{{#Wiki_filter:No. III 021 Contacts:
{{#Wiki_filter:No. III-10-021 Contacts:
Viktoria Mitlyng     630-829-9662  
Viktoria Mitlyng 630-829-9662 Prema Chandrathil 630-829-9663 May 24, 2010 E-Mail: opa3@nrc.gov Web site: www.nrc.gov NRC TO DISCUSS 2009 PERFORMANCE ASSESSMENT OF BRAIDWOOD NUCLEAR PLANT JUNE 3 The Nuclear Regulatory Commission staff will meet with representatives of Exelon Generation Company, LLC, on Thursday, June 3, to discuss the agencys assessment of last years safety performance at the Braidwood Nuclear Power Plant. The plant has two reactor units in Braceville, Ill., 20 miles southwest of Joliet.
 
The meeting, which will be open to the public, is scheduled to begin at 6 p.m. CDT at the Fossil Ridge Public Library District meeting room, 386 W. Kennedy Rd., in Braidwood. The NRC staff will present the results of the assessment, talk about the NRC, and its range of activities, and be available to respond to questions or comments from the public before the close of the meeting.
Prema Chandrathil 630-829-9663 May 24, 2010                                       E-Mail: opa3@nrc.gov Web site: www.nrc.gov NRC TO DISCUSS 2009 PERFOR MANCE ASSESSMENT OF BRAIDWOOD NUCLEAR PLANT JUNE 3 The Nuclear Regulatory Commission staff will meet with representatives of Exelon Generation Company, LLC, on Thursday, June 3, to discuss the agency's assessment of last year's safety performance at the Braidwood Nuclear Power Plant. The plant has two reactor units in Braceville, Ill., 20 miles southwest of Joliet.  
The NRC continually reviews the performance of the Braidwood plant and the nations other commercial nuclear power facilities, NRC Region III Administrator Mark Satorius said. This meeting allows us to discuss our annual assessment of safety performance with the company and area residents. One of NRCs main goals is to explain to people in the community how the agency regulates nuclear power plants to protect people and the environment.
 
The meeting, which will be open to the public, is scheduled to begin at 6 p.m. CDT at the Fossil Ridge Public Library District meeting room, 386 W. Kennedy Rd., in Braidwood. The NRC staff will present the results of th e assessment, talk about the NRC, and its range of activities, and be available to respond to questions or comments from the public before the close of the meeting.
 
"The NRC continually reviews the performance of the Braidwood plant and the nation's other commercial nuclear power facilities," NRC Region III Administrator Mark Satorius said. "This meeting allows us to discuss our annual assessment of safety performance with the company and area residents. One of NRC's main goals is to explain to people in the community how the agency regulates nuclear power plants to protect people and the environment."
 
A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC Web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/brai_2009q4.pdf.
A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC Web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/brai_2009q4.pdf.
The NRC's assessment concluded Braidwood operated safely during the period. The agency uses color-coded inspection findings and performance indicators to assess nuclear plant performance. The colors start with "green" and then increase to "white," "yellow" or "re d," commensurate with the safety significance of the issues involved.
The NRCs assessment concluded Braidwood operated safely during the period. The agency uses color-coded inspection findings and performance indicators to assess nuclear plant performance.
 
The colors start with green and then increase to white, yellow or red, commensurate with the safety significance of the issues involved.
NRC inspectors identified one "white" finding of low to moderate safety significance in 2009 for Braidwood Unit 1. This finding involved the failu re of the containment sump suction isolation NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532  
NRC inspectors identified one white finding of low to moderate safety significance in 2009 for Braidwood Unit 1. This finding involved the failure of the containment sump suction isolation NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532  
 
valve to fully open due to deficiencies in valve design. The valve is not required for routine plant operations, but would be used in certain accident conditions.
If it failed to operate during an accident, other safety equipment would fulfill its safety function. The NRC will conduct a supplemental inspection to make sure the problems associated with the finding have been understood and resolved.


valve to fully open due to deficiencies in valve design. The valve is not required for routine plant operations, but would be used in certain accident conditions. If it failed to operate during an accident, other safety equipment would fulfill its safety function. The NRC will conduct a supplemental inspection to make sure the problems associated with the finding have been understood and resolved.
Braidwood Unit 2 performed at a level that requires no additional oversight from the NRC.
Braidwood Unit 2 performed at a level that requires no additional oversight from the NRC.
 
The NRC letter also addressed a substantive cross-cutting issue in the area of human performance. Cross-cutting issues cut across multiple areas of plant operation. Examples of cross-cutting issues include problems associated with the plant staffs ability to identify and correct problems, to develop effective procedures and adhere to these procedures. Cross-cutting issues cannot be quantified and are not assigned safety significance. However, they serve as early indicators of potential performance deficiencies. In Braidwoods case, the cross-cutting issue involves a failure to make conservative assumptions and demonstrate a proposed action is safe. The plant has developed a plan to address this issue but these actions have not yet been effective. When a substantive cross-cutting issue is identified at a nuclear power plant, the NRC expects the problem to be corrected.
The NRC letter also addressed a substantive cross-cutting issue in the area of human performance. Cross-cutting issues "cut across" multiple areas of plant operation. Examples of cross-cutting issues include problems associated with the plant staff's ability to identify and correct problems, to develop effective procedures and adhere to these procedures. Cross-cutting issues  
The NRC also plans to conduct an inspection of the independent spent fuel storage facility the utility plans to open at Braidwood. It will focus on preoperational testing of installation plans and activities and the review of the operating plan.
 
Braidwood will continue to receive the detailed inspection regime used by the NRC for all nuclear plants. In addition, a supplemental inspection will be conducted of the independent spent fuel storage facility. Inspections are performed by two NRC Resident Inspectors assigned to the plant and by specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md.
cannot be quantified and are not assigned safety significance. However, they serve as early indicators of potential performance deficiencies. In Braidwood's case, the cross-cutting issue involves a failure to make conservative assumptions and demonstrate a proposed ac tion is safe. The plant has developed a plan to address this issue but these actions have not yet been effective. When a substantive cross-cutting issue is identified at a nuclear power plant, the NRC expects the problem to be corrected.  
Among the areas of plant operations to be inspected this year by NRC specialists are emergency preparedness and radiation monitoring.
 
Current performance information for Braidwood is available on the NRCs web site at:
The NRC also plans to conduct an inspection of the independent spent fuel storage facility the utility plans to open at Braidwood. It will focus on preoperational testing of installation plans and activities and the review of the operating plan.
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI1/brai1_chart.html (Unit 1) and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI2/brai2_chart.html (Unit 2).
 
News releases are available through a free listserv subscription at the following Web address:
Braidwood will continue to receive the detailed inspection regime used by the NRC for all nuclear plants. In addition, a supplemental inspecti on will be conducted of the independent spent fuel storage facility. Inspections are performed by two NRC Resident Inspectors assigned to the plant and by specialists from the Region III Office in Lisle, Ill., and the agency's hea dquarters in Rockville, Md. Among the areas of plant operations to be inspected this year by NRC specialists are emergency preparedness and radiation monitoring.  
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link.
 
E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.}}
Current performance information for Braidwood is available on the NRC's web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI1/brai1_chart.html (Unit 1) and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI2/brai2_chart.html (Unit 2). ###  News releases are available through a free listserv subscription at the following Web address: http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.}}

Latest revision as of 04:48, 14 January 2025

Press Release-III-10-021: NRC to Discuss 2009 Performance Assessment of Braidwood Nuclear Plant June 3
ML101440421
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 05/24/2010
From:
Office of Public Affairs Region II
To:
Category:Press Release
References
Press Release-III-10-021
Download: ML101440421 (2)


Text

No. III-10-021 Contacts:

Viktoria Mitlyng 630-829-9662 Prema Chandrathil 630-829-9663 May 24, 2010 E-Mail: opa3@nrc.gov Web site: www.nrc.gov NRC TO DISCUSS 2009 PERFORMANCE ASSESSMENT OF BRAIDWOOD NUCLEAR PLANT JUNE 3 The Nuclear Regulatory Commission staff will meet with representatives of Exelon Generation Company, LLC, on Thursday, June 3, to discuss the agencys assessment of last years safety performance at the Braidwood Nuclear Power Plant. The plant has two reactor units in Braceville, Ill., 20 miles southwest of Joliet.

The meeting, which will be open to the public, is scheduled to begin at 6 p.m. CDT at the Fossil Ridge Public Library District meeting room, 386 W. Kennedy Rd., in Braidwood. The NRC staff will present the results of the assessment, talk about the NRC, and its range of activities, and be available to respond to questions or comments from the public before the close of the meeting.

The NRC continually reviews the performance of the Braidwood plant and the nations other commercial nuclear power facilities, NRC Region III Administrator Mark Satorius said. This meeting allows us to discuss our annual assessment of safety performance with the company and area residents. One of NRCs main goals is to explain to people in the community how the agency regulates nuclear power plants to protect people and the environment.

A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC Web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/brai_2009q4.pdf.

The NRCs assessment concluded Braidwood operated safely during the period. The agency uses color-coded inspection findings and performance indicators to assess nuclear plant performance.

The colors start with green and then increase to white, yellow or red, commensurate with the safety significance of the issues involved.

NRC inspectors identified one white finding of low to moderate safety significance in 2009 for Braidwood Unit 1. This finding involved the failure of the containment sump suction isolation NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532

valve to fully open due to deficiencies in valve design. The valve is not required for routine plant operations, but would be used in certain accident conditions. If it failed to operate during an accident, other safety equipment would fulfill its safety function. The NRC will conduct a supplemental inspection to make sure the problems associated with the finding have been understood and resolved.

Braidwood Unit 2 performed at a level that requires no additional oversight from the NRC.

The NRC letter also addressed a substantive cross-cutting issue in the area of human performance. Cross-cutting issues cut across multiple areas of plant operation. Examples of cross-cutting issues include problems associated with the plant staffs ability to identify and correct problems, to develop effective procedures and adhere to these procedures. Cross-cutting issues cannot be quantified and are not assigned safety significance. However, they serve as early indicators of potential performance deficiencies. In Braidwoods case, the cross-cutting issue involves a failure to make conservative assumptions and demonstrate a proposed action is safe. The plant has developed a plan to address this issue but these actions have not yet been effective. When a substantive cross-cutting issue is identified at a nuclear power plant, the NRC expects the problem to be corrected.

The NRC also plans to conduct an inspection of the independent spent fuel storage facility the utility plans to open at Braidwood. It will focus on preoperational testing of installation plans and activities and the review of the operating plan.

Braidwood will continue to receive the detailed inspection regime used by the NRC for all nuclear plants. In addition, a supplemental inspection will be conducted of the independent spent fuel storage facility. Inspections are performed by two NRC Resident Inspectors assigned to the plant and by specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md.

Among the areas of plant operations to be inspected this year by NRC specialists are emergency preparedness and radiation monitoring.

Current performance information for Braidwood is available on the NRCs web site at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI1/brai1_chart.html (Unit 1) and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/BRAI2/brai2_chart.html (Unit 2).

News releases are available through a free listserv subscription at the following Web address:

http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link.

E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.