{{#Wiki_filter:April 21, 2008  
{{#Wiki_filter:UNITED STATES
  D. J. Bannister  
                                  NU CLE AR RE GU LATOR Y C O M M I S S I O N
Vice President and CNO Omaha Public Power District Fort Calhoun Station FC-2-4 Adm. P.O. Box 550 Fort Calhoun, NE 68023-0550  
                                                      R EGI ON I V
                                          611 R YAN PLAZA D R IV E, SU ITE 400
                                            AR LI N GTON , TEXAS 76011-4005
                                                April 21, 2008
D. J. Bannister
Vice President and CNO
Omaha Public Power District
Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550
Fort Calhoun, NE 68023-0550
SUBJECT:        FORT CALHOUN STATION - NOTIFICATION OF AN NRC TRIENNIAL FIRE
                PROTECTION BASELINE INSPECTION 05000285/2008006
Dear Mr. Bannister:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),
Region IV staff will conduct a triennial fire protection baseline inspection at your Fort Calhoun
Station in July and August of 2008. The inspection team will be comprised of reactor inspectors
from the NRC Region IV office and a contractor. The team will conduct the inspection in
accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection (Triennial)."
The schedule for the inspection is as follows:
        *      Information gathering visit: July 8-10, 2008
        *      Onsite inspection:                July 28-August 1, 2008
                                                  August 11-15, 2008
The team will visit the Fort Calhoun Station on July 8-10, 2008, to gather information, select the
fire areas for evaluation, identify documents needed to support the inspection, obtain
unescorted access, and to become familiar with your fire protection program. The enclosure to
this letter provides an initial list of the documents the team will want to review. The team leader
will request that you transmit copies of some of the documents to the NRC Region IV office for
team use in preparation for the inspection. We would appreciate it if you could send this
information so that it will arrive in our office in Arlington, Texas, by the dates listed in the
enclosure.
We request that during the onsite inspection weeks, you ensure that copies of analyses,
evaluations, or documentation regarding the implementation and maintenance of the fire
protection program, including post-fire safe shutdown capability, be readily accessible to the
team for their review. Of specific interest are those documents that establish that your fire
protection program satisfies NRC regulatory requirements and conforms to applicable NRC and


SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF AN NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION 05000285/2008006
Omaha Public Power District                  -2-
Dear Mr. Bannister:  
industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),  
systems required to achieve and maintain safe shutdown conditions from inside and outside the
Region IV staff will conduct a triennial fire protection baseline inspection at your Fort Calhoun Station in July and August of 2008.  The inspection team will be comprised of reactor inspectors from the NRC Region IV office and a contractor. The team will conduct the inspection in accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection (Triennial).
control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant
fire protection systems, and (4) the fire protection program and its implementation should be
The schedule for the inspection is as follows:
available to support the team at the site during the inspection.
* Information gathering visit:  July 8-10, 2008 * Onsite inspection: July 28-August 1, 2008    August 11-15, 2008
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Your cooperation and support during this inspection will be appreciated. If you have questions
concerning this inspection or the inspection team's information or logistical needs, please
contact Greg Pick at 817-860-8270.
                                              Sincerely,
                                                /RA/
                                              Linda J. Smith, Chief
                                              Engineering Branch 2
                                              Division of Reactor Safety
Docket: 50-285
License: DPR-40
Enclosure: Triennial Fire Protection
  Inspection Supporting Documentation
cc:
Joe l. McManis,
Manager - Nuclear Licensing
Omaha Public Power District
Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550
Fort Calhoun, NE 68023-0550
Winston & Strawn
Attn: James R. Curtiss
1700 K Street NW
Washington, DC 20006-3817
Chairman
Washington County Board of Supervisors
P.O. Box 466
Blair, NE 68008


The team will visit the Fort Calhoun Station on July 8-10, 2008, to gather information, select the fire areas for evaluation, identify documents needed to support the inspection, obtain unescorted access, and to become familiar with your fire protection program. The enclosure to this letter provides an initial list of the documents the team will want to review.  The team leader
Omaha Public Power District            -3-
will request that you transmit copies of some of the documents to the NRC Region IV office for team use in preparation for the inspection.  We would appreciate it if you could send this information so that it will arrive in our office in Arlington, Texas, by the dates listed in the enclosure.
Julia Schmitt, Manager
We request that during the onsite inspection weeks, you ensure that copies of analyses, evaluations, or documentation regarding the implementation and maintenance of the fire
Radiation Control Program
protection program, including post-fire safe shutdown capability, be readily accessible to the team for their review. Of specific interest are those documents that establish that your fire protection program satisfies NRC regulatory requirements and conforms to applicable NRC and
Nebraska Health & Human Services
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV611 RYAN PLAZA DRIVE, SUITE 400ARLINGTON, TEXAS 76011-4005
Dept. of Regulation & Licensing
Omaha Public Power District - 2 -
Division of Public Health Assurance
  industry fire protection guidance.  Also, appropriate personnel knowledgeable of:  (1) plant systems required to achieve and maintain safe shutdown conditions from inside and outside the control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant
301 Centennial Mall, South
fire protection systems, and (4) the fire protection program and its implementation should be available to support the team at the site during the inspection. 
P.O. Box 95007
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Lincoln, NE 68509-5007
Your cooperation and support during this inspection will be appreciated.  If you have questions concerning this inspection or the inspection team's information or logistical needs, please contact Greg Pick at 817-860-8270.
Melanie Rasmussen
Bureau of Radiological Health
Iowa Department of Public Health
Lucas State Office Building, 5th Floor
321 East 12th Street
Des Moines, IA 50319
Ronald L. McCabe, Chief
Technological Hazards Branch
National Preparedness Division
DHS/FEMA
9221 Ward Parkway
Suite 300
Kansas City, MO 64114-3372


      Sincerely,
Omaha Public Power District              -4-
/RA/
Electronic distribution by RIV:
      Linda J. Smith, Chief      Engineering Branch 2      Division of Reactor Safety
Regional Administrator (Elmo.Collins@nrc.gov)
Docket:   50-285
DRP Director (Dwight.Chamberlain@nrc.gov)
License: DPR-40
DRS Director (Roy.Caniano@nrc.gov)
Enclosure: Triennial Fire Protection    Inspection Supporting Documentation
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (John.Hanna@nrc.gov)
cc: Joe l. McManis,  Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
P.O. Box 550 Fort Calhoun, NE  68023-0550
Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)
Winston & Strawn Attn:  James R. Curtiss 1700 K Street NW Washington, DC  20006-3817
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
SUNSI Review Completed: _GAP__ADAMS: X Yes                Initials: __GAP____
X Publicly Available            X Non-Sensitive
S:\DRS\REPORTS\FC2008006-GAP                              ML081120496
SRI:DRS/EB2          C: EB2
GAP/tek              LJSmith
04/    /08          04/    /08
OFFICIAL RECORD COPY T=Telephone                E=E-mail F=Fax


Chairman Washington County Board of Supervisors P.O. Box 466 Blair, NE  68008
                                            ENCLOSURE
                Triennial Fire Protection Inspection Documentation Requested
Please provide the following documentation prior to the onsite information-gathering trip,
preferably no later than June 23, 2008. Where practical, please provide copies electronically.
1.      The current version of your fire protection program and fire hazards analysis.
2.      Post-fire safe shutdown analysis and the supporting calculations that demonstrate
        acceptable plant response.
3.       Copies of the licensing basis documents for fire protection (Safety Evaluation Reports,
        pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters
        to/from the NRC regarding fire protection/fire safe shutdown, etc.).
4.      The Fire PRA or portions of the plants IPEEE addressing fire events.
Please provide the following documentation during the information-gathering visit or by
July 18, 2008, in order to support inspection preparation. Where practical, please provide
copies electronically. However, drawings should be provided as paper copies of sufficient size
that all details are legible.
5.      Fire protection program implementing procedures (e.g., administrative controls, operator
        response procedures for fires, fire fighting procedures, etc.).
6.      Operating procedures used for achieving and maintaining hot and cold shutdown
        conditions from the control room in the event of a fire outside the control room (III.G.2
        areas).
7.      Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)
        capability with or without control room evacuation.
8.      Pre-fire plans for the selected fire areas (areas to be selected by the team during the
        information-gathering trip).
9.      A list of equipment used to achieve and maintain hot standby and cold shutdowns in the
        event of a fire (safe shutdown equipment lists).
10.      Piping and instrumentation (flow) diagrams showing the components used to achieve
        and maintain hot standby and cold shutdowns for fires outside the control room and
        those components used for those areas requiring alternative shutdown capability. Two
        copies of the piping and instrumentation (flow) diagrams for these systems of a size
        sufficient to read all details. These should include the systems used for RCS makeup,
        RCS pressure control, decay heat removal, and reactivity control, including the essential
        support systems.


 
11. Plant layout and equipment drawings for the selected fire areas that identify (a) the
Omaha Public Power District - 3 -
    physical plant locations of major hot standby and cold shutdown equipment; (b) plant fire
Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services Dept. of Regulation & Licensing
    area and/or fire zone delineation; and (c) the locations of fire protection equipment, such
Division of Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE  68509-5007
    as detection, suppression, and post-fire emergency lighting units, and (d) fire area
    boundaries.
Melanie Rasmussen Bureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA  50319
12. A listing of design change packages, which were determined to impact fire protection
    and post-fire safe shutdowns, performed in the last 3 years.
Ronald L. McCabe, Chief Technological Hazards Branch National Preparedness Division DHS/FEMA 9221 Ward Parkway
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.
Suite 300 Kansas City,  MO  64114-3372
14. A listing of open and closed corrective action documents initiated in the last 3 years,
      
    which relate to the fire protection program or equipment. Include corrective action
Omaha Public Power District - 4 -
     document number, date, and subject.
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) DRP Director (Dwight.Chamberlain@nrc.gov) DRS Director (Roy.Caniano@nrc.gov)
15. A listing of the applicable codes and standards (with the versions) related to the design
DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (John.Hanna@nrc.gov) Branch Chief, DRP/E (Jeff.Clark@nrc.gov) Senior Project Engineer, DRP/E (George.Replogle@nrc.gov) Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)  
    of plant fire protection features and evaluations of any code deviations.
RITS Coordinator (Marisa.Herrera@nrc.gov)
16. Drawings of the portions of the emergency lighting system which support fire response.
     
17. Procedures used to remove smoke from safety-related areas and the engineering
   
    studies or calculations which support the design basis.
   
18. Drawings of communication systems credited in the license basis for firefighting and
   
    plant operations during fires where control room is occupied and/or evacuated.
   
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
  SUNSI Review Completed:  _GAP__ ADAMS:  X  Yes            Initials: __GAP____  X  Publicly Available      X  Non-Sensitive
20. A listing of maintenance and surveillance testing procedures for alternative shutdown
S:\DRS\REPORTS\FC2008006-GAP    ML081120496 SRI:DRS/EB2 C: EB2    GAP/tek LJSmith   
    capability and fire barriers, detectors, pumps and suppression systems.
      04/      /08 04/      /08      
21. Maintenance Rule performance criteria and a summary of the last 3 years performance
OFFICIAL RECORD COPY  T=Telephone          E=E-mail        F=Fax 
    history for fire protection program systems or functions monitored within the
ENCLOSURE  Triennial Fire Protection Inspection Documentation Requested
    Maintenance Rule program.
  Please provide the following documentation prior to the onsite information-gathering trip, preferably no later than June 23, 2008. Where practical, please provide copies electronically.
22. A copy of fire protection program requirements (e.g. limiting conditions for operation,
1. The current version of your fire protection program and fire hazards analysis.
    surveillance test requirements) covered by Technical Specifications, Technical
    Requirements Manual, UFSAR, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar
     reviews related to post-fire safe shutdown capability or the fire protection program
    completed since July 1, 2005.
24. A list of manual actions taken outside the control room which are credited to mitigate the
    consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should
    group actions by the initiating fire area or zone and indicate where the action must take
    place.
25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design
    basis documents that describe the purpose/function/operating characteristics of the safe


2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate acceptable plant response. 
    shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports, pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters to/from the NRC regarding fire protection/fire safe shutdown, etc.).
    reactivity control, including the essential support systems).
4. The Fire PRA or portions of the plant's IPEEE addressing fire events.
26. Two copies of one-line diagrams of the electrical distribution system. These should
Please provide the following documentation during the information-gathering visit or by July 18, 2008, in order to support inspection preparation.  Where practical, please provide
    depict how power gets from the switchyard to ESF loads (480V and 4160V). Also,
copies electronically.  However, drawings should be provided as paper copies of sufficient size that all details are legible. 
    include the vital DC distribution system one-line diagrams.
5. Fire protection program implementing procedures (e.g., administrative controls, operator response procedures for fires, fire fighting procedures, etc.). 
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant,
6. Operating procedures used for achieving and maintaining hot and cold shutdown conditions from the control room in the event of a fire outside the control room (III.G.2 areas). 
    giving location and the key equipment being protected.
7. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas) capability with or without control room evacuation.
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or
8. Pre-fire plans for the selected fire areas (areas to be selected by the team during the information-gathering trip). 
    maintain hot shutdown and b) reach and/or maintain cold shutdown.
9. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the event of a fire (safe shutdown equipment lists).
29. A list of high to low pressure interface valves.
10. Piping and instrumentation (flow) diagrams showing the components used to achieve and maintain hot standby and cold shutdowns for fires outside the control room and those components used for those areas requiring alternative shutdown capability.  Two
30. A copy of procedures governing the training and operation of the fire brigade.
copies of the piping and instrumentation (flow) diagrams for these systems of a size sufficient to read all details.  These should include the systems used for RCS makeup, RCS pressure control, decay heat removal, and reactivity control, including the essential support systems.
31. Organization charts of site personnel down to the level of fire protection staff personnel.
 
32. A contact list of key site personnel who will be supporting this inspection, giving location
11. Plant layout and equipment drawings for the selected fire areas that identify (a) the physical plant locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or fire zone delineation; and (c) the locations of fire protection equipment, such as detection, suppression, and post-fire emergency lighting units, and (d) fire area boundaries. 
    of their office and phone number onsite.
12. A listing of design change packages, which were determined to impact fire protection and post-fire safe shutdowns, performed in the last 3 years.
33. The team would like to observe a fire brigade drill in the plant, if possible, during the
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.
    week of August 11, 2008. Please put us in contact with the appropriate personnel for
 
    planning drills during the onsite information gathering trip.
14. A listing of open and closed corrective action documents initiated in the last 3 years, which relate to the fire protection program or equipment.  Include corrective action document number, date, and subject.
34. The team would like to perform a walkthrough of the procedure for control room due to
15. A listing of the applicable codes and standards (with the versions) related to the design of plant fire protection features and evaluations of any code deviations.
    fire with qualified operators in the plant during the week of July 28, 2008. Please put us
16. Drawings of the portions of the emergency lighting system which support fire response. 
    in contact with the appropriate personnel for planning the walkthrough during the onsite
17. Procedures used to remove smoke from safety-related areas and the engineering studies or calculations which support the design basis.
    information gathering trip.
18. Drawings of communication systems credited in the license basis for firefighting and plant operations during fires where control room is occupied and/or evacuated.
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
 
20. A listing of maintenance and surveillance testing procedures for alternative shutdown capability and fire barriers, detectors, pumps and suppression systems.
21. Maintenance Rule performance criteria and a summary of the last 3 years' performance history for fire protection program systems or functions monitored within the Maintenance Rule program.
22. A copy of fire protection program requirements (e.g. limiting conditions for operation, surveillance test requirements) covered by Technical Specifications, Technical
Requirements Manual, UFSAR, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar reviews related to post-fire safe shutdown capability or the fire protection program completed since July 1, 2005.
24. A list of manual actions taken outside the control room which are credited to mitigate the consequences of fires in III.G.2 areas (non-alternative shutdown areas).  The list should group actions by the initiating fire area or zone and indicate where the action must take place.  25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design basis documents that describe the purpose/function/operating characteristics of the safe 
shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and reactivity control, including the essential support systems).  
26. Two copies of one-line diagrams of the electrical distribution system. These should depict how power gets from the switchyard to ESF loads (480V and 4160V). Also,  
include the vital DC distribution system one-line diagrams.
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant, giving location and the key equipment being protected.  
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or maintain hot shutdown and b) reach and/or maintain cold shutdown.  
29. A list of high to low pressure interface valves.  
30. A copy of procedures governing the training and operation of the fire brigade.  
31. Organization charts of site personnel down to the level of fire protection staff personnel.  
32. A contact list of key site personnel who will be supporting this inspection, giving location of their office and phone number onsite.  
33. The team would like to observe a fire brigade drill in the plant, if possible, during the week of August 11, 2008. Please put us in contact with the appropriate personnel for planning drills during the onsite information gathering trip.  
34. The team would like to perform a walkthrough of the procedure for control room due to fire with qualified operators in the plant during the week of July 28, 2008. Please put us in contact with the appropriate personnel for planning the walkthrough during the onsite information gathering trip.
}}
}}

Revision as of 17:36, 14 November 2019

Notification of an NRC Triennial Fire Protection Baseline Inspection 05000285-08-006
ML081120496
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/21/2008
From: Laura Smith
NRC/RGN-IV/DRS/EB2
To: Bannister D
Omaha Public Power District
References
IR-08-006
Download: ML081120496 (7)


See also: IR 05000285/2008006

Text

UNITED STATES

NU CLE AR RE GU LATOR Y C O M M I S S I O N

R EGI ON I V

611 R YAN PLAZA D R IV E, SU ITE 400

AR LI N GTON , TEXAS 76011-4005

April 21, 2008

D. J. Bannister

Vice President and CNO

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF AN NRC TRIENNIAL FIRE

PROTECTION BASELINE INSPECTION 05000285/2008006

Dear Mr. Bannister:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),

Region IV staff will conduct a triennial fire protection baseline inspection at your Fort Calhoun

Station in July and August of 2008. The inspection team will be comprised of reactor inspectors

from the NRC Region IV office and a contractor. The team will conduct the inspection in

accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection (Triennial)."

The schedule for the inspection is as follows:

  • Information gathering visit: July 8-10, 2008
  • Onsite inspection: July 28-August 1, 2008

August 11-15, 2008

The team will visit the Fort Calhoun Station on July 8-10, 2008, to gather information, select the

fire areas for evaluation, identify documents needed to support the inspection, obtain

unescorted access, and to become familiar with your fire protection program. The enclosure to

this letter provides an initial list of the documents the team will want to review. The team leader

will request that you transmit copies of some of the documents to the NRC Region IV office for

team use in preparation for the inspection. We would appreciate it if you could send this

information so that it will arrive in our office in Arlington, Texas, by the dates listed in the

enclosure.

We request that during the onsite inspection weeks, you ensure that copies of analyses,

evaluations, or documentation regarding the implementation and maintenance of the fire

protection program, including post-fire safe shutdown capability, be readily accessible to the

team for their review. Of specific interest are those documents that establish that your fire

protection program satisfies NRC regulatory requirements and conforms to applicable NRC and

Omaha Public Power District -2-

industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant

systems required to achieve and maintain safe shutdown conditions from inside and outside the

control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant

fire protection systems, and (4) the fire protection program and its implementation should be

available to support the team at the site during the inspection.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection or the inspection team's information or logistical needs, please

contact Greg Pick at 817-860-8270.

Sincerely,

/RA/

Linda J. Smith, Chief

Engineering Branch 2

Division of Reactor Safety

Docket: 50-285

License: DPR-40

Enclosure: Triennial Fire Protection

Inspection Supporting Documentation

cc:

Joe l. McManis,

Manager - Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

Winston & Strawn

Attn: James R. Curtiss

1700 K Street NW

Washington, DC 20006-3817

Chairman

Washington County Board of Supervisors

P.O. Box 466

Blair, NE 68008

Omaha Public Power District -3-

Julia Schmitt, Manager

Radiation Control Program

Nebraska Health & Human Services

Dept. of Regulation & Licensing

Division of Public Health Assurance

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Melanie Rasmussen

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

Ronald L. McCabe, Chief

Technological Hazards Branch

National Preparedness Division

DHS/FEMA

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

Omaha Public Power District -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (John.Hanna@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)

Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

SUNSI Review Completed: _GAP__ADAMS: X Yes Initials: __GAP____

X Publicly Available X Non-Sensitive

S:\DRS\REPORTS\FC2008006-GAP ML081120496

SRI:DRS/EB2 C: EB2

GAP/tek LJSmith

04/ /08 04/ /08

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

Triennial Fire Protection Inspection Documentation Requested

Please provide the following documentation prior to the onsite information-gathering trip,

preferably no later than June 23, 2008. Where practical, please provide copies electronically.

1. The current version of your fire protection program and fire hazards analysis.

2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate

acceptable plant response.

3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports,

pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters

to/from the NRC regarding fire protection/fire safe shutdown, etc.).

4. The Fire PRA or portions of the plants IPEEE addressing fire events.

Please provide the following documentation during the information-gathering visit or by

July 18, 2008, in order to support inspection preparation. Where practical, please provide

copies electronically. However, drawings should be provided as paper copies of sufficient size

that all details are legible.

5. Fire protection program implementing procedures (e.g., administrative controls, operator

response procedures for fires, fire fighting procedures, etc.).

6. Operating procedures used for achieving and maintaining hot and cold shutdown

conditions from the control room in the event of a fire outside the control room (III.G.2

areas).

7. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)

capability with or without control room evacuation.

8. Pre-fire plans for the selected fire areas (areas to be selected by the team during the

information-gathering trip).

9. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the

event of a fire (safe shutdown equipment lists).

10. Piping and instrumentation (flow) diagrams showing the components used to achieve

and maintain hot standby and cold shutdowns for fires outside the control room and

those components used for those areas requiring alternative shutdown capability. Two

copies of the piping and instrumentation (flow) diagrams for these systems of a size

sufficient to read all details. These should include the systems used for RCS makeup,

RCS pressure control, decay heat removal, and reactivity control, including the essential

support systems.

11. Plant layout and equipment drawings for the selected fire areas that identify (a) the

physical plant locations of major hot standby and cold shutdown equipment; (b) plant fire

area and/or fire zone delineation; and (c) the locations of fire protection equipment, such

as detection, suppression, and post-fire emergency lighting units, and (d) fire area

boundaries.

12. A listing of design change packages, which were determined to impact fire protection

and post-fire safe shutdowns, performed in the last 3 years.

13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.

14. A listing of open and closed corrective action documents initiated in the last 3 years,

which relate to the fire protection program or equipment. Include corrective action

document number, date, and subject.

15. A listing of the applicable codes and standards (with the versions) related to the design

of plant fire protection features and evaluations of any code deviations.

16. Drawings of the portions of the emergency lighting system which support fire response.

17. Procedures used to remove smoke from safety-related areas and the engineering

studies or calculations which support the design basis.

18. Drawings of communication systems credited in the license basis for firefighting and

plant operations during fires where control room is occupied and/or evacuated.

19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.

20. A listing of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps and suppression systems.

21. Maintenance Rule performance criteria and a summary of the last 3 years performance

history for fire protection program systems or functions monitored within the

Maintenance Rule program.

22. A copy of fire protection program requirements (e.g. limiting conditions for operation,

surveillance test requirements) covered by Technical Specifications, Technical

Requirements Manual, UFSAR, or similar documents.

23. Copies of internal and external self-assessments, audits, peer-assessments or similar

reviews related to post-fire safe shutdown capability or the fire protection program

completed since July 1, 2005.

24. A list of manual actions taken outside the control room which are credited to mitigate the

consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should

group actions by the initiating fire area or zone and indicate where the action must take

place.

25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design

basis documents that describe the purpose/function/operating characteristics of the safe

shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and

reactivity control, including the essential support systems).

26. Two copies of one-line diagrams of the electrical distribution system. These should

depict how power gets from the switchyard to ESF loads (480V and 4160V). Also,

include the vital DC distribution system one-line diagrams.

27. A list of automatic and manually initiated gaseous fire suppression systems in the plant,

giving location and the key equipment being protected.

28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or

maintain hot shutdown and b) reach and/or maintain cold shutdown.

29. A list of high to low pressure interface valves.

30. A copy of procedures governing the training and operation of the fire brigade.

31. Organization charts of site personnel down to the level of fire protection staff personnel.

32. A contact list of key site personnel who will be supporting this inspection, giving location

of their office and phone number onsite.

33. The team would like to observe a fire brigade drill in the plant, if possible, during the

week of August 11, 2008. Please put us in contact with the appropriate personnel for

planning drills during the onsite information gathering trip.

34. The team would like to perform a walkthrough of the procedure for control room due to

fire with qualified operators in the plant during the week of July 28, 2008. Please put us

in contact with the appropriate personnel for planning the walkthrough during the onsite

information gathering trip.