{{#Wiki_filter:NEXTeraM ENERG--YPA DUANýARNOLD February 28, 2013 NG-1 3-0085 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NextEra Energy-Duane Arnold, LLC's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents (Order Number EA-12-050) | {{#Wiki_filter:NEXTeraM ENERG--YPA DUAN | ||
ýARNOLD February 28, 2013 NG-1 3-0085 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NextEra Energy-Duane Arnold, LLC's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents (Order Number EA-12-050) | |||
==References:== | ==References:== | ||
: 1. NRC Order Number EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, dated March 12, 2012, Accession No. ML12054A694 | : 1. NRC Order Number EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, dated March 12, 2012, Accession No. ML12054A694 | ||
: 2. NRC Interim Staff Guidance JLD-ISG-2012-02, Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, Revision 0, dated August 29, 2012, Accession No. ML12229A475 | : 2. NRC Interim Staff Guidance JLD-ISG-2012-02, Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, Revision 0, dated August 29, 2012, Accession No. ML12229A475 | ||
: 3. Letter, R. Anderson (NextEra Energy Duane Arnold, LLC) to U.S. NRC,"NextEra Energy Duane Arnold, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)," NG-12-0427, dated October 29, 2012, Accession No. ML12305A375 On March 12, 2012, the Nuclear Regulatory Commission | : 3. Letter, R. Anderson (NextEra Energy Duane Arnold, LLC) to U.S. NRC, "NextEra Energy Duane Arnold, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)," NG-12-0427, dated October 29, 2012, Accession No. ML12305A375 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an Order (Reference 1) to NextEra Energy Duane Arnold, LLC (hereafter, NextEra Energy Duane Arnold). Reference 1 was immediately effective and directs NextEra Energy Duane Arnold to have a reliable hardened vent (RHV) installed at its Boiling Water Reactor (BWR) with a Mark I Containment to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged Station Blackout (SBO). Specific requirements are outlined in Attachment 2 of Reference 1. | ||
("NRC" or "Commission") | Reference 1 requires submission of an Overall Integrated Plan by February 28, 2013. The NRC Interim Staff Guidance (Reference 2) was issued August 29, 2012, which provides direction regarding the content of this Overall Integrated Plan. | ||
issued an Order (Reference | NextEra Energy Duane Arnold, LLC, 3277 DAEC Road, Palo, IA52324 | ||
Document Control Desk NG-13-0085 Page 2 of 2 Reference 3 acknowledged NextEra Energy Duane Arnold's receipt of Reference 2 and provided the initial status report regarding the RHV, as required by Reference 1. | |||
The purpose of this letter is to provide the Overall Integrated Plan pursuant to Section IV, Condition C.1, of Reference 1. Reference 2, Section 4.0 contains the specific reporting requirements for the Overall Integrated Plan. The Enclosure to this letter provides NextEra Energy Duane Arnold's Overall Integrated Plan in accordance with Section 4.0 of Reference 2. | |||
The Enclosure contains the current design information as of the writing of this letter, much of which is still preliminary, pending completion of on-going evaluations and analyses. | For the purposes of compliance with Order EA-1 2-050 (Reference 1), NextEra Energy Duane Arnold plans to use a wetwell vent system. The potential addition of a hardened drywell vent system will not be determined until additional review of industry studies of severe accidents is completed. | ||
Due to the synergy between the design of the RHV system and the equipment to be utilized in the Mitigating Strategies (so called FLEX) required by Order EA-12-049, some of the design details, in particular those regarding backup DC power and pneumatic supplies for the RHV, are still being developed. | The Enclosure contains the current design information as of the writing of this letter, much of which is still preliminary, pending completion of on-going evaluations and analyses. Due to the synergy between the design of the RHV system and the equipment to be utilized in the Mitigating Strategies (so called FLEX) required by Order EA-12-049, some of the design details, in particular those regarding backup DC power and pneumatic supplies for the RHV, are still being developed. As further design details and associated procedure guidance are finalized, that additional information, as well as any revisions to the information contained in the Enclosure, will be communicated to the Staff in the 6-month updates required by the Orders. | ||
As further design details and associated procedure guidance are finalized, that additional information, as well as any revisions to the information contained in the Enclosure, will be communicated to the Staff in the 6-month updates required by the Orders.This letter contains no new regulatory commitments. | This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact Ken Putnam at 319-851-7238. | ||
If you have any questions regarding this report, please contact Ken Putnam at 319-851-7238. | I declare under penalty of perjury that the foregoing is true and correct. | ||
I declare under penalty of perjury that the foregoing is true and correct.Executed on February 28, 2013 Richard L. Anderson Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC | Executed on February 28, 2013 Richard L. Anderson Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC | ||
==Enclosure:== | ==Enclosure:== | ||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System cc: NRC Regional Administrator (Region Ill) | |||
NRC Resident Inspector (DAEC) | |||
NRC Licensing Project Manager (DAEC) | |||
Enclosure to NG-13-0085 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System 25 Pages to Follow | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Table of Contents: | |||
Section 1: System Description Section 2: Design Objectives Requirement 1.1.1 - Minimize the Reliance on Operator Actions Requirement 1.1.2 - Minimize Plant Operators' Exposure to Occupational Hazards Requirement 1.1.3 - Minimize Radiological Consequences Section 3: Operational Characteristics Requirement 1.2.1 - Capacity to Vent Equivalent of 1% | |||
Requirement 1.2.2 - HCVS Shall be Accessible to Plant Operators Requirement 1.2.3 - Prevent Inadvertent Actuation Requirement 1.2.4 - Monitor the Status of the Vent System Requirement 1.2.5 - Monitor the Effluent Discharge for Radioactivity Requirement 1.2.6 - Minimize Unintended Cross Flow of Vented Fluids Requirement 1.2.7 - Provision for the Operation, Testing, Inspection and Maintenance Requirement 1.2.8 - Design Pressures Requirement 1.2.9 - Discharge Release Point Section 4: Applicable Quality Requirements Requirement 2.1 - Containment Isolation Function Requirement 2.2 - Reliable and Rugged Performance Section 5: Procedures and Training Requirement 3.1 - Develop, Implement, and Maintain Procedures Requirement 3.2 - Train Appropriate Personnel Section 6: Implementation Schedule Milestones Section 7: Changes/Updates to this Overall Integrated Implementation Plan Section 8: Figures/Diagrams | |||
==References:== | ==References:== | ||
1 Generic Letter 89-16, Installation of a Hardened Wetwell Vent, dated September 1, 1989 2 Order EA-049, Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 3 Order EA-050, Reliable Hardened Containment Vents, dated March 12, 2012 4 JLD-ISG-2012-02, Compliance with Order EA-12-050, Reliable Hardened Containment Vents, dated August 29, 2012 5 NRC Responses to Public Comments, Japan Lessons-Learned Project Directorate Interim Staff Guidance JLD-ISG-2012-02: | 1 Generic Letter 89-16, Installation of a Hardened Wetwell Vent, dated September 1, 1989 2 Order EA-049, Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 3 Order EA-050, Reliable Hardened Containment Vents, dated March 12, 2012 4 JLD-ISG-2012-02, Compliance with Order EA-12-050, Reliable Hardened Containment Vents, dated August 29, 2012 5 NRC Responses to Public Comments, Japan Lessons-Learned Project Directorate Interim Staff Guidance JLD-ISG-2012-02: Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, dated August 29, 2012, ADAMS Accession No. ML12229A477 6 NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012 Page I of 25 | ||
Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, dated August 29, 2012, ADAMS Accession No. ML12229A477 6 NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012 Page I of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 1: System Description ISG Criteria: Licensees shall provide a complete description of the system, including | |||
The level of detail generally considered adequate is consistent with the level of detail | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 1: System Description ISG Criteria: | ||
The vent will be designed with sufficient capacity to accommodate decay heat input equivalent to approximately 1% of current licensed thermal power and will be capable of venting greater than the decay heat present when venting must be initiated to ensure the containment does not exceed design pressure. | Licensees shall provide a complete description of the system, including importantoperational characteristics.The level of detail generally considered adequate is consistent with the level of detail containedin the licensee's Final Safety Analysis Report. | ||
And thus, the hardened vent capacity will be adequate to relieve decay heat for a prolonged station blackout (SBO) event. The HCVS is intended for use as one element of core damage prevention strategies The HCVS flow path from the containment to an elevated release point is shown in the simplified diagram below. No ductwork will be used in the flow path.Page 2 of 25 Duane Arnold Enerav Center Overall Integrated Plan for the Reliable Hardened Vent System Figure 1 Simplified Vent Line Connections to Wetwell and Other Systems System Connection Options Option 1 -Dedicated wetwell vent-Not Currently Selected Option Vent% Detail Option 2 -Wetwell vent interfacing with another wetwell-connected system, dedicated release point-Currently Selected Option Vent To other | |||
The following equipment and components will be provided: i. HCVS Mechanical Components | ===Response=== | ||
System Overview: | |||
c) The interface valves provide isolation to the interconnected system. The HCVS shares part of its flow path with the Standby Gas Treatment System (SGTS).Prior to initiating the HCVS, the valve to the SGTS must be isolated. | The Hardened Containment Vent System (HCVS) will be designed to mitigate loss-of-decay-heat removal by providing sufficient containment venting capability to limit containment pressurization and maintain core cooling capability. The vent will be designed with sufficient capacity to accommodate decay heat input equivalent to approximately 1% of current licensed thermal power and will be capable of venting greater than the decay heat present when venting must be initiated to ensure the containment does not exceed design pressure. And thus, the hardened vent capacity will be adequate to relieve decay heat for a prolonged station blackout (SBO) event. The HCVS is intended for use as one element of core damage prevention strategies The HCVS flow path from the containment to an elevated release point is shown in the simplified diagram below. No ductwork will be used in the flow path. | ||
However, since SGTS isolation valves are fail-close AOV(s), with air-to-open and spring to shut, the containment isolation signal will automatically isolate the valve(s) upon any abnormal containment pressure.d) A rupture disk is currently provided in the vent line downstream of the CIVs. It is anticipated that this rupture disk will be retained following the modifications to improve the reliability of the hardened vent. Provisions will be made to pressurize the disk from Main Control Room as directed by applicable procedures to allow venting earlier in the event if desired. The final design may elect to remove the rupture disk or replace it with a rupture disk with a different pressure set.ii. Instrumentation to monitor the status of the HCVS -a) Instrumentation indications will be available in the Main Control Room b) Effluent radiation monitor will be located external to the vent piping.c) HCVS vent flow path valves position indication, temperature and pressure instrumentation will monitor the status of the HCVS to aid the operator to ensure verification of proper venting operation. | Page 2 of 25 | ||
A failure of the position indication instrumentation would not prevent opening and closing the valves.iii. Support systems -a) Existing power for the HCVS DC valve solenoids is provided from the 125 Volt Essential DC Batteries. | |||
b) Motive air/gas supply for HCVS operation under the current plant design are adequate for at least three strokes of the valves during the first 24 hours during operation under prolonged SBO conditions is provided from an accumulator in the Atmosphere Control System (1T429). | Duane Arnold Enerav Center Overall Integrated Plan for the Reliable Hardened Vent System Figure 1 Simplified Vent Line Connections to Wetwell and Other Systems System Connection Options Option 1 - Dedicated wetwell vent-Not Currently Selected Option Vent | ||
Power will be supplied from a portable 480 volt generator connected to the applicable battery chargers. | %Detail Option 2 - Wetwell vent interfacing with another wetwell-connected system, dedicated release point-Currently Selected Option Vent To other sys te m s | ||
Motive air/gas for HCVS operation can be supplied from a portable cylinder if needed. Power for instrumentation will be supplied from the same batteries as the solenoids. | P Option 3 - Wetwell vent interfacing with another wetwell-connected system and with an existing release point-Not Currently Selected Option To Stack A9 To othe4 ~~ | ||
In addition, alternate means to power critical indicators of containment parameters will be provided under the FLEX program.System control: Active: Control Valves are operated in accordance with EOPs to control containment pressure. | syste ms Detail Options Option A - No control valve or rupture disk (Not Currently Selected Option) | ||
The CIVs are currently designed for 3 open / close cycles. Current procedures call for operation of the valves to maintain a containment pressure band between 45 PSIG and 53 PSIG (PCPL) unless otherwise directed by the Technical Support Center.ii. Passive: Inadvertent actuation protection will be provided by key lock switches for the CIV's that must be opened to permit flow.Page 5 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 2: Design Obiectives Order EA-050 1.1.1 Requirement: | Option B - Rupture disk (Currently Selected Option) | ||
The HCVS shall be designed to minimize the reliance on | Option C - Control valve (Not Currently Selected Option) ii+/- 1 Page 3 of 25 | ||
During the prolonged SBO condition at the Fukushima Dai-ichi units, operators faced many significant challenges while attempting to restore numerous plant systems that were necessary to cool the | |||
The HCVS shall be designed to be fully functional and self sufficient with permanently installed equipment in the plant, without the need for portable equipment or connecting thereto, until such time that | Duane Arnold Enerqy Center Overall Integrated Plan for the Reliable Hardened Vent System Equipment and components: | ||
The HCVS shall be capable of | The following equipment and components will be provided: | ||
The HCVS operation in this mode depends on a variety of conditions, such as the cause for the SBO (e.g., seismic event, flood, tornado, high winds), severity of the event, and time | : i. HCVS Mechanical Components - | ||
a) Containment isolation piping, valves and controls - The HCVS vent piping and supports up to and including the second containment isolation are designed in accordance with existing design basis. Containment isolation valves (CIVs) are provided consistent with the plants primary containment isolation valve design basis. The valves are air-operated valves (AOV) operated by a DC powered solenoid valve (SOV), and can be operated from switches in the Main Control Room. | |||
The operator actions that will be required to open a vent path are: Operator Actions Necessary to Vent the Containment during a Prolonged SBO Task Location Close interfacing system valves (new) MCR or Other Accessible Location Override containment isolation signal for CV4300 MCR Page 6 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Open Containment Isolation Valve CV4300 MCR Open HCVS control valve CV4357 MCR Isolation or cycling of the vent path can be directly performed from the MCR by operating either of the containment isolation valves (CV4300 or CV4357).The HCVS will be designed to allow initiation, control, and monitoring of venting from the MCR or other accessible location. | b) Other system valves and piping - The HCVS piping and supports downstream of the second containment isolation valve, including valve actuator pneumatic supply components, will be designed/analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake. | ||
The location minimizes plant operators' exposure to adverse temperature and radiological conditions and is protected from hazards consistent with the existing plant design. In addition, an alternate capability to open the valves from a location outside the main control room in the essential switchgear room or another accessible location will be provided that allows applying portable pneumatic supply to directly actuate the HCVS valves in the event normal operation from the MCR is not available. | c) The interface valves provide isolation to the interconnected system. The HCVS shares part of its flow path with the Standby Gas Treatment System (SGTS). | ||
Permanently installed power and motive gas capability will be available to support operation and monitoring of the HCVS in the modified design. The current motive gas accumulator is sized for three cycles of the HCVS valves. In the event final containment analysis and procedure concludes addition cycle capacity is needed the accumulator will be upgraded accordingly. | Prior to initiating the HCVS, the valve to the SGTS must be isolated. However, since SGTS isolation valves are fail-close AOV(s), with air-to-open and spring to shut, the containment isolation signal will automatically isolate the valve(s) upon any abnormal containment pressure. | ||
DC power will be maintained throughout the event using portable generators under the FLEX program and NEI 12-06. If for any reason, DC power or installed motive gas is unavailable, a back up capability will be provided to open the HCVS remotely from the essential switchgear room or other accessible location using a portable pneumatic supply.Order EA-050 1.1.2 Requirement: | d) A rupture disk is currently provided in the vent line downstream of the CIVs. It is anticipated that this rupture disk will be retained following the modifications to improve the reliability of the hardened vent. Provisions will be made to pressurize the disk from Main Control Room as directed by applicable procedures to allow venting earlier in the event if desired. The final design may elect to remove the rupture disk or replace it with a rupture disk with a different pressure set. | ||
The HCVS shall be designed to minimize plant operators' exposure to | ii. Instrumentation to monitor the status of the HCVS - | ||
Licensees should take into | a) Instrumentation indications will be available in the Main Control Room b) Effluent radiation monitor will be located external to the vent piping. | ||
c) HCVS vent flow path valves position indication, temperature and pressure instrumentation will monitor the status of the HCVS to aid the operator to ensure verification of proper venting operation. A failure of the position indication instrumentation would not prevent opening and closing the valves. | |||
iii. Support systems - | |||
a) Existing power for the HCVS DC valve solenoids is provided from the 125 Volt Essential DC Batteries. | |||
b) Motive air/gas supply for HCVS operation under the current plant design are adequate for at least three strokes of the valves during the first 24 hours during operation under prolonged SBO conditions is provided from an accumulator in the Atmosphere Control System (1T429). Ifthe final containment analysis Page 4 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System supporting the HCVS determines that additional valve cycles are needed, the accumulator capacity will be upgraded to match the required number of cycles. | |||
c) Under DAEC implementation of NRC Order EA-12-049 for Mitigation of Strategies for Beyond -Design-Bases External Events, FLEX equipment will have the capability to provide back-up support equipment for reliable HCVS operation. Power will be supplied from a portable 480 volt generator connected to the applicable battery chargers. Motive air/gas for HCVS operation can be supplied from a portable cylinder if needed. Power for instrumentation will be supplied from the same batteries as the solenoids. In addition, alternate means to power critical indicators of containment parameters will be provided under the FLEX program. | |||
System control: | |||
Active: Control Valves are operated in accordance with EOPs to control containment pressure. The CIVs are currently designed for 3 open / close cycles. Current procedures call for operation of the valves to maintain a containment pressure band between 45 PSIG and 53 PSIG (PCPL) unless otherwise directed by the Technical Support Center. | |||
ii. Passive: Inadvertent actuation protection will be provided by key lock switches for the CIV's that must be opened to permit flow. | |||
Page 5 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 2: Design Obiectives Order EA-050 1.1.1 Requirement: | |||
The HCVS shall be designed to minimize the reliance on operatoractions. | |||
ISG 1.1.1 Criteria: | |||
During events that significantly challenge plant operations,individual operators are more prone to human error.In addition, the plant operationsstaff may be required to implement strategies and/ortake many concurrent actions that furtherplaces a burden on its personnel. During the prolonged SBO condition at the Fukushima Dai-ichi units, operators faced many significant challenges while attempting to restore numerous plant systems that were necessary to cool the reactorcore, including the containment venting systems. The difficulties faced by the operatorsrelated to the location of the HCVS valves, ambient temperaturesand radiologicalconditions, loss of all alternatingcurrentelectricalpower,loss of motive force to open the vent valves, and exhausting dc battery power. The NRC staff recognizes that operatoractions will be needed to operate the HCVS valves; however, the licensees shall considerdesign features for the system that will minimize the need and relianceon operatoractions to the extent possible during a variety of plant conditions, as further discussed in this ISG. | |||
The HCVS shall be designed to be operated from a control panel located in the main control room or a remote but readily accessible location. The HCVS shall be designed to be fully functional and self sufficient with permanently installed equipment in the plant, without the need for portable equipment or connecting thereto, until such time that additionalon-site or off-site personnel and portable equipment become available. The HCVS shall be capable of operatingin this mode (i.e., relying on permanently installed equipment) for at least 24 hours during the prolonged SBO, unless a shorterperiod is justified by the licensee. The HCVS operation in this mode depends on a variety of conditions, such as the cause for the SBO (e.g., seismic event, flood, tornado, high winds), severity of the event, and time requiredfor additional help to reach the plant, move portableequipment into place, and make connections to the HCVS. | |||
When evaluating licenseejustification for periods less than 24 hours, the NRC staff will considerthe number of actions and the cumulative demand on personnelresources that are needed to maintainHCVS functionality (e.g., installation of portable equipment during the first 24 hours to restore power to the HCVS controls and/orinstrumentation)as a result of design limitations. Forexample, the use of supplemental portablepower sources may be acceptable if the supplementalpower was readily available, could be quickly and easily moved into place, and installed through the use of pre-engineeredquick disconnects, and the necessary human actions were identified along with the time needed to complete those actions. | |||
Conversely, supplemental power sources located in an unattended warehouse that require a qualified electrician to temporarilywire into the panel would not be consideredacceptable by the staff because its installation requires a series of complex, time-consuming actions in orderto achieve a successful outcome. | |||
There are similarexamples that could apply to mechanical systems, such as pneumatic/compressedair systems. | |||
Response (ref. ISG Item 1.1.1): | |||
The operation of the HCVS will be designed to minimize the reliance on operator actions in response to hazards identified in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) | |||
Implementation Guide. The design will allow immediate operator actions to be completed by reactor operators in the Main Control Room (MCR) or other accessible location. The operator actions that will be required to open a vent path are: | |||
Operator Actions Necessary to Vent the Containment during a Prolonged SBO Task Location Close interfacing system valves (new) MCR or Other Accessible Location Override containment isolation signal for CV4300 MCR Page 6 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Open Containment Isolation Valve CV4300 MCR Open HCVS control valve CV4357 MCR Isolation or cycling of the vent path can be directly performed from the MCR by operating either of the containment isolation valves (CV4300 or CV4357). | |||
The HCVS will be designed to allow initiation, control, and monitoring of venting from the MCR or other accessible location. The location minimizes plant operators' exposure to adverse temperature and radiological conditions and is protected from hazards consistent with the existing plant design. In addition, an alternate capability to open the valves from a location outside the main control room in the essential switchgear room or another accessible location will be provided that allows applying portable pneumatic supply to directly actuate the HCVS valves in the event normal operation from the MCR is not available. | |||
Permanently installed power and motive gas capability will be available to support operation and monitoring of the HCVS in the modified design. The current motive gas accumulator is sized for three cycles of the HCVS valves. In the event final containment analysis and procedure concludes addition cycle capacity is needed the accumulator will be upgraded accordingly. DC power will be maintained throughout the event using portable generators under the FLEX program and NEI 12-06. If for any reason, DC power or installed motive gas is unavailable, a back up capability will be provided to open the HCVS remotely from the essential switchgear room or other accessible location using a portable pneumatic supply. | |||
Order EA-050 1.1.2 Requirement: | |||
The HCVS shall be designed to minimize plant operators'exposure to occupationalhazards, such as extreme heat stress, while operating the HCVS system. | |||
ISG 1.1.2 Criteria: | |||
During a prolonged SBO, the drywell, wetwell (torus), and nearby areasin the plant where HCVS components are expected to be located will likely experience an excursion in temperatures due to inadequatecontainment cooling combined with loss of normal and emergency building ventilation systems. | |||
In addition, installed normal and emergency lighting in the plant may not be available. Licensees should take into considerationplant conditions expected to be experienced during applicable beyond design basis externalevents when locatingvalves, instrumentair supplies, and other components that will be required to safely operate the HCVS system. Components requiredfor manual operation should be placed in areas that are readily accessible to plant operators,and not require additionalactions, such as the installationof ladders or temporary scaffolding, to operate the system. | |||
When developing a design strategy, the NRC staff expects licensees to analyze potentialplant conditions and use its acquiredknowledge of these areas, in terms of how temperatures would reactto extended SBO conditions and the lighting that would be available during beyond design basis externalevents. This knowledge also provides an input to system operatingprocedures, training,the choice of protective clothing, required tools and equipment, and portable lighting. | |||
Response (ref. ISG Item 1.1.2): | |||
The HCVS design will allow operating the HCVS from the MCR or other accessible location which minimizes plant operators' exposure to adverse temperature and radiological conditions. | |||
The MCR is protected from hazards consistent with the existing plant design and will be evaluated for acceptable temperature and radiological conditions. | The MCR is protected from hazards consistent with the existing plant design and will be evaluated for acceptable temperature and radiological conditions. | ||
In order to minimize operator exposure to temperature excursions due to the impact of the prolonged SBO (i.e., loss of normal and emergency building ventilation systems and/or containment temperature changes) procedures will not require access to suppression pool Page 7 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (wetwell) area and exposure to extreme occupational hazards for normal and backup operation of electrical and pneumatic systems.Connections for supplemental equipment needed for sustained operation will be located in accessible areas protected from severe natural phenomena and minimize exposure to occupational hazards. Tools required for sustained operation, such as portable lights and connection specific tooling will be pre-staged in the NEI 12-06 storage locations or the control room.Neither temporary ladders nor scaffold will be required to access these connections or storage locations. | In order to minimize operator exposure to temperature excursions due to the impact of the prolonged SBO (i.e., loss of normal and emergency building ventilation systems and/or containment temperature changes) procedures will not require access to suppression pool Page 7 of 25 | ||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (wetwell) area and exposure to extreme occupational hazards for normal and backup operation of electrical and pneumatic systems. | |||
Connections for supplemental equipment needed for sustained operation will be located in accessible areas protected from severe natural phenomena and minimize exposure to occupational hazards. Tools required for sustained operation, such as portable lights and connection specific tooling will be pre-staged in the NEI 12-06 storage locations or the control room. | |||
Neither temporary ladders nor scaffold will be required to access these connections or storage locations. | |||
Order EA-050 1.1.3 Requirement: | Order EA-050 1.1.3 Requirement: | ||
The HCVS shall also be designed to minimize | The HCVS shall also be designed to minimize radiologicalconsequences that would impede personnel actions needed for event response. | ||
During the Fukushima event, | ISG 1.1.3 Criteria: | ||
The system shall be deigned to function in this mode with peirnanently installed equipment providing | The design of the HCVS should take into considerationthe radiologicalconsequences resultingfrom the event that could negatively impact event response. During the Fukushima event, personnelactions to manually operate the vent valves were impeded due to the location of the valves in the torus rooms. The HCVS shall be designed to be placed in operation by operatoractions at a control panel, located in the main control room or in a remote location. The system shall be deigned to function in this mode with peirnanently installed equipment providing electricalpower (e.g., dc power batteries)and valve motive force (e.g., N2Iair cylinders). The system shall be designed to function in this mode for a minimum duration of 24 hours with no operatoractions required or credited, other than the system initiatingactions at the control panel. | ||
The system shall be designed to function in this mode for a minimum duration of 24 hours with no | Durationsof less than 24 hours will be considered if justified by adequate supporting information from the licensee. To ensure continued operation of the HCVS beyond 24 hours, licensees may credit manual actions, such as moving portable equipment to supplement electricalpower and valve motive power sources. | ||
To ensure continued operation of the HCVS beyond 24 hours, licensees may credit manual actions, such as moving portable equipment to supplement | In response to Generic Letter (GL) 89-16, a number of facilities with Mark I containments installed vent valves in the torus room, near the drywell, or both. Licensees can continue to use these venting locations or select new locations,provided the requirements of this guidance document are satisfied. The HCVS improves the chances of core cooling by removing heat from containment and lowering containment pressure, when core cooling is provided by other systems. If core cooling were to fail and result in the onset core damage, closure of the vent valves may become necessary if the system was not designed for severe accident service. In addition, leakage from the HCVS within the plant and the location of the externalrelease from the HCVS could impact the event response from on-site operators and off-site help arrivingat the plant. | ||
The HCVS improves the chances of core cooling by removing heat from containment and lowering containment pressure, when core cooling is provided by other systems. If core cooling were to fail and result in the onset core damage, closure of the vent valves may become necessary if the system was not designed for severe accident service. In addition, leakage from the HCVS within the plant and the location of the | An adequate strategy to minimize radiologicalconsequences that could impede personnelactions should include the following: | ||
: 1. Licensees shall provide permanent | : 1. Licensees shall provide permanent radiationshielding where necessary to facilitate personnel access to valves and allow manual operation of the valves locally. Licensee may use altematives such as providing features to facilitate manual operation of valves from remote locations, as discussed furtherin this guidance under Requirement 1.2.2, or relocate the vent valves to areas that are significantly less challenging to operatoraccess/actions. | ||
: 2. In accordance with Requirement 1.2.8, the HCVS shall be designed for pressures that are consistent with the higher of the primary containment design pressure and the primary | : 2. In accordance with Requirement 1.2.8, the HCVS shall be designed for pressures that are consistent with the higher of the primary containment design pressure and the primary containmentpressure limit (PCPL), | ||
In addition, the system shall be leak-tight. As such, ventilation duct work (i.e., sheet metal) shall not be utilized in the design of the HCVS.Licensees should perform | as well as including dynamic loading resultingfrom system actuation.In addition, the system shall be leak-tight. As such, ventilation duct work (i.e., sheet metal) shall not be utilized in the design of the HCVS. | ||
Release through existing plant stacks is considered acceptable, provided the guidance under Requirement 1.2.6 is satisfied. | Licensees should perform appropriatetesting, such as hydrostatic or pneumatic testing, to establish the leak-tightness of the HCVS. | ||
If the release from HCVS is through a vent stack different than the plant stack, the elevation of the stack should be | : 3. The HCVS release to outside atmosphere shall be at an elevation higherthan adjacent plant structures. | ||
Page 8 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Response (ref. ISG Item 1.1.3): The HCVS will be designed for reliable remote-manual operation. | Release through existing plant stacks is considered acceptable,provided the guidance under Requirement 1.2.6 is satisfied. If the release from HCVS is through a vent stack different than the plant stack, the elevation of the stack should be higherthan the nearest building or structure. | ||
Operators will not be required to access the suppression pool area. The HCVS will be designed to minimize system cross flow, prevent steam flow into unintended areas, provide containment isolation, and provide reliable and rugged performance as discussed below for Order requirements 1.2.6.Dose rates will be evaluated consistent with the assumption that the HCVS is to be used for the prevention of significant core damage. Shielding or other alternatives to facilitate manual actions are not required for operation of the vent under these conditions since no core damage has occurred and operator actions can be completed in the MCR or other accessible location.Page 9 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 3: Operational Characteristics Order EA-050 1.2.1 Requirement: | Page 8 of 25 | ||
The HCVS shall have the capacity to vent the steam/energy equivalent of I percent of licensed/rated | |||
The primary design objective of the HCVS is to provide sufficient venting capacity to prevent a long-term overpressure failure of the containment by keeping the | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Response (ref. ISG Item 1.1.3): | ||
This determination is based on studies that have shown that the torus suppression capacity is typically sufficient to absorb the decay heat | The HCVS will be designed for reliable remote-manual operation. Operators will not be required to access the suppression pool area. The HCVS will be designed to minimize system cross flow, prevent steam flow into unintended areas, provide containment isolation, and provide reliable and rugged performance as discussed below for Order requirements 1.2.6. | ||
Licensees shall have an auditable engineering basis for the decay heat | Dose rates will be evaluated consistent with the assumption that the HCVS is to be used for the prevention of significant core damage. Shielding or other alternatives to facilitate manual actions are not required for operation of the vent under these conditions since no core damage has occurred and operator actions can be completed in the MCR or other accessible location. | ||
Licensees may also use a venting capacity sized under conditions of constant heat input at a rate lower than 1 percent of thermal power if it can be justified by analysis that primary containment design pressure and the PCPL would not be exceeded. | Page 9 of 25 | ||
In cases where plants were granted, have applied, or plan to apply for power uprates, the licensees shall use 1 percent thermal power | |||
The vent would then be able to prevent containment pressure from increasing above the containment design pressure. | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 3: Operational Characteristics Order EA-050 1.2.1 Requirement: | ||
As part of the final detailed design, the duration of suppression pool decay heat absorption will be confirmed. | The HCVS shall have the capacity to vent the steam/energy equivalent of I percent of licensed/rated thermalpower (unless a lower value is justified by analyses), and be able to maintain containmentpressure below the primary containment design pressure. | ||
ISG 1.2.1 Criteria: | |||
Beyond design basis extemal events such as a prolonged SBO could result in the loss of active containment heat removal capability. The primary design objective of the HCVS is to provide sufficient venting capacity to prevent a long-term overpressure failure of the containment by keeping the containmentpressure below the primary containment design pressure and the PCPL. The PCPL may be dictated by other factors, such as the maximum containmentpressure at which the safety relief valves (SRVs) and the HCVS valves can be opened and closed. | |||
The NRC staff has determined that, for a vent sized under conditions of constant heat input at a rate equal to I percent of rated thermal power and containmentpressure equal to the lower of the primary containment design pressure and the PCPL, the exhaust-flow through the vent would be sufficient to prevent the containmentpressure from increasing. This determination is based on studies that have shown that the torus suppression capacity is typically sufficient to absorb the decay heat generatedduring at least the first three hours following the shutdown of the reactorwith suppression pool as the source of injection, that decay heat is typically less than 1 percent of rated thermalpower three hours following shutdown of the reactor,and that decay heat continues to decrease to well under 1 percent, thereafter.Licensees shall have an auditable engineering basis for the decay heat absorbingcapacity of theirsuppression pools, selection of venting pressure such that the HCVS will have sufficient venting capacity under such conditions to maintain containmentpressure at or below the primary containmentdesign pressure and the PCPL. If required, venting capacity shall be increasedto an appropriatelevel commensurate with the licensee's venting strategy. Licensees may also use a venting capacity sized under conditions of constant heat input at a rate lower than 1 percent of thermal power if it can be justified by analysis that primary containment design pressure and the PCPL would not be exceeded. In cases where plants were granted,have applied, or plan to apply for power uprates, the licensees shall use 1 percent thermal power correspondingto the uprated thermalpower. The basis for the venting capacityshall give appropriateconsiderationof where venting is being performed from (i.e., wetwell or drywell) and the difference in pressure between the drywell and the suppression chamber. Vent sizing for multi-unit sites must take into considerationsimultaneous venting from all the units, and ensure that venting on one unit does not negatively impact the ability to vent on the other units. | |||
Response (ref. ISG Item 1.2.1): | |||
The current HCVS wetwell path is designed for venting steam/energy at a nominal capacity of slightly less than 1% of 1912 MWt thermal power at pressure of 53 psig. During the design and licensing of the extended power uprate of the DAEC this capacity of slightly less than 1% was evaluated and found acceptable for the anticipated decay heat level that would be present at the time venting is required for the assumed loss of decay heat removal event per GL 89-16. This pressure is the Primary Containment Pressure Limit (PCPL) which is the lower of the containment design pressure and the PCPL value. | |||
The design assumes that the pressure suppression capacity of the suppression pool is sufficient to absorb the decay heat generated during initial plant response. The vent would then be able to prevent containment pressure from increasing above the containment design pressure. As part of the final detailed design, the duration of suppression pool decay heat absorption will be confirmed. | |||
Order EA-050 1.2.2 Requirement: | Order EA-050 1.2.2 Requirement: | ||
The HCVS shall be accessible to plant | The HCVS shall be accessible to plant operatorsand be capable of remote operation and control, or manual operation, during sustainedoperations. | ||
Page 10 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System ISG 1.2.2 Criteria: The preferred location for remote operation and control of the HCVS is from the main control room. However, altemate locations to the control room are also acceptable, provided the licensees take into consideration the following: | Page 10 of 25 | ||
: 1. Sustained operations mean the ability to open/close the valves multiple times during the event. Licensees shall determine the number of open/close cycles | |||
Licensee may use altematives such as providing features to facilitate manual operation of valves from remote locations or relocating/ | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System ISG 1.2.2 Criteria: | ||
The connections between the valves and portable equipment should be designed for quick deployment. | The preferred location for remote operation and control of the HCVS is from the main control room. However, altemate locations to the control room are also acceptable, provided the licensees take into consideration the following: | ||
If a portable motive force (e.g., | : 1. Sustained operations mean the ability to open/close the valves multiple times during the event. Licensees shall determine the number of open/close cycles necessaryduring the first 24 hours of operation and provide supporting basis consistent with the plant-specificcontainment venting strategy. | ||
: 5. The design shall preclude the need for | : 2. An assessment of temperature and radiologicalconditions that operatingpersonnel may encounter both in transit and locally at the controls. Licensee may use altematives such as providing features to facilitate manual operation of valves from remote locations or relocating/reorientingthe valves. | ||
Response (ref. ISG Item 1.2.2): The HCVS design will allow initiating and then operating and monitoring the HCVS from the MCR or other accessible location. | : 3. All permanently installed HCVS equipment, including any connections required to supplement the HCVS operation during a prolonged SBO (electricpower, N2/air)shall be located above the maximum design basis extemal flood level or protected from the design basis extemal flood. | ||
Alternate capability for operation from the essential switch gear room or other accessible location will be provided. | : 4. During a prolonged SBO, manual operation/actionmay become necessary to operate the HCVS. As demonstratedduring the Fukushima event, the valves lost motive force including electric power and pneumatic airsupply to the valve operators,and control power to solenoid valves. If direct access and local operation of the valves is not feasible due to temperature or radiologicalhazards, licensees should include design features to facilitate remote manual operation of the HCVS valves by means such as reach rods, chain links, hand wheels, and portable equipment to provide motive force (e.g., air/N2 bottles, diesel powered compressors,and dc batteries). The connections between the valves and portable equipment should be designed for quick deployment. If a portable motive force (e.g., airor N2 bottles, dc power supplies)is used in the design strategy, licensees shall provide reasonableprotection of that equipment consistent with the staffs guidance delineatedin JLD-ISG-2012-01 for OrderEA-12-049. | ||
These locations are protected from adverse natural phenomena. | : 5. The design shall preclude the need for operatorsto move temporary laddersor operate from atop scaffolding to access the HCVS valves or remote operatinglocations. | ||
Response (ref. ISG Item 1.2.2): | |||
The HCVS design will allow initiating and then operating and monitoring the HCVS from the MCR or other accessible location. Alternate capability for operation from the essential switch gear room or other accessible location will be provided. These locations are protected from adverse natural phenomena. | |||
: 1. The HCVS flow path valves are air-operated valves with air-to-open and spring-to-shut. | : 1. The HCVS flow path valves are air-operated valves with air-to-open and spring-to-shut. | ||
Opening the valves requires energizing a DC powered solenoid operated valve (SOV)and providing motive air/gas. The detailed design will ensure a permanently installed DC power source and motive air/gas supply. The response to NRC EA-12-049 will demonstrate the capability under the FLEX effort to maintain the DC source throughout the period. The initial stored motive gas will allow for a minimum of three valve operating cycles; however, the final detailed design will determine the number of required valve cycles for the first 24-hours. | Opening the valves requires energizing a DC powered solenoid operated valve (SOV) and providing motive air/gas. The detailed design will ensure a permanently installed DC power source and motive air/gas supply. The response to NRC EA-12-049 will demonstrate the capability under the FLEX effort to maintain the DC source throughout the period. The initial stored motive gas will allow for a minimum of three valve operating cycles; however, the final detailed design will determine the number of required valve cycles for the first 24-hours. If required, the stored motive gas will be upgraded to be consistent with the required number of valve cycles. | ||
If required, the stored motive gas will be upgraded to be consistent with the required number of valve cycles.2. All primary controls can be operated from the MCR or other accessible location therefore temperature and radiological conditions that operating personnel may encounter at the controls are acceptable. | : 2. All primary controls can be operated from the MCR or other accessible location therefore temperature and radiological conditions that operating personnel may encounter at the controls are acceptable. No transit through inaccessible areas to local controls will be required. | ||
No transit through inaccessible areas to local controls will be required.3. All permanently installed HCVS equipment, including any connections required to supplement the HCVS operation during a prolonged SBO (electric power, Nitrogen/air) will be located in areas reasonably protected from defined hazards from NEI 12-06.4. All valves required to open the flow path will be designed for remote manual operation following a prolonged SBO, i.e., no valve operation via hand wheel, reach-rod or similar Page 11 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System means that requires close proximity to the valve. Alternate means for operation of the HCVS valves will be provided in the essential switchgear room, or other accessible location, which will also be accessible for operations personnel. | : 3. All permanently installed HCVS equipment, including any connections required to supplement the HCVS operation during a prolonged SBO (electric power, Nitrogen/air) will be located in areas reasonably protected from defined hazards from NEI 12-06. | ||
Any supplemental connections will be pre-engineered to minimize man-power resources and any needed portable gas supply will be reasonably protected from defined hazards as noted in NEI 12-06.5. Access to the locations described above will not require temporary ladders or scaffolding. | : 4. All valves required to open the flow path will be designed for remote manual operation following a prolonged SBO, i.e., no valve operation via hand wheel, reach-rod or similar Page 11 of 25 | ||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System means that requires close proximity to the valve. Alternate means for operation of the HCVS valves will be provided in the essential switchgear room, or other accessible location, which will also be accessible for operations personnel. Any supplemental connections will be pre-engineered to minimize man-power resources and any needed portable gas supply will be reasonably protected from defined hazards as noted in NEI 12-06. | |||
: 5. Access to the locations described above will not require temporary ladders or scaffolding. | |||
Order EA-050 1.2.3 Requirement: | Order EA-050 1.2.3 Requirement: | ||
The HCVS shall include a means to prevent | The HCVS shall include a means to prevent inadvertentactuation. | ||
ISG 1.2.3 Criteria: The design of the HCVS | ISG 1.2.3 Criteria: | ||
The currently installed rupture disc may be retained but the final design may elect to either remove this disk or modify it to a different pressure setting.EOP/ERG operating procedures provide clear guidance that the HCVS is not to be used to defeat containment integrity during any design basis transients and accident. | The design of the HCVS shallincorporate features, such as control panel key-locked switches, locking systems, rupture discs, or administrativecontrols to prevent the inadvertentuse of the vent valves. The system shall be designed to preclude inadvertentactuation of the HCVS due to any single active failure. The design should considergeneral guidelines such as single point vulnerability and spurious operationsof any plant installed equipment associated with HCVS. | ||
In addition, the HCVS will be designed to provide features to prevent inadvertent actuation due to a design error, equipment malfunction, or operator error such that any credited containment accident pressure (CAP) that would provide net positive suction head (NPSH) to the emergency core cooling system (ECCS) pumps will be available (inclusive of a design basis loss-of-coolant accident (DBLOCA)). | The objective of the HCVS is to provide sufficient venting of containment and prevent long-term overpressurefailure of containment following the loss of active containmentheat removal capability or prolonged SBO. However, inadvertentactuation of HCVS due to a design error,equipment malfunction, or Qperator errorduring a design basis loss-of-coolant accident (DBLOCA) could have an undesirable effect on the containment accidentpressure (CAP) to provide adequate net positive suction head to the emergency core cooling system (ECCS) pumps. Therefore, prevention of inadvertentactuation, while importantfor all plants, is essential for plants relying on CAP. The licensee submittals on HCVS shall specifically include details on how this issue will be addressedon their individualplants for all situationswhen CAP credit is required. | ||
UFSAR Section 5.4.7 discusses credit for containment over pressure to assist in maintaining NPSH and applicable values are displayed in Figure 5.4-15.Order EA-050 1.2.4 Requirement: | Response (ref. ISG Item 1.2.3): | ||
The HCVS shall include a means to monitor the status of the vent system (e.g., valve position indication) from the control room or other location(s). | The features that prevent inadvertent actuation are two normally closed CIV's in series with keylock switches controlled administratively. The currently installed rupture disc may be retained but the final design may elect to either remove this disk or modify it to a different pressure setting. | ||
The monitoring system shall be designed for | EOP/ERG operating procedures provide clear guidance that the HCVS is not to be used to defeat containment integrity during any design basis transients and accident. In addition, the HCVS will be designed to provide features to prevent inadvertent actuation due to a design error, equipment malfunction, or operator error such that any credited containment accident pressure (CAP) that would provide net positive suction head (NPSH) to the emergency core cooling system (ECCS) pumps will be available (inclusive of a design basis loss-of-coolant accident (DBLOCA)). UFSAR Section 5.4.7 discusses credit for containment over pressure to assist in maintaining NPSH and applicable values are displayed in Figure 5.4-15. | ||
Licensees | Order EA-050 1.2.4 Requirement: | ||
Page 12 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (1) HCVS vent valves' position (open or closed), (2) system pressure, and (3) effluent temperature. | The HCVS shall include a means to monitor the status of the vent system (e.g., valve position indication) from the control room or other location(s). The monitoring system shall be designed for sustainedoperation during a prolonged SBO. | ||
Other | ISG 1.2.4 Criteria: | ||
Monitoring by means of permanently | Plant operatorsmust be able to readily monitor the status of the HCVS at all times, including being able to understandwhether or not containmentpressure/energyis being vented through the HCVS, and whether or not containmentintegrity has been restoredfollowing venting operations. Licensees shallprovide a means to allow plant operatorsto readily determine, or have knowledge of, the following system parameters: | ||
The staff will | Page 12 of 25 | ||
The means to monitor system status shall support | |||
These HCVS indications will be at or near the same location as the valve control switches (CV4300 and CV4357), which are in the MCR. Power for the instrumentation will be from the same source used for the SOVs used to position the AOVs. Refer to the response to 1.2.2 for discussion on the power.The approximate range for the temperature indication will be 50°F to 600 | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (1) HCVS vent valves' position (open or closed), | ||
The ranges will be finalized when the detailed design and equipment specifications are prepared.The detailed design will address the radiological, temperature, pressure, flow induced vibration (if applicable) and internal piping dynamic forces, humidity/condensation and seismic qualification requirements. | (2) system pressure,and (3) effluent temperature. | ||
Assumed radiological conditions will be those expected after a prolonged SBO (without significant fuel failure), and will bound normal plant conditions. | Other importantinformation includes the status of supportingsystems, such as availabilityof electricalpower and pneumatic supply pressure. Monitoring by means of permanently installedgauges that are at, or nearby, the HCVS control panel is acceptable. The staff will consideralternativeapproachesfor system status instrumentation;however, licensees must provide sufficient information andjustificationfor alternative approaches. | ||
The means to monitor system status shall support sustainedoperations during a prolonged SBO, and be designed to operate under potentially harsh environmental conditions that would be expected following a loss of containment heat removal capability and SBO. Power supplies to all instruments, controls, and indicationsshall be from the same power sources supporting the HCVS operation. "Sustainedoperations" may include the use of portable equipment to provide an alternatesource of power to components used to monitor HCVS status. Licensees shall demonstrate instrument reliability via an appropriatecombination of design, analyses, operatingexperience, and/ortesting of channel components for the following sets of parameters: | |||
" radiologicalconditions that the instruments may encounter under normal plant conditions, and during and after a prolongedSBO event. | |||
" temperaturesand pressure conditions as describedunder requirement 1.2.8, including dynamic loadingfrom system operation. | |||
" humidity based on instrument location and effluent conditions in the HCVS. | |||
Response (ref. ISG Item 1.2.4): | |||
The design of the HCVS will have temperature and pressure monitoring downstream of the last isolation valve / rupture disc. All flow path valves will have open and closed position indication. | |||
These HCVS indications will be at or near the same location as the valve control switches (CV4300 and CV4357), which are in the MCR. Power for the instrumentation will be from the same source used for the SOVs used to position the AOVs. Refer to the response to 1.2.2 for discussion on the power. | |||
The approximate range for the temperature indication will be 50°F to 600 0F. The approximate range for the pressure indication will be 0 psig to 120 psig. The upper limits are approximately twice the required containment design temperature and pressure. The ranges will be finalized when the detailed design and equipment specifications are prepared. | |||
The detailed design will address the radiological, temperature, pressure, flow induced vibration (if applicable) and internal piping dynamic forces, humidity/condensation and seismic qualification requirements. Assumed radiological conditions will be those expected after a prolonged SBO (without significant fuel failure), and will bound normal plant conditions. | |||
Order EA-050 1.2.5 Requirement: | Order EA-050 1.2.5 Requirement: | ||
The HCVS shall include a means to monitor the effluent discharge for | The HCVS shall include a means to monitor the effluent discharge for radioactivitythat may be released from operation of the HCVS. The monitoring system shall provide indication in the control room or other location(s), and shall be designed for sustainedoperation during a prolonged SBO. | ||
The | ISG 1.2.5 Criteria: | ||
The use of other existing radiation monitoring | Licensees shall provide an independentmeans to monitoroverall radioactivitythat may be released from the HCVS discharge. The radiationmonitor does not need to meet the requirements of NUREG 0737 for monitored releases, nor does it need to be able to monitor releases quantitatively to ensure compliance with Title 10 of the Code of FederalRegulations (10 CFR) Part 100 or 10 CFR Section 50.67. A wide-range monitoring system to monitor the overall activity in the release providing indicationthat effluent from the Page 13 of 25 | ||
The detector will be physically mounted on the outside of the piping, accounting for the pipe wall thickness shielding in order to provide a measurement of the radiation level on the inside of the HCVS piping. The radiation level will be indicated at the MCR or other accessible location. | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System containmentenvironment that is passing by the monitoris acceptable. The use of other existing radiation monitoring capabilityin lieu of an independent HCVS radiationmonitor is not acceptable because plant operatorsneed accurateinformation aboutreleases coming from the containmentvia the HCVS in order to make informed decisions on operation of the reliablehardened venting system. | ||
The RMS will be powered from the same source as other electrically powered HCVS components. | The monitoringsystem shall provide indicationin the control room or a remote location (i.e., HCVS control panel)for the first 24 hours of an extended SBO with electric power provided by permanent DC battery sources, and supplemented by portablepower sources for sustained operations.Monitoringradiation levels is requiredonly during the events that necessitate operation of the HCVS. The reliabilityof the effluent monitoring system under the applicable environmentalconditions shall be demonstrated by methods described under Requirement 1.2.4. | ||
Refer to the response to 1.2.2 for discussion on sustainability of the power.Order EA-050 1.2.6 Requirement: | Response (ref. ISG Item 1.2.5): | ||
The HCVS shall include design features to minimize unintended cross flow of vented fluids within a unit and between units on the site.ISG 1.2.6 Criteria: At Fukushima, an explosion | The HCVS radiation monitoring system (RMS) will be dedicated to the HCVS. The approximate range of the (RMS) will be 0.1 mRem/hr to 1000 mRem/hr. This range is considered adequate to determine core integrity per the NRC Responses to Public Comments on the draft ISG (ML12229A477). | ||
Regardless, system design shall provide design features to prevent the cross flow of vented fluids and migration to other areas within the plant or to adjacent units at multi-unit sites.The current design of the hardened vent at several plants in the U.S. includes cross connections with the standby gas treatment system, which contains sheet metal ducts and filter and fan housings that are not as leak tight as hard pipes. In addition, dual unit plant sites are often equipped with a common plant stack.Examples of acceptable means for prevention of cross flow is by valves, leak-tight dampers, and check valves, which shall be designed to | The detector will be physically mounted on the outside of the piping, accounting for the pipe wall thickness shielding in order to provide a measurement of the radiation level on the inside of the HCVS piping. The radiation level will be indicated at the MCR or other accessible location. The RMS will be powered from the same source as other electrically powered HCVS components. | ||
Licensee's shall evaluate the environmental conditions (e.g.pressure, temperature) at the | Refer to the response to 1.2.2 for discussion on sustainability of the power. | ||
However, since SGTS isolation valves are AOV(s) that fail closed and receive containment isolation signals that will automatically isolate the valve(s) upon an abnormal containment pressure or loss of power, no Page 14 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System operator action is required. | Order EA-050 1.2.6 Requirement: | ||
The detailed design phase will review the valve(s) to determine if the inter-system valves can meet the required leakage criteria under the limiting HCVS design conditions. | The HCVS shall include design features to minimize unintended cross flow of vented fluids within a unit and between units on the site. | ||
If required, the valve(s) will be replaced or upgraded. | ISG 1.2.6 Criteria: | ||
The current hardened vent flow path downstream of the rupture disc includes valves that must isolate the flow stream from interfacing equipment. | At Fukushima, an explosion occurredin Unit 4, which was in a maintenance outage at the time of the event. | ||
These valves would not close automatically with a loss of AC power and currently need to be closed by local manual operator action. To improve reliability, these interfacing valves will be upgrade to ensure they can be remotely closed from the MCR or other accessible location and meet required leakage testing criteria.Order EA-050 1.2.7 Requirement: | Although the facts have not been fully established, a likely cause of the explosion in Unit 4 is that hydrogen leaked from Unit 3 to Unit 4 through a common venting system. System cross-connectionspresent a potentialfor steam, hydrogen, and airborne radioactivityleakage to other areas of the plant and to adjacent units at multi-unit sites if the units are equipped with common vent piping. In this context, a design that is free of physical and control interfaces with other systems eliminates the potential for any cross-flow and is one way to satisfy this requirement. Regardless,system design shall provide design features to prevent the cross flow of vented fluids and migration to other areas within the plant or to adjacent units at multi-unit sites. | ||
The HCVS shall include features and provision for the operation, testing, inspection and maintenance adequate to ensure that | The current design of the hardened vent at several plants in the U.S. includes cross connections with the standby gas treatment system, which contains sheet metal ducts and filter and fan housings that are not as leak tight as hard pipes. In addition, dual unit plant sites are often equipped with a common plant stack. | ||
ISG 1.2.7 Criteria: The HCVS piping run shall be designed to eliminate the potential for condensation accumulation, as subsequent water hammer could complicate system operation during intermittent venting or to withstand the potential for water hammer without compromising the functionality of the system. Licensees | Examples of acceptable means for prevention of cross flow is by valves, leak-tight dampers, and check valves, which shall be designed to automaticallyclose upon the initiation of the HCVS and shall remain closed for as long as the HCVS is in operation.Licensee's shall evaluate the environmental conditions (e.g. | ||
In situations where total elimination of | pressure, temperature)at the damperlocations during venting operationsto ensure that the dampers will remain functional and sufficiently leak-tight, and if necessary, replace the dampers with other suitable equipment such as valves. If power is requiredfor the interfacing valves to move to isolation position, it shall be from the same power sources as the vent valves. Leak tightness of any such barrersshall be periodically verified by testing as described under Requirement 1.2.7. | ||
When reviewing such requests, the NRC staff will consider the impact of the leakage on the | Response (ref. ISG Item 1.2.6): | ||
Perform visual | DAEC is a single unit site. | ||
Once per | The HCVS shares part of its flow path with the Standby Gas Treatment System (SGTS). Prior to initiating the HCVS, the valve to the SGTS must be isolated. However, since SGTS isolation valves are AOV(s) that fail closed and receive containment isolation signals that will automatically isolate the valve(s) upon an abnormal containment pressure or loss of power, no Page 14 of 25 | ||
Response (ref. ISG Item 1.2.7): The detailed design for the HCVS will address condensation accumulation resulting from intermittent venting. In situations where total elimination of condensation is not feasible, the HCVS will be designed to accommodate condensation, including allowance for applicable water hammer loads.The HCVS Containment Isolation Valves will be tested in accordance with the licensing and design basis for the plant. The HCVS past the outboard Containment Isolation Valve will be tested in conformance to the ISG methods. The test pressure shall be based on the HCVS design pressure. | |||
Permissible leakage rates for the interfacing valves will be within the requirements of American Society of Mechanical Engineers Operation and Maintenance of Nuclear Power Plants Code (ASME OM) -2009, Subsection ISTC -3630, or later edition of the ASME OM Code. When testing the HCVS volume, the allowed leakage will not exceed the sum of the interfacing valve leakages as determined from the ASME OM Code unless a higher leakage acceptance value is justified to the NRC.The test types and frequencies will conform to the ISG 1.2.7 Table "Testing and inspection Requirements" with the clarification that "Leak test the HCVS" applies to the HCVS boundary valves. Rupture disks (if retained in the final design) will be replaced at manufacturer's recommendations not to exceed 10 years. Interfacing system valves that cannot be cycled on line without challenging plant operation will be on an operating cycle frequency rather than once per year.Order EA-050 1.2.8 Requirement: | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System operator action is required. The detailed design phase will review the valve(s) to determine if the inter-system valves can meet the required leakage criteria under the limiting HCVS design conditions. If required, the valve(s) will be replaced or upgraded. The current hardened vent flow path downstream of the rupture disc includes valves that must isolate the flow stream from interfacing equipment. These valves would not close automatically with a loss of AC power and currently need to be closed by local manual operator action. To improve reliability, these interfacing valves will be upgrade to ensure they can be remotely closed from the MCR or other accessible location and meet required leakage testing criteria. | ||
The HCVS shall be designed for pressures that are consistent with maximum | Order EA-050 1.2.7 Requirement: | ||
ISG 1.2.8 Criteria: The vent system shall be designed for the higher of the primary | The HCVS shall include features and provision for the operation, testing, inspection and maintenance adequate to ensure that reliablefunction and capabilityare maintained. | ||
However, if the venting | ISG 1.2.7 Criteria: | ||
The HCVS piping run shall be designed to eliminate the potential for condensation accumulation, as subsequent water hammer could complicate system operation during intermittent venting or to withstand the potential for water hammer without compromising the functionality of the system. Licensees shallprovide a means (e.g., drain valves, pressure and temperaturegauge connections) to periodicallytest system components, including exercising (opening and closing) the vent valve(s). In situations where total elimination of condensationis not feasible, HCVS shall be designed to accommodate condensation, including applicable water hammerloads. | |||
The HCVS outboardof the containmentboundary shall be tested to ensure that vent flow is releasedto the outside with minimal leakage, if any, through the interfacingboundarieswith other systems or units. | |||
Licensees have the option of individually leak testing interfacingvalves or testing the overall leakage of the HCVS volume by conventional leak rate testing methods. The test volume shall envelope the HCVS between the outerprimary containment isolation barrierand the vent exiting the plant buildings, including the volume up to the interfacing valves. The test pressure shall be based on the HCVS design pressure. | |||
Permissibleleakage rates for the interfacingvalves shall be within the requirements of American Society of MechanicalEngineers Operationand Maintenanceof Nuclear Power Plants Code (ASME OM) - 2009, Subsection ISTC - 3630 (e) (2), orlateredition of the ASME OM Code. When testing the HCVS volume, allowed leakage shall not exceed the sum of the interfacingvalve leakages as determined from the ASME OM Code. The NRC staff will considera higher leakage acceptance values if licensees provide acceptable justification. When reviewing such requests, the NRC staff will consider the impact of the leakage on the habitabilityof the rooms and areas within the building and operability of equipment in these areasduring the event response and subsequent recovery periods. Licensees shall implement the following operation, testing and inspection requirementsfor the HCVS to ensure reliableoperation of the system. | |||
Testing and Inspection Requirements Description Frequency Cycle the HCVS valves and the interfacingsystem Once per year valves not used to maintain containment integrity during operations. | |||
Perform visual inspectionsand a walkdown of Once per operating cycle HCVS components Test and calibrate the HCVS radiationmonitors. Once per operatingcycle Leak test the HCVS. (1) Priorto first declaringthe system functional; (2) Once every five years thereafter and (3) After restorationof any breach of system boundary within the buildings Page 15 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Validate the HCVS operatingprocedures by Once per every other operating cycle conducting an open/close test of the HCVS control logic from its controlpanel and ensuring that all interfacing system valves move to their proper(intended)positions. | |||
Response (ref. ISG Item 1.2.7): | |||
The detailed design for the HCVS will address condensation accumulation resulting from intermittent venting. In situations where total elimination of condensation is not feasible, the HCVS will be designed to accommodate condensation, including allowance for applicable water hammer loads. | |||
The HCVS Containment Isolation Valves will be tested in accordance with the licensing and design basis for the plant. The HCVS past the outboard Containment Isolation Valve will be tested in conformance to the ISG methods. The test pressure shall be based on the HCVS design pressure. Permissible leakage rates for the interfacing valves will be within the requirements of American Society of Mechanical Engineers Operation and Maintenance of Nuclear Power Plants Code (ASME OM) - 2009, Subsection ISTC - 3630, or later edition of the ASME OM Code. When testing the HCVS volume, the allowed leakage will not exceed the sum of the interfacing valve leakages as determined from the ASME OM Code unless a higher leakage acceptance value is justified to the NRC. | |||
The test types and frequencies will conform to the ISG 1.2.7 Table "Testing and inspection Requirements" with the clarification that "Leak test the HCVS" applies to the HCVS boundary valves. Rupture disks (if retained in the final design) will be replaced at manufacturer's recommendations not to exceed 10 years. Interfacing system valves that cannot be cycled on line without challenging plant operation will be on an operating cycle frequency rather than once per year. | |||
Order EA-050 1.2.8 Requirement: | |||
The HCVS shall be designed for pressures that are consistent with maximum containmentdesign pressures, as well as, dynamic loading resulting from system actuation. | |||
ISG 1.2.8 Criteria: | |||
The vent system shall be designed for the higher of the primary containmentdesign pressure or PCPL, and a saturationtemperaturecorrespondingto the HCVS design pressure.However, if the venting locationis from the drywell, an additionalmargin of 50 TF shall be added to the design temperaturebecause of the potential for superheatedconditions in the drywell. The piping, valves, and the valve actuators shall be designed to withstand the dynamic loadingresulting from the actuation of the system, including piping reactionloads from valve opening, concurrenthydrodynamic loads from SRV dischargesto the suppression pool, and potential for water hammer from accumulation of steam condensation during multiple venting cycles. | |||
Response (ref. ISG Item 1.2.8): | |||
The HCVS design pressure will be 56 psig and design temperature is 281°F. The HCVS design pressure is the higher of the containment design pressure and the PCPL value. The HCVS design temperature is the saturation temperature corresponding to the design pressure. | |||
The piping, valves, and valve actuators will be designed to withstand the dynamic loading resulting from the actuation of the HCVS, including piping reaction loads from valve opening, concurrent hydrodynamic loads from SRV discharges to the suppression pool, and potential for water hammer from accumulation of condensation during multiple venting cycles. | |||
Page 16 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Order EA-050 1.2.9 Requirement: | |||
The HCVS shall discharge the effluent to a release point above main plant structures. | The HCVS shall discharge the effluent to a release point above main plant structures. | ||
ISG 1.2.9 Criteria: The HCVS release to outside atmosphere shall be at an elevation higher than | ISG 1.2.9 Criteria: | ||
Release through existing plant stacks is considered acceptable, provided the guidance under Requirement 1.2.6 is satisfied. | The HCVS release to outside atmosphere shall be at an elevation higher than adjacentplant structures. | ||
If the release from HCVS is through a stack different than the plant stack, the elevation of the stack should be higher than the | Release through existing plant stacks is considered acceptable,provided the guidance under Requirement 1.2.6 is satisfied. If the release from HCVS is through a stack different than the plant stack, the elevation of the stack should be higher than the nearestbuilding or structure. The releasepoint should be situated away from ventilation system intake and exhaust openings, and emergency response facilities. The release stack or structure exposed to outside shall be designed or protected to withstand missiles that could be generated by the externalevents causing the prolonged SBO (e.g., tornadoes, high winds). | ||
The | Response (ref. ISG Item 1.2.9): | ||
The release stack or structure exposed to outside shall be designed or protected to withstand missiles that could be generated by the | The HCVS discharge path will use the existing path through the plant off gas stack whose release point is elevated above other plant structures. As noted above upgrades to interfacing valves in the flow path are needed to ensure requirements in 1.2.6 above are satisfied. | ||
As noted above upgrades to interfacing valves in the flow path are needed to ensure requirements in 1.2.6 above are satisfied. | The detailed design will address missile protection from external events as defined by the existing plant design requirements for the off gas stack. | ||
The detailed design will address missile protection from external events as defined by the existing plant design requirements for the off gas stack.Page 17 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 4: Applicable Quality Requirements Order EA-050 2.1 Requirement: | Page 17 of 25 | ||
The HCVS system design shall not preclude the containment isolation valves, including the vent valve from performing their intended containment isolation function consistent with the design basis for the plant. These items include piping, piping supports, | |||
ISG 2.1 Criteria: The HCVS vent path up to and including the second containment | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 4: Applicable Quality Requirements Order EA-050 2.1 Requirement: | ||
The HCVS design, out to and including the second | The HCVS system design shall not preclude the containment isolation valves, including the vent valve from performing their intended containment isolation function consistent with the design basis for the plant. These items include piping, piping supports, containmentisolation valves, containmentisolation valve actuators and containment isolation valve position indication components. | ||
All other HCVS components shall be designed for reliable and rugged performance that is capable of ensuring HCVS functionality following a seismic event. These items include | ISG 2.1 Criteria: | ||
ISG 2.2 Criteria: All components of the HCVS beyond the second | The HCVS vent path up to and including the second containment isolationbarriershall be designed consistent with the design basis of the plant. These items include piping, piping supports, containment isolation valves, containmentisolation valve actuators and containment isolation valve position indication components. The HCVS design, out to and including the second containmentisolation barrier,shall meet safety-related requirements consistent with the design basis of the plant. The staff notes that in response to GL 89-16, in many cases, the HCVS vent line connections were made to existing systems. In some cases, the connection was made in between two existing containmentisolation valves and in others to the vacuum breakerline. The HCVS system design shall not preclude the containment isolation valves, including the vent valve from performing their intended containmentisolation function consistent with the design basis for the plant. The design shall include all necessary overrides of containmentisolation signalsand other interface system signalsto enable the vent valves to open upon initiation of the HCVS from its control panel Response (ref. ISG Item 2.1): | ||
The design of power and pneumatic supply lines between the HCVS valves and remote locations (if portable sources were to be employed) shall also be designed to ensure HCVS functionality. | The HCVS vent path up to and including the second containment isolation barrier piping and supports will be designed in accordance with existing design basis. The HCVS system design will not preclude the containment isolation valves, including the vent valve from performing their intended containment isolation function consistent with the design basis for the plant. The control circuit will allow manual overrides of containment isolation signals or if applicable interface system signal to enable the vent valves to open upon initiation of the HCVS from the MCR or other accessible location. | ||
Licensees shall ensure that the HCVS will not impact other safety-related structures and components and that the HCVS will not be impacted by non-seismic components. | Order EA-050 2.2 Requirement: | ||
The staff prefers that the HCVS components, including the piping run, be located in seismically | All other HCVS components shall be designed for reliable and rugged performance that is capable of ensuring HCVS functionality following a seismic event. These items include electricalpower supply, valve actuatorpneumatic supply, and instrumentation (localand remote) components. | ||
However, short runs of HCVS piping in non-seismic structures are acceptable if the licensee provides | ISG 2.2 Criteria: | ||
The hardened vent shall be designed to conform to the | All components of the HCVS beyond the second containmentisolation barriershall be designed to ensure HCVS functionality following the plant's design basis seismic event. These components include, in addition to the hardened vent pipe, electric power supply, pneumatic supply and instrumentation. The design of power and pneumatic supply lines between the HCVS valves and remote locations (if portable sources were to be employed) shall also be designed to ensure HCVS functionality. Licensees shall ensure that the HCVS will not impact other safety-related structures and components and that the HCVS will not be impacted by non-seismic components. The staff prefers that the HCVS components, including the piping run, be located in seismically qualifiedstructures. However, short runs of HCVS piping in non-seismic structures are acceptable if the licensee provides adequatejustification on the seismic ruggednessof these structures. The hardened vent shall be designed to conform to the requirementsconsistent with the applicable design codes for the plant,such as the American Society of Mechanical EngineersBoiler and Pressure Vessel Code and the applicable Specifications, Codes and Standardsof the American Institute of Steel Construction. | ||
To ensure the functionality of instruments following a seismic event, the NRC staff considers any of the following as | To ensure the functionality of instruments following a seismic event, the NRC staff considers any of the following as acceptablemethods: | ||
* | * Use of instruments and supporting components with known operating principles that are supplied by manufacturers with commercial quality assurance programs, such as IS09001. The procurement specifications shall include the seismic requirements and/or instrument design requirements, and Page 18 of 25 | ||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System specify the need for commercial design standards and testing under seismic loadings consistent with design basis values at the instrument locations. | |||
* Demonstrationof the seismic reliabilityof the instrumentation through methods that predict performance by analysis, qualification testing under simulated seismic conditions, a combination of testing and analysis, or the use of experience data. Guidance for these is based on sections 7, 8, 9, and 10 of IEEE Standard 344-2004, "IEEE | |||
" Recommended Practice for Seismic Qualification of Class 1E Equipment for Nuclear Power Generating Stations," or a substantiallysimilarindustrialstandardcould be used. | |||
" Demonstration that the instrumentation is substantially similar in design to instrumentation that has been previously tested to seismic loading levels in accordance with the plant design basis at the location where the instrument is to be installed (g-levels and frequency ranges). Such testing and analysisshould be similarto that performed for the plant licensingbasis. | |||
Response (ref. ISG Item 2.2): | |||
The HCVS components downstream of the second containment isolation valve and components that interface with the HCVS will be routed in seismically qualified structures or reviewed for seismic ruggedness to ensure that any potential failure would not adversely impact the function of the HCVS or other safety related structures or components (i.e. seismic category II over category I criteria). | |||
The HCVS downstream of the second containment isolation valve, including piping and supports, electrical power supply, valve actuator pneumatic supply, and instrumentation (local and remote) components, will be designed/analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake. | The HCVS downstream of the second containment isolation valve, including piping and supports, electrical power supply, valve actuator pneumatic supply, and instrumentation (local and remote) components, will be designed/analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake. | ||
The HCVS instruments, including valve position indication, process instrumentation, radiation monitoring, and support system monitoring, will be qualified by using one of the three methods described in the ISG, which includes: 1. Purchase of instruments and supporting components with known operating principles from manufacturers with commercial quality assurance programs (e.g., IS09001) where the procurement specifications include the applicable seismic requirements, design requirements, and applicable testing.2. Demonstration of seismic reliability via methods that predict performance described in IEEE 344-2004 3. Demonstration that instrumentation is substantially similar to the design of instrumentation previously qualified. | The HCVS instruments, including valve position indication, process instrumentation, radiation monitoring, and support system monitoring, will be qualified by using one of the three methods described in the ISG, which includes: | ||
Instrument Qualification Method*HCVS Process Temperature IS09001 / IEEE 344-2004 / Demonstration HCVS Process Pressure ISO9001 / IEEE 344-2004 / Demonstration HCVS Process Radiation Monitor IS09001 / IEEE 344-2004 1 Demonstration HCVS Process Valve Position IS09001 / IEEE 344-2004 / Demonstration HCVS Pneumatic Supply Pressure IS09001 / IEEE 344-2004 / Demonstration HCVS Electrical Power Supply Availability IS09001 / IEEE 344-2004 / Demonstration Page 19 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 5: Procedures and Training Order EA-050 3.1 Requirement: | : 1. Purchase of instruments and supporting components with known operating principles from manufacturers with commercial quality assurance programs (e.g., IS09001) where the procurement specifications include the applicable seismic requirements, design requirements, and applicable testing. | ||
Licensees shall develop, implement, and | : 2. Demonstration of seismic reliability via methods that predict performance described in IEEE 344-2004 | ||
ISG 3.1 Criteria: | : 3. Demonstration that instrumentation is substantially similar to the design of instrumentation previously qualified. | ||
The | Instrument Qualification Method* | ||
These provisions shall be documented in the Technical Requirements Manual (TRM) or similar document. | HCVS Process Temperature IS09001 / IEEE 344-2004 / Demonstration HCVS Process Pressure ISO9001 / IEEE 344-2004 / Demonstration HCVS Process Radiation Monitor IS09001 / IEEE 344-2004 1 Demonstration HCVS Process Valve Position IS09001 / IEEE 344-2004 / Demonstration HCVS Pneumatic Supply Pressure IS09001 / IEEE 344-2004 / Demonstration HCVS Electrical Power Supply Availability IS09001 / IEEE 344-2004 / Demonstration Page 19 of 25 | ||
The allowed | |||
The HCVS procedures will be developed and implemented following the plants process for initiating or revising procedures and contain the following details:* appropriate conditions and criteria for use of the HCVS* when and how to place the HCVS in operation,* the location of system components,* instrumentation available,* normal and backup power supplies,* directions for sustained operation(reference NEI 12-06), including the storage location of portable equipment,* training on operating the portable equipment, and* testing of portable equipment. | Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 5: Procedures and Training Order EA-050 3.1 Requirement: | ||
The procedures will ensure adequate containment over-pressure is maintained for ECCS pump net positive suction head during a DBA LOCA.The following provisions for out-of-service restrictions for the HCVS and associated compensatory measures will be documented in the Technical Requirements Manual (TRM): The allowed out of service time for the HCVS shall not exceed 30 days during Modes 1, 2, and 3.* If the out of service time exceeds 30 days: o The condition will be entered into the corrective action system, o Action will be initiated to restore functionality of the HCVS o A cause assessment will be performed to prevent future unavailability for similar causes.Page 20 of 25 Duane Arnold Enerqy Center Overall Integrated Plan for the Reliable Hardened Vent System Order EA-050 3.2 Requirement: | Licensees shall develop, implement, and maintainprocedures necessary for the safe operation of the HCVS. Proceduresshall be established for system operationswhen normal and backup power is available, and during SBO conditions. | ||
Licensee shall train | ISG 3.1 Criteria: | ||
ISG 3.2 Criteria: All | Proceduresshall be developed describingwhen and how to place the HCVS in operation,the location of system components, instrumentation available, normal and backup power supplies, directions for sustained operation,including the storage location of portable equipment, training on operating the portable equipment, and testing of equipment. The proceduresshall identify appropriateconditions and criteria for use of the HCVS. The procedures shall clearly state the nexus between CAP and ECCS pumps during a DBLOCA and how an inadvertentopening of the vent valve could have an adverse impact on this nexus. | ||
The | The HCVS proceduresshall be developed and implemented in the same manner as otherplant procedures necessary to support the execution of the Emergency OperatingProcedures(EOPs). | ||
The training will be performed on a periodic basis and as any changes occur to the HCVS. The training will utilize the systematic approach to training.Page 21 of 25 Duane Arnold Enerqv Center Overall Intearated Plan for the Reliable Hardened Vent System Section 6: Implementation Schedule Milestones The following milestone schedule is provided. | Licensees shall establishprovisions for out-of-service requirements of the HCVS and compensatory measures. These provisions shall be documented in the Technical Requirements Manual (TRM) or similar document. The allowed unavailabilitytime for the HCVS shall not exceed 30 days during modes 1, 2, and 3. | ||
The dates are planning dates subject to change as design and implementation details are developed. | If the unavailabilitytime exceeds 30 days, the TRM shall direct licensees to perform a cause assessment and take the necessary actions to restore HCVS availabilityin a timely manner, consistent with plant procedures and prevent future unavailabilityfor similarcauses. | ||
Any changes to the following target dates will be reflected in the subsequent 6 month status reports.Original Target Activity Status Date Oct. 2012 Submit 60 Day Status Report Complete Feb. 2013 Submit Overall Integrated Implementation Plan Complete Aug 2013 Submit 6 Month Status Report Feb. 2014 Submit 6 Month Status Report Aug. 2014 Submit 6 Month Status Report Feb. 2015 Submit 6 Month Status Report Aug. 2015 Submit 6 Month Status Report Dec. 2015 Completed Design Change Package issued for construction Feb. 2016 Submit 6 Month Status Report June 2016 Procedure Changes Training Material Complete July 2016 Design Change Major Material On-site Aug. 2016 Submit 6 Month Status Report RFO 25 Fall 2016 Design Change Construction Completed RFO 25 Fall 2016 Procedure Changes Active RFO 25 Fall 2016 Demonstration/Functional Test Dec. 2016 Submit Completion Report Page 22 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 7: Changes/Updates to this Overall Integrated Implementation Plan Any significant changes to this plan will be communicated to the NRC staff in the 6 Month Status Reports.Page 23 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 8: Figures/Diagrams ISG IV.C. 1. Reporting Requirements: | Response (ref. ISG Item 3.1): | ||
A piping and | Procedures will be established for system operations when normal and backup power is available, and during prolonged SBO conditions. | ||
Response (ref. ISG Item 3.2): In addition, per Staff request, a Table has been included to discuss various potential failure modes in the proposed design.V05-0197 V05-0134 GE V04-0B84 Page 24 of 25 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent Svstem Potential Failure Evaluation Table (Proposed Design)Functional Failure Failure Cause Alternate Action Alternate Action Mode Corrects Failure One or Both Loss of Normal AC power to DC power solenoid supplying Yes Containment Isolation solenoid valve supplying nitrogen gas Valve Fails to Open on nitrogen gas, Demand Loss of AC and DC power Recharge DC batteries with FLEX Yes diesel generator or portable pneumatic supply via manual connection (future installation) | The HCVS procedures will be developed and implemented following the plants process for initiating or revising procedures and contain the following details: | ||
Loss of safety related Portable pneumatic supply via Yes Alternate Nitrogen manual connection (future installation) | * appropriate conditions and criteria for use of the HCVS | ||
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation) | * when and how to place the HCVS in operation, | ||
Mechanical valve problem None No One Containment Any failure Close alternate valve Yes Isolation Valve Fails to Close on Demand Both Containment Both solenoid valves fail to De-pressurize Alternate Nitrogen Yes Isolation valves Fail to close for any reason supply to solenoid Close and Rupture Disc | * the location of system components, | ||
Failure to be able to Loss of safety related Portable pneumatic supply via Yes open rupture disc if Alternate Nitrogen manual connection (future rupture disk is retained installation) | * instrumentation available, | ||
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation) | * normal and backup power supplies, | ||
Rupture disk does not open None. No as designed at available pressure Page 25 of 25}} | * directions for sustained operation(reference NEI 12-06), including the storage location of portable equipment, | ||
* training on operating the portable equipment, and | |||
* testing of portable equipment. | |||
The procedures will ensure adequate containment over-pressure is maintained for ECCS pump net positive suction head during a DBA LOCA. | |||
The following provisions for out-of-service restrictions for the HCVS and associated compensatory measures will be documented in the Technical Requirements Manual (TRM): | |||
The allowed out of service time for the HCVS shall not exceed 30 days during Modes 1, 2, and 3. | |||
* If the out of service time exceeds 30 days: | |||
o The condition will be entered into the corrective action system, o Action will be initiated to restore functionality of the HCVS o A cause assessment will be performed to prevent future unavailability for similar causes. | |||
Page 20 of 25 | |||
Duane Arnold Enerqy Center Overall Integrated Plan for the Reliable Hardened Vent System Order EA-050 3.2 Requirement: | |||
Licensee shall train appropriatepersonnelin the use of the HCVS. The trainingcurricula shall include system operations when normal and backup power is available, and during SBO conditions. | |||
ISG 3.2 Criteria: | |||
All personnelexpected to operate the HCVS shall receive trainingin the use of plantprocedures developed for system operationswhen normal and backup power is available, and during SBO conditions consistent with the plants systematic approachto training. The trainingshall be refreshed on a periodic basis and as any changes occur to the HCVS. | |||
Response (ref. ISG Item 3.2): | |||
Personnel expected to operate the HCVS will receive necessary training in the use of plant procedures for system operations when normal and backup power is available and during prolonged SBO conditions. The training will be performed on a periodic basis and as any changes occur to the HCVS. The training will utilize the systematic approach to training. | |||
Page 21 of 25 | |||
Duane Arnold Enerqv Center Overall Intearated Plan for the Reliable Hardened Vent System Section 6: Implementation Schedule Milestones The following milestone schedule is provided. The dates are planning dates subject to change as design and implementation details are developed. Any changes to the following target dates will be reflected in the subsequent 6 month status reports. | |||
Original Target Activity Status Date Oct. 2012 Submit 60 Day Status Report Complete Feb. 2013 Submit Overall Integrated Implementation Plan Complete Aug 2013 Submit 6 Month Status Report Feb. 2014 Submit 6 Month Status Report Aug. 2014 Submit 6 Month Status Report Feb. 2015 Submit 6 Month Status Report Aug. 2015 Submit 6 Month Status Report Dec. 2015 Completed Design Change Package issued for construction Feb. 2016 Submit 6 Month Status Report June 2016 Procedure Changes Training Material Complete July 2016 Design Change Major Material On-site Aug. 2016 Submit 6 Month Status Report RFO 25 Fall 2016 Design Change Construction Completed RFO 25 Fall 2016 Procedure Changes Active RFO 25 Fall 2016 Demonstration/Functional Test Dec. 2016 Submit Completion Report Page 22 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 7: Changes/Updates to this Overall Integrated Implementation Plan Any significant changes to this plan will be communicated to the NRC staff in the 6 Month Status Reports. | |||
Page 23 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 8: Figures/Diagrams ISG IV.C. 1. Reporting Requirements: | |||
A piping and instrumentationdiagram or a similar diagram that shows system components and interfaces with plant systems and structures is acceptable. | |||
Response (ref. ISG Item 3.2): | |||
In addition, per Staff request, a Table has been included to discuss various potential failure modes in the proposed design. | |||
V05-0197 V05-0134 GE V04-0B84 Page 24 of 25 | |||
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent Svstem Potential Failure Evaluation Table (Proposed Design) | |||
Functional Failure Failure Cause Alternate Action Alternate Action Mode Corrects Failure One or Both Loss of Normal AC power to DC power solenoid supplying Yes Containment Isolation solenoid valve supplying nitrogen gas Valve Fails to Open on nitrogen gas, Demand Loss of AC and DC power Recharge DC batteries with FLEX Yes diesel generator or portable pneumatic supply via manual connection (future installation) | |||
Loss of safety related Portable pneumatic supply via Yes Alternate Nitrogen manual connection (future installation) | |||
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation) | |||
Mechanical valve problem None No One Containment Any failure Close alternate valve Yes Isolation Valve Fails to Close on Demand Both Containment Both solenoid valves fail to De-pressurize Alternate Nitrogen Yes Isolation valves Fail to close for any reason supply to solenoid Close Open and Rupture Disc Mechanical problems in both None valves No Spurious Containment Not credible as key locked NA NA Isolation Valve Opening switches prevent miss-positioning and two valves are normally closed Automatic Containment High containment pressure Over ride containment isolation Yes Isolation Closure from signal or portable pneumatic other signals supply via manual connection (future installation) | |||
Failure to be able to Loss of safety related Portable pneumatic supply via Yes open rupture disc if Alternate Nitrogen manual connection (future rupture disk is retained installation) | |||
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation) | |||
Rupture disk does not open None. No as designed at available pressure Page 25 of 25}} | |||
Revision as of 21:30, 4 November 2019
| ML13063A019 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 02/28/2013 |
| From: | Richard Anderson NextEra Energy Duane Arnold |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| EA-12-050, NG-13-0085 | |
| Download: ML13063A019 (28) | |
Text
NEXTeraM ENERG--YPA DUAN
ýARNOLD February 28, 2013 NG-1 3-0085 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NextEra Energy-Duane Arnold, LLC's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents (Order Number EA-12-050)
References:
- 1. NRC Order Number EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, dated March 12, 2012, Accession No. ML12054A694
- 2. NRC Interim Staff Guidance JLD-ISG-2012-02, Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents, Revision 0, dated August 29, 2012, Accession No. ML12229A475
- 3. Letter, R. Anderson (NextEra Energy Duane Arnold, LLC) to U.S. NRC, "NextEra Energy Duane Arnold, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)," NG-12-0427, dated October 29, 2012, Accession No. ML12305A375 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an Order (Reference 1) to NextEra Energy Duane Arnold, LLC (hereafter, NextEra Energy Duane Arnold). Reference 1 was immediately effective and directs NextEra Energy Duane Arnold to have a reliable hardened vent (RHV) installed at its Boiling Water Reactor (BWR) with a Mark I Containment to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged Station Blackout (SBO). Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an Overall Integrated Plan by February 28, 2013. The NRC Interim Staff Guidance (Reference 2) was issued August 29, 2012, which provides direction regarding the content of this Overall Integrated Plan.
NextEra Energy Duane Arnold, LLC, 3277 DAEC Road, Palo, IA52324
Document Control Desk NG-13-0085 Page 2 of 2 Reference 3 acknowledged NextEra Energy Duane Arnold's receipt of Reference 2 and provided the initial status report regarding the RHV, as required by Reference 1.
The purpose of this letter is to provide the Overall Integrated Plan pursuant to Section IV, Condition C.1, of Reference 1. Reference 2, Section 4.0 contains the specific reporting requirements for the Overall Integrated Plan. The Enclosure to this letter provides NextEra Energy Duane Arnold's Overall Integrated Plan in accordance with Section 4.0 of Reference 2.
For the purposes of compliance with Order EA-1 2-050 (Reference 1), NextEra Energy Duane Arnold plans to use a wetwell vent system. The potential addition of a hardened drywell vent system will not be determined until additional review of industry studies of severe accidents is completed.
The Enclosure contains the current design information as of the writing of this letter, much of which is still preliminary, pending completion of on-going evaluations and analyses. Due to the synergy between the design of the RHV system and the equipment to be utilized in the Mitigating Strategies (so called FLEX) required by Order EA-12-049, some of the design details, in particular those regarding backup DC power and pneumatic supplies for the RHV, are still being developed. As further design details and associated procedure guidance are finalized, that additional information, as well as any revisions to the information contained in the Enclosure, will be communicated to the Staff in the 6-month updates required by the Orders.
This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact Ken Putnam at 319-851-7238.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on February 28, 2013 Richard L. Anderson Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC
Enclosure:
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System cc: NRC Regional Administrator (Region Ill)
NRC Resident Inspector (DAEC)
NRC Licensing Project Manager (DAEC)
Enclosure to NG-13-0085 Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System 25 Pages to Follow
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Table of Contents:
Section 1: System Description Section 2: Design Objectives Requirement 1.1.1 - Minimize the Reliance on Operator Actions Requirement 1.1.2 - Minimize Plant Operators' Exposure to Occupational Hazards Requirement 1.1.3 - Minimize Radiological Consequences Section 3: Operational Characteristics Requirement 1.2.1 - Capacity to Vent Equivalent of 1%
Requirement 1.2.2 - HCVS Shall be Accessible to Plant Operators Requirement 1.2.3 - Prevent Inadvertent Actuation Requirement 1.2.4 - Monitor the Status of the Vent System Requirement 1.2.5 - Monitor the Effluent Discharge for Radioactivity Requirement 1.2.6 - Minimize Unintended Cross Flow of Vented Fluids Requirement 1.2.7 - Provision for the Operation, Testing, Inspection and Maintenance Requirement 1.2.8 - Design Pressures Requirement 1.2.9 - Discharge Release Point Section 4: Applicable Quality Requirements Requirement 2.1 - Containment Isolation Function Requirement 2.2 - Reliable and Rugged Performance Section 5: Procedures and Training Requirement 3.1 - Develop, Implement, and Maintain Procedures Requirement 3.2 - Train Appropriate Personnel Section 6: Implementation Schedule Milestones Section 7: Changes/Updates to this Overall Integrated Implementation Plan Section 8: Figures/Diagrams
References:
1 Generic Letter 89-16, Installation of a Hardened Wetwell Vent, dated September 1, 1989 2 Order EA-049, Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 3 Order EA-050, Reliable Hardened Containment Vents, dated March 12, 2012 4 JLD-ISG-2012-02, Compliance with Order EA-12-050, Reliable Hardened Containment Vents, dated August 29, 2012 5 NRC Responses to Public Comments, Japan Lessons-Learned Project Directorate Interim Staff Guidance JLD-ISG-2012-02: Compliance with Order EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, dated August 29, 2012, ADAMS Accession No. ML12229A477 6 NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012 Page I of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 1: System Description ISG Criteria:
Licensees shall provide a complete description of the system, including importantoperational characteristics.The level of detail generally considered adequate is consistent with the level of detail containedin the licensee's Final Safety Analysis Report.
Response
System Overview:
The Hardened Containment Vent System (HCVS) will be designed to mitigate loss-of-decay-heat removal by providing sufficient containment venting capability to limit containment pressurization and maintain core cooling capability. The vent will be designed with sufficient capacity to accommodate decay heat input equivalent to approximately 1% of current licensed thermal power and will be capable of venting greater than the decay heat present when venting must be initiated to ensure the containment does not exceed design pressure. And thus, the hardened vent capacity will be adequate to relieve decay heat for a prolonged station blackout (SBO) event. The HCVS is intended for use as one element of core damage prevention strategies The HCVS flow path from the containment to an elevated release point is shown in the simplified diagram below. No ductwork will be used in the flow path.
Page 2 of 25
Duane Arnold Enerav Center Overall Integrated Plan for the Reliable Hardened Vent System Figure 1 Simplified Vent Line Connections to Wetwell and Other Systems System Connection Options Option 1 - Dedicated wetwell vent-Not Currently Selected Option Vent
%Detail Option 2 - Wetwell vent interfacing with another wetwell-connected system, dedicated release point-Currently Selected Option Vent To other sys te m s
P Option 3 - Wetwell vent interfacing with another wetwell-connected system and with an existing release point-Not Currently Selected Option To Stack A9 To othe4 ~~
syste ms Detail Options Option A - No control valve or rupture disk (Not Currently Selected Option)
Option B - Rupture disk (Currently Selected Option)
Option C - Control valve (Not Currently Selected Option) ii+/- 1 Page 3 of 25
Duane Arnold Enerqy Center Overall Integrated Plan for the Reliable Hardened Vent System Equipment and components:
The following equipment and components will be provided:
- i. HCVS Mechanical Components -
a) Containment isolation piping, valves and controls - The HCVS vent piping and supports up to and including the second containment isolation are designed in accordance with existing design basis. Containment isolation valves (CIVs) are provided consistent with the plants primary containment isolation valve design basis. The valves are air-operated valves (AOV) operated by a DC powered solenoid valve (SOV), and can be operated from switches in the Main Control Room.
b) Other system valves and piping - The HCVS piping and supports downstream of the second containment isolation valve, including valve actuator pneumatic supply components, will be designed/analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake.
c) The interface valves provide isolation to the interconnected system. The HCVS shares part of its flow path with the Standby Gas Treatment System (SGTS).
Prior to initiating the HCVS, the valve to the SGTS must be isolated. However, since SGTS isolation valves are fail-close AOV(s), with air-to-open and spring to shut, the containment isolation signal will automatically isolate the valve(s) upon any abnormal containment pressure.
d) A rupture disk is currently provided in the vent line downstream of the CIVs. It is anticipated that this rupture disk will be retained following the modifications to improve the reliability of the hardened vent. Provisions will be made to pressurize the disk from Main Control Room as directed by applicable procedures to allow venting earlier in the event if desired. The final design may elect to remove the rupture disk or replace it with a rupture disk with a different pressure set.
ii. Instrumentation to monitor the status of the HCVS -
a) Instrumentation indications will be available in the Main Control Room b) Effluent radiation monitor will be located external to the vent piping.
c) HCVS vent flow path valves position indication, temperature and pressure instrumentation will monitor the status of the HCVS to aid the operator to ensure verification of proper venting operation. A failure of the position indication instrumentation would not prevent opening and closing the valves.
iii. Support systems -
a) Existing power for the HCVS DC valve solenoids is provided from the 125 Volt Essential DC Batteries.
b) Motive air/gas supply for HCVS operation under the current plant design are adequate for at least three strokes of the valves during the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> during operation under prolonged SBO conditions is provided from an accumulator in the Atmosphere Control System (1T429). Ifthe final containment analysis Page 4 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System supporting the HCVS determines that additional valve cycles are needed, the accumulator capacity will be upgraded to match the required number of cycles.
c) Under DAEC implementation of NRC Order EA-12-049 for Mitigation of Strategies for Beyond -Design-Bases External Events, FLEX equipment will have the capability to provide back-up support equipment for reliable HCVS operation. Power will be supplied from a portable 480 volt generator connected to the applicable battery chargers. Motive air/gas for HCVS operation can be supplied from a portable cylinder if needed. Power for instrumentation will be supplied from the same batteries as the solenoids. In addition, alternate means to power critical indicators of containment parameters will be provided under the FLEX program.
System control:
Active: Control Valves are operated in accordance with EOPs to control containment pressure. The CIVs are currently designed for 3 open / close cycles. Current procedures call for operation of the valves to maintain a containment pressure band between 45 PSIG and 53 PSIG (PCPL) unless otherwise directed by the Technical Support Center.
ii. Passive: Inadvertent actuation protection will be provided by key lock switches for the CIV's that must be opened to permit flow.
Page 5 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 2: Design Obiectives Order EA-050 1.1.1 Requirement:
The HCVS shall be designed to minimize the reliance on operatoractions.
ISG 1.1.1 Criteria:
During events that significantly challenge plant operations,individual operators are more prone to human error.In addition, the plant operationsstaff may be required to implement strategies and/ortake many concurrent actions that furtherplaces a burden on its personnel. During the prolonged SBO condition at the Fukushima Dai-ichi units, operators faced many significant challenges while attempting to restore numerous plant systems that were necessary to cool the reactorcore, including the containment venting systems. The difficulties faced by the operatorsrelated to the location of the HCVS valves, ambient temperaturesand radiologicalconditions, loss of all alternatingcurrentelectricalpower,loss of motive force to open the vent valves, and exhausting dc battery power. The NRC staff recognizes that operatoractions will be needed to operate the HCVS valves; however, the licensees shall considerdesign features for the system that will minimize the need and relianceon operatoractions to the extent possible during a variety of plant conditions, as further discussed in this ISG.
The HCVS shall be designed to be operated from a control panel located in the main control room or a remote but readily accessible location. The HCVS shall be designed to be fully functional and self sufficient with permanently installed equipment in the plant, without the need for portable equipment or connecting thereto, until such time that additionalon-site or off-site personnel and portable equipment become available. The HCVS shall be capable of operatingin this mode (i.e., relying on permanently installed equipment) for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> during the prolonged SBO, unless a shorterperiod is justified by the licensee. The HCVS operation in this mode depends on a variety of conditions, such as the cause for the SBO (e.g., seismic event, flood, tornado, high winds), severity of the event, and time requiredfor additional help to reach the plant, move portableequipment into place, and make connections to the HCVS.
When evaluating licenseejustification for periods less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, the NRC staff will considerthe number of actions and the cumulative demand on personnelresources that are needed to maintainHCVS functionality (e.g., installation of portable equipment during the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to restore power to the HCVS controls and/orinstrumentation)as a result of design limitations. Forexample, the use of supplemental portablepower sources may be acceptable if the supplementalpower was readily available, could be quickly and easily moved into place, and installed through the use of pre-engineeredquick disconnects, and the necessary human actions were identified along with the time needed to complete those actions.
Conversely, supplemental power sources located in an unattended warehouse that require a qualified electrician to temporarilywire into the panel would not be consideredacceptable by the staff because its installation requires a series of complex, time-consuming actions in orderto achieve a successful outcome.
There are similarexamples that could apply to mechanical systems, such as pneumatic/compressedair systems.
Response (ref. ISG Item 1.1.1):
The operation of the HCVS will be designed to minimize the reliance on operator actions in response to hazards identified in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX)
Implementation Guide. The design will allow immediate operator actions to be completed by reactor operators in the Main Control Room (MCR) or other accessible location. The operator actions that will be required to open a vent path are:
Operator Actions Necessary to Vent the Containment during a Prolonged SBO Task Location Close interfacing system valves (new) MCR or Other Accessible Location Override containment isolation signal for CV4300 MCR Page 6 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Open Containment Isolation Valve CV4300 MCR Open HCVS control valve CV4357 MCR Isolation or cycling of the vent path can be directly performed from the MCR by operating either of the containment isolation valves (CV4300 or CV4357).
The HCVS will be designed to allow initiation, control, and monitoring of venting from the MCR or other accessible location. The location minimizes plant operators' exposure to adverse temperature and radiological conditions and is protected from hazards consistent with the existing plant design. In addition, an alternate capability to open the valves from a location outside the main control room in the essential switchgear room or another accessible location will be provided that allows applying portable pneumatic supply to directly actuate the HCVS valves in the event normal operation from the MCR is not available.
Permanently installed power and motive gas capability will be available to support operation and monitoring of the HCVS in the modified design. The current motive gas accumulator is sized for three cycles of the HCVS valves. In the event final containment analysis and procedure concludes addition cycle capacity is needed the accumulator will be upgraded accordingly. DC power will be maintained throughout the event using portable generators under the FLEX program and NEI 12-06. If for any reason, DC power or installed motive gas is unavailable, a back up capability will be provided to open the HCVS remotely from the essential switchgear room or other accessible location using a portable pneumatic supply.
Order EA-050 1.1.2 Requirement:
The HCVS shall be designed to minimize plant operators'exposure to occupationalhazards, such as extreme heat stress, while operating the HCVS system.
ISG 1.1.2 Criteria:
During a prolonged SBO, the drywell, wetwell (torus), and nearby areasin the plant where HCVS components are expected to be located will likely experience an excursion in temperatures due to inadequatecontainment cooling combined with loss of normal and emergency building ventilation systems.
In addition, installed normal and emergency lighting in the plant may not be available. Licensees should take into considerationplant conditions expected to be experienced during applicable beyond design basis externalevents when locatingvalves, instrumentair supplies, and other components that will be required to safely operate the HCVS system. Components requiredfor manual operation should be placed in areas that are readily accessible to plant operators,and not require additionalactions, such as the installationof ladders or temporary scaffolding, to operate the system.
When developing a design strategy, the NRC staff expects licensees to analyze potentialplant conditions and use its acquiredknowledge of these areas, in terms of how temperatures would reactto extended SBO conditions and the lighting that would be available during beyond design basis externalevents. This knowledge also provides an input to system operatingprocedures, training,the choice of protective clothing, required tools and equipment, and portable lighting.
Response (ref. ISG Item 1.1.2):
The HCVS design will allow operating the HCVS from the MCR or other accessible location which minimizes plant operators' exposure to adverse temperature and radiological conditions.
The MCR is protected from hazards consistent with the existing plant design and will be evaluated for acceptable temperature and radiological conditions.
In order to minimize operator exposure to temperature excursions due to the impact of the prolonged SBO (i.e., loss of normal and emergency building ventilation systems and/or containment temperature changes) procedures will not require access to suppression pool Page 7 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (wetwell) area and exposure to extreme occupational hazards for normal and backup operation of electrical and pneumatic systems.
Connections for supplemental equipment needed for sustained operation will be located in accessible areas protected from severe natural phenomena and minimize exposure to occupational hazards. Tools required for sustained operation, such as portable lights and connection specific tooling will be pre-staged in the NEI 12-06 storage locations or the control room.
Neither temporary ladders nor scaffold will be required to access these connections or storage locations.
Order EA-050 1.1.3 Requirement:
The HCVS shall also be designed to minimize radiologicalconsequences that would impede personnel actions needed for event response.
ISG 1.1.3 Criteria:
The design of the HCVS should take into considerationthe radiologicalconsequences resultingfrom the event that could negatively impact event response. During the Fukushima event, personnelactions to manually operate the vent valves were impeded due to the location of the valves in the torus rooms. The HCVS shall be designed to be placed in operation by operatoractions at a control panel, located in the main control room or in a remote location. The system shall be deigned to function in this mode with peirnanently installed equipment providing electricalpower (e.g., dc power batteries)and valve motive force (e.g., N2Iair cylinders). The system shall be designed to function in this mode for a minimum duration of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with no operatoractions required or credited, other than the system initiatingactions at the control panel.
Durationsof less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> will be considered if justified by adequate supporting information from the licensee. To ensure continued operation of the HCVS beyond 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, licensees may credit manual actions, such as moving portable equipment to supplement electricalpower and valve motive power sources.
In response to Generic Letter (GL) 89-16, a number of facilities with Mark I containments installed vent valves in the torus room, near the drywell, or both. Licensees can continue to use these venting locations or select new locations,provided the requirements of this guidance document are satisfied. The HCVS improves the chances of core cooling by removing heat from containment and lowering containment pressure, when core cooling is provided by other systems. If core cooling were to fail and result in the onset core damage, closure of the vent valves may become necessary if the system was not designed for severe accident service. In addition, leakage from the HCVS within the plant and the location of the externalrelease from the HCVS could impact the event response from on-site operators and off-site help arrivingat the plant.
An adequate strategy to minimize radiologicalconsequences that could impede personnelactions should include the following:
- 1. Licensees shall provide permanent radiationshielding where necessary to facilitate personnel access to valves and allow manual operation of the valves locally. Licensee may use altematives such as providing features to facilitate manual operation of valves from remote locations, as discussed furtherin this guidance under Requirement 1.2.2, or relocate the vent valves to areas that are significantly less challenging to operatoraccess/actions.
- 2. In accordance with Requirement 1.2.8, the HCVS shall be designed for pressures that are consistent with the higher of the primary containment design pressure and the primary containmentpressure limit (PCPL),
as well as including dynamic loading resultingfrom system actuation.In addition, the system shall be leak-tight. As such, ventilation duct work (i.e., sheet metal) shall not be utilized in the design of the HCVS.
Licensees should perform appropriatetesting, such as hydrostatic or pneumatic testing, to establish the leak-tightness of the HCVS.
- 3. The HCVS release to outside atmosphere shall be at an elevation higherthan adjacent plant structures.
Release through existing plant stacks is considered acceptable,provided the guidance under Requirement 1.2.6 is satisfied. If the release from HCVS is through a vent stack different than the plant stack, the elevation of the stack should be higherthan the nearest building or structure.
Page 8 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Response (ref. ISG Item 1.1.3):
The HCVS will be designed for reliable remote-manual operation. Operators will not be required to access the suppression pool area. The HCVS will be designed to minimize system cross flow, prevent steam flow into unintended areas, provide containment isolation, and provide reliable and rugged performance as discussed below for Order requirements 1.2.6.
Dose rates will be evaluated consistent with the assumption that the HCVS is to be used for the prevention of significant core damage. Shielding or other alternatives to facilitate manual actions are not required for operation of the vent under these conditions since no core damage has occurred and operator actions can be completed in the MCR or other accessible location.
Page 9 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 3: Operational Characteristics Order EA-050 1.2.1 Requirement:
The HCVS shall have the capacity to vent the steam/energy equivalent of I percent of licensed/rated thermalpower (unless a lower value is justified by analyses), and be able to maintain containmentpressure below the primary containment design pressure.
ISG 1.2.1 Criteria:
Beyond design basis extemal events such as a prolonged SBO could result in the loss of active containment heat removal capability. The primary design objective of the HCVS is to provide sufficient venting capacity to prevent a long-term overpressure failure of the containment by keeping the containmentpressure below the primary containment design pressure and the PCPL. The PCPL may be dictated by other factors, such as the maximum containmentpressure at which the safety relief valves (SRVs) and the HCVS valves can be opened and closed.
The NRC staff has determined that, for a vent sized under conditions of constant heat input at a rate equal to I percent of rated thermal power and containmentpressure equal to the lower of the primary containment design pressure and the PCPL, the exhaust-flow through the vent would be sufficient to prevent the containmentpressure from increasing. This determination is based on studies that have shown that the torus suppression capacity is typically sufficient to absorb the decay heat generatedduring at least the first three hours following the shutdown of the reactorwith suppression pool as the source of injection, that decay heat is typically less than 1 percent of rated thermalpower three hours following shutdown of the reactor,and that decay heat continues to decrease to well under 1 percent, thereafter.Licensees shall have an auditable engineering basis for the decay heat absorbingcapacity of theirsuppression pools, selection of venting pressure such that the HCVS will have sufficient venting capacity under such conditions to maintain containmentpressure at or below the primary containmentdesign pressure and the PCPL. If required, venting capacity shall be increasedto an appropriatelevel commensurate with the licensee's venting strategy. Licensees may also use a venting capacity sized under conditions of constant heat input at a rate lower than 1 percent of thermal power if it can be justified by analysis that primary containment design pressure and the PCPL would not be exceeded. In cases where plants were granted,have applied, or plan to apply for power uprates, the licensees shall use 1 percent thermal power correspondingto the uprated thermalpower. The basis for the venting capacityshall give appropriateconsiderationof where venting is being performed from (i.e., wetwell or drywell) and the difference in pressure between the drywell and the suppression chamber. Vent sizing for multi-unit sites must take into considerationsimultaneous venting from all the units, and ensure that venting on one unit does not negatively impact the ability to vent on the other units.
Response (ref. ISG Item 1.2.1):
The current HCVS wetwell path is designed for venting steam/energy at a nominal capacity of slightly less than 1% of 1912 MWt thermal power at pressure of 53 psig. During the design and licensing of the extended power uprate of the DAEC this capacity of slightly less than 1% was evaluated and found acceptable for the anticipated decay heat level that would be present at the time venting is required for the assumed loss of decay heat removal event per GL 89-16. This pressure is the Primary Containment Pressure Limit (PCPL) which is the lower of the containment design pressure and the PCPL value.
The design assumes that the pressure suppression capacity of the suppression pool is sufficient to absorb the decay heat generated during initial plant response. The vent would then be able to prevent containment pressure from increasing above the containment design pressure. As part of the final detailed design, the duration of suppression pool decay heat absorption will be confirmed.
Order EA-050 1.2.2 Requirement:
The HCVS shall be accessible to plant operatorsand be capable of remote operation and control, or manual operation, during sustainedoperations.
Page 10 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System ISG 1.2.2 Criteria:
The preferred location for remote operation and control of the HCVS is from the main control room. However, altemate locations to the control room are also acceptable, provided the licensees take into consideration the following:
- 1. Sustained operations mean the ability to open/close the valves multiple times during the event. Licensees shall determine the number of open/close cycles necessaryduring the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of operation and provide supporting basis consistent with the plant-specificcontainment venting strategy.
- 2. An assessment of temperature and radiologicalconditions that operatingpersonnel may encounter both in transit and locally at the controls. Licensee may use altematives such as providing features to facilitate manual operation of valves from remote locations or relocating/reorientingthe valves.
- 3. All permanently installed HCVS equipment, including any connections required to supplement the HCVS operation during a prolonged SBO (electricpower, N2/air)shall be located above the maximum design basis extemal flood level or protected from the design basis extemal flood.
- 4. During a prolonged SBO, manual operation/actionmay become necessary to operate the HCVS. As demonstratedduring the Fukushima event, the valves lost motive force including electric power and pneumatic airsupply to the valve operators,and control power to solenoid valves. If direct access and local operation of the valves is not feasible due to temperature or radiologicalhazards, licensees should include design features to facilitate remote manual operation of the HCVS valves by means such as reach rods, chain links, hand wheels, and portable equipment to provide motive force (e.g., air/N2 bottles, diesel powered compressors,and dc batteries). The connections between the valves and portable equipment should be designed for quick deployment. If a portable motive force (e.g., airor N2 bottles, dc power supplies)is used in the design strategy, licensees shall provide reasonableprotection of that equipment consistent with the staffs guidance delineatedin JLD-ISG-2012-01 for OrderEA-12-049.
- 5. The design shall preclude the need for operatorsto move temporary laddersor operate from atop scaffolding to access the HCVS valves or remote operatinglocations.
Response (ref. ISG Item 1.2.2):
The HCVS design will allow initiating and then operating and monitoring the HCVS from the MCR or other accessible location. Alternate capability for operation from the essential switch gear room or other accessible location will be provided. These locations are protected from adverse natural phenomena.
- 1. The HCVS flow path valves are air-operated valves with air-to-open and spring-to-shut.
Opening the valves requires energizing a DC powered solenoid operated valve (SOV) and providing motive air/gas. The detailed design will ensure a permanently installed DC power source and motive air/gas supply. The response to NRC EA-12-049 will demonstrate the capability under the FLEX effort to maintain the DC source throughout the period. The initial stored motive gas will allow for a minimum of three valve operating cycles; however, the final detailed design will determine the number of required valve cycles for the first 24-hours. If required, the stored motive gas will be upgraded to be consistent with the required number of valve cycles.
- 2. All primary controls can be operated from the MCR or other accessible location therefore temperature and radiological conditions that operating personnel may encounter at the controls are acceptable. No transit through inaccessible areas to local controls will be required.
- 3. All permanently installed HCVS equipment, including any connections required to supplement the HCVS operation during a prolonged SBO (electric power, Nitrogen/air) will be located in areas reasonably protected from defined hazards from NEI 12-06.
- 4. All valves required to open the flow path will be designed for remote manual operation following a prolonged SBO, i.e., no valve operation via hand wheel, reach-rod or similar Page 11 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System means that requires close proximity to the valve. Alternate means for operation of the HCVS valves will be provided in the essential switchgear room, or other accessible location, which will also be accessible for operations personnel. Any supplemental connections will be pre-engineered to minimize man-power resources and any needed portable gas supply will be reasonably protected from defined hazards as noted in NEI 12-06.
- 5. Access to the locations described above will not require temporary ladders or scaffolding.
Order EA-050 1.2.3 Requirement:
The HCVS shall include a means to prevent inadvertentactuation.
ISG 1.2.3 Criteria:
The design of the HCVS shallincorporate features, such as control panel key-locked switches, locking systems, rupture discs, or administrativecontrols to prevent the inadvertentuse of the vent valves. The system shall be designed to preclude inadvertentactuation of the HCVS due to any single active failure. The design should considergeneral guidelines such as single point vulnerability and spurious operationsof any plant installed equipment associated with HCVS.
The objective of the HCVS is to provide sufficient venting of containment and prevent long-term overpressurefailure of containment following the loss of active containmentheat removal capability or prolonged SBO. However, inadvertentactuation of HCVS due to a design error,equipment malfunction, or Qperator errorduring a design basis loss-of-coolant accident (DBLOCA) could have an undesirable effect on the containment accidentpressure (CAP) to provide adequate net positive suction head to the emergency core cooling system (ECCS) pumps. Therefore, prevention of inadvertentactuation, while importantfor all plants, is essential for plants relying on CAP. The licensee submittals on HCVS shall specifically include details on how this issue will be addressedon their individualplants for all situationswhen CAP credit is required.
Response (ref. ISG Item 1.2.3):
The features that prevent inadvertent actuation are two normally closed CIV's in series with keylock switches controlled administratively. The currently installed rupture disc may be retained but the final design may elect to either remove this disk or modify it to a different pressure setting.
EOP/ERG operating procedures provide clear guidance that the HCVS is not to be used to defeat containment integrity during any design basis transients and accident. In addition, the HCVS will be designed to provide features to prevent inadvertent actuation due to a design error, equipment malfunction, or operator error such that any credited containment accident pressure (CAP) that would provide net positive suction head (NPSH) to the emergency core cooling system (ECCS) pumps will be available (inclusive of a design basis loss-of-coolant accident (DBLOCA)). UFSAR Section 5.4.7 discusses credit for containment over pressure to assist in maintaining NPSH and applicable values are displayed in Figure 5.4-15.
Order EA-050 1.2.4 Requirement:
The HCVS shall include a means to monitor the status of the vent system (e.g., valve position indication) from the control room or other location(s). The monitoring system shall be designed for sustainedoperation during a prolonged SBO.
ISG 1.2.4 Criteria:
Plant operatorsmust be able to readily monitor the status of the HCVS at all times, including being able to understandwhether or not containmentpressure/energyis being vented through the HCVS, and whether or not containmentintegrity has been restoredfollowing venting operations. Licensees shallprovide a means to allow plant operatorsto readily determine, or have knowledge of, the following system parameters:
Page 12 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System (1) HCVS vent valves' position (open or closed),
(2) system pressure,and (3) effluent temperature.
Other importantinformation includes the status of supportingsystems, such as availabilityof electricalpower and pneumatic supply pressure. Monitoring by means of permanently installedgauges that are at, or nearby, the HCVS control panel is acceptable. The staff will consideralternativeapproachesfor system status instrumentation;however, licensees must provide sufficient information andjustificationfor alternative approaches.
The means to monitor system status shall support sustainedoperations during a prolonged SBO, and be designed to operate under potentially harsh environmental conditions that would be expected following a loss of containment heat removal capability and SBO. Power supplies to all instruments, controls, and indicationsshall be from the same power sources supporting the HCVS operation. "Sustainedoperations" may include the use of portable equipment to provide an alternatesource of power to components used to monitor HCVS status. Licensees shall demonstrate instrument reliability via an appropriatecombination of design, analyses, operatingexperience, and/ortesting of channel components for the following sets of parameters:
" radiologicalconditions that the instruments may encounter under normal plant conditions, and during and after a prolongedSBO event.
" temperaturesand pressure conditions as describedunder requirement 1.2.8, including dynamic loadingfrom system operation.
" humidity based on instrument location and effluent conditions in the HCVS.
Response (ref. ISG Item 1.2.4):
The design of the HCVS will have temperature and pressure monitoring downstream of the last isolation valve / rupture disc. All flow path valves will have open and closed position indication.
These HCVS indications will be at or near the same location as the valve control switches (CV4300 and CV4357), which are in the MCR. Power for the instrumentation will be from the same source used for the SOVs used to position the AOVs. Refer to the response to 1.2.2 for discussion on the power.
The approximate range for the temperature indication will be 50°F to 600 0F. The approximate range for the pressure indication will be 0 psig to 120 psig. The upper limits are approximately twice the required containment design temperature and pressure. The ranges will be finalized when the detailed design and equipment specifications are prepared.
The detailed design will address the radiological, temperature, pressure, flow induced vibration (if applicable) and internal piping dynamic forces, humidity/condensation and seismic qualification requirements. Assumed radiological conditions will be those expected after a prolonged SBO (without significant fuel failure), and will bound normal plant conditions.
Order EA-050 1.2.5 Requirement:
The HCVS shall include a means to monitor the effluent discharge for radioactivitythat may be released from operation of the HCVS. The monitoring system shall provide indication in the control room or other location(s), and shall be designed for sustainedoperation during a prolonged SBO.
ISG 1.2.5 Criteria:
Licensees shall provide an independentmeans to monitoroverall radioactivitythat may be released from the HCVS discharge. The radiationmonitor does not need to meet the requirements of NUREG 0737 for monitored releases, nor does it need to be able to monitor releases quantitatively to ensure compliance with Title 10 of the Code of FederalRegulations (10 CFR) Part 100 or 10 CFR Section 50.67. A wide-range monitoring system to monitor the overall activity in the release providing indicationthat effluent from the Page 13 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System containmentenvironment that is passing by the monitoris acceptable. The use of other existing radiation monitoring capabilityin lieu of an independent HCVS radiationmonitor is not acceptable because plant operatorsneed accurateinformation aboutreleases coming from the containmentvia the HCVS in order to make informed decisions on operation of the reliablehardened venting system.
The monitoringsystem shall provide indicationin the control room or a remote location (i.e., HCVS control panel)for the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of an extended SBO with electric power provided by permanent DC battery sources, and supplemented by portablepower sources for sustained operations.Monitoringradiation levels is requiredonly during the events that necessitate operation of the HCVS. The reliabilityof the effluent monitoring system under the applicable environmentalconditions shall be demonstrated by methods described under Requirement 1.2.4.
Response (ref. ISG Item 1.2.5):
The HCVS radiation monitoring system (RMS) will be dedicated to the HCVS. The approximate range of the (RMS) will be 0.1 mRem/hr to 1000 mRem/hr. This range is considered adequate to determine core integrity per the NRC Responses to Public Comments on the draft ISG (ML12229A477).
The detector will be physically mounted on the outside of the piping, accounting for the pipe wall thickness shielding in order to provide a measurement of the radiation level on the inside of the HCVS piping. The radiation level will be indicated at the MCR or other accessible location. The RMS will be powered from the same source as other electrically powered HCVS components.
Refer to the response to 1.2.2 for discussion on sustainability of the power.
Order EA-050 1.2.6 Requirement:
The HCVS shall include design features to minimize unintended cross flow of vented fluids within a unit and between units on the site.
ISG 1.2.6 Criteria:
At Fukushima, an explosion occurredin Unit 4, which was in a maintenance outage at the time of the event.
Although the facts have not been fully established, a likely cause of the explosion in Unit 4 is that hydrogen leaked from Unit 3 to Unit 4 through a common venting system. System cross-connectionspresent a potentialfor steam, hydrogen, and airborne radioactivityleakage to other areas of the plant and to adjacent units at multi-unit sites if the units are equipped with common vent piping. In this context, a design that is free of physical and control interfaces with other systems eliminates the potential for any cross-flow and is one way to satisfy this requirement. Regardless,system design shall provide design features to prevent the cross flow of vented fluids and migration to other areas within the plant or to adjacent units at multi-unit sites.
The current design of the hardened vent at several plants in the U.S. includes cross connections with the standby gas treatment system, which contains sheet metal ducts and filter and fan housings that are not as leak tight as hard pipes. In addition, dual unit plant sites are often equipped with a common plant stack.
Examples of acceptable means for prevention of cross flow is by valves, leak-tight dampers, and check valves, which shall be designed to automaticallyclose upon the initiation of the HCVS and shall remain closed for as long as the HCVS is in operation.Licensee's shall evaluate the environmental conditions (e.g.
pressure, temperature)at the damperlocations during venting operationsto ensure that the dampers will remain functional and sufficiently leak-tight, and if necessary, replace the dampers with other suitable equipment such as valves. If power is requiredfor the interfacing valves to move to isolation position, it shall be from the same power sources as the vent valves. Leak tightness of any such barrersshall be periodically verified by testing as described under Requirement 1.2.7.
Response (ref. ISG Item 1.2.6):
DAEC is a single unit site.
The HCVS shares part of its flow path with the Standby Gas Treatment System (SGTS). Prior to initiating the HCVS, the valve to the SGTS must be isolated. However, since SGTS isolation valves are AOV(s) that fail closed and receive containment isolation signals that will automatically isolate the valve(s) upon an abnormal containment pressure or loss of power, no Page 14 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System operator action is required. The detailed design phase will review the valve(s) to determine if the inter-system valves can meet the required leakage criteria under the limiting HCVS design conditions. If required, the valve(s) will be replaced or upgraded. The current hardened vent flow path downstream of the rupture disc includes valves that must isolate the flow stream from interfacing equipment. These valves would not close automatically with a loss of AC power and currently need to be closed by local manual operator action. To improve reliability, these interfacing valves will be upgrade to ensure they can be remotely closed from the MCR or other accessible location and meet required leakage testing criteria.
Order EA-050 1.2.7 Requirement:
The HCVS shall include features and provision for the operation, testing, inspection and maintenance adequate to ensure that reliablefunction and capabilityare maintained.
ISG 1.2.7 Criteria:
The HCVS piping run shall be designed to eliminate the potential for condensation accumulation, as subsequent water hammer could complicate system operation during intermittent venting or to withstand the potential for water hammer without compromising the functionality of the system. Licensees shallprovide a means (e.g., drain valves, pressure and temperaturegauge connections) to periodicallytest system components, including exercising (opening and closing) the vent valve(s). In situations where total elimination of condensationis not feasible, HCVS shall be designed to accommodate condensation, including applicable water hammerloads.
The HCVS outboardof the containmentboundary shall be tested to ensure that vent flow is releasedto the outside with minimal leakage, if any, through the interfacingboundarieswith other systems or units.
Licensees have the option of individually leak testing interfacingvalves or testing the overall leakage of the HCVS volume by conventional leak rate testing methods. The test volume shall envelope the HCVS between the outerprimary containment isolation barrierand the vent exiting the plant buildings, including the volume up to the interfacing valves. The test pressure shall be based on the HCVS design pressure.
Permissibleleakage rates for the interfacingvalves shall be within the requirements of American Society of MechanicalEngineers Operationand Maintenanceof Nuclear Power Plants Code (ASME OM) - 2009, Subsection ISTC - 3630 (e) (2), orlateredition of the ASME OM Code. When testing the HCVS volume, allowed leakage shall not exceed the sum of the interfacingvalve leakages as determined from the ASME OM Code. The NRC staff will considera higher leakage acceptance values if licensees provide acceptable justification. When reviewing such requests, the NRC staff will consider the impact of the leakage on the habitabilityof the rooms and areas within the building and operability of equipment in these areasduring the event response and subsequent recovery periods. Licensees shall implement the following operation, testing and inspection requirementsfor the HCVS to ensure reliableoperation of the system.
Testing and Inspection Requirements Description Frequency Cycle the HCVS valves and the interfacingsystem Once per year valves not used to maintain containment integrity during operations.
Perform visual inspectionsand a walkdown of Once per operating cycle HCVS components Test and calibrate the HCVS radiationmonitors. Once per operatingcycle Leak test the HCVS. (1) Priorto first declaringthe system functional; (2) Once every five years thereafter and (3) After restorationof any breach of system boundary within the buildings Page 15 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Validate the HCVS operatingprocedures by Once per every other operating cycle conducting an open/close test of the HCVS control logic from its controlpanel and ensuring that all interfacing system valves move to their proper(intended)positions.
Response (ref. ISG Item 1.2.7):
The detailed design for the HCVS will address condensation accumulation resulting from intermittent venting. In situations where total elimination of condensation is not feasible, the HCVS will be designed to accommodate condensation, including allowance for applicable water hammer loads.
The HCVS Containment Isolation Valves will be tested in accordance with the licensing and design basis for the plant. The HCVS past the outboard Containment Isolation Valve will be tested in conformance to the ISG methods. The test pressure shall be based on the HCVS design pressure. Permissible leakage rates for the interfacing valves will be within the requirements of American Society of Mechanical Engineers Operation and Maintenance of Nuclear Power Plants Code (ASME OM) - 2009, Subsection ISTC - 3630, or later edition of the ASME OM Code. When testing the HCVS volume, the allowed leakage will not exceed the sum of the interfacing valve leakages as determined from the ASME OM Code unless a higher leakage acceptance value is justified to the NRC.
The test types and frequencies will conform to the ISG 1.2.7 Table "Testing and inspection Requirements" with the clarification that "Leak test the HCVS" applies to the HCVS boundary valves. Rupture disks (if retained in the final design) will be replaced at manufacturer's recommendations not to exceed 10 years. Interfacing system valves that cannot be cycled on line without challenging plant operation will be on an operating cycle frequency rather than once per year.
Order EA-050 1.2.8 Requirement:
The HCVS shall be designed for pressures that are consistent with maximum containmentdesign pressures, as well as, dynamic loading resulting from system actuation.
ISG 1.2.8 Criteria:
The vent system shall be designed for the higher of the primary containmentdesign pressure or PCPL, and a saturationtemperaturecorrespondingto the HCVS design pressure.However, if the venting locationis from the drywell, an additionalmargin of 50 TF shall be added to the design temperaturebecause of the potential for superheatedconditions in the drywell. The piping, valves, and the valve actuators shall be designed to withstand the dynamic loadingresulting from the actuation of the system, including piping reactionloads from valve opening, concurrenthydrodynamic loads from SRV dischargesto the suppression pool, and potential for water hammer from accumulation of steam condensation during multiple venting cycles.
Response (ref. ISG Item 1.2.8):
The HCVS design pressure will be 56 psig and design temperature is 281°F. The HCVS design pressure is the higher of the containment design pressure and the PCPL value. The HCVS design temperature is the saturation temperature corresponding to the design pressure.
The piping, valves, and valve actuators will be designed to withstand the dynamic loading resulting from the actuation of the HCVS, including piping reaction loads from valve opening, concurrent hydrodynamic loads from SRV discharges to the suppression pool, and potential for water hammer from accumulation of condensation during multiple venting cycles.
Page 16 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Order EA-050 1.2.9 Requirement:
The HCVS shall discharge the effluent to a release point above main plant structures.
ISG 1.2.9 Criteria:
The HCVS release to outside atmosphere shall be at an elevation higher than adjacentplant structures.
Release through existing plant stacks is considered acceptable,provided the guidance under Requirement 1.2.6 is satisfied. If the release from HCVS is through a stack different than the plant stack, the elevation of the stack should be higher than the nearestbuilding or structure. The releasepoint should be situated away from ventilation system intake and exhaust openings, and emergency response facilities. The release stack or structure exposed to outside shall be designed or protected to withstand missiles that could be generated by the externalevents causing the prolonged SBO (e.g., tornadoes, high winds).
Response (ref. ISG Item 1.2.9):
The HCVS discharge path will use the existing path through the plant off gas stack whose release point is elevated above other plant structures. As noted above upgrades to interfacing valves in the flow path are needed to ensure requirements in 1.2.6 above are satisfied.
The detailed design will address missile protection from external events as defined by the existing plant design requirements for the off gas stack.
Page 17 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 4: Applicable Quality Requirements Order EA-050 2.1 Requirement:
The HCVS system design shall not preclude the containment isolation valves, including the vent valve from performing their intended containment isolation function consistent with the design basis for the plant. These items include piping, piping supports, containmentisolation valves, containmentisolation valve actuators and containment isolation valve position indication components.
ISG 2.1 Criteria:
The HCVS vent path up to and including the second containment isolationbarriershall be designed consistent with the design basis of the plant. These items include piping, piping supports, containment isolation valves, containmentisolation valve actuators and containment isolation valve position indication components. The HCVS design, out to and including the second containmentisolation barrier,shall meet safety-related requirements consistent with the design basis of the plant. The staff notes that in response to GL 89-16, in many cases, the HCVS vent line connections were made to existing systems. In some cases, the connection was made in between two existing containmentisolation valves and in others to the vacuum breakerline. The HCVS system design shall not preclude the containment isolation valves, including the vent valve from performing their intended containmentisolation function consistent with the design basis for the plant. The design shall include all necessary overrides of containmentisolation signalsand other interface system signalsto enable the vent valves to open upon initiation of the HCVS from its control panel Response (ref. ISG Item 2.1):
The HCVS vent path up to and including the second containment isolation barrier piping and supports will be designed in accordance with existing design basis. The HCVS system design will not preclude the containment isolation valves, including the vent valve from performing their intended containment isolation function consistent with the design basis for the plant. The control circuit will allow manual overrides of containment isolation signals or if applicable interface system signal to enable the vent valves to open upon initiation of the HCVS from the MCR or other accessible location.
Order EA-050 2.2 Requirement:
All other HCVS components shall be designed for reliable and rugged performance that is capable of ensuring HCVS functionality following a seismic event. These items include electricalpower supply, valve actuatorpneumatic supply, and instrumentation (localand remote) components.
ISG 2.2 Criteria:
All components of the HCVS beyond the second containmentisolation barriershall be designed to ensure HCVS functionality following the plant's design basis seismic event. These components include, in addition to the hardened vent pipe, electric power supply, pneumatic supply and instrumentation. The design of power and pneumatic supply lines between the HCVS valves and remote locations (if portable sources were to be employed) shall also be designed to ensure HCVS functionality. Licensees shall ensure that the HCVS will not impact other safety-related structures and components and that the HCVS will not be impacted by non-seismic components. The staff prefers that the HCVS components, including the piping run, be located in seismically qualifiedstructures. However, short runs of HCVS piping in non-seismic structures are acceptable if the licensee provides adequatejustification on the seismic ruggednessof these structures. The hardened vent shall be designed to conform to the requirementsconsistent with the applicable design codes for the plant,such as the American Society of Mechanical EngineersBoiler and Pressure Vessel Code and the applicable Specifications, Codes and Standardsof the American Institute of Steel Construction.
To ensure the functionality of instruments following a seismic event, the NRC staff considers any of the following as acceptablemethods:
- Use of instruments and supporting components with known operating principles that are supplied by manufacturers with commercial quality assurance programs, such as IS09001. The procurement specifications shall include the seismic requirements and/or instrument design requirements, and Page 18 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System specify the need for commercial design standards and testing under seismic loadings consistent with design basis values at the instrument locations.
- Demonstrationof the seismic reliabilityof the instrumentation through methods that predict performance by analysis, qualification testing under simulated seismic conditions, a combination of testing and analysis, or the use of experience data. Guidance for these is based on sections 7, 8, 9, and 10 of IEEE Standard 344-2004, "IEEE
" Recommended Practice for Seismic Qualification of Class 1E Equipment for Nuclear Power Generating Stations," or a substantiallysimilarindustrialstandardcould be used.
" Demonstration that the instrumentation is substantially similar in design to instrumentation that has been previously tested to seismic loading levels in accordance with the plant design basis at the location where the instrument is to be installed (g-levels and frequency ranges). Such testing and analysisshould be similarto that performed for the plant licensingbasis.
Response (ref. ISG Item 2.2):
The HCVS components downstream of the second containment isolation valve and components that interface with the HCVS will be routed in seismically qualified structures or reviewed for seismic ruggedness to ensure that any potential failure would not adversely impact the function of the HCVS or other safety related structures or components (i.e. seismic category II over category I criteria).
The HCVS downstream of the second containment isolation valve, including piping and supports, electrical power supply, valve actuator pneumatic supply, and instrumentation (local and remote) components, will be designed/analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake.
The HCVS instruments, including valve position indication, process instrumentation, radiation monitoring, and support system monitoring, will be qualified by using one of the three methods described in the ISG, which includes:
- 1. Purchase of instruments and supporting components with known operating principles from manufacturers with commercial quality assurance programs (e.g., IS09001) where the procurement specifications include the applicable seismic requirements, design requirements, and applicable testing.
- 2. Demonstration of seismic reliability via methods that predict performance described in IEEE 344-2004
- 3. Demonstration that instrumentation is substantially similar to the design of instrumentation previously qualified.
Instrument Qualification Method*
HCVS Process Temperature IS09001 / IEEE 344-2004 / Demonstration HCVS Process Pressure ISO9001 / IEEE 344-2004 / Demonstration HCVS Process Radiation Monitor IS09001 / IEEE 344-2004 1 Demonstration HCVS Process Valve Position IS09001 / IEEE 344-2004 / Demonstration HCVS Pneumatic Supply Pressure IS09001 / IEEE 344-2004 / Demonstration HCVS Electrical Power Supply Availability IS09001 / IEEE 344-2004 / Demonstration Page 19 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 5: Procedures and Training Order EA-050 3.1 Requirement:
Licensees shall develop, implement, and maintainprocedures necessary for the safe operation of the HCVS. Proceduresshall be established for system operationswhen normal and backup power is available, and during SBO conditions.
ISG 3.1 Criteria:
Proceduresshall be developed describingwhen and how to place the HCVS in operation,the location of system components, instrumentation available, normal and backup power supplies, directions for sustained operation,including the storage location of portable equipment, training on operating the portable equipment, and testing of equipment. The proceduresshall identify appropriateconditions and criteria for use of the HCVS. The procedures shall clearly state the nexus between CAP and ECCS pumps during a DBLOCA and how an inadvertentopening of the vent valve could have an adverse impact on this nexus.
The HCVS proceduresshall be developed and implemented in the same manner as otherplant procedures necessary to support the execution of the Emergency OperatingProcedures(EOPs).
Licensees shall establishprovisions for out-of-service requirements of the HCVS and compensatory measures. These provisions shall be documented in the Technical Requirements Manual (TRM) or similar document. The allowed unavailabilitytime for the HCVS shall not exceed 30 days during modes 1, 2, and 3.
If the unavailabilitytime exceeds 30 days, the TRM shall direct licensees to perform a cause assessment and take the necessary actions to restore HCVS availabilityin a timely manner, consistent with plant procedures and prevent future unavailabilityfor similarcauses.
Response (ref. ISG Item 3.1):
Procedures will be established for system operations when normal and backup power is available, and during prolonged SBO conditions.
The HCVS procedures will be developed and implemented following the plants process for initiating or revising procedures and contain the following details:
- appropriate conditions and criteria for use of the HCVS
- when and how to place the HCVS in operation,
- the location of system components,
- instrumentation available,
- normal and backup power supplies,
- directions for sustained operation(reference NEI 12-06), including the storage location of portable equipment,
- training on operating the portable equipment, and
- testing of portable equipment.
The procedures will ensure adequate containment over-pressure is maintained for ECCS pump net positive suction head during a DBA LOCA.
The following provisions for out-of-service restrictions for the HCVS and associated compensatory measures will be documented in the Technical Requirements Manual (TRM):
The allowed out of service time for the HCVS shall not exceed 30 days during Modes 1, 2, and 3.
- If the out of service time exceeds 30 days:
o The condition will be entered into the corrective action system, o Action will be initiated to restore functionality of the HCVS o A cause assessment will be performed to prevent future unavailability for similar causes.
Page 20 of 25
Duane Arnold Enerqy Center Overall Integrated Plan for the Reliable Hardened Vent System Order EA-050 3.2 Requirement:
Licensee shall train appropriatepersonnelin the use of the HCVS. The trainingcurricula shall include system operations when normal and backup power is available, and during SBO conditions.
ISG 3.2 Criteria:
All personnelexpected to operate the HCVS shall receive trainingin the use of plantprocedures developed for system operationswhen normal and backup power is available, and during SBO conditions consistent with the plants systematic approachto training. The trainingshall be refreshed on a periodic basis and as any changes occur to the HCVS.
Response (ref. ISG Item 3.2):
Personnel expected to operate the HCVS will receive necessary training in the use of plant procedures for system operations when normal and backup power is available and during prolonged SBO conditions. The training will be performed on a periodic basis and as any changes occur to the HCVS. The training will utilize the systematic approach to training.
Page 21 of 25
Duane Arnold Enerqv Center Overall Intearated Plan for the Reliable Hardened Vent System Section 6: Implementation Schedule Milestones The following milestone schedule is provided. The dates are planning dates subject to change as design and implementation details are developed. Any changes to the following target dates will be reflected in the subsequent 6 month status reports.
Original Target Activity Status Date Oct. 2012 Submit 60 Day Status Report Complete Feb. 2013 Submit Overall Integrated Implementation Plan Complete Aug 2013 Submit 6 Month Status Report Feb. 2014 Submit 6 Month Status Report Aug. 2014 Submit 6 Month Status Report Feb. 2015 Submit 6 Month Status Report Aug. 2015 Submit 6 Month Status Report Dec. 2015 Completed Design Change Package issued for construction Feb. 2016 Submit 6 Month Status Report June 2016 Procedure Changes Training Material Complete July 2016 Design Change Major Material On-site Aug. 2016 Submit 6 Month Status Report RFO 25 Fall 2016 Design Change Construction Completed RFO 25 Fall 2016 Procedure Changes Active RFO 25 Fall 2016 Demonstration/Functional Test Dec. 2016 Submit Completion Report Page 22 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 7: Changes/Updates to this Overall Integrated Implementation Plan Any significant changes to this plan will be communicated to the NRC staff in the 6 Month Status Reports.
Page 23 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent System Section 8: Figures/Diagrams ISG IV.C. 1. Reporting Requirements:
A piping and instrumentationdiagram or a similar diagram that shows system components and interfaces with plant systems and structures is acceptable.
Response (ref. ISG Item 3.2):
In addition, per Staff request, a Table has been included to discuss various potential failure modes in the proposed design.
V05-0197 V05-0134 GE V04-0B84 Page 24 of 25
Duane Arnold Energy Center Overall Integrated Plan for the Reliable Hardened Vent Svstem Potential Failure Evaluation Table (Proposed Design)
Functional Failure Failure Cause Alternate Action Alternate Action Mode Corrects Failure One or Both Loss of Normal AC power to DC power solenoid supplying Yes Containment Isolation solenoid valve supplying nitrogen gas Valve Fails to Open on nitrogen gas, Demand Loss of AC and DC power Recharge DC batteries with FLEX Yes diesel generator or portable pneumatic supply via manual connection (future installation)
Loss of safety related Portable pneumatic supply via Yes Alternate Nitrogen manual connection (future installation)
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation)
Mechanical valve problem None No One Containment Any failure Close alternate valve Yes Isolation Valve Fails to Close on Demand Both Containment Both solenoid valves fail to De-pressurize Alternate Nitrogen Yes Isolation valves Fail to close for any reason supply to solenoid Close Open and Rupture Disc Mechanical problems in both None valves No Spurious Containment Not credible as key locked NA NA Isolation Valve Opening switches prevent miss-positioning and two valves are normally closed Automatic Containment High containment pressure Over ride containment isolation Yes Isolation Closure from signal or portable pneumatic other signals supply via manual connection (future installation)
Failure to be able to Loss of safety related Portable pneumatic supply via Yes open rupture disc if Alternate Nitrogen manual connection (future rupture disk is retained installation)
Solenoid valve fails to open Portable pneumatic supply via Yes manual connection (future installation)
Rupture disk does not open None. No as designed at available pressure Page 25 of 25