{{#Wiki_filter: | {{#Wiki_filter:Roley Au 20call summary Jontha Pg From: Jonathan Rowley To: jdevinc@entergy.com; mhamer@entergy.com Date: 10/18/2007 10:54:36 AM | ||
==Subject:== | ==Subject:== | ||
Aug 20 call summary Please review and comment where you deem necessary on the attached August 20 telephone call summary.Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission | Aug 20 call summary Please review and comment where you deem necessary on the attached August 20 telephone call summary. | ||
'(301) 415-4053 | Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission | ||
'(301) 415-4053 | |||
? | Ic:*temp\GW}0009iiTMP ? ...... -/Z Z- -1*III 2.... viiiii i 2 Z Z I2i :2 Page*ZZ i !1 Mail Envelope Properties (471773AC.7F0 : 12 : 35182) | ||
2.... viiiii i 2 Z Z I2i :2 i !1 Mail Envelope Properties (471773AC.7F0 | |||
: 12 : 35182) | |||
==Subject:== | ==Subject:== | ||
Aug 20 call summary Creation Date 10/18/2007 10:54:36 AM From: Jonathan Rowley Created By: JGR(anrc.gov Recipients Action Date & Time entergy.com Transferred 10/18/2007 10:55:11 AM jdevinc (idevinc(T,ýentergy.com) mhamer (mhamer(aentergy.com) | |||
Post Office Deliveired Route entergy.com Files Size Date & Time MESSAGE 820 10/18/ 2007 10:54:36 AM TEXT.htm 585 Summary of Telephone Conference - August 20, 2007.wpd 22824 10/18/2007 10:52:22 AM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification: | |||
-August 20, 2007.wpd 10:52:22 AM Options Auto Delete: No Expiration Date: None Notify Recipients: | |||
Yes Priority: | |||
Standard ReplyRequested: | |||
No Return Notification: | |||
Send Notification when Opened Concealed | Send Notification when Opened Concealed | ||
==Subject:== | ==Subject:== | ||
No Security: | No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened | ||
Standard To Be Delivered: | |||
Immediate Status Tracking: | Rowley -_S phone Conference - August 20, 2007.wpd Paqe Pane 1 1 Jonathan Rowley-Summary of Telephone Conference-August 20, 2007 wpd LICENSEE: Entergy Nuclear Operations, Inc. | ||
Delivered | FACILITY: Vermont Yankee Nuclear Power Station | ||
& Opened | |||
-August 20, 2007.wpd Paqe Jonathan Rowley-Summary of Telephone Conference-August 20, 2007 wpd | |||
Entergy Nuclear Operations, Inc.FACILITY: | |||
Vermont Yankee Nuclear Power Station | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 20, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR Part 54.21 (c)(1 ) as it relates to the Vermont Yankee Nuclear Power Station safety evaluation report.Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the issue discussed with the applicant. | OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 20, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR Part 54.21 (c)(1 ) as it relates to the Vermont Yankee Nuclear Power Station safety evaluation report. | ||
The applicant had an opportunity to comment on this summary.Jonathan G. Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271 | Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the issue discussed with the applicant. | ||
The applicant had an opportunity to comment on this summary. | |||
Jonathan G. Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271 | |||
==Enclosures:== | ==Enclosures:== | ||
: 1. List of Participants | : 1. List of Participants | ||
: 2. Summary of Discussion cc w/encls: See next page I | : 2. Summary of Discussion cc w/encls: See next page I | ||
DOCUMENT NAME: Conference - August 20, 2007.wpdctempgwprintSummary of Telephone Conference - August 20, 2007.wpd OFFICE LA:DLR PM:RLRB:DLR BC:RLRB:DLR NAME JRowley RAuluck DATE / / I | |||
Jonathan Row-ley - Summary of Telephone Conference -August 20, 2007.wpd P TELEPHONE CONFERENCE CALL VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AUGUST 20, 2007 PARTICIPANTS AFFILIATIONS Jonathan Rowley Nuclear Regulatory Commission (NRC) | |||
Kenneth Chang NRC Stephen Hoffman NRC Michael Metell Entergy Nuclear Operations, Inc. (Entergy) | |||
Gary Young Entergy Allen Cox Entergy David Lach Entergy David Mannai Entergy Michael Hamer Entergy | |||
?? Ford Entergy Enclosure 1 | |||
09QOýn Rowleyý §!4_TMý!ry'of Telephone Conference ý_49ý1Lsj'.11 ?1. | |||
9, 12 1007.wpd ppage 4I! | |||
Jonat....n.. o.. l.......m..... of..Telephone...C.nf..ren..e.A.gust..20,.........pd..Pa..e.41 OPEN ITEMS VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT AUGUST 20, 2007 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR 54.21 (c)(1) as it relates to the Vermont Yankee Nuclear Power Station (VYNPS) safety evaluation report (SER). | |||
Discussion summary: It is the NRC position that in order to meet the requirements of 10 CFR 54.21(c)(1), an applicant for license renewal must demonstrate in the renewal application that the evaluation of the time-limited aging analyses (TLAA) has been completed. | |||
09QOýn Rowleyý §! | |||
o.. l.......m..... | |||
of.. Telephone...C.nf..ren..e.A.gust..20,.........pd..Pa..e.41 OPEN ITEMS VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT AUGUST 20, 2007 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR 54.21 (c)(1) as it relates to the Vermont Yankee Nuclear Power Station (VYNPS) safety evaluation report (SER).Discussion summary: It is the NRC position that in order to meet the requirements of 10 CFR 54.21(c)(1), an applicant for license renewal must demonstrate in the renewal application that the evaluation of the time-limited aging analyses (TLAA) has been completed. | |||
The NRC does not except a commitment to complete the evaluation of the TLAA prior to entering the period of extended operation. | The NRC does not except a commitment to complete the evaluation of the TLAA prior to entering the period of extended operation. | ||
Based on the discussion, the applicant agreed to amended its license renewal application to demonstrate that the evaluation of the TLAA has been completed. | Based on the discussion, the applicant agreed to amended its license renewal application to demonstrate that the evaluation of the TLAA has been completed. The NRC's review of this TLAA evaluation will be documented in the final VYNPS SER. | ||
The NRC's review of this TLAA evaluation will be documented in the final VYNPS SER.Enclosure 2}} | Enclosure 2}} | ||
Revision as of 01:19, 23 November 2019
| ML073040080 | |
| Person / Time | |
|---|---|
| Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
| Issue date: | 10/18/2007 |
| From: | Rowley J NRC/NRR/ADRO/DLR/RLRB |
| To: | Devince J, Hamer M Entergy Nuclear Vermont Yankee |
| References | |
| TAC MD2297 | |
| Download: ML073040080 (6) | |
Text
Roley Au 20call summary Jontha Pg From: Jonathan Rowley To: jdevinc@entergy.com; mhamer@entergy.com Date: 10/18/2007 10:54:36 AM
Subject:
Aug 20 call summary Please review and comment where you deem necessary on the attached August 20 telephone call summary.
Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission
'(301) 415-4053
Ic:*temp\GW}0009iiTMP ? ...... -/Z Z- -1*III 2.... viiiii i 2 Z Z I2i :2 Page*ZZ i !1 Mail Envelope Properties (471773AC.7F0 : 12 : 35182)
Subject:
Aug 20 call summary Creation Date 10/18/2007 10:54:36 AM From: Jonathan Rowley Created By: JGR(anrc.gov Recipients Action Date & Time entergy.com Transferred 10/18/2007 10:55:11 AM jdevinc (idevinc(T,ýentergy.com) mhamer (mhamer(aentergy.com)
Post Office Deliveired Route entergy.com Files Size Date & Time MESSAGE 820 10/18/ 2007 10:54:36 AM TEXT.htm 585 Summary of Telephone Conference - August 20, 2007.wpd 22824 10/18/2007 10:52:22 AM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification:
Send Notification when Opened Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened
Rowley -_S phone Conference - August 20, 2007.wpd Paqe Pane 1 1 Jonathan Rowley-Summary of Telephone Conference-August 20, 2007 wpd LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Vermont Yankee Nuclear Power Station
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON AUGUST 20, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR Part 54.21 (c)(1 ) as it relates to the Vermont Yankee Nuclear Power Station safety evaluation report.
Enclosure 1 provides a listing of the participants and Enclosure 2 contains a summary of the issue discussed with the applicant.
The applicant had an opportunity to comment on this summary.
Jonathan G. Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosures:
- 1. List of Participants
- 2. Summary of Discussion cc w/encls: See next page I
DOCUMENT NAME: Conference - August 20, 2007.wpdctempgwprintSummary of Telephone Conference - August 20, 2007.wpd OFFICE LA:DLR PM:RLRB:DLR BC:RLRB:DLR NAME JRowley RAuluck DATE / / I
Jonathan Row-ley - Summary of Telephone Conference -August 20, 2007.wpd P TELEPHONE CONFERENCE CALL VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AUGUST 20, 2007 PARTICIPANTS AFFILIATIONS Jonathan Rowley Nuclear Regulatory Commission (NRC)
Kenneth Chang NRC Stephen Hoffman NRC Michael Metell Entergy Nuclear Operations, Inc. (Entergy)
Gary Young Entergy Allen Cox Entergy David Lach Entergy David Mannai Entergy Michael Hamer Entergy
?? Ford Entergy Enclosure 1
09QOýn Rowleyý §!4_TMý!ry'of Telephone Conference ý_49ý1Lsj'.11 ?1.
9, 12 1007.wpd ppage 4I!
Jonat....n.. o.. l.......m..... of..Telephone...C.nf..ren..e.A.gust..20,.........pd..Pa..e.41 OPEN ITEMS VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL SAFETY EVALUATION REPORT AUGUST 20, 2007 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. held a telephone conference call on August 20, 2007, to discuss the regulatory requirements stated in 10 CFR 54.21 (c)(1) as it relates to the Vermont Yankee Nuclear Power Station (VYNPS) safety evaluation report (SER).
Discussion summary: It is the NRC position that in order to meet the requirements of 10 CFR 54.21(c)(1), an applicant for license renewal must demonstrate in the renewal application that the evaluation of the time-limited aging analyses (TLAA) has been completed.
The NRC does not except a commitment to complete the evaluation of the TLAA prior to entering the period of extended operation.
Based on the discussion, the applicant agreed to amended its license renewal application to demonstrate that the evaluation of the TLAA has been completed. The NRC's review of this TLAA evaluation will be documented in the final VYNPS SER.
Enclosure 2