ML082490720: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:G. L. Johnson (Greg) | {{#Wiki_filter:G. L. Johnson (Greg) | ||
Site Engineering Director Plant Edwin I. Hatch | Site Engineering Director Plant Edwin I. Hatch 1 1028 Hatch Parkway North Baxley, GA 31 51 3 Tel. 912.537.5874 September 3,2008 | ||
COMPANY Phillip K. Niebaum NRC Resident Inspector Nuclear Regulatory Commission Plant Edwin I. Hatch Baxley, GA 3 | \\ | ||
SOUTHERN li COMPANY Phillip K. Niebaum NRC Resident Inspector Nuclear Regulatory Commission Plant Edwin I. Hatch Baxley, GA 3 15 13 | |||
==Dear Mr. Niebaum:== | ==Dear Mr. Niebaum:== | ||
It is my understanding that you wish to use three photographs of the failed coupling for the swing diesel generator and one of the replacement coupling in the NRC inspection report soon to be issued that resulted from the recent special NRC inspection that was conducted. It is also my understanding that the attached pictures were taken by the resident inspector during the course of Plant Hatch's troubleshooting/repair efforts associated with the degraded coupling for the swing diesel generator. I have confirmed that these are pictures of the Hatch swing diesel generator degraded and replacement couplings. | It is my understanding that you wish to use three photographs of the failed coupling for the swing diesel generator and one of the replacement coupling in the NRC inspection report soon to be issued that resulted from the recent special NRC inspection that was conducted. It is also my understanding that the attached pictures were taken by the resident inspector during the course of Plant Hatch's troubleshooting/repair efforts associated with the degraded coupling for the swing diesel generator. I have confirmed that these are pictures of the Hatch swing diesel generator degraded and replacement couplings. | ||
You have permission to use these pictures for the purpose of adding value to the special inspection report and to provide needed perspective in understanding the technical issues involved. | You have permission to use these pictures for the purpose of adding value to the special inspection report and to provide needed perspective in understanding the technical issues involved. | ||
G. L. Johnson Site ~ n g i n e e w i r e c t o r xc: S. B. Tipps File | G. L. Johnson - | ||
Site ~ n g i n e e w i r e c t o r xc: S. B. Tipps File | |||
Crack in rubber gland of the failed 1B EDG coupling viewed from diesel (Photo 1) | Crack in rubber gland of the failed 1B EDG coupling viewed from diesel (Photo 1) | ||
Close up of above crack along inner rim when viewed from diesel (Photo 2) | Close up of above crack along inner rim when viewed from diesel (Photo 2) | ||
Another crack around inner rim on 1B EDG coupling viewed from generator (Photo 3 Replacement coupling for the 1B EDG awaiting installation (Photo 4}} | Another crack around inner rim on 1B EDG coupling viewed from generator (Photo 3 Replacement coupling for the 1B EDG awaiting installation (Photo 4}} | ||
Latest revision as of 15:17, 14 January 2025
| ML082490720 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 09/03/2008 |
| From: | Johnson G Southern Nuclear Operating Co |
| To: | Phil Niebaum NRC/RGN-II/DRP/RPB2 |
| References | |
| Download: ML082490720 (3) | |
Text
G. L. Johnson (Greg)
Site Engineering Director Plant Edwin I. Hatch 1 1028 Hatch Parkway North Baxley, GA 31 51 3 Tel. 912.537.5874 September 3,2008
\\
SOUTHERN li COMPANY Phillip K. Niebaum NRC Resident Inspector Nuclear Regulatory Commission Plant Edwin I. Hatch Baxley, GA 3 15 13
Dear Mr. Niebaum:
It is my understanding that you wish to use three photographs of the failed coupling for the swing diesel generator and one of the replacement coupling in the NRC inspection report soon to be issued that resulted from the recent special NRC inspection that was conducted. It is also my understanding that the attached pictures were taken by the resident inspector during the course of Plant Hatch's troubleshooting/repair efforts associated with the degraded coupling for the swing diesel generator. I have confirmed that these are pictures of the Hatch swing diesel generator degraded and replacement couplings.
You have permission to use these pictures for the purpose of adding value to the special inspection report and to provide needed perspective in understanding the technical issues involved.
G. L. Johnson -
Site ~ n g i n e e w i r e c t o r xc: S. B. Tipps File
Crack in rubber gland of the failed 1B EDG coupling viewed from diesel (Photo 1)
Close up of above crack along inner rim when viewed from diesel (Photo 2)
Another crack around inner rim on 1B EDG coupling viewed from generator (Photo 3 Replacement coupling for the 1B EDG awaiting installation (Photo 4