{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Kelvin Henderson Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 29745 Mr. Steven D. Capps Vice President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078-8985 June 27, 2013 SUBJECT CATAWBA NUCLEAR STATION, UNITS 1 AND 2-MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, PROJECT MANAGER ASSIGNMENTS Dear Mr. Henderson and Mr. Capps: This letter is to inform you that effective July 1, 2013, Mr. Jason Paige is assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Catawba Nuclear Station, Units 1 and 2, and McGuire Nuclear Station, Units 1 and 2. Mr. Paige may be reached at 301-415-5888 or by e-mail to Jason.Paige@nrc.gov.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 27, 2013 Mr. Kelvin Henderson Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 29745 Mr. Steven D. Capps Vice President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078-8985 SUBJECT         CATAWBA NUCLEAR STATION, UNITS 1 AND 2- MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, PROJECT MANAGER ASSIGNMENTS
Docket Nos.: 50-413 and 50-414 50-369 and 50-370 cc: Distribution via Listserv Sincerely, Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation June 27, 2013 Mr. Kelvin Henderson Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 29745 Mr. Steven D. Capps ViceAII time units had been approved for DORL Thank you! President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078-8985


==SUBJECT:==
==Dear Mr. Henderson and Mr. Capps:==
CATAWBA NUCLEAR STATION, UNITS 1 AND 2-MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, PROJECT MANAGER ASSIGNMENTS Dear Mr. Henderson and Mr. Capps: This letter is to inform you that effective July 1, 2013, Mr. Jason Paige is assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Catawba Nuclear Station, Units 1 and 2, and McGuire Nuclear Station, Units 1 and 2. Mr. Paige may be reached at 301-415-5888 or by e-mail to Jason.Paige@nrc.gov.
 
Sincerely, IRA/ Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-413 and 50-414 50-369 and 50-370 cc: Distribution via Ustserv DISTRIBUTION:
This letter is to inform you that effective July 1, 2013, Mr. Jason Paige is assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Catawba Nuclear Station, Units 1 and 2, and McGuire Nuclear Station, Units 1 and 2.
PUBLIC RidsAcrsAcnw
Mr. Paige may be reached at 301-415-5888 or by e-mail to Jason.Paige@nrc.gov.
_ MaiiCTR RidsNrrOd Resource RidsNrrPMMcGuire Resource LPL2-1 Reading RidsNrrDorllpl2-1 Resource RidsNrrLASFigueroa Resource J.Kim, NRRJDORL RidsRgn2MaiiCenter Resource RidsNrrDorl Resource RidsNrrPMCatawba Resource L.Cox, NRR/DORL ADAMS Accession No* ML13177A308  
Sincerely, Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-413 and 50-414 50-369 and 50-370 cc: Distribution via Listserv
.. OFFICE NRRILPL2-1/PM NRR/LPL2-1/PM NRR/LPL2-1/BC NAME JPaige SFigueroa JPascarem DATE 06/27/13 06/27/13 06/27/13 OFFICIAL RECORD COPY}}
 
*        .. ML13177A308 OFFICE     NRRILPL2-1/PM         NRR/LPL2-1/PM           NRR/LPL2-1/BC NAME       JPaige                 SFigueroa               JPascarem DATE       06/27/13               06/27/13               06/27/13}}

Revision as of 16:35, 4 November 2019

Units 1 and 2 - Project Manager Assignments
ML13177A308
Person / Time
Site: Mcguire, Catawba, McGuire  Duke Energy icon.png
Issue date: 06/27/2013
From: Robert Pascarelli
Plant Licensing Branch II
To: Capps S, Henderson K
Duke Energy Carolinas
Kim J NRR/DORL/LPL2-1
References
Download: ML13177A308 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 27, 2013 Mr. Kelvin Henderson Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 29745 Mr. Steven D. Capps Vice President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078-8985 SUBJECT CATAWBA NUCLEAR STATION, UNITS 1 AND 2- MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, PROJECT MANAGER ASSIGNMENTS

Dear Mr. Henderson and Mr. Capps:

This letter is to inform you that effective July 1, 2013, Mr. Jason Paige is assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Catawba Nuclear Station, Units 1 and 2, and McGuire Nuclear Station, Units 1 and 2.

Mr. Paige may be reached at 301-415-5888 or by e-mail to Jason.Paige@nrc.gov.

Sincerely, Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-413 and 50-414 50-369 and 50-370 cc: Distribution via Listserv

  • .. ML13177A308 OFFICE NRRILPL2-1/PM NRR/LPL2-1/PM NRR/LPL2-1/BC NAME JPaige SFigueroa JPascarem DATE 06/27/13 06/27/13 06/27/13