ML112000064: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:July 18, 2011 | ||
EA-11-025 | |||
David J. Bannister, Vice President | |||
EA-11-025 | and Chief Nuclear Officer | ||
David J. Bannister, Vice President | Omaha Public Power District | ||
Fort Calhoun Station FC-2-4 | |||
Omaha Public Power District | P.O. Box 550 | ||
Fort Calhoun Station FC-2-4 | Fort Calhoun, NE 68023-0550 | ||
P.O. Box 550 | |||
Fort Calhoun, NE 68023-0550 | SUBJECT: | ||
SUBJECT: | FORT CALHOUN STATION - FINAL SIGNIFICANCE DETERMINATION | ||
FOR A WHITE FINDING AND NOTICE OF VIOLATION, NRC INSPECTION | |||
REPORT 05000285/2011007 | |||
Dear Mr. Bannister: | |||
The purpose of this letter is to provide you the final significance determination of the preliminary | Dear Mr. Bannister: | ||
Yellow finding identified in our previous communication dated May 6, 2011, which included the | |||
subject inspection report. The inspection finding was assessed using the Significance | The purpose of this letter is to provide you the final significance determination of the preliminary | ||
Determination Process and was preliminarily characterized as a Yellow finding with substantial | Yellow finding identified in our previous communication dated May 6, 2011, which included the | ||
importance to safety that may result in additional NRC inspection and potentially other NRC | subject inspection report. The inspection finding was assessed using the Significance | ||
action. This finding was associated with the June 14, 2010, failure of a reactor trip | Determination Process and was preliminarily characterized as a Yellow finding with substantial | ||
contactor (M2) in your reactor protection system. | importance to safety that may result in additional NRC inspection and potentially other NRC | ||
At your request, a regulatory conference was held on June 2, 2011, to further discuss your | action. This finding was associated with the June 14, 2010, failure of a reactor trip | ||
views on this issue. During the regulatory conference, your staff described the Fort Calhoun | contactor (M2) in your reactor protection system. | ||
Stations assessment of the significance of the finding and they provided a summary of the | |||
corrective actions, and insights from the root cause analysis of the finding. This material is | At your request, a regulatory conference was held on June 2, 2011, to further discuss your | ||
documented in the NRC Meeting Summary (ML111660027) dated June 14, 2011. You also | views on this issue. During the regulatory conference, your staff described the Fort Calhoun | ||
requested that the NRC reconsider its evaluation of the findings risk significance based on four | Stations assessment of the significance of the finding and they provided a summary of the | ||
specific areas of consideration where differences exist between the NRCs preliminary | corrective actions, and insights from the root cause analysis of the finding. This material is | ||
significance determination and your staffs risk assessment. These are: 1) Shorter Exposure | documented in the NRC Meeting Summary (ML111660027) dated June 14, 2011. You also | ||
Time (T/2 + repair vs. T + repair); 2) Lower Failure Probability for Clutch Power Supply Breaker; | requested that the NRC reconsider its evaluation of the findings risk significance based on four | ||
3) Common Cause Failure Determination; and 4) Higher Operator Reliability in Tripping the | specific areas of consideration where differences exist between the NRCs preliminary | ||
Reactor. Between June 6 and June 28, 2011, you provided supplemental information regarding | significance determination and your staffs risk assessment. These are: 1) Shorter Exposure | ||
follow-up questions asked by NRC staff at the conference. This additional material was | Time (T/2 + repair vs. T + repair); 2) Lower Failure Probability for Clutch Power Supply Breaker; | ||
docketed as ADAMS document ML111881131. | 3) Common Cause Failure Determination; and 4) Higher Operator Reliability in Tripping the | ||
The NRC has reviewed your areas of consideration and our evaluation of each is provided in | Reactor. Between June 6 and June 28, 2011, you provided supplemental information regarding | ||
Enclosure 2 of this letter along with the revised NRC risk assessment. The NRC considered the | follow-up questions asked by NRC staff at the conference. This additional material was | ||
information developed during the inspection, and the information that you provided at, and | docketed as ADAMS document ML111881131. | ||
subsequent to, the conference. The NRC has concluded that the finding is appropriately | |||
The NRC has reviewed your areas of consideration and our evaluation of each is provided in | |||
Enclosure 2 of this letter along with the revised NRC risk assessment. The NRC considered the | |||
information developed during the inspection, and the information that you provided at, and | |||
subsequent to, the conference. The NRC has concluded that the finding is appropriately | |||
UNITED STATES | |||
NUCLEAR REGULATORY COMMISSION | |||
REGION IV | |||
612 EAST LAMAR BLVD, SUITE 400 | |||
ARLINGTON, TEXAS 76011-4125 | |||
Omaha Public Power District | Omaha Public Power District | ||
characterized as White, a finding with low to moderate importance to safety and will result in | - 2 - | ||
additional NRC inspection and potentially other NRC actions. | EA-11-025 | ||
You have 30 calendar days from the date of this letter to appeal the staffs determination of | |||
significance for the identified White finding. Such appeals will be considered to have merit only | |||
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. An | |||
appeal must be sent in writing to the Regional Administrator, U.S. Nuclear Regulatory | |||
Commission, Region IV, 612 E. Lamar Blvd., Suite 400, Arlington, Texas 76011-4125. | characterized as White, a finding with low to moderate importance to safety and will result in | ||
The NRC has concluded that failure to assure that the cause of a significant condition adverse | additional NRC inspection and potentially other NRC actions. | ||
to quality was determined and failure to take corrective actions to preclude repetition of the | |||
condition, is a violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, | You have 30 calendar days from the date of this letter to appeal the staffs determination of | ||
Appendix B, Criterion XVI, Corrective Action, as cited in the enclosed Notice of Violation. The | significance for the identified White finding. Such appeals will be considered to have merit only | ||
circumstances surrounding the violation are described in detail in the subject inspection report. | if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. An | ||
In accordance with the NRC Enforcement Policy, the Notice of Violation is considered an | appeal must be sent in writing to the Regional Administrator, U.S. Nuclear Regulatory | ||
escalated enforcement action because it is associated with a White finding. | Commission, Region IV, 612 E. Lamar Blvd., Suite 400, Arlington, Texas 76011-4125. | ||
You are required to respond to this letter. Please follow the instructions specified in the | |||
enclosed Notice of Violation when preparing your response. If you have additional information | The NRC has concluded that failure to assure that the cause of a significant condition adverse | ||
that you believe the NRC should consider, you may provide it in your response to the Notice. | to quality was determined and failure to take corrective actions to preclude repetition of the | ||
The NRC review of your response to the Notice will also determine whether further enforcement | condition, is a violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, | ||
action is necessary to ensure compliance with regulatory requirements. | Appendix B, Criterion XVI, Corrective Action, as cited in the enclosed Notice of Violation. The | ||
Because your current plant performance is in the Degraded Cornerstone (Mitigating Systems) | circumstances surrounding the violation are described in detail in the subject inspection report. | ||
Column, and this violation also impacts that cornerstone, the NRC will use the NRC Action | In accordance with the NRC Enforcement Policy, the Notice of Violation is considered an | ||
Matrix to determine the most appropriate NRC response to this violation. The NRC will notify | escalated enforcement action because it is associated with a White finding. | ||
you, by separate correspondence, of that determination. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its | You are required to respond to this letter. Please follow the instructions specified in the | ||
enclosures, and your response will be available electronically for public inspection in the NRC | enclosed Notice of Violation when preparing your response. If you have additional information | ||
Public Document Room or from the NRCs document system (ADAMS). ADAMS is accessible | that you believe the NRC should consider, you may provide it in your response to the Notice. | ||
from the NRC Web site at www.nrc.gov/reading-rm/adams.html. To the extent possible, your | The NRC review of your response to the Notice will also determine whether further enforcement | ||
response should not include any personal privacy, proprietary, or safeguards information so that | action is necessary to ensure compliance with regulatory requirements. | ||
it can be made available to the Public without redaction. | |||
Because your current plant performance is in the Degraded Cornerstone (Mitigating Systems) | |||
Column, and this violation also impacts that cornerstone, the NRC will use the NRC Action | |||
Matrix to determine the most appropriate NRC response to this violation. The NRC will notify | |||
you, by separate correspondence, of that determination. | |||
Docket: 50-285 | |||
License: DPR-40 | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its | ||
Enclosures: | enclosures, and your response will be available electronically for public inspection in the NRC | ||
1. Notice of Violation | Public Document Room or from the NRCs document system (ADAMS). ADAMS is accessible | ||
from the NRC Web site at www.nrc.gov/reading-rm/adams.html. To the extent possible, your | |||
response should not include any personal privacy, proprietary, or safeguards information so that | |||
it can be made available to the Public without redaction. | |||
Sincerely, | |||
/RA/ | |||
Elmo E. Collins | |||
Regional Administrator | |||
Docket: 50-285 | |||
License: DPR-40 | |||
Enclosures: | |||
1. Notice of Violation | |||
Omaha Public Power District | Omaha Public Power District | ||
2. Fort Calhoun Reactor Protection System Issue | - 3 - | ||
EA-11-025 | |||
cc w/Enclosures: | |||
Distribution via Listserv | |||
2. Fort Calhoun Reactor Protection System Issue | |||
Final Significance Determination | |||
cc w/Enclosures: | |||
Distribution via Listserv | |||
Omaha Public Power District | Omaha Public Power District | ||
Electronic distribution by RIV: | - 4 - | ||
Regional Administrator (Elmo.Collins@nrc.gov) | EA-11-025 | ||
Deputy Regional Administrator (Art.Howell@nrc.gov) | |||
DRP Director (Kriss.Kennedy@nrc.gov) | |||
Acting DRP Deputy Director (Jeff.Clark@nrc.gov) | |||
DRS Director (Anton.Vegel@nrc.gov) | |||
Acting DRS Deputy Director (Robert.Caldwell@nrc.gov) | Electronic distribution by RIV: | ||
Senior Resident Inspector (John.Kirkland@nrc.gov) | Regional Administrator (Elmo.Collins@nrc.gov) | ||
Resident Inspector (Jacob.Wingebach@nrc.gov) | Deputy Regional Administrator (Art.Howell@nrc.gov) | ||
Acting Branch Chief, DRP/E (Ray.Azua@nrc.gov) | DRP Director (Kriss.Kennedy@nrc.gov) | ||
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) | Acting DRP Deputy Director (Jeff.Clark@nrc.gov) | ||
Project Engineer (Jim.Melfi@nrc.gov) | DRS Director (Anton.Vegel@nrc.gov) | ||
Project Engineer (Chris.Smith@nrc.gov) | Acting DRS Deputy Director (Robert.Caldwell@nrc.gov) | ||
RIV Enforcement, ACES (Ray.Kellar@nrc.gov) | Senior Resident Inspector (John.Kirkland@nrc.gov) | ||
FCS Administrative Assistant (Berni.Madison@nrc.gov) | Resident Inspector (Jacob.Wingebach@nrc.gov) | ||
Public Affairs Officer (Victor.Dricks@nrc.gov) | Acting Branch Chief, DRP/E (Ray.Azua@nrc.gov) | ||
Public Affairs Officer (Lara.Uselding@nrc.gov) | Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) | ||
Acting Branch Chief, DRS/TSB (Dale Powers@nrc.gov) | Project Engineer (Jim.Melfi@nrc.gov) | ||
Project Manager (Lynnea.Wilkins@nrc.gov) | Project Engineer (Chris.Smith@nrc.gov) | ||
RITS Coordinator (Marisa.Herrera@nrc.gov) | RIV Enforcement, ACES (Ray.Kellar@nrc.gov) | ||
Regional Counsel (Karla.Fuller@nrc.gov) | FCS Administrative Assistant (Berni.Madison@nrc.gov) | ||
Regional State Liaison Officer (Bill.Maier@nrc.gov) | Public Affairs Officer (Victor.Dricks@nrc.gov) | ||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) | Public Affairs Officer (Lara.Uselding@nrc.gov) | ||
OEMail Resource | Acting Branch Chief, DRS/TSB (Dale Powers@nrc.gov) | ||
DRS/TSB STA (Dale.Powers@nrc.gov) | Project Manager (Lynnea.Wilkins@nrc.gov) | ||
RIV/ETA: OEDO (John.McHale@nrc.gov) | RITS Coordinator (Marisa.Herrera@nrc.gov) | ||
R:_\Reactors\FCS\FCS-Final-Significance.docx | Regional Counsel (Karla.Fuller@nrc.gov) | ||
Regional State Liaison Officer (Bill.Maier@nrc.gov) | |||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) | |||
OEMail Resource | |||
DRS/TSB STA (Dale.Powers@nrc.gov) | |||
RIV/ETA: OEDO (John.McHale@nrc.gov) | |||
R:_\\Reactors\\FCS\\FCS-Final-Significance.docx | |||
ADAMS | |||
Yes | |||
SUNSI Review Complete | |||
Reviewer Initials: JAC | |||
Publicly Available | |||
Non-publicly Available | |||
Sensitive | |||
Non-sensitive | |||
RIV/DRP:PBE | |||
DRP:PBE | |||
DRS-SRA | |||
D:DRS | |||
ACES | |||
RVAzua | |||
JAClark | |||
DPLoveless | |||
AVegel | |||
RKellar | |||
/RA/ | |||
/RA/ | |||
/RA/ | |||
/RA/ | |||
/RA/via email | |||
07/08/11 | |||
07/08/11 | |||
07/14/11 | |||
07/14/11 | |||
07/07/11 | |||
Counsel | |||
NRR/OE | |||
D:DRP | |||
ORA | |||
MBarkman Marsh | |||
NColeman | |||
KMKennedy | |||
EECollins | |||
/RA/via email | |||
/RA/via email | |||
/RA/ | |||
/RA/ | |||
07/13/11 | |||
07/13/11 | |||
07/15/11 | |||
07/18/11 | |||
OFFICIAL RECORD COPY | |||
T=Telephone E=E-mail F=Fax | |||
Omaha Public Power District | |||
Fort Calhoun Station | |||
During an NRC inspection conducted from January 17 through April 15, 2011, one violation of | -1- | ||
NRC requirements was identified. In accordance with the NRC Enforcement Policy, the | Enclosure 1 | ||
violation is listed below: | NOTICE OF VIOLATION | ||
Omaha Public Power District | |||
Docket No.: 05000285 | |||
Fort Calhoun Station | |||
License No.: DPR-40 | |||
EA-11-025 | |||
During an NRC inspection conducted from January 17 through April 15, 2011, one violation of | |||
NRC requirements was identified. In accordance with the NRC Enforcement Policy, the | |||
violation is listed below: | |||
Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI, | |||
Corrective Action, requires, in part, that measures shall be established to assure that | |||
conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, | |||
This violation is associated with a White significance determination process finding in the | defective material and equipment, and nonconformances are promptly identified and | ||
Mitigating Systems Cornerstone. | corrected. In the case of significant conditions adverse to quality, the measures shall | ||
Pursuant to the provisions of 10 CFR 2.201, Omaha Public Power District is hereby required to | assure that the cause of the condition is determined and corrective action taken to | ||
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, | preclude repetition. | ||
ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional | |||
Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400, | Contrary to the above, between November 3, 2008, and June 14, 2010, the licensee | ||
Arlington, Texas, 76011-4125, and a copy to the NRC Resident Inspector - Fort Calhoun | failed to assure that the cause of a significant condition adverse to quality was | ||
Station, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This | determined and corrective actions were taken to preclude repetition. Specifically, the | ||
reply should be clearly marked as a "Reply to a Notice of Violation; EA-11-025" and should | licensee failed to preclude shading coils from repetitively becoming loose material in the | ||
include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing | M2 reactor trip contactor. The licensee failed to identify that the loose parts in the trip | ||
the violation or severity level, (2) the corrective steps that have been taken and the results | contactor represented a potential failure of the contactor if they became an obstruction; | ||
achieved, (3) the corrective steps that will be taken, and (4) the date when full compliance will | and therefore, failed to preclude repetition of this significant condition adverse to quality, | ||
be achieved. Your response may reference or include previous docketed correspondence, if | that subsequently resulted in the contactor failing. | ||
the correspondence adequately addresses the required response. If an adequate reply is not | |||
received within the time specified in this Notice, an order or a Demand for Information may be | This violation is associated with a White significance determination process finding in the | ||
issued as to why the license should not be modified, suspended, or revoked, or why such other | Mitigating Systems Cornerstone. | ||
action as may be proper should not be taken. Where good cause is shown, consideration will | |||
be given to extending the response time. | Pursuant to the provisions of 10 CFR 2.201, Omaha Public Power District is hereby required to | ||
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, | |||
ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional | |||
Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400, | |||
Arlington, Texas, 76011-4125, and a copy to the NRC Resident Inspector - Fort Calhoun | |||
Station, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This | |||
reply should be clearly marked as a "Reply to a Notice of Violation; EA-11-025" and should | |||
include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing | |||
the violation or severity level, (2) the corrective steps that have been taken and the results | |||
achieved, (3) the corrective steps that will be taken, and (4) the date when full compliance will | |||
be achieved. Your response may reference or include previous docketed correspondence, if | |||
the correspondence adequately addresses the required response. If an adequate reply is not | |||
received within the time specified in this Notice, an order or a Demand for Information may be | |||
issued as to why the license should not be modified, suspended, or revoked, or why such other | |||
action as may be proper should not be taken. Where good cause is shown, consideration will | |||
be given to extending the response time. | |||
If you contest this enforcement action, you should also provide a copy of your response, with | |||
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear | |||
Regulatory Commission, Washington DC 20555-0001. | |||
Because your response will be made available electronically for public inspection in the NRC | |||
Public Document Room or from the NRCs document system (ADAMS), accessible from the | -2- | ||
NRCs website at www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not | Enclosure 1 | ||
include any personal privacy, proprietary, or safeguards information so that it can be made | If you contest this enforcement action, you should also provide a copy of your response, with | ||
available to the public without redaction. If personal privacy or proprietary information is | the basis for your denial, to the Director, Office of Enforcement, United States Nuclear | ||
necessary to provide an acceptable response, then please provide a bracketed copy of your | Regulatory Commission, Washington DC 20555-0001. | ||
response that identifies the information that should be protected and a redacted copy of your | |||
response that deletes such information. If you request withholding of such material, you must | Because your response will be made available electronically for public inspection in the NRC | ||
specifically identify the portions of your response that you seek to have withheld and provide in | Public Document Room or from the NRCs document system (ADAMS), accessible from the | ||
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will | NRCs website at www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not | ||
create an unwarranted invasion of personal privacy or provide the information required by | include any personal privacy, proprietary, or safeguards information so that it can be made | ||
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial | available to the public without redaction. If personal privacy or proprietary information is | ||
information). If safeguards information is necessary to provide an acceptable response, please | necessary to provide an acceptable response, then please provide a bracketed copy of your | ||
provide the level of protection described in 10 CFR 73.21. | response that identifies the information that should be protected and a redacted copy of your | ||
In accordance with 10 CFR 19.11, you may be required to post this Notice within two working | response that deletes such information. If you request withholding of such material, you must | ||
days. | specifically identify the portions of your response that you seek to have withheld and provide in | ||
Dated this 18th day of July 2011 | detail the bases for your claim of withholding (e.g., explain why the disclosure of information will | ||
create an unwarranted invasion of personal privacy or provide the information required by | |||
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial | |||
information). If safeguards information is necessary to provide an acceptable response, please | |||
provide the level of protection described in 10 CFR 73.21. | |||
In accordance with 10 CFR 19.11, you may be required to post this Notice within two working | |||
days. | |||
Dated this 18th day of July 2011 | |||
Fort Calhoun Station Reactor Protection System Issue | |||
Final Significance Determination | |||
During the regulatory conference held on June 2, 2011, the Fort Calhoun Station (FCS) staff | |||
described your assessment of the significance of the finding as summarized below. Specifically, | |||
your staff discussed four differences that existed between the NRCs preliminary significance | |||
determination and your risk assessment. These differences and our conclusions are as follows: | - 1 - | ||
Item 1 - Shorter Exposure Time (T/2 + repair vs. T + repair) | Enclosure 2 | ||
Your staff stated that exposure time for this issue should not utilize T plus repair time, but use | During the regulatory conference held on June 2, 2011, the Fort Calhoun Station (FCS) staff | ||
T/2 plus repair time instead. This would result in a reduced exposure period from 64.0 days to | described your assessment of the significance of the finding as summarized below. Specifically, | ||
32.5 days. This was based on your analysis that a shading coil must fragment, due to wear, prior | your staff discussed four differences that existed between the NRCs preliminary significance | ||
to a piece of it being able to jam the contactor in the closed position. You also stated this wear | determination and your risk assessment. These differences and our conclusions are as follows: | ||
would likely take weeks or months. Therefore, you concluded that the fragmenting and jamming | |||
occurred at some unknown time between April 10, and June 14, 2010. This would indicate that | Item 1 - Shorter Exposure Time (T/2 + repair vs. T + repair) | ||
the use of T/2 is more applicable to this case. | Your staff stated that exposure time for this issue should not utilize T plus repair time, but use | ||
NRC staff determined that the provided failure modes and effects analysis for the shading coil | T/2 plus repair time instead. This would result in a reduced exposure period from 64.0 days to | ||
was very comprehensive and understandable. However, there was no corresponding failure | 32.5 days. This was based on your analysis that a shading coil must fragment, due to wear, prior | ||
modes and effects analysis presented for the overall contactor (i.e., how the shading coil failure | to a piece of it being able to jam the contactor in the closed position. You also stated this wear | ||
could cause the contactor failure). Definitive testing or evaluation of the jamming sequence for | would likely take weeks or months. Therefore, you concluded that the fragmenting and jamming | ||
the contactor was not provided. | occurred at some unknown time between April 10, and June 14, 2010. This would indicate that | ||
During discussions with your forensic specialist at the regulatory conference, NRC staff | the use of T/2 is more applicable to this case. | ||
questioned the methods used to determine how the shading coil actually jammed the contactor. | |||
The specialist indicated that specific confirmation testing was not conducted, but that a shading | NRC staff determined that the provided failure modes and effects analysis for the shading coil | ||
coil fragment was likely repositioned during vibration, moved in an upward direction, and then | was very comprehensive and understandable. However, there was no corresponding failure | ||
jammed the contactor mechanism in its opening motion on June 14, 2010. Based on visual and | modes and effects analysis presented for the overall contactor (i.e., how the shading coil failure | ||
physical evidence, NRC staff concluded that this was unlikely. The travel on the contactor | could cause the contactor failure). Definitive testing or evaluation of the jamming sequence for | ||
mechanism, from full contact closure until the contacts open, was only approximately 1/8 inch. | the contactor was not provided. | ||
The NRC staff concluded it would be extremely difficult for a shading coil fragment to both enter | |||
the gap between the frame and the contactor slide and stop the contactor slide from moving in | During discussions with your forensic specialist at the regulatory conference, NRC staff | ||
such a small amount of travel. However, when a contactor slide moves from the full open to the | questioned the methods used to determine how the shading coil actually jammed the contactor. | ||
closed position, the travel is over 1/2 inch. The NRC staff believes it is more likely a whole | The specialist indicated that specific confirmation testing was not conducted, but that a shading | ||
shading coil or fragment was forced into the gap between the frame and the contactor slide | coil fragment was likely repositioned during vibration, moved in an upward direction, and then | ||
during a closing action; specifically the April 10, 2010, closing prior to the June 14, 2010, failure. | jammed the contactor mechanism in its opening motion on June 14, 2010. Based on visual and | ||
Therefore, the NRC concludes the applicable exposure time was 63 days, plus a 1 day repair | physical evidence, NRC staff concluded that this was unlikely. The travel on the contactor | ||
time, for a total of 64 days. | mechanism, from full contact closure until the contacts open, was only approximately 1/8 inch. | ||
Item 2 - Lower Failure Probability for Clutch Power Supply Breaker | The NRC staff concluded it would be extremely difficult for a shading coil fragment to both enter | ||
Your staff stated that the generic breaker failure data used in the preliminary significance | the gap between the frame and the contactor slide and stop the contactor slide from moving in | ||
determination was not the best available information for vital breakers CB-AB and CB-CD. | such a small amount of travel. However, when a contactor slide moves from the full open to the | ||
Instead your staff suggested that the NRC staff use generic data from NUREG/CR-6928, | closed position, the travel is over 1/2 inch. The NRC staff believes it is more likely a whole | ||
Industry-Average Performance for Components and Initiating Events at U.S. Commercial | shading coil or fragment was forced into the gap between the frame and the contactor slide | ||
Nuclear Power Plants, plus data developed using test results from testing the two breakers | during a closing action; specifically the April 10, 2010, closing prior to the June 14, 2010, failure. | ||
previously installed at Fort Calhoun. However, your final assessment indicated that you believed | Therefore, the NRC concludes the applicable exposure time was 63 days, plus a 1 day repair | ||
a Bayesian update of the test data, using a Jeffreys non-informative prior distribution would be | time, for a total of 64 days. | ||
the appropriate value. | |||
The NRC staff determined that, to the extent the test data from the previously installed breakers | Item 2 - Lower Failure Probability for Clutch Power Supply Breaker | ||
represented the installed conditions of the breakers, this data should be used to update the | Your staff stated that the generic breaker failure data used in the preliminary significance | ||
generic data. However, the NRC staff concluded that the test data should not be used to update | determination was not the best available information for vital breakers CB-AB and CB-CD. | ||
Instead your staff suggested that the NRC staff use generic data from NUREG/CR-6928, | |||
Industry-Average Performance for Components and Initiating Events at U.S. Commercial | |||
Nuclear Power Plants, plus data developed using test results from testing the two breakers | |||
previously installed at Fort Calhoun. However, your final assessment indicated that you believed | |||
a Bayesian update of the test data, using a Jeffreys non-informative prior distribution would be | |||
the appropriate value. | |||
The NRC staff determined that, to the extent the test data from the previously installed breakers | |||
represented the installed conditions of the breakers, this data should be used to update the | |||
generic data. However, the NRC staff concluded that the test data should not be used to update | |||
Fort Calhoun Station Reactor Protection System Issue | |||
Final Significance Determination | |||
a Jeffreys non-informative prior distribution when existing generic priors were available that | |||
adequately represented the population of the breakers in question. The staff also concluded that | |||
data from NUREG/CR-6928 should not be used because the breakers in question were neither | |||
reactor trip breakers nor were they maintained and tested to the standards used for reactor trip | - 2 - | ||
breakers. | Enclosure 2 | ||
The NRC staff updated the priors used in the preliminary significance determination with the data | a Jeffreys non-informative prior distribution when existing generic priors were available that | ||
obtained from the test results on vital breakers CB-AB and CB-CD. The NRC concluded that this | adequately represented the population of the breakers in question. The staff also concluded that | ||
approach represented the best available information. The calculated total failure probability for | data from NUREG/CR-6928 should not be used because the breakers in question were neither | ||
the breakers was 3.81 x 10-4 demand which is a change from 7.5 x 10-3 documented in the | reactor trip breakers nor were they maintained and tested to the standards used for reactor trip | ||
preliminary determination. | breakers. | ||
Item 3 - Common Cause Failure Determination | |||
Your staff stated that there was no single clear path for analysis of common cause failure for this | The NRC staff updated the priors used in the preliminary significance determination with the data | ||
issue and recommended that the NRC staff use the definition of common cause failure | obtained from the test results on vital breakers CB-AB and CB-CD. The NRC concluded that this | ||
documented in NUREG/CR-5500, Volume 10, Reliability Study: Combustion Engineering | approach represented the best available information. The calculated total failure probability for | ||
Reactor Protection System, 1984-1998. Additionally, your staff commented that the NRC staff | the breakers was 3.81 x 10-4 demand which is a change from 7.5 x 10-3 documented in the | ||
made an incorrect reference to Revision 1.01 of the Risk Assessment of Operational Events | preliminary determination. | ||
handbook in our inspection report. Finally, your staff stated that the common cause observations | |||
in the inspection report under Assumption 7 may need to be updated based on new information | Item 3 - Common Cause Failure Determination | ||
provided in the Engineering Systems, Inc. report. | Your staff stated that there was no single clear path for analysis of common cause failure for this | ||
The NRC staff determined that the reference to Revision 1.01 of the handbook was incorrect. | issue and recommended that the NRC staff use the definition of common cause failure | ||
However, this definition was not used in the common cause methodology utilized in our analysis. | documented in NUREG/CR-5500, Volume 10, Reliability Study: Combustion Engineering | ||
The reasons for adjusting the common cause failure probability were best described in the | Reactor Protection System, 1984-1998. Additionally, your staff commented that the NRC staff | ||
inspection report Page A-4, Assumptions 7 and 8. | made an incorrect reference to Revision 1.01 of the Risk Assessment of Operational Events | ||
The NRC staff also determined that NUREG/CR-5500 provides a concise definition of a common | handbook in our inspection report. Finally, your staff stated that the common cause observations | ||
cause failure. However, in the significance determination, the NRC staff did not assume that a | in the inspection report under Assumption 7 may need to be updated based on new information | ||
common cause failure event had occurred. If a failure of Contactors M1 and M2 had occurred at | provided in the Engineering Systems, Inc. report. | ||
the same time, the risk would have been significantly higher than our original estimates. The | |||
guidance contained in NUREG/CR-5500 was not intended to be used to evaluate a condition | The NRC staff determined that the reference to Revision 1.01 of the handbook was incorrect. | ||
where the analyst believes that the common cause failure probability should be increased based | However, this definition was not used in the common cause methodology utilized in our analysis. | ||
on observed conditions. The NRC staff has determined that the approach used in the inspection | The reasons for adjusting the common cause failure probability were best described in the | ||
report is the appropriate method to adjust common cause failure probabilities when components | inspection report Page A-4, Assumptions 7 and 8. | ||
are maintained and operated under similar conditions. | |||
The NRC staff reviewed Assumption 7 in the NRC inspection report in light of the findings | The NRC staff also determined that NUREG/CR-5500 provides a concise definition of a common | ||
documented in the report generated by the professional engineering consulting firm Engineering | cause failure. However, in the significance determination, the NRC staff did not assume that a | ||
Systems, Inc. However, the only condition that may have changed based on the Engineering | common cause failure event had occurred. If a failure of Contactors M1 and M2 had occurred at | ||
Systems, Inc. report was that, subparts exhibited significant scratching and indentations. The | the same time, the risk would have been significantly higher than our original estimates. The | ||
NRC staff determined that despite such a change, the subject conditions, operation and | guidance contained in NUREG/CR-5500 was not intended to be used to evaluate a condition | ||
maintenance history of the contactors still warranted adjustment of the common cause failure | where the analyst believes that the common cause failure probability should be increased based | ||
probability of contactor M1 given that contactor M2 failed. | on observed conditions. The NRC staff has determined that the approach used in the inspection | ||
Common cause failure probabilities are included in probabilistic risk assessment because | report is the appropriate method to adjust common cause failure probabilities when components | ||
analysts have long recognized that many factors, such as the poor maintenance practices | are maintained and operated under similar conditions. | ||
indicated in the inspection report, which are not modeled explicitly in the models, can defeat | |||
redundancy or diversity and make failures of multiple similar components more likely than would | The NRC staff reviewed Assumption 7 in the NRC inspection report in light of the findings | ||
be the case if these factors were absent. The effect of these factors on risk can be significant. | documented in the report generated by the professional engineering consulting firm Engineering | ||
Systems, Inc. However, the only condition that may have changed based on the Engineering | |||
Systems, Inc. report was that, subparts exhibited significant scratching and indentations. The | |||
NRC staff determined that despite such a change, the subject conditions, operation and | |||
maintenance history of the contactors still warranted adjustment of the common cause failure | |||
probability of contactor M1 given that contactor M2 failed. | |||
Common cause failure probabilities are included in probabilistic risk assessment because | |||
analysts have long recognized that many factors, such as the poor maintenance practices | |||
indicated in the inspection report, which are not modeled explicitly in the models, can defeat | |||
redundancy or diversity and make failures of multiple similar components more likely than would | |||
be the case if these factors were absent. The effect of these factors on risk can be significant. | |||
Fort Calhoun Station Reactor Protection System Issue | |||
Final Significance Determination | |||
For practical reasons related to data availability, the common cause failure probabilities of similar | |||
components are estimated using data collected at the component level, without regard to failure | |||
cause. | |||
Factors such as poor maintenance processes are often part of the environment in which the | - 3 - | ||
components are embedded and are not intrinsic properties of the components themselves. The | Enclosure 2 | ||
NRC staff uses the failure memory approach in evaluating the significance of a performance | For practical reasons related to data availability, the common cause failure probabilities of similar | ||
deficiency. Observed failures are mapped into the probabilistic model, but successes are treated | components are estimated using data collected at the component level, without regard to failure | ||
probabilistically. Thus, failure probabilities are left at their nominal values or are conditioned as | cause. | ||
necessary to reflect the details of the event. | Factors such as poor maintenance processes are often part of the environment in which the | ||
To address this conditioning, the NRC staff has determined that there are three basic ground | components are embedded and are not intrinsic properties of the components themselves. The | ||
rules for treatment of common cause failure: | NRC staff uses the failure memory approach in evaluating the significance of a performance | ||
a. | deficiency. Observed failures are mapped into the probabilistic model, but successes are treated | ||
probabilistically. Thus, failure probabilities are left at their nominal values or are conditioned as | |||
necessary to reflect the details of the event. | |||
To address this conditioning, the NRC staff has determined that there are three basic ground | |||
rules for treatment of common cause failure: | |||
b. | |||
a. | |||
The shared cause is the deficiency identified in the inspection report which led to the | |||
observed equipment failure. In the case of the subject finding, the licensees failure to | |||
identify the cause of the loose shading coils was the performance deficiency. The | |||
c. | inspectors observed that at least one shading coil would easily come out of its recess on | ||
all contactors. | |||
b. | |||
Common cause failures are of concern when they occur during the mission time of the | |||
Therefore, the NRC concludes that the treatment of common cause failure probabilities for the | probabilistic risk assessment, which for internal hazard groups is generally 24 hours. The | ||
reactor protection system contactors was appropriate and the conditional failure probability of the | common cause failure analysis methodology used and alpha vectors documented in the | ||
M1 contactor is best approximated as 3.59 x 10-2/demand. | inspection report were developed to intrinsically incorporate this requirement into the | ||
Item 4 - Higher Operator Reliability in Tripping the Reactor | common cause failure probabilities. | ||
Item 4a - Under Anticipated Transient Without Scram Conditions | |||
Your staff indicated that follow-up operator actions, past the 10-minute point in the anticipated | c. | ||
transient without scram (ATWS) scenario, should be credited. You provided an evaluation by | Credit for programmatic actions to mitigate common cause failure potential (staggering | ||
Westinghouse of the expected Fort Calhoun Station plant response to this event. The evaluation | equipment modifications, etc.) should be applied qualitatively during the enforcement | ||
indicated that, due to a large negative moderator temperature coefficient, power would | process and not incorporated into the numerical risk result. For the subject performance | ||
automatically be reduced before the American Society of Mechanical Engineers (ASME) Level C | deficiency, this condition is moot. Inspection of components and records reviews | ||
pressure limit of 3200 psig was exceeded. This would indicate that further operator actions could | indicated that all contactors had been handled in the same manner. | ||
be taken to trip the control rods without physical damage to key reactor components or systems. | |||
NRC staff determined that the reactor response to a delayed tripping of the control rods in an | Therefore, the NRC concludes that the treatment of common cause failure probabilities for the | ||
ATWS scenario, especially the pressure response, is a critical aspect in preventing core damage. | reactor protection system contactors was appropriate and the conditional failure probability of the | ||
The details of the calculations and thermal-hydraulic runs of record are well established. | M1 contactor is best approximated as 3.59 x 10-2/demand. | ||
NUREG-1780 states that pressure transients are unacceptable if the ASME Level C value of | |||
3200 psig is exceeded. It further stated that a higher ASME service level was considered for | Item 4 - Higher Operator Reliability in Tripping the Reactor | ||
Item 4a - Under Anticipated Transient Without Scram Conditions | |||
Your staff indicated that follow-up operator actions, past the 10-minute point in the anticipated | |||
transient without scram (ATWS) scenario, should be credited. You provided an evaluation by | |||
Westinghouse of the expected Fort Calhoun Station plant response to this event. The evaluation | |||
indicated that, due to a large negative moderator temperature coefficient, power would | |||
automatically be reduced before the American Society of Mechanical Engineers (ASME) Level C | |||
pressure limit of 3200 psig was exceeded. This would indicate that further operator actions could | |||
be taken to trip the control rods without physical damage to key reactor components or systems. | |||
NRC staff determined that the reactor response to a delayed tripping of the control rods in an | |||
ATWS scenario, especially the pressure response, is a critical aspect in preventing core damage. | |||
The details of the calculations and thermal-hydraulic runs of record are well established. | |||
NUREG-1780 states that pressure transients are unacceptable if the ASME Level C value of | |||
3200 psig is exceeded. It further stated that a higher ASME service level was considered for | |||
Fort Calhoun Station Reactor Protection System Issue | |||
Final Significance Determination | |||
Babcock & Wilcox and Combustion Engineering plants, but was rejected on the basis that the | |||
reactor coolant system pressure boundary could deform to the point of inoperability. | |||
Your evaluation showed a peak pressure of 3176 psia (approximately 3162 psig) during a run of | |||
the Combustion Engineering Nuclear Transient Simulator (CENTS) code. The NRC noted that | - 4 - | ||
similar thermal-hydraulic code runs, referenced in NUREG-1000 and NUREG-1780, were very | Enclosure 2 | ||
sensitive to small variations or uncertainties in plant-specific parameters such as moderator | Babcock & Wilcox and Combustion Engineering plants, but was rejected on the basis that the | ||
temperature coefficient, reactor vessel volumes, and other physical parameters. Your analysis | reactor coolant system pressure boundary could deform to the point of inoperability. | ||
did not include sensitivities to variations or uncertainties in these parameters. For example, your | |||
analysis used the Fort Calhoun Station predicted beginning of life full power moderator | Your evaluation showed a peak pressure of 3176 psia (approximately 3162 psig) during a run of | ||
temperature coefficient. However, you did not provide a sensitivity analysis for moderator | the Combustion Engineering Nuclear Transient Simulator (CENTS) code. The NRC noted that | ||
temperature coefficient showing potential inaccuracies in this value or its variation with power. | similar thermal-hydraulic code runs, referenced in NUREG-1000 and NUREG-1780, were very | ||
NUREG-1780 states that during the first part of the fuel cycle, below 100 percent power, the | sensitive to small variations or uncertainties in plant-specific parameters such as moderator | ||
moderator temperature coefficient can be positive or insufficiently negative. If an ATWS occurs | temperature coefficient, reactor vessel volumes, and other physical parameters. Your analysis | ||
when the moderator temperature coefficient is either positive or insufficiently negative to limit | did not include sensitivities to variations or uncertainties in these parameters. For example, your | ||
reactor power, and the ATWS pressure increases, all subsequent mitigating functions are likely to | analysis used the Fort Calhoun Station predicted beginning of life full power moderator | ||
be ineffective. NRC staff reviewed your predicted moderator temperature coefficient values over | temperature coefficient. However, you did not provide a sensitivity analysis for moderator | ||
core life and at different power levels and concluded you also have positive or insufficiently | temperature coefficient showing potential inaccuracies in this value or its variation with power. | ||
negative values at lower powers. | NUREG-1780 states that during the first part of the fuel cycle, below 100 percent power, the | ||
It is the NRCs judgment that the 3176 psia outcome of your analysis is insufficient to assure the | moderator temperature coefficient can be positive or insufficiently negative. If an ATWS occurs | ||
ASME Level C value is not actually exceeded, considering the potential inaccuracies and | when the moderator temperature coefficient is either positive or insufficiently negative to limit | ||
uncertainties of the analysis. Therefore, the NRC concluded the preliminary assessment time | reactor power, and the ATWS pressure increases, all subsequent mitigating functions are likely to | ||
limitations for the ATWS response should still be used and no changes were made to the | be ineffective. NRC staff reviewed your predicted moderator temperature coefficient values over | ||
assessment for additional operator actions beyond 10 minutes. | core life and at different power levels and concluded you also have positive or insufficiently | ||
Item 4b - Manual Trip Probability | negative values at lower powers. | ||
Your staff pointed out that the failure of operators to push manual trip pushbutton No. 2 was not | |||
dependant on the success or failure of manual trip pushbutton No. 1. Based on your procedures | It is the NRCs judgment that the 3176 psia outcome of your analysis is insufficient to assure the | ||
the NRC staff concluded that, based on procedural guidance and operator training, the failure of | ASME Level C value is not actually exceeded, considering the potential inaccuracies and | ||
operators to push manual trip pushbutton No. 2 would not likely be affected by the success or | uncertainties of the analysis. Therefore, the NRC concluded the preliminary assessment time | ||
failure of manual trip pushbutton No. 1. Therefore, additional credit was given for the former | limitations for the ATWS response should still be used and no changes were made to the | ||
probability under RPS-XHE-ERROR as shown in Table 1. However, the NRC did not use your | assessment for additional operator actions beyond 10 minutes. | ||
suggested values (6 x 10-4) for either manual pushbutton, as those values were based on | |||
additional time available to the operators in an ATWS scenario which the NRC staff determined | Item 4b - Manual Trip Probability | ||
should not be credited as discussed in Item 4a. | Your staff pointed out that the failure of operators to push manual trip pushbutton No. 2 was not | ||
dependant on the success or failure of manual trip pushbutton No. 1. Based on your procedures | |||
the NRC staff concluded that, based on procedural guidance and operator training, the failure of | |||
operators to push manual trip pushbutton No. 2 would not likely be affected by the success or | |||
failure of manual trip pushbutton No. 1. Therefore, additional credit was given for the former | |||
probability under RPS-XHE-ERROR as shown in Table 1. However, the NRC did not use your | |||
suggested values (6 x 10-4) for either manual pushbutton, as those values were based on | |||
additional time available to the operators in an ATWS scenario which the NRC staff determined | |||
should not be credited as discussed in Item 4a. | |||
Fort Calhoun Station Reactor Protection System Issue | |||
Final Significance Determination | |||
Summary | |||
- 5 - | |||
Enclosure 2 | |||
Parameter | Summary | ||
Table 1 | |||
1 Shorter Exposure Time | Summary of Parameter Changes | ||
Fort Calhoun Station Reactor Protector System Contactor Issue | |||
2 Lower Failure Probability for RPS-BSN-FO-CBAB | Final Significance Determination | ||
Parameter | |||
Basic Event | |||
3 Common Cause Failure | SPAR | ||
Value | |||
3 Contactor Failure | Preliminary | ||
Significance | |||
4a Operator Reliability Under | Licensee | ||
Recommended | |||
Final | |||
4b Manual Trip 1 | Significance | ||
1 Shorter Exposure Time | |||
N/A | |||
4b Manual Trip 2 | N/A | ||
The NRC staff requantified the detailed model of the reactor protection system used in the | 64 days | ||
preliminary significance determination using the modified parameters listed in Table 1. The | 32.5 days | ||
revised internal change in core damage frequency was calculated to be 6.47 x 10-6. Combining | 64 days | ||
this with the external risk calculated in the preliminary determination the total change in core | 2 Lower Failure Probability for | ||
damage frequency was 7.14 x 10-6. | Clutch Power Supply Breaker | ||
The staff has considered the information you provided to the NRC regarding the significance of | RPS-BSN-FO-CBAB | ||
this issue and has concluded that the finding is appropriately characterized as being of low to | RPS-BSN-FO-CBCD | ||
moderate safety significance (White). The agencys preliminary evaluation, as documented in | 7.5 x 10-3 | ||
NRC Inspection Report 05000285/2011007, has been modified as shown above to reflect that the | 7.5 x 10-3 | ||
1.2 x 10-4 | |||
3.81 x 10-4 | |||
3 Common Cause Failure | |||
RPS-RYT-CF-M12 | |||
2.4 x 10-6 | |||
3.59 x 10-2 | |||
2.4 x 10-6 | |||
3.59 x 10-2 | |||
3 Contactor Failure | |||
RPS-RYT-CC-M1 | |||
1.2 x 10-4 | |||
1.0 | |||
1.0 | |||
1.0 | |||
4a Operator Reliability Under | |||
ATWS Conditions (EOP-20) | |||
N/A | |||
N/A | |||
N/A | |||
1.4 x 10-3 | |||
N/A | |||
4b Manual Trip 1 | |||
RPS-XHE-XM- | |||
SCRAM | |||
1 x 10-2 | |||
1.5 x 10-3 | |||
6.0 x 10-4 | |||
1.5 x 10-3 | |||
4b Manual Trip 2 | |||
RPS-XHE-ERROR | |||
N/A | |||
0.5 | |||
6.0 x 10-4 | |||
6.0 x 10-3 | |||
The NRC staff requantified the detailed model of the reactor protection system used in the | |||
preliminary significance determination using the modified parameters listed in Table 1. The | |||
revised internal change in core damage frequency was calculated to be 6.47 x 10-6. Combining | |||
this with the external risk calculated in the preliminary determination the total change in core | |||
damage frequency was 7.14 x 10-6. | |||
The staff has considered the information you provided to the NRC regarding the significance of | |||
this issue and has concluded that the finding is appropriately characterized as being of low to | |||
moderate safety significance (White). The agencys preliminary evaluation, as documented in | |||
NRC Inspection Report 05000285/2011007, has been modified as shown above to reflect that the | |||
change in core damage frequency for the finding was 7.14 x 10-6 as compared with 2.6 x 10-5. | change in core damage frequency for the finding was 7.14 x 10-6 as compared with 2.6 x 10-5. | ||
}} | }} | ||
Latest revision as of 05:23, 13 January 2025
| ML112000064 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 07/18/2011 |
| From: | Collins E Region 4 Administrator |
| To: | Bannister D Omaha Public Power District |
| References | |
| EA-11-025 IR-11-007 | |
| Download: ML112000064 (11) | |
See also: IR 05000285/2011007
Text
July 18, 2011
David J. Bannister, Vice President
and Chief Nuclear Officer
Omaha Public Power District
Fort Calhoun Station FC-2-4
P.O. Box 550
Fort Calhoun, NE 68023-0550
SUBJECT:
FORT CALHOUN STATION - FINAL SIGNIFICANCE DETERMINATION
FOR A WHITE FINDING AND NOTICE OF VIOLATION, NRC INSPECTION
REPORT 05000285/2011007
Dear Mr. Bannister:
The purpose of this letter is to provide you the final significance determination of the preliminary
Yellow finding identified in our previous communication dated May 6, 2011, which included the
subject inspection report. The inspection finding was assessed using the Significance
Determination Process and was preliminarily characterized as a Yellow finding with substantial
importance to safety that may result in additional NRC inspection and potentially other NRC
action. This finding was associated with the June 14, 2010, failure of a reactor trip
contactor (M2) in your reactor protection system.
At your request, a regulatory conference was held on June 2, 2011, to further discuss your
views on this issue. During the regulatory conference, your staff described the Fort Calhoun
Stations assessment of the significance of the finding and they provided a summary of the
corrective actions, and insights from the root cause analysis of the finding. This material is
documented in the NRC Meeting Summary (ML111660027) dated June 14, 2011. You also
requested that the NRC reconsider its evaluation of the findings risk significance based on four
specific areas of consideration where differences exist between the NRCs preliminary
significance determination and your staffs risk assessment. These are: 1) Shorter Exposure
Time (T/2 + repair vs. T + repair); 2) Lower Failure Probability for Clutch Power Supply Breaker;
3) Common Cause Failure Determination; and 4) Higher Operator Reliability in Tripping the
Reactor. Between June 6 and June 28, 2011, you provided supplemental information regarding
follow-up questions asked by NRC staff at the conference. This additional material was
docketed as ADAMS document ML111881131.
The NRC has reviewed your areas of consideration and our evaluation of each is provided in
Enclosure 2 of this letter along with the revised NRC risk assessment. The NRC considered the
information developed during the inspection, and the information that you provided at, and
subsequent to, the conference. The NRC has concluded that the finding is appropriately
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125
Omaha Public Power District
- 2 -
characterized as White, a finding with low to moderate importance to safety and will result in
additional NRC inspection and potentially other NRC actions.
You have 30 calendar days from the date of this letter to appeal the staffs determination of
significance for the identified White finding. Such appeals will be considered to have merit only
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. An
appeal must be sent in writing to the Regional Administrator, U.S. Nuclear Regulatory
Commission, Region IV, 612 E. Lamar Blvd., Suite 400, Arlington, Texas 76011-4125.
The NRC has concluded that failure to assure that the cause of a significant condition adverse
to quality was determined and failure to take corrective actions to preclude repetition of the
condition, is a violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50,
Appendix B, Criterion XVI, Corrective Action, as cited in the enclosed Notice of Violation. The
circumstances surrounding the violation are described in detail in the subject inspection report.
In accordance with the NRC Enforcement Policy, the Notice of Violation is considered an
escalated enforcement action because it is associated with a White finding.
You are required to respond to this letter. Please follow the instructions specified in the
enclosed Notice of Violation when preparing your response. If you have additional information
that you believe the NRC should consider, you may provide it in your response to the Notice.
The NRC review of your response to the Notice will also determine whether further enforcement
action is necessary to ensure compliance with regulatory requirements.
Because your current plant performance is in the Degraded Cornerstone (Mitigating Systems)
Column, and this violation also impacts that cornerstone, the NRC will use the NRC Action
Matrix to determine the most appropriate NRC response to this violation. The NRC will notify
you, by separate correspondence, of that determination.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its
enclosures, and your response will be available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS). ADAMS is accessible
from the NRC Web site at www.nrc.gov/reading-rm/adams.html. To the extent possible, your
response should not include any personal privacy, proprietary, or safeguards information so that
it can be made available to the Public without redaction.
Sincerely,
/RA/
Elmo E. Collins
Regional Administrator
Docket: 50-285
License: DPR-40
Enclosures:
Omaha Public Power District
- 3 -
2. Fort Calhoun Reactor Protection System Issue
Final Significance Determination
cc w/Enclosures:
Distribution via Listserv
Omaha Public Power District
- 4 -
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
Acting DRP Deputy Director (Jeff.Clark@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
Acting DRS Deputy Director (Robert.Caldwell@nrc.gov)
Senior Resident Inspector (John.Kirkland@nrc.gov)
Resident Inspector (Jacob.Wingebach@nrc.gov)
Acting Branch Chief, DRP/E (Ray.Azua@nrc.gov)
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)
Project Engineer (Jim.Melfi@nrc.gov)
Project Engineer (Chris.Smith@nrc.gov)
RIV Enforcement, ACES (Ray.Kellar@nrc.gov)
FCS Administrative Assistant (Berni.Madison@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Acting Branch Chief, DRS/TSB (Dale Powers@nrc.gov)
Project Manager (Lynnea.Wilkins@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Regional State Liaison Officer (Bill.Maier@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
DRS/TSB STA (Dale.Powers@nrc.gov)
RIV/ETA: OEDO (John.McHale@nrc.gov)
R:_\\Reactors\\FCS\\FCS-Final-Significance.docx
Yes
SUNSI Review Complete
Reviewer Initials: JAC
Publicly Available
Non-publicly Available
Sensitive
Non-sensitive
RIV/DRP:PBE
DRP:PBE
DRS-SRA
D:DRS
ACES
RVAzua
JAClark
DPLoveless
AVegel
RKellar
/RA/
/RA/
/RA/
/RA/
/RA/via email
07/08/11
07/08/11
07/14/11
07/14/11
07/07/11
Counsel
NRR/OE
D:DRP
ORA
MBarkman Marsh
NColeman
KMKennedy
EECollins
/RA/via email
/RA/via email
/RA/
/RA/
07/13/11
07/13/11
07/15/11
07/18/11
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax
-1-
Enclosure 1
Omaha Public Power District
Docket No.: 05000285
Fort Calhoun Station
License No.: DPR-40
During an NRC inspection conducted from January 17 through April 15, 2011, one violation of
NRC requirements was identified. In accordance with the NRC Enforcement Policy, the
violation is listed below:
Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI,
Corrective Action, requires, in part, that measures shall be established to assure that
conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations,
defective material and equipment, and nonconformances are promptly identified and
corrected. In the case of significant conditions adverse to quality, the measures shall
assure that the cause of the condition is determined and corrective action taken to
preclude repetition.
Contrary to the above, between November 3, 2008, and June 14, 2010, the licensee
failed to assure that the cause of a significant condition adverse to quality was
determined and corrective actions were taken to preclude repetition. Specifically, the
licensee failed to preclude shading coils from repetitively becoming loose material in the
M2 reactor trip contactor. The licensee failed to identify that the loose parts in the trip
contactor represented a potential failure of the contactor if they became an obstruction;
and therefore, failed to preclude repetition of this significant condition adverse to quality,
that subsequently resulted in the contactor failing.
This violation is associated with a White significance determination process finding in the
Mitigating Systems Cornerstone.
Pursuant to the provisions of 10 CFR 2.201, Omaha Public Power District is hereby required to
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission,
ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional
Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400,
Arlington, Texas, 76011-4125, and a copy to the NRC Resident Inspector - Fort Calhoun
Station, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This
reply should be clearly marked as a "Reply to a Notice of Violation; EA-11-025" and should
include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing
the violation or severity level, (2) the corrective steps that have been taken and the results
achieved, (3) the corrective steps that will be taken, and (4) the date when full compliance will
be achieved. Your response may reference or include previous docketed correspondence, if
the correspondence adequately addresses the required response. If an adequate reply is not
received within the time specified in this Notice, an order or a Demand for Information may be
issued as to why the license should not be modified, suspended, or revoked, or why such other
action as may be proper should not be taken. Where good cause is shown, consideration will
be given to extending the response time.
-2-
Enclosure 1
If you contest this enforcement action, you should also provide a copy of your response, with
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington DC 20555-0001.
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS), accessible from the
NRCs website at www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not
include any personal privacy, proprietary, or safeguards information so that it can be made
available to the public without redaction. If personal privacy or proprietary information is
necessary to provide an acceptable response, then please provide a bracketed copy of your
response that identifies the information that should be protected and a redacted copy of your
response that deletes such information. If you request withholding of such material, you must
specifically identify the portions of your response that you seek to have withheld and provide in
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will
create an unwarranted invasion of personal privacy or provide the information required by
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial
information). If safeguards information is necessary to provide an acceptable response, please
provide the level of protection described in 10 CFR 73.21.
In accordance with 10 CFR 19.11, you may be required to post this Notice within two working
days.
Dated this 18th day of July 2011
Fort Calhoun Station Reactor Protection System Issue
Final Significance Determination
- 1 -
Enclosure 2
During the regulatory conference held on June 2, 2011, the Fort Calhoun Station (FCS) staff
described your assessment of the significance of the finding as summarized below. Specifically,
your staff discussed four differences that existed between the NRCs preliminary significance
determination and your risk assessment. These differences and our conclusions are as follows:
Item 1 - Shorter Exposure Time (T/2 + repair vs. T + repair)
Your staff stated that exposure time for this issue should not utilize T plus repair time, but use
T/2 plus repair time instead. This would result in a reduced exposure period from 64.0 days to
32.5 days. This was based on your analysis that a shading coil must fragment, due to wear, prior
to a piece of it being able to jam the contactor in the closed position. You also stated this wear
would likely take weeks or months. Therefore, you concluded that the fragmenting and jamming
occurred at some unknown time between April 10, and June 14, 2010. This would indicate that
the use of T/2 is more applicable to this case.
NRC staff determined that the provided failure modes and effects analysis for the shading coil
was very comprehensive and understandable. However, there was no corresponding failure
modes and effects analysis presented for the overall contactor (i.e., how the shading coil failure
could cause the contactor failure). Definitive testing or evaluation of the jamming sequence for
the contactor was not provided.
During discussions with your forensic specialist at the regulatory conference, NRC staff
questioned the methods used to determine how the shading coil actually jammed the contactor.
The specialist indicated that specific confirmation testing was not conducted, but that a shading
coil fragment was likely repositioned during vibration, moved in an upward direction, and then
jammed the contactor mechanism in its opening motion on June 14, 2010. Based on visual and
physical evidence, NRC staff concluded that this was unlikely. The travel on the contactor
mechanism, from full contact closure until the contacts open, was only approximately 1/8 inch.
The NRC staff concluded it would be extremely difficult for a shading coil fragment to both enter
the gap between the frame and the contactor slide and stop the contactor slide from moving in
such a small amount of travel. However, when a contactor slide moves from the full open to the
closed position, the travel is over 1/2 inch. The NRC staff believes it is more likely a whole
shading coil or fragment was forced into the gap between the frame and the contactor slide
during a closing action; specifically the April 10, 2010, closing prior to the June 14, 2010, failure.
Therefore, the NRC concludes the applicable exposure time was 63 days, plus a 1 day repair
time, for a total of 64 days.
Item 2 - Lower Failure Probability for Clutch Power Supply Breaker
Your staff stated that the generic breaker failure data used in the preliminary significance
determination was not the best available information for vital breakers CB-AB and CB-CD.
Instead your staff suggested that the NRC staff use generic data from NUREG/CR-6928,
Industry-Average Performance for Components and Initiating Events at U.S. Commercial
Nuclear Power Plants, plus data developed using test results from testing the two breakers
previously installed at Fort Calhoun. However, your final assessment indicated that you believed
a Bayesian update of the test data, using a Jeffreys non-informative prior distribution would be
the appropriate value.
The NRC staff determined that, to the extent the test data from the previously installed breakers
represented the installed conditions of the breakers, this data should be used to update the
generic data. However, the NRC staff concluded that the test data should not be used to update
Fort Calhoun Station Reactor Protection System Issue
Final Significance Determination
- 2 -
Enclosure 2
a Jeffreys non-informative prior distribution when existing generic priors were available that
adequately represented the population of the breakers in question. The staff also concluded that
data from NUREG/CR-6928 should not be used because the breakers in question were neither
reactor trip breakers nor were they maintained and tested to the standards used for reactor trip
breakers.
The NRC staff updated the priors used in the preliminary significance determination with the data
obtained from the test results on vital breakers CB-AB and CB-CD. The NRC concluded that this
approach represented the best available information. The calculated total failure probability for
the breakers was 3.81 x 10-4 demand which is a change from 7.5 x 10-3 documented in the
preliminary determination.
Item 3 - Common Cause Failure Determination
Your staff stated that there was no single clear path for analysis of common cause failure for this
issue and recommended that the NRC staff use the definition of common cause failure
documented in NUREG/CR-5500, Volume 10, Reliability Study: Combustion Engineering
Reactor Protection System, 1984-1998. Additionally, your staff commented that the NRC staff
made an incorrect reference to Revision 1.01 of the Risk Assessment of Operational Events
handbook in our inspection report. Finally, your staff stated that the common cause observations
in the inspection report under Assumption 7 may need to be updated based on new information
provided in the Engineering Systems, Inc. report.
The NRC staff determined that the reference to Revision 1.01 of the handbook was incorrect.
However, this definition was not used in the common cause methodology utilized in our analysis.
The reasons for adjusting the common cause failure probability were best described in the
inspection report Page A-4, Assumptions 7 and 8.
The NRC staff also determined that NUREG/CR-5500 provides a concise definition of a common
cause failure. However, in the significance determination, the NRC staff did not assume that a
common cause failure event had occurred. If a failure of Contactors M1 and M2 had occurred at
the same time, the risk would have been significantly higher than our original estimates. The
guidance contained in NUREG/CR-5500 was not intended to be used to evaluate a condition
where the analyst believes that the common cause failure probability should be increased based
on observed conditions. The NRC staff has determined that the approach used in the inspection
report is the appropriate method to adjust common cause failure probabilities when components
are maintained and operated under similar conditions.
The NRC staff reviewed Assumption 7 in the NRC inspection report in light of the findings
documented in the report generated by the professional engineering consulting firm Engineering
Systems, Inc. However, the only condition that may have changed based on the Engineering
Systems, Inc. report was that, subparts exhibited significant scratching and indentations. The
NRC staff determined that despite such a change, the subject conditions, operation and
maintenance history of the contactors still warranted adjustment of the common cause failure
probability of contactor M1 given that contactor M2 failed.
Common cause failure probabilities are included in probabilistic risk assessment because
analysts have long recognized that many factors, such as the poor maintenance practices
indicated in the inspection report, which are not modeled explicitly in the models, can defeat
redundancy or diversity and make failures of multiple similar components more likely than would
be the case if these factors were absent. The effect of these factors on risk can be significant.
Fort Calhoun Station Reactor Protection System Issue
Final Significance Determination
- 3 -
Enclosure 2
For practical reasons related to data availability, the common cause failure probabilities of similar
components are estimated using data collected at the component level, without regard to failure
cause.
Factors such as poor maintenance processes are often part of the environment in which the
components are embedded and are not intrinsic properties of the components themselves. The
NRC staff uses the failure memory approach in evaluating the significance of a performance
deficiency. Observed failures are mapped into the probabilistic model, but successes are treated
probabilistically. Thus, failure probabilities are left at their nominal values or are conditioned as
necessary to reflect the details of the event.
To address this conditioning, the NRC staff has determined that there are three basic ground
rules for treatment of common cause failure:
a.
The shared cause is the deficiency identified in the inspection report which led to the
observed equipment failure. In the case of the subject finding, the licensees failure to
identify the cause of the loose shading coils was the performance deficiency. The
inspectors observed that at least one shading coil would easily come out of its recess on
all contactors.
b.
Common cause failures are of concern when they occur during the mission time of the
probabilistic risk assessment, which for internal hazard groups is generally 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The
common cause failure analysis methodology used and alpha vectors documented in the
inspection report were developed to intrinsically incorporate this requirement into the
common cause failure probabilities.
c.
Credit for programmatic actions to mitigate common cause failure potential (staggering
equipment modifications, etc.) should be applied qualitatively during the enforcement
process and not incorporated into the numerical risk result. For the subject performance
deficiency, this condition is moot. Inspection of components and records reviews
indicated that all contactors had been handled in the same manner.
Therefore, the NRC concludes that the treatment of common cause failure probabilities for the
reactor protection system contactors was appropriate and the conditional failure probability of the
M1 contactor is best approximated as 3.59 x 10-2/demand.
Item 4 - Higher Operator Reliability in Tripping the Reactor
Item 4a - Under Anticipated Transient Without Scram Conditions
Your staff indicated that follow-up operator actions, past the 10-minute point in the anticipated
transient without scram (ATWS) scenario, should be credited. You provided an evaluation by
Westinghouse of the expected Fort Calhoun Station plant response to this event. The evaluation
indicated that, due to a large negative moderator temperature coefficient, power would
automatically be reduced before the American Society of Mechanical Engineers (ASME) Level C
pressure limit of 3200 psig was exceeded. This would indicate that further operator actions could
be taken to trip the control rods without physical damage to key reactor components or systems.
NRC staff determined that the reactor response to a delayed tripping of the control rods in an
ATWS scenario, especially the pressure response, is a critical aspect in preventing core damage.
The details of the calculations and thermal-hydraulic runs of record are well established.
NUREG-1780 states that pressure transients are unacceptable if the ASME Level C value of
3200 psig is exceeded. It further stated that a higher ASME service level was considered for
Fort Calhoun Station Reactor Protection System Issue
Final Significance Determination
- 4 -
Enclosure 2
Babcock & Wilcox and Combustion Engineering plants, but was rejected on the basis that the
reactor coolant system pressure boundary could deform to the point of inoperability.
Your evaluation showed a peak pressure of 3176 psia (approximately 3162 psig) during a run of
the Combustion Engineering Nuclear Transient Simulator (CENTS) code. The NRC noted that
similar thermal-hydraulic code runs, referenced in NUREG-1000 and NUREG-1780, were very
sensitive to small variations or uncertainties in plant-specific parameters such as moderator
temperature coefficient, reactor vessel volumes, and other physical parameters. Your analysis
did not include sensitivities to variations or uncertainties in these parameters. For example, your
analysis used the Fort Calhoun Station predicted beginning of life full power moderator
temperature coefficient. However, you did not provide a sensitivity analysis for moderator
temperature coefficient showing potential inaccuracies in this value or its variation with power.
NUREG-1780 states that during the first part of the fuel cycle, below 100 percent power, the
moderator temperature coefficient can be positive or insufficiently negative. If an ATWS occurs
when the moderator temperature coefficient is either positive or insufficiently negative to limit
reactor power, and the ATWS pressure increases, all subsequent mitigating functions are likely to
be ineffective. NRC staff reviewed your predicted moderator temperature coefficient values over
core life and at different power levels and concluded you also have positive or insufficiently
negative values at lower powers.
It is the NRCs judgment that the 3176 psia outcome of your analysis is insufficient to assure the
ASME Level C value is not actually exceeded, considering the potential inaccuracies and
uncertainties of the analysis. Therefore, the NRC concluded the preliminary assessment time
limitations for the ATWS response should still be used and no changes were made to the
assessment for additional operator actions beyond 10 minutes.
Item 4b - Manual Trip Probability
Your staff pointed out that the failure of operators to push manual trip pushbutton No. 2 was not
dependant on the success or failure of manual trip pushbutton No. 1. Based on your procedures
the NRC staff concluded that, based on procedural guidance and operator training, the failure of
operators to push manual trip pushbutton No. 2 would not likely be affected by the success or
failure of manual trip pushbutton No. 1. Therefore, additional credit was given for the former
probability under RPS-XHE-ERROR as shown in Table 1. However, the NRC did not use your
suggested values (6 x 10-4) for either manual pushbutton, as those values were based on
additional time available to the operators in an ATWS scenario which the NRC staff determined
should not be credited as discussed in Item 4a.
Fort Calhoun Station Reactor Protection System Issue
Final Significance Determination
- 5 -
Enclosure 2
Summary
Table 1
Summary of Parameter Changes
Fort Calhoun Station Reactor Protector System Contactor Issue
Final Significance Determination
Parameter
Basic Event
Value
Preliminary
Significance
Licensee
Recommended
Final
Significance
1 Shorter Exposure Time
N/A
N/A
64 days
32.5 days
64 days
2 Lower Failure Probability for
Clutch Power Supply Breaker
RPS-BSN-FO-CBAB
RPS-BSN-FO-CBCD
7.5 x 10-3
7.5 x 10-3
1.2 x 10-4
3.81 x 10-4
3 Common Cause Failure
RPS-RYT-CF-M12
2.4 x 10-6
3.59 x 10-2
2.4 x 10-6
3.59 x 10-2
3 Contactor Failure
RPS-RYT-CC-M1
1.2 x 10-4
1.0
1.0
1.0
4a Operator Reliability Under
N/A
N/A
N/A
1.4 x 10-3
N/A
4b Manual Trip 1
RPS-XHE-XM-
1 x 10-2
1.5 x 10-3
6.0 x 10-4
1.5 x 10-3
4b Manual Trip 2
RPS-XHE-ERROR
N/A
0.5
6.0 x 10-4
6.0 x 10-3
The NRC staff requantified the detailed model of the reactor protection system used in the
preliminary significance determination using the modified parameters listed in Table 1. The
revised internal change in core damage frequency was calculated to be 6.47 x 10-6. Combining
this with the external risk calculated in the preliminary determination the total change in core
damage frequency was 7.14 x 10-6.
The staff has considered the information you provided to the NRC regarding the significance of
this issue and has concluded that the finding is appropriately characterized as being of low to
moderate safety significance (White). The agencys preliminary evaluation, as documented in
NRC Inspection Report 05000285/2011007, has been modified as shown above to reflect that the
change in core damage frequency for the finding was 7.14 x 10-6 as compared with 2.6 x 10-5.