ML053050258: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 24: Line 24:
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - Break
- Break
* NRC Questions 2
* NRC Questions 2


Line 34: Line 34:
* Introduction
* Introduction
* SONGS Grid Requirements
* SONGS Grid Requirements
  - (Ken Johnson)
- (Ken Johnson)
* CAISO and SCE Roles and Responsibilities
* CAISO and SCE Roles and Responsibilities
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - Break
- Break
* NRC Questions 4
* NRC Questions 4


Implementing the GDC GDC-1 7 FSAR I       TS LOcAISO TCA   (App E)
Implementing the GDC GDC-1 7 FSAR I
TS LOcAISO TCA (App E)
The Transmission Control Agreement (TCA) is a FERC approved agreement that the CAISO is committed to fulfill.
The Transmission Control Agreement (TCA) is a FERC approved agreement that the CAISO is committed to fulfill.
5
5
Line 48: Line 49:
...an offsite electric power system...shall...provide sufficient capacity and capability to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained in the event of postulated accidents.
...an offsite electric power system...shall...provide sufficient capacity and capability to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained in the event of postulated accidents.
Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits (not necessarily on separate rights of way) designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.
Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits (not necessarily on separate rights of way) designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.
emphasis added   6
emphasis added 6


GDC1 7           (Continued)
GDC1 7 (Continued)
Each of these circuits shall be designed to be available in sufficient time following a loss of all onsite alternating current power supplies and the other offsite electric power circuit, to assure that specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded.
Each of these circuits shall be designed to be available in sufficient time following a loss of all onsite alternating current power supplies and the other offsite electric power circuit, to assure that specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded.
Provisions shall be included to minimize the probability of losing electric power from any of the remaining supplies as a result of, or coincident with, the loss of power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electric power supplies.
Provisions shall be included to minimize the probability of losing electric power from any of the remaining supplies as a result of, or coincident with, the loss of power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electric power supplies.
Line 65: Line 66:


SONGS SWYD One Line Diagram 230KV SWYD Talega
SONGS SWYD One Line Diagram 230KV SWYD Talega
                                                                                            #2 Santiago           Santiago                                             San Luis Rey San Luis Rey San Luis Rey Talega          4f         SnLusRySnLiRe
# 2 Santiago
                        #1                #2          Serrano   Viejo             # 1           ftz e)
# 1 Santiago
                                                                                                                      # 1          #3
# 2
                                              .I 1      2      3    4       5     6       7   8     9   10     12     13     14 115         16 -       17   18 4                    4-I-4                                                                                    _-
.I Talega San Luis Rey San Luis Rey San Luis Rey 4f e)
SCE
SnLusRySnLiRe Serrano Viejo 1
                                                                            ,Kill:
2 3
SDG&E XI     Unit 2 Unit 3 VI Main wE ManT *pi                -     ,                                                                      _________    i -           ,A
4 5
              'v'J     JL               AL     Reserve
6 7
                                                                                                                    -              I V f W%-I    .
8 9
T T JA Lwv    L                          TfT        Auxiliary Reserve          M Auxiliary 2 A04                2 A06                                                              3 A06 l-           l3   A04 10
10 4
4-I-4
# 1 ftz
# 1 12 13 14 115 16 -
17 18
,Kill:
# 3 SCE SDG&E XI Unit 2 wE ManT Lwv L
'v
* pi
,A Unit 3 VI Main f W%-I i -
'J JL JA AL Reserve fT T
Auxiliary 2 A04 2 A06 I
V Reserve M
Auxiliary T T 3 A06 l-l3 A04 10


Technical Specification
Technical Specification
* Bases 3.8.1 Each offsite circuit must be capable of maintaining rated frequency and voltage, and accepting required loads during an accident, while connected to Class 1E buses.
* Bases 3.8.1 Each offsite circuit must be capable of maintaining rated frequency and voltage, and accepting required loads during an accident, while connected to Class 1 E buses.
* LCO. 3.8.1 Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electrical Power Distribution System (shall be OPERABLE)
* LCO. 3.8.1 Two qualified circuits between the offsite transmission network and the onsite Class 1 E AC Electrical Power Distribution System (shall be OPERABLE)
* SR 3.8.1.1 Verify correct breaker alignment and power availability for each required offsite circuit.
* SR 3.8.1.1 Verify correct breaker alignment and power availability for each required offsite circuit.
* SR 3.8.1.8 Verify capability of automatic and manual transfer of AC power sources from the normal offsite circuit to each alternate required offsite circuit
* SR 3.8.1.8 Verify capability of automatic and manual transfer of AC power sources from the normal offsite circuit to each alternate required offsite circuit
Line 91: Line 105:
CAISO Transmission Control Agreement (continued)
CAISO Transmission Control Agreement (continued)
In order for the offsite power supply to be OPERABLE:
In order for the offsite power supply to be OPERABLE:
/(   The SONGS switchyard voltage must stay within the range of 218 to 238kV under all normal and plant accident conditions
/(
/     It is imperative that a unit trip not impair the Operability of the offsite power system.
The SONGS switchyard voltage must stay within the range of 218 to 238kV under all normal and plant accident conditions
X     Following a trip of a SONGS unit, the SONGS switchyard voltage must recover and be maintained at or above 218kV within 2.5 seconds following the trip.
/
X     The SONGS offsite power source shall be capable of providing 158MW and 96 MVAR to SONGS for normal operation and for shutting down the units during plant DBA conditions.
It is imperative that a unit trip not impair the Operability of the offsite power system.
v     A trip of one SONGS unit shall not cause a sustained grid frequency drop below 59.7 Hertz.
X Following a trip of a SONGS unit, the SONGS switchyard voltage must recover and be maintained at or above 218kV within 2.5 seconds following the trip.
X The SONGS offsite power source shall be capable of providing 158MW and 96 MVAR to SONGS for normal operation and for shutting down the units during plant DBA conditions.
v A trip of one SONGS unit shall not cause a sustained grid frequency drop below 59.7 Hertz.
13
13


Line 106: Line 122:
* SONGS Grid Requirements
* SONGS Grid Requirements
* CAISO and SCE Roles and Responsibilities
* CAISO and SCE Roles and Responsibilities
  - (Jim McIntosh)
- (Jim McIntosh)
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - Break
- Break
* NRC Questions 15
* NRC Questions 15


CAISO and SCE Roles and Responsibilities
CAISO and SCE Roles and Responsibilities
* CAISO is the Control Area Operator
* CAISO is the Control Area Operator Responsible for balancing load and generation Inter control area communication Managing transmission system Directing load curtailment if required:
  - Responsible for balancing load and generation
  - Inter control area communication
  - Managing transmission system
  - Directing load curtailment if required:
* to relieve transmission overloads
* to relieve transmission overloads
* for a generation capacity shortage event 16
* for a generation capacity shortage event 16
Line 123: Line 135:
CAISO and SCE Roles and Responsibilities (continued)
CAISO and SCE Roles and Responsibilities (continued)
* SCE and SDGE are the Transmission Owners /
* SCE and SDGE are the Transmission Owners /
Operators
Operators Responsible for grid construction (additions and modifications)
  - Responsible for grid construction (additions and modifications)
Perform required maintenance Operate all distribution and transmission assets Coordinate transmission operations with the CAISO
  - Perform required maintenance
  - Operate all distribution and transmission assets
  - Coordinate transmission operations with the CAISO
* CAISO, SCE and SDGE comply with all applicable NERC/ WECC Planning and Operating Standards and Criteria.
* CAISO, SCE and SDGE comply with all applicable NERC/ WECC Planning and Operating Standards and Criteria.
17
17


NERC and WECC
NERC and WECC NERC - North American Electric Reliability Council Historically a voluntary reliability organization that has developed voluntary reliability standards.
* NERC - North American Electric Reliability Council
Energy legislation directs NERC to develop mandatory reliability standards.
  - Historically a voluntary reliability             NERC Interconnections organization that has developed                                                                               R  - ,,'
* WECC - Western Electric Coordinating Council Regional reliability council representing western US, Canada and Northern Mexico.
voluntary reliability standards.
One of nine councils under NERC.
r I .e1 r,
Developed mandatory reliability standards after 1996 Western interuption.
                                                          -~            I
Reliability Coordination Centers have been in effect since 1998.
  -  Energy legislation directs NERC to develop mandatory reliability standards.
NERC Interconnections
* WECC - Western Electric                           J NECC          l I      I        MAI Coordinating Council W? ' rI
-~
  -  Regional reliability council                   -jVI0X00:          lI;0? 2    $
I J
representing western US,                             1          ,II ---
I NECC l
0O*JFRCC Canada and Northern Mexico.             Western Interconnection
I MAI W? ' rI
  - One of nine councils under                                 /
-jVI0X00:
                                                                /
I;0?
Eastern Interconnection NERC.                                                   /
l 2
ERCOT    ' .
1
Interconnection    I
,I ---
  - Developed mandatory reliability standards after 1996 Western interuption.
I R r I.e1 r,
  - Reliability Coordination Centers have been in effect since 1998.
Western Interconnection 0O*JFRCC Eastern Interconnection
/
/
/
ERCOT Interconnection I
18 C(o
18 C(o


Line 156: Line 169:
* CAISO and SCE Roles and Responsibilities
* CAISO and SCE Roles and Responsibilities
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
  - (Gary Tarplee)
- (Gary Tarplee)
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - Break
- Break
* NRC Questions 19
* NRC Questions 19


Grid Analysis
Grid Analysis
* CAISO and SCE participate in reviewing grid limits for intertie lines.
* CAISO and SCE participate in reviewing grid limits for intertie lines.
  - System vulnerabilities change between different seasons
System vulnerabilities change between different seasons Results are approved by the WECC.
  - Results are approved by the WECC.
* SCE prepares operating nomograms as part of Grid Control Center Operating Procedure -13 (OP-1 3) that defines the safe operating region for SONGS and the surrounding grid to maintain adequate grid voltage for safety related systems.
* SCE prepares operating nomograms as part of Grid Control Center Operating Procedure -13 (OP-1 3) that defines the safe operating region for SONGS and the surrounding grid to maintain adequate grid voltage for safety related systems.
  - CAISO reviews and accepts results.
CAISO reviews and accepts results.
* CAISO and SCE Operations Engineering will perform analysis on proposed grid changes / outages that are not covered by OP-13, SONGS Voltage, before they are allowed.
* CAISO and SCE Operations Engineering will perform analysis on proposed grid changes / outages that are not covered by OP-13, SONGS Voltage, before they are allowed.
20
20


GCC Operating Procedure               - 13 Developed to identify any transmission outage(s) in conjunction with one SONGS unit off line that could result in the SONGS 230 kV switchyard voltage being below 218 kV.
GCC Operating Procedure - 13 Developed to identify any transmission outage(s) in conjunction with one SONGS unit off line that could result in the SONGS 230 kV switchyard voltage being below 218 kV.
  - 218 kV is required to assure proper operation of the safety systems should the remaining SONGS unit trip.
- 218 kV is required to assure proper operation of the safety systems should the remaining SONGS unit trip.
* Reviewed or updated annually or when necessary due to grid changes.
* Reviewed or updated annually or when necessary due to grid changes.
* Reviewed and approved by the CAISO.
* Reviewed and approved by the CAISO.
Line 178: Line 190:
21
21


OP-13 Nomogram SONGS Off-Line Unit 300                                        Mode Derates*
OP-13 Nomogram 300 0-j LL200 z0C,)
Mode 1-4           -30         f 5-6             0 Critical Units Status 0
U-0 I 100 0
-j                                                Derates*
z 0
LL200 Alamitos3             -25 Alamitos 4             -25 Alamitos 5             -40 Alamitos 6             -40 z                                      Hunt. Beach I         -15 0
SONGS Off-Line Unit Mode Derates*
C,)                                    Hunt. Beach 2         -15   off-line U-0 Encina 1               -5 I 100                                  Encina 2               -5 0                                      Encina 3               -5 z
Mode 1-4  
Encina 4             -20     off-line Encina 5               -90 Southbay   I         -10 Southbay    2        -10 Southbay    3        -10 Southbay    4        -10     off-line 0
-30 f
      -300     -200             -100 0
5-6 0
* Shift Nomogramn Line Down SOUTH OF SONGS MVAR FLOW
Critical Units Status Derates*
( inthe negative Y-Direction)
Alamitos3  
-25 Alamitos 4  
-25 Alamitos 5  
-40 Alamitos 6  
-40 Hunt. Beach I  
-15 Hunt. Beach 2  
-15 off-line Encina 1  
-5 Encina 2  
-5 Encina 3  
-5 Encina 4  
-20 off-line Encina 5  
-90 Southbay I Southbay 2 Southbay 3 Southbay 4
-10
-10
-10
-10 off-line
-300
-200  
-100 SOUTH OF SONGS MVAR FLOW 0
* Shift Nomogramn Line Down
( in the negative Y-Direction)
Palo Verde-Devers Line Out 22 COZ.
Palo Verde-Devers Line Out 22 COZ.


Line 197: Line 229:
23
23


Protection of the Grid by Load Shedding Other SCE                 Other SDG&E SONGS Area Generators             Area Generators 2      3 Western Grid 24
Protection of the Grid by Load Shedding Other SCE Area Generators SONGS 2
3 Other SDG&E Area Generators Western Grid 24


Protection of the Grid by Load Shedding (continued)
Protection of the Grid by Load Shedding (continued)
Manual Methods                               Automatic Underfrequency Load Shedding
Manual Methods
: 1. Voluntary customer interruption
: 1. Voluntary customer interruption Customers sign up for lower rates in exchange for potential interruption If time allows, first group of load interrupted
  -  Customers sign up for       601---      _  _  _    _    _  _    _    _    _
: 2. Mandatory customer interruption If time allows, second group of load interrupted Automatic Method
lower rates in exchange
: 1. Underfrequency load shedding When time does not allow manual interruption Automatic Underfrequency Load Shedding 601---
                                >I for potential interruption
>I C)
  - If time allows, first group of load interrupted       C)
I-Time -*
I-
Point A = 400 MW Load Shed at 59.5 Hz Point B = 400 MW Load Shed at 59.0 Hz Point C = 400 MW Load Shed at 58.5 Hz 25
: 2. Mandatory customer interruption
  -  If time allows, second group of load interrupted                         Time -*
Automatic Method Point A = 400 MW Load Shed at 59.5 Hz
: 1. Underfrequency load shedding                            Point B = 400 MW Load Shed at 59.0 Hz
  -  When time does not                Point C = 400 MW Load Shed at 58.5 Hz allow manual interruption 25


Communications
Communications
Line 222: Line 250:
An Example of Grid Operation August 25, 2005 HVDC Line Outage 27
An Example of Grid Operation August 25, 2005 HVDC Line Outage 27


Chronology of August 25 HVDC Line Outage Time                                               Event 1547   Pacific HVDC line blocked and failed to restart (Sylmar Converter Relay Malfunction). DC Monopolar Ground Return Operation.
Chronology of August 25 HVDC Line Outage Time Event 1547 Pacific HVDC line blocked and failed to restart (Sylmar Converter Relay Malfunction). DC Monopolar Ground Return Operation.
1550   DC Initiating Ramp to Zero in 5 Minutes. CAISO Declares Transmission Emergency and Requests Voluntary Load Curtailment in SP 26.
1550 DC Initiating Ramp to Zero in 5 Minutes. CAISO Declares Transmission Emergency and Requests Voluntary Load Curtailment in SP 26.
1553 System Frequency Declines (59.729 Hz) When BPA Remedial Action Responds to DC Ramp Down.
1553 System Frequency Declines (59.729 Hz) When BPA Remedial Action Responds to DC Ramp Down.
1557 CAISO Requests Mandatory Load Curtailment in SP 26.
1557 CAISO Requests Mandatory Load Curtailment in SP 26.
1558 SCE Switching Centers Initiate Rotating Outages Using EMS.
1558 SCE Switching Centers Initiate Rotating Outages Using EMS.
1608 System Frequency Recovers to 60 Hz.
1608 System Frequency Recovers to 60 Hz.
1617 CAISO Mandatory Load Curtailment Request Reduced by 350 MW.
1617 CAISO Mandatory Load Curtailment Request Reduced by 350 MW.
1634 CAISO Mandatory Load Curtailment Request Terminated.
1634 CAISO Mandatory Load Curtailment Request Terminated.
1708 Voluntary Load Curtailment Request Terminated.
1708 Voluntary Load Curtailment Request Terminated.
1800 Transmission Emergency Terminated.
1800 Transmission Emergency Terminated.
28
28


August 25, 2005 HVDC Line Outage (continued)
August 25, 2005 HVDC Line Outage (continued)
SONGS Voltage SONGS Bus Voltage 8/25/2005 233.5
SONGS Voltage SONGS Bus Voltage 8/25/2005 233.5
            ~~A.,
~~A.,  
              .1-232.5 0   232 231.5 231 230.5 230
.1-232.5 0 232 231.5 231 230.5 230
: 0.       ,  ,    N   N,   N. N .       ' -i Time I   -SONGS     A\erage 220 kV 29
: 0.
N N, N.
N.
-i Time I  
-SONGS A\\erage 220 kV 29


August 25, 2005 HVDC Line Outage (continued)
August 25, 2005 HVDC Line Outage (continued)
System Frequency System Frequency 8125/2005 60.1 60.05 C. *.-
System Frequency System Frequency 8125/2005 60.1 60.05 60 59.95 59.9 N
U
..
                                                          .A.-*.
.*
                                                                                      .. S * &
U.. *.'-*.
                                                                                      .ft :,-a..ft....ft.
S * & 
60 59.95 59.9 N
.. :,-a..ft....ft.
59.85 59.8 59.75 Operability Limit     l   59.7 59.65 b&deg;.-                                                   SP   r-             .42   .S< 4f     N' AO Time
.ft C. *.-
                                                                        -    Frequency 30
.A.-*.
59.85 59.8 59.75 Operability Limit l
59.7 59.65 b&deg;.-
SP r-  
.42  
.S<
4f N'
AO Time Frequency 30


August 25, 2005 HVDC Line Outage (continued)
August 25, 2005 HVDC Line Outage (continued)
CAISO Reserves CAISO Percent Reserves 8/25/2005 9
CAISO Reserves CAISO Percent Reserves 8/25/2005 9
8 7
8 7
6
6 c)
                      '        !.    ,44s; 5
Gl 0
0 c)
CL 5
Gl CL 4
LaCutlmnt L Lad Restoration.,
LoadLaCutlmnt L      Cu tali          t-                    ' L Lad Restoration.,   t*      n    ,
44s;
                                                '        . .,.        ._,;_,_,i
.;,4
                                                                      .;,4
._, ;_,_,i L Load Cu tali t-t n
                                                ,ed
:,ted '
:,ted '
,ed 4
3 2
3 2
1 0
1 0
dk C   N.P                               N.                               '  N         N N N   N N.
dk C
N.41tNf                                                                N e 3q, ap    44N33*      e                                          TieN                          ,0
N.P ap 44N33*
                                                                                              ,~
e 3q, N.41 N.
Time
tNf N.
                                              -    CAISO Operating Reserve             I 31
TieN Time N
N N N
N
,~,0 N e CAISO Operating Reserve I
31


August 25, 2005 HVDC Line Outage (continued)
August 25, 2005 HVDC Line Outage (continued)
Line 280: Line 323:
August 25, 2005 HVDC Line Outage (continued)
August 25, 2005 HVDC Line Outage (continued)
* Observations from this event:
* Observations from this event:
  - Communications between LADWP, CAISO and BPA need to improve on the operation of the HVDC line to reduce the exposure to unnecessary load curtailment.
Communications between LADWP, CAISO and BPA need to improve on the operation of the HVDC line to reduce the exposure to unnecessary load curtailment.
  - CAISO management of the grid preserved grid reliability.
CAISO management of the grid preserved grid reliability.
  - CAISO's broad view of system enabled framework for proper reliability decision.
CAISO's broad view of system enabled framework for proper reliability decision.
  - During the 2003 NE blackout, proper management of grid reliability would have required early load curtailment.
During the 2003 NE blackout, proper management of grid reliability would have required early load curtailment.
33
33


Line 292: Line 335:
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - (Michelle Carr)
- (Michelle Carr)
  - Break
- Break
* NRC Questions 34
* NRC Questions 34


Line 306: Line 349:
PRA Model /Maintenance Rule Program (continued)
PRA Model /Maintenance Rule Program (continued)
Two "off-normal" operating conditions that increase the average LOOP IE (continued)
Two "off-normal" operating conditions that increase the average LOOP IE (continued)
Grid Declared Inoperable -LOOP IE increased by a Factor of 100 based on engineering judgment i-         'l GO 37
Grid Declared Inoperable -LOOP IE increased by a Factor of 1 00 based on engineering judgment i-  
'l GO 37


Agenda
Agenda
Line 314: Line 358:
* SCE Grid Analysis and Operation
* SCE Grid Analysis and Operation
* PRA Model/Maintenance Rule Program
* PRA Model/Maintenance Rule Program
  - Break
- Break
* NRC Questions 38}}
* NRC Questions 38}}

Latest revision as of 14:17, 15 January 2025

SONGS Slides - Meeting with California Edison Company on the San Onofre Nuclear Generating Station the California Independent System Operator (Caiso)
ML053050258
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 10/26/2005
From:
Southern California Edison Co
To:
Office of Nuclear Reactor Regulation
Donohew J N, NRR/DLPM,415-1307
References
Download: ML053050258 (38)


Text

i:

SONGS Interface With the Grid Operator October 26, 2005 1

Agenda

  • Introduction
  • CAISO and SCE Roles and Responsibilities
  • SCE Grid Analysis and Operation
  • PRA Model/Maintenance Rule Program

- Break

  • NRC Questions 2

Purpose of Meeting

  • Discuss SCE and SONGS Interface with CAISO and SCE Generation Operation Center and Grid Control Center
  • Discuss August 25, 2005 Event 3

Agenda

  • Introduction

- (Ken Johnson)

  • CAISO and SCE Roles and Responsibilities
  • SCE Grid Analysis and Operation
  • PRA Model/Maintenance Rule Program

- Break

  • NRC Questions 4

Implementing the GDC GDC-1 7 FSAR I

TS LOcAISO TCA (App E)

The Transmission Control Agreement (TCA) is a FERC approved agreement that the CAISO is committed to fulfill.

5

GDC-17

...an offsite electric power system...shall...provide sufficient capacity and capability to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained in the event of postulated accidents.

Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits (not necessarily on separate rights of way) designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.

emphasis added 6

GDC1 7 (Continued)

Each of these circuits shall be designed to be available in sufficient time following a loss of all onsite alternating current power supplies and the other offsite electric power circuit, to assure that specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded.

Provisions shall be included to minimize the probability of losing electric power from any of the remaining supplies as a result of, or coincident with, the loss of power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electric power supplies.

emphasis added 7

UFSAR

  • The maximum sustained voltage fluctuation for the SCE switchyard is within the limits of 21 8-kV and 238-kV.
  • The preferred power sources are two physically and electrically independent 230-kV systems, one SCE and the other the SDG&E system.
  • Design provisions, which safeguard against loss of power to the switchyard due to electrical disturbances, are supported by detailed analytical electrical studies
  • Loss of the single largest unit on the system will result in a momentary frequency drop of the system of less than 0.2 Hz.

8

SCE Southern Portion Grid Diagram Confidential: Subject to FERC Standards of Conduct 9

SONGS SWYD One Line Diagram 230KV SWYD Talega

  1. 2 Santiago
  1. 1 Santiago
  1. 2

.I Talega San Luis Rey San Luis Rey San Luis Rey 4f e)

SnLusRySnLiRe Serrano Viejo 1

2 3

4 5

6 7

8 9

10 4

4-I-4

  1. 1 ftz
  1. 1 12 13 14 115 16 -

17 18

,Kill:

  1. 3 SCE SDG&E XI Unit 2 wE ManT Lwv L

'v

  • pi

,A Unit 3 VI Main f W%-I i -

'J JL JA AL Reserve fT T

Auxiliary 2 A04 2 A06 I

V Reserve M

Auxiliary T T 3 A06 l-l3 A04 10

Technical Specification

  • Bases 3.8.1 Each offsite circuit must be capable of maintaining rated frequency and voltage, and accepting required loads during an accident, while connected to Class 1 E buses.
  • LCO. 3.8.1 Two qualified circuits between the offsite transmission network and the onsite Class 1 E AC Electrical Power Distribution System (shall be OPERABLE)
  • SR 3.8.1.11 Maintain steady state frequency Ž 59.7 and < 61.2 HZ 11

CAISO Transmission Control Agreement

  • The basic requirement for offsite power supply is that it provide sufficient capacity and capability to safely shut down the reactor and to mitigate certain specified accident scenarios.
  • When this condition is met, the offsite power supply system is considered OPERABLE with respect to the SONG Operating License and Technical Specifications.
  • It is a necessary condition of the Operating License that the offsite power supply be OPERABLE at all times.

12

CAISO Transmission Control Agreement (continued)

In order for the offsite power supply to be OPERABLE:

/(

The SONGS switchyard voltage must stay within the range of 218 to 238kV under all normal and plant accident conditions

/

It is imperative that a unit trip not impair the Operability of the offsite power system.

X Following a trip of a SONGS unit, the SONGS switchyard voltage must recover and be maintained at or above 218kV within 2.5 seconds following the trip.

X The SONGS offsite power source shall be capable of providing 158MW and 96 MVAR to SONGS for normal operation and for shutting down the units during plant DBA conditions.

v A trip of one SONGS unit shall not cause a sustained grid frequency drop below 59.7 Hertz.

13

CAISO Transmission Control Agreement (continued)

System Operating procedures and programs shall be in place to ensure that various system operation conditions, including multiple contingency events, are evaluated and understood, such that impaired or potentially degraded conditions are recognized, assessed and communicated to the SONGS control room.

14

Agenda

  • Introduction
  • CAISO and SCE Roles and Responsibilities

- (Jim McIntosh)

  • SCE Grid Analysis and Operation
  • PRA Model/Maintenance Rule Program

- Break

  • NRC Questions 15

CAISO and SCE Roles and Responsibilities

  • CAISO is the Control Area Operator Responsible for balancing load and generation Inter control area communication Managing transmission system Directing load curtailment if required:
  • to relieve transmission overloads
  • for a generation capacity shortage event 16

CAISO and SCE Roles and Responsibilities (continued)

  • SCE and SDGE are the Transmission Owners /

Operators Responsible for grid construction (additions and modifications)

Perform required maintenance Operate all distribution and transmission assets Coordinate transmission operations with the CAISO

  • CAISO, SCE and SDGE comply with all applicable NERC/ WECC Planning and Operating Standards and Criteria.

17

NERC and WECC NERC - North American Electric Reliability Council Historically a voluntary reliability organization that has developed voluntary reliability standards.

Energy legislation directs NERC to develop mandatory reliability standards.

  • WECC - Western Electric Coordinating Council Regional reliability council representing western US, Canada and Northern Mexico.

One of nine councils under NERC.

Developed mandatory reliability standards after 1996 Western interuption.

Reliability Coordination Centers have been in effect since 1998.

NERC Interconnections

-~

I J

I NECC l

I MAI W? ' rI

-jVI0X00:

I;0?

l 2

1

,I ---

I R r I.e1 r,

Western Interconnection 0O*JFRCC Eastern Interconnection

/

/

/

ERCOT Interconnection I

18 C(o

Agenda

  • Introduction
  • CAISO and SCE Roles and Responsibilities
  • SCE Grid Analysis and Operation

- (Gary Tarplee)

  • PRA Model/Maintenance Rule Program

- Break

  • NRC Questions 19

Grid Analysis

  • CAISO and SCE participate in reviewing grid limits for intertie lines.

System vulnerabilities change between different seasons Results are approved by the WECC.

  • SCE prepares operating nomograms as part of Grid Control Center Operating Procedure -13 (OP-1 3) that defines the safe operating region for SONGS and the surrounding grid to maintain adequate grid voltage for safety related systems.

CAISO reviews and accepts results.

  • CAISO and SCE Operations Engineering will perform analysis on proposed grid changes / outages that are not covered by OP-13, SONGS Voltage, before they are allowed.

20

GCC Operating Procedure - 13 Developed to identify any transmission outage(s) in conjunction with one SONGS unit off line that could result in the SONGS 230 kV switchyard voltage being below 218 kV.

- 218 kV is required to assure proper operation of the safety systems should the remaining SONGS unit trip.

  • Reviewed or updated annually or when necessary due to grid changes.
  • Reviewed and approved by the CAISO.
  • Includes twelve transmission contingencies with various combinations of 28 other generating units and 27 capacitor banks.
  • Nomogram monitored by the SCE GCC and the CAISO.

21

OP-13 Nomogram 300 0-j LL200 z0C,)

U-0 I 100 0

z 0

SONGS Off-Line Unit Mode Derates*

Mode 1-4

-30 f

5-6 0

Critical Units Status Derates*

Alamitos3

-25 Alamitos 4

-25 Alamitos 5

-40 Alamitos 6

-40 Hunt. Beach I

-15 Hunt. Beach 2

-15 off-line Encina 1

-5 Encina 2

-5 Encina 3

-5 Encina 4

-20 off-line Encina 5

-90 Southbay I Southbay 2 Southbay 3 Southbay 4

-10

-10

-10

-10 off-line

-300

-200

-100 SOUTH OF SONGS MVAR FLOW 0

  • Shift Nomogramn Line Down

( in the negative Y-Direction)

Palo Verde-Devers Line Out 22 COZ.

Management of Load and Resource Balance

  • CAISO as the control area operator, is responsible for providing adequate operating reserves.
  • Operating reserves are unloaded generation or resources that can be made available within 10 minutes to respond to the loss of generation to restore load and resource balance.
  • For normal operation, the operating reserve requirement is about 6.8%.
  • If operating reserves are insufficient, the CAISO will procure additional reserves.
  • If no additional reserves are available, then the CAISO will request voluntary load curtailment when reserves fall below 5%. Mandatory load is curtailed if reserves are expected to drop lower.

23

Protection of the Grid by Load Shedding Other SCE Area Generators SONGS 2

3 Other SDG&E Area Generators Western Grid 24

Protection of the Grid by Load Shedding (continued)

Manual Methods

1. Voluntary customer interruption Customers sign up for lower rates in exchange for potential interruption If time allows, first group of load interrupted
2. Mandatory customer interruption If time allows, second group of load interrupted Automatic Method
1. Underfrequency load shedding When time does not allow manual interruption Automatic Underfrequency Load Shedding 601---

>I C)

I-Time -*

Point A = 400 MW Load Shed at 59.5 Hz Point B = 400 MW Load Shed at 59.0 Hz Point C = 400 MW Load Shed at 58.5 Hz 25

Communications

  • Control areas such as CAISO, BPA and LADWP are responsible to communicate system events among effected parties.
  • Control areas are also responsible for coordination of interconnecting transmission and generation outages that effect other control area grids.
  • SCE responsible to coordinate with CAISO any planned maintenance and construction outages, and also forced outages of transmission lines.
  • SCE Grid Control Center communicates to SONGS if offsite power operability cannot be maintained through OP-13.

26

An Example of Grid Operation August 25, 2005 HVDC Line Outage 27

Chronology of August 25 HVDC Line Outage Time Event 1547 Pacific HVDC line blocked and failed to restart (Sylmar Converter Relay Malfunction). DC Monopolar Ground Return Operation.

1550 DC Initiating Ramp to Zero in 5 Minutes. CAISO Declares Transmission Emergency and Requests Voluntary Load Curtailment in SP 26.

1553 System Frequency Declines (59.729 Hz) When BPA Remedial Action Responds to DC Ramp Down.

1557 CAISO Requests Mandatory Load Curtailment in SP 26.

1558 SCE Switching Centers Initiate Rotating Outages Using EMS.

1608 System Frequency Recovers to 60 Hz.

1617 CAISO Mandatory Load Curtailment Request Reduced by 350 MW.

1634 CAISO Mandatory Load Curtailment Request Terminated.

1708 Voluntary Load Curtailment Request Terminated.

1800 Transmission Emergency Terminated.

28

August 25, 2005 HVDC Line Outage (continued)

SONGS Voltage SONGS Bus Voltage 8/25/2005 233.5

~~A.,

.1-232.5 0 232 231.5 231 230.5 230

0.

N N, N.

N.

-i Time I

-SONGS A\\erage 220 kV 29

August 25, 2005 HVDC Line Outage (continued)

System Frequency System Frequency 8125/2005 60.1 60.05 60 59.95 59.9 N

..

.*

U.. *.'-*.

S * & 

.. :,-a..ft....ft.

.ft C. *.-

.A.-*.

59.85 59.8 59.75 Operability Limit l

59.7 59.65 b°.-

SP r-

.42

.S<

4f N'

AO Time Frequency 30

August 25, 2005 HVDC Line Outage (continued)

CAISO Reserves CAISO Percent Reserves 8/25/2005 9

8 7

6 c)

Gl 0

CL 5

LaCutlmnt L Lad Restoration.,

44s;

.;,4

._, ;_,_,i L Load Cu tali t-t n

,ted '

,ed 4

3 2

1 0

dk C

N.P ap 44N33*

e 3q, N.41 N.

tNf N.

TieN Time N

N N N

N

,~,0 N e CAISO Operating Reserve I

31

August 25, 2005 HVDC Line Outage (continued)

  • CAISO had required NERC / WECC control area operating reserves prior to the event.
  • Voltages were not an issue and the load / resource balance recovered within the required timeframe of 15 minutes.
  • After the event the southern part of the ISO control area had insufficient reserves to mitigate an overload of the Midway-Vincent transmission path resulting in the need for load curtailment.
  • Inadequate communication between CAISO, LADWP and BPA contributed to the need for shedding of CAISO load.
  • Grid performed well and grid reliability preserved. All systems operated properly including BPA generator dropping scheme.

32

August 25, 2005 HVDC Line Outage (continued)

  • Observations from this event:

Communications between LADWP, CAISO and BPA need to improve on the operation of the HVDC line to reduce the exposure to unnecessary load curtailment.

CAISO management of the grid preserved grid reliability.

CAISO's broad view of system enabled framework for proper reliability decision.

During the 2003 NE blackout, proper management of grid reliability would have required early load curtailment.

33

Agenda

  • Introduction
  • CAISO and SCE Roles and Responsibilities
  • SCE Grid Analysis and Operation
  • PRA Model/Maintenance Rule Program

- (Michelle Carr)

- Break

  • NRC Questions 34

PRA Model /Maintenance Rule Program

  • The calculated average LOOP IE used in the Safety Monitor for Maintenance Rule (a)(4) serves as a measure of grid reliability on any given day 35

PRA Model /Maintenance Rule Program (continued)

Two "off-normal" operating conditions that increase the average LOOP IE Switchyard Maintenance - Maintenance Personnel, Trucks/Cranes in the Switchyard; Plant-Centered LOOP IE increased by Factor - 3 based on latest draft update to NUREG/CR-5496

  • As a normal practice, switchyard maintenance is conservatively assumed to be in effect in San Onofre's (a)(4) maintenance planning process 36

PRA Model /Maintenance Rule Program (continued)

Two "off-normal" operating conditions that increase the average LOOP IE (continued)

Grid Declared Inoperable -LOOP IE increased by a Factor of 1 00 based on engineering judgment i-

'l GO 37

Agenda

  • Introduction
  • CAISO and SCE Roles and Responsibilities
  • SCE Grid Analysis and Operation
  • PRA Model/Maintenance Rule Program

- Break

  • NRC Questions 38