IR 05000333/2017404: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (6 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML17228A078 | | number = ML17228A078 | ||
| issue date = 08/15/2017 | | issue date = 08/15/2017 | ||
| title = | | title = Problem Identification and Resolution Sample Inspection Report 05000333/2017404 (Letter Only) | ||
| author name = Dentel G | | author name = Dentel G | ||
| author affiliation = NRC/RGN-I/DRS/EB2 | | author affiliation = NRC/RGN-I/DRS/EB2 | ||
| addressee name = Hanson B | | addressee name = Hanson B | ||
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | | addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | ||
| docket = 05000333 | | docket = 05000333 | ||
| license number = DPR-059 | | license number = DPR-059 | ||
| contact person = Dentel G | | contact person = Dentel G | ||
| document report number = IR 2017404 | | document report number = IR 2017404 | ||
| document type = Letter | | document type = Letter | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter | {{#Wiki_filter:August 15, 2017 | ||
==SUBJECT:== | |||
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - PROBLEM IDENTIFICATION AND RESOLUTION SAMPLE INSPECTION REPORT 05000333/2017404 | |||
SUBJECT: JAMES A. FITZPATRICK NUCLEAR POWER PLANT - PROBLEM IDENTIFICATION AND RESOLUTION SAMPLE INSPECTION REPORT 05000333/2017404 | |||
==Dear Mr. Hanson:== | ==Dear Mr. Hanson:== | ||
On July 13, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security-related Problem Identification and Resolution inspection at your James A. Fitzpatrick Nuclear Power Plant and the NRC inspectors discussed the results of this inspection with Mr. Joseph Pacher, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report. | On July 13, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security-related Problem Identification and Resolution inspection at your James A. Fitzpatrick Nuclear Power Plant and the NRC inspectors discussed the results of this inspection with Mr. Joseph Pacher, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report. | ||
The inspector documented one finding of very low security significance (Green) in this report | The inspector documented one finding of very low security significance (Green) in this report. | ||
This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. | |||
James A. Fitzpatrick Nuclear Power Plant. | If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at the James A. Fitzpatrick Nuclear Power Plant. | ||
If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I and the NRC Resident Inspector at the James A. Fitzpatrick Nuclear Power Plant. | If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I and the NRC Resident Inspector at the James A. Fitzpatrick Nuclear Power Plant. | ||
| Line 40: | Line 36: | ||
A cross-cutting aspect was assigned to this finding in the area of Problem Identification and Resolution, Resolution, because Entergy did not take effective corrective actions to resolve and correct a previous NRC-identified violation. [P.3] | A cross-cutting aspect was assigned to this finding in the area of Problem Identification and Resolution, Resolution, because Entergy did not take effective corrective actions to resolve and correct a previous NRC-identified violation. [P.3] | ||
Enclosure contains | Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, the transmittal document is decontrolled. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding. | ||
However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii). | |||
Sincerely, | |||
/RA/ | |||
Glenn T. Dentel, Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket No: 50-333 License No: DPR-59 | Docket No: 50-333 License No: DPR-59 | ||
Nonpublic | Nonpublic Enclosure: | ||
Inspection Report 05000333/2017404 w/Attachment: Supplementary Information | |||
cc w/o encl; w/o OUO-SRI: | |||
Distribution via ListServ | |||
cc w/encl; w/OUO-SRI: | |||
T. Redfearn, Site Security Manager A. Peterson, State Liaison Office Designee, NY State Energy, Research & Development Authority | |||
ML17228A078 (Cover letter) | |||
ADAMS ACCESSION NUMBER: ML17228A075 (Cover letter w/enclosure) | |||
Non-Public Designation Category: MD 3.4 Non-Public A.3 Cover Letter SUNSI Review X Non-Sensitive Sensitive X Publicly Available Non-Publicly Available Cover Letter w/Enclosure SUNSI Review Non-Sensitive X Sensitive Publicly Available X Non-Publicly Available OFFICE RI/DRS RI/DRP RI/DRS | |||
NAME LDumont ABurritt GDentel | |||
DATE 8/7/17 8/14/17 8/8/17 | |||
}} | }} | ||
Latest revision as of 13:52, 8 January 2025
| ML17228A078 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 08/15/2017 |
| From: | Glenn Dentel Engineering Region 1 Branch 2 |
| To: | Bryan Hanson Exelon Generation Co, Exelon Nuclear |
| Dentel G | |
| References | |
| IR 2017404 | |
| Download: ML17228A078 (3) | |
Text
August 15, 2017
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - PROBLEM IDENTIFICATION AND RESOLUTION SAMPLE INSPECTION REPORT 05000333/2017404
Dear Mr. Hanson:
On July 13, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security-related Problem Identification and Resolution inspection at your James A. Fitzpatrick Nuclear Power Plant and the NRC inspectors discussed the results of this inspection with Mr. Joseph Pacher, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
The inspector documented one finding of very low security significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at the James A. Fitzpatrick Nuclear Power Plant.
If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I and the NRC Resident Inspector at the James A. Fitzpatrick Nuclear Power Plant.
A cross-cutting aspect was assigned to this finding in the area of Problem Identification and Resolution, Resolution, because Entergy did not take effective corrective actions to resolve and correct a previous NRC-identified violation. [P.3]
Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, the transmittal document is decontrolled. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Glenn T. Dentel, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No: 50-333 License No: DPR-59
Nonpublic Enclosure:
Inspection Report 05000333/2017404 w/Attachment: Supplementary Information
cc w/o encl; w/o OUO-SRI:
Distribution via ListServ
cc w/encl; w/OUO-SRI:
T. Redfearn, Site Security Manager A. Peterson, State Liaison Office Designee, NY State Energy, Research & Development Authority
ML17228A078 (Cover letter)
ADAMS ACCESSION NUMBER: ML17228A075 (Cover letter w/enclosure)
Non-Public Designation Category: MD 3.4 Non-Public A.3 Cover Letter SUNSI Review X Non-Sensitive Sensitive X Publicly Available Non-Publicly Available Cover Letter w/Enclosure SUNSI Review Non-Sensitive X Sensitive Publicly Available X Non-Publicly Available OFFICE RI/DRS RI/DRP RI/DRS
NAME LDumont ABurritt GDentel
DATE 8/7/17 8/14/17 8/8/17