ML081080218: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 04/16/2008
| issue date = 04/16/2008
| title = Units 1 and 2, EOC Summary of 04/08/2008 Public Meeting
| title = Units 1 and 2, EOC Summary of 04/08/2008 Public Meeting
| author name = Skokowski R A
| author name = Skokowski R
| author affiliation = NRC/RGN-III/DRP/B3
| author affiliation = NRC/RGN-III/DRP/B3
| addressee name =  
| addressee name =  

Revision as of 12:30, 12 July 2019

Units 1 and 2, EOC Summary of 04/08/2008 Public Meeting
ML081080218
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/16/2008
From: Richard Skokowski
Region 3 Branch 3
To:
Nuclear Management Co
References
Download: ML081080218 (5)


Text

April 16, 2008

LICENSEE: Nuclear Management Company, LLC

FACILITY: Prairie Island, Units 1 and 2

SUBJECT:

SUMMARY

OF THE APRIL 7, 2008, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND UNITS 1 AND 2 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT

On April 7, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Prairie Island Training Center in Welch, MN. The meeting was between NRC Region III management and Nuclear Management Company management to discuss the NRC

=s assessment of Prairie Island Units 1 and 2

=s safety performance for the period from January 1 through December 31, 2007. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML080740383 and ML081000444, respectively. A list of principal NRC and licensee meeting participants can be found in the Attachment to this letter.

The NRC began the meeting with an overview of the NRC

=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of Prairie Island Units 1 and 2

=s performance in calendar year 2007, which was documented in the March 3, 2008, end-of-cycle assessment letter, as ML080600308. As part of this regulatory performance meeting, NMC briefly responded to the NRC

=s assessment. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and NMC representatives.

Sincerely, /RA/

Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects

Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60

Attachment:

As Stated

DISTRIBUTION:

See next page

LICENSEE: Nuclear Management Company, LLC

FACILITY: Prairie Island, Units 1 and 2

SUBJECT:

SUMMARY

OF THE APRIL 7, 2008, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND UNITS 1 AND 2 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT

On April 7, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Prairie Island Training Center in Welch, MN. The meeting was between NRC Region III management and Nuclear Management Company management to discuss the NRC

=s assessment of Prairie Island Units 1 and 2

=s safety performance for the period from January 1 through December 31, 2007. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML080740383 and ML081000444, respectively. A list of principal NRC and licensee meeting participants can be found in the Attachment to this letter.

The NRC began the meeting with an overview of the NRC

=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of Prairie Island Units 1 and 2

=s performance in calendar year 2007, which was documented in the March 3, 2008, end-of-cycle assessment letter, as ML080600308. As part of this regulatory performance meeting, NMC briefly responded to the NRC

=s assessment. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and NMC representatives.

Sincerely,

Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects

Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60

Attachment:

As Stated

DISTRIBUTION:

See next page

DOCUMENT NAME: G:\Branch TSS\All EOC\EOC CY 2007\EOC Meeting Notices Letters\Prairie Island EOC Mtg Summary Cy 2007.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME CZoia:dtp RSkokowski

DATE 04/16/2008 04/16/2008 OFFICIAL RECORD COPY

Letter to Nuclear Management Company from R. Skokowski dated April 16, 2008

SUBJECT:

SUMMARY

OF THE APRIL 7, 2008, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND UNITS 1 AND 2 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT

cc: D. Koehl, Chief Nuclear Officer P. Glass, Assistant General Counsel Nuclear Asset Manager J. Stine, Division Director, Minnesota Department of Health Tribal Council, Prairie Island Indian Community Administrator, Goodhue County Courthouse Commissioner, Minnesota Department of Commerce Manager, Environmental Protection Division Office of the Attorney General of Minnesota Council Administrator President, Prairie Island Tribal Council Goodhue County Sheriff Director, Pierce County Emergency Management Agency Chair, Pierce County Board of Commissioners Chair, Dakota County Board of Commissioners Mayor of Red Wing Director, Goodhue County Emergency Management Agency Chair, Goodhue County Board of Commissioners Pierce County Sheriff Dakota County Sheriff G. Mortensen, INPO

Letter to Nuclear Management Company from R. Skokowski dated April 16, 2008

SUBJECT:

SUMMARY

OF THE APRIL 7, 2008, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND UNITS 1 AND 2 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT

DISTRIBUTION

TEB MLC RidsNrrDirslpab

JLC1 MAS JKH3 KGO RML2 SRI Prairie Island DRPIII DRSIII PLB1 TXN

Meeting Participants

NRC R. Skokowski, Chief, Branch 3, Division of Reactor Projects K. Stoedter, Senior Resident Inspector, Prairie Island P. Zurawski, Resident Inspector, Prairie Island

Nuclear Management Company

M. Wadley, Site Vice President D. Koehl, Chief Nuclear Officer S. Northard, Plant Manager J. Sorensen, Site Director M. Davis, Regulatory Compliance Coordinator J. Kivi, Regulatory Compliance Engineer M. Schimmel, Engineering Director K. Huxford, Public Affairs Officer J. Muth, nuclear Oversight Services J. Anderson, Regulatory Affairs Manager R. Hite, Radiation Protection Manager J. Tobias, Senior Chemist Other members of licensee staff

Prairie Island Indian Community

B. Frazier, Tribe Emergency Preparedness Coordinator

Goodhue County

G. Fried, Emergency Preparedness Coordinator

Attachment