{{#Wiki_filter:UNITED STATES | {{#Wiki_filter:UNITED STATES | ||
NUCLEAR REGULATORY COMMISSION | |||
REGION II | |||
SAM NUNN ATLANTA FEDERAL CENTER | |||
61 FORSYTH STREET, SW, SUITE 23T85 | |||
ATLANTA, GEORGIA 30303-8931 | |||
Mr. Tom E. Tynan | October 28, 2009 | ||
Vice President | |||
Southern Nuclear Operating Company, Inc. | |||
Vogtle Electric Generating Plant | Mr. Tom E. Tynan | ||
7821 River Road | Vice President | ||
Waynesboro, GA 30830 | Southern Nuclear Operating Company, Inc. | ||
SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED | Vogtle Electric Generating Plant | ||
7821 River Road | |||
Dear Mr. Tynan: | Waynesboro, GA 30830 | ||
In a telephone conversation on October 27, 2009, between Mr. George Gunn, Operations | |||
Training Supervisor and Mr. Dan Scukanec, Lead Instructor, of your staff, and Mr. Edwin Lea, | SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED | ||
Senior Operations Engineer, of the Nuclear Regulatory Commission (NRC), arrangements were | OPERATOR INITIAL EXAMINATION 05000424/2010301 AND 05000425/2010301 | ||
made for the administration of licensing examinations at Vogtle Electric Generating Plant. The | |||
operating test is scheduled to be administered during the week of February 22, 2010. The | Dear Mr. Tynan: | ||
written examination is scheduled to be administered the week of March 1, 2010. The on-site | |||
preparatory week is scheduled for the week of January 25, 2010. | In a telephone conversation on October 27, 2009, between Mr. George Gunn, Operations | ||
As agreed during the telephone conversation, your staff will prepare both the operating test and | Training Supervisor and Mr. Dan Scukanec, Lead Instructor, of your staff, and Mr. Edwin Lea, | ||
written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, | Senior Operations Engineer, of the Nuclear Regulatory Commission (NRC), arrangements were | ||
"Operator Licensing Examination Standards for Power Reactors." The U.S. NRC regional office | made for the administration of licensing examinations at Vogtle Electric Generating Plant. The | ||
will discuss with your staff any changes that might be necessary before the examinations are | operating test is scheduled to be administered during the week of February 22, 2010. The | ||
administered. Your staff has also agreed to make copies of all examination materials that are | written examination is scheduled to be administered the week of March 1, 2010. The on-site | ||
necessary for administering the examination. | preparatory week is scheduled for the week of January 25, 2010. | ||
To meet the above schedule, it will be necessary for your staff to furnish the operating test | |||
outline by December 9, 2009. Mr. Lea provided the written outline to members of your staff in | As agreed during the telephone conversation, your staff will prepare both the operating test and | ||
September 2009. The operating test, written examination, and the supporting reference | written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, | ||
materials identified in Attachment 3 to ES-201 will be due by January 8, 2010. Pursuant to Title | "Operator Licensing Examination Standards for Power Reactors." The U.S. NRC regional office | ||
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | will discuss with your staff any changes that might be necessary before the examinations are | ||
representative of the facility licensee shall approve the outline, examination, and test before | administered. Your staff has also agreed to make copies of all examination materials that are | ||
they are submitted to the NRC for review and approval. All materials shall be complete and | necessary for administering the examination. | ||
ready-to-use. | |||
To meet the above schedule, it will be necessary for your staff to furnish the operating test | |||
outline by December 9, 2009. Mr. Lea provided the written outline to members of your staff in | |||
September 2009. The operating test, written examination, and the supporting reference | |||
materials identified in Attachment 3 to ES-201 will be due by January 8, 2010. Pursuant to Title | |||
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | |||
representative of the facility licensee shall approve the outline, examination, and test before | |||
they are submitted to the NRC for review and approval. All materials shall be complete and | |||
ready-to-use. | |||
SNC | SNC | ||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in | 2 | ||
your response be contained in a separate enclosure and appropriately marked. Any delay in | |||
receiving the required examination and reference materials, or the submittal of inadequate or | We request that any personal, proprietary, sensitive unclassified, or safeguards information in | ||
incomplete materials, may cause the examinations to be rescheduled. | your response be contained in a separate enclosure and appropriately marked. Any delay in | ||
In order to conduct the requested written examinations and operating tests, it will be necessary | receiving the required examination and reference materials, or the submittal of inadequate or | ||
for your staff to provide adequate space and accommodations in accordance with ES-402, and | incomplete materials, may cause the examinations to be rescheduled. | ||
to make the simulation facility available on the dates noted above. In accordance with ES-302, | |||
your staff should retain the original simulator performance data (e.g., system pressures, | In order to conduct the requested written examinations and operating tests, it will be necessary | ||
temperatures, and levels) generated during the dynamic operating tests until the examination | for your staff to provide adequate space and accommodations in accordance with ES-402, and | ||
results are final. | to make the simulation facility available on the dates noted above. In accordance with ES-302, | ||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | your staff should retain the original simulator performance data (e.g., system pressures, | ||
effect while the written examinations and operating tests are being administered. | temperatures, and levels) generated during the dynamic operating tests until the examination | ||
To permit timely NRC review and evaluation, your staff should submit preliminary reactor | results are final. | ||
operator and senior reactor operator license applications, medical certifications, and waiver | |||
requests (if any) at least 30 days before the first examination date. If the applications are not | Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | ||
received at least 30 days before the examination date, a postponement may be necessary. | effect while the written examinations and operating tests are being administered. | ||
Signed applications certifying that all training has been completed should be submitted at least | |||
14 days before the first examination date. | To permit timely NRC review and evaluation, your staff should submit preliminary reactor | ||
This letter contains information collections that are subject to the Paperwork Reduction Act of | operator and senior reactor operator license applications, medical certifications, and waiver | ||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of | requests (if any) at least 30 days before the first examination date. If the applications are not | ||
Management and Budget. The public reporting burden for this collection of information is | received at least 30 days before the examination date, a postponement may be necessary. | ||
estimated to average 500 hours per response, including the time for reviewing instructions, | Signed applications certifying that all training has been completed should be submitted at least | ||
gathering and maintaining the data needed, writing the examinations, and completing and | 14 days before the first examination date. | ||
reviewing the collection of information. Send comments on any aspect of this collection of | |||
information, including suggestions for reducing the burden, to the Information and Records | This letter contains information collections that are subject to the Paperwork Reduction Act of | ||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of | |||
Management and Budget. The public reporting burden for this collection of information is | |||
estimated to average 500 hours per response, including the time for reviewing instructions, | |||
gathering and maintaining the data needed, writing the examinations, and completing and | |||
reviewing the collection of information. Send comments on any aspect of this collection of | |||
information, including suggestions for reducing the burden, to the Information and Records | |||
Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555- | Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555- | ||
0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, | 0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, | ||
Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management | Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management | ||
and Budget, Washington, DC 20503. | and Budget, Washington, DC 20503. | ||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its | |||
enclosures will be available electronically for public inspection in the NRC Public Document | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its | ||
Room or from the Publicly Available Records (PARS) component of the NRCs document | enclosures will be available electronically for public inspection in the NRC Public Document | ||
system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading- | Room or from the Publicly Available Records (PARS) component of the NRCs document | ||
rm.adams.html (the Public Electronic Reading Room). | system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading- | ||
rm.adams.html (the Public Electronic Reading Room). | |||
SNC | SNC | ||
Thank you for your cooperation in this matter. Mr. Scukanec has been advised of the policies | 3 | ||
and guidelines referenced in this letter. If you have any questions regarding the NRC's | |||
examination procedures and guidelines, please contact Mr. Edwin Lea at (404) 562-4567, | Thank you for your cooperation in this matter. Mr. Scukanec has been advised of the policies | ||
(Internet E-mail: edwin.lea @nrc.gov), or me at (404) 562-4550, (Internet E-mail: | and guidelines referenced in this letter. If you have any questions regarding the NRC's | ||
malcolm.widmann@nrc.gov). | examination procedures and guidelines, please contact Mr. Edwin Lea at (404) 562-4567, | ||
(Internet E-mail: edwin.lea @nrc.gov), or me at (404) 562-4550, (Internet E-mail: | |||
malcolm.widmann@nrc.gov). | |||
Sincerely, | |||
Docket Nos.: 50-424, 50-425 | |||
License Nos.: NPF-68, NPF-81 | |||
cc: (See Page 4) | |||
/RA/ | |||
Malcolm T. Widmann, Chief | |||
Operations Branch | |||
Division of Reactor Safety | |||
Docket Nos.: 50-424, 50-425 | |||
License Nos.: NPF-68, NPF-81 | |||
cc: (See Page 4) | |||
_________________________ | _________________________ | ||
OFFICE | |||
SIGNATURE | X SUNSI REVIEW COMPLETE MTW | ||
NAME | OFFICE | ||
DATE | RII:DRS | ||
E-MAIL COPY? | RII:DRS | ||
SIGNATURE | |||
EXL /RA/ | |||
MTW /RA/ | |||
NAME | |||
ELea | |||
MWidmann | |||
DATE | |||
10/28/2009 | |||
10/28/2009 | |||
E-MAIL COPY? | |||
YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO | |||
SNC | SNC | ||
cc | 4 | ||
cc w/encl: | |||
Angela Thornhill | |||
Managing Attorney and Compliance Officer | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | |||
N. J. Stringfellow | |||
Manager | |||
Licensing | |||
Environmental | Southern Nuclear Operating Company, Inc. | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Jeffrey T. Gasser | |||
Executive Vice President | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | Electronic Mail Distribution | ||
L. Mike Stinson | |||
Vice President | |||
Fleet Operations Support | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | |||
Michael A. MacFarlane | |||
Southern Nuclear Operating Company, Inc. | |||
40 Inverness Center Parkway | |||
P.O. Box 1295 | |||
Birmingham, AL 35201-1295 | |||
Paula Marino | |||
Vice President | |||
Engineering | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | |||
Bob Masse | |||
Resident Manager | |||
Vogtle Electric Generating Plant | |||
Oglethorpe Power Corporation | |||
Electronic Mail Distribution | |||
Moanica Caston | |||
Vice President and General Counsel | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | |||
Office of the Attorney General | |||
Electronic Mail Distribution | |||
Lee Foley | |||
Manager of Contracts Generation | |||
Oglethorpe Power Corporation | |||
Electronic Mail Distribution | |||
Mr. N. Holcomb | |||
Commissioner | |||
Department of Natural Resources | |||
Electronic Mail Distribution | |||
Dr. Carol Couch | |||
Director | |||
Environmental Protection | |||
Department of Natural Resources | |||
Electronic Mail Distribution | |||
Cynthia Sanders | |||
Program Manager | |||
Radioactive Materials Program | |||
Department of Natural Resources | |||
Electronic Mail Distribution | |||
Jim Sommerville | |||
(Acting) Chief | |||
Environmental Protection Division | |||
Department of Natural Resources | |||
Electronic Mail Distribution | |||
Mr. Steven M. Jackson | |||
Senior Engineer - Power Supply | |||
Municipal Electric Authority of Georgia | |||
Electronic Mail Distribution | |||
Mr. Reece McAlister | |||
Executive Secretary | |||
Georgia Public Service Commission | |||
Electronic Mail Distribution | |||
Office of the County Commissioner | |||
Burke County Commission | |||
Electronic Mail Distribution | |||
Arthur H. Domby, Esq. | |||
Troutman Sanders | |||
Electronic Mail Distribution | |||
(cc continued next page) | |||
SNC | SNC | ||
Letter to Tom E. Tynan from Malcolm T. Widmann dated October 28, 2009 | 5 | ||
SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED | |||
cc continued | |||
Distribution w/encl: | |||
C. Evans, RII | Director | ||
L. Slack, RII | Consumers' Utility Counsel Division | ||
OE Mail | Govenor's Office of Consumer Affairs | ||
RIDSNRRDIRS | 2 M. L. King, Jr. Drive | ||
PUBLIC | Plaza Level East; Suite 356 | ||
Atlanta, GA 30334-4600 | |||
Susan E. Jenkins | |||
Director, Division of Waste Management | |||
Bureau of Land and Waste Management | |||
S.C. Department of Health and | |||
Environmental Control | |||
Electronic Mail Distribution | |||
Richard D. Brigdon | |||
Plant Training and | |||
Emergency Preparedness Manager | |||
Southern Nuclear Operating Company, Inc. | |||
Electronic Mail Distribution | |||
SNC | |||
6 | |||
Letter to Tom E. Tynan from Malcolm T. Widmann dated October 28, 2009 | |||
SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED | |||
OPERATOR INITIAL EXAMINATION 05000424/2010301 AND 05000425/2010301 | |||
Distribution w/encl: | |||
C. Evans, RII | |||
L. Slack, RII | |||
OE Mail | |||
RIDSNRRDIRS | |||
PUBLIC | |||
RidsNrrPMVogtle Resource | RidsNrrPMVogtle Resource | ||
}} | }} | ||
Latest revision as of 08:38, 14 January 2025
| ML093010327 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 10/28/2009 |
| From: | Widmann M Division of Reactor Safety II |
| To: | Tynan T Southern Nuclear Operating Co |
| References | |
| 50-424/10-301, 50-425/10-301 | |
| Download: ML093010327 (7) | |
See also: IR 05000424/2010301
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
SAM NUNN ATLANTA FEDERAL CENTER
61 FORSYTH STREET, SW, SUITE 23T85
ATLANTA, GEORGIA 30303-8931
October 28, 2009
Mr. Tom E. Tynan
Vice President
Southern Nuclear Operating Company, Inc.
Vogtle Electric Generating Plant
7821 River Road
Waynesboro, GA 30830
SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED
OPERATOR INITIAL EXAMINATION 05000424/2010301 AND 05000425/2010301
Dear Mr. Tynan:
In a telephone conversation on October 27, 2009, between Mr. George Gunn, Operations
Training Supervisor and Mr. Dan Scukanec, Lead Instructor, of your staff, and Mr. Edwin Lea,
Senior Operations Engineer, of the Nuclear Regulatory Commission (NRC), arrangements were
made for the administration of licensing examinations at Vogtle Electric Generating Plant. The
operating test is scheduled to be administered during the week of February 22, 2010. The
written examination is scheduled to be administered the week of March 1, 2010. The on-site
preparatory week is scheduled for the week of January 25, 2010.
As agreed during the telephone conversation, your staff will prepare both the operating test and
written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021,
"Operator Licensing Examination Standards for Power Reactors." The U.S. NRC regional office
will discuss with your staff any changes that might be necessary before the examinations are
administered. Your staff has also agreed to make copies of all examination materials that are
necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outline by December 9, 2009. Mr. Lea provided the written outline to members of your staff in
September 2009. The operating test, written examination, and the supporting reference
materials identified in Attachment 3 to ES-201 will be due by January 8, 2010. Pursuant to Title
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outline, examination, and test before
they are submitted to the NRC for review and approval. All materials shall be complete and
ready-to-use.
2
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications, medical certifications, and waiver
requests (if any) at least 30 days before the first examination date. If the applications are not
received at least 30 days before the examination date, a postponement may be necessary.
Signed applications certifying that all training has been completed should be submitted at least
14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of
Management and Budget. The public reporting burden for this collection of information is
estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions,
gathering and maintaining the data needed, writing the examinations, and completing and
reviewing the collection of information. Send comments on any aspect of this collection of
information, including suggestions for reducing the burden, to the Information and Records
Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer,
Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management
and Budget, Washington, DC 20503.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosures will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of the NRCs document
system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-
rm.adams.html (the Public Electronic Reading Room).
3
Thank you for your cooperation in this matter. Mr. Scukanec has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRC's
examination procedures and guidelines, please contact Mr. Edwin Lea at (404) 562-4567,
(Internet E-mail: edwin.lea @nrc.gov), or me at (404) 562-4550, (Internet E-mail:
malcolm.widmann@nrc.gov).
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operations Branch
Division of Reactor Safety
Docket Nos.: 50-424, 50-425
cc: (See Page 4)
_________________________
X SUNSI REVIEW COMPLETE MTW
OFFICE
RII:DRS
RII:DRS
SIGNATURE
EXL /RA/
MTW /RA/
NAME
ELea
MWidmann
DATE
10/28/2009
10/28/2009
E-MAIL COPY?
YES
NO YES
NO YES
NO YES
NO YES
NO YES
NO YES
NO
4
cc w/encl:
Angela Thornhill
Managing Attorney and Compliance Officer
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
N. J. Stringfellow
Manager
Licensing
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
Jeffrey T. Gasser
Executive Vice President
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
L. Mike Stinson
Vice President
Fleet Operations Support
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
Michael A. MacFarlane
Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway
P.O. Box 1295
Birmingham, AL 35201-1295
Paula Marino
Vice President
Engineering
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
Bob Masse
Resident Manager
Vogtle Electric Generating Plant
Oglethorpe Power Corporation
Electronic Mail Distribution
Moanica Caston
Vice President and General Counsel
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
Office of the Attorney General
Electronic Mail Distribution
Lee Foley
Manager of Contracts Generation
Oglethorpe Power Corporation
Electronic Mail Distribution
Mr. N. Holcomb
Commissioner
Department of Natural Resources
Electronic Mail Distribution
Dr. Carol Couch
Director
Environmental Protection
Department of Natural Resources
Electronic Mail Distribution
Cynthia Sanders
Program Manager
Radioactive Materials Program
Department of Natural Resources
Electronic Mail Distribution
Jim Sommerville
(Acting) Chief
Environmental Protection Division
Department of Natural Resources
Electronic Mail Distribution
Mr. Steven M. Jackson
Senior Engineer - Power Supply
Municipal Electric Authority of Georgia
Electronic Mail Distribution
Mr. Reece McAlister
Executive Secretary
Georgia Public Service Commission
Electronic Mail Distribution
Office of the County Commissioner
Burke County Commission
Electronic Mail Distribution
Arthur H. Domby, Esq.
Troutman Sanders
Electronic Mail Distribution
(cc continued next page)
5
cc continued
Director
Consumers' Utility Counsel Division
Govenor's Office of Consumer Affairs
2 M. L. King, Jr. Drive
Plaza Level East; Suite 356
Atlanta, GA 30334-4600
Susan E. Jenkins
Director, Division of Waste Management
Bureau of Land and Waste Management
S.C. Department of Health and
Environmental Control
Electronic Mail Distribution
Richard D. Brigdon
Plant Training and
Emergency Preparedness Manager
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
6
Letter to Tom E. Tynan from Malcolm T. Widmann dated October 28, 2009
SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NOTIFICATION OF LICENSED
OPERATOR INITIAL EXAMINATION 05000424/2010301 AND 05000425/2010301
Distribution w/encl:
C. Evans, RII
L. Slack, RII
OE Mail
RIDSNRRDIRS
PUBLIC
RidsNrrPMVogtle Resource