ML080600164: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:February 29, | {{#Wiki_filter:February 29, 2008 | ||
EA-08-028 | |||
Mike Blevins, Senior Vice President | |||
and Chief Nuclear Officer | |||
Luminant Generation Company, LLC | Luminant Generation Company, LLC | ||
ATTN: | ATTN: Regulatory Affairs | ||
Comanche Peak Steam Electric Station | Comanche Peak Steam Electric Station | ||
P.O. Box 1002 | P.O. Box 1002 | ||
Glen Rose, TX | Glen Rose, TX 76043 | ||
NRC SPECIAL INSPECTION REPORT 05000445/ | SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND | ||
On January 24, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed its | NOTICE OF VIOLATION - COMANCHE PEAK STEAM ELECTRIC STATION - | ||
NRC SPECIAL INSPECTION REPORT 05000445/2007008 | |||
Dear Mr. Blevins: | |||
On January 24, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed its reviews | |||
related to a Special Inspection at your Comanche Peak Steam Electric Station, Unit 1, facility. | |||
This Special Inspection Team was chartered to review the circumstances related to the failure | |||
of Emergency Diesel Generator (EDG) 1-02 to start on November 21, 2007, and to evaluate the | of Emergency Diesel Generator (EDG) 1-02 to start on November 21, 2007, and to evaluate the | ||
actions taken in response to the problem. | actions taken in response to the problem. The NRC's initial evaluation satisfied the criteria in | ||
NRC Management Directive 8.3, | NRC Management Directive 8.3, NRC Incident Investigation Program, for conducting a special | ||
inspection. | inspection. The possibility that adverse generic implications were associated with the EDG | ||
failure mechanism was the deterministic criterion met. | failure mechanism was the deterministic criterion met. Additionally, the result of the NRCs | ||
initial conditional risk assessment associated with this degraded condition indicated that a | initial conditional risk assessment associated with this degraded condition indicated that a | ||
special inspection was warranted. | special inspection was warranted. The determination that the inspection would be conducted | ||
was made by the NRC on November 30, 2007, and the inspection started on December 4, | was made by the NRC on November 30, 2007, and the inspection started on December 4, | ||
2007. | |||
The inspection examined activities conducted under your license as they relate to safety and | |||
compliance with the Commissions rules and regulations and with the conditions of your license. | |||
The inspectors reviewed selected procedures and records, observed activities, and interviewed | The inspectors reviewed selected procedures and records, observed activities, and interviewed | ||
personnel.The enclosed inspection report documents the inspection results, which were discussed | personnel. | ||
respectively, and other members of your staff. | The enclosed inspection report documents the inspection results, which were discussed on | ||
with Mr. F. Madden, Director, Regulatory Affairs, and other members of your staff to convey the | December 7, 2007, and again on January 10, 2008, with Mr. R. Flores and Mr. T. Hope, | ||
Luminant Generating Company, LLC-2-final disposition of the inspection findings. | respectively, and other members of your staff. On January 24, 2008, an exit meeting was held | ||
with Mr. F. Madden, Director, Regulatory Affairs, and other members of your staff to convey the | |||
Luminant Generating Company, LLC -2- | |||
final disposition of the inspection findings. Following a discussion of the preliminary safety | |||
significance of this finding during the exit briefing, Mr. Madden indicated that Luminant Power | |||
does not contest the characterization of the risk significance of this finding, and that you have | does not contest the characterization of the risk significance of this finding, and that you have | ||
declined to further discuss this issue at a Regulatory Conference or provide a written response. | declined to further discuss this issue at a Regulatory Conference or provide a written response. | ||
Accordingly, the NRC is issuing the final significance determination for the inspection finding as | Accordingly, the NRC is issuing the final significance determination for the inspection finding as | ||
discussed below. | discussed below. On February 25, 2008, an additional exit meeting was held with Mr. T. Hope, | ||
and other members of your staff to convey a revision to one of the inspection findings. This report documents one finding concerning a failure to satisfy Technical Specification (TS)Limiting Condition for Operation (LCO) 3.8.1 due to EDG 1-02 being in an inoperable | and other members of your staff to convey a revision to one of the inspection findings. | ||
This report documents one finding concerning a failure to satisfy Technical Specification (TS) | |||
Limiting Condition for Operation (LCO) 3.8.1 due to EDG 1-02 being in an inoperable condition | |||
following maintenance. Following the discovery of this condition, the TS required actions were | |||
satisfied however, the time period between the occurrence of the condition and the discovery of | satisfied however, the time period between the occurrence of the condition and the discovery of | ||
the condition exceeded the TS allowed outage time for the EDG. | the condition exceeded the TS allowed outage time for the EDG. This finding has been | ||
determined to be of low to moderate safety significance (White). | determined to be of low to moderate safety significance (White). This finding does not | ||
represent an immediate safety concern because of the corrective actions you have taken. | represent an immediate safety concern because of the corrective actions you have taken. | ||
These actions included restoring EDG 1-02 to an operable status, ensuring that all other EDGs | These actions included restoring EDG 1-02 to an operable status, ensuring that all other EDGs | ||
were not in a similar degraded condition, and curtailing painting activities pending the | were not in a similar degraded condition, and curtailing painting activities pending the | ||
implementation of suitable measures to prevent the recurrence of a similar condition.You have 30 calendar days from the date of this letter to appeal the | implementation of suitable measures to prevent the recurrence of a similar condition. | ||
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. | You have 30 calendar days from the date of this letter to appeal the NRCs determination of | ||
significance for the identified White finding. Such appeals will be considered to have merit only | |||
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. In | |||
accordance with the NRC Enforcement Policy, the Notice of Violation is considered an | accordance with the NRC Enforcement Policy, the Notice of Violation is considered an | ||
escalated enforcement action because it is associated with a White finding.You are required to respond to this letter and should follow the instructions specified in | escalated enforcement action because it is associated with a White finding. | ||
You are required to respond to this letter and should follow the instructions specified in the | |||
enclosed Notice when preparing your response. | |||
In addition, we will use the NRC Action Matrix to determine the most appropriate NRC response | |||
to this issue, and we will notify you by separate correspondence of that determination. | |||
The report also documents one NRC-identified finding of very low safety significance (Green). | |||
This finding was determined to involve a violation of NRC requirements. However, because of | |||
the very low safety significance and because it is entered into your corrective action program, | the very low safety significance and because it is entered into your corrective action program, | ||
the NRC is treating the finding as a noncited violation (NCV) consistent with Section VI.A.1 of | the NRC is treating the finding as a noncited violation (NCV) consistent with Section VI.A.1 of | ||
the NRC Enforcement Policy. | the NRC Enforcement Policy. If you contest this NCV, you should provide a response within | ||
30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear | 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear | ||
Regulatory Commission, ATTN.: | Regulatory Commission, ATTN.: Document Control Desk, Washington, DC 20555-0001; with | ||
copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611 | copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611 | ||
Ryan Plaza Drive, Suite 400, Arlington, Texas 76011-4005; the Director, Office of Enforcement, | Ryan Plaza Drive, Suite 400, Arlington, Texas 76011-4005; the Director, Office of Enforcement, | ||
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident | U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident | ||
Inspector at the Comanche Peak Steam Electric Station.In accordance with 10 CFR 2.390 of the NRC's | Inspector at the Comanche Peak Steam Electric Station. | ||
Luminant Generating Company, LLC-3-NRC Public Document Room or from the Publicly Available Records (PARS) component | In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its | ||
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | enclosure, and your response (if any) will be available electronically for public inspection in the | ||
safeguards information so that it can be made available to the public without redaction.Sincerely, /RA/Elmo E. | |||
2.NRC Inspection Report 05000445/2007008 | Luminant Generating Company, LLC -3- | ||
NRC Public Document Room or from the Publicly Available Records (PARS) component of | |||
Attachment 3:Significance Determination | NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at | ||
Regulatory Affairs | http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). To the | ||
extent possible, your response should not include any personal privacy, proprietary, or | |||
safeguards information so that it can be made available to the public without redaction. | |||
Sincerely, | |||
/RA/ | |||
Elmo E. Collins | |||
Regional Administrator | |||
Dockets: 50-445 | |||
Licenses: NPF-87 | |||
Enclosures: | |||
1. Notice of Violation | |||
2. NRC Inspection Report 05000445/2007008 | |||
w/Attachments | |||
Attachment 1: Supplemental Information | |||
Attachment 2: Special Inspection Charter | |||
Attachment 3: Significance Determination Evaluation | |||
cc w/enclosures: | |||
Fred W. Madden, Director | |||
Regulatory Affairs | |||
Luminant Generation Company LLC | Luminant Generation Company LLC | ||
P.O. Box 1002 | P.O. Box 1002 | ||
Glen Rose, TX | Glen Rose, TX 76043 | ||
Timothy P. Matthews, Esq. | |||
Morgan Lewis | |||
1111 Pennsylvania Avenue, NW | 1111 Pennsylvania Avenue, NW | ||
Washington, DC | Washington, DC 20004 | ||
Anthony Jones, Chief Boiler Inspector | |||
Texas Department of Licensing | |||
and Regulation | |||
Boiler Program | Boiler Program | ||
P.O. Box 12157 | P.O. Box 12157 | ||
Austin, TX | Austin, TX 78711 | ||
Glen Rose, TX | Somervell County Judge | ||
Luminant Generating Company, LLC-4-Richard A. Ratliff, | P.O. Box 851 | ||
Glen Rose, TX 76043 | |||
Luminant Generating Company, LLC -4- | |||
Richard A. Ratliff, Chief | |||
Bureau of Radiation Control | |||
Texas Department of Health | Texas Department of Health | ||
1100 West 49th Street | 1100 West 49th Street | ||
Austin, TX | Austin, TX 78756-3189 | ||
Environmental and Natural | |||
Resources Policy Director | |||
Office of the Governor | Office of the Governor | ||
P.O. Box 12428 | P.O. Box 12428 | ||
Austin, TX | Austin, TX 78711-3189 | ||
Brian Almon | |||
Public Utility Commission | |||
William B. Travis Building | William B. Travis Building | ||
P.O. Box 13326 | P.O. Box 13326 | ||
Austin, TX | Austin, TX 78711-3326 | ||
Susan M. Jablonski | |||
Texas Commission on | Office of Permitting, Remediation | ||
and Registration | |||
Texas Commission on | |||
Environmental Quality | |||
MC-122 | MC-122 | ||
P.O. Box 13087 | P.O. Box 13087 | ||
Austin, TX | Austin, TX 78711-3087 | ||
Environmental and Natural | |||
Resources Policy Director | |||
Office of the Governor | Office of the Governor | ||
P.O. Box 12428 | P.O. Box 12428 | ||
Austin, TX 78711- | Austin, TX 78711-3189 | ||
Lisa R. Hammond, Chief | |||
Technological Hazards Branch | |||
National Preparedness Division | National Preparedness Division | ||
FEMA Region VI | FEMA Region VI | ||
800 N. Loop 288 | 800 N. Loop 288 | ||
Denton, TX | Denton, TX 76209 | ||
Luminant Generating Company, LLC-5-Electronic distribution: | |||
Luminant Generating Company, LLC -5- | |||
RIDSNRRADIP RIDSOPAMAIL | Electronic distribution: | ||
ROPreports | |||
RIDSSECYMAILCENTER RIDSOCAMAILCENTER | |||
RIDSEDOMAILCENTER RIDSOEMAILCENTER | |||
RIDSOGCMAILCENTER RIDSNRROD | |||
Vegel - | RIDSNRRADIP RIDSOPAMAIL | ||
Caniano - | RIDSOIMAILCENTER RIDSOIGMAILCENTER | ||
ACampbell - | RIDSOCFOMAILCENTER RIDSRGN1MAILCENTER | ||
DLoveless - | RIDSRGN2MAILCENTER RIDSRGN3MAILCENTER | ||
Herrera - | RIDSNRRDIPMIIPB OEWEB | ||
Mary Ann Ashley, | ECollins AHowell Fuller - KSF | ||
Dricks - | C Maier Vasquez - GMV D Furst, NSIR | ||
DPowers - | Vegel - AXV Chamberlain - DDC N Hilton, OE | ||
Caniano - RJC1 Powers - DAP June Cai, OE | |||
G | ACampbell - ACC CJohnson - CEJ1 John Wray, OE | ||
G | DLoveless - DPL DAllen - DBA ASanchez - AAS1 | ||
Herrera - MSH3 SSanner - ESS Starkey, OE - DRS | |||
Mary Ann Ashley, NRR Paulk -CJP M Burrell, OE | |||
Dricks - VLD WMaier - WAM R Barnes, OE | |||
onsite Class 1E power distribution subsystem(s) shall be operable. | DPowers - DAP DPelton - DLP1 | ||
one DG being inoperable, the required action is to restore the DG to an operable status | SUNSI Review Completed: CEJ ADAMS: / Yes G No Initials: CEJ | ||
within 72 hours and within 6 days from the discovery of the failure to meet the Limiting | / Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive | ||
Condition for Operation (LCO), or be in Mode 3 within 6 hours and Mode 5 within 36 | R:\_REACTORS\_CPSES\2007\CP2007-08 CHY.wpd ADAMS ML080600164 | ||
hours.Contrary to the above, from November 1, 2007, through November 21, 2007, while | RIV:RI:DRP/E SRI:DRP/E SRA C:DRP/A SES/ACES | ||
power distribution subsystem(s) was inoperable, and action was not taken to either | CHYoung:vlh;mjs AASanchez DPLoveless CEJohnson GMVasquez | ||
restore the DG to an operable status within 72 hours or be in Mode 3 within 6 hours and | E-CEJ E-CEJ /RA/ /RA/ /RA/ | ||
Mode 5 within 36 hours. | 1/31/08 2/08/08 2/08/08 2/12/08 2/11/08 | ||
made inoperable as a result of painting activities due to paint having been deposited and | D:DRS D:DRP C:ACES DRA RA | ||
remaining on at least one fuel rack in a location that prevented motion required to | RJCaniano DDChamberlain KSFuller ATHowell EECollins | ||
support the operation of the EDG. | /RA/ /RA/ /RA/ /RA/ /RA/ | ||
a surveillance test on November 21, 2007. This violation is associated with a White significance determination process finding.Pursuant to the provisions of 10 CFR 2.201, Luminant Generation Company, LLC is | 2/11/08 2/21/08 2/14/08 2/22/08 2/28/08 | ||
Commission, ATTN.: | OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax | ||
NOTICE OF VIOLATION | |||
Luminant Generation Company, LLC Docket No. 50-445 | |||
Comanche Peak Steam Electric Station License No. NPF-87 | |||
EA-08-028 | |||
During an NRC inspection completed on January 24, 2008, a violation of NRC requirements | |||
was identified. In accordance with the NRC Enforcement Policy, the violation is listed below: | |||
Unit 1 Technical Specification (TS) 3.8.1, AC Sources - Operating, requires that while | |||
the plant is in Modes 1, 2, 3, or 4, two diesel generators (DGs) capable of supplying the | |||
onsite Class 1E power distribution subsystem(s) shall be operable. For the condition of | |||
one DG being inoperable, the required action is to restore the DG to an operable status | |||
within 72 hours and within 6 days from the discovery of the failure to meet the Limiting | |||
Condition for Operation (LCO), or be in Mode 3 within 6 hours and Mode 5 within 36 | |||
hours. | |||
Contrary to the above, from November 1, 2007, through November 21, 2007, while the | |||
plant was in Mode 1, one of the two DGs capable of supplying the onsite Class 1E | |||
power distribution subsystem(s) was inoperable, and action was not taken to either | |||
restore the DG to an operable status within 72 hours or be in Mode 3 within 6 hours and | |||
Mode 5 within 36 hours. Specifically, Emergency Diesel Generator (EDG) 1-02 was | |||
made inoperable as a result of painting activities due to paint having been deposited and | |||
remaining on at least one fuel rack in a location that prevented motion required to | |||
support the operation of the EDG. This condition caused EDG 1-02 to fail to start during | |||
a surveillance test on November 21, 2007. | |||
This violation is associated with a White significance determination process finding. | |||
Pursuant to the provisions of 10 CFR 2.201, Luminant Generation Company, LLC is hereby | |||
required to submit a written statement or explanation to the U.S. Nuclear Regulatory | |||
Commission, ATTN.: Document Control Desk, Washington, DC 20555-0001 with a copy to the | |||
Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the facility that | Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the facility that | ||
is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of | is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of | ||
Violation (Notice). | Violation (Notice). This reply should be clearly marked as a Reply to a Notice of Violation; | ||
EA-08-028, and should include for each violation: (1) the reason for the violation, or, if | |||
contested, the basis for disputing the violation or severity level; (2) the corrective steps that | contested, the basis for disputing the violation or severity level; (2) the corrective steps that | ||
have been taken and the results achieved; (3) the corrective steps that will be taken to avoid | have been taken and the results achieved; (3) the corrective steps that will be taken to avoid | ||
further violations and (4) the date when full compliance will be achieved. | further violations and (4) the date when full compliance will be achieved. Your response may | ||
reference or include previous docketed correspondence, if the correspondence adequately | reference or include previous docketed correspondence, if the correspondence adequately | ||
addresses the required response. | addresses the required response. If an adequate reply is not received within the time specified | ||
in this Notice, an order or a Demand for Information may be issued as to why the license should | in this Notice, an order or a Demand for Information may be issued as to why the license should | ||
Enclosure 1 | Enclosure 1 | ||
not be modified, suspended, or revoked, or why such other action as may be proper should not | |||
be taken. Where good cause is shown, consideration will be given to extending the response | |||
time. | time. | ||
If you contest this enforcement action, you should also provide a copy of your response, with | If you contest this enforcement action, you should also provide a copy of your response, with | ||
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear | the basis for your denial, to the Director, Office of Enforcement, United States Nuclear | ||
Regulatory Commission, Washington, DC 20555-0001. Because your response will be made available electronically for public inspection in the | Regulatory Commission, Washington, DC 20555-0001. | ||
NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it | Because your response will be made available electronically for public inspection in the NRC | ||
available to the public without redaction. | Public Document Room or from the NRCs document system (ADAMS), accessible from the | ||
NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should | |||
not include any personal privacy, proprietary, or safeguards information so that it can be made | |||
available to the public without redaction. If personal privacy or proprietary information is | |||
necessary to provide an acceptable response, then please provide a bracketed copy of your | necessary to provide an acceptable response, then please provide a bracketed copy of your | ||
response that identifies the information that should be protected and a redacted copy of your | response that identifies the information that should be protected and a redacted copy of your | ||
response that deletes such information. | response that deletes such information. If you request withholding of such material, you must | ||
specifically identify the portions of your response that you seek to have withheld and provide in | |||
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will | detail the bases for your claim of withholding (e.g., explain why the disclosure of information will | ||
create an unwarranted invasion of personal privacy or provide the information required by | create an unwarranted invasion of personal privacy or provide the information required by | ||
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial | 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial | ||
information). | information). If safeguards information is necessary to provide an acceptable response, please | ||
provide the level of protection described in 10 CFR 73.21. | provide the level of protection described in 10 CFR 73.21. | ||
Dated this 29th day of February 2008. | |||
U.S. NUCLEAR REGULATORY | -2- Enclosure 1 | ||
Report:05000445/2007008 | |||
Licensee:Luminant Generation Company, LLC | U.S. NUCLEAR REGULATORY COMMISSION | ||
Facility:Comanche Peak Steam Electric Station, Unit 1 | REGION IV | ||
Location:FM-56, Glen Rose, Texas | Dockets: 50-445 | ||
Dates:December 4, 2007, through January 24, 2008 | Licenses: NPF-87 | ||
Team Leader:C. Young, P.E., Resident Inspector, Arkansas Nuclear One | Report: 05000445/2007008 | ||
Inspectors:A. Sanchez, Resident Inspector, Comanche Peak Steam Electric | Licensee: Luminant Generation Company, LLC | ||
Facility: Comanche Peak Steam Electric Station, Unit 1 | |||
to start on demand on November 21, 2007.The report covered a 6-day period (December 4-7, 2007) of onsite inspection, with | Location: FM-56, Glen Rose, Texas | ||
inspectors and one senior reactor analyst. | Dates: December 4, 2007, through January 24, 2008 | ||
noncited violation, and one White violation. | Team Leader: C. Young, P.E., Resident Inspector, Arkansas Nuclear One | ||
color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, | Inspectors: A. Sanchez, Resident Inspector, Comanche Peak Steam Electric Station | ||
Determination Process. | D. Loveless, Senior Reactor Analyst | ||
apply may be Green or be assigned a severity level after NRC management review. | Branch Chief: C. Johnson, Chief, Project Branch A | ||
Division of Reactor Projects | |||
Approved By: D. Chamberlain, Director | |||
Division of Reactor Projects | |||
SUMMARY OF FINDINGS | |||
IR 05000445/2007008; 12/04/07 - 01/24/08; Comanche Peak Steam Electric Station (CPSES), | |||
Unit 1; Special Inspection in response to the failure of the Train B Emergency Diesel Generator | |||
to start on demand on November 21, 2007. | |||
The report covered a 6-day period (December 4-7, 2007) of onsite inspection, with inoffice | |||
review through January 24, 2008, by a special inspection team consisting of two resident | |||
inspectors and one senior reactor analyst. Two findings were identified, including one Green | |||
noncited violation, and one White violation. The significance of most findings is indicated by its | |||
color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance | |||
Determination Process. Findings for which the significance determination process does not | |||
apply may be Green or be assigned a severity level after NRC management review. The | |||
NRC's program for overseeing the safe operation of commercial nuclear power reactors is | NRC's program for overseeing the safe operation of commercial nuclear power reactors is | ||
described in NUREG-1649, | described in NUREG-1649, Reactor Oversight Process, Revision 4, dated July 2000. | ||
*White. | A. NRC-Identified and Self-Revealing Findings | ||
for Operation 3.8.1 in that painting activities conducted on the Unit 1 Train B | Cornerstone: Mitigating Systems | ||
EDG 1-02 resulted in paint being deposited and left in a location that caused the | * White. A violation of Unit 1 Technical Specification 3.8.1, AC Sources - | ||
EDG to become inoperable. | Operating, was identified for the licensees failure to satisfy Limiting Condition | ||
during the subsequent monthly surveillance test. | for Operation 3.8.1 in that painting activities conducted on the Unit 1 Train B | ||
condition, the required actions were satisfied; however, the time period between | EDG 1-02 resulted in paint being deposited and left in a location that caused the | ||
the occurrence of the condition and the discovery of the condition exceeded the | EDG to become inoperable. As a result, EDG 1-02 failed to start on demand | ||
allowed outage time. | during the subsequent monthly surveillance test. Following the discovery of the | ||
program as SMF-2007-03253.The finding was greater than minor because it was associated with the | condition, the required actions were satisfied; however, the time period between | ||
cornerstone objective to ensure the availability, reliability, and capability of | the occurrence of the condition and the discovery of the condition exceeded the | ||
systems that respond to initiating events to prevent undesirable consequences. | allowed outage time. This issue was entered into the licensees corrective action | ||
The Phase 1 Worksheets in Manual Chapter 0609, | program as SMF-2007-03253. | ||
Process, | The finding was greater than minor because it was associated with the human | ||
the performance deficiency affected the emergency power supply system that is | performance attribute of the mitigating systems cornerstone, and it affected the | ||
a support system for both mitigating and containment barrier systems. | cornerstone objective to ensure the availability, reliability, and capability of | ||
the results of the Phase 2 analysis, the finding was determined to have low to | systems that respond to initiating events to prevent undesirable consequences. | ||
moderate safety significance (White). | The Phase 1 Worksheets in Manual Chapter 0609, Significance Determination | ||
that a more detailed Phase 3 analysis was needed to fully assess the safety | Process, were used to conclude that a Phase 2 analysis was required because | ||
significance. | the performance deficiency affected the emergency power supply system that is | ||
determined to have low to moderate safety significance (White). | a support system for both mitigating and containment barrier systems. Based on | ||
2, and 3 Significance Determination Process analyses associated with this | the results of the Phase 2 analysis, the finding was determined to have low to | ||
finding, including assumptions and limiting core damage sequences, is included | moderate safety significance (White). The senior reactor analyst determined | ||
as Attachment 3 to this report. | that a more detailed Phase 3 analysis was needed to fully assess the safety | ||
a crosscutting aspect in the area of human performance associated with work | significance. Based on the results of the Phase 3 analysis, the finding was | ||
Enclosure 2 | determined to have low to moderate safety significance (White). The Phase 1, | ||
safety is supported [H.4(c)]. | 2, and 3 Significance Determination Process analyses associated with this | ||
assess and control the operational impact of the painting activities on the | finding, including assumptions and limiting core damage sequences, is included | ||
functionality of the emergency diesel generator were not reflective of adequate | as Attachment 3 to this report. The cause of this finding was determined to have | ||
supervisory and management oversight of the activities (Section 2.1).*Green. | a crosscutting aspect in the area of human performance associated with work | ||
procedure. | -2- Enclosure 2 | ||
Generator 1-02 Panel, | |||
did not cause the responders to verify that the fuel racks were free as part of the | practices in that the licensee failed to provide adequate supervisory and | ||
response actions to investigate the cause of the unit failing to start. | management oversight of work activities, including contractors, such that nuclear | ||
Consequently, the licensee failed to identify that the Unit 1 Train B Emergency | safety is supported [H.4(c)]. Specifically, the actions planned and taken to | ||
Diesel Generator 1-02 fuel racks were not free to move, which led to an | assess and control the operational impact of the painting activities on the | ||
extended period of inoperability and a significant delay in diagnosing the cause | functionality of the emergency diesel generator were not reflective of adequate | ||
of the emergency diesel generator failure to start. | supervisory and management oversight of the activities (Section 2.1). | ||
the | * Green. The inspectors identified a noncited violation of Unit 1 Technical | ||
affected the cornerstone objective to ensure the availability, reliability, and | Specification 5.4.1.a, Procedures, for an inadequate alarm response | ||
capability of systems that respond to initiating events to prevent undesirable | procedure. The inspectors determined that Procedure ALM-1302A, Diesel | ||
consequences. | Generator 1-02 Panel, Revision 5, was inadequate in that it was ambiguous and | ||
Process, | did not cause the responders to verify that the fuel racks were free as part of the | ||
safety significance (Green) because it was not a design or qualification | response actions to investigate the cause of the unit failing to start. | ||
deficiency, did not represent a loss of safety function, did not represent an actual | Consequently, the licensee failed to identify that the Unit 1 Train B Emergency | ||
loss of a single train for greater than its Technical Specification allowed outage | Diesel Generator 1-02 fuel racks were not free to move, which led to an | ||
time, did not represent a loss of a non-Technical Specification Train of | extended period of inoperability and a significant delay in diagnosing the cause | ||
equipment for greater than 24 hours, and did not screen as potentially risk | of the emergency diesel generator failure to start. This issue was entered into | ||
significant due to a seismic, flooding, or severe weather initiating event | the licensees corrective action program as SMF-2007-03426. | ||
(Section 2.2).B.Licensee-Identified Violations | The finding was determined to be more than minor because it was associated | ||
None. | with the procedure quality attribute of the mitigating systems cornerstone, and it | ||
Enclosure 2 | affected the cornerstone objective to ensure the availability, reliability, and | ||
Emergency Diesel Generator (EDG) 1-02 to start on demand during a monthly | capability of systems that respond to initiating events to prevent undesirable | ||
surveillance test on November 21, 2007. | consequences. Using Manual Chapter 0609, Significance Determination | ||
troubleshooting, EDG 1-02 was restored to an operable status. | Process, Phase 1 Worksheet, the finding was determined to have very low | ||
Management Directive 8.3, it was determined that the period of inoperability of the EDG, | safety significance (Green) because it was not a design or qualification | ||
both prior to and during the failure to start event, had sufficient risk significance to | deficiency, did not represent a loss of safety function, did not represent an actual | ||
warrant a special inspection. | loss of a single train for greater than its Technical Specification allowed outage | ||
associated with the assumed period of EDG inoperability was estimated to be | time, did not represent a loss of a non-Technical Specification Train of | ||
1.76 x 10-5. | equipment for greater than 24 hours, and did not screen as potentially risk | ||
inspection. | significant due to a seismic, flooding, or severe weather initiating event | ||
(Section 2.2). | |||
B. Licensee-Identified Violations | |||
None. | |||
-3- Enclosure 2 | |||
REPORT DETAILS | |||
1.0 SPECIAL INSPECTION SCOPE | |||
The NRC conducted a special inspection at Comanche Peak Steam Electric Station to | |||
better understand the circumstances surrounding the failure of the Unit 1 Train B | |||
Emergency Diesel Generator (EDG) 1-02 to start on demand during a monthly | |||
surveillance test on November 21, 2007. Following approximately 11 hours of | |||
troubleshooting, EDG 1-02 was restored to an operable status. In accordance with NRC | |||
Management Directive 8.3, it was determined that the period of inoperability of the EDG, | |||
both prior to and during the failure to start event, had sufficient risk significance to | |||
warrant a special inspection. The initial incremental conditional core damage probability | |||
associated with the assumed period of EDG inoperability was estimated to be | |||
1.76 x 10-5. The possibility that adverse generic implications were associated with the | |||
EDG failure mechanism was the deterministic criterion met to warrant a special | |||
inspection. | |||
The team conducted the inspection in accordance with Inspection Procedure 93812, | |||
Special Inspection, and the inspection charter, which is included in this report as | |||
Attachment 2. The special inspection team reviewed procedures, corrective action | |||
documents, operator logs, and maintenance records for the EDG system. The team | |||
interviewed various licensee personnel regarding the events that led up to and response | |||
actions that followed the EDG failure, as well as design and operational characteristics | |||
of the EDG and its support systems. The team reviewed the licensees root cause | |||
analysis report, past failure records, extent of condition evaluation, immediate and long | |||
term corrective actions, and industry operating experience. A list of specific documents | |||
reviewed is provided in Attachment 1. | |||
1.1 Event Summary | |||
On November 21, 2007, at 10:20 a.m., EDG 1-02 failed to start on demand during a | |||
monthly slow start surveillance test. Prior to this, the last successful surveillance test on | |||
EDG 1-02 was on October 24, 2007. The licensees response to the failure to start is | |||
described in Section 1.2 below. Troubleshooting efforts were ultimately successful, and | |||
EDG 1-02 was restored to an operable status at 3:08 a.m. on November 22, 2007. The | |||
failure was determined to be the result of fuel racks being stuck in the closed positions, | |||
and not responding to a full open governor demand, thereby preventing sufficient fuel | |||
from reaching the engine. The failure mechanism is described in Section 1.4 below. | |||
The cause of the fuel rack binding was ultimately determined to be a drop of paint on a | |||
fuel rack which prevented the rack from being able to move through the fuel pump | |||
housing. The root and contributing causes of this failure are discussed on Section 1.3 | |||
below. | |||
Prior to the failed surveillance test on November 21, 2007, painting was conducted on | |||
and around EDG 1-02 and EDG 2-02 (Unit 2 Train B EDG). The painting activities | |||
associated with EDG 1-02 began on October 15, 2007, and continued through | |||
November 8, 2007. | |||
-4- Enclosure 2 | |||
Included below is a timeline that includes significant elements pertaining to this event. | |||
Date/Time Event | |||
October 15, 2007 Painting begins on EDG 1-02 on top of engine and around | |||
heads. | |||
October 15, 2007 - Painting activities continue on a daily basis. | |||
November 1, 2007 | |||
October 24, 2007 Successful monthly slow start surveillance test of EDG 1-02. | |||
No painting is done on this day. | |||
October 29, 2007 - Painting occurs around the 6L fuel pump. | |||
November 1, 2007 | |||
November 1, 2007 Painting in locations that could have reasonably resulted in | |||
stray paint/drops on fuel rack(s) is completed. | |||
November 21, 2007 EDG 1-02 declared inoperable due to bar over in preparation | |||
3:28 a.m. for monthly surveillance test. | |||
4:09 a.m. Bar over completed. Successful water roll via the air start | |||
system was completed. EDG 1-02 declared operable. | |||
10:17 a.m. EDG 1-02 declared inoperable for monthly surveillance test. | |||
10:20 a.m. EDG 1-02 failed to start on demand for monthly slow start | |||
surveillance test. Operations personnel believed the EDG did | |||
not roll. Troubleshooting commences. | |||
4:49 p.m. Slow start attempt of EDG 1-02 resulted in EDG rolling up to | |||
90-100 rpm and failing to start. Troubleshooting continues. | |||
6:02 p.m. Fast start attempt of EDG 1-02 resulted in a failure to start. | |||
Fuel racks were observed not to move in response to a | |||
governor demand. | |||
7:39 p.m. Fuel racks were manually stroked. Rack 6L was found to be | |||
stuck. Rack 2L moved approximately half of its travel range, | |||
then became bound. Both racks were freed and stroked until | |||
normal free range of motion was restored. | |||
9:25 p.m. Walkdown inspections revealed residual paint on 6L, 4L, and | |||
4R fuel racks. Residue of paint on 6L was wiped away. | |||
9:32 p.m. Successful start and run of EDG 1-02. | |||
November 22, 2007 EDG 1-02 was declared operable. | |||
3:08 a.m. | |||
-5- Enclosure 2 | |||
1.2 Licensee Response to the Failure of the EDG to Start | |||
The | The inspectors evaluated the licensees implementation of procedures (abnormal, alarm, | ||
troubleshooting, and normal operations) and Technical Specifications, reviewed plant | |||
managements control and decision making actions, and reviewed the troubleshooting | |||
and investigating activities that occurred following the Unit 1 Train B EDG failure to start | |||
during the monthly surveillance test on November 21, 2007. The inspectors reviewed | |||
corrective action documents, procedures, Technical Specifications, and operations logs. | |||
The team performed system walkdowns and interviewed engineering, maintenance, and | |||
operations personnel. | |||
The inspectors determined that, in general, the licensee responded to the event properly | |||
and in accordance with plant procedures. Nuclear equipment operators (NEO) quickly | |||
identified that the EDG 1-02 failed to start and immediately responded to the local EDG | |||
alarm panel. The operations field support supervisor performed an inspection to look for | |||
any obvious problems that could have caused the EDG to fail. NEOs noted that it did | |||
failure | not sound like a normal start, and assumed that a possible issue associated with the | ||
starting air system had something to do with the failure to start. The licensee had | |||
already declared the EDG inoperable prior to the attempted start in conjunction with the | |||
surveillance test. | |||
fuel | In response to the Unit Failure To Start alarm on the local EDG alarm panel, NEOs | ||
performed the steps of the local alarm panel procedure, Alarm Procedure | |||
Manual ALM-1302A, Diesel Generator 1-02 Panel, Revision 5, which instructed the | |||
operations personnel to investigate the cause of the failure. This included checking for | |||
proper operation and issues associated with the fuel racks, day tank, and the starting air | |||
system. One of the applicable steps was to check fuel racks free. This was | |||
accomplished in accordance with the expectations of senior operations personnel by | |||
visually verifying that there were no apparent conditions that would obstruct the motion | |||
not | of the fuel racks. No abnormalities were identified at this time. | ||
The operations staff reviewed drawings and diagrams, interviewed the NEOs, and | |||
consulted with meter and relay representatives, system engineering department | |||
personnel, and the mechanical services department to develop a troubleshooting plan. | |||
Due in large part to the testimony of the NEOs that the EDG did not even roll in | |||
response to the start attempt, the troubleshooting plan focused on the starting air | |||
system as the suspected cause of the failed start. The plan called for meter and relay | |||
personnel to monitor various solenoids and relays during a subsequent slow start | |||
attempt of the EDG. This attempt resulted in the EDG rolling up to 90-100 rpm, and | |||
again failing to start. Indications now suggested that a fuel-related problem must exist, | |||
and focus was shifted accordingly. A third attempt was performed with the EDG in a | |||
fast start configuration. Again, the EDG failed to start. Observers noted that the fuel | |||
racks did not move from their closed positions in response to the mechanical governors | |||
attempt to drive the fuel racks to the full open position. The licensee then attempted to | |||
exercise the fuel racks and metering rods individually and discovered that two metering | |||
not | rods (2L and 6L) were partially and fully bound, respectively. Licensee personnel | ||
physically exercised the metering rods until they were free to move, and removed | |||
evidence of paint that was found to be on the 6L metering rod by the fuel pump housing | |||
interface. The licensee then performed a fourth attempt to start EDG 1-02, which was | |||
-6- Enclosure 2 | |||
successful. The EDG was fully loaded, and operations personnel completed the | |||
surveillance testing. The EDG 1-02 was subsequently declared operable on the | |||
morning of November 22, 2007 at 3:08 a.m. | |||
The inspectors determined that the initial troubleshooting plan was too narrowly focused | |||
on finding an EDG starting air problem (despite a successful water roll via the air start | |||
system that occurred earlier that morning), as opposed to pursuing all likely causes of a | |||
failed start. If the focus of the response were broader, it is likely that the stuck metering | |||
rod would have been discovered earlier, and the duration of EDG inoperability following | |||
the failed start would have been reduced. | |||
Subsequently during the troubleshooting efforts, the joint engineering team developed a | |||
confirm and refute matrix to process the results from troubleshooting. Possible causes | |||
that were analyzed over the course of troubleshooting included: | |||
* Starting air receiver discharge valves mispositioned | |||
* Manual stop button mispositioned | |||
* Tachometers operational | |||
* Malfunctioning of air start solenoid valves | |||
* Mechanical governor bound | |||
* Fuel supply to the engine | |||
* Main control board handswitch | |||
* Electronic governor not operating | |||
* Fuel racks not functioning* | |||
*Determined to be the cause of the failure | |||
As described in Section 1.3 below, the Unit 2 Train B EDG was also in the process of | |||
being painted. Once the cause of EDG 1-02 inoperability was determined to be stuck | |||
metering fuel rods, the operations staff inspected the Unit 2 Train B EDG and | |||
determined that the same issue did not exist. Operations also inspected the Units 1 | |||
and 2 Train A EDGs and determined that the stuck metering rods issue did not exist. | |||
The Unit 1 Train B EDG was the only EDG affected. | |||
1.3 Root Cause and Corrective Action Assessment | |||
.1 Root Cause Analysis | |||
The inspectors reviewed and assessed the licensees root cause analysis for technique, | |||
accuracy, thoroughness, and corrective actions proposed and taken. The inspectors | |||
reviewed the scope and processes used by licensee personnel to identify the root cause | |||
for the failure of the Unit 1 Train B EDG to start during a monthly surveillance test. The | |||
inspectors compared information gained through inspection to the event information and | |||
assumptions made in the root cause reports. The inspectors interviewed licensee | |||
personnel, reviewed logs, reviewed personal statements, and observed root cause team | |||
meetings. The inspectors evaluated the licensees extent of condition review and | |||
common cause evaluation. | |||
-7- Enclosure 2 | |||
The licensee captured the EDG 1-02 failure to start problem in the corrective action | |||
program as SMF-2007-03253, and performed a root cause analysis in response to | |||
determine the cause of the failure. Evaluation techniques utilized by the licensee | |||
included an Events and Causal Factors Chart and a Barrier Analysis. The result of | |||
determine the cause of the failure. | |||
included an Events and Causal Factors Chart and a Barrier Analysis. | |||
these efforts identified the most probable root cause of the failure to be a drop of paint | these efforts identified the most probable root cause of the failure to be a drop of paint | ||
that was deposited and adhered to the 6L fuel rack in a location that prevented the rack | that was deposited and adhered to the 6L fuel rack in a location that prevented the rack | ||
(along with all other fuel racks) from moving in the open direction in response to the | (along with all other fuel racks) from moving in the open direction in response to the | ||
governor demand associated with an EDG start signal. | governor demand associated with an EDG start signal. This failure mechanism is | ||
further discussed in Section 1.4 below. | further discussed in Section 1.4 below. Although there was no documented evidence of | ||
the actual paint drop, there was paint residue observed which remained in the subject | the actual paint drop, there was paint residue observed which remained in the subject | ||
location following the manual manipulation and freeing of the stuck fuel rack during | location following the manual manipulation and freeing of the stuck fuel rack during | ||
troubleshooting. | troubleshooting. This residue was wiped off upon discovery. | ||
sensitive engine components.*The tools and techniques used by painters were not completely effective | Additionally, the following four contributing causes to the failure were identified in the | ||
the problem was extended.*The fuel control shaft break away force may have increased over time due | final root cause analysis: | ||
the adhesion of the paint drop.*This issue was also identified early in the inspection process by the inspectors and | * Work practices of painters and other groups who performed daily inspections | ||
were effective in considering and ruling out all other potential causes of the failure:*Electrical and control circuitry problems were investigated and ruled out. | failed to identify paint spatter and drops that should have been cleaned off | ||
over, the root cause team investigated other possibilities that could have caused | sensitive engine components. | ||
the EDG not to have rolled, and still brought in the alarms that were received. | * The tools and techniques used by painters were not completely effective in | ||
One viable possibility considered was a possible fault associated with the | preventing paint spatter and drips. | ||
piece of original equipment. | * *Because the directions in alarm response procedure ALM-1302A were not | ||
hand switch when the 6L fuel pump and metering rod was replaced after the | specific, the time period following the failure until the discovery of the cause of | ||
event. | the problem was extended. | ||
determined that the switch not only functioned properly without signs of | * The fuel control shaft break away force may have increased over time due to | ||
degradation, but it would not be physically possible to have the switch | wear and aging effects. This may have added to the force required to overcome | ||
Enclosure 2 | the adhesion of the paint drop. | ||
switch internals and reviewed the testing methods and results. | *This issue was also identified early in the inspection process by the inspectors and is | ||
concluded that the EDG start/stop control switch would not have caused the | further discussed in Section 2.2 below. | ||
EDG failure to start on November 21, 2007.*The starting air system was examined and proven to be functional. | The root cause team assessed that the engineering confirm/refute evaluation performed | ||
was performed satisfactorily.*The fuel day tank was inspected to ensure proper alignment and fuel quality. | during troubleshooting, along with the subsequent investigative actions outlined below, | ||
*Inspections of the joints that connect the fuel pump control shaft levers to | were effective in considering and ruling out all other potential causes of the failure: | ||
binding. | * Electrical and control circuitry problems were investigated and ruled out. Due to | ||
pump was determined not to be a cause of the event.*The capability of single paint drop to counter the force applied and prevent | the initial reports that the field operator did not believe that the EDG even rolled | ||
subjected to a series of field tests to determine the force required to overcome | over, the root cause team investigated other possibilities that could have caused | ||
the adhesion of a drop of paint in the location that had been identified. | the EDG not to have rolled, and still brought in the alarms that were received. | ||
results were consistent with the hypothesis that the force applied from the | One viable possibility considered was a possible fault associated with the EDG | ||
mechanical governor could have been overcome by the presence of the paint | Start/Stop hand switch in the control room. The hand switch in question was a | ||
drop becoming wedged in the minimal clearance between the fuel rack and the | piece of original equipment. One of the corrective actions was to replace the | ||
pump housing. | hand switch when the 6L fuel pump and metering rod was replaced after the | ||
various combinations of dirt and grit would not require appreciably more pull | event. The switch was bench tested, disassembled, and inspected, and it was | ||
tension to operate.Aspects of organizational and programmatic effectiveness were also evaluated by | determined that the switch not only functioned properly without signs of | ||
degradation, but it would not be physically possible to have the switch | |||
-8- Enclosure 2 | |||
manipulated to send a stop signal to the diesel while an operator takes the | |||
switch to the start position. The inspectors performed a visual inspection of the | |||
switch internals and reviewed the testing methods and results. The inspectors | |||
concluded that the EDG start/stop control switch would not have caused the | |||
EDG failure to start on November 21, 2007. | |||
* The starting air system was examined and proven to be functional. The | |||
inspectors confirmed this by performing system walkdowns. A water roll check | |||
was performed satisfactorily. | |||
* The fuel day tank was inspected to ensure proper alignment and fuel quality. | |||
* Inspections of the joints that connect the fuel pump control shaft levers to the | |||
fuel racks were performed, and determined that none were exhibiting mechanical | |||
binding. The inspectors confirmed this by performing a system walkdown. | |||
* The 6L fuel pump was replaced and sent to the vendor for testing, disassembly, | |||
and inspection. No abnormalities were identified, and internal binding of the | |||
pump was determined not to be a cause of the event. | |||
* The capability of single paint drop to counter the force applied and prevent the | |||
motion of the fuel control shafts was assessed. A spare fuel pump was | |||
subjected to a series of field tests to determine the force required to overcome | |||
the adhesion of a drop of paint in the location that had been identified. The | |||
results were consistent with the hypothesis that the force applied from the | |||
mechanical governor could have been overcome by the presence of the paint | |||
drop becoming wedged in the minimal clearance between the fuel rack and the | |||
pump housing. Another pull test was done to confirm that a fuel rack exposed to | |||
various combinations of dirt and grit would not require appreciably more pull | |||
tension to operate. | |||
Aspects of organizational and programmatic effectiveness were also evaluated by the | |||
root cause team, and confirmed by the inspectors. These included inadequate | |||
supervisory and management involvement with the painting activities, work practices | supervisory and management involvement with the painting activities, work practices | ||
employed during the job, and the less than comprehensive development of the | employed during the job, and the less than comprehensive development of the | ||
procedures and work packages associated with the activity.The extent of the condition that was determined to be the cause of the EDG 1-02 | procedures and work packages associated with the activity. | ||
The extent of the condition that was determined to be the cause of the EDG 1-02 failure | |||
was assessed by the root cause team. All other EDGs were thoroughly inspected to | |||
verify that the same condition did not exist, particularly with the Unit 2 Train B EDG 2-02, | verify that the same condition did not exist, particularly with the Unit 2 Train B EDG 2-02, | ||
which had been similarly painted in September and October. | which had been similarly painted in September and October. All other EDGs were | ||
verified to be free of the subject degraded condition. | verified to be free of the subject degraded condition. Emergency Diesel Generator 2-02 | ||
successfully passed its monthly surveillance test on November 28, 2007. | successfully passed its monthly surveillance test on November 28, 2007. The | ||
inspectors reviewed the | inspectors reviewed the licensees actions and concluded that the licensees extent of | ||
condition evaluation was adequate.The inspectors concluded, following interviews as well as a review of | condition evaluation was adequate. | ||
other work groups who performed daily paint clean-up inspections to identify paint | The inspectors concluded, following interviews as well as a review of personal | ||
Enclosure 2 | statements made by the maintenance personnel, that the work practices of painters and | ||
documentation nor feedback from the inspections to the painters or operations | other work groups who performed daily paint clean-up inspections to identify paint | ||
management regarding the results of those inspections was performed. | -9- Enclosure 2 | ||
communication of those results, to the right individuals, could have identified the need to | |||
reinforce expectations, alter paint methods or barriers, or institute a stand down that | spatter and drops that needed to be cleaned off of sensitive engine components was a | ||
may have led to the prevention of the event. | valid contributor to the event. The inspectors also determined that neither | ||
organizations (maintenance, inspection, operations, and management) was not as | documentation nor feedback from the inspections to the painters or operations | ||
strong as it could have been for this work on highly risk significant, safety-related | management regarding the results of those inspections was performed. The | ||
equipment.Along with the discussion above, the inspections that were performed as part of | communication of those results, to the right individuals, could have identified the need to | ||
the inspections nor any other applicable postmaintenance testing was specified by the | reinforce expectations, alter paint methods or barriers, or institute a stand down that | ||
work order for performing the painting activities. | may have led to the prevention of the event. At a minimum, communication between | ||
concerning foreign materials control exclusion (FME) controls. | organizations (maintenance, inspection, operations, and management) was not as | ||
significant issue with the licensee in the recent past, but no mention of this | strong as it could have been for this work on highly risk significant, safety-related | ||
having been done nor were any of the findings stemming from the inspections. The inspectors found that the licensee assembled an effective root cause team. | equipment. | ||
Unit 1 Train B EDG failed to start on November 21, 2007. | Along with the discussion above, the inspections that were performed as part of the | ||
that the scope, methods, and rigor associated with the root cause analysis were | postpainting activities were agreed upon between operations and maintenance. Neither | ||
appropriate and consistent with the safety significance of the problem, and that the | the inspections nor any other applicable postmaintenance testing was specified by the | ||
evaluation was successful in determining and addressing the most probable root and | work order for performing the painting activities. Also, there was no discussion | ||
contributing causes of this issue.. | concerning foreign materials control exclusion (FME) controls. FME has been a | ||
of the EDG 1-02 failure. | significant issue with the licensee in the recent past, but no mention of this sensitivity | ||
by the licensee were appropriate to address the degraded condition, to result in the | was made. The inspections that were performed were not documented anywhere as | ||
prevention of a future similar failure, and were consistent with the safety significance of | having been done nor were any of the findings stemming from the inspections. | ||
the event. | The inspectors found that the licensee assembled an effective root cause team. The | ||
be free of paint spatter/drops*Verify the information contained in the painting pre-job briefing book to ensure | root cause team investigated every lead that was available to determine exactly why the | ||
Enclosure 2 | Unit 1 Train B EDG failed to start on November 21, 2007. The inspectors determined | ||
components or block air pathways*Improve tools and techniques used by painters to minimize drops and spatter. Also research available FME barriers that could be used to shield sensitive | that the scope, methods, and rigor associated with the root cause analysis were | ||
*Develop a preventive maintenance activity to perform a fuel control shaft | appropriate and consistent with the safety significance of the problem, and that the | ||
bearings*Revise alarm response Procedure ALM-1302A to remove ambiguity | evaluation was successful in determining and addressing the most probable root and | ||
to include a manual manipulation of the | contributing causes of this issue. | ||
analysis, developed a scope of the mechanism that was determined to be the root | .2 Corrective Action Assessment | ||
cause of the EDG 1-02 failure. | The inspectors evaluated the scope, adequacy, and timeliness of the licensees | ||
prevented from moving from their normal standby (closed) positions in response to a | corrective measures that were both planned and implemented in response to the cause | ||
governor demand by the presence of a drop of paint that had adhered to the fuel rack in | of the EDG 1-02 failure. The inspectors concluded that the actions planned and taken | ||
a location where the rack enters the housing of the fuel pump (with very minimal | by the licensee were appropriate to address the degraded condition, to result in the | ||
clearance) when moving in the open direction. | prevention of a future similar failure, and were consistent with the safety significance of | ||
linked by the common fuel control shafts and cross shaft linkages, the motion of the | the event. Corrective actions to be taken prior to resuming painting activities include: | ||
entire system in the open direction (back to the extensible link from the mechanical | * Revise Procedure MSM-G0-0220 used for painting to require a shiftly | ||
governor) was inhibited by one fuel rack that was stuck in the standby (closed) position. | manipulation of the fuel racks in addition to a visual inspection of components to | ||
A torsion spring on the control shaft associated with each fuel pump control shaft lever | be free of paint spatter/drops | ||
functions to allow continued motion of the system in the closed direction if one or more | * Verify the information contained in the painting pre-job briefing book to ensure it | ||
individual fuel racks become bound. | contains all sensitive areas on the EDG that should not be painted | ||
for system motion in the open direction, as in the response to an EDG start signal.1. | * Revise Procedure MSM-G0-0220 to include pictures and other information | ||
corrective action documents and interviewed system engineers in order to identify any | contained in the painters prejob briefing book used during EDG painting | ||
previous related issues that may have been precursors to the Unit 1 Train B EDG failure | * Revise Procedure MSM-G0-0220 to provide for as you go inspections and | ||
to start. | cleaning when painting is done around sensitive components | ||
that fell into each of the following two categories: | -10- Enclosure 2 | ||
failures, and (2) Previous issues involving equipment failures related to painting. | |||
inspectors determined that there had been no previous EDG or painting related issues | * Include this event in prejob briefings for future activities to heighten sensitivity to | ||
that may have been precursors to this event. | the potential effects of paint spatter/drops in areas that can bind mechanical | ||
Enclosure 2 | components or block air pathways | ||
and schedules related to preventive maintenance and testing of the EDGs. | * Improve tools and techniques used by painters to minimize drops and spatter. | ||
inspectors also interviewed several system engineers to gain an understanding of the | Also research available FME barriers that could be used to shield sensitive areas | ||
Additional planned corrective actions include: | |||
inspectors determined that the | * Develop a preventive maintenance activity to perform a fuel control shaft break | ||
programs are adequate and that the licensee is following the program provisions. | away force test to monitor for potential degradation in the shaft linkage or | ||
However, the inspectors determined that these maintenance and testing practices for | bearings | ||
painting activities were not adequate as discussed in Section 2.0.1. | * Revise alarm response Procedure ALM-1302A to remove ambiguity regarding | ||
cause evaluation. | checking components for freedom of movement by providing specific instruction | ||
of pertinent OE materials discovered independently as well as with the assistance of the | to include a manual manipulation of the components | ||
1.4 Scope of the Failure Mechanism | |||
in response to relevant OE. | The inspectors, through inspection and investigation, interviews of system engineers, | ||
in Attachment 1 of this report.The inspectors determined that the licensee had appropriately reviewed | reviews of EDG design documentation, and assessment of the licensees root cause | ||
to incorporate applicable OE into station practices was not a contributing cause to the | analysis, developed a scope of the mechanism that was determined to be the root | ||
EDG failure. | cause of the EDG 1-02 failure. The fuel pump control racks (fuel metering rods) were | ||
licensee event reports (LERs). | prevented from moving from their normal standby (closed) positions in response to a | ||
applicable cases. | governor demand by the presence of a drop of paint that had adhered to the fuel rack in | ||
the exception of LERs. | a location where the rack enters the housing of the fuel pump (with very minimal | ||
not specifically the LER database. | clearance) when moving in the open direction. Since all fuel racks are mechanically | ||
available OE at the time that could have reasonably been obtained and reviewed.All of the OE pertaining to notification events of inoperable diesels due to | linked by the common fuel control shafts and cross shaft linkages, the motion of the | ||
inappropriate/movable components being painted). | entire system in the open direction (back to the extensible link from the mechanical | ||
into consideration when developing the work plan for painting of the EDGs in the | governor) was inhibited by one fuel rack that was stuck in the standby (closed) position. | ||
associated rooms. | A torsion spring on the control shaft associated with each fuel pump control shaft lever | ||
painting window, ensured that operations and maintenance personnel were | functions to allow continued motion of the system in the closed direction if one or more | ||
communicating, and developed a | individual fuel racks become bound. However, the feature does not provide this function | ||
as clear photographs of the areas and components not to paint. | for system motion in the open direction, as in the response to an EDG start signal. | ||
adequate for the knowledge that the plant had on site at the time. | 1.5 Event Precursors | ||
one paint drop in a specific, unintended location could render the EDG inoperable was | The root cause of the EDG failure to start was determined to be paint that was | ||
not considered by the licensee in their preparation and conduct of the EDG painting | inadvertently dropped onto a fuel pump metering rod. The inspectors reviewed | ||
activities, but this was not a subject of previous OE.One item that was not specifically incorporated into the procedures for painting the | corrective action documents and interviewed system engineers in order to identify any | ||
previous related issues that may have been precursors to the Unit 1 Train B EDG failure | |||
Enclosure 2 | to start. The inspectors reviewed all available documented issues dating back to 1999 | ||
The licensee employees were aware of the potential to make the EDG inoperable by | that fell into each of the following two categories: (1) Previous similar or related EDG | ||
painting activities, but did not get enough information to be as sensitive as necessary for | failures, and (2) Previous issues involving equipment failures related to painting. The | ||
their painting activities. | inspectors determined that there had been no previous EDG or painting related issues | ||
during the benchmarking trip to ask more questions, and then discovered that one plant | that may have been precursors to this event. | ||
had knowledge that very little paint or other foreign materials on the metering rods could | -11- Enclosure 2 | ||
render the EDG inoperable. | |||
if their staff were to have asked more probing questions, given the work that was | 1.6 EDG Maintenance and Testing | ||
planned at the site. | The inspectors reviewed the licensees EDG Maintenance and testing programs. The | ||
addressing operating experience associated with painting impacts on emergency diesel | inspectors reviewed maintenance and testing records as well as the licensees plans | ||
generator operability.1. | and schedules related to preventive maintenance and testing of the EDGs. The | ||
numerous licensee personnel and reviewed industry operating experience as well as | inspectors also interviewed several system engineers to gain an understanding of the | ||
NRC generic communications with the goal of identifying any potential generic issues | licensees approaches and programs involving EDG maintenance and testing. The | ||
that should be addressed as a result of the event.The inspection team concluded that, while painting activities occur at all plants, there | inspectors determined that the licensees EDG routine maintenance and testing | ||
The licensee has also issued an action in the corrective action program to issue an OE | programs are adequate and that the licensee is following the program provisions. | ||
report to INPO for future reference.2. | However, the inspectors determined that these maintenance and testing practices for | ||
LCO 3.8.1 in that painting activities conducted on the Unit 1 Train B EDG 1-02 resulted | painting activities were not adequate as discussed in Section 2.0. | ||
in paint being deposited and left in a location that caused the EDG to become | 1.7 Industry Operating Experience (OE) | ||
inoperable. | The inspectors reviewed the industry operating experience (OE) the licensee gained | ||
monthly surveillance test. | through their normal review, as well as that which was referenced in the licensees root | ||
actions were satisfied; however, the time period between the occurrence of the condition | cause evaluation. The inspectors conducted interviews of licensee personnel, reviews | ||
and the discovery of the condition exceeded the TS allowed outage time.Description: | of pertinent OE materials discovered independently as well as with the assistance of the | ||
was performed on October 24, 2007. | NRCs Operating Experience Section, and an evaluation of actions taken by the licensee | ||
2007. | in response to relevant OE. The specific documents reviewed during this review is listed | ||
the painting activities on and around EDG 1-02 and specified that painting was to be | in Attachment 1 of this report. | ||
performed per the requirements of Procedure MSM-G0-0220, | The inspectors determined that the licensee had appropriately reviewed and | ||
Revision 2. | incorporated OE associated with the circumstances of the EDG failure, and that a failure | ||
Enclosure 2 | to incorporate applicable OE into station practices was not a contributing cause to the | ||
of equipment and post-painting functional testing.5.1.1.2 | EDG failure. The inspectors reviewed several items of OE, inspection reports, and | ||
similar activities are recommended practices that should be employed when | licensee event reports (LERs). The inspectors reviewed the licensees responses to the | ||
painting equipment.Through interviews, the inspectors determined that representatives from | applicable cases. The licensee did have all of the OE in their OE review system, with | ||
discussed plans for verifying at the end of each day that the EDG remained operable. | the exception of LERs. The licensee reviews industry OE that comes from INPO and | ||
not specifically the LER database. It appeared that the licensee had accounted for all | |||
available OE at the time that could have reasonably been obtained and reviewed. | |||
All of the OE pertaining to notification events of inoperable diesels due to painting | |||
described gross painting errors that resulted in inoperable diesel generators (e.g., | |||
inappropriate/movable components being painted). The licensee did take those events | |||
into consideration when developing the work plan for painting of the EDGs in the | |||
associated rooms. The licensee held meetings well in advance of the scheduled | |||
painting window, ensured that operations and maintenance personnel were | |||
communicating, and developed a painters handbook that presented precautions as well | |||
as clear photographs of the areas and components not to paint. The preparation was | |||
adequate for the knowledge that the plant had on site at the time. The sensitivity that | |||
one paint drop in a specific, unintended location could render the EDG inoperable was | |||
not considered by the licensee in their preparation and conduct of the EDG painting | |||
activities, but this was not a subject of previous OE. | |||
One item that was not specifically incorporated into the procedures for painting the EDG | |||
was a specific postmaintenance test to be performed to prove operability. The | |||
licensees procedure described and recommended any of several postmaintenance | |||
-12- Enclosure 2 | |||
options, including visual inspections and equipment functionality tests. This procedure | |||
and its weaknesses were discussed as part of the root cause evaluation in Section 1.3. | |||
The licensee sent two of its employees (a system engineer and a painting supervisor) | |||
on a benchmarking trip prior to cleaning up, painting, and relamping the EDG Rooms. | |||
The licensee employees were aware of the potential to make the EDG inoperable by | |||
painting activities, but did not get enough information to be as sensitive as necessary for | |||
their painting activities. After the failed EDG start, the licensee called the plants visited | |||
during the benchmarking trip to ask more questions, and then discovered that one plant | |||
had knowledge that very little paint or other foreign materials on the metering rods could | |||
render the EDG inoperable. The licensee could have possibly obtained this information | |||
if their staff were to have asked more probing questions, given the work that was | |||
planned at the site. The inspectors concluded that the licensee was not fully effective in | |||
addressing operating experience associated with painting impacts on emergency diesel | |||
generator operability. | |||
1.8 Potential Generic Issues | |||
The inspection team evaluated the circumstances surrounding the event and assessed | |||
the root cause of the Unit 1Train B EDG failure to start. The team interviewed | |||
numerous licensee personnel and reviewed industry operating experience as well as | |||
NRC generic communications with the goal of identifying any potential generic issues | |||
that should be addressed as a result of the event. | |||
The inspection team concluded that, while painting activities occur at all plants, there are | |||
no specific generic concerns associated with this instance of procedural compliance. | |||
The licensee has also issued an action in the corrective action program to issue an OE | |||
report to INPO for future reference. | |||
2.0 SPECIAL INSPECTION FINDINGS | |||
2.1 Painting Activities Result in Inoperability of EDG | |||
Introduction: A White self-revealing violation of Unit 1 Technical Specification (TS) | |||
3.8.1, AC Sources - Operating, was identified for the licensees failure to satisfy TS | |||
LCO 3.8.1 in that painting activities conducted on the Unit 1 Train B EDG 1-02 resulted | |||
in paint being deposited and left in a location that caused the EDG to become | |||
inoperable. As a result, EDG 1-02 failed to start on demand during the subsequent | |||
monthly surveillance test. Following the discovery of the condition, the TS required | |||
actions were satisfied; however, the time period between the occurrence of the condition | |||
and the discovery of the condition exceeded the TS allowed outage time. | |||
Description: On October 15, 2007, the licensee commenced painting activities that | |||
occurred on and around EDG 1-02. A successful monthly slow start surveillance test | |||
was performed on October 24, 2007. Painting activities continued through November 1, | |||
2007. The inspectors reviewed Work Order (WO) 4-07-175968-00, which implemented | |||
the painting activities on and around EDG 1-02 and specified that painting was to be | |||
performed per the requirements of Procedure MSM-G0-0220, General Plant Painting, | |||
Revision 2. The inspectors noted that the WO did not contain requirements for | |||
-13- Enclosure 2 | |||
postmaintenance testing of the EDG, and that Procedure MSM-G0-0220, General Plant | |||
Painting, Revision 2, contained the following steps: | |||
NOTE: System engineer, operations, maintenance services or other | |||
departments may provide useful guidance in determining appropriate protection | |||
of equipment and post-painting functional testing. | |||
5.1.1.2 Painting conducted on equipment should be done in such a manner as | |||
to ensure paint does not bind components required to move. Prejob briefings, | |||
visual verification of postpainting operation, equipment functional testing or other | |||
similar activities are recommended practices that should be employed when | |||
painting equipment. | |||
Through interviews, the inspectors determined that representatives from the | |||
maintenance services, system engineering, maintenance, and operations departments | |||
discussed plans for verifying at the end of each day that the EDG remained operable. | |||
The above requirement and guidance of the general plant painting procedure was not | The above requirement and guidance of the general plant painting procedure was not | ||
referenced in this discussion. | referenced in this discussion. It was decided that a senior operations department | ||
personnel would perform a visual inspection at the end of each day to verify that | personnel would perform a visual inspection at the end of each day to verify that | ||
painting had not been done so as to affect the operability of the EDG. | painting had not been done so as to affect the operability of the EDG. This plan was | ||
understood and executed, but was not documented, nor were any inspection results | understood and executed, but was not documented, nor were any inspection results | ||
documented. | documented. Prejob briefs and postpainting inspections were focused on avoiding the | ||
painting of components that were not supposed to be painted and were appropriate and | painting of components that were not supposed to be painted and were appropriate and | ||
effective in that regard. | effective in that regard. However, appropriate sensitivity to the potential functional | ||
impact of stray drop(s) of paint in sensitive location(s) was not emphasized.On November 21, 2007, EDG 1-02 failed to start on demand during its next | impact of stray drop(s) of paint in sensitive location(s) was not emphasized. | ||
successfully started. | On November 21, 2007, EDG 1-02 failed to start on demand during its next monthly | ||
program as SMF-2007-003253-00. | surveillance test. Following approximately 11 hours of troubleshooting, EDG 1-02 was | ||
determine the cause of the failure. | successfully started. This issue was entered into the licensees corrective action | ||
program as SMF-2007-003253-00. The licensee performed a root cause analysis to | |||
determine the cause of the failure. The most likely cause of the failure was determined | |||
to be a paint drop that had been deposited on the 6L fuel rack that caused the rack to | to be a paint drop that had been deposited on the 6L fuel rack that caused the rack to | ||
become stuck. | become stuck. This prevented motion of all 16 fuel racks, thereby preventing the EDG | ||
from receiving sufficient fuel to run. | from receiving sufficient fuel to run. Corrective actions planned and taken by the | ||
licensee are discussed in Section 1.3 of this enclosure. Analysis: | licensee are discussed in Section 1.3 of this enclosure. | ||
not affected by the performance of scheduled maintenance activities. | Analysis: The performance deficiency associated with this finding involved the | ||
licensees failure to ensure that the assumed operability of safety-related equipment was | |||
not affected by the performance of scheduled maintenance activities. Specifically, | |||
painting was conducted on and around EDG 1-02 in such a manner that paint was | painting was conducted on and around EDG 1-02 in such a manner that paint was | ||
deposited and remained in a location that caused the EDG to become inoperable and | deposited and remained in a location that caused the EDG to become inoperable and | ||
fail to start on demand during a subsequent surveillance test. | fail to start on demand during a subsequent surveillance test. Postpainting verification | ||
of equipment functionality was inadequate. | of equipment functionality was inadequate. Consequently, the requirements of TS LCO | ||
3.8.1.b and the associated required TS Actions B.4 and G.1 and 2 were not met. | 3.8.1.b and the associated required TS Actions B.4 and G.1 and 2 were not met. The | ||
finding was greater than minor because it was associated with the human performance | finding was greater than minor because it was associated with the human performance | ||
attribute of the mitigating systems cornerstone, and it affected the cornerstone objective | attribute of the mitigating systems cornerstone, and it affected the cornerstone objective | ||
to ensure the availability, reliability, and capability of systems that respond to initiating | to ensure the availability, reliability, and capability of systems that respond to initiating | ||
events to prevent undesirable consequences. | events to prevent undesirable consequences. The Phase 1 Worksheets in Manual | ||
Chapter 0609, | Chapter 0609, Significance Determination Process, were used to conclude that a | ||
Enclosure 2 | -14- Enclosure 2 | ||
containment barrier systems. | |||
was determined to have low to moderate safety significance (White). | Phase 2 analysis was required because the performance deficiency affected the | ||
analyst determined that a more detailed Phase 3 analysis was needed to fully assess | emergency power supply system that is a support system for both mitigating and | ||
the safety significance. | containment barrier systems. Based on the results of the Phase 2 analysis, the finding | ||
determined to have low to moderate safety significance (White). | was determined to have low to moderate safety significance (White). The senior reactor | ||
significance determination process analyses associated with this finding, including | analyst determined that a more detailed Phase 3 analysis was needed to fully assess | ||
assumptions and limiting core damage sequences, is included as Attachment 3 to this | the safety significance. Based on the results of the Phase 3 analysis, the finding was | ||
report. | determined to have low to moderate safety significance (White). The Phase 1, 2, and 3 | ||
provide adequate supervisory and management oversight of work activities, including | significance determination process analyses associated with this finding, including | ||
contractors, such that nuclear safety is supported [H.4(c)]. | assumptions and limiting core damage sequences, is included as Attachment 3 to this | ||
planned and taken to assess and control the operational impact of the painting activities | report. The cause of this finding was determined to have a crosscutting aspect in the | ||
on the functionality of the EDG were not reflective of adequate supervisory and | area of human performance associated with work practices in that the licensee failed to | ||
management oversight of the activities.Enforcement: | provide adequate supervisory and management oversight of work activities, including | ||
capable of supplying the onsite Class 1E power distribution subsystem(s) shall be | contractors, such that nuclear safety is supported [H.4(c)]. Specifically, the actions | ||
operable. | planned and taken to assess and control the operational impact of the painting activities | ||
the DG to an operable status within 72 hours and within 6 days from the discovery of the | on the functionality of the EDG were not reflective of adequate supervisory and | ||
failure to meet the Limiting Condition for Operation (LCO), or be in Mode 3 within 6 | management oversight of the activities. | ||
hours and Mode 5 within 36 hours. | Enforcement: Unit 1 Technical Specification (TS) 3.8.1, AC Sources - Operating, | ||
through November 21, 2007, while the plant was in Mode 1, one of the two DGs capable | requires that while the plant is in Modes 1, 2, 3, or 4, two diesel generators (DGs) | ||
of supplying the onsite Class 1E power distribution subsystem(s) was inoperable, and | capable of supplying the onsite Class 1E power distribution subsystem(s) shall be | ||
action was not taken to either restore the DG to an operable status within 72 hours or be | operable. For the condition of one DG being inoperable, the required action is to restore | ||
in Mode 3 within 6 hours and Mode 5 within 36 hours. | the DG to an operable status within 72 hours and within 6 days from the discovery of the | ||
Generator (EDG) 1-02 was made inoperable as a result of painting activities due to paint | failure to meet the Limiting Condition for Operation (LCO), or be in Mode 3 within 6 | ||
having been deposited and remaining on at least one fuel rack in a location that | hours and Mode 5 within 36 hours. Contrary to the above, from November 1, 2007, | ||
prevented motion required to support the operation of the EDG. | through November 21, 2007, while the plant was in Mode 1, one of the two DGs capable | ||
EDG 1-02 to fail to start during a surveillance test on November 21, 2007. | of supplying the onsite Class 1E power distribution subsystem(s) was inoperable, and | ||
discovery of the condition on November 21, 2007, the licensee satisfied the TS required | action was not taken to either restore the DG to an operable status within 72 hours or be | ||
actions by restoring the EDG to an operable status on November 22, 2007. | in Mode 3 within 6 hours and Mode 5 within 36 hours. Specifically, Emergency Diesel | ||
violation is the subject of the enclosed Notice of Violation: | Generator (EDG) 1-02 was made inoperable as a result of painting activities due to paint | ||
having been deposited and remaining on at least one fuel rack in a location that | |||
inspectors determined that Procedure ALM-1302A, | prevented motion required to support the operation of the EDG. This condition caused | ||
Revision 5, was inadequate in that it was ambiguous and did not cause the responders | EDG 1-02 to fail to start during a surveillance test on November 21, 2007. Following the | ||
to verify that the fuel racks were free as part of the response actions to investigate the | discovery of the condition on November 21, 2007, the licensee satisfied the TS required | ||
cause of the unit failing to start. | actions by restoring the EDG to an operable status on November 22, 2007. This | ||
Unit 1 Train B EDG 1-02 fuel racks were not free to move, which led to an extended | violation is the subject of the enclosed Notice of Violation: VIO 05000445/2007008-01, | ||
period of inoperability and a significant delay in diagnosing the cause of the EDG failure | Painting Activities Result in Inoperability of Emergency Diesel Generator. | ||
to start. | 2.2 Inadequate Alarm Response Procedure for EDG Failure to Start | ||
Enclosure 2 | Introduction: The inspectors identified a Green noncited violation of Unit 1 Technical | ||
panel. | Specification 5.4.1.a, Procedures, for an inadequate alarm response procedure. The | ||
Generator 1-02 Panel, | inspectors determined that Procedure ALM-1302A, Diesel Generator 1-02 Panel, | ||
Failure To Start. | Revision 5, was inadequate in that it was ambiguous and did not cause the responders | ||
failure to start were indicated. | to verify that the fuel racks were free as part of the response actions to investigate the | ||
improper starting air alignment, failed timing chain, and a Governor malfunction.Operators implemented the | cause of the unit failing to start. Consequently, the licensee failed to identify that the | ||
to | Unit 1 Train B EDG 1-02 fuel racks were not free to move, which led to an extended | ||
period of inoperability and a significant delay in diagnosing the cause of the EDG failure | |||
to start. | |||
-15- Enclosure 2 | |||
Description: On November 21, 2007, at 10:20 a.m., EDG 1-02 failed to start during a | |||
slow start monthly surveillance test. Field operators responded to the EDG local alarm | |||
panel. Operators referenced the alarm response Procedure ALM-1302A, Diesel | |||
Generator 1-02 Panel, Revision 5, and reviewed the section for Alarm Window 6.6 Unit | |||
Failure To Start. A limited number of system malfunctions that could have caused the | |||
failure to start were indicated. These included fuel rack or fuel oil day tank issues, | |||
improper starting air alignment, failed timing chain, and a Governor malfunction. | |||
Operators implemented the Operator Actions section of the procedure, which included | |||
actions to determine the cause of the unit failing to start. The first action indicated was | |||
to Check fuel racks free and in max fuel position. The field support supervisor (senior | |||
reactor operator) believed that the appropriate action was to perform a visual inspection | reactor operator) believed that the appropriate action was to perform a visual inspection | ||
of the fuel racks. | of the fuel racks. The fuel racks were not in the "max fuel" position. The inspectors | ||
later determined that, following the majority of postulated failed start scenarios, the fuel | later determined that, following the majority of postulated failed start scenarios, the fuel | ||
racks would not be expected to remain in the "max fuel" position, even if they had | racks would not be expected to remain in the "max fuel" position, even if they had | ||
initially moved. | initially moved. In accordance with the operators' training, the expectation for | ||
performing this step was to visually inspect the racks. | performing this step was to visually inspect the racks. However, the inspectors | ||
determined that without observing them being in a position other than their normal | determined that without observing them being in a position other than their normal | ||
standby (closed) position, this visual check would not be sufficient to meet the intent of | standby (closed) position, this visual check would not be sufficient to meet the intent of | ||
the procedure step (i.e., to ensure that the racks were not stuck in the "no fuel" position, | the procedure step (i.e., to ensure that the racks were not stuck in the "no fuel" position, | ||
which was a probable failure cause that was indicated earlier in the procedure). | which was a probable failure cause that was indicated earlier in the procedure). The | ||
operator completed this procedure step, as well as subsequent steps for starting air | operator completed this procedure step, as well as subsequent steps for starting air | ||
alignment, EDG day tank alignment, and fuel quality with no abnormalities identified. | alignment, EDG day tank alignment, and fuel quality with no abnormalities identified. | ||
Field operator actions were completed at 11:05 a.m. | Field operator actions were completed at 11:05 a.m. | ||
not responding to the Governor demand to open. | The licensee developed a troubleshooting plan and attempted two more starts of the | ||
EDG (both unsuccessful) before determining that the fuel racks and metering rods were | |||
not responding to the Governor demand to open. At 7:39 p.m. the licensee exercised | |||
the fuel racks and discovered that two of the metering rods were stuck, with one fully | the fuel racks and discovered that two of the metering rods were stuck, with one fully | ||
stuck in the closed position and one which became partially stuck following some motion | stuck in the closed position and one which became partially stuck following some motion | ||
in the open direction. | in the open direction. Operations and maintenance performed followup inspections and | ||
successfully started the EDG at 9:32 p.m. | successfully started the EDG at 9:32 p.m. The diesel was declared operable following | ||
the surveillance run and post run inspections on November 22, 2007 at 3:08 a.m.The inspectors concluded that the field operators performed the actions of the | the surveillance run and post run inspections on November 22, 2007 at 3:08 a.m. | ||
and operations | The inspectors concluded that the field operators performed the actions of the alarm | ||
response Procedure ALM-1302A, in accordance with station procedures and training, | |||
and operations managements expectations. The inspectors further concluded that the | |||
inadequacy of the alarm response procedure to give clear instruction and guidance to | inadequacy of the alarm response procedure to give clear instruction and guidance to | ||
ensure that the EDG fuel racks were verified to be free and not binding resulted in | ensure that the EDG fuel racks were verified to be free and not binding resulted in | ||
missing an opportunity to identify the cause of the EDG failure to start in a timely | missing an opportunity to identify the cause of the EDG failure to start in a timely | ||
manner. | manner. This missed diagnosis not only led to a narrowly focused troubleshooting effort | ||
by the licensee, but also allowed the EDG to remain unnecessarily inoperable for | by the licensee, but also allowed the EDG to remain unnecessarily inoperable for | ||
approximately an additional 8.5 hours.Analysis: | approximately an additional 8.5 hours. | ||
response Procedure ALM-1302A. | Analysis: The performance deficiency associated with this finding involved the | ||
licensees failure to adequately establish clear procedure guidelines to implement alarm | |||
response Procedure ALM-1302A. This resulted in the licensees failure to identify the | |||
binding of the Unit 1 Train B EDG fuel racks and metering rods in a timely manner | binding of the Unit 1 Train B EDG fuel racks and metering rods in a timely manner | ||
following a failure to start. | following a failure to start. The finding was determined to be more than minor because | ||
Enclosure 2 | -16- Enclosure 2 | ||
reliability, and capability of systems that respond to initiating events to prevent | |||
undesirable consequences. | it was associated with the procedure quality attribute of the mitigating systems | ||
Process, | cornerstone, and it affected the cornerstone objective to ensure the availability, | ||
significance (Green) because it was not a design or qualification deficiency, did not | reliability, and capability of systems that respond to initiating events to prevent | ||
represent a loss of safety function, did not represent an actual loss of a single train for | undesirable consequences. Using Manual Chapter 0609, Significance Determination | ||
greater than its Technical Specification allowed outage time, did not represent a loss of | Process, Phase 1 Worksheet, the finding was determined to have very low safety | ||
a non-Technical Specification train of equipment for greater than 24 hours, and did not | significance (Green) because it was not a design or qualification deficiency, did not | ||
screen as potentially risk significant due to a seismic, flooding, or severe weather | represent a loss of safety function, did not represent an actual loss of a single train for | ||
initiating event.Enforcement: | greater than its Technical Specification allowed outage time, did not represent a loss of | ||
Guide 1.33, | a non-Technical Specification train of equipment for greater than 24 hours, and did not | ||
Section 5, for Abnormal, Off-Normal, or Alarm Conditions. | screen as potentially risk significant due to a seismic, flooding, or severe weather | ||
November 21, 2007, the licensee failed to adequately establish, implement, and | initiating event. | ||
maintain a procedure for an alarm condition. | Enforcement: Unit 1 Technical Specification 5.4.1.a requires that written procedures be | ||
Procedure ALM-1302A, | established, implemented, and maintained covering the procedures listed in Regulatory | ||
established and maintained, which resulted in the | Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, | ||
EDG 1-02 fuel racks and metering rods were bound and caused the failure of the EDG | Section 5, for Abnormal, Off-Normal, or Alarm Conditions. Contrary to the above, on | ||
to start on November 21, 2007. | November 21, 2007, the licensee failed to adequately establish, implement, and | ||
approximately 8.5 hours longer than necessary. | maintain a procedure for an alarm condition. Specifically, alarm response | ||
be of very low safety significance and has been entered in the | Procedure ALM-1302A, Diesel Generator 1-02 Panel, Revision 5, was not adequately | ||
action program as SMF-2007-003426, this violation is being treated as an NCV | established and maintained, which resulted in the licensees failure to recognize that the | ||
consistent with Section VI.A of the Enforcement Policy: | EDG 1-02 fuel racks and metering rods were bound and caused the failure of the EDG | ||
to start on November 21, 2007. Consequently, the EDG remained inoperable for | |||
Performance Manager, respectively, and other licensee personnel who acknowledged | approximately 8.5 hours longer than necessary. Because the finding was determined to | ||
the findings. | be of very low safety significance and has been entered in the licensees correction | ||
presented to Mr. F. Madden, Director, Regulatory Affairs, and other members of the | action program as SMF-2007-003426, this violation is being treated as an NCV | ||
licensee staff who acknowledged the findings. | consistent with Section VI.A of the Enforcement Policy: NCV 05000445/2007008-02, | ||
meeting was conducted with Mr. T. Hope and other licensee personnel who | Inadequate Alarm Response Procedure for EDG Failure to Start. | ||
acknowledged the findings. | 4OA6 Meetings, Including Exit | ||
retained during the inspection. | On December 7, 2007, and January 10, 2008, the results of this inspection were | ||
ATTACHMENT 3: | presented to Mr. R. Flores, Site Vice President, and Mr. T. Hope, Regulatory | ||
Performance Manager, respectively, and other licensee personnel who acknowledged | |||
the findings. Additionally on January 24, 2008, the final results of this inspection were | |||
presented to Mr. F. Madden, Director, Regulatory Affairs, and other members of the | |||
licensee staff who acknowledged the findings. On February 25, 2008, an additional exit | |||
meeting was conducted with Mr. T. Hope and other licensee personnel who | |||
acknowledged the findings. The inspectors confirmed that no proprietary material was | |||
retained during the inspection. | |||
ATTACHMENT 1: Supplemental Information | |||
ATTACHMENT 2: Special Inspection Charter | |||
ATTACHMENT 3: Significance Determination Evaluation | |||
-17- Enclosure 2 | |||
SUPPLEMENTAL INFORMATION | |||
KEY POINTS OF CONTACT | |||
Licensee Personnel | |||
J. Bain, System Engineer | |||
J. Bales, Maintenance Services | |||
T. Bennette, Operations | T. Bennette, Operations | ||
M. Blevins, Senior Vice President and Chief Nuclear Officer | M. Blevins, Senior Vice President and Chief Nuclear Officer | ||
| Line 645: | Line 982: | ||
J. Meyer, Technical Support Manager | J. Meyer, Technical Support Manager | ||
W. Morrison, Maintenance Smart Team Manager | W. Morrison, Maintenance Smart Team Manager | ||
J. | J. OQuinn, Maintenance | ||
W. Reppa, System Engineering Manager | W. Reppa, System Engineering Manager | ||
D. Scott, Root Cause Analyst | D. Scott, Root Cause Analyst | ||
| Line 655: | Line 992: | ||
W. Williams, Maintenance Services | W. Williams, Maintenance Services | ||
M. Wisdom, System Engineering | M. Wisdom, System Engineering | ||
NRC | |||
Attachment | D. Allen, Senior Resident Inspector | ||
Closed None Discussed | LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED | ||
MSM-G0- | Opened | ||
MSM-P0- | 05000445/2007008-01 VIO Painting Activities Result in Inoperability of Emergency | ||
Diesel Generator (Section 2.1) | |||
A1-1 Attachment 1 | |||
MSM-G0- | |||
MSM-G0- | Opened and Closed | ||
CMP-CV- | 05000445/2007008-02 NCV Inadequate Alarm Response Procedure for EDG Failure to | ||
Outside of Containment | Start (Section 2.2) | ||
Closed | |||
Attachment | None | ||
STA- | Discussed | ||
STA- | None | ||
TSP- | LIST OF DOCUMENTS REVIEWED | ||
Procedures | |||
NUMBER TITLE REVISION | |||
4-07-176582 | ALM-1302A Diesel Generator 1-02 Panel 5 | ||
4- | MSM-G0-0002 General Plant Painting 2 | ||
MSM-P0-3374 Emergency Diesel Generator Monthly Run Related 3 | |||
LER 07-004-00, | Inspections | ||
OPT-215-1 Offsite Transmission Network Operability Data Sheet 14 | |||
OWI-104-28 Plant Equipment Operator Diesel Generator 1-02 13 | |||
Operating Log | |||
OWI-104-26 Control Room Diesel Generator 1-02 Operating Log 11 | |||
MSM-G0-0216 Protective Coatings 23 | |||
MSM-G0-0217 Maintenance Protective Coatings-Concrete 0 | |||
MSM-G0-0218 Maintenance Protective Coatings-Steel 0 | |||
CMP-CV-1009 Application of Protective Coatings to Carbon Steel 0 | |||
Surfaces in the Containment and Radiation Areas | |||
Outside of Containment | |||
ODA-102 Conduct of Operations 24 | |||
ODA-401 Control of Annunciators, Instruments, and Protective 9 | |||
Relays | |||
ODA-407 Guidelines on Use of Procedures 12 | |||
A1-2 Attachment 1 | |||
OPT-214A Emergency Diesel Operability Test 19 | |||
SOP-609 Diesel Generator System 17 | |||
STA-426 Industry Operating Experience Program 1 | |||
STA-692 Protective Coatings Program 0 | |||
TSP-503 Emergency Diesel Generator Reliability Program 3 | |||
Smart Forms | |||
SMF-2007-03253 SMF-2007-03426 SMF-2007-03302 | |||
SMF-2007-02319 | |||
WOs | |||
4-07-176522 4-07-175968 4-07-176545 | |||
4-07-176543 4-07-176544 4-95-091357-00 | |||
5-05-501230-AA 4-07-176582 4-94-078722-00 | |||
5-07-502391-AK 4-07-175492 | |||
Miscellaneous Information | |||
Evaluation EVAL-2007-003253-02-00, Root Cause Analysis | |||
Post-Work Test Guide, Revision 12 | |||
LER 07-004-00, Emergency Diesel Generator Failed Surveillance Test Due to Paint on Fuel | |||
Injector Control Linkage | |||
TUElectric Office Memorandum, CPSES-9125952, October 10, 1991 | |||
TUElectric Office Memorandum, CPSES-9108929, April 3, 1991 | TUElectric Office Memorandum, CPSES-9108929, April 3, 1991 | ||
TUElectric Office Mamorandum, CPSES-91000861, January 11, 1991 | TUElectric Office Mamorandum, CPSES-91000861, January 11, 1991 | ||
Technical Evaluation TE# SE-90-1814 | Technical Evaluation TE# SE-90-1814 | ||
Cooper-Enterprise Clearinghouse R4/RV4 Preventative maintenance Program (PMP) | Cooper-Enterprise Clearinghouse R4/RV4 Preventative maintenance Program (PMP) for | ||
Attachment | Nuclear Standby Applications, Revision 0 | ||
Information | Operations Guideline 3, Attachment 4, Operations Department Alarm Response Expectations, | ||
August 2006 | |||
A1-3 Attachment 1 | |||
CPNPP Operations Logs, November 21-22, 2007 | |||
Amercoat 220, Waterborne Acrylic Topcoat Product Datasheet, circa 1999 | |||
Information Notices | |||
IN 93-76, Inadequate Control of Paint and Cleaners for Safety-Related Equipment | |||
IN 91-46, Degradation of Emergency Diesel Generator Fuel Oil Delivery Systems | |||
NRC Inspection Documents | |||
Inspection Procedure 93812, Special Inspection, 7/18/2007 | |||
Special Inspection Charter to Evaluate the Comanche Peak Steam Electric Station Diesel | |||
Generator Failure to Start Event, November 30, 2007 | |||
NRC Inspection Reports | |||
ML073060511 (RBS) | |||
SUBJECT:SPECIAL INSPECTION CHARTER TO EVALUATE THE | ML072040388 (DC Cook IR 05000316/2007004) | ||
TO START | LIST OF ACRONYMS | ||
You are hereby designated as the Special Inspection Team members. | ADAMS agency document and management system | ||
Resident Inspector, ANO, is designated as the team leader. | CFR Code of Federal Regulations | ||
team is David Loveless.A. | CPSES Comanche Peak Steam Electric Station | ||
licensee engineers developed a trouble shooting plan to determine the cause of the | EDG emergency diesel generator | ||
diesel failing to start. | FME foreign material exclusion | ||
that two fuel rack linkage/metering rods (L2 and L6) on DG-102 appeared to be binding. | INPO Institute of Nuclear Power Operations | ||
Additional inspections indicated that there were very small signs of paint on the metering | LER licensee event report | ||
rods for the L2 and L6 fuel pumps, but not enough to prevent movement. | NRC Nuclear Regulatory Commission | ||
activities in all EDG rooms were suspended until further measures were taken to prevent | OE operating experience | ||
reoccurrence of this issue. | PARS publicly available records system | ||
pump was manually operated by maintenance personnel and all but two moved freely. | NEO nuclear equipment operator | ||
Maintenance personnel were able to manually move, and subsequently free, the L2 and | SDP significance determination process | ||
L6 metering rods. | SMF smart form | ||
satisfactorily. | WO work order | ||
EDGs had free movement of all fuel rack linkage/metering rods.During further investigation into when painting had occurred inside the EDG room, it | A1-4 Attachment 1 | ||
successful surveillance test. | |||
been able to perform its intended function if called upon from October 24 to | November 30, 2007 | ||
November 21, 2007. | MEMORANDUM TO: Cale Young, Resident Inspector, ANO | ||
A2- | Alfred Sanchez, Resident Inspector, CPSES | ||
resolving these problems.B. | FROM: Arthur T. Howell III, Director, Division of Reactor Projects AVegel for/RA/ | ||
1.Develop a chronology (time-line) that includes significant event elements. | SUBJECT: SPECIAL INSPECTION CHARTER TO EVALUATE THE COMANCHE | ||
2.Evaluate the | PEAK STEAM ELECTRIC STATION DIESEL GENERATOR FAILURE | ||
Specifications.3.Assess the | TO START EVENT | ||
Evaluate whether the timeliness of the corrective measures are consistent with | A Special Inspection Team is being chartered in response to the Comanche Peak Steam | ||
the safety significance of the problem.4.Develop a complete scope of the failure mechanism identified by the | Electric Station emergency diesel generator (EDG) failure to start event on November 21, 2007. | ||
condition reviews for those problems.6.Evaluate the | You are hereby designated as the Special Inspection Team members. Mr. Cale Young, | ||
licensee actions taken in response to the operating experience.8.Determine if there are any potential generic issues related to the EDG failure | Resident Inspector, ANO, is designated as the team leader. The assigned SRA to support the | ||
Region IV management.9.Collect data as necessary to support a risk analysis. | team is David Loveless. | ||
A2- | A. Basis | ||
Procedure 93812. | On November 21, 2007, Comanche Peak Unit 1 diesel generator, DG-102, failed to start | ||
circumstances surrounding the event. | during the monthly surveillance test. After several failed attempts to start the diesel, | ||
the regulatory process. | licensee engineers developed a trouble shooting plan to determine the cause of the | ||
event should be reported to the Region IV office for appropriate action.The Team will report to the site, conduct an entrance, and begin inspection no later | diesel failing to start. During the trouble shooting efforts, licensee personnel identified | ||
management, who will coordinate with the Office of Nuclear Reactor Regulation, to | that two fuel rack linkage/metering rods (L2 and L6) on DG-102 appeared to be binding. | ||
ensure that all other parties are kept informed. | Additional inspections indicated that there were very small signs of paint on the metering | ||
the inspection should be issued within 30 days of the completion of the inspection.This Charter may be modified should the team develop significant new information | rods for the L2 and L6 fuel pumps, but not enough to prevent movement. Painting | ||
(817) 860-8148. | activities in all EDG rooms were suspended until further measures were taken to prevent | ||
reoccurrence of this issue. During the trouble shooting activities, each individual fuel | |||
1.Phase 1 Screening Logic, Results, and | pump was manually operated by maintenance personnel and all but two moved freely. | ||
deficiency. | Maintenance personnel were able to manually move, and subsequently free, the L2 and | ||
was associated with the equipment performance attribute and affected the mitigating | L6 metering rods. Operations personnel then performed the surveillance test | ||
systems cornerstone objective to ensure the availability, reliability, or function of a | satisfactorily. Maintenance personnel verified that the metering rods on the remaining | ||
system or train in a mitigating system in that Emergency Diesel Generator DG-102 | EDGs had free movement of all fuel rack linkage/metering rods. | ||
would not have started upon demand.The team evaluated this finding using the | During further investigation into when painting had occurred inside the EDG room, it was | ||
Chapter 0609, Appendix A, | discovered that the painters continued to paint in the diesel room after the last | ||
Findings for At-Power Situations. | successful surveillance test. This brings into question whether DG-102 would have | ||
because the performance deficiency affected the emergency power supply system that | been able to perform its intended function if called upon from October 24 to | ||
is a support system for both mitigating and containment barrier systems. | November 21, 2007. | ||
2.Phase 2 Risk | A2-1 Attachment 2 | ||
At-Power Situations, | |||
Risk-Informed Inspection Notebook for Comanche Peak Steam Electric Station, Units 1 | This Special Inspection Team is chartered to review the circumstances related to the | ||
and 2, Revision 2.01a. | failure of DG-102 to start, and to assess the effectiveness of the licensees actions for | ||
November 21, 2007.b.In accordance with Manual Chapter 0609, Appendix A, Attachment 2, | resolving these problems. | ||
Time, | B. Scope | ||
the risk of plant operations. | The team is expected to address the following: | ||
exposure time of t/2 from the last valid test was used. | 1. Develop a chronology (time-line) that includes significant event elements. | ||
between tests, or 14 days. | 2. Evaluate the licensees response to the failure of the EDG to start. Ensure that | ||
time used to represent the time that the performance deficiency affected plant | plant personnel responded in accordance with plant procedures and Technical | ||
risk was between 3 and 30 days. | Specifications. | ||
A3- | 3. Assess the licensees root cause determination for the EDG failure, the extent of | ||
are applicable: | condition review, the common cause evaluation and corrective measures. | ||
worksheets from the risk-informed notebook.d.According to the risk-informed notebook, Table 1, for a 3-30 day exposure, the initiating event likelihood should be 3 for a loss of offsite power and 5 for a loss | Evaluate whether the timeliness of the corrective measures are consistent with | ||
of offsite power with loss of one vital 6.9kV bus.e.The analyst gave no operator action credit as discussed in | the safety significance of the problem. | ||
Capability Credit. | 4. Develop a complete scope of the failure mechanism identified by the licensees | ||
trained the operators in recovery under similar conditions for such credit were not | root cause determination. | ||
met.The dominant sequences from the notebook were documented below:TABLE C. | 5. Identify previous EDG issues that may have been precursors to the November 1, | ||
2007, event. Evaluate the licensees corrective measures and extent of | |||
condition reviews for those problems. | |||
6. Evaluate the licensees EDG maintenance and testing programs. Verify that the | |||
analyst determined that this estimate did not include a full coverage of the risk | programs are adequate and that the licensee is following the program provisions. | ||
related to the failure identified and that a better evaluation of the internal risk | 7. Evaluate pertinent industry operating experience that represents potential | ||
would be necessary for fully assessing the risk related to external initiators. | precursors to the November 21, 2007, event, including the effectiveness of | ||
3.Phase 3 | licensee actions taken in response to the operating experience. | ||
Revision 3.31, dated August 2006, to simulate the failed Diesel Generator 1-02. | 8. Determine if there are any potential generic issues related to the EDG failure at | ||
Additionally, the analyst conducted an assessment of the risk contributions from external | Comanche Peak Unit 1. Promptly communicate any potential generic issues to | ||
initiators using insights and/or values provided by the | Region IV management. | ||
assessment model, in the | 9. Collect data as necessary to support a risk analysis. Work closely with the | ||
for diesel generators (Reference 1), and simplified fire probabilistic risk assessment.Reference 1: | Senior Reactor Analyst during this inspection. | ||
A2-2 Attachment 2 | |||
A3- | |||
C. Guidance | |||
not take actions to shed unnecessary loads from the vital dc buses. | Inspection Procedure 93812, Special Inspection, provides additional guidance to be | ||
value used in the | used by the Special Inspection Team. Your duties will be as described in Inspection | ||
around the diesel.D.Emergency Diesel Generator 1-02 successfully started and loaded during | Procedure 93812. The inspection should emphasize fact-finding in its review of the | ||
surveillance on November 21, 2007, because the fuel rack on at least one injection | circumstances surrounding the event. It is not the responsibility of the team to examine | ||
pump was bound to the extent that the entire fuel rack assembly was unable to leave | the regulatory process. Safety concerns identified that are not directly related to the | ||
the | event should be reported to the Region IV office for appropriate action. | ||
fail had to have been in place at that time for the root cause to be valid (See | The Team will report to the site, conduct an entrance, and begin inspection no later than | ||
Assumption C). F.The exposure time used for evaluating this finding should be determined | December 4, 2007. While on site, you will provide daily status briefings to Region IV | ||
Specific Risk-Informed Inspection Notebook Usage Rules. | management, who will coordinate with the Office of Nuclear Reactor Regulation, to | ||
the approach to establishing the exposure time that should be used for the | ensure that all other parties are kept informed. If information is discovered that shows a | ||
significance determination process. | more significant risk was associated with this issue, immediately contact Region IV | ||
known to have existed. | management for discussion of appropriate actions. A report documenting the results of | ||
exposure time of one half of the time period since the last successful | the inspection should be issued within 30 days of the completion of the inspection. | ||
demonstration of the component or function (t/2) should be used. | This Charter may be modified should the team develop significant new information that | ||
condition existed after the completion of painting activities on November 1, 2007. | warrants review. Should you have any questions concerning this Charter, contact me at | ||
A3- | (817) 860-8148. | ||
November 21, 2007.Additionally, the inception of the condition could have occurred any time | A2-3 Attachment 2 | ||
painting activities on November 1. | |||
Emergency Diesel Generator 1-02 would not have started upon demand for one | ATTACHMENT 3 | ||
half of the period from October 24 through November 1, or for an additional 4- | SIGNIFICANCE DETERMINATION EVALUATION | ||
day period.Based on these two arguments, the analyst determined that the | Comanche Peak Steam Electric Station | ||
assumed to have failed and one half the 8 day period that could have resulted in | EDG Inoperability Caused By Painting Activities | ||
the failure condition.H.Given the condition of the fuel rack and the interpretation by licensed operators | Significance Determination Basis | ||
Emergency Diesel Generator 1-02 prior to postulated core damage for sequences | 1. Phase 1 Screening Logic, Results, and Assumptions | ||
less than 2 hours. | In accordance with NRC Inspection Manual Chapter 0612, Appendix B, Issue | ||
procedure would not have directed operators to manipulate the fuel racks by hand | Screening, the team determined that this finding represented a licensee performance | ||
nor does it require operators to request maintenance personnel perform such a task.I.The appropriate nonrecovery probability for sequences longer than 2 hours is 0.29. The analyst conducted a human reliability analysis using the SPAR-H method to | deficiency. The team then determined that the issue was more than minor because it | ||
determine an appropriate nonrecovery probability. | was associated with the equipment performance attribute and affected the mitigating | ||
analyst used the following assumptions:a.The analyst assumed that nominal time was available for recovery diagnosis | systems cornerstone objective to ensure the availability, reliability, or function of a | ||
nonemergency conditions. Therefore, the analyst assumed that, if required, | system or train in a mitigating system in that Emergency Diesel Generator DG-102 | ||
recovery could have been reasonably performed within the 4 hour coping period | would not have started upon demand. | ||
plus extended boil down times.b.The analyst assumed that emergency response personnel would be under | The team evaluated this finding using the SDP Phase 1 Screening Worksheet for the | ||
that recovery personnel would know that the consequences of the task would | Initiating Events, Mitigating Systems, and Barriers Cornerstones, provided in Manual | ||
represent a direct threat to plant safety.c.The complexity of this task was considered to be nominal. | Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection | ||
diagnosis. | Findings for At-Power Situations. For this finding, a Phase 2 estimation was required | ||
taken into account in the performance shaping factor for procedure quality.d.Procedures for the diagnosis were incomplete. | because the performance deficiency affected the emergency power supply system that | ||
available in the annunciator response procedure, although it is not clear that this | is a support system for both mitigating and containment barrier systems. | ||
procedure would have been governing and/or utilized by the recovery personnel. | 2. Phase 2 Risk Estimation | ||
A3- | In accordance with Manual Chapter 0609, Appendix A, Attachment 1, User Guidance | ||
conducted on that diesel. | for Phase 2 and Phase 3 Significance Determination of Reactor Inspection Findings for | ||
probability at | At-Power Situations, the senior reactor analyst evaluated the subject finding using the | ||
Emergency Diesel Generator 1-02 would be handled separately, the analyst | Risk-Informed Inspection Notebook for Comanche Peak Steam Electric Station, Units 1 | ||
adjusted the generic nonrecovery value to account for only Emergency Diesel | and 2, Revision 2.01a. The following assumptions were made: | ||
Generator 1-01 being the only machine available for random failure recovery.L.The nominal likelihood for a loss of offsite power was unaffected by the | a. The identified performance deficiency occurred some time between the last | ||
The conditional core damage frequency (CCDFSEISMIC) given by the licensee was 2.1 x 10-6/year.N.The | successful test on October 24, 2007, and the test failure that occurred on | ||
November 21, 2007. | |||
posed by the analyst and included a larger scope of fires than was feasible for | b. In accordance with Manual Chapter 0609, Appendix A, Attachment 2, Site | ||
the analyst to evaluate.O.Traditionally, the initiation of most high wind events, including those that cause | Specific Risk-Informed Inspection Notebook Usage Rules, Rule 1.1, Exposure | ||
However, the | Time, the analyst determined the time frame over which the finding impacted | ||
risk. | the risk of plant operations. Because the exact time of failure was unknown, an | ||
(CCDFWIND) given the failure of a diesel generator to be 2.3 x 10 | exposure time of t/2 from the last valid test was used. This was 1/2 of the 28 days | ||
-5/year.P.The best estimate of the risk contribution from the subject finding related to | between tests, or 14 days. Therefore, for the phase 2 analysis, the exposure | ||
Reference 1. | time used to represent the time that the performance deficiency affected plant | ||
flooding derived from their internal events PRA was approximately 1 percent ( | risk was between 3 and 30 days. | ||
A3-1 Attachment 3 | |||
A3- | |||
were several global differences including: | c. Table 2 of the risk-informed notebook requires that when a performance | ||
diesel generators in the | deficiency affects the diesel generators, the following initiating event scenarios | ||
SPAR model. | are applicable: LOOP and LEAC. Therefore, the analyst utilized these | ||
consequence to this evaluation because the final results were within the same color | worksheets from the risk-informed notebook. | ||
band. Internal Initiating | d. According to the risk-informed notebook, Table 1, for a 3-30 day exposure, the | ||
initiating event likelihood should be 3 for a loss of offsite power and 5 for a loss | |||
of offsite power with loss of one vital 6.9kV bus. | |||
e. The analyst gave no operator action credit as discussed in Manual | |||
Chapter 0609, Appendix A, Attachment 1, Table 4, Remaining Mitigation | |||
Capability Credit. The requirements to have procedures in place and to have | |||
trained the operators in recovery under similar conditions for such credit were not | |||
met. | |||
The dominant sequences from the notebook were documented below: | |||
TABLE C.b | |||
Failure of Emergency Diesel Generator 102 to Start | |||
Phase 2 Sequences | |||
Initiating Event Sequence Mitigating Functions Results | |||
Loss of Offsite Power 2 LOOP-AFW-FB 8 | |||
4 LOOP-EAC-REC5 6 | |||
7 LOOP-EAC-TDAFW 6 | |||
Loss of Offsite Power with 1 LEAC-PORV-HPR-MKRWST 8 | |||
Loss of One Vital 6.9 kV Bus LEAC-PORV-HPI 7 | |||
3 | |||
Using the counting rule worksheet, the result from this estimation indicated that | |||
the finding was of low to moderate safety significance (WHITE). However, the | |||
analyst determined that this estimate did not include a full coverage of the risk | |||
related to the failure identified and that a better evaluation of the internal risk | |||
would be necessary for fully assessing the risk related to external initiators. | |||
3. Phase 3 Analysis | |||
In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3 | |||
analysis using the Standardized Plant Analysis Risk (SPAR) Model for Comanche Peak, | |||
Revision 3.31, dated August 2006, to simulate the failed Diesel Generator 1-02. | |||
Additionally, the analyst conducted an assessment of the risk contributions from external | |||
initiators using insights and/or values provided by the licensees probabilistic risk | |||
assessment model, in the licensees recent submittal for extension of completion times | |||
for diesel generators (Reference 1), and simplified fire probabilistic risk assessment. | |||
Reference 1: Letter dated November 15, 2007, Blevins to U.S. NRC, Subject: Comanche Peak Steam Electric Station (CPSES) | |||
Docket Nos. 50-445 and 50-446, Response to Request for Additional Information Related to Licence Amendment Request (LAR) 06-009, | |||
Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating; Extension of Completion Times for Diesel Generators. | |||
A3-2 Attachment 3 | |||
Assumptions | |||
To evaluate the change in risk caused by this performance deficiency, the analyst made | |||
the following assumptions: | |||
A. The vital batteries at Comanche Peak will deplete after approximately 4 hours of full | |||
postaccident loads without an operating battery charger, assuming that operators do | |||
not take actions to shed unnecessary loads from the vital dc buses. This is the | |||
value used in the licensees probabilistic risk assessment. | |||
B. The Comanche Peak SPAR model, Revision 3.31, represents an appropriate tool for | |||
evaluation of the subject finding. | |||
C. The failure of Emergency Diesel Generator 1-02 was the result of binding of the fuel | |||
rack on at least one injection pump that was caused by painting activities on and | |||
around the diesel. | |||
D. Emergency Diesel Generator 1-02 successfully started and loaded during a | |||
surveillance performed on October 24, 2007. The diesel failed to start during a | |||
surveillance on November 21, 2007, because the fuel rack on at least one injection | |||
pump was bound to the extent that the entire fuel rack assembly was unable to leave | |||
the no fuel position. | |||
E. Painting activities in and around the Emergency Diesel Generator 1-02 engine | |||
ended on November 1, 2007. Therefore, the conditions that caused the engine to | |||
fail had to have been in place at that time for the root cause to be valid (See | |||
Assumption C). | |||
F. The exposure time used for evaluating this finding should be determined in | |||
accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2, Site | |||
Specific Risk-Informed Inspection Notebook Usage Rules. Attachment 2 discusses | |||
the approach to establishing the exposure time that should be used for the | |||
significance determination process. Step 1.1 states: | |||
The exposure time used in determining the initiating event likelihood should | |||
correspond to the time period that the condition being assessed is reasonably | |||
known to have existed. If the inception of the condition is unknown, then an | |||
exposure time of one half of the time period since the last successful | |||
demonstration of the component or function (t/2) should be used. | |||
G. The appropriate exposure time (EXP), representing the time that Emergency Diesel | |||
Generator 1-02 was not functional, for use in this evaluation is 24 days. | |||
The exact time at which the residual paint that caused the binding of the fuel | |||
racks occurred is unknown. However, it is reasonable to assume that the | |||
condition existed after the completion of painting activities on November 1, 2007. | |||
A3-3 Attachment 3 | |||
Therefore, in accordance with Assumption F, Emergency Diesel Generator 1-02 | |||
would not have started upon demand for the 20 days November 1 through | |||
November 21, 2007. | |||
Additionally, the inception of the condition could have occurred any time between | |||
the last successful run of the machine on October 24 and the completion of the | |||
painting activities on November 1. Therefore, in accordance with Assumption F, | |||
Emergency Diesel Generator 1-02 would not have started upon demand for one | |||
half of the period from October 24 through November 1, or for an additional 4- | |||
day period. | |||
Based on these two arguments, the analyst determined that the appropriate | |||
exposure time was the sum of the 20 days that the machine was reasonably | |||
assumed to have failed and one half the 8 day period that could have resulted in | |||
the failure condition. | |||
H. Given the condition of the fuel rack and the interpretation by licensed operators of | |||
annunciator response procedures, operators would not have been able to recover | |||
Emergency Diesel Generator 1-02 prior to postulated core damage for sequences | |||
less than 2 hours. Licensed operators stated that the annunciator response | |||
procedure would not have directed operators to manipulate the fuel racks by hand | |||
nor does it require operators to request maintenance personnel perform such a task. | |||
I. The appropriate nonrecovery probability for sequences longer than 2 hours is 0.29. | |||
The analyst conducted a human reliability analysis using the SPAR-H method to | |||
determine an appropriate nonrecovery probability. To calculate this value, the | |||
analyst used the following assumptions: | |||
a. The analyst assumed that nominal time was available for recovery diagnosis and | |||
action. The licensee recovered the diesel in 11 hours 11 minutes during | |||
nonemergency conditions. Therefore, the analyst assumed that, if required, | |||
recovery could have been reasonably performed within the 4 hour coping period | |||
plus extended boil down times. | |||
b. The analyst assumed that emergency response personnel would be under high | |||
stress during the diagnosis and recovery. This is based primarily on the belief | |||
that recovery personnel would know that the consequences of the task would | |||
represent a direct threat to plant safety. | |||
c. The complexity of this task was considered to be nominal. There is some | |||
ambiguity in the diagnosis. However, there are only two fundamental paths in | |||
diagnosis. The probability that the wrong path would be initially investigated is | |||
taken into account in the performance shaping factor for procedure quality. | |||
d. Procedures for the diagnosis were incomplete. Solely following the procedures | |||
available would not have led to recovery. The basic items to consider were | |||
available in the annunciator response procedure, although it is not clear that this | |||
procedure would have been governing and/or utilized by the recovery personnel. | |||
A3-4 Attachment 3 | |||
e. All other performance shaping factors were considered nominal for obvious | |||
reasons. | |||
J. Emergency Diesel Generator 1-01 would not have failed from the same cause as | |||
Emergency Diesel Generator 1-02 because painting activities had not been | |||
conducted on that diesel. Therefore, the analyst left the common cause failure | |||
probability at its nominal value. | |||
K. The nominal nonrecovery values used by the SPAR model are for the average | |||
nonrecovery for either of two diesel generators. Therefore, given that recovery of | |||
Emergency Diesel Generator 1-02 would be handled separately, the analyst | |||
adjusted the generic nonrecovery value to account for only Emergency Diesel | |||
Generator 1-01 being the only machine available for random failure recovery. | |||
L. The nominal likelihood for a loss of offsite power was unaffected by the subject | |||
finding. | |||
M. Evaluating the risk contribution of this finding related to seismic events is | |||
appropriately conducted by utilizing the licensees assessment found in Reference 1. | |||
The conditional core damage frequency (CCDFSEISMIC) given by the licensee was | |||
2.1 x 10-6/year. | |||
N. The licensees fire risk model is an appropriate tool for evaluation of the subject | |||
finding. The CCDF for fire (CCDFFIRE) provided by the licensee in Reference 1 was | |||
7.8 x 10-6/year. | |||
The analyst independently evaluated the risk change related to internal fires. | |||
These insights were then used to challenge and evaluate the results of the | |||
licensees model. In all cases, the licensees model covered the scenarios | |||
posed by the analyst and included a larger scope of fires than was feasible for | |||
the analyst to evaluate. | |||
O. Traditionally, the initiation of most high wind events, including those that cause a | |||
loss of offsite power, are included in the licensees PRA and/or the SPAR model. | |||
However, the licensees assessment in their individual plant evaluation for external | |||
events did not include events that damage other pieces of equipment that may affect | |||
risk. As stated in Reference 1, the licensee estimated the CCDF for tornados | |||
(CCDFWIND) given the failure of a diesel generator to be 2.3 x 10-5/year. | |||
P. The best estimate of the risk contribution from the subject finding related to internal | |||
flooding is best evaluated using a ratio from the licensees PRA as was discussed in | |||
Reference 1. In their evaluation, the licensee stated that the risk from internal | |||
flooding derived from their internal events PRA was approximately 1 percent (PFLOOD) | |||
of the total plant core damage frequency. | |||
Q. The ratio of sequences going to core damage in the first 2 hours to those going | |||
through battery depletion is the same for internal and external initiators. This | |||
A3-5 Attachment 3 | |||
assumption permits the analyst to use the ratio from the internal events SPAR in | |||
applying recovery to external initiators. | |||
R. The differences between the SPAR and the licensees models were inconsequential. | |||
The analyst, in reviewing the differences between the models, determined that there | |||
were several global differences including: the lack of random failure recovery for | |||
diesel generators in the licensees model and the lack of convolution integrals in the | |||
SPAR model. However, the analyst determined that these differences were not of | |||
consequence to this evaluation because the final results were within the same color | |||
band. | |||
Internal Initiating Events | |||
The senior reactor analyst used the SPAR model for CPSES to estimate the change in | |||
risk associated with internal initiators that was caused by the finding. Average test and | |||
maintenance of modeled equipment was assumed and a cutset truncation of 1.0E-12 | maintenance of modeled equipment was assumed and a cutset truncation of 1.0E-12 | ||
was used.Consistent with guidance in the RASP Handbook, including NRC document, | was used. | ||
3.C, 3.G, and 3.K, the SRA modeled the condition by adjusting the following | Consistent with guidance in the RASP Handbook, including NRC document, | ||
Common-Cause Failure Analysis in Event Assessment (June 2007), and Assumptions | |||
3.C, 3.G, and 3.K, the SRA modeled the condition by adjusting the following basic | |||
-1 | events in the SPAR model: | ||
-1 EPS-XHE-XL-NR02H | Basic Event Original Value Conditional Value | ||
-1 | -3 | ||
-1 EPS-XHE-XL-NR03H | EPS-DGN-FS-1EG1 5.0 X 10 TRUE | ||
-1 | EPS-XHE-XL-NR01H 7.72 X 10-1 8.79 X 10-1 | ||
-1 EPS-XHE-XL-NR04H | EPS-XHE-XL-NR02H 6.48 X 10-1 8.05 X 10-1 | ||
-1 | EPS-XHE-XL-NR03H 5.56 X 10-1 7.46 X 10-1 | ||
EPS-XHE-XL-NR04H 4.84 X 10-1 6.95 X 10-1 | |||
The SPAR baseline core damage frequency (CDFBASE) was 1.80 x 10-5/year. The | |||
-5/year. | evaluation case for the above change set resulted in a conditional core damage | ||
frequency ( | frequency (CCDFSPAR) of 3.78 x 10-4/year. The dominant core damage sequences were | ||
documented in the table below: | |||
-4/year. | A3-6 Attachment 3 | ||
A3- | |||
combined with RCS Pump | Initiating Event Sequence Preponderant Failures Frequency | ||
Seal Failure . | Loss of Offsite 20-03 Failure of EDG 1-01 with 2.62 x 10-4/year | ||
Damage at 1 hour. | Power Battery Depletion at 4 hours | ||
Pumps and/or Operator Fails | 20-06 Failure of EDG 1-01 with 6.56 x 10-5/year | ||
to Control. | Battery Depletion at 4 hours | ||
combined with RCS Pump | |||
-4/year - | Seal Failure . | ||
-5/year= | 20-45 Failure of EDG 1-01 and the 2.37 x 10-5/year | ||
-4/ | Turbine-Driven Auxiliary | ||
the change in core damage frequency (CDFIntNR) caused by this finding, | Feedwater Pump with Core | ||
calculated as follows:CDFIntNR= | Damage at 1 hour. | ||
-4/year | 19 Failure of Motor and Turbine- 1.07 x 10-5/year | ||
Driven Auxiliary Feedwater | |||
in less than 2 hours. | Pumps and/or Operator Fails | ||
to Control. | |||
The change in incremental conditional core damage frequency (ICCDP) was calculated | |||
as follows: | |||
ICCDF = CCDFSPAR - CDFbase | |||
= 3.78 x 10-4/year - 1.80 x 10-5/year | |||
= 3.60 x 10-4/year | |||
Given Assumptions 3.C through 3.G, the exposure time, representing the time that the | |||
performance deficiency impacted the plant, for this analysis was 24 days. Therefore, | |||
the change in core damage frequency (CDFIntNR) caused by this finding, without | |||
applying any recovery to the subject condition, and related to internal initiators was | |||
calculated as follows: | |||
CDFIntNR = ICCDF * EXP | |||
= 3.60 x 10-4/year * (24 days ÷ 365 days/year) | |||
= 2.37 x 10-5 | |||
Given Assumption 3.H, the analyst determined that recovery credit for Emergency | |||
Diesel Generator 1-01 would not be provided for any sequence that led to core damage | |||
in less than 2 hours. Using utilities in the SAPHIRE software to slice cutsets by basic | |||
event, the analyst determined that 7.6 percent of all internal cutsets went to core | event, the analyst determined that 7.6 percent of all internal cutsets went to core | ||
damage in less than 2 hours ( | damage in less than 2 hours (PSHORT). | ||
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of 0.29 to all | |||
A3-7 Attachment 3 | |||
A3- | |||
-5 * 0.076] + [2.37 x 10 | remaining cutsets. Therefore, the change in core damage frequency (CDFInternal) | ||
-5 * (1 - 0.076) * 0.29]= | caused by this finding and related to internal initiators was calculated as follows: | ||
CDFInternal = [CDFIntNR * PSHORT] + [CDFIntNR * (1 - PSHORT) * PNR] | |||
= [2.37 x 10-5 * 0.076] + [2.37 x 10-5 * (1 - 0.076) * 0.29] | |||
= 8.15 x 10-6 | |||
External Initiating Events | |||
In accordance with Manual Chapter 0609, Appendix A, Attachment 1, Step 2.2.5, | |||
Screen for the Potential Risk Contribution Due to External Initiating Events, the analyst | |||
assessed the impact of external initiators on each of the findings, because the Phase 2 | assessed the impact of external initiators on each of the findings, because the Phase 2 | ||
SDP result provided a Risk Significance Estimation of 7 or greater. | SDP result provided a Risk Significance Estimation of 7 or greater. The analyst | ||
determined that, for the risk of an external initiator to be impacted by this performance | determined that, for the risk of an external initiator to be impacted by this performance | ||
deficiency, the external event would have to cause a loss of offsite power that was not | deficiency, the external event would have to cause a loss of offsite power that was not | ||
accounted for in the internal events model. | accounted for in the internal events model. Using the licensees individual plant | ||
evaluation for external events and Reference 1, the analyst determined that the | evaluation for external events and Reference 1, the analyst determined that the | ||
dominant sequences affected by the subject performance deficiency were from seismic | dominant sequences affected by the subject performance deficiency were from seismic | ||
events, high winds, fire, and internal flooding events.A.Seismic Event | events, high winds, fire, and internal flooding events. | ||
generator. | A. Seismic Event Initiators | ||
-6/year * (24 days | As discussed in Assumption 3.M, the analyst utilized the licensees value | ||
for the affects on the risk of seismic events associated with a failed diesel | |||
generator. The incremental risk without recovery (ICCDPSeisNR) was | |||
the change in core damage frequency (CDFSEISMIC) caused by | calculated as follows: | ||
-7 * 0.076] + [1.38 x 10 | ICCDPSeisNR = CCDFSEISMIC * EXP | ||
-7 * (1 - 0.076) * 0.29]= | = 2.1 x 10-6/year * (24 days ÷ 365 days/year) | ||
-8 | = 1.38 x 10-7 | ||
A3- | Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying | ||
generator. | the change in risk from seismic events. | ||
-6/year * (24 days | Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of | ||
0.29 to the remaining portion of the risk from seismic events. Therefore, | |||
the change in core damage frequency (CDFSEISMIC) caused by this | |||
the change in core damage frequency (CDFFIRE) caused by this | finding and related to seismic events was calculated as follows: | ||
-7 * 0.076] + [5.14 x 10 | CDFSEISMIC = [ICCDPSeisNR * PSHORT] + [ICCDPSeisNR * (1 - PSHORT) * PNR] | ||
-7 * (1 - 0.076) * 0.29]= | = [1.38 x 10-7 * 0.076] + [1.38 x 10-7 * (1 - 0.076) * 0.29] | ||
= 4.75 x 10-8 | |||
As discussed in Assumption 3.O, the analyst utilized the | A3-8 Attachment 3 | ||
diesel generator. | |||
-5/year * (24 days | B. Internal Fire Initiators | ||
As discussed in Assumption 3.N, the analyst utilized the licensees value | |||
for the affects on the risk of internal fires associated with a failed diesel | |||
Therefore, the change in core damage frequency (CDFWIND) caused | generator. The incremental risk without recovery (ICCDPFireNR) was | ||
A3- | calculated as follows: | ||
-6 * 0.076] + [1.38 x 10 | ICCDPFireNR = CCDFFIRE * EXP | ||
-6 * (1 - 0.076) * 0.29]= | = 7.8 x 10-6/year * (24 days ÷ 365 days/year) | ||
= 5.14 x 10-7 | |||
As discussed in Assumption 3.O, the analyst | Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying | ||
the change in risk from internal fires. | |||
value of 1 percent, the change in core damage frequency ( | Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of | ||
follows: | 0.29 to the remaining portion of the risk from seismic events. Therefore, | ||
the change in core damage frequency (CDFFIRE) caused by this finding | |||
change in core damage frequency (CDF) could be calculated by taking the sum | and related to seismic events was calculated as follows: | ||
follows:CDF= | CDFFIRE = [ICCDPFireNR * PSHORT] + [ICCDPFireNR * (1 - PSHORT) * PNR] | ||
-6 + [4.75 x 10 | = [5.14 x 10-7 * 0.076] + [5.14 x 10-7 * (1 - 0.076) * 0.29] | ||
-8 + 1.77 x 10 | = 1.77 x 10-7 | ||
-7 + 4.75 x 10 | C. Tornados and High Wind Initiators | ||
-7 + 8.15 x 10 | As discussed in Assumption 3.O, the analyst utilized the licensees value | ||
-8]= | for the affects on the risk of high wind events associated with a failed | ||
diesel generator. The incremental risk without recovery (ICCDFWindNR) | |||
was calculated as follows: | |||
ICCDPWindNR = CCDFWIND * EXP | |||
= 2.1 x 10-5/year * (24 days ÷ 365 days/year) | |||
= 1.38 x 10-6 | |||
Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying | |||
the change in risk from high wind events. | |||
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of | |||
0.29 to the remaining portion of the risk from high wind events. | |||
Therefore, the change in core damage frequency (CDFWIND) caused by | |||
this finding and related to seismic events was calculated as follows: | |||
A3-9 Attachment 3 | |||
CDFWIND = [ICCDPWindNR * PSHORT] + [ICCDPWindNR * (1 - PSHORT) * PNR] | |||
= [1.38 x 10-6 * 0.076] + [1.38 x 10-6 * (1 - 0.076) * 0.29] | |||
= 4.75 x 10-7 | |||
D. Internal Flooding Initiators | |||
As discussed in Assumption 3.O, the analyst utilized the ratio determined | |||
by the licensees PRA for internal flooding to other initiators. Given a | |||
value of 1 percent, the change in core damage frequency (CDFFLOOD) | |||
caused by this finding and related to internal flooding was calculated as | |||
follows: | |||
CDFFLOOD = CDFInternal * PFLOOD | |||
= 8.15 x 10-6 * 0.01 | |||
= 8.15 x 10-8 | |||
Total Change in Core Damage Frequency | |||
Given that each of the initiators in this analysis were treated to ensure that the final | |||
probabilities were independent of each other, the analyst determined that he total | |||
change in core damage frequency (CDF) could be calculated by taking the sum of | |||
each independent change. Therefore, the final Phase 3 result was calculated as | |||
follows: | |||
CDF = CDFInternal + CDFExternal | |||
= CDFInternal + [CDFSEISMIC + CDFFIRE + CDFWIND + CDFFLOOD] | |||
= 8.15 x 10-6 + [4.75 x 10-8 + 1.77 x 10-7 + 4.75 x 10-7 + 8.15 x 10-8] | |||
= 8.93 x 10-6 | |||
This result indicated that the finding was of low to moderate significance to the risk of | |||
internal initiating events. | |||
Large Early Release Frequency Contribution | |||
In accordance with Manual Chapter 0609, Appendix A, Attachment 1, Step 2.2.6, | |||
Screen for the Potential Risk Contribution Due to LERF, the analyst assessed the | |||
impact on the large early release frequency because the Phase 2 SDP result provided a | impact on the large early release frequency because the Phase 2 SDP result provided a | ||
risk significance estimation of greater than 7.Using NRC Inspection Manual Chapter 0609 Appendix H, | risk significance estimation of greater than 7. | ||
a Type A finding (i.e., a finding that can influence the likelihood of accidents leading to | Using NRC Inspection Manual Chapter 0609 Appendix H, Containment Integrity | ||
A3- | Significance Determination Process, the senior reactor analyst determined that this was | ||
a Type A finding (i.e., a finding that can influence the likelihood of accidents leading to | |||
A3-10 Attachment 3 | |||
core damage that is also a LERF contributor). For a pressurized water reactor with a | |||
large, dry containment, like Comanche Peak Steam Electric Station, findings related to | |||
inter-system loss-of-coolant accidents and steam generator tube ruptures have the | inter-system loss-of-coolant accidents and steam generator tube ruptures have the | ||
potential to impact LERF.Appendix H, Table 5.1, "Phase 1 Screening - Type A Findings at Full Power," | potential to impact LERF. | ||
initiators, screen out from further evaluation. | Appendix H, Table 5.1, "Phase 1 Screening - Type A Findings at Full Power," provides | ||
considered to be significant to LERF. | that station blackout scenarios and all other transients, including loss of offsite power | ||
-7. | initiators, screen out from further evaluation. These accident sequences are not | ||
-6 White/ | considered to be significant to LERF. Therefore, the estimated LERF was calculated | ||
to be less than 6.8 x 10-7. Because the LERF was less than the 1 x 10-6 White/Yellow | |||
threshold, the finding remains characterized as of low to moderate safety significance | |||
(White). | (White). | ||
A3-11 Attachment 3 | |||
}} | }} | ||
Revision as of 19:05, 14 November 2019
| ML080600164 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 02/29/2008 |
| From: | Collins E Region 4 Administrator |
| To: | Blevins M Luminant Generation Co |
| References | |
| EA-08-028 IR-07-008 | |
| Download: ML080600164 (42) | |
See also: IR 05000445/2007008
Text
February 29, 2008
Mike Blevins, Senior Vice President
and Chief Nuclear Officer
Luminant Generation Company, LLC
ATTN: Regulatory Affairs
Comanche Peak Steam Electric Station
P.O. Box 1002
Glen Rose, TX 76043
SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND
NOTICE OF VIOLATION - COMANCHE PEAK STEAM ELECTRIC STATION -
NRC SPECIAL INSPECTION REPORT 05000445/2007008
Dear Mr. Blevins:
On January 24, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed its reviews
related to a Special Inspection at your Comanche Peak Steam Electric Station, Unit 1, facility.
This Special Inspection Team was chartered to review the circumstances related to the failure
of Emergency Diesel Generator (EDG) 1-02 to start on November 21, 2007, and to evaluate the
actions taken in response to the problem. The NRC's initial evaluation satisfied the criteria in
NRC Management Directive 8.3, NRC Incident Investigation Program, for conducting a special
inspection. The possibility that adverse generic implications were associated with the EDG
failure mechanism was the deterministic criterion met. Additionally, the result of the NRCs
initial conditional risk assessment associated with this degraded condition indicated that a
special inspection was warranted. The determination that the inspection would be conducted
was made by the NRC on November 30, 2007, and the inspection started on December 4,
2007.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
The enclosed inspection report documents the inspection results, which were discussed on
December 7, 2007, and again on January 10, 2008, with Mr. R. Flores and Mr. T. Hope,
respectively, and other members of your staff. On January 24, 2008, an exit meeting was held
with Mr. F. Madden, Director, Regulatory Affairs, and other members of your staff to convey the
Luminant Generating Company, LLC -2-
final disposition of the inspection findings. Following a discussion of the preliminary safety
significance of this finding during the exit briefing, Mr. Madden indicated that Luminant Power
does not contest the characterization of the risk significance of this finding, and that you have
declined to further discuss this issue at a Regulatory Conference or provide a written response.
Accordingly, the NRC is issuing the final significance determination for the inspection finding as
discussed below. On February 25, 2008, an additional exit meeting was held with Mr. T. Hope,
and other members of your staff to convey a revision to one of the inspection findings.
This report documents one finding concerning a failure to satisfy Technical Specification (TS)
Limiting Condition for Operation (LCO) 3.8.1 due to EDG 1-02 being in an inoperable condition
following maintenance. Following the discovery of this condition, the TS required actions were
satisfied however, the time period between the occurrence of the condition and the discovery of
the condition exceeded the TS allowed outage time for the EDG. This finding has been
determined to be of low to moderate safety significance (White). This finding does not
represent an immediate safety concern because of the corrective actions you have taken.
These actions included restoring EDG 1-02 to an operable status, ensuring that all other EDGs
were not in a similar degraded condition, and curtailing painting activities pending the
implementation of suitable measures to prevent the recurrence of a similar condition.
You have 30 calendar days from the date of this letter to appeal the NRCs determination of
significance for the identified White finding. Such appeals will be considered to have merit only
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Attachment 2. In
accordance with the NRC Enforcement Policy, the Notice of Violation is considered an
escalated enforcement action because it is associated with a White finding.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response.
In addition, we will use the NRC Action Matrix to determine the most appropriate NRC response
to this issue, and we will notify you by separate correspondence of that determination.
The report also documents one NRC-identified finding of very low safety significance (Green).
This finding was determined to involve a violation of NRC requirements. However, because of
the very low safety significance and because it is entered into your corrective action program,
the NRC is treating the finding as a noncited violation (NCV) consistent with Section VI.A.1 of
the NRC Enforcement Policy. If you contest this NCV, you should provide a response within
30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear
Regulatory Commission, ATTN.: Document Control Desk, Washington, DC 20555-0001; with
copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611
Ryan Plaza Drive, Suite 400, Arlington, Texas 76011-4005; the Director, Office of Enforcement,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident
Inspector at the Comanche Peak Steam Electric Station.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its
enclosure, and your response (if any) will be available electronically for public inspection in the
Luminant Generating Company, LLC -3-
NRC Public Document Room or from the Publicly Available Records (PARS) component of
NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). To the
extent possible, your response should not include any personal privacy, proprietary, or
safeguards information so that it can be made available to the public without redaction.
Sincerely,
/RA/
Elmo E. Collins
Regional Administrator
Dockets: 50-445
Licenses: NPF-87
Enclosures:
2. NRC Inspection Report 05000445/2007008
w/Attachments
Attachment 1: Supplemental Information
Attachment 2: Special Inspection Charter
Attachment 3: Significance Determination Evaluation
cc w/enclosures:
Fred W. Madden, Director
Regulatory Affairs
Luminant Generation Company LLC
P.O. Box 1002
Glen Rose, TX 76043
Timothy P. Matthews, Esq.
Morgan Lewis
1111 Pennsylvania Avenue, NW
Washington, DC 20004
Anthony Jones, Chief Boiler Inspector
Texas Department of Licensing
and Regulation
Boiler Program
P.O. Box 12157
Austin, TX 78711
Somervell County Judge
P.O. Box 851
Glen Rose, TX 76043
Luminant Generating Company, LLC -4-
Richard A. Ratliff, Chief
Bureau of Radiation Control
Texas Department of Health
1100 West 49th Street
Austin, TX 78756-3189
Environmental and Natural
Resources Policy Director
Office of the Governor
P.O. Box 12428
Austin, TX 78711-3189
Brian Almon
Public Utility Commission
William B. Travis Building
P.O. Box 13326
Austin, TX 78711-3326
Susan M. Jablonski
Office of Permitting, Remediation
and Registration
Texas Commission on
Environmental Quality
MC-122
P.O. Box 13087
Austin, TX 78711-3087
Environmental and Natural
Resources Policy Director
Office of the Governor
P.O. Box 12428
Austin, TX 78711-3189
Lisa R. Hammond, Chief
Technological Hazards Branch
National Preparedness Division
FEMA Region VI
800 N. Loop 288
Denton, TX 76209
Luminant Generating Company, LLC -5-
Electronic distribution:
ROPreports
RIDSSECYMAILCENTER RIDSOCAMAILCENTER
RIDSEDOMAILCENTER RIDSOEMAILCENTER
RIDSOGCMAILCENTER RIDSNRROD
RIDSNRRADIP RIDSOPAMAIL
RIDSOIMAILCENTER RIDSOIGMAILCENTER
RIDSOCFOMAILCENTER RIDSRGN1MAILCENTER
RIDSRGN2MAILCENTER RIDSRGN3MAILCENTER
RIDSNRRDIPMIIPB OEWEB
ECollins AHowell Fuller - KSF
C Maier Vasquez - GMV D Furst, NSIR
Vegel - AXV Chamberlain - DDC N Hilton, OE
Caniano - RJC1 Powers - DAP June Cai, OE
ACampbell - ACC CJohnson - CEJ1 John Wray, OE
DLoveless - DPL DAllen - DBA ASanchez - AAS1
Herrera - MSH3 SSanner - ESS Starkey, OE - DRS
Mary Ann Ashley, NRR Paulk -CJP M Burrell, OE
Dricks - VLD WMaier - WAM R Barnes, OE
DPowers - DAP DPelton - DLP1
SUNSI Review Completed: CEJ ADAMS: / Yes G No Initials: CEJ
/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive
R:\_REACTORS\_CPSES\2007\CP2007-08 CHY.wpd ADAMS ML080600164
RIV:RI:DRP/E SRI:DRP/E SRA C:DRP/A SES/ACES
CHYoung:vlh;mjs AASanchez DPLoveless CEJohnson GMVasquez
E-CEJ E-CEJ /RA/ /RA/ /RA/
1/31/08 2/08/08 2/08/08 2/12/08 2/11/08
RJCaniano DDChamberlain KSFuller ATHowell EECollins
/RA/ /RA/ /RA/ /RA/ /RA/
2/11/08 2/21/08 2/14/08 2/22/08 2/28/08
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Luminant Generation Company, LLC Docket No. 50-445
Comanche Peak Steam Electric Station License No. NPF-87
During an NRC inspection completed on January 24, 2008, a violation of NRC requirements
was identified. In accordance with the NRC Enforcement Policy, the violation is listed below:
Unit 1 Technical Specification (TS) 3.8.1, AC Sources - Operating, requires that while
the plant is in Modes 1, 2, 3, or 4, two diesel generators (DGs) capable of supplying the
onsite Class 1E power distribution subsystem(s) shall be operable. For the condition of
one DG being inoperable, the required action is to restore the DG to an operable status
within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and within 6 days from the discovery of the failure to meet the Limiting
Condition for Operation (LCO), or be in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Mode 5 within 36
hours.
Contrary to the above, from November 1, 2007, through November 21, 2007, while the
plant was in Mode 1, one of the two DGs capable of supplying the onsite Class 1E
power distribution subsystem(s) was inoperable, and action was not taken to either
restore the DG to an operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and
Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Specifically, Emergency Diesel Generator (EDG) 1-02 was
made inoperable as a result of painting activities due to paint having been deposited and
remaining on at least one fuel rack in a location that prevented motion required to
support the operation of the EDG. This condition caused EDG 1-02 to fail to start during
a surveillance test on November 21, 2007.
This violation is associated with a White significance determination process finding.
Pursuant to the provisions of 10 CFR 2.201, Luminant Generation Company, LLC is hereby
required to submit a written statement or explanation to the U.S. Nuclear Regulatory
Commission, ATTN.: Document Control Desk, Washington, DC 20555-0001 with a copy to the
Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the facility that
is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of
Violation (Notice). This reply should be clearly marked as a Reply to a Notice of Violation;
EA-08-028, and should include for each violation: (1) the reason for the violation, or, if
contested, the basis for disputing the violation or severity level; (2) the corrective steps that
have been taken and the results achieved; (3) the corrective steps that will be taken to avoid
further violations and (4) the date when full compliance will be achieved. Your response may
reference or include previous docketed correspondence, if the correspondence adequately
addresses the required response. If an adequate reply is not received within the time specified
in this Notice, an order or a Demand for Information may be issued as to why the license should
Enclosure 1
not be modified, suspended, or revoked, or why such other action as may be proper should not
be taken. Where good cause is shown, consideration will be given to extending the response
time.
If you contest this enforcement action, you should also provide a copy of your response, with
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, DC 20555-0001.
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS), accessible from the
NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should
not include any personal privacy, proprietary, or safeguards information so that it can be made
available to the public without redaction. If personal privacy or proprietary information is
necessary to provide an acceptable response, then please provide a bracketed copy of your
response that identifies the information that should be protected and a redacted copy of your
response that deletes such information. If you request withholding of such material, you must
specifically identify the portions of your response that you seek to have withheld and provide in
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will
create an unwarranted invasion of personal privacy or provide the information required by
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial
information). If safeguards information is necessary to provide an acceptable response, please
provide the level of protection described in 10 CFR 73.21.
Dated this 29th day of February 2008.
-2- Enclosure 1
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Dockets: 50-445
Licenses: NPF-87
Report: 05000445/2007008
Licensee: Luminant Generation Company, LLC
Facility: Comanche Peak Steam Electric Station, Unit 1
Location: FM-56, Glen Rose, Texas
Dates: December 4, 2007, through January 24, 2008
Team Leader: C. Young, P.E., Resident Inspector, Arkansas Nuclear One
Inspectors: A. Sanchez, Resident Inspector, Comanche Peak Steam Electric Station
D. Loveless, Senior Reactor Analyst
Branch Chief: C. Johnson, Chief, Project Branch A
Division of Reactor Projects
Approved By: D. Chamberlain, Director
Division of Reactor Projects
SUMMARY OF FINDINGS
IR 05000445/2007008; 12/04/07 - 01/24/08; Comanche Peak Steam Electric Station (CPSES),
Unit 1; Special Inspection in response to the failure of the Train B Emergency Diesel Generator
to start on demand on November 21, 2007.
The report covered a 6-day period (December 4-7, 2007) of onsite inspection, with inoffice
review through January 24, 2008, by a special inspection team consisting of two resident
inspectors and one senior reactor analyst. Two findings were identified, including one Green
noncited violation, and one White violation. The significance of most findings is indicated by its
color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance
Determination Process. Findings for which the significance determination process does not
apply may be Green or be assigned a severity level after NRC management review. The
NRC's program for overseeing the safe operation of commercial nuclear power reactors is
described in NUREG-1649, Reactor Oversight Process, Revision 4, dated July 2000.
A. NRC-Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
- White. A violation of Unit 1 Technical Specification 3.8.1, AC Sources -
Operating, was identified for the licensees failure to satisfy Limiting Condition
for Operation 3.8.1 in that painting activities conducted on the Unit 1 Train B
EDG 1-02 resulted in paint being deposited and left in a location that caused the
EDG to become inoperable. As a result, EDG 1-02 failed to start on demand
during the subsequent monthly surveillance test. Following the discovery of the
condition, the required actions were satisfied; however, the time period between
the occurrence of the condition and the discovery of the condition exceeded the
allowed outage time. This issue was entered into the licensees corrective action
program as SMF-2007-03253.
The finding was greater than minor because it was associated with the human
performance attribute of the mitigating systems cornerstone, and it affected the
cornerstone objective to ensure the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences.
The Phase 1 Worksheets in Manual Chapter 0609, Significance Determination
Process, were used to conclude that a Phase 2 analysis was required because
the performance deficiency affected the emergency power supply system that is
a support system for both mitigating and containment barrier systems. Based on
the results of the Phase 2 analysis, the finding was determined to have low to
moderate safety significance (White). The senior reactor analyst determined
that a more detailed Phase 3 analysis was needed to fully assess the safety
significance. Based on the results of the Phase 3 analysis, the finding was
determined to have low to moderate safety significance (White). The Phase 1,
2, and 3 Significance Determination Process analyses associated with this
finding, including assumptions and limiting core damage sequences, is included
as Attachment 3 to this report. The cause of this finding was determined to have
a crosscutting aspect in the area of human performance associated with work
-2- Enclosure 2
practices in that the licensee failed to provide adequate supervisory and
management oversight of work activities, including contractors, such that nuclear
safety is supported H.4(c). Specifically, the actions planned and taken to
assess and control the operational impact of the painting activities on the
functionality of the emergency diesel generator were not reflective of adequate
supervisory and management oversight of the activities (Section 2.1).
- Green. The inspectors identified a noncited violation of Unit 1 Technical
Specification 5.4.1.a, Procedures, for an inadequate alarm response
procedure. The inspectors determined that Procedure ALM-1302A, Diesel
Generator 1-02 Panel, Revision 5, was inadequate in that it was ambiguous and
did not cause the responders to verify that the fuel racks were free as part of the
response actions to investigate the cause of the unit failing to start.
Consequently, the licensee failed to identify that the Unit 1 Train B Emergency
Diesel Generator 1-02 fuel racks were not free to move, which led to an
extended period of inoperability and a significant delay in diagnosing the cause
of the emergency diesel generator failure to start. This issue was entered into
the licensees corrective action program as SMF-2007-03426.
The finding was determined to be more than minor because it was associated
with the procedure quality attribute of the mitigating systems cornerstone, and it
affected the cornerstone objective to ensure the availability, reliability, and
capability of systems that respond to initiating events to prevent undesirable
consequences. Using Manual Chapter 0609, Significance Determination
Process, Phase 1 Worksheet, the finding was determined to have very low
safety significance (Green) because it was not a design or qualification
deficiency, did not represent a loss of safety function, did not represent an actual
loss of a single train for greater than its Technical Specification allowed outage
time, did not represent a loss of a non-Technical Specification Train of
equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and did not screen as potentially risk
significant due to a seismic, flooding, or severe weather initiating event
(Section 2.2).
B. Licensee-Identified Violations
None.
-3- Enclosure 2
REPORT DETAILS
1.0 SPECIAL INSPECTION SCOPE
The NRC conducted a special inspection at Comanche Peak Steam Electric Station to
better understand the circumstances surrounding the failure of the Unit 1 Train B
Emergency Diesel Generator (EDG) 1-02 to start on demand during a monthly
surveillance test on November 21, 2007. Following approximately 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> of
troubleshooting, EDG 1-02 was restored to an operable status. In accordance with NRC
Management Directive 8.3, it was determined that the period of inoperability of the EDG,
both prior to and during the failure to start event, had sufficient risk significance to
warrant a special inspection. The initial incremental conditional core damage probability
associated with the assumed period of EDG inoperability was estimated to be
1.76 x 10-5. The possibility that adverse generic implications were associated with the
EDG failure mechanism was the deterministic criterion met to warrant a special
inspection.
The team conducted the inspection in accordance with Inspection Procedure 93812,
Special Inspection, and the inspection charter, which is included in this report as
Attachment 2. The special inspection team reviewed procedures, corrective action
documents, operator logs, and maintenance records for the EDG system. The team
interviewed various licensee personnel regarding the events that led up to and response
actions that followed the EDG failure, as well as design and operational characteristics
of the EDG and its support systems. The team reviewed the licensees root cause
analysis report, past failure records, extent of condition evaluation, immediate and long
term corrective actions, and industry operating experience. A list of specific documents
reviewed is provided in Attachment 1.
1.1 Event Summary
On November 21, 2007, at 10:20 a.m., EDG 1-02 failed to start on demand during a
monthly slow start surveillance test. Prior to this, the last successful surveillance test on
EDG 1-02 was on October 24, 2007. The licensees response to the failure to start is
described in Section 1.2 below. Troubleshooting efforts were ultimately successful, and
EDG 1-02 was restored to an operable status at 3:08 a.m. on November 22, 2007. The
failure was determined to be the result of fuel racks being stuck in the closed positions,
and not responding to a full open governor demand, thereby preventing sufficient fuel
from reaching the engine. The failure mechanism is described in Section 1.4 below.
The cause of the fuel rack binding was ultimately determined to be a drop of paint on a
fuel rack which prevented the rack from being able to move through the fuel pump
housing. The root and contributing causes of this failure are discussed on Section 1.3
below.
Prior to the failed surveillance test on November 21, 2007, painting was conducted on
and around EDG 1-02 and EDG 2-02 (Unit 2 Train B EDG). The painting activities
associated with EDG 1-02 began on October 15, 2007, and continued through
November 8, 2007.
-4- Enclosure 2
Included below is a timeline that includes significant elements pertaining to this event.
Date/Time Event
October 15, 2007 Painting begins on EDG 1-02 on top of engine and around
heads.
October 15, 2007 - Painting activities continue on a daily basis.
November 1, 2007
October 24, 2007 Successful monthly slow start surveillance test of EDG 1-02.
No painting is done on this day.
October 29, 2007 - Painting occurs around the 6L fuel pump.
November 1, 2007
November 1, 2007 Painting in locations that could have reasonably resulted in
stray paint/drops on fuel rack(s) is completed.
November 21, 2007 EDG 1-02 declared inoperable due to bar over in preparation
3:28 a.m. for monthly surveillance test.
4:09 a.m. Bar over completed. Successful water roll via the air start
system was completed. EDG 1-02 declared operable.
10:17 a.m. EDG 1-02 declared inoperable for monthly surveillance test.
10:20 a.m. EDG 1-02 failed to start on demand for monthly slow start
surveillance test. Operations personnel believed the EDG did
not roll. Troubleshooting commences.
4:49 p.m. Slow start attempt of EDG 1-02 resulted in EDG rolling up to
90-100 rpm and failing to start. Troubleshooting continues.
6:02 p.m. Fast start attempt of EDG 1-02 resulted in a failure to start.
Fuel racks were observed not to move in response to a
governor demand.
7:39 p.m. Fuel racks were manually stroked. Rack 6L was found to be
stuck. Rack 2L moved approximately half of its travel range,
then became bound. Both racks were freed and stroked until
normal free range of motion was restored.
9:25 p.m. Walkdown inspections revealed residual paint on 6L, 4L, and
4R fuel racks. Residue of paint on 6L was wiped away.
9:32 p.m. Successful start and run of EDG 1-02.
November 22, 2007 EDG 1-02 was declared operable.
3:08 a.m.
-5- Enclosure 2
1.2 Licensee Response to the Failure of the EDG to Start
The inspectors evaluated the licensees implementation of procedures (abnormal, alarm,
troubleshooting, and normal operations) and Technical Specifications, reviewed plant
managements control and decision making actions, and reviewed the troubleshooting
and investigating activities that occurred following the Unit 1 Train B EDG failure to start
during the monthly surveillance test on November 21, 2007. The inspectors reviewed
corrective action documents, procedures, Technical Specifications, and operations logs.
The team performed system walkdowns and interviewed engineering, maintenance, and
operations personnel.
The inspectors determined that, in general, the licensee responded to the event properly
and in accordance with plant procedures. Nuclear equipment operators (NEO) quickly
identified that the EDG 1-02 failed to start and immediately responded to the local EDG
alarm panel. The operations field support supervisor performed an inspection to look for
any obvious problems that could have caused the EDG to fail. NEOs noted that it did
not sound like a normal start, and assumed that a possible issue associated with the
starting air system had something to do with the failure to start. The licensee had
already declared the EDG inoperable prior to the attempted start in conjunction with the
surveillance test.
In response to the Unit Failure To Start alarm on the local EDG alarm panel, NEOs
performed the steps of the local alarm panel procedure, Alarm Procedure
Manual ALM-1302A, Diesel Generator 1-02 Panel, Revision 5, which instructed the
operations personnel to investigate the cause of the failure. This included checking for
proper operation and issues associated with the fuel racks, day tank, and the starting air
system. One of the applicable steps was to check fuel racks free. This was
accomplished in accordance with the expectations of senior operations personnel by
visually verifying that there were no apparent conditions that would obstruct the motion
of the fuel racks. No abnormalities were identified at this time.
The operations staff reviewed drawings and diagrams, interviewed the NEOs, and
consulted with meter and relay representatives, system engineering department
personnel, and the mechanical services department to develop a troubleshooting plan.
Due in large part to the testimony of the NEOs that the EDG did not even roll in
response to the start attempt, the troubleshooting plan focused on the starting air
system as the suspected cause of the failed start. The plan called for meter and relay
personnel to monitor various solenoids and relays during a subsequent slow start
attempt of the EDG. This attempt resulted in the EDG rolling up to 90-100 rpm, and
again failing to start. Indications now suggested that a fuel-related problem must exist,
and focus was shifted accordingly. A third attempt was performed with the EDG in a
fast start configuration. Again, the EDG failed to start. Observers noted that the fuel
racks did not move from their closed positions in response to the mechanical governors
attempt to drive the fuel racks to the full open position. The licensee then attempted to
exercise the fuel racks and metering rods individually and discovered that two metering
rods (2L and 6L) were partially and fully bound, respectively. Licensee personnel
physically exercised the metering rods until they were free to move, and removed
evidence of paint that was found to be on the 6L metering rod by the fuel pump housing
interface. The licensee then performed a fourth attempt to start EDG 1-02, which was
-6- Enclosure 2
successful. The EDG was fully loaded, and operations personnel completed the
surveillance testing. The EDG 1-02 was subsequently declared operable on the
morning of November 22, 2007 at 3:08 a.m.
The inspectors determined that the initial troubleshooting plan was too narrowly focused
on finding an EDG starting air problem (despite a successful water roll via the air start
system that occurred earlier that morning), as opposed to pursuing all likely causes of a
failed start. If the focus of the response were broader, it is likely that the stuck metering
rod would have been discovered earlier, and the duration of EDG inoperability following
the failed start would have been reduced.
Subsequently during the troubleshooting efforts, the joint engineering team developed a
confirm and refute matrix to process the results from troubleshooting. Possible causes
that were analyzed over the course of troubleshooting included:
- Starting air receiver discharge valves mispositioned
- Manual stop button mispositioned
- Tachometers operational
- Malfunctioning of air start solenoid valves
- Mechanical governor bound
- Fuel supply to the engine
- Main control board handswitch
- Electronic governor not operating
- Fuel racks not functioning*
- Determined to be the cause of the failure
As described in Section 1.3 below, the Unit 2 Train B EDG was also in the process of
being painted. Once the cause of EDG 1-02 inoperability was determined to be stuck
metering fuel rods, the operations staff inspected the Unit 2 Train B EDG and
determined that the same issue did not exist. Operations also inspected the Units 1
and 2 Train A EDGs and determined that the stuck metering rods issue did not exist.
The Unit 1 Train B EDG was the only EDG affected.
1.3 Root Cause and Corrective Action Assessment
.1 Root Cause Analysis
The inspectors reviewed and assessed the licensees root cause analysis for technique,
accuracy, thoroughness, and corrective actions proposed and taken. The inspectors
reviewed the scope and processes used by licensee personnel to identify the root cause
for the failure of the Unit 1 Train B EDG to start during a monthly surveillance test. The
inspectors compared information gained through inspection to the event information and
assumptions made in the root cause reports. The inspectors interviewed licensee
personnel, reviewed logs, reviewed personal statements, and observed root cause team
meetings. The inspectors evaluated the licensees extent of condition review and
common cause evaluation.
-7- Enclosure 2
The licensee captured the EDG 1-02 failure to start problem in the corrective action
program as SMF-2007-03253, and performed a root cause analysis in response to
determine the cause of the failure. Evaluation techniques utilized by the licensee
included an Events and Causal Factors Chart and a Barrier Analysis. The result of
these efforts identified the most probable root cause of the failure to be a drop of paint
that was deposited and adhered to the 6L fuel rack in a location that prevented the rack
(along with all other fuel racks) from moving in the open direction in response to the
governor demand associated with an EDG start signal. This failure mechanism is
further discussed in Section 1.4 below. Although there was no documented evidence of
the actual paint drop, there was paint residue observed which remained in the subject
location following the manual manipulation and freeing of the stuck fuel rack during
troubleshooting. This residue was wiped off upon discovery.
Additionally, the following four contributing causes to the failure were identified in the
final root cause analysis:
- Work practices of painters and other groups who performed daily inspections
failed to identify paint spatter and drops that should have been cleaned off
sensitive engine components.
- The tools and techniques used by painters were not completely effective in
preventing paint spatter and drips.
- *Because the directions in alarm response procedure ALM-1302A were not
specific, the time period following the failure until the discovery of the cause of
the problem was extended.
- The fuel control shaft break away force may have increased over time due to
wear and aging effects. This may have added to the force required to overcome
the adhesion of the paint drop.
- This issue was also identified early in the inspection process by the inspectors and is
further discussed in Section 2.2 below.
The root cause team assessed that the engineering confirm/refute evaluation performed
during troubleshooting, along with the subsequent investigative actions outlined below,
were effective in considering and ruling out all other potential causes of the failure:
- Electrical and control circuitry problems were investigated and ruled out. Due to
the initial reports that the field operator did not believe that the EDG even rolled
over, the root cause team investigated other possibilities that could have caused
the EDG not to have rolled, and still brought in the alarms that were received.
One viable possibility considered was a possible fault associated with the EDG
Start/Stop hand switch in the control room. The hand switch in question was a
piece of original equipment. One of the corrective actions was to replace the
hand switch when the 6L fuel pump and metering rod was replaced after the
event. The switch was bench tested, disassembled, and inspected, and it was
determined that the switch not only functioned properly without signs of
degradation, but it would not be physically possible to have the switch
-8- Enclosure 2
manipulated to send a stop signal to the diesel while an operator takes the
switch to the start position. The inspectors performed a visual inspection of the
switch internals and reviewed the testing methods and results. The inspectors
concluded that the EDG start/stop control switch would not have caused the
EDG failure to start on November 21, 2007.
- The starting air system was examined and proven to be functional. The
inspectors confirmed this by performing system walkdowns. A water roll check
was performed satisfactorily.
- The fuel day tank was inspected to ensure proper alignment and fuel quality.
- Inspections of the joints that connect the fuel pump control shaft levers to the
fuel racks were performed, and determined that none were exhibiting mechanical
binding. The inspectors confirmed this by performing a system walkdown.
- The 6L fuel pump was replaced and sent to the vendor for testing, disassembly,
and inspection. No abnormalities were identified, and internal binding of the
pump was determined not to be a cause of the event.
- The capability of single paint drop to counter the force applied and prevent the
motion of the fuel control shafts was assessed. A spare fuel pump was
subjected to a series of field tests to determine the force required to overcome
the adhesion of a drop of paint in the location that had been identified. The
results were consistent with the hypothesis that the force applied from the
mechanical governor could have been overcome by the presence of the paint
drop becoming wedged in the minimal clearance between the fuel rack and the
pump housing. Another pull test was done to confirm that a fuel rack exposed to
various combinations of dirt and grit would not require appreciably more pull
tension to operate.
Aspects of organizational and programmatic effectiveness were also evaluated by the
root cause team, and confirmed by the inspectors. These included inadequate
supervisory and management involvement with the painting activities, work practices
employed during the job, and the less than comprehensive development of the
procedures and work packages associated with the activity.
The extent of the condition that was determined to be the cause of the EDG 1-02 failure
was assessed by the root cause team. All other EDGs were thoroughly inspected to
verify that the same condition did not exist, particularly with the Unit 2 Train B EDG 2-02,
which had been similarly painted in September and October. All other EDGs were
verified to be free of the subject degraded condition. Emergency Diesel Generator 2-02
successfully passed its monthly surveillance test on November 28, 2007. The
inspectors reviewed the licensees actions and concluded that the licensees extent of
condition evaluation was adequate.
The inspectors concluded, following interviews as well as a review of personal
statements made by the maintenance personnel, that the work practices of painters and
other work groups who performed daily paint clean-up inspections to identify paint
-9- Enclosure 2
spatter and drops that needed to be cleaned off of sensitive engine components was a
valid contributor to the event. The inspectors also determined that neither
documentation nor feedback from the inspections to the painters or operations
management regarding the results of those inspections was performed. The
communication of those results, to the right individuals, could have identified the need to
reinforce expectations, alter paint methods or barriers, or institute a stand down that
may have led to the prevention of the event. At a minimum, communication between
organizations (maintenance, inspection, operations, and management) was not as
strong as it could have been for this work on highly risk significant, safety-related
equipment.
Along with the discussion above, the inspections that were performed as part of the
postpainting activities were agreed upon between operations and maintenance. Neither
the inspections nor any other applicable postmaintenance testing was specified by the
work order for performing the painting activities. Also, there was no discussion
concerning foreign materials control exclusion (FME) controls. FME has been a
significant issue with the licensee in the recent past, but no mention of this sensitivity
was made. The inspections that were performed were not documented anywhere as
having been done nor were any of the findings stemming from the inspections.
The inspectors found that the licensee assembled an effective root cause team. The
root cause team investigated every lead that was available to determine exactly why the
Unit 1 Train B EDG failed to start on November 21, 2007. The inspectors determined
that the scope, methods, and rigor associated with the root cause analysis were
appropriate and consistent with the safety significance of the problem, and that the
evaluation was successful in determining and addressing the most probable root and
contributing causes of this issue.
.2 Corrective Action Assessment
The inspectors evaluated the scope, adequacy, and timeliness of the licensees
corrective measures that were both planned and implemented in response to the cause
of the EDG 1-02 failure. The inspectors concluded that the actions planned and taken
by the licensee were appropriate to address the degraded condition, to result in the
prevention of a future similar failure, and were consistent with the safety significance of
the event. Corrective actions to be taken prior to resuming painting activities include:
- Revise Procedure MSM-G0-0220 used for painting to require a shiftly
manipulation of the fuel racks in addition to a visual inspection of components to
be free of paint spatter/drops
- Verify the information contained in the painting pre-job briefing book to ensure it
contains all sensitive areas on the EDG that should not be painted
- Revise Procedure MSM-G0-0220 to include pictures and other information
contained in the painters prejob briefing book used during EDG painting
- Revise Procedure MSM-G0-0220 to provide for as you go inspections and
cleaning when painting is done around sensitive components
-10- Enclosure 2
- Include this event in prejob briefings for future activities to heighten sensitivity to
the potential effects of paint spatter/drops in areas that can bind mechanical
components or block air pathways
- Improve tools and techniques used by painters to minimize drops and spatter.
Also research available FME barriers that could be used to shield sensitive areas
Additional planned corrective actions include:
- Develop a preventive maintenance activity to perform a fuel control shaft break
away force test to monitor for potential degradation in the shaft linkage or
bearings
- Revise alarm response Procedure ALM-1302A to remove ambiguity regarding
checking components for freedom of movement by providing specific instruction
to include a manual manipulation of the components
1.4 Scope of the Failure Mechanism
The inspectors, through inspection and investigation, interviews of system engineers,
reviews of EDG design documentation, and assessment of the licensees root cause
analysis, developed a scope of the mechanism that was determined to be the root
cause of the EDG 1-02 failure. The fuel pump control racks (fuel metering rods) were
prevented from moving from their normal standby (closed) positions in response to a
governor demand by the presence of a drop of paint that had adhered to the fuel rack in
a location where the rack enters the housing of the fuel pump (with very minimal
clearance) when moving in the open direction. Since all fuel racks are mechanically
linked by the common fuel control shafts and cross shaft linkages, the motion of the
entire system in the open direction (back to the extensible link from the mechanical
governor) was inhibited by one fuel rack that was stuck in the standby (closed) position.
A torsion spring on the control shaft associated with each fuel pump control shaft lever
functions to allow continued motion of the system in the closed direction if one or more
individual fuel racks become bound. However, the feature does not provide this function
for system motion in the open direction, as in the response to an EDG start signal.
1.5 Event Precursors
The root cause of the EDG failure to start was determined to be paint that was
inadvertently dropped onto a fuel pump metering rod. The inspectors reviewed
corrective action documents and interviewed system engineers in order to identify any
previous related issues that may have been precursors to the Unit 1 Train B EDG failure
to start. The inspectors reviewed all available documented issues dating back to 1999
that fell into each of the following two categories: (1) Previous similar or related EDG
failures, and (2) Previous issues involving equipment failures related to painting. The
inspectors determined that there had been no previous EDG or painting related issues
that may have been precursors to this event.
-11- Enclosure 2
1.6 EDG Maintenance and Testing
The inspectors reviewed the licensees EDG Maintenance and testing programs. The
inspectors reviewed maintenance and testing records as well as the licensees plans
and schedules related to preventive maintenance and testing of the EDGs. The
inspectors also interviewed several system engineers to gain an understanding of the
licensees approaches and programs involving EDG maintenance and testing. The
inspectors determined that the licensees EDG routine maintenance and testing
programs are adequate and that the licensee is following the program provisions.
However, the inspectors determined that these maintenance and testing practices for
painting activities were not adequate as discussed in Section 2.0.
1.7 Industry Operating Experience (OE)
The inspectors reviewed the industry operating experience (OE) the licensee gained
through their normal review, as well as that which was referenced in the licensees root
cause evaluation. The inspectors conducted interviews of licensee personnel, reviews
of pertinent OE materials discovered independently as well as with the assistance of the
NRCs Operating Experience Section, and an evaluation of actions taken by the licensee
in response to relevant OE. The specific documents reviewed during this review is listed
in Attachment 1 of this report.
The inspectors determined that the licensee had appropriately reviewed and
incorporated OE associated with the circumstances of the EDG failure, and that a failure
to incorporate applicable OE into station practices was not a contributing cause to the
EDG failure. The inspectors reviewed several items of OE, inspection reports, and
licensee event reports (LERs). The inspectors reviewed the licensees responses to the
applicable cases. The licensee did have all of the OE in their OE review system, with
the exception of LERs. The licensee reviews industry OE that comes from INPO and
not specifically the LER database. It appeared that the licensee had accounted for all
available OE at the time that could have reasonably been obtained and reviewed.
All of the OE pertaining to notification events of inoperable diesels due to painting
described gross painting errors that resulted in inoperable diesel generators (e.g.,
inappropriate/movable components being painted). The licensee did take those events
into consideration when developing the work plan for painting of the EDGs in the
associated rooms. The licensee held meetings well in advance of the scheduled
painting window, ensured that operations and maintenance personnel were
communicating, and developed a painters handbook that presented precautions as well
as clear photographs of the areas and components not to paint. The preparation was
adequate for the knowledge that the plant had on site at the time. The sensitivity that
one paint drop in a specific, unintended location could render the EDG inoperable was
not considered by the licensee in their preparation and conduct of the EDG painting
activities, but this was not a subject of previous OE.
One item that was not specifically incorporated into the procedures for painting the EDG
was a specific postmaintenance test to be performed to prove operability. The
licensees procedure described and recommended any of several postmaintenance
-12- Enclosure 2
options, including visual inspections and equipment functionality tests. This procedure
and its weaknesses were discussed as part of the root cause evaluation in Section 1.3.
The licensee sent two of its employees (a system engineer and a painting supervisor)
on a benchmarking trip prior to cleaning up, painting, and relamping the EDG Rooms.
The licensee employees were aware of the potential to make the EDG inoperable by
painting activities, but did not get enough information to be as sensitive as necessary for
their painting activities. After the failed EDG start, the licensee called the plants visited
during the benchmarking trip to ask more questions, and then discovered that one plant
had knowledge that very little paint or other foreign materials on the metering rods could
render the EDG inoperable. The licensee could have possibly obtained this information
if their staff were to have asked more probing questions, given the work that was
planned at the site. The inspectors concluded that the licensee was not fully effective in
addressing operating experience associated with painting impacts on emergency diesel
generator operability.
1.8 Potential Generic Issues
The inspection team evaluated the circumstances surrounding the event and assessed
the root cause of the Unit 1Train B EDG failure to start. The team interviewed
numerous licensee personnel and reviewed industry operating experience as well as
NRC generic communications with the goal of identifying any potential generic issues
that should be addressed as a result of the event.
The inspection team concluded that, while painting activities occur at all plants, there are
no specific generic concerns associated with this instance of procedural compliance.
The licensee has also issued an action in the corrective action program to issue an OE
report to INPO for future reference.
2.0 SPECIAL INSPECTION FINDINGS
2.1 Painting Activities Result in Inoperability of EDG
Introduction: A White self-revealing violation of Unit 1 Technical Specification (TS)
3.8.1, AC Sources - Operating, was identified for the licensees failure to satisfy TS
LCO 3.8.1 in that painting activities conducted on the Unit 1 Train B EDG 1-02 resulted
in paint being deposited and left in a location that caused the EDG to become
inoperable. As a result, EDG 1-02 failed to start on demand during the subsequent
monthly surveillance test. Following the discovery of the condition, the TS required
actions were satisfied; however, the time period between the occurrence of the condition
and the discovery of the condition exceeded the TS allowed outage time.
Description: On October 15, 2007, the licensee commenced painting activities that
occurred on and around EDG 1-02. A successful monthly slow start surveillance test
was performed on October 24, 2007. Painting activities continued through November 1,
2007. The inspectors reviewed Work Order (WO) 4-07-175968-00, which implemented
the painting activities on and around EDG 1-02 and specified that painting was to be
performed per the requirements of Procedure MSM-G0-0220, General Plant Painting,
Revision 2. The inspectors noted that the WO did not contain requirements for
-13- Enclosure 2
postmaintenance testing of the EDG, and that Procedure MSM-G0-0220, General Plant
Painting, Revision 2, contained the following steps:
NOTE: System engineer, operations, maintenance services or other
departments may provide useful guidance in determining appropriate protection
of equipment and post-painting functional testing.
5.1.1.2 Painting conducted on equipment should be done in such a manner as
to ensure paint does not bind components required to move. Prejob briefings,
visual verification of postpainting operation, equipment functional testing or other
similar activities are recommended practices that should be employed when
painting equipment.
Through interviews, the inspectors determined that representatives from the
maintenance services, system engineering, maintenance, and operations departments
discussed plans for verifying at the end of each day that the EDG remained operable.
The above requirement and guidance of the general plant painting procedure was not
referenced in this discussion. It was decided that a senior operations department
personnel would perform a visual inspection at the end of each day to verify that
painting had not been done so as to affect the operability of the EDG. This plan was
understood and executed, but was not documented, nor were any inspection results
documented. Prejob briefs and postpainting inspections were focused on avoiding the
painting of components that were not supposed to be painted and were appropriate and
effective in that regard. However, appropriate sensitivity to the potential functional
impact of stray drop(s) of paint in sensitive location(s) was not emphasized.
On November 21, 2007, EDG 1-02 failed to start on demand during its next monthly
surveillance test. Following approximately 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> of troubleshooting, EDG 1-02 was
successfully started. This issue was entered into the licensees corrective action
program as SMF-2007-003253-00. The licensee performed a root cause analysis to
determine the cause of the failure. The most likely cause of the failure was determined
to be a paint drop that had been deposited on the 6L fuel rack that caused the rack to
become stuck. This prevented motion of all 16 fuel racks, thereby preventing the EDG
from receiving sufficient fuel to run. Corrective actions planned and taken by the
licensee are discussed in Section 1.3 of this enclosure.
Analysis: The performance deficiency associated with this finding involved the
licensees failure to ensure that the assumed operability of safety-related equipment was
not affected by the performance of scheduled maintenance activities. Specifically,
painting was conducted on and around EDG 1-02 in such a manner that paint was
deposited and remained in a location that caused the EDG to become inoperable and
fail to start on demand during a subsequent surveillance test. Postpainting verification
of equipment functionality was inadequate. Consequently, the requirements of TS LCO 3.8.1.b and the associated required TS Actions B.4 and G.1 and 2 were not met. The
finding was greater than minor because it was associated with the human performance
attribute of the mitigating systems cornerstone, and it affected the cornerstone objective
to ensure the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. The Phase 1 Worksheets in Manual
Chapter 0609, Significance Determination Process, were used to conclude that a
-14- Enclosure 2
Phase 2 analysis was required because the performance deficiency affected the
emergency power supply system that is a support system for both mitigating and
containment barrier systems. Based on the results of the Phase 2 analysis, the finding
was determined to have low to moderate safety significance (White). The senior reactor
analyst determined that a more detailed Phase 3 analysis was needed to fully assess
the safety significance. Based on the results of the Phase 3 analysis, the finding was
determined to have low to moderate safety significance (White). The Phase 1, 2, and 3
significance determination process analyses associated with this finding, including
assumptions and limiting core damage sequences, is included as Attachment 3 to this
report. The cause of this finding was determined to have a crosscutting aspect in the
area of human performance associated with work practices in that the licensee failed to
provide adequate supervisory and management oversight of work activities, including
contractors, such that nuclear safety is supported H.4(c). Specifically, the actions
planned and taken to assess and control the operational impact of the painting activities
on the functionality of the EDG were not reflective of adequate supervisory and
management oversight of the activities.
Enforcement: Unit 1 Technical Specification (TS) 3.8.1, AC Sources - Operating,
requires that while the plant is in Modes 1, 2, 3, or 4, two diesel generators (DGs)
capable of supplying the onsite Class 1E power distribution subsystem(s) shall be
operable. For the condition of one DG being inoperable, the required action is to restore
the DG to an operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and within 6 days from the discovery of the
failure to meet the Limiting Condition for Operation (LCO), or be in Mode 3 within 6
hours and Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Contrary to the above, from November 1, 2007,
through November 21, 2007, while the plant was in Mode 1, one of the two DGs capable
of supplying the onsite Class 1E power distribution subsystem(s) was inoperable, and
action was not taken to either restore the DG to an operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be
in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Specifically, Emergency Diesel
Generator (EDG) 1-02 was made inoperable as a result of painting activities due to paint
having been deposited and remaining on at least one fuel rack in a location that
prevented motion required to support the operation of the EDG. This condition caused
EDG 1-02 to fail to start during a surveillance test on November 21, 2007. Following the
discovery of the condition on November 21, 2007, the licensee satisfied the TS required
actions by restoring the EDG to an operable status on November 22, 2007. This
violation is the subject of the enclosed Notice of Violation: VIO 05000445/2007008-01,
Painting Activities Result in Inoperability of Emergency Diesel Generator.
2.2 Inadequate Alarm Response Procedure for EDG Failure to Start
Introduction: The inspectors identified a Green noncited violation of Unit 1 Technical
Specification 5.4.1.a, Procedures, for an inadequate alarm response procedure. The
inspectors determined that Procedure ALM-1302A, Diesel Generator 1-02 Panel,
Revision 5, was inadequate in that it was ambiguous and did not cause the responders
to verify that the fuel racks were free as part of the response actions to investigate the
cause of the unit failing to start. Consequently, the licensee failed to identify that the
Unit 1 Train B EDG 1-02 fuel racks were not free to move, which led to an extended
period of inoperability and a significant delay in diagnosing the cause of the EDG failure
to start.
-15- Enclosure 2
Description: On November 21, 2007, at 10:20 a.m., EDG 1-02 failed to start during a
slow start monthly surveillance test. Field operators responded to the EDG local alarm
panel. Operators referenced the alarm response Procedure ALM-1302A, Diesel
Generator 1-02 Panel, Revision 5, and reviewed the section for Alarm Window 6.6 Unit
Failure To Start. A limited number of system malfunctions that could have caused the
failure to start were indicated. These included fuel rack or fuel oil day tank issues,
improper starting air alignment, failed timing chain, and a Governor malfunction.
Operators implemented the Operator Actions section of the procedure, which included
actions to determine the cause of the unit failing to start. The first action indicated was
to Check fuel racks free and in max fuel position. The field support supervisor (senior
reactor operator) believed that the appropriate action was to perform a visual inspection
of the fuel racks. The fuel racks were not in the "max fuel" position. The inspectors
later determined that, following the majority of postulated failed start scenarios, the fuel
racks would not be expected to remain in the "max fuel" position, even if they had
initially moved. In accordance with the operators' training, the expectation for
performing this step was to visually inspect the racks. However, the inspectors
determined that without observing them being in a position other than their normal
standby (closed) position, this visual check would not be sufficient to meet the intent of
the procedure step (i.e., to ensure that the racks were not stuck in the "no fuel" position,
which was a probable failure cause that was indicated earlier in the procedure). The
operator completed this procedure step, as well as subsequent steps for starting air
alignment, EDG day tank alignment, and fuel quality with no abnormalities identified.
Field operator actions were completed at 11:05 a.m.
The licensee developed a troubleshooting plan and attempted two more starts of the
EDG (both unsuccessful) before determining that the fuel racks and metering rods were
not responding to the Governor demand to open. At 7:39 p.m. the licensee exercised
the fuel racks and discovered that two of the metering rods were stuck, with one fully
stuck in the closed position and one which became partially stuck following some motion
in the open direction. Operations and maintenance performed followup inspections and
successfully started the EDG at 9:32 p.m. The diesel was declared operable following
the surveillance run and post run inspections on November 22, 2007 at 3:08 a.m.
The inspectors concluded that the field operators performed the actions of the alarm
response Procedure ALM-1302A, in accordance with station procedures and training,
and operations managements expectations. The inspectors further concluded that the
inadequacy of the alarm response procedure to give clear instruction and guidance to
ensure that the EDG fuel racks were verified to be free and not binding resulted in
missing an opportunity to identify the cause of the EDG failure to start in a timely
manner. This missed diagnosis not only led to a narrowly focused troubleshooting effort
by the licensee, but also allowed the EDG to remain unnecessarily inoperable for
approximately an additional 8.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.
Analysis: The performance deficiency associated with this finding involved the
licensees failure to adequately establish clear procedure guidelines to implement alarm
response Procedure ALM-1302A. This resulted in the licensees failure to identify the
binding of the Unit 1 Train B EDG fuel racks and metering rods in a timely manner
following a failure to start. The finding was determined to be more than minor because
-16- Enclosure 2
it was associated with the procedure quality attribute of the mitigating systems
cornerstone, and it affected the cornerstone objective to ensure the availability,
reliability, and capability of systems that respond to initiating events to prevent
undesirable consequences. Using Manual Chapter 0609, Significance Determination
Process, Phase 1 Worksheet, the finding was determined to have very low safety
significance (Green) because it was not a design or qualification deficiency, did not
represent a loss of safety function, did not represent an actual loss of a single train for
greater than its Technical Specification allowed outage time, did not represent a loss of
a non-Technical Specification train of equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event.
Enforcement: Unit 1 Technical Specification 5.4.1.a requires that written procedures be
established, implemented, and maintained covering the procedures listed in Regulatory
Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A,
Section 5, for Abnormal, Off-Normal, or Alarm Conditions. Contrary to the above, on
November 21, 2007, the licensee failed to adequately establish, implement, and
maintain a procedure for an alarm condition. Specifically, alarm response
Procedure ALM-1302A, Diesel Generator 1-02 Panel, Revision 5, was not adequately
established and maintained, which resulted in the licensees failure to recognize that the
EDG 1-02 fuel racks and metering rods were bound and caused the failure of the EDG
to start on November 21, 2007. Consequently, the EDG remained inoperable for
approximately 8.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> longer than necessary. Because the finding was determined to
be of very low safety significance and has been entered in the licensees correction
action program as SMF-2007-003426, this violation is being treated as an NCV
consistent with Section VI.A of the Enforcement Policy: NCV 05000445/2007008-02,
Inadequate Alarm Response Procedure for EDG Failure to Start.
4OA6 Meetings, Including Exit
On December 7, 2007, and January 10, 2008, the results of this inspection were
presented to Mr. R. Flores, Site Vice President, and Mr. T. Hope, Regulatory
Performance Manager, respectively, and other licensee personnel who acknowledged
the findings. Additionally on January 24, 2008, the final results of this inspection were
presented to Mr. F. Madden, Director, Regulatory Affairs, and other members of the
licensee staff who acknowledged the findings. On February 25, 2008, an additional exit
meeting was conducted with Mr. T. Hope and other licensee personnel who
acknowledged the findings. The inspectors confirmed that no proprietary material was
retained during the inspection.
ATTACHMENT 1: Supplemental Information
ATTACHMENT 2: Special Inspection Charter
ATTACHMENT 3: Significance Determination Evaluation
-17- Enclosure 2
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
J. Bain, System Engineer
J. Bales, Maintenance Services
T. Bennette, Operations
M. Blevins, Senior Vice President and Chief Nuclear Officer
H. Davenport, System Engineer
D. Davis, Performance Improvement Director
R. Flores, Site Vice President
D. Goodwin, Manager, Shift Operations
T. Hope, Manager, Regulatory Performance
M. Kanavos, Plant Manager
D. Kross, Director, Operations
S. Lakdawala, Corrective Action Program Manager
F. Madden, Director, Regulatory Affairs
D. McGaughey, Manager, Shift Operations
G. Merka, Regulatory Affairs
J. Meyer, Technical Support Manager
W. Morrison, Maintenance Smart Team Manager
J. OQuinn, Maintenance
W. Reppa, System Engineering Manager
D. Scott, Root Cause Analyst
S. Smith, Director, System Engineering
R. Sorrell, System Engineer
T. Terryah, System Engineering Manager
T. Tigner, Programs Supervisor
B. Wagner, PROMPT Team
W. Williams, Maintenance Services
M. Wisdom, System Engineering
NRC
D. Allen, Senior Resident Inspector
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
05000445/2007008-01 VIO Painting Activities Result in Inoperability of Emergency
Diesel Generator (Section 2.1)
A1-1 Attachment 1
Opened and Closed
05000445/2007008-02 NCV Inadequate Alarm Response Procedure for EDG Failure to
Start (Section 2.2)
Closed
None
Discussed
None
LIST OF DOCUMENTS REVIEWED
Procedures
NUMBER TITLE REVISION
ALM-1302A Diesel Generator 1-02 Panel 5
MSM-G0-0002 General Plant Painting 2
MSM-P0-3374 Emergency Diesel Generator Monthly Run Related 3
Inspections
OPT-215-1 Offsite Transmission Network Operability Data Sheet 14
OWI-104-28 Plant Equipment Operator Diesel Generator 1-02 13
Operating Log
OWI-104-26 Control Room Diesel Generator 1-02 Operating Log 11
MSM-G0-0216 Protective Coatings 23
MSM-G0-0217 Maintenance Protective Coatings-Concrete 0
MSM-G0-0218 Maintenance Protective Coatings-Steel 0
CMP-CV-1009 Application of Protective Coatings to Carbon Steel 0
Surfaces in the Containment and Radiation Areas
Outside of Containment
ODA-102 Conduct of Operations 24
ODA-401 Control of Annunciators, Instruments, and Protective 9
Relays
ODA-407 Guidelines on Use of Procedures 12
A1-2 Attachment 1
OPT-214A Emergency Diesel Operability Test 19
SOP-609 Diesel Generator System 17
STA-426 Industry Operating Experience Program 1
STA-692 Protective Coatings Program 0
TSP-503 Emergency Diesel Generator Reliability Program 3
Smart Forms
SMF-2007-03253 SMF-2007-03426 SMF-2007-03302
SMF-2007-02319
4-07-176522 4-07-175968 4-07-176545
4-07-176543 4-07-176544 4-95-091357-00
5-05-501230-AA 4-07-176582 4-94-078722-00
5-07-502391-AK 4-07-175492
Miscellaneous Information
Evaluation EVAL-2007-003253-02-00, Root Cause Analysis
Post-Work Test Guide, Revision 12
LER 07-004-00, Emergency Diesel Generator Failed Surveillance Test Due to Paint on Fuel
Injector Control Linkage
TUElectric Office Memorandum, CPSES-9125952, October 10, 1991
TUElectric Office Memorandum, CPSES-9108929, April 3, 1991
TUElectric Office Mamorandum, CPSES-91000861, January 11, 1991
Technical Evaluation TE# SE-90-1814
Cooper-Enterprise Clearinghouse R4/RV4 Preventative maintenance Program (PMP) for
Nuclear Standby Applications, Revision 0
Operations Guideline 3, Attachment 4, Operations Department Alarm Response Expectations,
August 2006
A1-3 Attachment 1
CPNPP Operations Logs, November 21-22, 2007
Amercoat 220, Waterborne Acrylic Topcoat Product Datasheet, circa 1999
Information Notices
IN 93-76, Inadequate Control of Paint and Cleaners for Safety-Related Equipment
IN 91-46, Degradation of Emergency Diesel Generator Fuel Oil Delivery Systems
NRC Inspection Documents
Inspection Procedure 93812, Special Inspection, 7/18/2007
Special Inspection Charter to Evaluate the Comanche Peak Steam Electric Station Diesel
Generator Failure to Start Event, November 30, 2007
NRC Inspection Reports
ML072040388 (DC Cook IR 05000316/2007004)
LIST OF ACRONYMS
ADAMS agency document and management system
CFR Code of Federal Regulations
CPSES Comanche Peak Steam Electric Station
EDG emergency diesel generator
FME foreign material exclusion
INPO Institute of Nuclear Power Operations
LER licensee event report
NRC Nuclear Regulatory Commission
OE operating experience
PARS publicly available records system
NEO nuclear equipment operator
SDP significance determination process
SMF smart form
WO work order
A1-4 Attachment 1
November 30, 2007
MEMORANDUM TO: Cale Young, Resident Inspector, ANO
Alfred Sanchez, Resident Inspector, CPSES
FROM: Arthur T. Howell III, Director, Division of Reactor Projects AVegel for/RA/
SUBJECT: SPECIAL INSPECTION CHARTER TO EVALUATE THE COMANCHE
PEAK STEAM ELECTRIC STATION DIESEL GENERATOR FAILURE
TO START EVENT
A Special Inspection Team is being chartered in response to the Comanche Peak Steam
Electric Station emergency diesel generator (EDG) failure to start event on November 21, 2007.
You are hereby designated as the Special Inspection Team members. Mr. Cale Young,
Resident Inspector, ANO, is designated as the team leader. The assigned SRA to support the
team is David Loveless.
A. Basis
On November 21, 2007, Comanche Peak Unit 1 diesel generator, DG-102, failed to start
during the monthly surveillance test. After several failed attempts to start the diesel,
licensee engineers developed a trouble shooting plan to determine the cause of the
diesel failing to start. During the trouble shooting efforts, licensee personnel identified
that two fuel rack linkage/metering rods (L2 and L6) on DG-102 appeared to be binding.
Additional inspections indicated that there were very small signs of paint on the metering
rods for the L2 and L6 fuel pumps, but not enough to prevent movement. Painting
activities in all EDG rooms were suspended until further measures were taken to prevent
reoccurrence of this issue. During the trouble shooting activities, each individual fuel
pump was manually operated by maintenance personnel and all but two moved freely.
Maintenance personnel were able to manually move, and subsequently free, the L2 and
L6 metering rods. Operations personnel then performed the surveillance test
satisfactorily. Maintenance personnel verified that the metering rods on the remaining
EDGs had free movement of all fuel rack linkage/metering rods.
During further investigation into when painting had occurred inside the EDG room, it was
discovered that the painters continued to paint in the diesel room after the last
successful surveillance test. This brings into question whether DG-102 would have
been able to perform its intended function if called upon from October 24 to
November 21, 2007.
A2-1 Attachment 2
This Special Inspection Team is chartered to review the circumstances related to the
failure of DG-102 to start, and to assess the effectiveness of the licensees actions for
resolving these problems.
B. Scope
The team is expected to address the following:
1. Develop a chronology (time-line) that includes significant event elements.
2. Evaluate the licensees response to the failure of the EDG to start. Ensure that
plant personnel responded in accordance with plant procedures and Technical
Specifications.
3. Assess the licensees root cause determination for the EDG failure, the extent of
condition review, the common cause evaluation and corrective measures.
Evaluate whether the timeliness of the corrective measures are consistent with
the safety significance of the problem.
4. Develop a complete scope of the failure mechanism identified by the licensees
root cause determination.
5. Identify previous EDG issues that may have been precursors to the November 1,
2007, event. Evaluate the licensees corrective measures and extent of
condition reviews for those problems.
6. Evaluate the licensees EDG maintenance and testing programs. Verify that the
programs are adequate and that the licensee is following the program provisions.
7. Evaluate pertinent industry operating experience that represents potential
precursors to the November 21, 2007, event, including the effectiveness of
licensee actions taken in response to the operating experience.
8. Determine if there are any potential generic issues related to the EDG failure at
Comanche Peak Unit 1. Promptly communicate any potential generic issues to
Region IV management.
9. Collect data as necessary to support a risk analysis. Work closely with the
Senior Reactor Analyst during this inspection.
A2-2 Attachment 2
C. Guidance
Inspection Procedure 93812, Special Inspection, provides additional guidance to be
used by the Special Inspection Team. Your duties will be as described in Inspection
Procedure 93812. The inspection should emphasize fact-finding in its review of the
circumstances surrounding the event. It is not the responsibility of the team to examine
the regulatory process. Safety concerns identified that are not directly related to the
event should be reported to the Region IV office for appropriate action.
The Team will report to the site, conduct an entrance, and begin inspection no later than
December 4, 2007. While on site, you will provide daily status briefings to Region IV
management, who will coordinate with the Office of Nuclear Reactor Regulation, to
ensure that all other parties are kept informed. If information is discovered that shows a
more significant risk was associated with this issue, immediately contact Region IV
management for discussion of appropriate actions. A report documenting the results of
the inspection should be issued within 30 days of the completion of the inspection.
This Charter may be modified should the team develop significant new information that
warrants review. Should you have any questions concerning this Charter, contact me at
(817) 860-8148.
A2-3 Attachment 2
ATTACHMENT 3
SIGNIFICANCE DETERMINATION EVALUATION
Comanche Peak Steam Electric Station
EDG Inoperability Caused By Painting Activities
Significance Determination Basis
1. Phase 1 Screening Logic, Results, and Assumptions
In accordance with NRC Inspection Manual Chapter 0612, Appendix B, Issue
Screening, the team determined that this finding represented a licensee performance
deficiency. The team then determined that the issue was more than minor because it
was associated with the equipment performance attribute and affected the mitigating
systems cornerstone objective to ensure the availability, reliability, or function of a
system or train in a mitigating system in that Emergency Diesel Generator DG-102
would not have started upon demand.
The team evaluated this finding using the SDP Phase 1 Screening Worksheet for the
Initiating Events, Mitigating Systems, and Barriers Cornerstones, provided in Manual
Chapter 0609, Appendix A, Determining the Significance of Reactor Inspection
Findings for At-Power Situations. For this finding, a Phase 2 estimation was required
because the performance deficiency affected the emergency power supply system that
is a support system for both mitigating and containment barrier systems.
2. Phase 2 Risk Estimation
In accordance with Manual Chapter 0609, Appendix A, Attachment 1, User Guidance
for Phase 2 and Phase 3 Significance Determination of Reactor Inspection Findings for
At-Power Situations, the senior reactor analyst evaluated the subject finding using the
Risk-Informed Inspection Notebook for Comanche Peak Steam Electric Station, Units 1
and 2, Revision 2.01a. The following assumptions were made:
a. The identified performance deficiency occurred some time between the last
successful test on October 24, 2007, and the test failure that occurred on
November 21, 2007.
b. In accordance with Manual Chapter 0609, Appendix A, Attachment 2, Site
Specific Risk-Informed Inspection Notebook Usage Rules, Rule 1.1, Exposure
Time, the analyst determined the time frame over which the finding impacted
the risk of plant operations. Because the exact time of failure was unknown, an
exposure time of t/2 from the last valid test was used. This was 1/2 of the 28 days
between tests, or 14 days. Therefore, for the phase 2 analysis, the exposure
time used to represent the time that the performance deficiency affected plant
risk was between 3 and 30 days.
A3-1 Attachment 3
c. Table 2 of the risk-informed notebook requires that when a performance
deficiency affects the diesel generators, the following initiating event scenarios
are applicable: LOOP and LEAC. Therefore, the analyst utilized these
worksheets from the risk-informed notebook.
d. According to the risk-informed notebook, Table 1, for a 3-30 day exposure, the
initiating event likelihood should be 3 for a loss of offsite power and 5 for a loss
of offsite power with loss of one vital 6.9kV bus.
e. The analyst gave no operator action credit as discussed in Manual
Chapter 0609, Appendix A, Attachment 1, Table 4, Remaining Mitigation
Capability Credit. The requirements to have procedures in place and to have
trained the operators in recovery under similar conditions for such credit were not
met.
The dominant sequences from the notebook were documented below:
TABLE C.b
Failure of Emergency Diesel Generator 102 to Start
Phase 2 Sequences
Initiating Event Sequence Mitigating Functions Results
Loss of Offsite Power 2 LOOP-AFW-FB 8
4 LOOP-EAC-REC5 6
7 LOOP-EAC-TDAFW 6
Loss of Offsite Power with 1 LEAC-PORV-HPR-MKRWST 8
Loss of One Vital 6.9 kV Bus LEAC-PORV-HPI 7
3
Using the counting rule worksheet, the result from this estimation indicated that
the finding was of low to moderate safety significance (WHITE). However, the
analyst determined that this estimate did not include a full coverage of the risk
related to the failure identified and that a better evaluation of the internal risk
would be necessary for fully assessing the risk related to external initiators.
3. Phase 3 Analysis
In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3
analysis using the Standardized Plant Analysis Risk (SPAR) Model for Comanche Peak,
Revision 3.31, dated August 2006, to simulate the failed Diesel Generator 1-02.
Additionally, the analyst conducted an assessment of the risk contributions from external
initiators using insights and/or values provided by the licensees probabilistic risk
assessment model, in the licensees recent submittal for extension of completion times
for diesel generators (Reference 1), and simplified fire probabilistic risk assessment.
Reference 1: Letter dated November 15, 2007, Blevins to U.S. NRC, Subject: Comanche Peak Steam Electric Station (CPSES)
Docket Nos. 50-445 and 50-446, Response to Request for Additional Information Related to Licence Amendment Request (LAR)06-009,
Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating; Extension of Completion Times for Diesel Generators.
A3-2 Attachment 3
Assumptions
To evaluate the change in risk caused by this performance deficiency, the analyst made
the following assumptions:
A. The vital batteries at Comanche Peak will deplete after approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of full
postaccident loads without an operating battery charger, assuming that operators do
not take actions to shed unnecessary loads from the vital dc buses. This is the
value used in the licensees probabilistic risk assessment.
B. The Comanche Peak SPAR model, Revision 3.31, represents an appropriate tool for
evaluation of the subject finding.
C. The failure of Emergency Diesel Generator 1-02 was the result of binding of the fuel
rack on at least one injection pump that was caused by painting activities on and
around the diesel.
D. Emergency Diesel Generator 1-02 successfully started and loaded during a
surveillance performed on October 24, 2007. The diesel failed to start during a
surveillance on November 21, 2007, because the fuel rack on at least one injection
pump was bound to the extent that the entire fuel rack assembly was unable to leave
the no fuel position.
E. Painting activities in and around the Emergency Diesel Generator 1-02 engine
ended on November 1, 2007. Therefore, the conditions that caused the engine to
fail had to have been in place at that time for the root cause to be valid (See
Assumption C).
F. The exposure time used for evaluating this finding should be determined in
accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2, Site
Specific Risk-Informed Inspection Notebook Usage Rules. Attachment 2 discusses
the approach to establishing the exposure time that should be used for the
significance determination process. Step 1.1 states:
The exposure time used in determining the initiating event likelihood should
correspond to the time period that the condition being assessed is reasonably
known to have existed. If the inception of the condition is unknown, then an
exposure time of one half of the time period since the last successful
demonstration of the component or function (t/2) should be used.
G. The appropriate exposure time (EXP), representing the time that Emergency Diesel
Generator 1-02 was not functional, for use in this evaluation is 24 days.
The exact time at which the residual paint that caused the binding of the fuel
racks occurred is unknown. However, it is reasonable to assume that the
condition existed after the completion of painting activities on November 1, 2007.
A3-3 Attachment 3
Therefore, in accordance with Assumption F, Emergency Diesel Generator 1-02
would not have started upon demand for the 20 days November 1 through
November 21, 2007.
Additionally, the inception of the condition could have occurred any time between
the last successful run of the machine on October 24 and the completion of the
painting activities on November 1. Therefore, in accordance with Assumption F,
Emergency Diesel Generator 1-02 would not have started upon demand for one
half of the period from October 24 through November 1, or for an additional 4-
day period.
Based on these two arguments, the analyst determined that the appropriate
exposure time was the sum of the 20 days that the machine was reasonably
assumed to have failed and one half the 8 day period that could have resulted in
the failure condition.
H. Given the condition of the fuel rack and the interpretation by licensed operators of
annunciator response procedures, operators would not have been able to recover
Emergency Diesel Generator 1-02 prior to postulated core damage for sequences
less than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Licensed operators stated that the annunciator response
procedure would not have directed operators to manipulate the fuel racks by hand
nor does it require operators to request maintenance personnel perform such a task.
I. The appropriate nonrecovery probability for sequences longer than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> is 0.29.
The analyst conducted a human reliability analysis using the SPAR-H method to
determine an appropriate nonrecovery probability. To calculate this value, the
analyst used the following assumptions:
a. The analyst assumed that nominal time was available for recovery diagnosis and
action. The licensee recovered the diesel in 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> 11 minutes during
nonemergency conditions. Therefore, the analyst assumed that, if required,
recovery could have been reasonably performed within the 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> coping period
plus extended boil down times.
b. The analyst assumed that emergency response personnel would be under high
stress during the diagnosis and recovery. This is based primarily on the belief
that recovery personnel would know that the consequences of the task would
represent a direct threat to plant safety.
c. The complexity of this task was considered to be nominal. There is some
ambiguity in the diagnosis. However, there are only two fundamental paths in
diagnosis. The probability that the wrong path would be initially investigated is
taken into account in the performance shaping factor for procedure quality.
d. Procedures for the diagnosis were incomplete. Solely following the procedures
available would not have led to recovery. The basic items to consider were
available in the annunciator response procedure, although it is not clear that this
procedure would have been governing and/or utilized by the recovery personnel.
A3-4 Attachment 3
e. All other performance shaping factors were considered nominal for obvious
reasons.
J. Emergency Diesel Generator 1-01 would not have failed from the same cause as
Emergency Diesel Generator 1-02 because painting activities had not been
conducted on that diesel. Therefore, the analyst left the common cause failure
probability at its nominal value.
K. The nominal nonrecovery values used by the SPAR model are for the average
nonrecovery for either of two diesel generators. Therefore, given that recovery of
Emergency Diesel Generator 1-02 would be handled separately, the analyst
adjusted the generic nonrecovery value to account for only Emergency Diesel
Generator 1-01 being the only machine available for random failure recovery.
L. The nominal likelihood for a loss of offsite power was unaffected by the subject
finding.
M. Evaluating the risk contribution of this finding related to seismic events is
appropriately conducted by utilizing the licensees assessment found in Reference 1.
The conditional core damage frequency (CCDFSEISMIC) given by the licensee was
2.1 x 10-6/year.
N. The licensees fire risk model is an appropriate tool for evaluation of the subject
finding. The CCDF for fire (CCDFFIRE) provided by the licensee in Reference 1 was
7.8 x 10-6/year.
The analyst independently evaluated the risk change related to internal fires.
These insights were then used to challenge and evaluate the results of the
licensees model. In all cases, the licensees model covered the scenarios
posed by the analyst and included a larger scope of fires than was feasible for
the analyst to evaluate.
O. Traditionally, the initiation of most high wind events, including those that cause a
loss of offsite power, are included in the licensees PRA and/or the SPAR model.
However, the licensees assessment in their individual plant evaluation for external
events did not include events that damage other pieces of equipment that may affect
risk. As stated in Reference 1, the licensee estimated the CCDF for tornados
(CCDFWIND) given the failure of a diesel generator to be 2.3 x 10-5/year.
P. The best estimate of the risk contribution from the subject finding related to internal
flooding is best evaluated using a ratio from the licensees PRA as was discussed in
Reference 1. In their evaluation, the licensee stated that the risk from internal
flooding derived from their internal events PRA was approximately 1 percent (PFLOOD)
of the total plant core damage frequency.
Q. The ratio of sequences going to core damage in the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to those going
through battery depletion is the same for internal and external initiators. This
A3-5 Attachment 3
assumption permits the analyst to use the ratio from the internal events SPAR in
applying recovery to external initiators.
R. The differences between the SPAR and the licensees models were inconsequential.
The analyst, in reviewing the differences between the models, determined that there
were several global differences including: the lack of random failure recovery for
diesel generators in the licensees model and the lack of convolution integrals in the
SPAR model. However, the analyst determined that these differences were not of
consequence to this evaluation because the final results were within the same color
band.
Internal Initiating Events
The senior reactor analyst used the SPAR model for CPSES to estimate the change in
risk associated with internal initiators that was caused by the finding. Average test and
maintenance of modeled equipment was assumed and a cutset truncation of 1.0E-12
was used.
Consistent with guidance in the RASP Handbook, including NRC document,
Common-Cause Failure Analysis in Event Assessment (June 2007), and Assumptions
3.C, 3.G, and 3.K, the SRA modeled the condition by adjusting the following basic
events in the SPAR model:
Basic Event Original Value Conditional Value
-3
EPS-DGN-FS-1EG1 5.0 X 10 TRUE
EPS-XHE-XL-NR01H 7.72 X 10-1 8.79 X 10-1
EPS-XHE-XL-NR02H 6.48 X 10-1 8.05 X 10-1
EPS-XHE-XL-NR03H 5.56 X 10-1 7.46 X 10-1
EPS-XHE-XL-NR04H 4.84 X 10-1 6.95 X 10-1
The SPAR baseline core damage frequency (CDFBASE) was 1.80 x 10-5/year. The
evaluation case for the above change set resulted in a conditional core damage
frequency (CCDFSPAR) of 3.78 x 10-4/year. The dominant core damage sequences were
documented in the table below:
A3-6 Attachment 3
Initiating Event Sequence Preponderant Failures Frequency
Loss of Offsite 20-03 Failure of EDG 1-01 with 2.62 x 10-4/year
Power Battery Depletion at 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
20-06 Failure of EDG 1-01 with 6.56 x 10-5/year
Battery Depletion at 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
combined with RCS Pump
Seal Failure .
20-45 Failure of EDG 1-01 and the 2.37 x 10-5/year
Turbine-Driven Auxiliary
Feedwater Pump with Core
Damage at 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
19 Failure of Motor and Turbine- 1.07 x 10-5/year
Driven Auxiliary Feedwater
Pumps and/or Operator Fails
to Control.
The change in incremental conditional core damage frequency (ICCDP) was calculated
as follows:
ICCDF = CCDFSPAR - CDFbase
= 3.78 x 10-4/year - 1.80 x 10-5/year
= 3.60 x 10-4/year
Given Assumptions 3.C through 3.G, the exposure time, representing the time that the
performance deficiency impacted the plant, for this analysis was 24 days. Therefore,
the change in core damage frequency (CDFIntNR) caused by this finding, without
applying any recovery to the subject condition, and related to internal initiators was
calculated as follows:
CDFIntNR = ICCDF * EXP
= 3.60 x 10-4/year * (24 days ÷ 365 days/year)
= 2.37 x 10-5
Given Assumption 3.H, the analyst determined that recovery credit for Emergency
Diesel Generator 1-01 would not be provided for any sequence that led to core damage
in less than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Using utilities in the SAPHIRE software to slice cutsets by basic
event, the analyst determined that 7.6 percent of all internal cutsets went to core
damage in less than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (PSHORT).
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of 0.29 to all
A3-7 Attachment 3
remaining cutsets. Therefore, the change in core damage frequency (CDFInternal)
caused by this finding and related to internal initiators was calculated as follows:
CDFInternal = [CDFIntNR * PSHORT] + [CDFIntNR * (1 - PSHORT) * PNR]
= [2.37 x 10-5 * 0.076] + [2.37 x 10-5 * (1 - 0.076) * 0.29]
= 8.15 x 10-6
External Initiating Events
In accordance with Manual Chapter 0609, Appendix A, Attachment 1, Step 2.2.5,
Screen for the Potential Risk Contribution Due to External Initiating Events, the analyst
assessed the impact of external initiators on each of the findings, because the Phase 2
SDP result provided a Risk Significance Estimation of 7 or greater. The analyst
determined that, for the risk of an external initiator to be impacted by this performance
deficiency, the external event would have to cause a loss of offsite power that was not
accounted for in the internal events model. Using the licensees individual plant
evaluation for external events and Reference 1, the analyst determined that the
dominant sequences affected by the subject performance deficiency were from seismic
events, high winds, fire, and internal flooding events.
A. Seismic Event Initiators
As discussed in Assumption 3.M, the analyst utilized the licensees value
for the affects on the risk of seismic events associated with a failed diesel
generator. The incremental risk without recovery (ICCDPSeisNR) was
calculated as follows:
ICCDPSeisNR = CCDFSEISMIC * EXP
= 2.1 x 10-6/year * (24 days ÷ 365 days/year)
= 1.38 x 10-7
Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying
the change in risk from seismic events.
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of
0.29 to the remaining portion of the risk from seismic events. Therefore,
the change in core damage frequency (CDFSEISMIC) caused by this
finding and related to seismic events was calculated as follows:
CDFSEISMIC = [ICCDPSeisNR * PSHORT] + [ICCDPSeisNR * (1 - PSHORT) * PNR]
= [1.38 x 10-7 * 0.076] + [1.38 x 10-7 * (1 - 0.076) * 0.29]
= 4.75 x 10-8
A3-8 Attachment 3
B. Internal Fire Initiators
As discussed in Assumption 3.N, the analyst utilized the licensees value
for the affects on the risk of internal fires associated with a failed diesel
generator. The incremental risk without recovery (ICCDPFireNR) was
calculated as follows:
ICCDPFireNR = CCDFFIRE * EXP
= 7.8 x 10-6/year * (24 days ÷ 365 days/year)
= 5.14 x 10-7
Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying
the change in risk from internal fires.
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of
0.29 to the remaining portion of the risk from seismic events. Therefore,
the change in core damage frequency (CDFFIRE) caused by this finding
and related to seismic events was calculated as follows:
CDFFIRE = [ICCDPFireNR * PSHORT] + [ICCDPFireNR * (1 - PSHORT) * PNR]
= [5.14 x 10-7 * 0.076] + [5.14 x 10-7 * (1 - 0.076) * 0.29]
= 1.77 x 10-7
C. Tornados and High Wind Initiators
As discussed in Assumption 3.O, the analyst utilized the licensees value
for the affects on the risk of high wind events associated with a failed
diesel generator. The incremental risk without recovery (ICCDFWindNR)
was calculated as follows:
ICCDPWindNR = CCDFWIND * EXP
= 2.1 x 10-5/year * (24 days ÷ 365 days/year)
= 1.38 x 10-6
Given Assumption 3.H and 3.Q, the analyst applied PSHORT in quantifying
the change in risk from high wind events.
Given Assumption 3.I, the analyst applied a nonrecovery factor (PNR) of
0.29 to the remaining portion of the risk from high wind events.
Therefore, the change in core damage frequency (CDFWIND) caused by
this finding and related to seismic events was calculated as follows:
A3-9 Attachment 3
CDFWIND = [ICCDPWindNR * PSHORT] + [ICCDPWindNR * (1 - PSHORT) * PNR]
= [1.38 x 10-6 * 0.076] + [1.38 x 10-6 * (1 - 0.076) * 0.29]
= 4.75 x 10-7
D. Internal Flooding Initiators
As discussed in Assumption 3.O, the analyst utilized the ratio determined
by the licensees PRA for internal flooding to other initiators. Given a
value of 1 percent, the change in core damage frequency (CDFFLOOD)
caused by this finding and related to internal flooding was calculated as
follows:
CDFFLOOD = CDFInternal * PFLOOD
= 8.15 x 10-6 * 0.01
= 8.15 x 10-8
Total Change in Core Damage Frequency
Given that each of the initiators in this analysis were treated to ensure that the final
probabilities were independent of each other, the analyst determined that he total
change in core damage frequency (CDF) could be calculated by taking the sum of
each independent change. Therefore, the final Phase 3 result was calculated as
follows:
CDF = CDFInternal + CDFExternal
= CDFInternal + [CDFSEISMIC + CDFFIRE + CDFWIND + CDFFLOOD]
= 8.15 x 10-6 + [4.75 x 10-8 + 1.77 x 10-7 + 4.75 x 10-7 + 8.15 x 10-8]
= 8.93 x 10-6
This result indicated that the finding was of low to moderate significance to the risk of
internal initiating events.
Large Early Release Frequency Contribution
In accordance with Manual Chapter 0609, Appendix A, Attachment 1, Step 2.2.6,
Screen for the Potential Risk Contribution Due to LERF, the analyst assessed the
impact on the large early release frequency because the Phase 2 SDP result provided a
risk significance estimation of greater than 7.
Using NRC Inspection Manual Chapter 0609 Appendix H, Containment Integrity
Significance Determination Process, the senior reactor analyst determined that this was
a Type A finding (i.e., a finding that can influence the likelihood of accidents leading to
A3-10 Attachment 3
core damage that is also a LERF contributor). For a pressurized water reactor with a
large, dry containment, like Comanche Peak Steam Electric Station, findings related to
inter-system loss-of-coolant accidents and steam generator tube ruptures have the
potential to impact LERF.
Appendix H, Table 5.1, "Phase 1 Screening - Type A Findings at Full Power," provides
that station blackout scenarios and all other transients, including loss of offsite power
initiators, screen out from further evaluation. These accident sequences are not
considered to be significant to LERF. Therefore, the estimated LERF was calculated
to be less than 6.8 x 10-7. Because the LERF was less than the 1 x 10-6 White/Yellow
threshold, the finding remains characterized as of low to moderate safety significance
(White).
A3-11 Attachment 3