cubicles
Beyond Allowed Installation Time
10/21/2016
CR-PLP-2017-
00364
Documentation Deficiencies in Process Applicability
Determination Forms
01/30/2017
CR-PLP-2017-
225
Legacy Shielding Installed in Evaporator Concentrate Tank
and Pump Rooms
09/14/2017
CR-PLP-2019-
00387
Remove Temporary Measuring and Test Equipment within
Days of Installation Or Perform 50.59 Screening for
Measuring and Test Equipment to Remain Installed Beyond
Measuring and Test Equipment to Remain Installed Beyond
Days
Days
CR-PLP-2019-   ADMIN 7.14 Does Not Address Extending Temporary           05/07/2019
01/24/2019
01872          Shielding Request Beyond Approved Duration
CR-PLP-2019-
CR-PLP-2019-   Pre-NRC Inspect Audit Identified, Identified Improperly   09/10/2019
01872
03552          Completed Process Applicability Determination
ADMIN 7.14 Does Not Address Extending Temporary
WT-WTPLP-     Evaluate Addressing Maintaining the Seismic Adequacy of   01/31/2017
Shielding Request Beyond Approved Duration
2017-00011    the Chemical and Volume Control System
05/07/2019
Corrective Action CR-PLP-2019-   PAD Log Number 17-0139 had Incorrect Boxes Checked       10/30/2019
CR-PLP-2019-
Documents        04362
03552
Resulting from    CR-PLP-2019-   Calculation Incorrectly Set to Historical in Electronic   10/31/2019
Pre-NRC Inspect Audit Identified, Identified Improperly
Inspection        04379          Database
Completed Process Applicability Determination
CR-PLP-2019-   Configuration Enhancements were Identified Related to     10/31/2019
09/10/2019
04381          Seismic Requirements in the Equipment Database
WT-WTPLP-
Inspection Type         Designation     Description or Title                                       Revision or
2017-00011
Procedure                                                                                            Date
Evaluate Addressing Maintaining the Seismic Adequacy of
Engineering   76687           V-24A/B/C/D Emergency Diesel Generator Rooms               0
the Chemical and Volume Control System
Changes                      Ventilation Fans Modify Control Circuit to Resolve CR-PLP-
01/31/2017
Corrective Action
Documents
Resulting from
Inspection
CR-PLP-2019-
04362
PAD Log Number 17-0139 had Incorrect Boxes Checked
10/30/2019
CR-PLP-2019-
04379
Calculation Incorrectly Set to Historical in Electronic
Database
10/31/2019
CR-PLP-2019-
04381
Configuration Enhancements were Identified Related to
Seismic Requirements in the Equipment Database  
 
10/31/2019
 
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Engineering
Changes
76687
V-24A/B/C/D Emergency Diesel Generator Rooms
Ventilation Fans Modify Control Circuit to Resolve CR-PLP-
2016-03456
2016-03456
76688           V-27A/B/C/D Engineered Safeguards Rooms Cooler Fans         0
76688
V-27A/B/C/D Engineered Safeguards Rooms Cooler Fans
Modify Control Circuit to Resolve CR-PLP-2016-03456
Modify Control Circuit to Resolve CR-PLP-2016-03456
2059           MO-3010 Spring Hanger, Reconcile Setting Basis             0
2059
Miscellaneous Licensing Basis Revise Final Safety Analysis Report Section 5.5.1 to Delete 10/06/2016
MO-3010 Spring Hanger, Reconcile Setting Basis
Document       Site Specific Tornado Missiles
Miscellaneous
Licensing Basis
Document
Change Request
Change Request
16-048
16-048
Licensing Basis Clarify Section 5.5.1 of Final Safety Aanalysis Report      04/24/2017
Revise Final Safety Analysis Report Section 5.5.1 to Delete
Document       (Tornado Missiles) to Accurately Reflect Licensing and
Site Specific Tornado Missiles
Change Request Design Bases of Plant
10/06/2016
Licensing Basis
Document
Change Request
17-0010
17-0010
Procedures   EN-CS-S-008-   Pipe Wall Thinning Structural Evaaluation                  2
Clarify Section 5.5.1 of Final Safety Aanalysis Report
(Tornado Missiles) to Accurately Reflect Licensing and
Design Bases of Plant
04/24/2017
Procedures
EN-CS-S-008-
MULTI
MULTI
EN-DC-214       Freeze Seal Evaluations                                     3
Pipe Wall Thinning Structural Evaaluation
EN-LI-100       Process Applicability Determination                         26
EN-DC-214
EN-MA-119-01   Control, Storage, and Inspection of Lifting Equipment       9
Freeze Seal Evaluations
EN-MA-159       Anchor Bolt Installation                                   1
EN-LI-100
EN-QV-137       Supplier Commercial Grade Survey Procedure                 2
Process Applicability Determination
Work Orders   52705342-01     Spent Fuel Pool Level and Temperature Instrument           01/02/2018
EN-MA-119-01
Control, Storage, and Inspection of Lifting Equipment
EN-MA-159
Anchor Bolt Installation
EN-QV-137
Supplier Commercial Grade Survey Procedure
Work Orders
2705342-01
Spent Fuel Pool Level and Temperature Instrument
Checkout
Checkout
2750453-01     LE/LI-2141 Pre-Refuel Outage Functional Check               09/21/2018
01/02/2018
2750454-01     LE/LI-2142 Pre-Refuel Outage Functional Check               09/21/2018
2750453-01
2837472-01     LE/LI-2141 Channel Functional Check                         08/20/2019
LE/LI-2141 Pre-Refuel Outage Functional Check
2837473-01     LE/LI-2142 Channel Functional Check                         09/16/2019
09/21/2018
6
2750454-01
LE/LI-2142 Pre-Refuel Outage Functional Check
09/21/2018
2837472-01
LE/LI-2141 Channel Functional Check
08/20/2019
2837473-01
LE/LI-2142 Channel Functional Check
09/16/2019
}}
}}

Revision as of 17:24, 25 December 2024

Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000255/2019011
ML19336C651
Person / Time
Site: Palisades Entergy icon.png
Issue date: 11/27/2019
From: Robert Daley
Engineering Branch 3
To: Corbin D
Entergy Nuclear Operations
References
IR 2019011
Download: ML19336C651 (8)


Text

November 27, 2019

SUBJECT:

PALISADES NUCLEAR PLANT - TRIENNIAL INSPECTION OF EVALUATION OF CHANGES, TESTS AND EXPERIMENTS BASELINE INSPECTION REPORT 05000255/2019011

Dear Mr. Corbin:

On November 1, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant and discussed the results of this inspection with Mr. Dale Lucy and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety

Docket No. 05000255 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255

License Number:

DPR-20

Report Number:

05000255/2019011

Enterprise Identifier: I-2019-011-0048

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Palisades Nuclear Plant

Location:

Covert, MI

Inspection Dates:

October 28, 2019 to November 01, 2019

Inspectors:

J. Neurauter, Senior Reactor Inspector

G. O'Dwyer, Reactor Engineer

D. Szwarc, Senior Reactor Inspector

Approved By:

Robert C. Daley, Branch Chief

Engineering Branch 3

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Palisades Nuclear Plant in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for Title 10 of the Code of Federal Regulations (10 CFR) 50.59 from 2016 to 2019.

(1)17-0122, Changes to Technical Specification Bases 3.8.3 Concerning the Fuel Oil Transfer System, Revision 0 (2)19-021, EC 76687 / V24A/B/C/D Emergency Diesel Generator Room Ventilation Fans Modify Control Circuit to Resolve CR-PLP-2016-03456, Revision 0 (3)19-022, EC 76688 / V-27A/B/C/D Engineering Safeguards Room Ventilation Fans Modify Circuit to Resolve CR-PLP_2016-03456, Revision 0 (4)17-0030, EC 44749 - Calculation Spent Fuel Pool Dilation Analysis (Calculation EA-WJB-00-01 Revision 2), Revision 0 (5)16-0230, MSM-M-29, Lifting Equipment, Rigging and Tackle Inspection, Revision 0 (6)17-0060, EN-QV-137, Supplier Commercial Grade Survey Procedure, Revision 0 (7)17-0193, EN-DC-214, Freeze Seal Evaluations, Revision 0 (8)18-0191, EN-MA-159, Concrete Anchor Bolt Installation, Revision 0 (9)19-0093, EC 82734 - Temporary Modification to Block CV-3223, Shutdown Cooling Heat Exchanger Inlet Valve, Open during VOP-3223 Removal for Overhaul, Revision 1 (10)16-0201, Licensing Basis Document Change Request (LBDCR 16-048) for Final Safety Analysis Report Section 5.5, Revision 0 (11)18-0090, Technical Specifications Bases Limiting Condition for Operation 3.7.6, Revision 0 (12)17-0094, EC [Engineering Change] 72434: TSR [Temporary Shielding Request]

2017-095 "P-55B Charging Pump Discharge Line (Elbow on South End and Support Bracket Above FE-0212):, Revision 0 (13)19-028, EC 81574 Evaluate Station Battery Remaining Life Capacity Relative to Ambient Temperature, Revision 0 (14)16-0248, Revise RT-35, Inservice Inspection of Safety Related Components, Revision 0 (15)17-0081, EC 1743, 1R25 Flow Accelerated Corrosion Evaluations, Revision 0 (16)17-0089, Long Term Scaffold 17-026 in 607 Component Cooling Water, Revision 0 (17)17-0139, ACADIA 4 Software Application, Revision 0 (18)18-0135, EC 78263, Revise Calculation EA-GL-8910-02 Torque Loss Calculation for Motor Operated Valves at Elevated Temperatures, Revision 0 (19)18-0143, EC 78472, Temporary Leak Repair of Two 2 Elbow Fittings on Steam Trap Drain Line Upstream of MV-CD190, Isolation Valve for Condensate Return from Main Steam Lines Steam Traps, Revision 0 (20)19-0018, EN-CS-S-008-MULTI, Pipe Wall Thinning Structural Evaluation, Revision 0 (21)19-0046, EC 82059, MO-3010 Spring Hanger, Reconcile Setting, Revision 0 (22)16-0110, EAR [Engineering Assistance Request] 199-0081, "Chemical and Volume Control Declassification", Revision 0 (23)19-0010, Revision of EN-DC-315, Rev 15, Flow Accelerated Corrosion Program; Revision 0 (24)19-0034, change to FSAR Section 9.4.2.1, System Description, to add floating filter used to clear spent fuel pool water; Revision 0 (25)19-0056, COP-2, Chemical and Volume Control System Chemistry, Revision 67; Revision 0 (26)19-0113; Procedure Change SOP-24, Ventilation and Air Conditioning System; Revision

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 1, 2019, the inspectors presented the triennial inspection of evaluation of changes, tests and experiments baseline inspection results to Mr. Dale Lucy and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.17T Calculations

EA-EC171743-01

Flow Accelerated Corrosion, 1R25 Non-Safety Related Wall

Thinning Evaluations

EA-EC171743-02

Flow Accelerated Corrosion, 1R25 Safety Related Wall

Thinning Evaluations

EA-EC171743-03

Engineering Analysis of Component ES-GB-2-E023

EA-WJB-00-01

Spent Fuel Pool Dilution Analysis

Corrective Action

Documents

CR-PLP-2016-

01143

Licensing Review of the NRC 4th Quarter 2015 Integrated

Inspection Report

03/07/2016

CR-PLP-2016-

05054

Temporary Shield Requests for the Charging Pump Cubicles

Beyond Allowed Installation Time

10/21/2016

CR-PLP-2017-

00364

Documentation Deficiencies in Process Applicability

Determination Forms

01/30/2017

CR-PLP-2017-

225

Legacy Shielding Installed in Evaporator Concentrate Tank

and Pump Rooms

09/14/2017

CR-PLP-2019-

00387

Remove Temporary Measuring and Test Equipment within

Days of Installation Or Perform 50.59 Screening for

Measuring and Test Equipment to Remain Installed Beyond

Days

01/24/2019

CR-PLP-2019-

01872

ADMIN 7.14 Does Not Address Extending Temporary

Shielding Request Beyond Approved Duration

05/07/2019

CR-PLP-2019-

03552

Pre-NRC Inspect Audit Identified, Identified Improperly

Completed Process Applicability Determination

09/10/2019

WT-WTPLP-

2017-00011

Evaluate Addressing Maintaining the Seismic Adequacy of

the Chemical and Volume Control System

01/31/2017

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2019-

04362

PAD Log Number 17-0139 had Incorrect Boxes Checked

10/30/2019

CR-PLP-2019-

04379

Calculation Incorrectly Set to Historical in Electronic

Database

10/31/2019

CR-PLP-2019-

04381

Configuration Enhancements were Identified Related to

Seismic Requirements in the Equipment Database

10/31/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

76687

V-24A/B/C/D Emergency Diesel Generator Rooms

Ventilation Fans Modify Control Circuit to Resolve CR-PLP-

2016-03456

76688

V-27A/B/C/D Engineered Safeguards Rooms Cooler Fans

Modify Control Circuit to Resolve CR-PLP-2016-03456

2059

MO-3010 Spring Hanger, Reconcile Setting Basis

Miscellaneous

Licensing Basis

Document

Change Request

16-048

Revise Final Safety Analysis Report Section 5.5.1 to Delete

Site Specific Tornado Missiles

10/06/2016

Licensing Basis

Document

Change Request

17-0010

Clarify Section 5.5.1 of Final Safety Aanalysis Report

(Tornado Missiles) to Accurately Reflect Licensing and

Design Bases of Plant

04/24/2017

Procedures

EN-CS-S-008-

MULTI

Pipe Wall Thinning Structural Evaaluation

EN-DC-214

Freeze Seal Evaluations

EN-LI-100

Process Applicability Determination

EN-MA-119-01

Control, Storage, and Inspection of Lifting Equipment

EN-MA-159

Anchor Bolt Installation

EN-QV-137

Supplier Commercial Grade Survey Procedure

Work Orders

2705342-01

Spent Fuel Pool Level and Temperature Instrument

Checkout

01/02/2018

2750453-01

LE/LI-2141 Pre-Refuel Outage Functional Check

09/21/2018

2750454-01

LE/LI-2142 Pre-Refuel Outage Functional Check

09/21/2018

2837472-01

LE/LI-2141 Channel Functional Check

08/20/2019

2837473-01

LE/LI-2142 Channel Functional Check

09/16/2019