{{#Wiki_filter:February 11, 2008 MEMORANDUM TO:               James T. Wiggins, Chairman Lessons-Learned Oversight Board David L. Pelton Lessons-Learned Program Manager FROM:                         Bruce S. Mallett /RA/
{{#Wiki_filter:February 11, 2008 MEMORANDUM TO:
Deputy Executive Director for Reactor and Preparedness Programs Office of the Executive Director for Operations
James T. Wiggins, Chairman Lessons-Learned Oversight Board David L. Pelton Lessons-Learned Program Manager FROM:
Bruce S. Mallett /RA/
Deputy Executive Director for Reactor and Preparedness Programs Office of the Executive Director for Operations  


==SUBJECT:==
==SUBJECT:==
PEACH BOTTOM REVIEW TEAM FINDINGS In December 2007, I tasked a team to review and evaluate NRC actions associated with the review of allegation and inspection activities related to inattentive security officers at the Peach Bottom nuclear power plant in 2007 and determine lessons-learned. The team made a thorough, independent, and supportable assessment of whether the NRCs allegation and inspection programs should be changed to more effectively evaluate and respond to allegations and to more effectively conduct inspections to detect inattentive security officers at nuclear facilities. The team, led by Marc Dapas, Deputy Regional Administrator, ZRegion I, issued a report of its findings to me on February 6, 2008. The report makes several recommendations that could improve our allegation and inspection program areas.
PEACH BOTTOM REVIEW TEAM FINDINGS In December 2007, I tasked a team to review and evaluate NRC actions associated with the review of allegation and inspection activities related to inattentive security officers at the Peach Bottom nuclear power plant in 2007 and determine lessons-learned. The team made a thorough, independent, and supportable assessment of whether the NRCs allegation and inspection programs should be changed to more effectively evaluate and respond to allegations and to more effectively conduct inspections to detect inattentive security officers at nuclear facilities. The team, led by Marc Dapas, Deputy Regional Administrator, ZRegion I, issued a report of its findings to me on February 6, 2008. The report makes several recommendations that could improve our allegation and inspection program areas.
Luis Reyes has issued a tasking memorandum in response to the teams findings. A copy is enclosed. The memorandum establishes a senior executive panel to review the teams recommendations and determine who should be tasked to implement actions and a schedule to address each recommendation. The memorandum also indicates specific actions for consideration in three areas, based on the recommendations. In parallel and in accordance with Management Directive 6.8, Lessons-Learned Program, I am forwarding the report of the teams findings and the memorandum from Mr. Reyes for review by you and the Lessons-Learned Oversight Board. If you have any question, please contact me.
Luis Reyes has issued a tasking memorandum in response to the teams findings. A copy is enclosed. The memorandum establishes a senior executive panel to review the teams recommendations and determine who should be tasked to implement actions and a schedule to address each recommendation. The memorandum also indicates specific actions for consideration in three areas, based on the recommendations. In parallel and in accordance with Management Directive 6.8, Lessons-Learned Program, I am forwarding the report of the teams findings and the memorandum from Mr. Reyes for review by you and the Lessons-Learned Oversight Board. If you have any question, please contact me.  


==Enclosures:==
==Enclosures:==
: 1. Peach Bottom Review Team Findings
: 1. Peach Bottom Review Team Findings
: 2. February 11, 2008 Memorandum
: 2. February 11, 2008 Memorandum  


ML080360426 OFFICE OEDO NAME         B. Mallett DATE         02/11/08}}
ML080360426 OFFICE OEDO NAME B. Mallett DATE 02/11/08}}

Latest revision as of 18:15, 14 January 2025

EDATS: OEDO-2008-0067 - Peach Bottom Review Team Findings - Memo to Wiggins/Pelton Fm Mallett
ML080360433
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 02/11/2008
From: Mallett B
NRC/EDO/DEDR
To: David Pelton, Wiggins J
Office of Nuclear Reactor Regulation
Mallett, Bruce S.
Shared Package
ML080430014 List:
References
OEDO-2008-0067
Download: ML080360433 (2)


Text

February 11, 2008 MEMORANDUM TO:

James T. Wiggins, Chairman Lessons-Learned Oversight Board David L. Pelton Lessons-Learned Program Manager FROM:

Bruce S. Mallett /RA/

Deputy Executive Director for Reactor and Preparedness Programs Office of the Executive Director for Operations

SUBJECT:

PEACH BOTTOM REVIEW TEAM FINDINGS In December 2007, I tasked a team to review and evaluate NRC actions associated with the review of allegation and inspection activities related to inattentive security officers at the Peach Bottom nuclear power plant in 2007 and determine lessons-learned. The team made a thorough, independent, and supportable assessment of whether the NRCs allegation and inspection programs should be changed to more effectively evaluate and respond to allegations and to more effectively conduct inspections to detect inattentive security officers at nuclear facilities. The team, led by Marc Dapas, Deputy Regional Administrator, ZRegion I, issued a report of its findings to me on February 6, 2008. The report makes several recommendations that could improve our allegation and inspection program areas.

Luis Reyes has issued a tasking memorandum in response to the teams findings. A copy is enclosed. The memorandum establishes a senior executive panel to review the teams recommendations and determine who should be tasked to implement actions and a schedule to address each recommendation. The memorandum also indicates specific actions for consideration in three areas, based on the recommendations. In parallel and in accordance with Management Directive 6.8, Lessons-Learned Program, I am forwarding the report of the teams findings and the memorandum from Mr. Reyes for review by you and the Lessons-Learned Oversight Board. If you have any question, please contact me.

Enclosures:

1. Peach Bottom Review Team Findings
2. February 11, 2008 Memorandum

ML080360426 OFFICE OEDO NAME B. Mallett DATE 02/11/08