{{#Wiki_filter: | {{#Wiki_filter:DRAFT REQUEST FOR ADDITIONAL INFORMATION PROPOSED REVISION TO REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULES FIRSTENERGY NUCLEAR OPERATING COMPANY BEAVER VALLEY POWER STATION, UNITS 1 AND 2 DOCKET NOS. 50-334 AND 50-412 By letter dated May 28, 2013,1 First Energy Nuclear Operating Company (FENOC, the licensee) submitted a request to revise the reactor vessel (RV) surveillance capsule withdrawal schedules for the Beaver Valley Power Station, Units 1 and 2 (BVPS-1 and BVPS-2). In order to complete its review, the staff requires additional information. | ||
Appendix H to 10 CFR Part 50 states, Each capsule withdrawal and the test results must be the subject of a summary technical report to be submitted, as specified in § 50.4, within one year of the date of capsule withdrawal, unless an extension is granted by the Director, Office of Nuclear Reactor Regulation. Electric Power Research Institutes Materials Reliability Program: | |||
Appendix H to 10 CFR Part 50 states, | Coordinated PWR Reactor Vessel Surveillance Program (CRVSP) Guidelines (MRP-326) dated December 2011,2 states that BVPS-1 Capsule X is planned to be withdrawn at a fluence of 5.01 x 1019 n/cm2 in 2013. | ||
Coordinated PWR Reactor Vessel Surveillance Program (CRVSP) Guidelines (MRP-326) | |||
dated December 2011, 2 states that BVPS-1 Capsule X | |||
RAI #1: | RAI #1: | ||
Provide the withdrawal date for BVPS-1 Capsule X. | Provide the withdrawal date for BVPS-1 Capsule X. | ||
1 Agencywide Documents Access Management System (ADAMS) Accession No. ML13151A058 2 | |||
1 Agencywide Documents Access Management System (ADAMS) Accession No. ML13151A058 2 ADAMS Accession Nos. ML12040A314 and ML12040A315}} | ADAMS Accession Nos. ML12040A314 and ML12040A315 DRAFT}} | ||
Revision as of 10:43, 4 November 2019
| ML13338A535 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 12/04/2013 |
| From: | Jeffrey Whited Plant Licensing Branch 1 |
| To: | |
| Whited J | |
| References | |
| Download: ML13338A535 (1) | |
Text
DRAFT REQUEST FOR ADDITIONAL INFORMATION PROPOSED REVISION TO REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULES FIRSTENERGY NUCLEAR OPERATING COMPANY BEAVER VALLEY POWER STATION, UNITS 1 AND 2 DOCKET NOS. 50-334 AND 50-412 By letter dated May 28, 2013,1 First Energy Nuclear Operating Company (FENOC, the licensee) submitted a request to revise the reactor vessel (RV) surveillance capsule withdrawal schedules for the Beaver Valley Power Station, Units 1 and 2 (BVPS-1 and BVPS-2). In order to complete its review, the staff requires additional information.
Appendix H to 10 CFR Part 50 states, Each capsule withdrawal and the test results must be the subject of a summary technical report to be submitted, as specified in § 50.4, within one year of the date of capsule withdrawal, unless an extension is granted by the Director, Office of Nuclear Reactor Regulation. Electric Power Research Institutes Materials Reliability Program:
Coordinated PWR Reactor Vessel Surveillance Program (CRVSP) Guidelines (MRP-326) dated December 2011,2 states that BVPS-1 Capsule X is planned to be withdrawn at a fluence of 5.01 x 1019 n/cm2 in 2013.
RAI #1:
Provide the withdrawal date for BVPS-1 Capsule X.
1 Agencywide Documents Access Management System (ADAMS) Accession No. ML13151A058 2