{{#Wiki_filter:SAFEGUARDS INFORMATION Constellation Energy Nine Mile Point Nuclear Station P.O. Box 63 Lycoming, NY 13093 April 26, 2006 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION:
{{#Wiki_filter:SAFEGUARDS INFORMATION Constellation Energy                                                     P.O. Box 63 Nine Mile Point Nuclear Station                                          Lycoming, NY 13093 April 26, 2006 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION:         Document Control Desk


==SUBJECT:==
==SUBJECT:==
Document Control Desk Nine Mile Point Nuclear Station Unit Nos. 1 & 2; Docket Nos. 50-220 & 50-410 Changes to Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan  
Nine Mile Point Nuclear Station Unit Nos. 1 & 2; Docket Nos. 50-220 & 50-410 Changes to Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan


==REFERENCES:==
==REFERENCES:==
(a) Letter from J.E. Dyer (NRC) to Timothy J. O'Connor (NMPNS), Issuance of Order Requiring Compliance with Updated Adversary Characteristic, dated March 20, 2006.(b) Letter from J.M. Heffley (CGG) to the Office of the Secretary of the Commission (NRC), Answer to the March 20, 2006 Commission Order Requiring Compliance with Updated Adversary Characteristic (EA-06-037), dated April 10, 2006.(c) Letter from W. C. Byrne (NMPNS) to NRC, Clarification Regarding Use of Supplemental Responders and Commitments to Incorporate Number of Supplemental Responders in the Security Plan, dated February 16, 2006 Pursuant to the requirements of NRC Order EA-06-037 (Reference a) and 10 CFR 50.5 4 (p), transmitted herewith are changed pages for Issue 6, Revision 1, of the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan (the Plan). The Order require. an Answer within 21 days, which was provided in Reference (b). In that Answer, Nine Mile Point Nuclear Station, LLC (NMPNS) consented to the Order. Further, the Order required that NMPNS notify the Commission when the Order has been fully implemented, but no later than 60 days from the date of the Order. This letter serves to notify the Commission that the Order has been fully implemented, and provides the revised Plan pages as also required by the Order. This Plan revision also incorporates changes recommended in the NRC/Nuclear Energy Institute (NEI) joint resolutions of Security Frequently Asked Questions (SFAQ) 04-09 and 05-03, and corrects an editorial error within Section 7.4 of Appendix C to the Plan. Incorporation of the Plan changes consistent with SFAQ 05-03 satisfies the NOTE: THE ATTACHMENTS TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY.
(a) Letter from J.E. Dyer (NRC) to Timothy J. O'Connor (NMPNS), Issuance of Order Requiring Compliance with Updated Adversary Characteristic, dated March 20, 2006.
UPON REMOVAL OF THE ATTACHMENTS, THIS LETTER IS"DECONTROLLED." SAFEGUARDS INFORMATION
(b) Letter from J.M. Heffley (CGG) to the Office of the Secretary of the Commission (NRC), Answer to the March 20, 2006 Commission Order Requiring Compliance with Updated Adversary Characteristic (EA-06-037), dated April 10, 2006.
.5.I , I's ,11;6 Document Control Desk April 26, 2006 Page 2 commitment contained in Reference (c). A summary of changes is provided in Attachment (1) and the revised pages of the Plan are provided in Attachment (2). Both attachments are classified as Safeguards InformE.tion.
(c) Letter from W. C. Byrne (NMPNS) to NRC, Clarification Regarding Use of Supplemental Responders and Commitments to Incorporate Number of Supplemental Responders in the Security Plan, dated February 16, 2006 Pursuant to the requirements of NRC Order EA-06-037 (Reference a) and 10 CFR 50.5 4 (p), transmitted herewith are changed pages for Issue 6, Revision 1, of the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan (the Plan). The Order require. an Answer within 21 days, which was provided in Reference (b). In that Answer, Nine Mile Point Nuclear Station, LLC (NMPNS) consented to the Order. Further, the Order required that NMPNS notify the Commission when the Order has been fully implemented, but no later than 60 days from the date of the Order. This letter serves to notify the Commission that the Order has been fully implemented, and provides the revised Plan pages as also required by the Order. This Plan revision also incorporates changes recommended in the NRC/Nuclear Energy Institute (NEI) joint resolutions of Security Frequently Asked Questions (SFAQ) 04-09 and 05-03, and corrects an editorial error within Section 7.4 of Appendix C to the Plan. Incorporation of the Plan changes consistent with SFAQ 05-03 satisfies the NOTE: THE ATTACHMENTS TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON REMOVAL OF THE ATTACHMENTS, THIS LETTER IS "DECONTROLLED."
NMPNS has reviewed the changes in this Plan revision and has determined that they do not reduce the effectiveness of the Plan or the overall Nuclear Security Program for Nine Mile Point Nuclear Station.Should you have any questions regarding the information in this submittal, please contact M. H. Miller, Licensing Director, at (315) 349-1510.Very truly yours, William C. Byrne Director Nuclear Security WCB/DEV/sac Attachments:
SAFEGUARDS INFORMATION                                                   .I ,.5I's
(1) Summary of Changes for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan (2) Changed Pages for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan cc: S. J. Collins, NRC T. G. Colburn, NRC Resident Inspector, NRC}}
                                                                                                      ,11;6
 
Document Control Desk April 26, 2006 Page 2 commitment contained in Reference (c). A summary of changes is provided in Attachment (1) and the revised pages of the Plan are provided in Attachment (2). Both attachments are classified as Safeguards InformE.tion.
NMPNS has reviewed the changes in this Plan revision and has determined that they do not reduce the effectiveness of the Plan or the overall Nuclear Security Program for Nine Mile Point Nuclear Station.
Should you have any questions regarding the information in this submittal, please contact M. H. Miller, Licensing Director, at (315) 349-1510.
Very truly yours, William C. Byrne Director Nuclear Security WCB/DEV/sac Attachments:     (1) Summary of Changes for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan (2) Changed Pages for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan cc:     S. J. Collins, NRC T. G. Colburn, NRC Resident Inspector, NRC}}

Revision as of 19:19, 23 November 2019

Changes to Nine Mile Point Physical Security, Safeguards Contingency and Security Training and Qualification Plan
ML061210094
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 04/26/2006
From: Byrne W
Constellation Energy Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML061210094 (2)


Text

SAFEGUARDS INFORMATION Constellation Energy P.O. Box 63 Nine Mile Point Nuclear Station Lycoming, NY 13093 April 26, 2006 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION: Document Control Desk

SUBJECT:

Nine Mile Point Nuclear Station Unit Nos. 1 & 2; Docket Nos. 50-220 & 50-410 Changes to Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan

REFERENCES:

(a) Letter from J.E. Dyer (NRC) to Timothy J. O'Connor (NMPNS), Issuance of Order Requiring Compliance with Updated Adversary Characteristic, dated March 20, 2006.

(b) Letter from J.M. Heffley (CGG) to the Office of the Secretary of the Commission (NRC), Answer to the March 20, 2006 Commission Order Requiring Compliance with Updated Adversary Characteristic (EA-06-037), dated April 10, 2006.

(c) Letter from W. C. Byrne (NMPNS) to NRC, Clarification Regarding Use of Supplemental Responders and Commitments to Incorporate Number of Supplemental Responders in the Security Plan, dated February 16, 2006 Pursuant to the requirements of NRC Order EA-06-037 (Reference a) and 10 CFR 50.5 4 (p), transmitted herewith are changed pages for Issue 6, Revision 1, of the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency and Security Training and Qualification Plan (the Plan). The Order require. an Answer within 21 days, which was provided in Reference (b). In that Answer, Nine Mile Point Nuclear Station, LLC (NMPNS) consented to the Order. Further, the Order required that NMPNS notify the Commission when the Order has been fully implemented, but no later than 60 days from the date of the Order. This letter serves to notify the Commission that the Order has been fully implemented, and provides the revised Plan pages as also required by the Order. This Plan revision also incorporates changes recommended in the NRC/Nuclear Energy Institute (NEI) joint resolutions of Security Frequently Asked Questions (SFAQ) 04-09 and 05-03, and corrects an editorial error within Section 7.4 of Appendix C to the Plan. Incorporation of the Plan changes consistent with SFAQ 05-03 satisfies the NOTE: THE ATTACHMENTS TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON REMOVAL OF THE ATTACHMENTS, THIS LETTER IS "DECONTROLLED."

SAFEGUARDS INFORMATION .I ,.5I's

,11;6

Document Control Desk April 26, 2006 Page 2 commitment contained in Reference (c). A summary of changes is provided in Attachment (1) and the revised pages of the Plan are provided in Attachment (2). Both attachments are classified as Safeguards InformE.tion.

NMPNS has reviewed the changes in this Plan revision and has determined that they do not reduce the effectiveness of the Plan or the overall Nuclear Security Program for Nine Mile Point Nuclear Station.

Should you have any questions regarding the information in this submittal, please contact M. H. Miller, Licensing Director, at (315) 349-1510.

Very truly yours, William C. Byrne Director Nuclear Security WCB/DEV/sac Attachments: (1) Summary of Changes for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan (2) Changed Pages for Issue 6, Revision 1, of the NMPNS Physical Security, Safeguards Contingency and Security Training and Qualification Plan cc: S. J. Collins, NRC T. G. Colburn, NRC Resident Inspector, NRC