IR 05000373/2006005: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:October 24, 2006 | ||
==SUBJECT:== | ==SUBJECT:== | ||
| Line 38: | Line 38: | ||
/RA/ | /RA/ | ||
Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure: | Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure: | ||
Inspection Report 05000373/2006005; 05000374/2006005 and 05000373/2006014; 05000374/2006014 w/Attachments: 1. Supplemental Information 2. Confirmatory Measurements Comparison Criteria 3. Trititum Sampling Results cc w/encl: Site Vice President - LaSalle County Station LaSalle County Station Plant Manager Regulatory Assurance Manager - LaSalle County Station Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission | Inspection Report 05000373/2006005; 05000374/2006005 and 05000373/2006014; 05000374/2006014 w/Attachments: | ||
1. Supplemental Information 2. Confirmatory Measurements Comparison Criteria 3. Trititum Sampling Results cc w/encl: | |||
Site Vice President - LaSalle County Station LaSalle County Station Plant Manager Regulatory Assurance Manager - LaSalle County Station Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission | |||
=SUMMARY OF FINDINGS= | =SUMMARY OF FINDINGS= | ||
| Line 45: | Line 47: | ||
The inspection was conducted by resident inspectors and regional inspectors. The report covers a 3-month period of resident inspection, an announced baseline biennial heat sink inspection, and an announced baseline radiation protection inspection. Three Green findings and associated non-cited violations (NCVs) were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using IMC 0609 Significance Determination Process (SDP). Findings for which the SDP does not apply may be "Green," or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000. | The inspection was conducted by resident inspectors and regional inspectors. The report covers a 3-month period of resident inspection, an announced baseline biennial heat sink inspection, and an announced baseline radiation protection inspection. Three Green findings and associated non-cited violations (NCVs) were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using IMC 0609 Significance Determination Process (SDP). Findings for which the SDP does not apply may be "Green," or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000. | ||
A. | A. | ||
Inspector-Identified and Self-Revealing Findings | |||
===Cornerstone: Mitigating Systems=== | ===Cornerstone: Mitigating Systems=== | ||
* | |||
: '''Green.''' | : '''Green.''' | ||
A finding of very low safety significance was identified by inspectors during a quarterly fire protection zone inspection of the 2B Emergency Diesel Generator (EDG) day tank room. Specifically, the inspectors identified a section of structural steel that was missing its requisite fireproof coating and had not been repaired in a timely manner. A non-cited violation of 10 CFR 50, | A finding of very low safety significance was identified by inspectors during a quarterly fire protection zone inspection of the 2B Emergency Diesel Generator (EDG) day tank room. Specifically, the inspectors identified a section of structural steel that was missing its requisite fireproof coating and had not been repaired in a timely manner. A non-cited violation of 10 CFR 50, | ||
| Line 53: | Line 58: | ||
The performance deficiency, identified during review of the event, involved the work planning for the repair of the structural steel fireproof coating. Specifically, in processing the work request, licensee work planners failed to recognize that the missing fireproof coating constituted a design deficiency for a safety-related structure, and was, therefore, required to be corrected in a prompt manner under NRC regulations. The finding was of more than minor significance in that it had a direct impact on the cornerstone objective. Specifically, the inspectors determined that the licensees failure to enact proper corrective action and restore the structural steel fireproof coating in the 2B EDG day tank room for multiple years resulted in a reduction of the reliability and capability of the safety-related structures ability to perform its designed function in the event of a fire. Because of the limited size and location of the missing fireproof coating, and because the EDG rooms at LaSalle Station are protected by an automatic carbon dioxide suppression system, the inspectors determined that the finding was of very low safety significance (Green) and within the licensees response band. Licensee corrective actions included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. The finding was also determined to involve the cross-cutting area of problem identification and resolution. (Sections 1R05 and 4OA2.1) | The performance deficiency, identified during review of the event, involved the work planning for the repair of the structural steel fireproof coating. Specifically, in processing the work request, licensee work planners failed to recognize that the missing fireproof coating constituted a design deficiency for a safety-related structure, and was, therefore, required to be corrected in a prompt manner under NRC regulations. The finding was of more than minor significance in that it had a direct impact on the cornerstone objective. Specifically, the inspectors determined that the licensees failure to enact proper corrective action and restore the structural steel fireproof coating in the 2B EDG day tank room for multiple years resulted in a reduction of the reliability and capability of the safety-related structures ability to perform its designed function in the event of a fire. Because of the limited size and location of the missing fireproof coating, and because the EDG rooms at LaSalle Station are protected by an automatic carbon dioxide suppression system, the inspectors determined that the finding was of very low safety significance (Green) and within the licensees response band. Licensee corrective actions included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. The finding was also determined to involve the cross-cutting area of problem identification and resolution. (Sections 1R05 and 4OA2.1) | ||
* | |||
: '''Green.''' | : '''Green.''' | ||
A finding of very low safety significance was identified by inspectors during observation of a GL 89-13 residual heat removal system heat exchanger (RHR HX) thermal performance test. Specifically, the inspectors identified that the licensees engineering staff failed to develop and use an adequate test procedure to implement the RHR HX performance monitoring program in accordance with docketed commitments and the established NRC Generic Letter (GL) 89-13 program basis. A non-cited violation of 10 CFR 50, Appendix B, | A finding of very low safety significance was identified by inspectors during observation of a GL 89-13 residual heat removal system heat exchanger (RHR HX) thermal performance test. Specifically, the inspectors identified that the licensees engineering staff failed to develop and use an adequate test procedure to implement the RHR HX performance monitoring program in accordance with docketed commitments and the established NRC Generic Letter (GL) 89-13 program basis. A non-cited violation of 10 CFR 50, Appendix B, | ||
| Line 62: | Line 68: | ||
Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. (Section 1R12.2) | Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. (Section 1R12.2) | ||
* | |||
: '''Green.''' | : '''Green.''' | ||
A finding of very low safety significance was identified by the inspectors. | A finding of very low safety significance was identified by the inspectors. | ||
| Line 73: | Line 80: | ||
===Licensee-Identified Violations=== | ===Licensee-Identified Violations=== | ||
A violation of very low safety significance that was identified by the licensee has been reviewed by inspectors. Corrective actions planned or taken by the licensee have been entered into the licensees corrective action program. The violation and corrective action tracking number is listed in Section 4OA7 of this report. | A violation of very low safety significance that was identified by the licensee has been reviewed by inspectors. Corrective actions planned or taken by the licensee have been entered into the licensees corrective action program. The violation and corrective action tracking number is listed in Section 4OA7 of this report. | ||
| Line 79: | Line 85: | ||
===Summary of Plant Status=== | ===Summary of Plant Status=== | ||
Unit 1 The unit began the inspection period operating at full power. On September 3, 2006, reactor power was reduced to approximately 66 percent to recover two control rods inserted for hydraulic control unit maintenance, to facilitate a control rod pattern adjustment, and to perform control rod scram timing and channel deformation surveillance activities. Operation at full power resumed on September 4, 2006, and the unit continued to operate at or near full power for the remainder of the inspection period. | Unit 1 The unit began the inspection period operating at full power. On September 3, 2006, reactor power was reduced to approximately 66 percent to recover two control rods inserted for hydraulic control unit maintenance, to facilitate a control rod pattern adjustment, and to perform control rod scram timing and channel deformation surveillance activities. Operation at full power resumed on September 4, 2006, and the unit continued to operate at or near full power for the remainder of the inspection period. | ||
| Line 87: | Line 92: | ||
==REACTOR SAFETY== | ==REACTOR SAFETY== | ||
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and | Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness {{a|1R04}} | ||
{{a|1R04}} | |||
==1R04 Equipment Alignment== | ==1R04 Equipment Alignment== | ||
{{IP sample|IP=IP 71111.04}} | {{IP sample|IP=IP 71111.04}} | ||
===.1 Semiannual Complete System Alignment Verification=== | ===.1 Semiannual Complete System Alignment Verification=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
Due to the systems risk significance, the inspectors selected the Unit 1 and 2 standby liquid control (SLC) systems for a complete alignment verification. The inspectors walked down the system to verify mechanical and electrical equipment lineups, component labeling, component lubrication, component and equipment cooling, hangers and supports, operability of support systems, and to ensure that ancillary equipment or debris did not interfere with equipment operation. | Due to the systems risk significance, the inspectors selected the Unit 1 and 2 standby liquid control (SLC) systems for a complete alignment verification. The inspectors walked down the system to verify mechanical and electrical equipment lineups, component labeling, component lubrication, component and equipment cooling, hangers and supports, operability of support systems, and to ensure that ancillary equipment or debris did not interfere with equipment operation. | ||
| Line 102: | Line 107: | ||
===.2 Quarterly Partial System Alignment Verifications=== | ===.2 Quarterly Partial System Alignment Verifications=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors performed partial alignment verifications on the following equipment trains to verify operability and proper equipment lineup. These systems were selected based upon risk significance, plant configuration, system work or testing, or inoperable or degraded conditions: | The inspectors performed partial alignment verifications on the following equipment trains to verify operability and proper equipment lineup. These systems were selected based upon risk significance, plant configuration, system work or testing, or inoperable or degraded conditions: | ||
| Line 116: | Line 120: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R05}} | No findings of significance were identified. {{a|1R05}} | ||
==1R05 Fire Protection== | ==1R05 Fire Protection== | ||
{{IP sample|IP=IP 71111.05}} | {{IP sample|IP=IP 71111.05}} | ||
===.1 Quarterly Fire Protection Zone Inspections=== | ===.1 Quarterly Fire Protection Zone Inspections=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors walked down the following risk significant areas looking for any fire protection issues. The inspectors selected areas containing systems, structures, or components that the licensee identified as important to reactor safety: | The inspectors walked down the following risk significant areas looking for any fire protection issues. The inspectors selected areas containing systems, structures, or components that the licensee identified as important to reactor safety: | ||
| Line 127: | Line 132: | ||
* Fire Zone 8C2 - Unit 2, Division 2, EDG fuel tank room, 674'0"; | * Fire Zone 8C2 - Unit 2, Division 2, EDG fuel tank room, 674'0"; | ||
* Fire Zone 4E2 - Unit 2, auxiliary equipment room, 731'0"; | * Fire Zone 4E2 - Unit 2, auxiliary equipment room, 731'0"; | ||
* Fire Zone 4E4 - Unit 2, Division 2, essential switchgear room ,731'0"; | * Fire Zone 4E4 - Unit 2, Division 2, essential switchgear room,731'0"; | ||
* Fire Zone 5B13 - Balance-of-plant cable zone, 731'0"; | * Fire Zone 5B13 - Balance-of-plant cable zone, 731'0"; | ||
* Fire Zone 2H1 - Unit 1, general area, 694'6"; | * Fire Zone 2H1 - Unit 1, general area, 694'6"; | ||
| Line 160: | Line 165: | ||
The licensee entered this issue into their CAP as issue report (IR) 515168. Corrective actions completed by the licensee included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion XVI, is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000374/2006005-01) | The licensee entered this issue into their CAP as issue report (IR) 515168. Corrective actions completed by the licensee included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion XVI, is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000374/2006005-01) | ||
{{a|1R06}} | {{a|1R06}} | ||
==1R06 Flood Protection Measures== | ==1R06 Flood Protection Measures== | ||
{{IP sample|IP=IP 71111.06}} | {{IP sample|IP=IP 71111.06}} | ||
===.1 Semiannual Internal Flooding Review=== | ===.1 Semiannual Internal Flooding Review=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed the licensee's flooding mitigation plans and equipment to determine consistency with design requirements and the risk analysis assumptions related to internal flooding. The following specific plant areas particularly susceptible to internal flooding were inspected: | The inspectors reviewed the licensee's flooding mitigation plans and equipment to determine consistency with design requirements and the risk analysis assumptions related to internal flooding. The following specific plant areas particularly susceptible to internal flooding were inspected: | ||
| Line 175: | Line 181: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R07}} | No findings of significance were identified. {{a|1R07}} | ||
==1R07 Heat Sink Performance== | ==1R07 Heat Sink Performance== | ||
{{IP sample|IP=IP 71111.07B}} | {{IP sample|IP=IP 71111.07B}} | ||
===.1 Biennial Review of Heat Sink Performance=== | ===.1 Biennial Review of Heat Sink Performance=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed the performance of the Unit 1 and Unit 2 HPCS pump room coolers, the Unit 1 and Unit 2 LPCS pump/RCIC pump room coolers, and the Unit 1 LPCS pump motor cooler. These heat exchangers were chosen for review based on their high risk assessment worth in the licensee's probabilistic safety analysis. | The inspectors reviewed the performance of the Unit 1 and Unit 2 HPCS pump room coolers, the Unit 1 and Unit 2 LPCS pump/RCIC pump room coolers, and the Unit 1 LPCS pump motor cooler. These heat exchangers were chosen for review based on their high risk assessment worth in the licensee's probabilistic safety analysis. | ||
| Line 195: | Line 202: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R11}} | No findings of significance were identified. {{a|1R11}} | ||
==1R11 Licensed Operator Requalification Program== | ==1R11 Licensed Operator Requalification Program== | ||
{{IP sample|IP=IP 71111.11}} | {{IP sample|IP=IP 71111.11}} | ||
| Line 207: | Line 215: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R12}} | No findings of significance were identified. {{a|1R12}} | ||
==1R12 Maintenance Effectiveness== | ==1R12 Maintenance Effectiveness== | ||
{{IP sample|IP=IP 71111.12}} | {{IP sample|IP=IP 71111.12}} | ||
===.1 (Closed) Unresolved Item (URI) 05000373/2006004-01; 05000374/2006004-01:=== | ===.1 (Closed) Unresolved Item (URI) 05000373/2006004-01; 05000374/2006004-01:=== | ||
Adequacy of B Control Room Ventilation (VC) Compressor Operability Determinations and Post-Maintenance Tests. | |||
Adequacy of B Control Room Ventilation (VC) Compressor Operability Determinations | |||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
| Line 223: | Line 232: | ||
The inspectors reviewed the licensees root cause report, documented under IR 497654, which had not been completed at the end of the previous inspection quarter. No findings of significance or violations of regulatory requirements were identified. | The inspectors reviewed the licensees root cause report, documented under IR 497654, which had not been completed at the end of the previous inspection quarter. No findings of significance or violations of regulatory requirements were identified. | ||
===.2 (Closed) URI 05000373/2006003-01; 05000374/2006003-01: | ===.2 (Closed) URI 05000373/2006003-01; 05000374/2006003-01:=== | ||
RHR Heat Exchanger (HX) Thermal Performance Testing and NRC Generic Letter (GL) 89-13 Conformance Issues. | |||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
| Line 271: | Line 279: | ||
The licensee had entered this issue into their corrective action program as IRs 458571, 463253, 473455, 478852, 479741, 500835, 513814, 515613, 522479, 522487, 522493, 534870, 534872, 534875, 534877, and 534889. Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion V is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000373/2006005-02; 05000374/2006005-02) | The licensee had entered this issue into their corrective action program as IRs 458571, 463253, 473455, 478852, 479741, 500835, 513814, 515613, 522479, 522487, 522493, 534870, 534872, 534875, 534877, and 534889. Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion V is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000373/2006005-02; 05000374/2006005-02) | ||
{{a|1R13}} | {{a|1R13}} | ||
==1R13 Maintenance Risk Assessments and Emergent Work Control== | ==1R13 Maintenance Risk Assessments and Emergent Work Control== | ||
{{IP sample|IP=IP 71111.13}} | {{IP sample|IP=IP 71111.13}} | ||
| Line 290: | Line 299: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R15}} | No findings of significance were identified. {{a|1R15}} | ||
==1R15 Operability Evaluations== | ==1R15 Operability Evaluations== | ||
{{IP sample|IP=IP 71111.15}} | {{IP sample|IP=IP 71111.15}} | ||
| Line 308: | Line 318: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R19}} | No findings of significance were identified. {{a|1R19}} | ||
==1R19 Post-Maintenance Testing== | ==1R19 Post-Maintenance Testing== | ||
{{IP sample|IP=IP 71111.19}} | {{IP sample|IP=IP 71111.19}} | ||
| Line 326: | Line 337: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1R22}} | No findings of significance were identified. {{a|1R22}} | ||
==1R22 Surveillance Testing== | ==1R22 Surveillance Testing== | ||
{{IP sample|IP=IP 71111.22}} | {{IP sample|IP=IP 71111.22}} | ||
===.1 General Surveillance Tests=== | ===.1 General Surveillance Tests=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The Inspectors selected the following general surveillance test activities for review. | The Inspectors selected the following general surveillance test activities for review. | ||
| Line 347: | Line 359: | ||
===.2 Inservice Testing (IST) Required by the American Society of Mechanical Engineers=== | ===.2 Inservice Testing (IST) Required by the American Society of Mechanical Engineers=== | ||
Operations and Maintenance Code | Operations and Maintenance Code | ||
| Line 358: | Line 369: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|1EP6}} | No findings of significance were identified. {{a|1EP6}} | ||
==1EP6 Drill Evaluation== | ==1EP6 Drill Evaluation== | ||
{{IP sample|IP=IP 71114.06}} | {{IP sample|IP=IP 71114.06}} | ||
| Line 375: | Line 387: | ||
===.1 Review of Licensee Performance Indicators for the Occupational Exposure Cornerstone=== | ===.1 Review of Licensee Performance Indicators for the Occupational Exposure Cornerstone=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed the licensees occupational exposure control cornerstone performance indicators (PIs) to determine whether or not the conditions surrounding the PIs had been evaluated and whether identified problems had been entered into the corrective action program for resolution. | The inspectors reviewed the licensees occupational exposure control cornerstone performance indicators (PIs) to determine whether or not the conditions surrounding the PIs had been evaluated and whether identified problems had been entered into the corrective action program for resolution. | ||
| Line 385: | Line 396: | ||
===.2 Plant Walkdowns and Radiation Work Permit Reviews=== | ===.2 Plant Walkdowns and Radiation Work Permit Reviews=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed radiation work permits (RWPs) for airborne radioactivity areas to verify barrier integrity and engineering controls performance (e.g., high efficiency particulate air ventilation system operation, etc.) and to determine if there was a potential for individual worker internal exposures of greater than 50 millirem committed effective dose equivalent. No areas of the plant were under airborne radioactivity work controls. | The inspectors reviewed radiation work permits (RWPs) for airborne radioactivity areas to verify barrier integrity and engineering controls performance (e.g., high efficiency particulate air ventilation system operation, etc.) and to determine if there was a potential for individual worker internal exposures of greater than 50 millirem committed effective dose equivalent. No areas of the plant were under airborne radioactivity work controls. | ||
| Line 401: | Line 411: | ||
===.3 Problem Identification and Resolution=== | ===.3 Problem Identification and Resolution=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed licensee documentation packages for all PI events occurring since the last inspection to determine if any of these PI events involved dose rates >25 R/hr at 30 centimeters or >500 R/hr at 1 meter. No PI events occurred since the last inspection. Barriers were evaluated for failure and to determine if there were any barriers left to prevent personnel access. Unintended exposures >100 millirem total effective dose equivalent (or >5 rem shallow dose equivalent or >1.5 rem lens dose equivalent) were evaluated to determine if there were any regulatory overexposures or if there was a substantial potential for an overexposure. There were no unintended exposures of this magnitude. | The inspectors reviewed licensee documentation packages for all PI events occurring since the last inspection to determine if any of these PI events involved dose rates >25 R/hr at 30 centimeters or >500 R/hr at 1 meter. No PI events occurred since the last inspection. Barriers were evaluated for failure and to determine if there were any barriers left to prevent personnel access. Unintended exposures >100 millirem total effective dose equivalent (or >5 rem shallow dose equivalent or >1.5 rem lens dose equivalent) were evaluated to determine if there were any regulatory overexposures or if there was a substantial potential for an overexposure. There were no unintended exposures of this magnitude. | ||
| Line 411: | Line 420: | ||
===.4 High Risk Significant, High Dose Rate High Radiation Area (HRA) and Very High=== | ===.4 High Risk Significant, High Dose Rate High Radiation Area (HRA) and Very High=== | ||
Radiation Area (VHRA) Controls | Radiation Area (VHRA) Controls | ||
| Line 427: | Line 435: | ||
===.5 RP Technician Proficiency=== | ===.5 RP Technician Proficiency=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
During job performance observations, the inspectors evaluated RP technician performance with respect to RP work requirements and evaluated whether they were aware of the radiological conditions in their workplace, the RWP controls and limits in place, and if their performance was consistent with their training and qualifications with respect to the radiological hazards and work activities. | During job performance observations, the inspectors evaluated RP technician performance with respect to RP work requirements and evaluated whether they were aware of the radiological conditions in their workplace, the RWP controls and limits in place, and if their performance was consistent with their training and qualifications with respect to the radiological hazards and work activities. | ||
| Line 440: | Line 447: | ||
===.1 Inspection Planning=== | ===.1 Inspection Planning=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed the UFSAR to identify applicable radiation monitors associated with measuring transient HRAs and VHRAs including those used in remote emergency assessment. The inspectors identified the types of portable radiation detection instrumentation used for job coverage of HRA work, including fixed area radiation monitors used to provide radiological information in various plant areas and continuous air monitors used to assess airborne radiological conditions and work areas with the potential for workers to receive a 50 millirem or greater committed effective dose equivalent. Contamination monitors, whole body counters, and those radiation detection instruments utilized for the release of personnel and equipment from the radiologically controlled area were also identified. | The inspectors reviewed the UFSAR to identify applicable radiation monitors associated with measuring transient HRAs and VHRAs including those used in remote emergency assessment. The inspectors identified the types of portable radiation detection instrumentation used for job coverage of HRA work, including fixed area radiation monitors used to provide radiological information in various plant areas and continuous air monitors used to assess airborne radiological conditions and work areas with the potential for workers to receive a 50 millirem or greater committed effective dose equivalent. Contamination monitors, whole body counters, and those radiation detection instruments utilized for the release of personnel and equipment from the radiologically controlled area were also identified. | ||
| Line 450: | Line 456: | ||
===.2 Identification and Walkdowns of Additional Radiation Monitoring Instrumentation=== | ===.2 Identification and Walkdowns of Additional Radiation Monitoring Instrumentation=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors conducted walkdowns of selected area radiation monitors (ARMs)to verify that they were located as described in the UFSAR and were adequately positioned relative to the potential source(s) of radiation they were intended to monitor. Walkdowns were also conducted of those areas where portable survey instruments were calibrated/repaired and maintained for RP staff use to determine if those instruments designated ready for use were sufficient in number to support the RP program, had current calibration stickers, were operable, and were in adequate physical condition. Additionally, the inspectors observed the licensees instrument calibration units and the radiation sources used for instrument checks to assess their material condition and discussed their use with RP staff to determine if they were used appropriately. Licensee personnel demonstrated the methods for performing source checks of portable survey instruments. | The inspectors conducted walkdowns of selected area radiation monitors (ARMs)to verify that they were located as described in the UFSAR and were adequately positioned relative to the potential source(s) of radiation they were intended to monitor. Walkdowns were also conducted of those areas where portable survey instruments were calibrated/repaired and maintained for RP staff use to determine if those instruments designated ready for use were sufficient in number to support the RP program, had current calibration stickers, were operable, and were in adequate physical condition. Additionally, the inspectors observed the licensees instrument calibration units and the radiation sources used for instrument checks to assess their material condition and discussed their use with RP staff to determine if they were used appropriately. Licensee personnel demonstrated the methods for performing source checks of portable survey instruments. | ||
| Line 460: | Line 465: | ||
===.3 Calibration and Testing of Radiation Monitoring Instrumentation=== | ===.3 Calibration and Testing of Radiation Monitoring Instrumentation=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors selectively reviewed calibration data for radiological instrumentation associated with monitoring transient high and/or very high radiation areas, instruments used for remote emergency assessment, and radiation monitors used to identify personnel contamination and for assessment of internal exposures to verify that the instruments had been calibrated as required by the licensees procedures, consistent with industry and regulatory standards. The inspectors also reviewed alarm setpoints for selected ARMs to verify that they were established consistent with the UFSAR or Technical Specifications, as applicable, and were consistent with industry practices and regulatory guidance. Specifically, the inspectors reviewed calibration procedures and the most recent calibration records and/or source output verification documents for the following radiation monitoring instrumentation and instrument calibration equipment: | The inspectors selectively reviewed calibration data for radiological instrumentation associated with monitoring transient high and/or very high radiation areas, instruments used for remote emergency assessment, and radiation monitors used to identify personnel contamination and for assessment of internal exposures to verify that the instruments had been calibrated as required by the licensees procedures, consistent with industry and regulatory standards. The inspectors also reviewed alarm setpoints for selected ARMs to verify that they were established consistent with the UFSAR or Technical Specifications, as applicable, and were consistent with industry practices and regulatory guidance. Specifically, the inspectors reviewed calibration procedures and the most recent calibration records and/or source output verification documents for the following radiation monitoring instrumentation and instrument calibration equipment: | ||
| Line 476: | Line 480: | ||
===.4 Problem Identification and Resolution=== | ===.4 Problem Identification and Resolution=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed the licensees CAP documents and any special reports that involved personnel contamination monitor alarms due to personnel internal exposures to verify that identified problems were entered into the CAP for resolution. Licensee self-assessments, audits, and associated CAP records were also reviewed to verify that problems with radiological instrumentation or self-contained breathing apparatus were identified, characterized, prioritized, and resolved effectively using the CAP. | The inspectors reviewed the licensees CAP documents and any special reports that involved personnel contamination monitor alarms due to personnel internal exposures to verify that identified problems were entered into the CAP for resolution. Licensee self-assessments, audits, and associated CAP records were also reviewed to verify that problems with radiological instrumentation or self-contained breathing apparatus were identified, characterized, prioritized, and resolved effectively using the CAP. | ||
| Line 496: | Line 499: | ||
===.5 RP Technician Instrument Use=== | ===.5 RP Technician Instrument Use=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors selectively verified that calibrations for those radiation survey instruments recently used by the licensee and for those currently designated for use had not lapsed. The inspectors also discussed instrument calibration methods and source response check practices with radiation protection staff and observed staff complete instrument source checks prior to use. | The inspectors selectively verified that calibrations for those radiation survey instruments recently used by the licensee and for those currently designated for use had not lapsed. The inspectors also discussed instrument calibration methods and source response check practices with radiation protection staff and observed staff complete instrument source checks prior to use. | ||
| Line 506: | Line 508: | ||
===.6 Self-Contained Breathing Apparatus (SCBA) Maintenance/Inspection and User Training=== | ===.6 Self-Contained Breathing Apparatus (SCBA) Maintenance/Inspection and User Training=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed aspects of the licensees respiratory protection program for compliance with the requirements of Subpart H of 10 CFR Part 20 and to determine if SCBAs were properly maintained and ready for emergency use. The inspectors reviewed records of inspection and functional tests for all SCBAs staged in the plant that were required by the licensees emergency plan. The inspectors verified the licensees capabilities for refilling and transporting SCBA air bottles during emergency conditions. | The inspectors reviewed aspects of the licensees respiratory protection program for compliance with the requirements of Subpart H of 10 CFR Part 20 and to determine if SCBAs were properly maintained and ready for emergency use. The inspectors reviewed records of inspection and functional tests for all SCBAs staged in the plant that were required by the licensees emergency plan. The inspectors verified the licensees capabilities for refilling and transporting SCBA air bottles during emergency conditions. | ||
| Line 526: | Line 527: | ||
===.1 Reviews of Radiological Environmental Monitoring Reports, Data and Quality Control=== | ===.1 Reviews of Radiological Environmental Monitoring Reports, Data and Quality Control=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The NRC performed a number of confirmatory measurements of water samples to evaluate the licensees proficiency in collecting and in analyzing water samples for tritium and other radioactive isotopes. The samples were collected independently by the inspectors and by licensee personnel and sent to the NRCs contract laboratory for the analysis of tritium. The NRC and licensee obtained these samples from surface water and groundwater sampling points identified in the licensees Radiological Environmental Monitoring Program and from onsite and offsite groundwater monitoring wells. In particular, samples were obtained as part of the licensees environmental study of tritium, potential groundwater contamination, and residual onsite contamination from historical leaks (ADAMS ML062760008). While tritium was the primary radionuclide of concern, selected samples were also analyzed for gamma emitting radionuclides and for strontium. The inspectors performed these reviews to assess the licensees analytical detection capabilities for radio-analysis of environmental samples and its ability to accurately quantify radionuclides to an acceptable level of sensitivity. The criteria used to compare the sample results is provided in Attachment 2, and the results of the comparisons between the NRC and licensee results is provided in Attachment 3. | The NRC performed a number of confirmatory measurements of water samples to evaluate the licensees proficiency in collecting and in analyzing water samples for tritium and other radioactive isotopes. The samples were collected independently by the inspectors and by licensee personnel and sent to the NRCs contract laboratory for the analysis of tritium. The NRC and licensee obtained these samples from surface water and groundwater sampling points identified in the licensees Radiological Environmental Monitoring Program and from onsite and offsite groundwater monitoring wells. In particular, samples were obtained as part of the licensees environmental study of tritium, potential groundwater contamination, and residual onsite contamination from historical leaks (ADAMS ML062760008). While tritium was the primary radionuclide of concern, selected samples were also analyzed for gamma emitting radionuclides and for strontium. The inspectors performed these reviews to assess the licensees analytical detection capabilities for radio-analysis of environmental samples and its ability to accurately quantify radionuclides to an acceptable level of sensitivity. The criteria used to compare the sample results is provided in Attachment 2, and the results of the comparisons between the NRC and licensee results is provided in Attachment 3. | ||
| Line 540: | Line 540: | ||
==OTHER ACTIVITIES== | ==OTHER ACTIVITIES== | ||
{{a|4OA1}} | {{a|4OA1}} | ||
==4OA1 Performance Indicator Verification== | ==4OA1 Performance Indicator Verification== | ||
{{IP sample|IP=IP 71151}} | {{IP sample|IP=IP 71151}} | ||
| Line 545: | Line 546: | ||
===.1 Initiating Events, Mitigating Systems, and Barrier Integrity Performance Indicator=== | ===.1 Initiating Events, Mitigating Systems, and Barrier Integrity Performance Indicator=== | ||
Verification | Verification | ||
| Line 565: | Line 565: | ||
===.2 Radiation Safety Performance Indicator Verification=== | ===.2 Radiation Safety Performance Indicator Verification=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors reviewed, at a minimum, the most recent 12 months of licensee event reports, licensee data reported to the NRC, plant logs, and NRC inspection reports to verify the following performance indicators reported by the licensee for the 2nd Quarter of 2006: | The inspectors reviewed, at a minimum, the most recent 12 months of licensee event reports, licensee data reported to the NRC, plant logs, and NRC inspection reports to verify the following performance indicators reported by the licensee for the 2nd Quarter of 2006: | ||
| Line 579: | Line 578: | ||
===.3 Data Submission=== | ===.3 Data Submission=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
The inspectors performed a review of the data submitted by the licensee for the 2nd Quarter 2006 performance indicators for any obvious inconsistencies prior to its public release in accordance with IMC 0608, Performance Indicator Program. | The inspectors performed a review of the data submitted by the licensee for the 2nd Quarter 2006 performance indicators for any obvious inconsistencies prior to its public release in accordance with IMC 0608, Performance Indicator Program. | ||
| Line 587: | Line 585: | ||
====b. Findings==== | ====b. Findings==== | ||
No findings of significance were identified. {{a|4OA2}} | No findings of significance were identified. {{a|4OA2}} | ||
==4OA2 Identification and Resolution of Problems== | ==4OA2 Identification and Resolution of Problems== | ||
{{IP sample|IP=IP 71152}} | {{IP sample|IP=IP 71152}} | ||
| Line 592: | Line 591: | ||
===.1 Routine Review of Identification and Resolution of Problems=== | ===.1 Routine Review of Identification and Resolution of Problems=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
As part of the various baseline inspection procedures conducted during the period, the inspectors verified that the licensee entered the problems identified during the inspection into their corrective action program. Additionally, the inspectors verified that the licensee was identifying issues at an appropriate threshold and entering them in the corrective action program, and verified that problems included in the licensee's corrective action program were properly addressed for resolution. Attributes reviewed included: the complete and accurate identification of the problem; that timeliness was commensurate with the safety significance; that evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews were proper and adequate; and that the classification, prioritization, focus, and timeliness of corrective actions were commensurate with safety and sufficient to prevent recurrence of the issue. | As part of the various baseline inspection procedures conducted during the period, the inspectors verified that the licensee entered the problems identified during the inspection into their corrective action program. Additionally, the inspectors verified that the licensee was identifying issues at an appropriate threshold and entering them in the corrective action program, and verified that problems included in the licensee's corrective action program were properly addressed for resolution. Attributes reviewed included: the complete and accurate identification of the problem; that timeliness was commensurate with the safety significance; that evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews were proper and adequate; and that the classification, prioritization, focus, and timeliness of corrective actions were commensurate with safety and sufficient to prevent recurrence of the issue. | ||
| Line 602: | Line 600: | ||
===.2 Daily Corrective Action Program Reviews=== | ===.2 Daily Corrective Action Program Reviews=== | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees CAP. This review was accomplished through inspection of the stations daily condition report packages. | In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees CAP. This review was accomplished through inspection of the stations daily condition report packages. | ||
| Line 611: | Line 608: | ||
No findings of significance were identified. | No findings of significance were identified. | ||
===.3 Selected Issue Follow-up Inspection: Generic Letter 89-13 Program Corrective Actions | ===.3 Selected Issue Follow-up Inspection:=== | ||
Generic Letter 89-13 Program Corrective Actions Introduction During the first Quarter of 2006, inspectors identified several issues associated with the licensees GL 89-13 program. These issues included potential inadequacies with the RHR HX test procedure (see Section 1R12), and inconsistencies between the GL 89-13 program bases, commitments made to the NRC, and implementation of the program with respect to RHR HX testing and inspection. Since the licensee revised their GL 89-13 RHR HX program in 1998, various issues with the program were entered into the CAP that had a potential impact on the RHR HX test procedure and performance monitoring program. Inspectors selected these condition reports for an annual sample review of the licensees problem identification and resolution program. | |||
Introduction During the first Quarter of 2006, inspectors identified several issues associated with the licensees GL 89-13 program. These issues included potential inadequacies with the RHR HX test procedure (see Section 1R12), and inconsistencies between the GL 89-13 program bases, commitments made to the NRC, and implementation of the program with respect to RHR HX testing and inspection. Since the licensee revised their GL 89-13 RHR HX program in 1998, various issues with the program were entered into the CAP that had a potential impact on the RHR HX test procedure and performance monitoring program. Inspectors selected these condition reports for an annual sample review of the licensees problem identification and resolution program. | |||
The inspectors review of this issue constituted a single inspection sample. | The inspectors review of this issue constituted a single inspection sample. | ||
| Line 666: | Line 662: | ||
The finding was also determined to involve the cross-cutting area of problem identification and resolution. Specifically, the corrective action program component of problem identification and resolution was identified because of the cross cutting aspect whereby the licensee should take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. (NCV 05000373/2006005-03; 05000374/2006005-03) | The finding was also determined to involve the cross-cutting area of problem identification and resolution. Specifically, the corrective action program component of problem identification and resolution was identified because of the cross cutting aspect whereby the licensee should take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. (NCV 05000373/2006005-03; 05000374/2006005-03) | ||
{{a|4OA5}} | {{a|4OA5}} | ||
==4OA5 Other== | ==4OA5 Other== | ||
===Cornerstone: Occupational Radiation Safety=== | ===Cornerstone: Occupational Radiation Safety=== | ||
===.1 (Closed) VIO 05000374/2006010-01:=== | |||
===.1 (Closed) VIO 05000374/2006010-01: Contractor Pipefitters Enter Condenser Pit HRA | Contractor Pipefitters Enter Condenser Pit HRA Without Required Radiation Protection Brief. | ||
Without Required Radiation Protection Brief. | |||
The inspectors reviewed the licensees response to the NRC letter dated March 31, 2006, delivering a Notice of Violation. The Notice of Violation was issued as a result of information developed by the Office of Investigation that established the facts surrounding willful activities that resulted in individuals entering a HRA on February 13, 2005. The licensee conducted a root cause evaluation of the event and identified: | The inspectors reviewed the licensees response to the NRC letter dated March 31, 2006, delivering a Notice of Violation. The Notice of Violation was issued as a result of information developed by the Office of Investigation that established the facts surrounding willful activities that resulted in individuals entering a HRA on February 13, 2005. The licensee conducted a root cause evaluation of the event and identified: | ||
| Line 680: | Line 674: | ||
{{a|4OA6}} | {{a|4OA6}} | ||
==4OA6 Meetings== | ==4OA6 Meetings== | ||
===.1 Exit Meeting=== | ===.1 Exit Meeting=== | ||
The inspectors presented the inspection results to the Plant Manager, Mr. Daniel Enright, and other members of licensee management on October 11, 2006. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified. | The inspectors presented the inspection results to the Plant Manager, Mr. Daniel Enright, and other members of licensee management on October 11, 2006. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified. | ||
===.2 Interim Exit Meetings=== | ===.2 Interim Exit Meetings=== | ||
Interim exits were conducted for: | Interim exits were conducted for: | ||
* A biennial heat sink performance inspection with the Site Vice President, Ms. Susan Landahl, and other members of licensee management on September 1, 2006. | * A biennial heat sink performance inspection with the Site Vice President, Ms. Susan Landahl, and other members of licensee management on September 1, 2006. | ||
* A periodic radiation protection instrumentation inspection with the Plant Manager, Mr. Daniel Enright, and other members of licensee management on September 29, 2006. | * A periodic radiation protection instrumentation inspection with the Plant Manager, Mr. Daniel Enright, and other members of licensee management on September 29, 2006. | ||
* Public Radiation Safety with Mr. M. Martin on October 13, 2006 | * Public Radiation Safety with Mr. M. Martin on October 13, 2006 | ||
{{a|4OA7}} | {{a|4OA7}} | ||
==4OA7 Licensee-Identified Violation== | ==4OA7 Licensee-Identified Violation== | ||
===Cornerstone: Mitigating Systems=== | ===Cornerstone: Mitigating Systems=== | ||
During a periodic review of temporary lead shielding packages, licensee personnel identified 10 lead blankets totaling 600 pounds hanging from a section of RHR shutdown cooling line piping in the Unit 2 reactor building. The temporary lead shielding had been installed during the February-March 2006 Unit 1 refueling outage using an informal maintenance work practice, vice approved procedural controls. Licensee procedure CC-AA-401, Maintenance Specification: Installation and Control of Temporary Shielding and Shielding Components, requires that all temporary lead shielding be installed in the plant using an appropriate shielding permit and a procedurally specified process. Further, Criterion V of 10 CFR 50, Appendix B, Instructions, Procedures, and Drawings, states, in part, that: Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. | During a periodic review of temporary lead shielding packages, licensee personnel identified 10 lead blankets totaling 600 pounds hanging from a section of RHR shutdown cooling line piping in the Unit 2 reactor building. The temporary lead shielding had been installed during the February-March 2006 Unit 1 refueling outage using an informal maintenance work practice, vice approved procedural controls. Licensee procedure CC-AA-401, Maintenance Specification: Installation and Control of Temporary Shielding and Shielding Components, requires that all temporary lead shielding be installed in the plant using an appropriate shielding permit and a procedurally specified process. Further, Criterion V of 10 CFR 50, Appendix B, Instructions, Procedures, and Drawings, states, in part, that: Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. | ||
| Line 703: | Line 694: | ||
The inspectors determined the violation to be of more than minor significance in that if this practice were left uncorrected it would constitute a potentially more significant safety concern. However, the violation was also determined to be of very low safety significance because the licensee was able to demonstrate through engineering analysis that, in this case, the associated RHR shutdown cooling piping remained seismically qualified with the lead installed on the piping. The licensee had entered this issue into their CAP as IR 497765. | The inspectors determined the violation to be of more than minor significance in that if this practice were left uncorrected it would constitute a potentially more significant safety concern. However, the violation was also determined to be of very low safety significance because the licensee was able to demonstrate through engineering analysis that, in this case, the associated RHR shutdown cooling piping remained seismically qualified with the lead installed on the piping. The licensee had entered this issue into their CAP as IR 497765. | ||
s: 1. Supplemental Information | s: 1. Supplemental Information | ||
===2. Confirmatory Measurements Comparison Criteria=== | |||
===3. Trititum Sampling Results=== | |||
=SUPPLEMENTAL INFORMATION= | =SUPPLEMENTAL INFORMATION= | ||
==KEY POINTS OF CONTACT== | ==KEY POINTS OF CONTACT== | ||
Licensee | Licensee | ||
: [[contact::S. Landahl]], Site Vice President | : [[contact::S. Landahl]], Site Vice President | ||
| Line 728: | Line 720: | ||
Nuclear Regulatory Commission | Nuclear Regulatory Commission | ||
: [[contact::B. Burgess]], Chief, Reactor Projects Branch 2 | : [[contact::B. Burgess]], Chief, Reactor Projects Branch 2 | ||
==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED== | ==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED== | ||
===Opened=== | ===Opened=== | ||
: 05000374/2006005-01 | : 05000374/2006005-01 NCV Failure to promptly repair a degraded condition associated with the 2B EDG day tank room structure. (Sections 1R05 and 4OA2.1) | ||
: 05000373/2006005-02; | : 05000373/2006005-02; | ||
: 05000374/2006005-02 NCV Inadequate procedure used for GL 89-13 Program thermal performance tests on RHR heat exchangers. | |||
(Section 1R12.2) | |||
: 05000373/2006005-03; | : 05000373/2006005-03; | ||
: 05000374/2006005-03 NCV Failure to promptly correct identified issues associated with the GL 89-13 Program for RHR heat exchangers. | |||
(Section 4OA2.3) | |||
===Closed=== | ===Closed=== | ||
: 05000374/2006005-01 | : 05000374/2006005-01 NCV Failure to promptly repair a degraded condition associated with the 2B EDG day tank room structure. (Section 1R05 and 4OA2.1) | ||
: 05000373/2006004-01; | : 05000373/2006004-01; | ||
: 05000374/2006004-01 URI Adequacy of B VC Compressor Operability Determinations and Post-Maintenance Tests (Section 1R12.1) | |||
: 05000373/2006003-01; | : 05000373/2006003-01; | ||
: 05000374/2006003-01 URI RHR Heat Exchanger Thermal Performance Testing and NRC GL 89-13 Conformance Issues (Section 1R12.2) | |||
: 05000373/2006005-02; | : 05000373/2006005-02; | ||
: 05000374/2006005-02 NCV Inadequate procedure used for GL 89-13 Program thermal performance tests on RHR heat exchangers. | |||
(Section 1R12.2) | |||
: 05000373/2006005-03; | : 05000373/2006005-03; | ||
: 05000374/2006005-03 NCV Failure to promptly correct identified issues associated with the GL 89-13 Program for RHR heat exchangers. | |||
(Section 4OA2.3) | |||
: 05000374/2006010-01 | : 05000374/2006010-01 VIO Contractor Pipefitters Enter Condenser Pit HRA Without Required Radiation Protection Brief (Section 4OA5.1) | ||
===Discussed=== | ===Discussed=== | ||
None. | None. | ||
==LIST OF DOCUMENTS REVIEWED== | ==LIST OF DOCUMENTS REVIEWED== | ||
}} | }} | ||
Latest revision as of 05:38, 15 January 2025
| ML062980255 | |
| Person / Time | |
|---|---|
| Site: | LaSalle |
| Issue date: | 10/24/2006 |
| From: | Burgess B NRC/RGN-III/DRP/RPB2 |
| To: | Crane C Exelon Generation Co |
| References | |
| FOIA/PA-2010-0209 IR-06-005, IR-06-014 | |
| Download: ML062980255 (53) | |
Text
October 24, 2006
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 NRC INTEGRATED INSPECTION REPORT 05000373/2006005; 05000374/2006005, AND 05000373/2006014; 05000374/2006014
Dear Mr. Crane:
On September 30, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed an integrated inspection at your LaSalle County Station, Units 1 and 2. The enclosed report documents the results of this inspection, which were discussed on October 11, 2006, with the Plant Manager, Mr. Daniel Enright, and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, three findings of very low safety significance were identified by NRC inspectors. All of these findings identified also involved violations of NRC requirements. However, because the findings associated with these violations were of very low safety significance and because the issues were entered into the licensees corrective action program, the NRC is treating these issues as non-cited violations in accordance with Section VI.A.1 of the NRC Enforcement Policy. Additionally, one licensee identified violation of very low safety significance is listed in Section 4OA7 of this report.
If you contest the subject or severity of any non-cited violation in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspectors Office at the LaSalle County Station. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure:
Inspection Report 05000373/2006005; 05000374/2006005 and 05000373/2006014; 05000374/2006014 w/Attachments:
1. Supplemental Information 2. Confirmatory Measurements Comparison Criteria 3. Trititum Sampling Results cc w/encl:
Site Vice President - LaSalle County Station LaSalle County Station Plant Manager Regulatory Assurance Manager - LaSalle County Station Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission
SUMMARY OF FINDINGS
IR 05000373/2006005, 05000374/2006005 and 05000373/2006014, 05000374/2006014; 07/01/2006 - 09/30/2006; LaSalle County Station, Units 1 & 2; Fire Protection, Maintenance Effectiveness, and Identification and Resolution of Problems Report.
The inspection was conducted by resident inspectors and regional inspectors. The report covers a 3-month period of resident inspection, an announced baseline biennial heat sink inspection, and an announced baseline radiation protection inspection. Three Green findings and associated non-cited violations (NCVs) were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using IMC 0609 Significance Determination Process (SDP). Findings for which the SDP does not apply may be "Green," or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.
A.
Inspector-Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green.
A finding of very low safety significance was identified by inspectors during a quarterly fire protection zone inspection of the 2B Emergency Diesel Generator (EDG) day tank room. Specifically, the inspectors identified a section of structural steel that was missing its requisite fireproof coating and had not been repaired in a timely manner. A non-cited violation of 10 CFR 50,
Appendix B, Criterion XVI, Corrective Action, was also identified for failure to assure that a condition adverse to quality associated with the design of the day tank room structure was promptly identified and corrected.
The performance deficiency, identified during review of the event, involved the work planning for the repair of the structural steel fireproof coating. Specifically, in processing the work request, licensee work planners failed to recognize that the missing fireproof coating constituted a design deficiency for a safety-related structure, and was, therefore, required to be corrected in a prompt manner under NRC regulations. The finding was of more than minor significance in that it had a direct impact on the cornerstone objective. Specifically, the inspectors determined that the licensees failure to enact proper corrective action and restore the structural steel fireproof coating in the 2B EDG day tank room for multiple years resulted in a reduction of the reliability and capability of the safety-related structures ability to perform its designed function in the event of a fire. Because of the limited size and location of the missing fireproof coating, and because the EDG rooms at LaSalle Station are protected by an automatic carbon dioxide suppression system, the inspectors determined that the finding was of very low safety significance (Green) and within the licensees response band. Licensee corrective actions included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. The finding was also determined to involve the cross-cutting area of problem identification and resolution. (Sections 1R05 and 4OA2.1)
- Green.
A finding of very low safety significance was identified by inspectors during observation of a GL 89-13 residual heat removal system heat exchanger (RHR HX) thermal performance test. Specifically, the inspectors identified that the licensees engineering staff failed to develop and use an adequate test procedure to implement the RHR HX performance monitoring program in accordance with docketed commitments and the established NRC Generic Letter (GL) 89-13 program basis. A non-cited violation of 10 CFR 50, Appendix B,
Criterion V, for an inadequate RHR HX thermal performance test procedure was also identified.
The inspectors determined that the licensees failure to establish and maintain an adequate GL 89-13 RHR HX thermal performance testing procedure represented a performance deficiency on the part of licensee engineering personnel. The issue was determined to be of more than minor significance in that it directly affected the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events.
Specifically, this finding impacted one of the key attributes of this objective, which is to ensure the quality of maintenance and test procedures for systems that must respond to initiating events. The inspectors determined that the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, and conducted a Phase 1 characterization and initial screening. Despite the widespread issues the inspectors identified with the licensees GL 89-13 program and associated bases, the licensees engineering staff was able to provide the inspectors with sufficient maintenance and testing records to permit the inspectors to conclude that each RHR HX remained fully capable of performing its design basis and safety functions. As a result, because the finding did not represent a actual loss of operability or safety function and was not potentially risk significant with respect to a seismic, flooding, or severe weather initiating event, the inspectors determined it to be of very low safety significance (Green) and within the licensees response band.
Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. (Section 1R12.2)
- Green.
A finding of very low safety significance was identified by the inspectors.
The inspectors determined that the licensee did not fully evaluate problems and properly prioritize corrective actions with respect to the RHR HX thermal performance test procedure and GL 89-13 HX performance monitoring program.
An associated non-cited violation of 10 CFR 50, Appendix B, Criterion XVI,
Corrective Action, was also identified by the inspectors.
The inspectors determined that there was a performance deficiency associated with the corrective actions taken by the licensee. Specifically, the inspectors determined that the licensee had not thoroughly evaluated, nor given proper priority to, identified deficiencies in the RHR HX test procedure as identified in Issue Report 98176. Further, the inspectors also determined that the licensee had failed to complete the GL 89-13 bases review and revision called for under Apparent Cause Evaluation 263535 in 2004. The inspectors determined that the finding was of more than minor significance in that it directly affected the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events. Specifically, this finding impacted one of the key attributes of this objective which is to ensure the quality of maintenance and test procedures for systems that must respond to initiating events. The inspectors conducted a Phase 1 characterization and initial screening in accordance with the SDP. Because the finding did not represent a actual loss of operability or safety function and was not potentially risk significant with respect to a seismic, flooding, or severe weather initiating event, it was determined to be of very low safety significance (Green) and within the licensees response band. Licensee corrective actions planned include review of GL 89-13 program Corrective Action Program documents to determine if any other identified issues were not fully dispositioned or resolved and to confirm that all corrective actions have been implemented and documented. The finding was also determined to involve the cross-cutting area of problem identification and resolution. (Section 4OA2.3)
Licensee-Identified Violations
A violation of very low safety significance that was identified by the licensee has been reviewed by inspectors. Corrective actions planned or taken by the licensee have been entered into the licensees corrective action program. The violation and corrective action tracking number is listed in Section 4OA7 of this report.
REPORT DETAILS
Summary of Plant Status
Unit 1 The unit began the inspection period operating at full power. On September 3, 2006, reactor power was reduced to approximately 66 percent to recover two control rods inserted for hydraulic control unit maintenance, to facilitate a control rod pattern adjustment, and to perform control rod scram timing and channel deformation surveillance activities. Operation at full power resumed on September 4, 2006, and the unit continued to operate at or near full power for the remainder of the inspection period.
Unit 2 The unit began the inspection period operating at full power. On September 10, 2006, reactor power was reduced to approximately 76 percent to facilitate a control rod pattern adjustment, and to perform control rod scram timing and channel deformation surveillance activities.
Operation at full power resumed later that same day, and the unit continued to operate at or near full power for the remainder of the inspection period.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness
1R04 Equipment Alignment
.1 Semiannual Complete System Alignment Verification
a. Inspection Scope
Due to the systems risk significance, the inspectors selected the Unit 1 and 2 standby liquid control (SLC) systems for a complete alignment verification. The inspectors walked down the system to verify mechanical and electrical equipment lineups, component labeling, component lubrication, component and equipment cooling, hangers and supports, operability of support systems, and to ensure that ancillary equipment or debris did not interfere with equipment operation.
This semiannual full system alignment verification constituted a single inspection sample.
b. Findings
No findings of significance were identified.
.2 Quarterly Partial System Alignment Verifications
a. Inspection Scope
The inspectors performed partial alignment verifications on the following equipment trains to verify operability and proper equipment lineup. These systems were selected based upon risk significance, plant configuration, system work or testing, or inoperable or degraded conditions:
- Unit 1 reactor core isolation cooling (RCIC) system;
- Unit 2 RCIC system;
- Unit 2 residual heat removal (RHR) system during a high pressure core spray (HPCS) system work window; and
- Unit 2 low pressure core spray (LPCS) system.
The inspectors verified the position of critical redundant equipment and looked for any discrepancies between the existing equipment lineup and the required lineup.
These quarterly partial system alignment verifications constituted four inspection samples.
b. Findings
No findings of significance were identified.
1R05 Fire Protection
.1 Quarterly Fire Protection Zone Inspections
a. Inspection Scope
The inspectors walked down the following risk significant areas looking for any fire protection issues. The inspectors selected areas containing systems, structures, or components that the licensee identified as important to reactor safety:
- Fire Zone 8B3 - Unit 2, Division 3, emergency diesel generator (EDG) day tank room, 710'6";
- Fire Zone 8B4 - Unit 2, Division 2, EDG day tank room, 710'6";
- Fire Zone 8C1 - Unit 2, Division 3, EDG fuel tank room, 674'0";
- Fire Zone 8C2 - Unit 2, Division 2, EDG fuel tank room, 674'0";
- Fire Zone 4E2 - Unit 2, auxiliary equipment room, 731'0";
- Fire Zone 4E4 - Unit 2, Division 2, essential switchgear room,731'0";
- Fire Zone 5B13 - Balance-of-plant cable zone, 731'0";
- Fire Zone 2H1 - Unit 1, general area, 694'6";
- Fire Zone 3E - Unit 2, general area, 761'0";
- Fire Zone 4F1 - Unit 1, Division 1, essential switchgear room, 710'6"; and
- Fire Zone 5B9 - Unit 1, motor-driven reactor feed pump room, 731'0".
The inspectors reviewed the control of transient combustibles and ignition sources, fire detection equipment, manual suppression capabilities, passive suppression capabilities, automatic suppression capabilities, and barriers to fire propagation.
These quarterly fire protection zone inspections constituted eleven inspection samples.
b. Findings
Introduction A finding of very low safety significance (Green) was identified by inspectors during a quarterly fire protection zone inspection of the 2B EDG day tank room. Specifically, the inspectors identified a section of structural steel that was missing its requisite fireproof coating and had not been repaired in a timely manner. A non-cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, was also identified for failure to assure that a condition adverse to quality, in this case a material deficiency associated with the design of the day tank room structure, was promptly identified and corrected.
Description On July 27, 2006, inspectors conducting a quarterly fire protection zone inspection of the 2B EDG day tank room identified a section of structural steel just inside the doorway to the day tank room that was not coated with the requisite fireproof material. Following up on this issue, the inspectors found that the missing fireproof coating had previously been identified by members of the licensees engineering staff on December 15, 2000, and entered into their corrective action program (CAP) as work request 99123692 and work order 99242235. The licensees fire protection engineer had noted on the CAP input documents that the structural steel was not a fire rated assembly per the stations Technical Requirements Manual, and therefore, was not subject to a operating limiting condition action statement. The same engineer did note, however, that the structural steel was required to be protected by a 3-hour rated fireproof coating per plant design drawings. Additionally, the fire protection engineer noted that the repairs to the fireproof coating on the structural steel should be completed in a timely fashion, since the 3-hour fireproof coating was required by Appendix A to NRC Branch Technical Position APCSB 9.5-1, Guidelines for Fire Protection for Nuclear Power Plants.
Although the licensee had entered the material deficiency into their CAP, further inspection revealed that licensee personnel had erroneously coded the work order as low-level facilities maintenance. Licensee work planning personnel processing the work request had focused on the fire protection engineers discussion that the structural steel was not a fire rated assembly and that no operating limiting condition action statement applied. These same planners missed the fact that the lack of fireproof coating on the structural steel constituted a design deficiency for a 10 CFR 50, Appendix B, structural component. As a result, over the course of an almost 6 year period, the work order was rescheduled several times in order to permit work that was perceived to have been more significant to take place.
Analysis The inspectors determined that there was a licensee performance deficiency associated with the work planning for the repair of the structural steel fireproof coating. Specifically, in processing the work request, licensee work planners failed to recognize that the missing fireproof coating constituted a design deficiency for a safety-related structure, and was, therefore, required to be corrected in a prompt manner under NRC regulations.
The objective of the Mitigating Systems Cornerstone of Reactor Safety is to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). In accordance with NRC Inspection Manual Chapter (IMC) 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, the inspectors determined that the finding was of more than minor significance in that it had a direct impact on this cornerstone objective.
Specifically, the inspectors determined that the licensees failure to enact proper corrective action and restore the structural steel fireproof coating in the 2B EDG day tank room for almost 6 years resulted in a reduction of the reliability and capability of the safety-related structures ability to perform its designed function in the event of a fire.
The inspectors determined that the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, and conducted a Phase 1 characterization and initial screening. Because the finding was associated with fire protection, this was accomplished using IMC 0609, Appendix F, Attachment 1, Fire Protection SDP Phase 1 Worksheet. Based on the size and location of the missing fireproof coating, the inspectors concluded that it represented a low degradation rating in the fire confinement category. Additionally, because the EDG rooms at LaSalle Station are protected by an automatic carbon dioxide suppression system, the inspectors determined that the finding was of very low safety significance (Green) and within the licensees response band.
In addition, the inspectors also determined that the finding was related to the cross-cutting area of problem identification and resolution. Specifically, the corrective action program component of problem identification and resolution was identified because of the cross-cutting aspect whereby the licensee should take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. Because the finding involved the cross-cutting area of problem identification and resolution, it is also noted in Section 4OA2.1 in this report.
Enforcement Criterion XVI of 10 CFR 50, Appendix B, Corrective Action, states, in part, that:
Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected. Contrary to this requirement, for a period of almost 6 years beginning in December of 2000, the licensee failed to correct a condition adverse to quality, a material deficiency associated with the 2B EDG day tank room structure.
The licensee entered this issue into their CAP as issue report (IR) 515168. Corrective actions completed by the licensee included a review of all open fire protection work orders to ensure their proper coding in accordance with their significance, and scheduling the immediate repair of the structural steel fireproof coating in the 2B EDG day tank room. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion XVI, is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000374/2006005-01)
1R06 Flood Protection Measures
.1 Semiannual Internal Flooding Review
a. Inspection Scope
The inspectors reviewed the licensee's flooding mitigation plans and equipment to determine consistency with design requirements and the risk analysis assumptions related to internal flooding. The following specific plant areas particularly susceptible to internal flooding were inspected:
- Unit 1 reactor building raceway areas; and
- Unit 2 reactor building raceway areas.
Walkdowns and reviews performed considered design measures, seals, drain systems, contingency equipment condition and availability of temporary equipment and barriers, performance and surveillance tests, procedural adequacy, and compensatory measures. In particular, the inspectors focused on plausible flooding scenarios of the reactor building raceways via the reactor building ventilation (VR) system, and assumed operator mitigating actions credited in the current LaSalle probabilistic risk assessment.
This semiannual internal flooding review constituted a single inspection sample.
b. Findings
No findings of significance were identified.
1R07 Heat Sink Performance
.1 Biennial Review of Heat Sink Performance
a. Inspection Scope
The inspectors reviewed the performance of the Unit 1 and Unit 2 HPCS pump room coolers, the Unit 1 and Unit 2 LPCS pump/RCIC pump room coolers, and the Unit 1 LPCS pump motor cooler. These heat exchangers were chosen for review based on their high risk assessment worth in the licensee's probabilistic safety analysis.
The inspectors verified that the inspection/maintenance were adequate to ensure proper heat transfer. This was done by conducting independent heat transfer capability calculations, reviewing the methods used to inspect the heat exchangers, and verifying that the as-found results were appropriately dispositioned, such that the final conditions were acceptable. The inspectors also verified, by review of procedures and test results, that chemical treatments, ultrasonic tests, and methods used to control biological fouling corrosion and macrofouling were sufficient to ensure required heat exchanger performance.
The inspectors verified that the condition and operation of these heat exchangers were consistent with design assumptions in heat transfer calculations by conducting a service water system walkdown and reviewing related procedures and surveillances. The inspectors also verified that redundant and infrequently used heat exchangers were flow tested periodically at maximum design flow. This was performed by reviewing related procedures and surveillances.
The inspectors verified that the performance of the ultimate heat sink and its sub-components, such as piping, intake screens, intake bays, pumps, valves, etc.,
were acceptable by reviewing procedures, surveillances, and inspections conducted on the systems.
Lastly, the inspectors verified that the licensee had entered significant heat exchanger/heat sink problems into their corrective action program, and that the corrective actions taken were appropriate.
This biennial heat sink performance review constituted three inspection samples.
b. Findings
No findings of significance were identified.
1R11 Licensed Operator Requalification Program
a. Inspection Scope
The inspectors observed a training crew during an evaluated simulator scenario and reviewed licensed operator performance in mitigating the consequences of events.
The scenario included multiple equipment and instrumentation failures, and the transient resulted in a complex accident that yielded the declaration of several emergency classifications. Areas observed by the inspectors included: clarity and formality of communications, timeliness of actions, prioritization of activities, procedural adequacy and implementation, control board manipulations, managerial oversight, emergency plan execution, and group dynamics.
This simulator training observation constituted a single inspection sample.
b. Findings
No findings of significance were identified.
1R12 Maintenance Effectiveness
.1 (Closed) Unresolved Item (URI)05000373/2006004-01; 05000374/2006004-01:
Adequacy of B Control Room Ventilation (VC) Compressor Operability Determinations and Post-Maintenance Tests.
a. Inspection Scope
The inspectors reviewed the licensee's handling of performance issues and the associated implementation of the Maintenance Rule (10 CFR 50.65) to evaluate maintenance effectiveness for the VC system. The VC system was selected based on being designated as risk significant under the Maintenance Rule, as well as recently identified performance issues and problems that may have potential impact on system work practices, reliability, or common cause failures.
The inspectors reviews included verification of the licensees categorization of specific issues, including evaluation of the performance criteria, appropriate work practices, identification of common cause errors, extent of condition, and trending of key parameters. Additionally, the inspectors reviewed the licensees implementation of the Maintenance Rule requirements, including a review of scoping, goal-setting, performance monitoring, short-term and long-term corrective actions, functional failure determinations associated with the condition reports reviewed, and current equipment performance status.
This maintenance effectiveness review and URI closure constituted a single inspection sample.
b. Findings
The inspectors reviewed the licensees root cause report, documented under IR 497654, which had not been completed at the end of the previous inspection quarter. No findings of significance or violations of regulatory requirements were identified.
.2 (Closed) URI 05000373/2006003-01; 05000374/2006003-01:
RHR Heat Exchanger (HX) Thermal Performance Testing and NRC Generic Letter (GL) 89-13 Conformance Issues.
a. Inspection Scope
The inspectors reviewed the licensee's handling of performance issues and the associated implementation of the Maintenance Rule (10 CFR 50.65) to evaluate RHR HX maintenance effectiveness. The licensees RHR HX maintenance program was selected based on an inspector identified issue that originated in the 1st Quarter of 2006, during observations of the licensees RHR HX thermal performance testing program.
The inspectors review included verification of the licensees categorization of specific issues, including evaluation of RHR HX performance criteria, maintenance work practices, identification of potential common cause errors, extent of condition for issues identified, and trending of key parameters. Additionally, the inspectors reviewed the licensees implementation of the Maintenance Rule requirements, including a review of scoping, goal-setting, performance monitoring, short-term and long-term corrective actions, functional failure determinations associated with the condition reports reviewed, and current RHR HX performance status.
This maintenance effectiveness review and URI closure constituted a single inspection sample.
b. Findings
Introduction A finding of very low safety significance (Green) was identified by inspectors during observation of a GL 89-13 RHR HX thermal performance test. Specifically, the inspectors identified that the licensees engineering staff failed to develop and use an adequate test procedure to implement the RHR HX performance monitoring program in accordance with docketed commitments and the established GL 89-13 program basis.
A non-cited violation of 10 CFR 50, Appendix B, Criterion V, for an inadequate RHR HX thermal performance test procedure was also identified.
Description In 1998, the GL 89-13 program was revised to test one RHR HX for three consecutive outages on each unit in order to determine the best frequency for testing or periodic maintenance. The 1A and 2B RHR HXs were selected for testing and the 1B and 2A RHR HXs were selected for cleaning each cycle until this initial testing was completed.
Per the program basis, this was a revised attempt to establish an initial baseline heat transfer test and a recurring heat transfer test trending program as the means for identifying the need for RHR HX cleaning.
Recurring maintenance work orders were established to perform heat transfer testing of the 1A and 2B RHR HXs once per cycle and inspections of the 1B and 2A HXs once every two cycles. No justification was documented for setting the inspection frequency at once every two cycles vice once every cycle. Furthermore, the recurring maintenance work orders established to perform eddy-current testing required cleaning of all of the HXs every other cycle. This was in conflict with the GL 89-13 programmatic requirement to perform three consecutive thermal performance tests without any intervening cleaning in order to trend HX performance.
In 1999, LTS-200-17, RHR Heat Exchanger Test, was revised to allow performance testing of the RHR HXs in the shutdown cooling mode. During the L1R08 outage in October 1999, the 1B RHR HX was tested using this new procedure. This was contrary to the GL 89-13 program basis, which specified testing the 1A HX. In 2000, the GL 89-13 program basis document was changed to no longer specify that the same RHR HX had to be tested once per cycle. However, the program basis for RHR performance monitoring, which included establishing an initial baseline heat transfer test and recurring heat transfer test trending, remained part of the program. In November of 2000, the 2B RHR HX was thermal performance tested using LTS-200-17 and the results from this test were indeterminate. The procedure was not revised to address this issue. In 2001, recurring maintenance work orders were created to accomplish heat transfer performance testing on each RHR HXs. However, the testing frequency for the 1A and 2B HXs within the GL 89-13 program documents was specified as no due date, vice every other cycle.
In 2002, the GL 89-13 program basis was revised once again. The programs test history was not updated to reflect the indeterminate test of the 2B HX during the L2R08 outage, nor the testing of the 1A HX during the L1R09 outage. An administrative change was made to LTS-200-17, but the indeterminate test of the 2B HX was not addressed.
In February of 2005, the results of a second thermal performance test of the 2B RHR HX were indeterminate. LTS-200-17 was revised to allow a higher shell-side temperature and to caution operations to maintain steady flows. In February of 2006, the results of a thermal performance test of the 1A RHR HX were indeterminate.
Inspectors questioned the engineering staff on the adequacy of the test procedure and the consequences of these indeterminate tests with respect to the implementation of the GL 89-13 program and its goals of verifying and maintaining the heat transfer capability of the RHR HXs. Inspectors also questioned the licensees engineering staff regarding any attempts that had been made to revise RHR HX testing procedures in order to address indeterminate testing results. Initially, the licensees engineering staff was unable to provide a consistent basis for their RHR HX testing program to the inspectors.
The inspectors determined that the licensees GL 89-13 program for the RHR HXs had been poorly maintained. Inconsistencies in program documentation and requirements, as well as weaknesses in the responsible engineering staffs knowledge of the GL 89-13 program itself, affected the ability of the licensee to properly implement the program.
For example, when questioned by the inspectors, the licensees engineering staff were initially not able to consistently describe the RHR HX testing methodology, basis, or program status. Additionally, engineering staff members responsible for the program did not document the basis for the current 4-year HX test interval and had difficulty retrieving past records documenting the historical program basis. Several cases were identified where the engineering staff did not follow their documented RHR HX test plan.
Inspectors also noted several problems with information provided to the NRC via commitment letters. The GL 89-13 program as described in docketed correspondence was not always consistent with the program as implemented. For example, commitment updates since 1998 did not document the change from a testing program to a maintenance program for RHR HXs, even though the licensee had, by actual practice, implemented such a change.
Additionally, inspectors determined that the procedure used to conduct RHR HX thermal performance tests was inadequate. The use of this procedure resulted in three cases in which test data was indeterminate and thus not usable for assessing the condition of the RHR HXs.
Analysis The inspectors determined that the licensees failure to establish and maintain an adequate GL 89-13 RHR HX thermal performance testing procedure represented a performance deficiency on the part of licensee engineering personnel. The issue was determined to be of more than minor significance in that it directly affected the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events. Specifically, this finding impacted one of the key attributes of this objective, which is to ensure the quality of maintenance and test procedures for systems that must respond to initiating events.
The inspectors determined that the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, and conducted a Phase 1 characterization and initial screening. Despite the widespread issues the inspectors identified with the licensees GL 89-13 program and associated bases, as discussed in the Description section above, the licensees engineering staff was able to provide the inspectors with sufficient maintenance and testing records to permit the inspectors to conclude that each RHR HX remained fully capable of performing its design basis and safety functions. As a result, because the finding did not represent a actual loss of operability or safety function and was not potentially risk significant with respect to a seismic, flooding, or severe weather initiating event, the inspectors determined it to be of very low safety significance (Green) and within the licensees response band.
Enforcement Table 3.2-1 of the licensees Updated Final Safety Analysis Report (UFSAR) indicated that the RHR system is subject to the requirements of 10 CFR 50, Appendix B.
Criterion V, Instructions, Procedures, and Drawings, of this appendix states, in part, that: Activities affecting quality shall be proscribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. Contrary to this requirement, the licensee failed to establish and maintain a testing procedure for RHR HX thermal performance testing that was appropriate to the circumstances and provided meaningful and usable test data in all cases.
The licensee had entered this issue into their corrective action program as IRs 458571, 463253, 473455, 478852, 479741, 500835, 513814, 515613, 522479, 522487, 522493, 534870, 534872, 534875, 534877, and 534889. Corrective actions by the licensee included: performing evaluations to document the basis for the 4-year HX clean and inspection interval; evaluating the material condition of the 2B RHR HX, conducting an analysis to determine how the current performance monitoring program meets the intent of GL 89-13; revising commitments to the NRC to be consistent with the current GL 89-13 program; and revising LTS-200-17, the RHR HX test procedure, per the recommendations of that analysis. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion V is being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy. (NCV 05000373/2006005-02; 05000374/2006005-02)
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
The inspectors reviewed and observed emergent work, preventive maintenance, or planning for risk significant maintenance activities. The inspectors observed maintenance or planning for the following activities or risk significant systems undergoing scheduled or emergent maintenance:
- Unit 2 Division 2 core standby cooling system (CSCS) ventilation damper failure;
- Unit 2 main generator exciter alterex brush replacements;
- Unit 2 SLC suction drain valve repairs;
- Unit 2 Division 1 switchgear room temperature controller repairs;
- Unit 2 drywell equipment drain sump drain line inboard containment isolation valve solenoid repairs;
- 1B EDG maintenance during a scheduled work window; and
- Unit 1 VR system radiation monitor calibrations.
The inspectors also reviewed the licensee's evaluation of plant risk, risk management, scheduling, and configuration control for these activities in coordination with other scheduled risk significant work. The inspectors verified that the licensees control of activities considered assessment of baseline and cumulative risk, management of plant configuration, control of maintenance, and external impacts on risk. In-plant activities were reviewed to ensure that the risk assessment of maintenance or emergent work was complete and adequate, and that the assessment included an evaluation of external factors. Additionally, the inspectors verified that the licensee entered the appropriate risk category for the evolutions.
These maintenance risk assessment and emergent work control reviews constituted seven inspection samples.
b. Findings
No findings of significance were identified.
1R15 Operability Evaluations
a. Inspection Scope
The inspectors reviewed the technical adequacy of the following operability evaluations to determine the impact on Technical Specifications, the significance of the evaluations, and to ensure that adequate justifications were documented:
- IR 497765, Lead on RHR shutdown cooling piping;
- Technical support center (TSC) operability with the TSC air conditioning compressor out-of-service;
- Operability of 1B RHR system after low pressure alarm due to system leakage; and
- Operability of Unit 2 control rods 14-35 and 26-23 following identification of slow settling time during control rod channel deformation testing.
These operability evaluations were selected based upon the relationship of the safety-related system, structure, or component to risk.
The inspectors review of these operability evaluations and issues constituted six inspection samples.
b. Findings
No findings of significance were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope
The inspectors selected the following post-maintenance activities for review. Activities were selected based upon the structure, system, or component's ability to impact risk:
- 1A RHR seal cooler post-maintenance test;
- 1B SLC pump post-maintenance test;
- Unit 2 drywell equipment drain sump inboard containment isolation valve testing following solenoid replacement; and
- Unit 1 control rods 30-27 and 30-07 post-maintenance timing testing.
The inspectors verified by witnessing the test or reviewing the test data that post-maintenance testing activities were adequate for the above maintenance activities.
The inspectors reviews included, but were not limited to, integration of testing activities, applicability of acceptance criteria, test equipment calibration and control, procedural use and compliance, control of temporary modifications or jumpers required for test performance, documentation of test data, Technical Specification applicability, system restoration, and evaluation of test data. Also, the inspectors verified that maintenance and post-maintenance testing activities adequately ensured that the equipment met the licensing basis, Technical Specifications, and UFSAR design requirements.
The inspectors review of these post maintenance testing activities constituted four inspection samples.
b. Findings
No findings of significance were identified.
1R22 Surveillance Testing
.1 General Surveillance Tests
a. Inspection Scope
The Inspectors selected the following general surveillance test activities for review.
Activities were selected based upon risk significance and the potential risk impact from an unidentified deficiency or performance degradation that a system, structure, or component could impose on the unit if the condition were left unresolved:
- 1B EDG idle start surveillance test;
- Control room and auxiliary electric equipment room pressurization surveillance test;
- Unit 1 control rod channel deformation tests; and
- Unit 2 scram time testing.
The inspectors observed the performance of surveillance testing activities, including reviews for preconditioning, integration of testing activities, applicability of acceptance criteria, test equipment calibration and control, procedural use, control of temporary modifications or jumpers required for test performance, documentation of test data, Technical Specification applicability, impact of testing relative to performance indicator reporting, and evaluation of test data.
The review of these general surveillance activities by the inspectors constituted four inspection samples.
b. Findings
No findings of significance were identified.
.2 Inservice Testing (IST) Required by the American Society of Mechanical Engineers
Operations and Maintenance Code
a. Inspection Scope
Based on the relatively high risk significance of the system, the inspectors selected the following Code pump IST activity for review:
- Quarterly IST for the 1A RHR pump The inspectors observed the performance of the test, including reviews for preconditioning, applicability of acceptance criteria, test equipment calibration and control, procedural use, documentation of test data, Technical Specification applicability, compliance with 10 CFR 50.55a, Codes and Standards, impact of testing relative to performance indicator reporting, and evaluation of the test data.
The review of this IST quarterly pump surveillance constituted a single inspection sample.
b. Findings
No findings of significance were identified.
1EP6 Drill Evaluation
a. Inspection Scope
The resident inspectors reviewed a simulator-based training evolution to evaluate drill conduct and the adequacy of the licensees critique of performance to identify weaknesses and deficiencies. The inspectors selected a simulator scenario that the licensee had scheduled as providing input to the Drill/Exercise Performance Indicator.
The inspectors observed the classification of events, notifications to off-site agencies, protective action recommendation development, and drill critiques. Observations were compared to the licensees observations and corrective action program entries. The inspectors verified that there were no discrepancies between observed performance and performance indicator reported statistics. The simulator scenario observed resulted in a site area emergency classification and declaration.
This simulator emergency preparedness drill observation constituted a single inspection sample.
b. Findings
No findings of significance were identified.
RADIATION SAFETY
Cornerstones: Occupational Radiation Safety, and Public Radiation Safety 2OS1 Access Control to Radiologically Significant Areas (71121.01)
.1 Review of Licensee Performance Indicators for the Occupational Exposure Cornerstone
a. Inspection Scope
The inspectors reviewed the licensees occupational exposure control cornerstone performance indicators (PIs) to determine whether or not the conditions surrounding the PIs had been evaluated and whether identified problems had been entered into the corrective action program for resolution.
This review constituted one inspection sample.
b. Findings
No findings of significance were identified.
.2 Plant Walkdowns and Radiation Work Permit Reviews
a. Inspection Scope
The inspectors reviewed radiation work permits (RWPs) for airborne radioactivity areas to verify barrier integrity and engineering controls performance (e.g., high efficiency particulate air ventilation system operation, etc.) and to determine if there was a potential for individual worker internal exposures of greater than 50 millirem committed effective dose equivalent. No areas of the plant were under airborne radioactivity work controls.
The adequacy of the licensees internal dose assessment process for internal exposures greater than 50 millirem committed effective dose equivalent was assessed.
No personnel had documented committed effective dose equivalent greater than 50 millirem.
The inspectors also reviewed the licensees physical and programmatic controls for highly activated and/or contaminated materials (non-fuel) stored within spent fuel or other storage pools.
These reviews constituted three inspection samples.
b. Findings
No findings of significance were identified.
.3 Problem Identification and Resolution
a. Inspection Scope
The inspectors reviewed licensee documentation packages for all PI events occurring since the last inspection to determine if any of these PI events involved dose rates >25 R/hr at 30 centimeters or >500 R/hr at 1 meter. No PI events occurred since the last inspection. Barriers were evaluated for failure and to determine if there were any barriers left to prevent personnel access. Unintended exposures >100 millirem total effective dose equivalent (or >5 rem shallow dose equivalent or >1.5 rem lens dose equivalent) were evaluated to determine if there were any regulatory overexposures or if there was a substantial potential for an overexposure. There were no unintended exposures of this magnitude.
This review constituted a single inspection sample.
b. Findings
No findings of significance were identified.
.4 High Risk Significant, High Dose Rate High Radiation Area (HRA) and Very High
Radiation Area (VHRA) Controls
a. Inspection Scope
The inspectors held discussions with the Radiation Protection Manager concerning high dose rate HRA and VHRA controls and procedures, including procedural changes that had occurred since the last inspection, in order to verify that any procedure modifications did not substantially reduce the effectiveness and level of worker protection. No procedural changes had been made since the last inspection.
The inspectors discussed with radiation protection (RP) supervisors the controls that were in place for special areas that had the potential to become VHRAs during certain plant operations to determine if these plant operations required communication beforehand with the RP group, so as to allow corresponding timely actions to properly post and control the radiation hazards.
The inspectors conducted plant walkdowns to verify the posting and locking of entrances to high dose rate HRAs, and VHRAs. No VHRAs are accessible in the plant.
These reviews represented three inspection samples.
b. Findings
No findings of significance were identified
.5 RP Technician Proficiency
a. Inspection Scope
During job performance observations, the inspectors evaluated RP technician performance with respect to RP work requirements and evaluated whether they were aware of the radiological conditions in their workplace, the RWP controls and limits in place, and if their performance was consistent with their training and qualifications with respect to the radiological hazards and work activities.
The inspectors reviewed two radiological problem reports which found that the cause of the event was RP technician error to determine if there was an observable pattern traceable to a similar cause, and to determine if this perspective matched the corrective action approach taken by the licensee to resolve the reported problems.
These reviews constituted two inspection samples.
b. Findings
No findings of significance were identified.
2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03)
.1 Inspection Planning
a. Inspection Scope
The inspectors reviewed the UFSAR to identify applicable radiation monitors associated with measuring transient HRAs and VHRAs including those used in remote emergency assessment. The inspectors identified the types of portable radiation detection instrumentation used for job coverage of HRA work, including fixed area radiation monitors used to provide radiological information in various plant areas and continuous air monitors used to assess airborne radiological conditions and work areas with the potential for workers to receive a 50 millirem or greater committed effective dose equivalent. Contamination monitors, whole body counters, and those radiation detection instruments utilized for the release of personnel and equipment from the radiologically controlled area were also identified.
This review constituted a single inspection sample.
b. Findings
No findings of significance were identified.
.2 Identification and Walkdowns of Additional Radiation Monitoring Instrumentation
a. Inspection Scope
The inspectors conducted walkdowns of selected area radiation monitors (ARMs)to verify that they were located as described in the UFSAR and were adequately positioned relative to the potential source(s) of radiation they were intended to monitor. Walkdowns were also conducted of those areas where portable survey instruments were calibrated/repaired and maintained for RP staff use to determine if those instruments designated ready for use were sufficient in number to support the RP program, had current calibration stickers, were operable, and were in adequate physical condition. Additionally, the inspectors observed the licensees instrument calibration units and the radiation sources used for instrument checks to assess their material condition and discussed their use with RP staff to determine if they were used appropriately. Licensee personnel demonstrated the methods for performing source checks of portable survey instruments.
This review constituted one inspection sample.
b. Findings
No findings of significance were identified.
.3 Calibration and Testing of Radiation Monitoring Instrumentation
a. Inspection Scope
The inspectors selectively reviewed calibration data for radiological instrumentation associated with monitoring transient high and/or very high radiation areas, instruments used for remote emergency assessment, and radiation monitors used to identify personnel contamination and for assessment of internal exposures to verify that the instruments had been calibrated as required by the licensees procedures, consistent with industry and regulatory standards. The inspectors also reviewed alarm setpoints for selected ARMs to verify that they were established consistent with the UFSAR or Technical Specifications, as applicable, and were consistent with industry practices and regulatory guidance. Specifically, the inspectors reviewed calibration procedures and the most recent calibration records and/or source output verification documents for the following radiation monitoring instrumentation and instrument calibration equipment:
- Post-accident Division 1 containment gamma radiation monitor;
- Reactor building fuel pool exhaust radiation monitor;
- Calibrator used to calibrate portable survey instruments and the associated instruments used to measure calibrator output; and
- Whole body counter.
The inspectors determined what actions were taken when, during calibration or source checks, an instrument was found out of calibration or exceeded as-found acceptance criteria. When that occurred, the inspectors verified that the licensees actions included a determination of the instrumentss previous usages and the possible consequences of that use since the prior calibration. The inspectors also discussed with RP staff the plants 10 CFR Part 61 source term (radionuclide mix) to determine if the calibration sources used were representative of the plant source term and to verify that difficult to detect nuclides were scaled into whole body count dose determinations.
This review constituted a single inspection sample.
b. Findings
No findings of significance were identified.
.4 Problem Identification and Resolution
a. Inspection Scope
The inspectors reviewed the licensees CAP documents and any special reports that involved personnel contamination monitor alarms due to personnel internal exposures to verify that identified problems were entered into the CAP for resolution. Licensee self-assessments, audits, and associated CAP records were also reviewed to verify that problems with radiological instrumentation or self-contained breathing apparatus were identified, characterized, prioritized, and resolved effectively using the CAP.
The inspectors reviewed CAP reports related to exposure significant radiological incidents that involved radiation monitoring instrument deficiencies since the last inspection in this area; none were identified. Members of the RP staff were interviewed and corrective action documents were reviewed to verify that follow-up activities were being conducted in an effective and timely manner commensurate with their importance to safety and risk based on the following:
- Initial problem identification, characterization, and tracking;
- Disposition of operability/reportability issues;
- Evaluation of safety significance/risk and priority for resolution;
- Identification of repetitive problems;
- Identification of contributing causes; and
- Identification and implementation of effective corrective actions.
The inspectors determined if the licensees self-assessment and audit activities completed for the 2-year period that preceded the inspection were identifying and addressing repetitive deficiencies or significant individual deficiencies in problem identification and resolution, as applicable.
This review represented three inspection samples.
b. Findings
No findings of significance were identified.
.5 RP Technician Instrument Use
a. Inspection Scope
The inspectors selectively verified that calibrations for those radiation survey instruments recently used by the licensee and for those currently designated for use had not lapsed. The inspectors also discussed instrument calibration methods and source response check practices with radiation protection staff and observed staff complete instrument source checks prior to use.
This review constituted a single inspection sample.
b. Findings
No findings of significance were identified.
.6 Self-Contained Breathing Apparatus (SCBA) Maintenance/Inspection and User Training
a. Inspection Scope
The inspectors reviewed aspects of the licensees respiratory protection program for compliance with the requirements of Subpart H of 10 CFR Part 20 and to determine if SCBAs were properly maintained and ready for emergency use. The inspectors reviewed records of inspection and functional tests for all SCBAs staged in the plant that were required by the licensees emergency plan. The inspectors verified the licensees capabilities for refilling and transporting SCBA air bottles during emergency conditions.
The inspectors verified that selected control room staff designated for the active on-shift duty roster from each shift including those individuals on the stations fire brigade were trained, respirator fit tested, and medically certified to use SCBAs.
Additionally, the inspectors reviewed SCBA qualification records for members of the licensees radiological emergency teams including the RP, chemistry, and maintenance staffs to determine if a sufficient number of staff were qualified to fulfill emergency response positions consistent with the licensees emergency plan and the requirements of 10 CFR 50.47. The inspectors verified that personal SCBA air bottle change-out was adequately covered as part the annual retraining plan.
The inspectors walked down spare SCBA air bottle stations located outside the main control room and inspected SCBA equipment maintained in the control room and staged for emergency use in various other areas of the plant. During the walkdowns, the inspectors examined several SCBA units to assess their material condition, to verify that air bottle hydrostatic tests were current, and to verify that bottles were pressurized to meet procedural requirements. The inspectors reviewed records of SCBA equipment inspection and testing and observed a member of the licensees staff demonstrate the methods used to conduct the inspections and functional tests to determine if these activities were performed consistent with procedure and the equipment manufacturers recommendations. The inspectors also ensured through record reviews that the required air cylinder hydrostatic testing was documented and current, that the Department of Transportation required retest air cylinder markings were in place for three randomly selected SCBA units and spare air bottles, and that the air quality for the compressor used to fill SCBA air bottles was routinely tested to verify Grade-D quality.
Additionally, the inspectors verified that licensee staff do not perform repairs of SCBA pressure regulators and maintenance on components vital to equipment function, therefore no manufacturer qualification was required.
These reviews represented two inspection samples.
b. Findings
No findings of significance were identified.
2PS3 Radiological Environmental Monitoring Program (REMP) and Radioactive Material Control Program (71122.03)
.1 Reviews of Radiological Environmental Monitoring Reports, Data and Quality Control
a. Inspection Scope
The NRC performed a number of confirmatory measurements of water samples to evaluate the licensees proficiency in collecting and in analyzing water samples for tritium and other radioactive isotopes. The samples were collected independently by the inspectors and by licensee personnel and sent to the NRCs contract laboratory for the analysis of tritium. The NRC and licensee obtained these samples from surface water and groundwater sampling points identified in the licensees Radiological Environmental Monitoring Program and from onsite and offsite groundwater monitoring wells. In particular, samples were obtained as part of the licensees environmental study of tritium, potential groundwater contamination, and residual onsite contamination from historical leaks (ADAMS ML062760008). While tritium was the primary radionuclide of concern, selected samples were also analyzed for gamma emitting radionuclides and for strontium. The inspectors performed these reviews to assess the licensees analytical detection capabilities for radio-analysis of environmental samples and its ability to accurately quantify radionuclides to an acceptable level of sensitivity. The criteria used to compare the sample results is provided in Attachment 2, and the results of the comparisons between the NRC and licensee results is provided in Attachment 3.
The inspectors considered the following activities in evaluating the cause of any comparisons that did not result in an agreement:
- re-analysis by licensee or NRCs contract laboratory;
- review of licensees interlaboratory cross check program results; and
- review of data for any apparent statistical biases.
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator Verification
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Occupational Radiation Safety, and Public Radiation Safety
.1 Initiating Events, Mitigating Systems, and Barrier Integrity Performance Indicator
Verification
a. Inspection Scope
The inspectors reviewed, at a minimum, the most recent 24 months of licensee event reports, licensee data reported to the NRC, plant logs, and NRC inspection reports to verify the following performance indicators reported by the licensee for the 2nd Quarter of 2006:
- Unplanned scrams per 7000 critical hours, Units 1 and 2;
- Scrams with loss of normal heat removal, Units 1 and 2;
- Unplanned power changes per 7000 critical hours, Units 1 and 2;
- Safety system functional failures, Units 1 and 2;
- Reactor coolant system (RCS) activity, Units 1 and 2; and
- RCS leakage, Units 1 and 2.
The inspectors verified that the licensee accurately reported performance as defined by the applicable revision of Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline.
These performance indicator reviews constituted twelve inspection samples.
b. Findings
No findings of significance were identified.
.2 Radiation Safety Performance Indicator Verification
a. Inspection Scope
The inspectors reviewed, at a minimum, the most recent 12 months of licensee event reports, licensee data reported to the NRC, plant logs, and NRC inspection reports to verify the following performance indicators reported by the licensee for the 2nd Quarter of 2006:
- Occupational exposure control effectiveness; and
- Radiological effluent technical specifications (RETS)/Offsite dose calculation manual (ODCM) radiological effluent occurrence.
The inspectors verified that the licensee accurately reported performance as defined by the applicable revision of Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline.
These performance indicator reviews constituted two inspection samples.
b. Findings
No findings of significance were identified.
.3 Data Submission
a. Inspection Scope
The inspectors performed a review of the data submitted by the licensee for the 2nd Quarter 2006 performance indicators for any obvious inconsistencies prior to its public release in accordance with IMC 0608, Performance Indicator Program.
This review was performed as part of the inspectors normal plant status activities and, as such, did not constitute a separate inspection sample.
b. Findings
No findings of significance were identified.
4OA2 Identification and Resolution of Problems
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
.1 Routine Review of Identification and Resolution of Problems
a. Inspection Scope
As part of the various baseline inspection procedures conducted during the period, the inspectors verified that the licensee entered the problems identified during the inspection into their corrective action program. Additionally, the inspectors verified that the licensee was identifying issues at an appropriate threshold and entering them in the corrective action program, and verified that problems included in the licensee's corrective action program were properly addressed for resolution. Attributes reviewed included: the complete and accurate identification of the problem; that timeliness was commensurate with the safety significance; that evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews were proper and adequate; and that the classification, prioritization, focus, and timeliness of corrective actions were commensurate with safety and sufficient to prevent recurrence of the issue.
These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.
b. Findings
A finding documented in Section 1R05 of this report was determined by inspectors to be related to the cross-cutting area of problem identification and resolution. Specifically, the corrective action program component of problem identification and resolution was identified because of the cross-cutting aspect whereby the licensee should take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity.
.2 Daily Corrective Action Program Reviews
a. Inspection Scope
In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees CAP. This review was accomplished through inspection of the stations daily condition report packages.
These daily reviews did not constitute any additional inspection samples. Instead, by procedure they were considered part of the inspectors daily plant status monitoring activities.
b. Findings
No findings of significance were identified.
.3 Selected Issue Follow-up Inspection:
Generic Letter 89-13 Program Corrective Actions Introduction During the first Quarter of 2006, inspectors identified several issues associated with the licensees GL 89-13 program. These issues included potential inadequacies with the RHR HX test procedure (see Section 1R12), and inconsistencies between the GL 89-13 program bases, commitments made to the NRC, and implementation of the program with respect to RHR HX testing and inspection. Since the licensee revised their GL 89-13 RHR HX program in 1998, various issues with the program were entered into the CAP that had a potential impact on the RHR HX test procedure and performance monitoring program. Inspectors selected these condition reports for an annual sample review of the licensees problem identification and resolution program.
The inspectors review of this issue constituted a single inspection sample.
a.
Effectiveness of Problem Identification
- (1) Inspection Scope The inspectors reviewed several years of IRs generated for GL 89-13 program issues to verify that the licensees identification of problems were complete, accurate, and timely, and that the consideration of extent of condition review, generic implications, common cause, and previous occurrences were adequate.
- (2) Issues Inspectors identified several issues with the effectiveness of problem identification.
Specifically, the licensees engineering staff did not identify underlying problems with the GL 89-13 program basis despite multiple entries in the CAP concerning the programs implementation and NRC commitment tracking. When issues were discovered, they were narrowly identified as low level independent problems and not related to other events affected by the GL 89-13 program status as a whole. For example, in 2002, IR 98176 identified that an indeterminate test of the 2B RHR HX had not been documented in the CAP. While this IR addressed why the test data was indeterminate, it missed the opportunity to identify the programmatic issue as to why an IR was not written until almost 2 years after the event. Instead, this IR was closed to a data point.
In 2004, IR 232215 identified a failure of the GL 89-13 program coordinator to update commitments to the NRC dating back to the year 2000. Assignment 3 of that IR required the licensees staff to review the GL 89-13 program basis document and verify that it accurately described current RHR HX maintenance and testing practices.
Further, IR 263535 identified several discrepancies between GL 89-13 commitments made to the NRC and the established program.
The licensees CAP assigned an apparent cause evaluation (ACE) to determine how these issues occurred and what measures should be taken to prevent these problems in the future. While the ACE did identify as the apparent cause a lack of knowledge of the GL 89-13 program administrator, both the ACE and IR 232215 assignment 3 failed to identify via extent of condition reviews the larger issues associated with the GL 89-13 program basis, including the change in the licensees RHR HX program from a test program to a maintenance program.
b.
Prioritization and Evaluation of Issues
- (1) Inspection Scope The inspectors reviewed the related CAP documents associated with the GL 89-13 program implementation, basis documents, and thermal performance test procedure.
The intent of this review was to determine if the CAP adequately evaluated and prioritized actions to address these problems.
- (2) Issues and Findings Introduction A finding of very low safety significance (Green) was identified by the inspectors. The inspectors determined that the licensee did not fully evaluate problems and properly prioritize corrective actions with respect to the RHR HX thermal performance test procedure and GL 89-13 HX performance monitoring program. An associated non-cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, was also identified by the inspectors.
Description In several cases, the inspectors determined that the CAP dispositioned corrective actions related to RHR HX testing and the GL 89-13 program with low priorities and inadequate evaluations. Some examples the inspectors identified included:
This IR recommended that the 2B HX should be retested at the next opportunity and that the testing procedure should be revised, yet the IR was closed to a data point. The RHR HX testing procedure was not revised to address this issue and the 2B RHR HX was not retested until 2005.
- In 2001, IR 95199 identified that a missed HX inspection indicated a breakdown in the implementation of the GL 89-13 program. This IR was closed to a data point.
- In 2004, IR 205117 identified that unqualified inspectors were performing GL 89-13 HX inspections during a review by the licensees nuclear oversight organization. The evaluation determined the problem was due to a procedural implementation issue. However, no evaluation was done as to why the GL 89-13 program did not already require and track the qualifications of HX inspectors.
- In 2004, in respond to discrepancies in GL 89-13 commitments, ACE 263535 assigned a focused area self assessment (FASA) to review, in part, commitments to GL 89-13. However, this FASA was not coded as corrective action, nor tied to ACE 263535. The FASA was assigned as IR 278122, which was later cancelled to IR 381358. IR 381358 was cancelled to IR 518151, which was not listed as due until November of 2006. Additionally, the ACE determined that the apparent cause was lack of knowledge by the program administrator, but it did not evaluate why, or to what extent, inconsistencies between commitments and the program bases may have been due to poor program documentation.
Additionally, IR 232215 assignment 3 directed the review of the GL 89-13 program basis document to verify it accurately described current licensee practices. The evaluation did include the RHR HX testing program, but was not thorough, as it consisted only of a restatement of the contents of the 1998 commitment change letter and did not actually evaluate current practices with respect to RHR HX testing.
- In 2005, IR 299006 documented the disruption of the 2B RHR HX heat transfer test due to unrelated operational activities occurring coincident with the test and the length of steady state data required by the test procedure. These conditions resulted in indeterminate test results. However, the evaluation performed in response to the IR did not fully address all problems with the test procedure.
Revisions were made to the test procedure based on the evaluation, but when the procedure was used to test the 1A RHR HX in 2006, the results were again indeterminate.
Analysis After reviewing CAP actions with respect to the RHR HX testing program, the inspectors determined that there was a performance deficiency associated with the corrective actions taken by the licensee. Specifically, the inspectors determined that the licensee had not thoroughly evaluated, nor given proper priority to, identified deficiencies in the RHR HX test procedure as identified in IR 98176. Further, the inspectors also determined that the licensee had failed to complete the GL 89-13 bases review and revision called for under ACE 263535 in 2004. The inspectors concluded that had these actions been completed in a timely manner in accordance with the licensees CAP requirements, many of the recent GL 89-13 program issues identified by the NRC could have been avoided.
In accordance with NRC IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, the inspectors determined that the finding was of more than minor significance in that it directly affected the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events. Specifically, this finding impacted one of the key attributes of this objective which is to ensure the quality of maintenance and test procedures for systems that must respond to initiating events.
The inspectors determined that the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, and conducted a Phase 1 characterization and initial screening. Because the finding did not represent a actual loss of operability or safety function and was not potentially risk significant with respect to a seismic, flooding, or severe weather initiating event, it was determined to be of very low safety significance (Green) and within the licensees response band.
Enforcement Table 3.2-1 of the licensees UFSAR indicated that the RHR system is subject to the requirements of 10 CFR 50, Appendix B. Criterion XVI of 10 CFR 50, Appendix B, states, in part, that: Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.
As discussed above, from 1998 through 2006, the licensee failed to properly evaluate and prioritize a number of corrective actions associated with their RHR HX performance monitoring program. In failing to do so, the licensee did not assure that these deficiencies were promptly identified and corrected, contrary to the requirements of 10 CFR 50, Appendix B, Criterion XVI.
The licensee has entered multiple items associated with this event into their corrective action program. (IRs 458571, 463253, 473455, 478852, 479741, 500835, 513814, 515613, 522479, 522487, 522493, 524622, 534870, 534872, 534875, 534877, and 534889). In response to these issues, licensee corrective actions planned include review of GL 89-13 program CAP documents to determine if any other identified issues were not fully dispositioned or resolved and to confirm that all corrective actions have been implemented and documented. Because the licensee has entered the issue into their corrective action program and the finding is of very low safety significance, this violation of 10 CFR 50, Appendix B, Criterion XVI, is being treated as a NCV, consistent with Section VI.A of the NRC Enforcement Policy.
The finding was also determined to involve the cross-cutting area of problem identification and resolution. Specifically, the corrective action program component of problem identification and resolution was identified because of the cross cutting aspect whereby the licensee should take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. (NCV 05000373/2006005-03; 05000374/2006005-03)
4OA5 Other
Cornerstone: Occupational Radiation Safety
.1 (Closed) VIO 05000374/2006010-01:
Contractor Pipefitters Enter Condenser Pit HRA Without Required Radiation Protection Brief.
The inspectors reviewed the licensees response to the NRC letter dated March 31, 2006, delivering a Notice of Violation. The Notice of Violation was issued as a result of information developed by the Office of Investigation that established the facts surrounding willful activities that resulted in individuals entering a HRA on February 13, 2005. The licensee conducted a root cause evaluation of the event and identified:
1) that communication weakness between the work group and the RP access control personnel led to a misunderstanding of the work location; and 2) contrary to known rules, the individuals believed permission had been granted to proceed to the work area regardless of the high radiation postings. The licensee took substantial corrective actions that included enhanced dynamic learning activities for all site personnel prior to outages to assure that clear communications during work briefings was improved.
Therefore, after review of these actions the NRC considers this matter closed.
4OA6 Meetings
.1 Exit Meeting
The inspectors presented the inspection results to the Plant Manager, Mr. Daniel Enright, and other members of licensee management on October 11, 2006. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
.2 Interim Exit Meetings
Interim exits were conducted for:
- A biennial heat sink performance inspection with the Site Vice President, Ms. Susan Landahl, and other members of licensee management on September 1, 2006.
- A periodic radiation protection instrumentation inspection with the Plant Manager, Mr. Daniel Enright, and other members of licensee management on September 29, 2006.
- Public Radiation Safety with Mr. M. Martin on October 13, 2006
4OA7 Licensee-Identified Violation
Cornerstone: Mitigating Systems
During a periodic review of temporary lead shielding packages, licensee personnel identified 10 lead blankets totaling 600 pounds hanging from a section of RHR shutdown cooling line piping in the Unit 2 reactor building. The temporary lead shielding had been installed during the February-March 2006 Unit 1 refueling outage using an informal maintenance work practice, vice approved procedural controls. Licensee procedure CC-AA-401, Maintenance Specification: Installation and Control of Temporary Shielding and Shielding Components, requires that all temporary lead shielding be installed in the plant using an appropriate shielding permit and a procedurally specified process. Further, Criterion V of 10 CFR 50, Appendix B, Instructions, Procedures, and Drawings, states, in part, that: Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.
Contrary to these requirements, the licensee installed 600 pounds of lead shielding on RHR shutdown cooling line 2RH04DA during the February-March 2006 Unit 1 refueling outage without using the procedurally required temporary shielding permit or process.
The inspectors determined the violation to be of more than minor significance in that if this practice were left uncorrected it would constitute a potentially more significant safety concern. However, the violation was also determined to be of very low safety significance because the licensee was able to demonstrate through engineering analysis that, in this case, the associated RHR shutdown cooling piping remained seismically qualified with the lead installed on the piping. The licensee had entered this issue into their CAP as IR 497765.
s: 1. Supplemental Information
2. Confirmatory Measurements Comparison Criteria
3. Trititum Sampling Results
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
- S. Landahl, Site Vice President
- D. Enright, Plant Manager
- J. Bashor, Site Engineering Director
- R. Bassett, Emergency Preparedness Manager
- R. Chrzanowski, Chemistry Manager
- T. Connor, Maintenance Director
- R. Ebright, Site Training Director
- F. Gogliotti, System Engineering Manager
- B. Kapellas, Radiation Protection Manager
- H. Madronero, Engineering Programs Manager
- S. Marik, Work Management Director
- J. Rappeport, Nuclear Oversight Manager
- D. Rhodes, Operations Director
- T. Simpkin, Regulatory Assurance Manager
- H. Vinyard, Shift Operations Superintendent
- C. Wilson, Station Security Manager
Nuclear Regulatory Commission
- B. Burgess, Chief, Reactor Projects Branch 2
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
- 05000374/2006005-01 NCV Failure to promptly repair a degraded condition associated with the 2B EDG day tank room structure. (Sections 1R05 and 4OA2.1)
- 05000374/2006005-02 NCV Inadequate procedure used for GL 89-13 Program thermal performance tests on RHR heat exchangers.
(Section 1R12.2)
- 05000374/2006005-03 NCV Failure to promptly correct identified issues associated with the GL 89-13 Program for RHR heat exchangers.
(Section 4OA2.3)
Closed
- 05000374/2006005-01 NCV Failure to promptly repair a degraded condition associated with the 2B EDG day tank room structure. (Section 1R05 and 4OA2.1)
- 05000374/2006004-01 URI Adequacy of B VC Compressor Operability Determinations and Post-Maintenance Tests (Section 1R12.1)
- 05000374/2006003-01 URI RHR Heat Exchanger Thermal Performance Testing and NRC GL 89-13 Conformance Issues (Section 1R12.2)
- 05000374/2006005-02 NCV Inadequate procedure used for GL 89-13 Program thermal performance tests on RHR heat exchangers.
(Section 1R12.2)
- 05000374/2006005-03 NCV Failure to promptly correct identified issues associated with the GL 89-13 Program for RHR heat exchangers.
(Section 4OA2.3)
- 05000374/2006010-01 VIO Contractor Pipefitters Enter Condenser Pit HRA Without Required Radiation Protection Brief (Section 4OA5.1)
Discussed
None.