DCL-12-036, Day Response to U.S. Nuclear Regulatory Commission'S Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review..: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[DCL-12-036, Day Response to U.S. Nuclear Regulatory Commissions Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review]]
| number = ML12102A184
| issue date = 04/11/2012
| title = Day Response to U.S. Nuclear Regulatory Commission'S Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review..
| author name = Halpin E
| author affiliation = Pacific Gas & Electric Co
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000275, 05000323
| license number = DPR-080, DPR-082
| contact person =
| case reference number = DCL-12-036
| document type = Letter type:DCL
| page count = 2
| project =
| stage = Request
}}
 
=Text=
{{#Wiki_filter:_ _ Pacific Gas and
~&~ Electric Company Diablo Canyon Power Plant PO. Box 56 Av il a Beach, CA 93424 800.545 .6000 April 11 ,2012 PG&E Letter DCL-12-036 u.s. Nuclear Regulatory Commission                                          10 CFR 50.54(f)
ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 30-Day Response to U.S. Nuclear Regulatory Commission's Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)
Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident
 
==Dear Commissioners and Staff:==
 
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50 .54(f)
Regarding Recommendations 2.1,2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident" (Information Request) to all NRC power reactor licensees and holders of construction permits in active or deferred status. In addition to requiring detailed information, the Information Request requires recipients to confirm receipt in writing within 30 days, and that the confirmation be signed under oath or affirmation.
In accordance with this requirement, Pacific Gas and Electric Company (PG&E) hereby submits notice to the NRC that it has received the Information Request and is currently assessing its contents and evaluating responses. Future responses will be provided to the NRC consistent with the terms of the Information Request.
PG&E makes no regulatory commitments (as defined by NEI 99-04) in this letter.
This letter includes no revisions to existing regulatory commitments.
If you have any questions, or require additional information, please contact Mr. Jearl Strickland at (805) 781-9785 or email LJS2@pge.com.
I state under penalty of perjury that the foregoing is true and correct.
Executed on April 11,2012.
A  member  of  the  STARS  (Strategic  Teaming  and  Resource  Sharing)  Alliance Callaway
* Comanche Peak
* Diablo Canyon
* Palo Verde
* San Onofre
* South Texas Project
* Wolf Creek
 
m  Document Control Desk April 11 ,2012
* & Page 2 Sincerely, PG&E Letter DCL-12-036 Edward D. Halpin Senior Vice President - Chief Nuclear Officer gwh2/SAPN 50465913-1 cc:        Elmo E. Collins, NRC Region IV Eric J. Leeds, NRC Director, Office of Nuclear Reactor Regulation Michael S. Peck, NRC, Senior Resident Inspector Joseph M. Sebrosky, NRR Project Manager Diablo Distribution A  member  of  the  STARS  (Strategic  Teaming  and  Resource  Sharing)  Alliance Callaway
* Comanche Peak
* Diablo Canyon
* Palo Verde
* San Onofre
* South Texas Project
* Wolf Creek}}