| title = IR 05000338-09-301, IR 05000339-09-301, on 02/10/2009, North Anna Power Station, Reactor and Senior Reactor Operator Initial Retake Examination | | title = IR 05000338-09-301, IR 05000339-09-301, on 02/10/2009, North Anna Power Station, Reactor and Senior Reactor Operator Initial Retake Examination | ||
| author name = Widmann M | | author name = Widmann M | ||
| author affiliation = NRC/RGN-II/DRS/OLB | | author affiliation = NRC/RGN-II/DRS/OLB | ||
| addressee name = Christian D | | addressee name = Christian D | ||
| addressee affiliation = Virginia Electric & Power Co (VEPCO) | | addressee affiliation = Virginia Electric & Power Co (VEPCO) | ||
| docket = 05000338, 05000339 | | docket = 05000338, 05000339 | ||
| Line 14: | Line 14: | ||
| page count = 8 | | page count = 8 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000338/2009301]] | ||
=Text= | =Text= | ||
{{#Wiki_filter:VEPCO 3 | {{#Wiki_filter:VEPCO | ||
October 17, 2008 | 3 | ||
October 17, 2008 | |||
| Line 27: | Line 33: | ||
5000 Dominion Boulevard | 5000 Dominion Boulevard | ||
Glen Allen, VA 23060-6711 | Glen Allen, VA 23060-6711 | ||
SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | SUBJECT: | ||
REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE | |||
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | |||
05000339/2009301 | 05000339/2009301 | ||
Dear Mr. Christian: | Dear Mr. Christian: | ||
In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear | In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear | ||
Training (Initial Operations), and Mr. Phillip | Training (Initial Operations), and Mr. Phillip G. Capehart, Operations Examiner, arrangements | ||
were made for the administration of a licensing retake written examination scheduled to be given | |||
on February 10, 2009, at the North Anna Power Station. | on February 10, 2009, at the North Anna Power Station. | ||
As agreed during the telephone conversation, your staff will prepare the written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing | As agreed during the telephone conversation, your staff will prepare the written examination | ||
based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing | |||
Examination Standards for Power Reactors." | Examination Standards for Power Reactors." | ||
To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your staff on August 13, 2008. The written examination and the supporting reference materials | To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your | ||
identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | staff on August 13, 2008. The written examination and the supporting reference materials | ||
representative of the facility licensee shall approve the examinations before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. Your | identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10, | ||
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | |||
representative of the facility licensee shall approve the examinations before they are submitted | |||
to the NRC for review and approval. All materials shall be complete and ready-to-use. Your | |||
staff has also agreed to make copies of all examination materials that are necessary for | staff has also agreed to make copies of all examination materials that are necessary for | ||
administering the examination. | administering the examination. | ||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in | We request that any personal, proprietary, sensitive unclassified, or safeguards information in | ||
| Line 56: | Line 63: | ||
receiving the required examination and reference materials, or the submittal of inadequate or | receiving the required examination and reference materials, or the submittal of inadequate or | ||
incomplete materials, may cause the examinations to be rescheduled. | incomplete materials, may cause the examinations to be rescheduled. | ||
In order to conduct the requested written examinations and | In order to conduct the requested written examinations and operating tests, it will be necessary | ||
operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and | for your staff to provide adequate space and accommodations in accordance with ES-402, and | ||
to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, | to make the simulation facility available on the dates noted above. In accordance with ES-302, | ||
your staff should retain the original simulator performance data (e.g., system pressures, | |||
temperatures, and levels) generated during the dynamic operating tests until the examination | temperatures, and levels) generated during the dynamic operating tests until the examination | ||
results are final. | results are final. | ||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | |||
effect while the written examinations is being administered. | |||
VEPCO | |||
2 | |||
To permit timely NRC review and evaluation, your staff should submit preliminary reactor | To permit timely NRC review and evaluation, your staff should submit preliminary reactor | ||
| Line 76: | Line 90: | ||
date, a postponement may be necessary. Signed applications certifying that all training has | date, a postponement may be necessary. Signed applications certifying that all training has | ||
been completed should be submitted at least 14 days before the first examination date. | been completed should be submitted at least 14 days before the first examination date. | ||
This letter contains information collections that are subject to the Paperwork Reduction Act of | This letter contains information collections that are subject to the Paperwork Reduction Act of | ||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for | 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under | ||
approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for | |||
this collection of information is estimated to average 500 hours per response, including the time | this collection of information is estimated to average 500 hours per response, including the time | ||
for reviewing instructions, gathering and maintaining the data needed, writing the examinations, | for reviewing instructions, gathering and maintaining the data needed, writing the examinations, | ||
| Line 88: | Line 102: | ||
and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150- | and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150- | ||
0018), Office of Management and Budget, Washington, DC 20503. | 0018), Office of Management and Budget, Washington, DC 20503. | ||
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of | The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of | ||
information unless it displays a currently valid OMB control number. | information unless it displays a currently valid OMB control number. | ||
In accordance with 10 CFR 2.390 of the | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be | ||
Publicly Available Records (PARS) component of the | available electronically for public inspection in the NRC Public Document Room or from the | ||
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room). | Publicly Available Records (PARS) component of the NRCs document system (ADAMS). | ||
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the | |||
Public Electronic Reading Room). | |||
Thank you for your cooperation in this matter. Mr. Walt Shura has been advised of the policies | Thank you for your cooperation in this matter. Mr. Walt Shura has been advised of the policies | ||
and guidelines referenced in this letter. If you have any questions regarding the NRC's | and guidelines referenced in this letter. If you have any questions regarding the NRC's | ||
examination | examination procedures and guidelines, please contact Mr. Phillip G. Capehart at (404) 562- | ||
4483, (Internet E-mail: Phillip.Capehart@nrc.gov), or me at (404) 562-4550, (Internet E-mail: | |||
G. Capehart at (404) 562- | Malcolm.Widmann@nrc.gov). | ||
4483, (Internet | |||
E-mail: Phillip.Capehart@nrc.gov), or me at (404) 562-4550, ( | Sincerely, | ||
/RA/ | |||
Malcolm T. Widmann, Chief | |||
Operator Licensing Branch | Operator Licensing Branch | ||
Division of Reactor Safety | Division of Reactor Safety | ||
| Line 114: | Line 134: | ||
Docket No.: 50-338, 50-339 | Docket No.: 50-338, 50-339 | ||
License No.: NPF-4, NPF-7 | License No.: NPF-4, NPF-7 | ||
(cc: w/encl - See Page 3) | (cc: w/encl - See Page 3) | ||
VEPCO | |||
3 | |||
cc w/encl: | |||
Daniel G. Stoddard | Daniel G. Stoddard | ||
Site Vice President | Site Vice President | ||
Virginia Electric and Power Company | Virginia Electric and Power Company | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Eric Hendrixson | Eric Hendrixson | ||
| Line 130: | Line 152: | ||
Virginia Electric and Power Company | Virginia Electric and Power Company | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Chris L. Funderburk | Chris L. Funderburk | ||
| Line 137: | Line 158: | ||
Virginia Electric and Power Company | Virginia Electric and Power Company | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Lillian M. Cuoco, Esq. | Lillian M. Cuoco, Esq. | ||
| Line 143: | Line 163: | ||
Dominion Resources Services, Inc. | Dominion Resources Services, Inc. | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Executive Vice President | Executive Vice President | ||
Old Dominion Electric Cooperative | Old Dominion Electric Cooperative | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Attorney General | Attorney General | ||
Supreme Court Building | Supreme Court Building | ||
900 East Main Street | 900 East Main Street | ||
Senior Resident Inspector | |||
Senior Resident Inspector | |||
North Anna Power Station | North Anna Power Station | ||
U.S. Nuclear Regulatory Commission | U.S. Nuclear Regulatory Commission | ||
P.O. Box 490 | P.O. Box 490 | ||
Mineral, VA 23117 | Mineral, VA 23117 | ||
County Administrator | County Administrator | ||
| Line 164: | Line 182: | ||
P.O. Box 160 | P.O. Box 160 | ||
Louisa, VA 23093 | Louisa, VA 23093 | ||
Michael M. Cline | Michael M. Cline | ||
| Line 171: | Line 188: | ||
Emergency Services Management | Emergency Services Management | ||
Electronic Mail Distribution | Electronic Mail Distribution | ||
Ginger L. Alligood | Ginger L. Alligood | ||
(NORTH ANNA EXAM | (NORTH ANNA EXAM | ||
REPORTS ONLY) | REPORTS ONLY) | ||
Virginia Electric and Power Company | Virginia Electric and Power Company | ||
| Line 184: | Line 199: | ||
P.O. Box 402 | P.O. Box 402 | ||
Mineral, VA 23117 | Mineral, VA 23117 | ||
Richmond, VA 23219 | |||
October 17, 2008 | |||
Mr. David A. Christian | Mr. David A. Christian | ||
Senior Vice President and Chief Nuclear Officer | Senior Vice President and Chief Nuclear Officer | ||
| Line 195: | Line 214: | ||
5000 Dominion Boulevard | 5000 Dominion Boulevard | ||
Glen Allen, VA 23060 | Glen Allen, VA 23060 | ||
SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | SUBJECT: | ||
REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE | |||
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | |||
05000339/2009301 | 05000339/2009301 | ||
Dear Mr. Christian: | Dear Mr. Christian: | ||
In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear | In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear | ||
Training (Initial Operations), and Mr. Phillip | Training (Initial Operations), and Mr. Phillip G. Capehart, Operations Examiner, arrangements | ||
were made for the administration of a licensing retake written examination scheduled to be given | |||
on February 10, 2009, at the North Anna Power Station. | on February 10, 2009, at the North Anna Power Station. | ||
As agreed during the telephone conversation, your staff will prepare the written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing | As agreed during the telephone conversation, your staff will prepare the written examination | ||
based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing | |||
Examination Standards for Power Reactors." | Examination Standards for Power Reactors." | ||
To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your staff on August 13, 2008. The written examination and the supporting reference materials | To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your | ||
identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | staff on August 13, 2008. The written examination and the supporting reference materials | ||
representative of the facility licensee shall approve the examinations before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. Your | identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10, | ||
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | |||
representative of the facility licensee shall approve the examinations before they are submitted | |||
to the NRC for review and approval. All materials shall be complete and ready-to-use. Your | |||
staff has also agreed to make copies of all examination materials that are necessary for | staff has also agreed to make copies of all examination materials that are necessary for | ||
administering the examination. | administering the examination. | ||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in | We request that any personal, proprietary, sensitive unclassified, or safeguards information in | ||
| Line 224: | Line 244: | ||
receiving the required examination and reference materials, or the submittal of inadequate or | receiving the required examination and reference materials, or the submittal of inadequate or | ||
incomplete materials, may cause the examinations to be rescheduled. | incomplete materials, may cause the examinations to be rescheduled. | ||
In order to conduct the requested written examinations and | In order to conduct the requested written examinations and operating tests, it will be necessary | ||
operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and | for your staff to provide adequate space and accommodations in accordance with ES-402, and | ||
to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, | to make the simulation facility available on the dates noted above. In accordance with ES-302, | ||
your staff should retain the original simulator performance data (e.g., system pressures, | |||
temperatures, and levels) generated during the dynamic operating tests until the examination | temperatures, and levels) generated during the dynamic operating tests until the examination | ||
results are final. | results are final. | ||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | |||
effect while the written examinations is being administered. | |||
_________________________ | |||
XG SUNSI REVIEW COMPLETE | |||
OFFICE | |||
RII:DRS | |||
RIII:DRS | |||
RIII:DRP | |||
SIGNATURE | |||
/RA/ | |||
/RA/ | |||
/RA/ | |||
NAME | |||
PCapehart | |||
MWidmann | |||
J. Dodson | |||
DATE | |||
10/16/2008 | |||
10/17/2008 | |||
10/17/2008 | |||
10/ /2008 | |||
10/ /2008 | |||
10/ /2008 | |||
E-MAIL COPY? | |||
YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO YES | |||
NO | |||
VEPCO | |||
Letter to: David A. Christian from Malcolm T. Widmann Dated October 17, 2008 | |||
3 | |||
Letter to: David A. Christian from Malcolm T. Widmann Dated October 17, 2008 | |||
SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE | ||
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND | |||
05000339/2009301 | 05000339/2009301 | ||
Distribution w/encl: | Distribution w/encl: | ||
RIDSNRRDIRS | |||
PUBLIC | PUBLIC | ||
S. P. Lingam, NRR | S. P. Lingam, NRR | ||
Richard Jervey, NRR | Richard Jervey, NRR | ||
}} | }} | ||
Latest revision as of 14:43, 14 January 2025
| ML082910130 | |
| Person / Time | |
|---|---|
| Site: | North Anna |
| Issue date: | 10/17/2008 |
| From: | Widmann M NRC/RGN-II/DRS/OLB |
| To: | Christian D Virginia Electric & Power Co (VEPCO) |
| References | |
| IR-09-301 | |
| Download: ML082910130 (8) | |
See also: IR 05000338/2009301
Text
3
October 17, 2008
Mr. David A. Christian
President and Chief Nuclear Officer
Virginia Electric and Power Company
Innsbrook Technical Center
5000 Dominion Boulevard
Glen Allen, VA 23060-6711
SUBJECT:
REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND
Dear Mr. Christian:
In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear
Training (Initial Operations), and Mr. Phillip G. Capehart, Operations Examiner, arrangements
were made for the administration of a licensing retake written examination scheduled to be given
on February 10, 2009, at the North Anna Power Station.
As agreed during the telephone conversation, your staff will prepare the written examination
based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing
Examination Standards for Power Reactors."
To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your
staff on August 13, 2008. The written examination and the supporting reference materials
identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10,
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the examinations before they are submitted
to the NRC for review and approval. All materials shall be complete and ready-to-use. Your
staff has also agreed to make copies of all examination materials that are necessary for
administering the examination.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations is being administered.
2
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications (Office of Management and Budget
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for
this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time
for reviewing instructions, gathering and maintaining the data needed, writing the examinations,
and completing and reviewing the collection of information. Send comments on any aspect of
this collection of information, including suggestions for reducing the burden, to the Information
and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov;
and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-
0018), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of
information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of the NRCs document system (ADAMS).
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the
Public Electronic Reading Room).
Thank you for your cooperation in this matter. Mr. Walt Shura has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRC's
examination procedures and guidelines, please contact Mr. Phillip G. Capehart at (404) 562-
4483, (Internet E-mail: Phillip.Capehart@nrc.gov), or me at (404) 562-4550, (Internet E-mail:
Malcolm.Widmann@nrc.gov).
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operator Licensing Branch
Division of Reactor Safety
Docket No.: 50-338, 50-339
(cc: w/encl - See Page 3)
3
cc w/encl:
Daniel G. Stoddard
Site Vice President
Virginia Electric and Power Company
Electronic Mail Distribution
Eric Hendrixson
Director, Nuclear Safety and Licensing
Virginia Electric and Power Company
Electronic Mail Distribution
Chris L. Funderburk
Director, Nuclear Licensing & Operations
Support
Virginia Electric and Power Company
Electronic Mail Distribution
Lillian M. Cuoco, Esq.
Senior Counsel
Dominion Resources Services, Inc.
Electronic Mail Distribution
Executive Vice President
Old Dominion Electric Cooperative
Electronic Mail Distribution
Attorney General
Supreme Court Building
900 East Main Street
Senior Resident Inspector
North Anna Power Station
U.S. Nuclear Regulatory Commission
P.O. Box 490
Mineral, VA 23117
County Administrator
Louisa County
P.O. Box 160
Louisa, VA 23093
Michael M. Cline
Director
Virginia Department of
Emergency Services Management
Electronic Mail Distribution
Ginger L. Alligood
(NORTH ANNA EXAM
REPORTS ONLY)
Virginia Electric and Power Company
ATTN: Mr. Christopher A. McClain
Manager Nuclear Training
North Anna Power Station
P.O. Box 402
Mineral, VA 23117
Richmond, VA 23219
October 17, 2008
Mr. David A. Christian
Senior Vice President and Chief Nuclear Officer
Virginia Electric and Power Company
Innsbrook Technical Center
5000 Dominion Boulevard
Glen Allen, VA 23060
SUBJECT:
REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND
Dear Mr. Christian:
In a telephone conversation on August 21, 2008, between Mr. Walt Shura, Supervisor Nuclear
Training (Initial Operations), and Mr. Phillip G. Capehart, Operations Examiner, arrangements
were made for the administration of a licensing retake written examination scheduled to be given
on February 10, 2009, at the North Anna Power Station.
As agreed during the telephone conversation, your staff will prepare the written examination
based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing
Examination Standards for Power Reactors."
To meet the above schedule, Mr. Phillip Capehart provided a written examination outline to your
staff on August 13, 2008. The written examination and the supporting reference materials
identified in Attachment 3 to ES-201 will be due by December 19, 2008. Pursuant to Title 10,
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the examinations before they are submitted
to the NRC for review and approval. All materials shall be complete and ready-to-use. Your
staff has also agreed to make copies of all examination materials that are necessary for
administering the examination.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations is being administered.
_________________________
XG SUNSI REVIEW COMPLETE
OFFICE
RII:DRS
RIII:DRS
RIII:DRP
SIGNATURE
/RA/
/RA/
/RA/
NAME
PCapehart
MWidmann
J. Dodson
DATE
10/16/2008
10/17/2008
10/17/2008
10/ /2008
10/ /2008
10/ /2008
E-MAIL COPY?
YES
NO YES
NO YES
NO YES
NO YES
NO YES
NO YES
NO
3
Letter to: David A. Christian from Malcolm T. Widmann Dated October 17, 2008
SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL RETAKE
EXAMINATION NORTH ANNA POWER STATION - 05000338/2009301 AND
Distribution w/encl:
RIDSNRRDIRS
PUBLIC
S. P. Lingam, NRR