ML14098A286: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 3: | Line 3: | ||
| issue date = 04/08/2014 | | issue date = 04/08/2014 | ||
| title = Notification of NRC Inspection and Request for Information | | title = Notification of NRC Inspection and Request for Information | ||
| author name = Lipa C | | author name = Lipa C | ||
| author affiliation = NRC/RGN-III/DRP/B1 | | author affiliation = NRC/RGN-III/DRP/B1 | ||
| addressee name = Pacilio M | | addressee name = Pacilio M | ||
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | | addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | ||
| docket = 05000461 | | docket = 05000461 | ||
Revision as of 14:11, 21 June 2019
| ML14098A286 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 04/08/2014 |
| From: | Christine Lipa NRC/RGN-III/DRP/B1 |
| To: | Pacilio M Exelon Generation Co, Exelon Nuclear |
| References | |
| Download: ML14098A286 (5) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 April 8, 2014
Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Co., LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CLINTON POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Pacilio:
On July 14, 2014, the U. S. Nuclear Regulatory Commission (NRC) will perform an in-depth review of a selected issue in accordance with the annual follow-up sample portion of the baseline Inspection Procedure 71152 "Problem Identification and Resolution." This on-site inspection is scheduled to be performed July 14 - 18, 2014. Experience has shown that this inspection is resource intens ive both for the NRC inspector and your staff. In order to minimize the impact to your on-site resources, and to ensure a productive inspection for both sides, we have enclosed a request for documents needed for this inspection upon arrival by the inspector at the site. It is important that all of these documents are up-to-date, and complete, in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. We have discussed the schedule for inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. Jim Peterson, of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Mr. Melvin Holmberg at 630-829-9748 or via e-mail at mel.holmberg@nrc.gov. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/ Christine A. Lipa, Chief
Branch 1 Division of Reactor Projects
Docket No. 50-461 License No. NPF-62
Enclosure:
IP 71152 Document Request w/Enclosure (Information Supporting the On-site During Inspection) cc w/encl: Distribution via ListServŽ
INSERVICE INSPECTION DOCUMENT REQUEST Enclosure Inspection Dates
- July 14 - 18, 2014
Inspection Procedures
- Inspection Procedure 71152, "Problem Identification and Resolution" Lead Inspector
- Melvin Holmberg, DRS 630-829-9748
On-site information needed on the first day of the inspection (e.g., following the entrance meeting). 1. Provide hard copies (if practicable) of the following documents: a. AR 01630641 "Power Increase Restrictions Resolved" with associated corrective actions planned or completed; b. Fabrication drawings of Steam Dryer (SD) (E-size);
- c. Inspection history for SD including nondestructive examination (NDE) reports (and pictures) for all flaw indication which have been identified; d. Cause evaluations performed for flaw indications identified in the SD;
- e. Construction and Design Standards applicable to the SD;
- f. Site program and basis documents applicable to inservice examination and maintenance of the SD (e.g. BWRVIP-139 and implementing site procedures); g. Engineering Change applicable to any SD repairs or acceptance of NDE indications in the SD; h. Engineering Change and/or calculations applicable to SD flaw growth analysis and evaluations; i. Engineering Change and associated calculations evaluating/accepting the SD for licensed full power operations (e.g. Extended Power Uprate); and j. Operating Experience (OE) Applicable to the SD. Specifically provide the vendor and industry issued OE (e.g.GE SILs) with applicable ARs and CAs completed in response to this OE. If you have questions regarding the information requested, please contact the lead inspector.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/ Christine A. Lipa, Chief
Branch 1 Division of Reactor Projects
Docket No. 50-461 License No. NPF-62
Enclosure:
IP 71152 Document Request w/Enclosure (Information Supporting the On-site During Inspection) cc w/encl: Distribution via ListServŽ DISTRIBUTION
- See next page
DOCUMENT NAME: Clinton PI&R Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in th e concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME MHolmberg:rj CLipa DATE 04/02/14 04/08/14 OFFICIAL RECORD COPY Letter to Michael Pacilio from Christine Lipa dated April 8, 2014
SUBJECT:
CLINTON POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION DISTRIBUTION
- Joseph Nick RidsNrrDorlLpl3-2 Resource
RidsNrrPMClinton Resource
RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Steven Orth
Carole Ariano Linda Linn DRSIII DRPIII Patricia Buckley