ML20235R342: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:_ _ .
{{#Wiki_filter:_ _ .
  . .
.
      "
.
  t
t
            .
"
  .
.
                                U.S. NUCLEAR REGULATORY COMMISSION
.
                              OFFICE OF NUCLEAR REACTOR REGULATION
U.S. NUCLEAR REGULATORY COMMISSION
                          Division of Reactor Inspection and Safeguards
OFFICE OF NUCLEAR REACTOR REGULATION
        Report Nos.:         50-325/88-200 and 50-324/88-200
Division of Reactor Inspection and Safeguards
        Docket Nos.:         50-325 and 50-324
Report Nos.:
        Licensee:           Carolina Power and Light Company
50-325/88-200 and 50-324/88-200
                              P.O. Box 1551
Docket Nos.:
                              Raleigh, NC 27602
50-325 and 50-324
        Inspection At:       Brunswick Steam Electric Plant, Units 1 and 2
Licensee:
        Inspection Dates:   September 26 through October 7, 1988
Carolina Power and Light Company
                                                                                                                          l
P.O. Box 1551
                                        -        ~ b' ^-                     l -T5- @
Raleigh, NC 27602
        Team Leader:
Inspection At:
Brunswick Steam Electric Plant, Units 1 and 2
Inspection Dates:
September 26 through October 7, 1988
l
~ b' ^-
Team Leader:
l -T5- @
-
C. A. VanDenburgh, Senior Operations
Date Signed
I
Engineer, NRR
.
l
,
,
                        C. A. VanDenburgh, Senior Operations                Date Signed                                    .
Team Members:
I                      Engineer, NRR                                                                                      l
G.T. Hopper, Region II
        Team Members: G.T. Hopper, Region II
P.R. Farron, Nuclear Engineers and Consultants
                        P.R. Farron, Nuclear Engineers and Consultants
D.H. Schultz, Comex Corporation
                        D.H. Schultz, Comex Corporation
J.F. Hanek, EG&G Idaho, Incorporated
                        J.F. Hanek, EG&G Idaho, Incorporated
W.E. Gilmore, EG&G Idaho, Incorporated
                        W.E. Gilmore, EG&G Idaho, Incorporated
Other NRC Personnel Attending Exit Meetings:
        Other NRC Personnel Attending Exit Meetings: J. Konklin, Section Chief NRR;
J. Konklin, Section Chief NRR;
        C. Julian, Branch Chief, Region II; B. Buckley, Project Manager, NRR; and
C. Julian, Branch Chief, Region II; B. Buckley, Project Manager, NRR; and
        W. Ruland, Senior Resident Inspector.
W. Ruland, Senior Resident Inspector.
l
l
        Reviewed By:       w                         '
Reviewed By:
                                                        /                   //ET//f'(
w
                          ames E. Konklin, Chief                           Ddte Signed
/
                        Special Team Support
//ET//f'(
                        & Integration Section, NRR
ames E. Konklin, Chief
        Approved By:             (164/4t(                                   //2Md7
Ddte Signed
                        Unarles p. Haughney, Chief                         Ddte Signed
'
                        Special inspection Branch, NRR
Special Team Support
& Integration Section, NRR
Approved By:
(164/4t(
//2Md7
Unarles p. Haughney, Chief
Ddte Signed
Special inspection Branch, NRR
i
i
              8903030263 890223
8903030263 890223
              PDR
PDR
              O
ADOCK 03000324
                    ADOCK 03000324
O
                                PDC
PDC
                                                                                _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _       -
_ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _
-


            .               -
-
          '
.
                                                ,
'
                                              ~
,
          .
~
                                  Scope:
.
                                                                                                                  1
Scope:
                                  From September 26 through October 7,1988 an NRC inspection team conducted an   '
1
                                  inspection of the Emergency Operating Procedures (E0Ps) for the Brunswick Steam
From September 26 through October 7,1988 an NRC inspection team conducted an
                                  Electric Plant (BSEP), Units 1 and 2. BSEP Units 1 and 2 are General Electric   i
'
                                  BWR-4 plants with Mark I containments. The objective of the inspection was to
inspection of the Emergency Operating Procedures (E0Ps) for the Brunswick Steam
                                  determine if the E0Ps (1) were technically correct (2) could be physically
Electric Plant (BSEP), Units 1 and 2.
                                  carried out in the plant, and (3) could be performed correctly by the
BSEP Units 1 and 2 are General Electric
                                  operators.
                                  The inspection team compared Revision 4AF of the BWR Owner's Group (BWROG)
                                  Emergency Procedure Guidelines (EPGs) to the Plant Specific Technical
                                  Guidelines (PSTGs); compared the PSTGs to the E0Ps; reviewed the calculations
                                  performed to develop the plant specific curves, values and setpoints utilized
                                  in the E0Ps; performed a plant walkthrough of all the E0Ps and the Local        l
                                                                                                                  '
                                  Emergency Procedures (LEPs) and Supplemental Emergency Procedures (SEPs)
                                  referenced by the E0Ps; observed a simulation of four emergency scenarios using
                                  the plant-specific simulator; performed a human factors review of the
                                  procedures and plant operations; interviewed licensed and non-licensed
                                  personnel who utilize the E0Ps; and reviewed the primary containment venting
                                  procedures.
                                  Results:
                                  The inspection was based on a draft of the E0Ps which were in the final stages
                                  of development and were expected to be implemented on December 15, 1988.    The
i
i
                                  draft E0Ps incorporated Revision 4AF of the BWROG EPGs. They corrected
BWR-4 plants with Mark I containments.
l                                 deficiencies which had been identified during an Operational Safety Assessment
The objective of the inspection was to
                                  and a Probabilistic Risk Assessment based inspection [ Inspection Reports
determine if the E0Ps (1) were technically correct (2) could be physically
carried out in the plant, and (3) could be performed correctly by the
operators.
The inspection team compared Revision 4AF of the BWR Owner's Group (BWROG)
Emergency Procedure Guidelines (EPGs) to the Plant Specific Technical
Guidelines (PSTGs); compared the PSTGs to the E0Ps; reviewed the calculations
performed to develop the plant specific curves, values and setpoints utilized
in the E0Ps; performed a plant walkthrough of all the E0Ps and the Local
l
Emergency Procedures (LEPs) and Supplemental Emergency Procedures (SEPs)
'
'
                                  50-325(324)/88-19 and 50-325(324)/88-11] performed by Region II to evaluate the
referenced by the E0Ps; observed a simulation of four emergency scenarios using
                                  E0Ps presently in use.
the plant-specific simulator; performed a human factors review of the
                                  The inspectors were impressed with the scope of the corrective actions taken in
procedures and plant operations; interviewed licensed and non-licensed
                                  response to the deficiencies identified during the previous inspections and
personnel who utilize the E0Ps; and reviewed the primary containment venting
                                  with the licensee's controls for the development of the E0Ps. All of the
procedures.
                                  previous deficiencies had been corrected, and the development process was well
Results:
                                  documented and defined.
The inspection was based on a draft of the E0Ps which were in the final stages
l                                 The BSEP E0Ps were developed as post-trip recovery procedures and integrated
of development and were expected to be implemented on December 15, 1988.
                                  the post-trip operator actions with the required actions of the EPGs and the
The
l                                 station blackout actions. The E0Ps provided a high level of detail and
draft E0Ps incorporated Revision 4AF of the BWROG EPGs.
l                                 prioritized the operators' actions based on the significance of the event. As
They corrected
                                  a result, however, the E0Ps had a significant potential to delay the required
i
                                  accident mitigation actions as post-trip recovery actions were accomplished.
l
                                  The inspection team concluded, based on the simulator scenarios, that the
deficiencies which had been identified during an Operational Safety Assessment
                                  required EPG actions could not be accomplished in a timely manner without the
'
                                  direct involvement of both the shift foreman and the shift technical adviscr to
and a Probabilistic Risk Assessment based inspection [ Inspection Reports
                                  read and perform the E0P action steps. The active participation of both these
50-325(324)/88-19 and 50-325(324)/88-11] performed by Region II to evaluate the
                                  individuals was not in accordance with the licensee's administrative
E0Ps presently in use.
                                  instructions, but was considered by the team to be an adequate method of E0P
The inspectors were impressed with the scope of the corrective actions taken in
                                  accomplishment.
response to the deficiencies identified during the previous inspections and
l                                 The inspection team determined that the draft E0Ps did not in every instance
with the licensee's controls for the development of the E0Ps. All of the
                                  represent an accurate incorporation of the BWROG EPGs and would not adequately
previous deficiencies had been corrected, and the development process was well
documented and defined.
l
The BSEP E0Ps were developed as post-trip recovery procedures and integrated
the post-trip operator actions with the required actions of the EPGs and the
l
station blackout actions.
The E0Ps provided a high level of detail and
l
prioritized the operators' actions based on the significance of the event. As
a result, however, the E0Ps had a significant potential to delay the required
accident mitigation actions as post-trip recovery actions were accomplished.
The inspection team concluded, based on the simulator scenarios, that the
required EPG actions could not be accomplished in a timely manner without the
direct involvement of both the shift foreman and the shift technical adviscr to
read and perform the E0P action steps. The active participation of both these
individuals was not in accordance with the licensee's administrative
instructions, but was considered by the team to be an adequate method of E0P
accomplishment.
l
The inspection team determined that the draft E0Ps did not in every instance
represent an accurate incorporation of the BWROG EPGs and would not adequately
1
1
m___._______________.___.__..______________._     _ _ _ _ _ _ _ _ _
m___._______________.___.__..______________._
_ _ _ _ _ _ _ _ _


. .
.
.
'
'
                                                                                            .
                                          .
.
.
        assure the successful accomplishment of all specified actions because several
.
        procedures had a low probability of success and several calculational errors
.
        were identified. Several of the inspection teams' concerns affected the E0P3
assure the successful accomplishment of all specified actions because several
        which were presently implemented. The licensee was requested to take innediate
procedures had a low probability of success and several calculational errors
        action to evaluate and correct these operational concerns.
were identified.
                                                                                                                                                                                                                      I
Several of the inspection teams' concerns affected the E0P3
                                                                                                                                                                                                                      J
which were presently implemented. The licensee was requested to take innediate
                                                                                                                                                                                                                      l
action to evaluate and correct these operational concerns.
                                                                                                                                                                                                                      l
J
                                                                                                                                                                                                                      I
l
                                                                                                                                                                                                                      l
l
    - _ _ _ . _ . - _ _ . - _ _ _ _ - _ _ _ . . _ _ _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ . _ _ - - . . _ . - - ,-. -_- _ _ . - , . - _ . . . , - - _ - - _ - . . . . - _ . , - - _ - - - - . - _ - - , . . - _ - - _ . -
- _ _ _ . _ . - _ _ . - _ _ _ _ - _ _ _ . . _ _ _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ . _ _ - - . . _ . - -
,-.
-_- _ _ . - , . - _ . . . , - -
_
- - _ - . . . . - _ . , - - _
- - - - . - _
- - , . . - _ - - _ . -


    . .
.
  t
.
                  .
t
            -
.
  .
-
                                                TABLE OF CONTENTS
.
                              EMERGENCY OPEP.ATING PROCEDURE INSPECTION at
TABLE OF CONTENTS
                            Brunswick Steam Electric Plant, Units 1 and 2
EMERGENCY OPEP.ATING PROCEDURE INSPECTION at
                        (Inspection Reports 50-325/88-200and50-324/88-200)
Brunswick Steam Electric Plant, Units 1 and 2
                                                                                                                  Page
(Inspection Reports 50-325/88-200and50-324/88-200)
        1.0 INSPECTION 0BJECTIVE.........................................                                         1
Page
        2.0   BACKGR0VND.......................................                             4 ..........         1
1.0 INSPECTION 0BJECTIVE.........................................
        3.0 DETAILED INSPECTION FINDINGS.................................                                         3
1
              3.1 Emergency Operation Procedure (E0P) Program Evaluation..                                       3
2.0
                    3.1.1 E0P Development..................................                                       3
BACKGR0VND.......................................
                    3.1.2 Licensee Verification and Validation of E0Ps.....                                       4   i
4
                    3.1.3 E0P Operator Training............................                                       5   1
1
                    3.1.4 Maintenance of E0Ps..............................                                       6
..........
                    3.1.5 Quality Assurance Involvement in PSTG                                                       l
3.0 DETAILED INSPECTION
                                                                                                                        1
FINDINGS.................................
                            Maintenance......................................                                    6
3
                    3.1.6 Licensee Response to IE Information Notice 86-64.                                      7
3.1 Emergency Operation Procedure (E0P) Program Evaluation..
              3.2 E0P P rocedu re Ve ri fi ca t i on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  7    !
3
                    3.2.1  EPG/PSTG Comparison..............................                                    7  I
3.1.1
                    3.2.2 PSTG/EOP Comparison..............................                                      12
E0P Development..................................
                    3.2.3 Calculation      Review...............................                                13
3
                    3.2.4 Adequacy of Writer's Guide.......................                                      15
3.1.2 Licensee Verification and Validation of E0Ps.....
                    3.2.5 Writer's Guide Implementation....................                                      16
4
              3.3 E0P Validation Using Plant Walkthroughs.................                                      17  j
i
                    3.3.1 Technical Adequacy of Procedures.................                                      18
3.1.3
                    3.3.2 Availability of Special Tools and Equipment......                                      19
E0P Operator Training............................
                    3.3.3 Station Material Condition.......................                                      21
5
                    3.3.4 Reactor Building Accessibility...................                                      21
1
3.1.4 Maintenance of E0Ps..............................
6
3.1.5 Quality Assurance Involvement in PSTG
l
l
              3.4 C0P Validation Using Plant           Simulator....................                           22
1
Maintenance......................................
6
3.1.6 Licensee Response to IE Information Notice 86-64.
7
3.2 E0P P rocedu re Ve ri fi ca t i on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7
!
3.2.1
EPG/PSTG Comparison..............................
7
I
3.2.2 PSTG/EOP Comparison..............................
12
3.2.3 Calculation Review...............................
13
3.2.4 Adequacy of Writer's
Guide.......................
15
3.2.5 Writer's Guide Implementation....................
16
3.3 E0P Validation Using Plant Walkthroughs.................
17
j
3.3.1 Technical Adequacy of Procedures.................
18
3.3.2 Availability of Special Tools and Equipment......
19
3.3.3 Station Material
Condition.......................
21
3.3.4 Reactor Building Accessibility...................
21
l
3.4 C0P Validation Using Plant Simulator....................
22
3.4.1
Scena rio Des c ri pti on. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
22
,
,
                    3.4.1  Scena rio Des c ri pti on. . . . . . . . . . . . . . . . . . . . . . . . . . . . .  22
3.4.2 Limitations of the Plant-Specific Simulator......
23
'
'
                    3.4.2 Limitations of the Plant-Specific Simulator......                                      23
3.4.3 Observations and Conclusions.....................
                    3.4.3 Observations and Conclusions.....................                                     24
24
                                                                                                                        '
'
              3.5 Operator Interviews.....................................                                       25
3.5 Operator Interviews.....................................
                    3.5.1 Observations and Conclusions.....................                                     26
25
              3.6 Prima ry Contai nment Venting Provi sions. . . . . . . . . . . . . . . . . .                   27
3.5.1 Observations and Conclusions.....................
        4.0 MANAGEMENT EXIT MEETING......................................                                         27
26
        Appendix A - PERSONNEL C0NTACTED..................................                                         A-1
3.6 Prima ry Contai nment Venting Provi sions. . . . . . . . . . . . . . . . . .
        Appendix B - DOCUMENTS REVIEWED...................................                                         B-1
27
4.0 MANAGEMENT EXIT MEETING......................................
27
Appendix A - PERSONNEL C0NTACTED..................................
A-1
Appendix B - DOCUMENTS REVIEWED...................................
B-1


    _ _ .                                         --                           .
_ _ .
                                                                                                - . . .
--
          -
.
  .                                                                                                     !
- .
  '
. .
                        .
!
  .
-
                  .
.
            1.0 INSPECTION OBJECTIVE
'
.
.
.
1.0 INSPECTION OBJECTIVE
l
l
            A special team inspection reviewed the licensee's Emergency Operating
'
'
            Procedures (E0Ps), operator training and plant systems in accordance with NRC
A special team inspection reviewed the licensee's Emergency Operating
            Temporary Instruction (TI) 2515/92 to accomplish the following objectives:
Procedures (E0Ps), operator training and plant systems in accordance with NRC
            1)     Determine whether the E0Ps conformed to the BWP Owner's Group (BWROG)
Temporary Instruction (TI) 2515/92 to accomplish the following objectives:
                    Emergency Procedure Guidelines EPGs) and were technically correct for the
1)
                    BrunswickSteamElectricPlantg{BSEP), Units 1and2.
Determine whether the E0Ps conformed to the BWP Owner's Group (BWROG)
Emergency Procedure Guidelines EPGs) and were technically correct for the
BrunswickSteamElectricPlantg{BSEP), Units 1and2.
,
,
            2)     Assess whether the E0Ps could be physically carried out in the plant using
2)
                    existing equipment, controls, and instrumentation, under the expected
Assess whether the E0Ps could be physically carried out in the plant using
                    environmental conditions.
existing equipment, controls, and instrumentation, under the expected
            3)     Evaluate whether the plant staff could correctly perform the E0P actions
environmental conditions.
                    in the time available.
3)
            2.0 BACKGROUND
Evaluate whether the plant staff could correctly perform the E0P actions
            Following the Three Mile Island (TMI) accident, the Office of Nuclear Reactor
in the time available.
            Regulation (NRR) developed the "TMI Action Plan," (NUREG-0660 and NUREG-0737).
2.0 BACKGROUND
            Item I.C.1 of this plan required licensees of operating plants to reanalyze
Following the Three Mile Island (TMI) accident, the Office of Nuclear Reactor
            transients and accidents and to upgrade E0Ps.       In addition, Item I.C.9 of the
Regulation (NRR) developed the "TMI Action Plan," (NUREG-0660 and NUREG-0737).
            plan required the NRC staff to develop a long-term plan that integrated and
Item I.C.1 of this plan required licensees of operating plants to reanalyze
            expanded efforts for the writing, reviewing, and monitoring of plant
transients and accidents and to upgrade E0Ps.
            procedures.     NUREG-0899, " Guidelines for the Preparation of Emergency Operating
In addition, Item I.C.9 of the
            Procedures," represents the NRC staff's long-term program for u
plan required the NRC staff to develop a long-term plan that integrated and
            and describes the use of a Procedures Generition Package to           (PGP)  pgrading
expanded efforts for the writing, reviewing, and monitoring of plant
                                                                                    prepare E0Ps. E0Ps,
procedures.
NUREG-0899, " Guidelines for the Preparation of Emergency Operating
and describes the use of a Procedures Generition Package (PGP) pgrading E0Ps,
Procedures," represents the NRC staff's long-term program for u
to prepare E0Ps.
l
l
            The licensees formed four vendor owners groups corresponding to the four major
The licensees formed four vendor owners groups corresponding to the four major
            reactor vendor types in the United States: Westinghouse, General Electric,
reactor vendor types in the United States: Westinghouse, General Electric,
            Babcock & Wilcox, and Combustion Engineering. Working with the vendor
Babcock & Wilcox, and Combustion Engineering. Working with the vendor
            companies and the NRC, the owner's groups developed generic procedures that set
companies and the NRC, the owner's groups developed generic procedures that set
            forth the desired accident mitigation strategy.       For General Electric plants,
forth the desired accident mitigation strategy.
            the generic guidelines are referred to as the BWR0G EPGs. These guidelines
For General Electric plants,
            were to be used by the licensees in developing their PGPs.
the generic guidelines are referred to as the BWR0G EPGs. These guidelines
            Generic Letter 82-33, " Supplement I to NUREG-0737 - Requirements for Emergency
were to be used by the licensees in developing their PGPs.
            Response Capability," required each licensee to submit to the NRC a PGP which
Generic Letter 82-33, " Supplement I to NUREG-0737 - Requirements for Emergency
Response Capability," required each licensee to submit to the NRC a PGP which
included, (1) Plant Specific Technical Guidelines (PSTGs) with justification
,
,
            included, (1) Plant Specific Technical Guidelines (PSTGs) with justification
for safety significant differences from the BWROG EPGs, (2) a Plant Specific
            for safety significant differences from the BWROG EPGs, (2) a Plant Specific
Writer's Guideline (PSWG), (3) a description of the program to be used for the
            Writer's Guideline (PSWG), (3) a description of the program to be used for the
verification and validation of E0Ps, and (4) a description of the training
            verification and validation of E0Ps, and (4) a description of the training
program for the upgraded E0Ps. The generic letter required the development of
            program for the upgraded E0Ps. The generic letter required the development of
plant-specific E0Ps which would provide the operators with directions to
            plant-specific E0Ps which would provide the operators with directions to
mitigate the consequences of a broad range of initiating events and subsequent
            mitigate the consequences of a broad range of initiating events and subsequent
multiple failures or operator errors.
            multiple failures or operator errors.       In addition, the upgraded E0Ps were
In addition, the upgraded E0Ps were
            required to be symptom-based procedures which would not require the operators               j
required to be symptom-based procedures which would not require the operators
            to diagnose specific events.                                                               I
j
            Although various circumstances caused long delays in achieving NRC approval of             J
to diagnose specific events.
            many of the PGPs, the licensees have all implemented their upgraded E0Ps. To
I
            determine the success of this implementation, a series of NRC inspections was
Although various circumstances caused long delays in achieving NRC approval of
            performed to examine the final product of the program - the E0Ps.
J
                                                                                                        !
many of the PGPs, the licensees have all implemented their upgraded E0Ps.
                                                                                                        i
To
                                                      1                                                 !
determine the success of this implementation, a series of NRC inspections was
performed to examine the final product of the program - the E0Ps.
!
i
1
!


  .
.
              .
.
  -
-
                                                                                            l
l
                                                                                            l
l
    Representative samples of each of the four vendor types were selected for               j
Representative samples of each of the four vendor types were selected for
    review by four inspection teams from Regions I, II, III and IV.
j
    An additional 13 inspections were identified at facilities with General
review by four inspection teams from Regions I, II, III and IV.
    Electric Mark I type containments. These inspections were conducted by the
An additional 13 inspections were identified at facilities with General
    Office of Nuclear Reactor Regulation and included a detailed review of the
Electric Mark I type containments. These inspections were conducted by the
    primary containment venting provisions of the E0Ps. This inspection is the
Office of Nuclear Reactor Regulation and included a detailed review of the
    final inspection in this series.
primary containment venting provisions of the E0Ps.
    3.0 DETAILED INSPECTION FINDINGS                                                         j
This inspection is the
                                                                                            I
final inspection in this series.
    3.1 Emergency Operating Procedure (EOP) Program Evaluation                               l
3.0 DETAILED INSPECTION FINDINGS
    3.1.1  E0P Development                                                                  ;
j
    A Confirmatory Order dated February 22, 1984, identified that the licensee had
I
    submitted a PGP on August 17, 1983, and implemented upgraded E0Ps.      The PSTG
3.1 Emergency Operating Procedure (EOP) Program Evaluation
    submitted and the E0Ps currently implemented at the facility were based upon
l  Revision 2 of the BWROG EPGs.
l
l
3.1.1
E0P Development
;
A Confirmatory Order dated February 22, 1984, identified that the licensee had
submitted a PGP on August 17, 1983, and implemented upgraded E0Ps.
The PSTG
submitted and the E0Ps currently implemented at the facility were based upon
l
l
    The inspection team reviewed a draft version of the E0Ps which were based upon
Revision 2 of the BWROG EPGs.
    Revision 4AF of the BWROG EPGs. This revision incorporated a revised accident
    mitigation strategy and calculational methods which were approved by the NRC in
    a generic safety evaluation report (SER) issued on September 12, 1988. The
    inspection team reviewed the draft E0Ps because the licensee was in the final
    stages of implementing this revision and had scheduled full implementation by
    December 15, 1988. Although the inspection was based upon the draft E0Ps, the            l
    inspection team verified whether identified deficiencies affected the approved
                                                                                              '
    ECPs. Two operational concerns were identified and are discussed in Sections
    3.2.1.1 and 3.2.1.2 of this report.
    Both the currently implemented E0Ps and '.he draft E0Ps had been developed in
    flowchart format with the post-trip recovery actions and the station blackout
    actions integrated with the steps of the BWROG EPG accident mitigation
    strategy. The post-trip recovery actions are event-based actions which are
    normally provided in separate procedures and are not appropriate for the
    symptom-based E0Ps.      The BWROG EPGs and the SER indicated that additional
    auxiliary event-specific procedures intended for use in conjunction with the
    symptomatic procedures must not contradict or subvert the symptomatic operator
    actions specified in the BWROG EPGs.
    The inspection team was concerned that the inclusion of the event-based actions
    into the E0Ps delayed the accomplishment of the actions directed by the BWROG
l
l
    EPGs, had the potential to result in incorrect event diagnosis, and affected
l
    the ability of the operators to implement the E0Ps and thereby respond to the
The inspection team reviewed a draft version of the E0Ps which were based upon
    emergency in a timely manner. As discussed in Section 3.4.3.1, the simulator
Revision 4AF of the BWROG EPGs.
    scenarios demonstrated that the shift foreman could not implement the E0Ps, as
This revision incorporated a revised accident
    required by the licensee's administrative procedures, without the assistance of
mitigation strategy and calculational methods which were approved by the NRC in
    the shif t technical advisor to directly monitor and control the specified E0P
a generic safety evaluation report (SER) issued on September 12, 1988.
    actions involving primary containment and radiological release control.
The
    Although operation in this manner was not in accordance with the administrative
inspection team reviewed the draft E0Ps because the licensee was in the final
    procedures, the inspection team concluded that the operating crew could
stages of implementing this revision and had scheduled full implementation by
    implement the specified E0P actions to shutdown the reactor and return the
December 15, 1988.
    plant to a safe, stable condition. However, the inspection team identified
Although the inspection was based upon the draft E0Ps, the
                                            2
l
                                                                                  _ _ _ - _-
inspection team verified whether identified deficiencies affected the approved
'
ECPs.
Two operational concerns were identified and are discussed in Sections
3.2.1.1 and 3.2.1.2 of this report.
Both the currently implemented E0Ps and '.he draft E0Ps had been developed in
flowchart format with the post-trip recovery actions and the station blackout
actions integrated with the steps of the BWROG EPG accident mitigation
strategy. The post-trip recovery actions are event-based actions which are
normally provided in separate procedures and are not appropriate for the
symptom-based E0Ps.
The BWROG EPGs and the SER indicated that additional
auxiliary event-specific procedures intended for use in conjunction with the
symptomatic procedures must not contradict or subvert the symptomatic operator
actions specified in the BWROG EPGs.
The inspection team was concerned that the inclusion of the event-based actions
into the E0Ps delayed the accomplishment of the actions directed by the BWROG
EPGs, had the potential to result in incorrect event diagnosis, and affected
l
the ability of the operators to implement the E0Ps and thereby respond to the
emergency in a timely manner. As discussed in Section 3.4.3.1, the simulator
scenarios demonstrated that the shift foreman could not implement the E0Ps, as
required by the licensee's administrative procedures, without the assistance of
the shif t technical advisor to directly monitor and control the specified E0P
actions involving primary containment and radiological release control.
Although operation in this manner was not in accordance with the administrative
procedures, the inspection team concluded that the operating crew could
implement the specified E0P actions to shutdown the reactor and return the
plant to a safe, stable condition. However, the inspection team identified
2
_ _ _ -
_-


                                                            _ - _ _ _ _ - _           . _ _ - _ _ _ - _ _ _ _ .
_ - _ _ _ _ - _
    .
. _ _ - _ _ _ - _ _ _ _ .
  .
.
                .
.
          -
.
  .
-
      several examples as a result of this method of implementation, in which
.
      specified E0P actions were not accomplished or were misinterpreted because the
several examples as a result of this method of implementation, in which
      shift foreman and the STA were involved in separate areas of the E0Ps and did
specified E0P actions were not accomplished or were misinterpreted because the
      not have the opportunity to consult and review each others actions.
shift foreman and the STA were involved in separate areas of the E0Ps and did
      The inspection team identified the following additional examples in which the
not have the opportunity to consult and review each others actions.
      E0Ps included event-based actions not related to post-trip recovery actions.
The inspection team identified the following additional examples in which the
      1)     Path-2, steps 35, 60 and 170, precluded the use of the feedwater or
E0Ps included event-based actions not related to post-trip recovery actions.
            condensate system for reactor pressure vessel (RPV) injection if the
1)
            feedwater conductivity was greater than 0.3 mmhos. This was an
Path-2, steps 35, 60 and 170, precluded the use of the feedwater or
            event-based action for condenser tube leakaoe which potentially delayed or
condensate system for reactor pressure vessel (RPV) injection if the
            prevented recovery from a low RPV water level condition.
feedwater conductivity was greater than 0.3 mmhos. This was an
      2)     Primary Containment Control Procedure, steps PC/P-19 through 22, were
event-based action for condenser tube leakaoe which potentially delayed or
            event-based actions for recirculation pump seal failure which were not
prevented recovery from a low RPV water level condition.
            related to primary containment control.
2)
      3)     In the Radiological Release Control Procedure, all the steps in the five
Primary Containment Control Procedure, steps PC/P-19 through 22, were
            flowpaths below step RR-6 were event-based actions for identification and
event-based actions for recirculation pump seal failure which were not
            mitigation of primary leakage. Although these steps were necessary in the
related to primary containment control.
            event of a primary leak, they wv.e not specified in the BWROG EPG for the
3)
            response to a radiological release.
In the Radiological Release Control Procedure, all the steps in the five
      Further licensee action is necessary to ensure that the E0Ps do not contain
flowpaths below step RR-6 were event-based actions for identification and
      event-based actions and to implement the E0Ps in a manner consistent with the
mitigation of primary leakage. Although these steps were necessary in the
event of a primary leak, they wv.e not specified in the BWROG EPG for the
response to a radiological release.
Further licensee action is necessary to ensure that the E0Ps do not contain
event-based actions and to implement the E0Ps in a manner consistent with the
administrative procedures.
,
,
      administrative procedures.
In addition to including event-based actions in the E0Ps, the licensee
      In addition to including event-based actions in the E0Ps, the licensee
developed the E0Ps with a high level of detail and complexity.
      developed the E0Ps with a high level of detail and complexity. The inspection
The inspection
      team was concerned that the additional detail and unnecessary complexity
team was concerned that the additional detail and unnecessary complexity
      represented by the following examples, had the potential to delay the                                     i
represented by the following examples, had the potential to delay the
      operator's response to an actual emergency. Further licensee action'is                                     I
i
      necessary to reduce the level of complexity of the E0Ps.                                                   l
operator's response to an actual emergency.
                                                                                                                l
Further licensee action'is
      1)     Primary Containment Control Procedure, step C.9.e (1), and section 1,                               !
I
necessary to reduce the level of complexity of the E0Ps.
l
l
1)
Primary Containment Control Procedure, step C.9.e (1), and section 1,
!
included reference to the head spray system, which was no longer
'
'
            included reference to the head spray system, which was no longer
applicable because of a plant modification.
The reference should be
'
'
            applicable because of a plant modification. The reference should be
deleted.
            deleted.
2)
      2)     Primary Containment Control Procedure, step PC/M-4, indicated that the
Primary Containment Control Procedure, step PC/M-4, indicated that the
            hydrogen monitor readings must be compensated for primary containment
hydrogen monitor readings must be compensated for primary containment
            conditions in accordance with operational procedure OP-24. In practice,
conditions in accordance with operational procedure OP-24.
            as evidenced by the simulator scenarios, the operators did not consult
In practice,
            OP-24 to determine correction values and there was inadequate time to
as evidenced by the simulator scenarios, the operators did not consult
            perform these calculations.
OP-24 to determine correction values and there was inadequate time to
      3)     Path-2 and Path-3 provided multiple steps for initiating suppression pool
perform these calculations.
            cooling. As demonstrated in the simulator exercises, the operators placed
3)
            suppression pool cooling into operation without working through each of
Path-2 and Path-3 provided multiple steps for initiating suppression pool
            these steps. By contrast, the SP/T path of primary containment control
cooling. As demonstrated in the simulator exercises, the operators placed
            for operating suppression pool cooling provided direction to the operator
suppression pool cooling into operation without working through each of
            using only a single step.
these steps.
                                                3
By contrast, the SP/T path of primary containment control
for operating suppression pool cooling provided direction to the operator
using only a single step.
3


  '
.
'
'
                ,
.
          .
'
.
,
    4)     Path-2 was entered following a reactor scram from a condition where the
.
            reactor mode switch was not in RUN. The power level at this condition is
.
            anticipated to be less than approximately eight percent power. Steps 12,
4)
            13 and 17 of this procedure represented actions for tripping the main
Path-2 was entered following a reactor scram from a condition where the
            turbine, ensuring that turbine auxiliaries started, and tripping the
reactor mode switch was not in RUN. The power level at this condition is
            heater drain pumps. These actions were not appropriate for this power
anticipated to be less than approximately eight percent power.
            level and diverted the operators attention from more important activities.
Steps 12,
    5)     Path-3, step 26, required the operator to set the reactor re irculation
13 and 17 of this procedure represented actions for tripping the main
            pump speed controllers to minimum; however, this step was not required for
turbine, ensuring that turbine auxiliaries started, and tripping the
            the pump logi: involved.
heater drain pumps. These actions were not appropriate for this power
    6)     Radiological Release Control Procedure, steps RR/PB-9 through 11,
level and diverted the operators attention from more important activities.
            identified core cooling systems which -ay be the source of a primary leak;   ,
5)
            however, these systems were not located in the turbine building and were     ;
Path-3, step 26, required the operator to set the reactor re irculation
            therefore not applicable.
pump speed controllers to minimum; however, this step was not required for
    7)     Path-3, steps 61 and 85, and Path-2, steps 61 and 85, provided redundant
the pump logi: involved.
            action steps for RPV pressure control.
6)
    P)     Throughout the E0Ps, there were several examples in which multiple action
Radiological Release Control Procedure, steps RR/PB-9 through 11,
            steps were used to accomplish a single action. For example, in each leg
identified core cooling systems which -ay be the source of a primary leak;
            of the Primary Containment Control Procedure, the generic monitor and
,
            control steps of the PSTG were restated in one step and the specific
however, these systems were not located in the turbine building and were
            direction on how to accomplish the referenced action was provided in the
therefore not applicable.
            subsequent step.   In addition, if a scram was required during the
7)
            performance of the Primary Containment Control Procedure, two action steps
Path-3, steps 61 and 85, and Path-2, steps 61 and 85, provided redundant
            were required. The first stated that a reactor scram was required and the
action steps for RPV pressure control.
            second executed the scram.                                                 ,
P)
                                                                                      l
Throughout the E0Ps, there were several examples in which multiple action
    9)     Path-2, steps 80, 90, 91, 99 and 100, and Path-3, steps 79 through 84,     j
steps were used to accomplish a single action.
            provided detailed steps for the operation of the suppression pool cooling
For example, in each leg
            system which were more appropriate for operational procedures. In           ,
of the Primary Containment Control Procedure, the generic monitor and
            addition, these actions should have been covered in a single action step   !
control steps of the PSTG were restated in one step and the specific
            as accomplished by procedure SP/T-3.                                       .
direction on how to accomplish the referenced action was provided in the
                                                                                      !
subsequent step.
    3.1.2 Licensee Verification and Validation of E0Ps                                 i
In addition, if a scram was required during the
                                                                                        l
performance of the Primary Containment Control Procedure, two action steps
    NUREG-0899, section 3.3.5, indicated that after E0Ps are written they must       i
were required. The first stated that a reactor scram was required and the
    undergo a process of verification and validation. This process was used to       l'
second executed the scram.
    establish the accuracy of information and instructions, to determine that the
,
    procedures could be carried out accurately and efficiently, and to demonstrate   :
l
    that the procedures were adequate to mitigate transients and accidents. Both
9)
    technical and human engineering adequacy were required to be addressed in the
Path-2, steps 80, 90, 91, 99 and 100, and Path-3, steps 79 through 84,
    review process.                                                                   ;
j
                                                                                      i
provided detailed steps for the operation of the suppression pool cooling
    Administrative Instruction AI-95, " Verification and Validation Program for EPG, ;
system which were more appropriate for operational procedures.
    Revision 4, based Emergency Operating Procedures," defined the program for
In
    verification and validation of the E0Ps at BSEP. BSEP administrative
,
    procedures (Volume 1, Book 1, sectic' 5.7.4.1, paragraph A.III.c) required that   ;
addition, these actions should have been covered in a single action step
    all E0P changes receive the review and approval of the E0P Review Committee.     i
as accomplished by procedure SP/T-3.
    The membership of the committee included operations, quality assurance,
.
    technical support, off-site nuclear safet.;, and the licensed training           !
3.1.2 Licensee Verification and Validation of E0Ps
    departments.
i
                                                4                                     !
NUREG-0899, section 3.3.5, indicated that after E0Ps are written they must
                                                                                      !
i
undergo a process of verification and validation. This process was used to
l
establish the accuracy of information and instructions, to determine that the
'
procedures could be carried out accurately and efficiently, and to demonstrate
:
that the procedures were adequate to mitigate transients and accidents.
Both
technical and human engineering adequacy were required to be addressed in the
review process.
;
i
Administrative Instruction AI-95, " Verification and Validation Program for EPG,
;
Revision 4, based Emergency Operating Procedures," defined the program for
verification and validation of the E0Ps at BSEP.
BSEP administrative
procedures (Volume 1, Book 1, sectic' 5.7.4.1, paragraph A.III.c) required that
;
all E0P changes receive the review and approval of the E0P Review Committee.
i
The membership of the committee included operations, quality assurance,
technical support, off-site nuclear safet.;, and the licensed training
!
departments.
4
!
!


                  '
'
  .
.
                              .
.
  4                                                                                                 j
4
                    lhe verification and validation required for implementation of Revision 4AF of
j
                    the BWROG EPGs was identified in an untitled supplement to AI-95. The licensee
lhe verification and validation required for implementation of Revision 4AF of
                    indicated that this methodology was reviewed and approved by the E0P Review
the BWROG EPGs was identified in an untitled supplement to AI-95. The licensee
                    Committee on December 14, 1987. The team was concerned that the specific
indicated that this methodology was reviewed and approved by the E0P Review
                    methodology for the verification and validation of the substantial changes
Committee on December 14, 1987.
                    represented by the incorporation of Revision 4AF of the BWROG EPGs had not been
The team was concerned that the specific
                    specifically identified and approved by the E0P Review Committee. Further
methodology for the verification and validation of the substantial changes
                    licensee action is necessary to ensure that the verification and validation
represented by the incorporation of Revision 4AF of the BWROG EPGs had not been
                    program approved by the E0P Review Comittee is successfully completed prior to
specifically identified and approved by the E0P Review Committee.
                    the implementation of the draft E0Ps.
Further
                    The inspection team's review of the verification and validation program
licensee action is necessary to ensure that the verification and validation
                    determined that a mechanism existed for ensuring that all portions of the E0Ps
program approved by the E0P Review Comittee is successfully completed prior to
                    could be validated using either the plant-specific simulator, plant
the implementation of the draft E0Ps.
The inspection team's review of the verification and validation program
determined that a mechanism existed for ensuring that all portions of the E0Ps
could be validated using either the plant-specific simulator, plant
l
walkthroughs, or desk top reviews. The preferred validation method was to
perform the E0Ps on the plant simulator.
In instances in which the E0P steps
exceeded the capability of the simulator, a combination plant walkthrough and
desk top review was employed.
In order to ensure that the full complement of
E0Ps were validated, a list of functional objectives to be accomplished by
performing the E0P was developed. The licensee defined the functional
objective of each E0P step and developed exercises to satisfy each functional
objective. The exercises were performed on the plant simulator or by some
combination of simulator exercises and plant walkthroughs.
Problems idantified
during the demonstration of the functional objectives were resolved by the E0P
revision process as described in Al-95.
l
The inspection team was concerned that the identified verification and
I
validation methodology did not indicate that appropriate consideration had been
l
l
                    walkthroughs, or desk top reviews. The preferred validation method was to
given to the necessity of performing all steps of the E0Ps on the plant
                    perform the E0Ps on the plant simulator. In instances in which the E0P steps
simulator or in table top exercises rather than evaluating them through plant
                    exceeded the capability of the simulator, a combination plant walkthrough and
walkthroughs. Based on the inability of the simulator to accurately model RPV
                    desk top review was employed. In order to ensure that the full complement of
level and decay heat (previously identified by the licensee and discussed in
                    E0Ps were validated, a list of functional objectives to be accomplished by
Section 3.4.2), it is extremely important to ensure that all steps of the E0Ps
                    performing the E0P was developed. The licensee defined the functional
would be effective in fulfilling the actions intended by the BWROG EPGs.
                    objective of each E0P step and developed exercises to satisfy each functional
Further licensee action is necessary to ensure that all E0P steps are validated
                    objective. The exercises were performed on the plant simulator or by some
on a simulator or by an equally acceptable methodology.
                    combination of simulator exercises and plant walkthroughs. Problems idantified
3.1.3
                    during the demonstration of the functional objectives were resolved by the E0P
E0P Operator Training
                    revision process as described in Al-95.
A review of the licensee's training program was conducted to determine the
l                    The inspection team was concerned that the identified verification and
adequacy of operator training prior to implementation of Revision 4 of the
I                    validation methodology did not indicate that appropriate consideration had been
l                    given to the necessity of performing all steps of the E0Ps on the plant
                    simulator or in table top exercises rather than evaluating them through plant
                    walkthroughs. Based on the inability of the simulator to accurately model RPV
                    level and decay heat (previously identified by the licensee and discussed in
                    Section 3.4.2), it is extremely important to ensure that all steps of the E0Ps
                    would be effective in fulfilling the actions intended by the BWROG EPGs.
                    Further licensee action is necessary to ensure that all E0P steps are validated
                    on a simulator or by an equally acceptable methodology.
                    3.1.3   E0P Operator Training
                    A review of the licensee's training program was conducted to determine the
                    adequacy of operator training prior to implementation of Revision 4 of the
.
.
                    EWP0G EPGs.   The inspection team compared the requirements of NUREG-0899, the
EWP0G EPGs.
The inspection team compared the requirements of NUREG-0899, the
l
Procedures Generation Package (PGP), and the operator training program
l
l
                    Procedures Generation Package (PGP), and the operator training program
developed for Revision 4.
l                    developed for Revision 4.
The PGP contained a detailed description of the initial operator training which
                    The PGP contained a detailed description of the initial operator training which
was conducted prior to the initial implementation of the upgraded E0Ps. The
                    was conducted prior to the initial implementation of the upgraded E0Ps. The
extent of the initial operator training met the requirements of NUREG-0899,
                    extent of the initial operator training met the requirements of NUREG-0899,
section 3.4
                    section 3.4 Although the PGP did not specify the operator training require-
Although the PGP did not specify the operator training require-
                    ments for revisions to the E0Ps, the licensee required all revisions to be
ments for revisions to the E0Ps, the licensee required all revisions to be
                    performed in accordance with Administrative Instruction Al-95, " Verification
performed in accordance with Administrative Instruction Al-95, " Verification
                    and Validation Program for EPG, Revision 4, based Emergency Operating
and Validation Program for EPG, Revision 4, based Emergency Operating
                    Procedures." This procedure required that an E0P Review Comittee review
Procedures." This procedure required that an E0P Review Comittee review
                    proposed E0P revisions and determine the implementation requirements.
proposed E0P revisions and determine the implementation requirements.
                                                                5
5
    ___- _ _ _ _ -
___- _ _ _ _ -


      _____-
_____-
            '
'
  .
.
  '
'
                        .
.
    .
.
              The inspection team was concerned that these instructions contained no guidance
The inspection team was concerned that these instructions contained no guidance
              concerning the scope of operator training required prior to implementation of
concerning the scope of operator training required prior to implementation of
              revisions to the E0Ps. Nevertheless, the licensee developed and incorporated a
revisions to the E0Ps.
              satisfactory training program into the E0P verification and validation process.
Nevertheless, the licensee developed and incorporated a
              This program was outlined in an untitled supplement to AI-95. The licensee
satisfactory training program into the E0P verification and validation process.
              recognized the need for ongoing operator training on the E0Ps and had
This program was outlined in an untitled supplement to AI-95. The licensee
              accomplished this goal with periodic licensed operator retraining and the         ,
recognized the need for ongoing operator training on the E0Ps and had
              Operator Real Time Training Program described in Operating Instruction 01-33.
accomplished this goal with periodic licensed operator retraining and the
              This latter program served to complement the annual operator retraining by
,
              accomplishing immediate training needs on a continuing basis.
Operator Real Time Training Program described in Operating Instruction 01-33.
              Interviews with training supervisors indicated that two of the three phases of
This latter program served to complement the annual operator retraining by
              training had been completed prior to the time of the inspection. Phase IA was
accomplishing immediate training needs on a continuing basis.
              completed in April 1988 and consisted of 24 hours of classroom instruction on     i
Interviews with training supervisors indicated that two of the three phases of
              the content and use of the new E0Ps. Phase IB was completed in June 1988 and       l
training had been completed prior to the time of the inspection. Phase IA was
              consisted of 16 hours of classroom instruction cambined with 20 hours of
completed in April 1988 and consisted of 24 hours of classroom instruction on
              simulator training designed to exercise the major branching points within the
i
              E0P flowcharts.   Phase 11 training was conducted in September 1988 and involved
the content and use of the new E0Ps.
l             four hours of classroom instruction followed by four hours of simulator
Phase IB was completed in June 1988 and
              exercises. This brief session served to update operators on changes made to
l
              the E0Ps since completion of Phase IB training. The final phase of training
consisted of 16 hours of classroom instruction cambined with 20 hours of
              (Phase III) was accomplished in December 1988 and served as the final operator
simulator training designed to exercise the major branching points within the
              training update prior to implementation of the revised E0Ps.
E0P flowcharts.
              3.1.4 Maintenance of E0Ps
Phase 11 training was conducted in September 1988 and involved
              During the review of the PSTGs and the E0Ps, the team determined that the PSTGs   j
l
              and BWROG EPG Appendix C calculations were being maintained up-to-date as a
four hours of classroom instruction followed by four hours of simulator
              basis document ar.d were properly controlled as a plant record by the document
exercises.
              control center. The E0P calculations based on Revision 2 of the BWROG EPGs
This brief session served to update operators on changes made to
              were reviewed and documented in a study entitled ENSA 84-038, "EOP Numerical
the E0Ps since completion of Phase IB training.
              Limits and Graphs," and the PSTG was contained in Operating Instruction 01-37,
The final phase of training
              " Preparation and Review of the Plant Specific Technical Guideline for EPG
(Phase III) was accomplished in December 1988 and served as the final operator
              Revision 2." The E0P calculations based on Revision 4 of the BWROG EPGs were
training update prior to implementation of the revised E0Ps.
              under review by the Nuclear Engineering Department and were scheduled to be
3.1.4 Maintenance of E0Ps
              published and the PSTG documented in a similar manner.
During the review of the PSTGs and the E0Ps, the team determined that the PSTGs
              3.1.5 Quality Assurance Involvement in PSTG Maintenance
j
              NUREG-0899, section 4.4, indicated that as a primary basis of the E0Ps, the
and BWROG EPG Appendix C calculations were being maintained up-to-date as a
              PS1Gs should be subject to examination under the plants' overall quality
basis document ar.d were properly controlled as a plant record by the document
              assurance (QA) program. Because the licensee was responsible for ensuring that
control center.
              the PSTGs were accurate and up-to-date, the review and control of the PSTGs
The E0P calculations based on Revision 2 of the BWROG EPGs
              shculd be included in the established QA program.
were reviewed and documented in a study entitled ENSA 84-038, "EOP Numerical
              The licensee indicated that QA surveillance 86-067 was performed in December
Limits and Graphs," and the PSTG was contained in Operating Instruction 01-37,
              1986 as a result of E0P development deficiencies identified by the NRC in IE
" Preparation and Review of the Plant Specific Technical Guideline for EPG
              Information Notice (IEN) 86-64. In addition, QA Audit QAA/0021-88-05, was
Revision 2."
              performed in August 1988 on Revision 4 of the E0Ps and identified one follow-up
The E0P calculations based on Revision 4 of the BWROG EPGs were
              item concerning justification 'of BWROG EPG deviations. Future audit schedules
under review by the Nuclear Engineering Department and were scheduled to be
              included a site QA surveillance, similar in scope to surveillance 86-067,
published and the PSTG documented in a similar manner.
              scheduled for the first quarter of 1989 and annually thereafter.
3.1.5 Quality Assurance Involvement in PSTG Maintenance
                                                      6
NUREG-0899, section 4.4, indicated that as a primary basis of the E0Ps, the
                                                                                _     ___ _ -   -
PS1Gs should be subject to examination under the plants' overall quality
assurance (QA) program.
Because the licensee was responsible for ensuring that
the PSTGs were accurate and up-to-date, the review and control of the PSTGs
shculd be included in the established QA program.
The licensee indicated that QA surveillance 86-067 was performed in December
1986 as a result of E0P development deficiencies identified by the NRC in IE
Information Notice (IEN) 86-64.
In addition, QA Audit QAA/0021-88-05, was
performed in August 1988 on Revision 4 of the E0Ps and identified one follow-up
item concerning justification 'of BWROG EPG deviations.
Future audit schedules
included a site QA surveillance, similar in scope to surveillance 86-067,
scheduled for the first quarter of 1989 and annually thereafter.
6
_
___ _
-
-


                                                                                          _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _
  '
.
'
'
              .
.
        .
'
.
.
    3.1.6 Licensee Response to IE Information Notice 86-64
.
    IEN 86-64 was issued on August 14, 1986, followed by IEN 86-64, Supplement 1,
.
    issued on April 20, 1987. IEN 86-64 alerted the licensee to problems found in
3.1.6 Licensee Response to IE Information Notice 86-64
    review and audits of Procedure Generation Packages (PGPs) and E0Ps. The IEN
IEN 86-64 was issued on August 14, 1986, followed by IEN 86-64, Supplement 1,
    indicated that many utilities had not appropriately developed or implemented
issued on April 20, 1987.
    upgraded E0Ps.   In addition, the IEN identified deficiencies in the development
IEN 86-64 alerted the licensee to problems found in
    and implementation of each of the four major aspects of the upgrade program.
review and audits of Procedure Generation Packages (PGPs) and E0Ps. The IEN
    These deficiencies included undocumented deviations from and inappropriate
indicated that many utilities had not appropriately developed or implemented
    adaptation of BWROG EPGs, failure to adhere to the PSWG and the verification
upgraded E0Ps.
    and validation programs, and deficient training programs. Supplement 1 to IEN
In addition, the IEN identified deficiencies in the development
    86-64 alerted the licensee's to significant problems that were continuing with
and implementation of each of the four major aspects of the upgrade program.
    plant E0Ps. Deficiencies were identified in all the major aspects of the E0P
These deficiencies included undocumented deviations from and inappropriate
    upgrade program. The licensee's were requested to review the information for
adaptation of BWROG EPGs, failure to adhere to the PSWG and the verification
    applicability to their facility and consider actions to correct or preclude
and validation programs, and deficient training programs.
    similar problems from occurring.
Supplement 1 to IEN
    The licensee's evaluation process for IENs was performed in accordance with
86-64 alerted the licensee's to significant problems that were continuing with
    Corporate huclear Safety Instruction CNSI-I and On-Site Nuclear Safety
plant E0Ps. Deficiencies were identified in all the major aspects of the E0P
    Instruction ONSI-1. The IENs were reviewed by the nuclear safety coordinator                                               ,
upgrade program.
    and assigned to responsible engineers for evaluation. IEN 86-64 and Supplement                                           l
The licensee's were requested to review the information for
    1 were evaluated by the coordinator and closed because a OA surveillance,
applicability to their facility and consider actions to correct or preclude
                                                                                                                                '
similar problems from occurring.
    discussed in Section 3.1.5, had already been initiated and had identified
The licensee's evaluation process for IENs was performed in accordance with
    similar deficiencies. The inspection team concluded that the licensee's                                                   i
Corporate huclear Safety Instruction CNSI-I and On-Site Nuclear Safety
    actions in response to IEN 86-64 were satisfactory.                                                                       l
Instruction ONSI-1.
                                                                                                                              .
The IENs were reviewed by the nuclear safety coordinator
    3.2 E0P Procedure Verification
,
    This portion of the inspection was performed to determine whether the E0Ps had
and assigned to responsible engineers for evaluation.
    been prepared in accordance with the BWROG EPGs, the PSTGs, and the PGP.                                                 l
IEN 86-64 and Supplement
    The inspection ccmpared Revision 4AF of the BWR0G EPGs to the PSTGs, and the
1 were evaluated by the coordinator and closed because a OA surveillance,
    PSTGs to the E0Ps. All differences were evaluated to ensure that safety
'
    significant deviations were identified and that a documented basis existed for
discussed in Section 3.1.5, had already been initiated and had identified
    all deviations. A review of selected calculations was performed to ensure that
similar deficiencies. The inspection team concluded that the licensee's
    plant-specific values utilized in the E0Ps were correct and had been performed
actions in response to IEN 86-64 were satisfactory.
    in accordance with a documented engineering analysis. Appendix B of this
.
    report lists the procedures reviewed.
3.2 E0P Procedure Verification
    3.2.I   FPG/PSTG Comparison
This portion of the inspection was performed to determine whether the E0Ps had
    Nine differences were identified between the BWROG EPGs and the PSTGs as
been prepared in accordance with the BWROG EPGs, the PSTGs, and the PGP.
    detailed below. Based on these discrepancies, the inspection team concluded
l
    that the draft PSTGs did not accurately incorporate the guidance of Revision
The inspection ccmpared Revision 4AF of the BWR0G EPGs to the PSTGs, and the
    4AF of the BWROG EPGs. The inspection team identified technical concerns
PSTGs to the E0Ps.
    relating to the measurement of RPV water level, which adversely affected the                                             I
All differences were evaluated to ensure that safety
    operator's ability to perform the level / power control procedure, and technical                                         I
significant deviations were identified and that a documented basis existed for
    concerns relating to the measurement of primary containment drywell temperature,
all deviations. A review of selected calculations was performed to ensure that
    which potentially raasked a valid entry condition. These concerns affected both
plant-specific values utilized in the E0Ps were correct and had been performed
    the E0Ps which were currently implemented at the facility (Revision 2) and the
in accordance with a documented engineering analysis. Appendix B of this
    draft E0Ps. In addition, numerous discrepancies were identified in the draft                                             i
report lists the procedures reviewed.
                                                                                                                              '
3.2.I
    E0Ps in which the entry conditions of the PWROG EPGs were changed without
FPG/PSTG Comparison
    sufficient technical justification.     Further licensee action is necessary to                                         l
Nine differences were identified between the BWROG EPGs and the PSTGs as
    evaluate and correct the E0Ps presently in use and to ensure that the draft                                             !
detailed below.
    E0Ps accurately incorporate the technical guidance of the BWROG EPGs.
Based on these discrepancies, the inspection team concluded
                                              7
that the draft PSTGs did not accurately incorporate the guidance of Revision
                                                                                      . _ _ - - _ _ _ _                 ___
4AF of the BWROG EPGs. The inspection team identified technical concerns
relating to the measurement of RPV water level, which adversely affected the
I
operator's ability to perform the level / power control procedure, and technical
I
concerns relating to the measurement of primary containment drywell temperature,
which potentially raasked a valid entry condition.
These concerns affected both
the E0Ps which were currently implemented at the facility (Revision 2) and the
draft E0Ps.
In addition, numerous discrepancies were identified in the draft
i
'
E0Ps in which the entry conditions of the PWROG EPGs were changed without
sufficient technical justification.
Further licensee action is necessary to
l
evaluate and correct the E0Ps presently in use and to ensure that the draft
!
E0Ps accurately incorporate the technical guidance of the BWROG EPGs.
7
. _ _ - - _ _ _ _
___


                                              _
_
                                                                                    ,
,
  '
'
.
.
            S
S
      -
-
.
.
                                                                                      l
1)
    1)   BWROG EPG Contingency No. 7 provided a methodology to control reactor
BWROG EPG Contingency No. 7 provided a methodology to control reactor
        power following an anticipated transient without scram (ATWS). This
power following an anticipated transient without scram (ATWS).
        methodology involved lowering the RPV water level to the top of active
This
        fuel (TAF) or to the minimum steam cooling water level (MSCWL). The
methodology involved lowering the RPV water level to the top of active
        licensee implemented these actions in the Level / Power Control Procedure.
fuel (TAF) or to the minimum steam cooling water level (MSCWL).
        BWROG EPG Caution ho. 1 provided operator precautions related to the
The
        nieasurement of RPV water level and the accuracy of various water level
licensee implemented these actions in the Level / Power Control Procedure.
        instruments. The licensee implemented these precautions in Caution No. 1
BWROG EPG Caution ho. 1 provided operator precautions related to the
        of the User's Guide. The inspection team reviewed the methodology and
nieasurement of RPV water level and the accuracy of various water level
        precautions for ATWS power level control implemented by the licensee and
instruments. The licensee implemented these precautions in Caution No. 1
        identified several undocumented and unjustified deviations which adversely
of the User's Guide. The inspection team reviewed the methodology and
        affected the ability of the operators to control reactor power.     These
precautions for ATWS power level control implemented by the licensee and
        deviations involved (1) the equivalency between the instrument zero           i
identified several undocumented and unjustified deviations which adversely
        indication and the TAF, (2) the restrictions on the use of the wide range     l
affected the ability of the operators to control reactor power.
        level instruments, and (3) the calibration of the fuel zone level
These
        instrument. These conditions, detailed in the following paragraphs,
deviations involved (1) the equivalency between the instrument zero
        affected the E0Ps which were presently in use at the facility.
indication and the TAF, (2) the restrictions on the use of the wide range
        a)   Instrument Zero - Based on the location of the instrument taps, the     i
level instruments, and (3) the calibration of the fuel zone level
              wide range level instruments (N0-26A and NO-26B) indicate 0 inches
instrument.
              when the actual RPV water level is +8.44 inches above the top of
These conditions, detailed in the following paragraphs,
              active fuel (TAF). In an attempt to simplify the E0Ps, the licensee     ,
affected the E0Ps which were presently in use at the facility.
              used this instrument zero indication as the TAF; however, the           I
a)
              licensee did not document this deviation from the BWROG EPGs and did
Instrument Zero - Based on the location of the instrument taps, the
              not evaluate the difference to ensure that there were no adverse
wide range level instruments (N0-26A and NO-26B) indicate 0 inches
              effects on the Level / Power Control Procedure. This deviation was
when the actual RPV water level is +8.44 inches above the top of
              significant because water levels higher than the TAF result in higher
active fuel (TAF).
              reactor power levels during an ATWS condition. Higher power levels
In an attempt to simplify the E0Ps, the licensee
              increase the amount of energy deposited in the primary containment
,
              and reduce the time until primary containment venting is t equired.
used this instrument zero indication as the TAF; however, the
              In addition, a larger primary containment vent path may bt. required
licensee did not document this deviation from the BWROG EPGs and did
              to remove this excess energy. The inspection team also noted that
not evaluate the difference to ensure that there were no adverse
              this condition affected the E0Ps which were presently in use at the
effects on the Level / Power Control Procedure. This deviation was
              facility.   Further licensee action is necessary to ensure that the
significant because water levels higher than the TAF result in higher
              higher power levels resulting from this deviation are technically
reactor power levels during an ATWS condition.
              acceptable and appropriately documented for the approved and draft
Higher power levels
              E0Ps.
increase the amount of energy deposited in the primary containment
        b)   Wide Range Level Instrument Restrictions - Caution No. 1 in the
and reduce the time until primary containment venting is t equired.
              User's Guide restricted the use of the wide range level instruments
In addition, a larger primary containment vent path may bt. required
              (N0-26A and NO-268) as a function of level. The caution required
to remove this excess energy. The inspection team also noted that
              that the instruments not be used when the indicated water level was
this condition affected the E0Ps which were presently in use at the
              below +10 inches (i.e., +18.44 inches actual) on both Units 1 and 2.
facility.
              In addition, the caution precluded use of the Unit 2 instruments when
Further licensee action is necessary to ensure that the
              the water level was below +40 inches (i.e., +48.44 inches actual)
higher power levels resulting from this deviation are technically
              when conditions indicative of a high energy line break (HELB) were
acceptable and appropriately documented for the approved and draft
              present. These restrictions were based upon the location of the
E0Ps.
              reference le.gs of the wide range instruments and the lack of
b)
              temperature compensation methods in the E0Ps.     The +40 inch
Wide Range Level Instrument Restrictions - Caution No. 1 in the
              precaution was not applicable on Unit 1 because the reference legs
User's Guide restricted the use of the wide range level instruments
              were in a different location.
(N0-26A and NO-268) as a function of level. The caution required
              The licensee had not developed a method to compensate the level
that the instruments not be used when the indicated water level was
              instruments when indication was below +10 inches and did not have a
below +10 inches (i.e., +18.44 inches actual) on both Units 1 and 2.
                                            8
In addition, the caution precluded use of the Unit 2 instruments when
the water level was below +40 inches (i.e., +48.44 inches actual)
when conditions indicative of a high energy line break (HELB) were
present.
These restrictions were based upon the location of the
reference le.gs of the wide range instruments and the lack of
temperature compensation methods in the E0Ps.
The +40 inch
precaution was not applicable on Unit 1 because the reference legs
were in a different location.
The licensee had not developed a method to compensate the level
instruments when indication was below +10 inches and did not have a
8


    '
'
  .
.
  '
'
            .
.
      +
+
  .
.
              method to compensate the instruments during a HELB because
method to compensate the instruments during a HELB because
              temperature instruments were not installed in the secondary
temperature instruments were not installed in the secondary
              containment. The level instrument restrictions adversely affected
containment. The level instrument restrictions adversely affected
              the performance of the Level / Power Control Procedure because the
the performance of the Level / Power Control Procedure because the
              operators did not have an accurate level instrument with which to
operators did not have an accurate level instrument with which to
              control the RPV level below an actual level of +18.44 inches or
control the RPV level below an actual level of +18.44 inches or
              +48.44 inches. This potentially degraded the control of reactor
+48.44 inches. This potentially degraded the control of reactor
              power during an ATWS condition and, as such, was an undocumented and
power during an ATWS condition and, as such, was an undocumented and
              unjustified deviation from the BWROG EPGs. The inspection team also
unjustified deviation from the BWROG EPGs. The inspection team also
              noted that these conditions affected the E0Ps which were presently in
noted that these conditions affected the E0Ps which were presently in
              use at the facility.     Further licensee action is necessary to
use at the facility.
              evaluate this deviation from the BWR0G EPGs and to provide an
Further licensee action is necessary to
              accurate method to control reactor power by means of water level
evaluate this deviation from the BWR0G EPGs and to provide an
              during the ATWS condition for the approved and draft E0Ps.
accurate method to control reactor power by means of water level
        c)   Fuel Zone Level Instruments Calibration - The fuel zone level
during the ATWS condition for the approved and draft E0Ps.
              instruments (N0-36 and NO-37) were calibrated under cold conditions
c)
              of 212 degrees F in the reactor building and the drywell, and 0 psig
Fuel Zone Level Instruments Calibration - The fuel zone level
              in the RPV. Under cold conditions, these instruments normally
instruments (N0-36 and NO-37) were calibrated under cold conditions
              indicate accurately from -150 to +150 inches. However, this cold
of 212 degrees F in the reactor building and the drywell, and 0 psig
              calibration resulted in a wide variance in actual versus indicated
in the RPV. Under cold conditions, these instruments normally
              level for the drywell temperatures, RPV pressure, and reactor
indicate accurately from -150 to +150 inches. However, this cold
              building temperature anticipated during an ATWS. Because no
calibration resulted in a wide variance in actual versus indicated
              compensation method was available to the operators, the fuel zone
level for the drywell temperatures, RPV pressure, and reactor
              instruments would be grossly inaccurate under the conditions in which
building temperature anticipated during an ATWS.
              they will be required to be used. The following level deviations
Because no
              would result if the fuel zone indicators were used at 1100 psig
compensation method was available to the operators, the fuel zone
              during ATWS conditions in accordance with the Level / Power Control
instruments would be grossly inaccurate under the conditions in which
              Procedure. With actual RPV water level at the actual TAF (i.e.,
they will be required to be used.
              -8.44" indicated on the wide range instruments), RPV pressure,
The following level deviations
              reactor building temperature at 200 degrees F, and drywell
would result if the fuel zone indicators were used at 1100 psig
              temperature in the area of the reference legs as indicated below, the
during ATWS conditions in accordance with the Level / Power Control
              fuel zone instruments would indicate the following levels.
Procedure. With actual RPV water level at the actual TAF (i.e.,
                          Drywell Temperature       Indicated Level
-8.44" indicated on the wide range instruments), RPV pressure,
l                             (degrees F)               (inches)
reactor building temperature at 200 degrees F, and drywell
temperature in the area of the reference legs as indicated below, the
fuel zone instruments would indicate the following levels.
Drywell Temperature
Indicated Level
l
(degrees F)
(inches)
1
1
                                  180                       a,09
180
l                                 200                     -61.45
a,09
                                  250                       57.06
l
                                  300                     -51.94
200
                                  400                     -39.60
-61.45
                                  500                     -23.24
250
              Since both units precluded the use of the wide range level
57.06
              instruments below an indication of +10 inches, the fuel zone
300
              indicators would be indicating approximately -42 inches below TAF at
-51.94
              the time when they became the only level indicators available.
400
              The inspection team also noted that the E0Ps and associated cautions
-39.60
              did not preclude the use of the fuel zone instruments in preference
500
              to the wide range instruments for water level control. If the wide
-23.24
              range instruments were not available, the operators were required to
Since both units precluded the use of the wide range level
:            use the fuel zone instruments to control RPV water level. Under
instruments below an indication of +10 inches, the fuel zone
indicators would be indicating approximately -42 inches below TAF at
the time when they became the only level indicators available.
The inspection team also noted that the E0Ps and associated cautions
did not preclude the use of the fuel zone instruments in preference
to the wide range instruments for water level control.
If the wide
range instruments were not available, the operators were required to
use the fuel zone instruments to control RPV water level. Under
:
I
I
                                            9
9
                                                                        _ - _ _ _ _ -
_ - _
_ _ _ -


                                                                                                                                                                        1
1
                                *                                                                                                                                       j
j
          a
*
          '
a
                                                                              .
'
                                                        -
.
            .
-
                                                                                    these conditions, and in the absence of compensation techniques, the
.
                                                                                    operators would control RPV water level to an indicativa of TAF
these conditions, and in the absence of compensation techniques, the
                                                                                      (i.e., an indication of 0 inches on the fuel zone instruments),
operators would control RPV water level to an indicativa of TAF
                                                                                    which would correspond to an actual RPV water level of approximately
(i.e., an indication of 0 inches on the fuel zone instruments),
                                                                                    +60 inches. Control of reactor power during an ATWS would not be
which would correspond to an actual RPV water level of approximately
                                                                                    effective at these elevated levels.
+60 inches. Control of reactor power during an ATWS would not be
                                                                                    The licensee's failure to provide a method of compensating the fuel
effective at these elevated levels.
                                                                                    zone instruments for use in conditions other than their calibration
The licensee's failure to provide a method of compensating the fuel
                                                                                    condition effectively prevented their use and had the potential to
zone instruments for use in conditions other than their calibration
                                                                                    adversely affect the performance of the Level / Power Control
condition effectively prevented their use and had the potential to
                                                                                    Procedure. This was a significant deviation from the BWROG EPGs
adversely affect the performance of the Level / Power Control
                                                                                    which was not documented or justified. The inspection team also
Procedure.
                                                                                    noted that this condition affected the E0Ps which were presently in
This was a significant deviation from the BWROG EPGs
                                                                                    use at the facility. Further licensee action is necessary to provide
which was not documented or justified.
                                                                                    an effective method of controlling water level under the conditions
The inspection team also
                                                                                    when use of the Level / Power Control Procedure is anticipated.
noted that this condition affected the E0Ps which were presently in
                                          2)                   The BWROG EPG drywell temperature entry condition was established at the
use at the facility.
                                                              drywell technical. specification (TS) limiting condition for operation
Further licensee action is necessary to provide
                                                                (LCO) or the maximum normal operating temperature, whichever was higher.
an effective method of controlling water level under the conditions
                                                              The PSTG entry condition was set at the primary containment volumetric
when use of the Level / Power Control Procedure is anticipated.
                                                              average temperature LC0 of 135 degrees. The BSEP TS did not contain a LC0
2)
                                                              for drywell temperature. The PSTG justified this deviation based on the
The BWROG EPG drywell temperature entry condition was established at the
                                                              assuinption that the values for drywell temperature LC0 and primary
drywell technical. specification (TS) limiting condition for operation
                                                              containment temperature LC0 were equivalent even though the primary
(LCO) or the maximum normal operating temperature, whichever was higher.
                                                              containment volumetric average included the suppression pool air space in
The PSTG entry condition was set at the primary containment volumetric
                                                              addition to the drywell airspace. Because the suppression pool air space
average temperature LC0 of 135 degrees. The BSEP TS did not contain a LC0
                                                              contributed 43 percent to the volumetric average of the primary contain-
for drywell temperature.
                                                              ment, the potential existed for the relatively cool suppression pool air
The PSTG justified this deviation based on the
                                                              temperature to mask a high temperature in the drywell. In addition, the
assuinption that the values for drywell temperature LC0 and primary
                                                              PSTG justification indicated that the normal maximum operating temperature
containment temperature LC0 were equivalent even though the primary
                                                              was lower than 135 degrees; however, there were times throughout the year
containment volumetric average included the suppression pool air space in
                                                              when the maximum operating temperature exceeded 135 degrees.                       The inssec-
addition to the drywell airspace.
                                                                tion team determined that this deficiency also affected the E0Ps whici
Because the suppression pool air space
                                                              were presently in use at the facility.                     Further licensee action is
contributed 43 percent to the volumetric average of the primary contain-
                                                              necessary to correct this operational concern.
ment, the potential existed for the relatively cool suppression pool air
                                          3)                   The BWROG EPG entry conditions for the RPV control guideline were: (1) RPV
temperature to mask a high temperature in the drywell.
                                                              water level at the low level scram setpoint, (2) RPV pressure above the
In addition, the
                                                                scram setpoint, (3) drywell pressure above the scram setpoint, and (4)
PSTG justification indicated that the normal maximum operating temperature
                                                                reactor power above the average power range monitor (APRM) down scale trip
was lower than 135 degrees; however, there were times throughout the year
                                                                for any scram. The entry conditions in the PSTG deviated from the BWROG
when the maximum operating temperature exceeded 135 degrees.
                                                                EPCs in that the PSTG entry condition was any plant condition requiring or
The inssec-
                                                              causing a scram.                     The PSTG justification stated that this conservative
tion team determined that this deficiency also affected the E0Ps whici
                                                              approach permitted execution of any of five scram recovery paths which
were presently in use at the facility.
                                                              would lead the operator to the End Path Procedure where the entry
Further licensee action is
                                                              conditions of the BWR0G EPG would be assessed.
necessary to correct this operational concern.
                                                                The inspection team was concerned that this methodology delayed essential
3)
                                                              operator actions. The potential existed for plant parameters indicative
The BWROG EPG entry conditions for the RPV control guideline were: (1) RPV
                                                                of an emergency (i.e., the BWROG EPG entry conditions), to remain
water level at the low level scram setpoint, (2) RPV pressure above the
                                                                unmonitored and therefore uncontrolled pending completion of the post-trip
scram setpoint, (3) drywell pressure above the scram setpoint, and (4)
                                                                actions. These post-trip actions were event-based and are normally
reactor power above the average power range monitor (APRM) down scale trip
                                                                                                                    10
for any scram.
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _                                                     _       _         _ _ _ _ .
The entry conditions in the PSTG deviated from the BWROG
                                                                                                                                                                        ,
EPCs in that the PSTG entry condition was any plant condition requiring or
causing a scram.
The PSTG justification stated that this conservative
approach permitted execution of any of five scram recovery paths which
would lead the operator to the End Path Procedure where the entry
conditions of the BWR0G EPG would be assessed.
The inspection team was concerned that this methodology delayed essential
operator actions. The potential existed for plant parameters indicative
of an emergency (i.e., the BWROG EPG entry conditions), to remain
unmonitored and therefore uncontrolled pending completion of the post-trip
actions. These post-trip actions were event-based and are normally
10
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_
_
_ _ _ _ .
,


  '
'
o
o
.
.
                                                                                              4
4
        -
-
.
.
          controlled as immediate, memorized actions' of the control room operators.
controlled as immediate, memorized actions' of the control room operators.
          As discussed in Section 3.1.1, the inspection team was concerned that the
As discussed in Section 3.1.1, the inspection team was concerned that the
          inclusion of these post-trip recovery actions into the E0Ps delayed the
inclusion of these post-trip recovery actions into the E0Ps delayed the
          accomplishment of the directed actions of the BWROG EPGs, had the
accomplishment of the directed actions of the BWROG EPGs, had the
          potential to result in incorrect event diagnosis, and affected the ability
potential to result in incorrect event diagnosis, and affected the ability
          of the operators to implement the E0Ps and thereby respond.to the                   i
of the operators to implement the E0Ps and thereby respond.to the
          emergency in a timely manner. The licensee's method of satisfying the               1
i
          BWROG EPG entry conditions and including event-based actions in the E0Ps           I
emergency in a timely manner. The licensee's method of satisfying the
          was a significant deviation from the BWROG EPGs and had the potential to
1
          adversely affect the satisfactory performance of the E0Ps.
BWROG EPG entry conditions and including event-based actions in the E0Ps
    4)   The BWROG EPG entry condition for drywell pressure was the high drywell
was a significant deviation from the BWROG EPGs and had the potential to
          pressure scram setpoint. The PSTG entry condition for drywell pressure
adversely affect the satisfactory performance of the E0Ps.
          was established at the maximum pressure allowed by the plant technical
4)
          specifications of 2.0 psig, while the actual scram setpoint was 1.83 psig
The BWROG EPG entry condition for drywell pressure was the high drywell
          +/- 0.076 psig. This deviation was not justified and was potentially
pressure scram setpoint. The PSTG entry condition for drywell pressure
          significant because a scram could occur at a high drywell pressure before
was established at the maximum pressure allowed by the plant technical
          the Primary Containment Control Procedure entry conditions were satisfied.
specifications of 2.0 psig, while the actual scram setpoint was 1.83 psig
    5)   The BWROG EPG entry condition for the Radiological Release Control-
+/- 0.076 psig. This deviation was not justified and was potentially
          Procedure was limited to an ALERT condition from a radioactivity release
significant because a scram could occur at a high drywell pressure before
          off-site. The PSTG entry conditions were more conservative than the BWROG
the Primary Containment Control Procedure entry conditions were satisfied.
          EPG entry conditions because the entr
5)
          abnormal operating procedures (A0Fs)  were yincorporated
The BWROG EPG entry condition for the Radiological Release Control-
                                                        conditions into
Procedure was limited to an ALERT condition from a radioactivity release
                                                                    andthe
off-site. The PSTG entry conditions were more conservative than the BWROG
                                                                        actions
abnormal operating procedures (A0Fs) y conditions and actions for several
                                                                            PSTG.forAsseveral
EPG entry conditions because the entr
          discussed in Section 3.1.1, these additional actions diverted the
were incorporated into the PSTG. As
          attention of the shift foreman during the simulator demonstration and
discussed in Section 3.1.1, these additional actions diverted the
          increased the complexity of the E0Ps.
attention of the shift foreman during the simulator demonstration and
    6)   BWROG EPG, step C6-3, vented the RPV to permit flooding of primary
increased the complexity of the E0Ps.
          containment with a flow path through the RPV. The specified vent paths
6)
          prevented pressurizing the primary containment during the Primary
BWROG EPG, step C6-3, vented the RPV to permit flooding of primary
          Containment Flooding Procedure. PSTG, step C6-2, improperly listed the
containment with a flow path through the RPV.
          reactor head vent valves which vented to the floor of the primary
The specified vent paths
          containment drywell. The vent lines did not accomplish the intent of the
prevented pressurizing the primary containment during the Primary
          BWROG EPGs because they were only 1/4 inch in diameter and were directed
Containment Flooding Procedure.
          inside primary containment. The same problem was noted at step C.7.a of
PSTG, step C6-2, improperly listed the
          the Primary Containment Flooding Procedure.
reactor head vent valves which vented to the floor of the primary
    7)   The BWR0G EPG entry condition for primary containment hydrogen
containment drywell. The vent lines did not accomplish the intent of the
          concentration was the high alarm setpoint for hydrogen concentration
BWROG EPGs because they were only 1/4 inch in diameter and were directed
          (i.e., 2 percent). The PSTG entry condition was set at the minimum
inside primary containment. The same problem was noted at step C.7.a of
          detectable hydrogen concentration of 1 percent. This value was
the Primary Containment Flooding Procedure.
          conservative with respect to the alarm, but relied on the operators to
7)
          monitor the concentration in order to identify the entry condition.
The BWR0G EPG entry condition for primary containment hydrogen
          During an emergency this entry condition could be missed and could
concentration was the high alarm setpoint for hydrogen concentration
          potentially delay the operator actions required to mitigate the emergency.
(i.e., 2 percent). The PSTG entry condition was set at the minimum
    8)   BWROG EPG, step C2-1.4, performed an emergency depressurization of the RPV
detectable hydrogen concentration of 1 percent.
          with other steam-driven equipment if the proper number of safety relief
This value was
          valves (SRVs) could not be opened. The PSTG did not reference equipment,
conservative with respect to the alarm, but relied on the operators to
          such as the reactor feed pump turbines and steam jet air ejectors which
monitor the concentration in order to identify the entry condition.
          were also available at BSEP as additional steam loads capable of reducing
During an emergency this entry condition could be missed and could
          RPV pressure.
potentially delay the operator actions required to mitigate the emergency.
                                              11
8)
BWROG EPG, step C2-1.4, performed an emergency depressurization of the RPV
with other steam-driven equipment if the proper number of safety relief
valves (SRVs) could not be opened. The PSTG did not reference equipment,
such as the reactor feed pump turbines and steam jet air ejectors which
were also available at BSEP as additional steam loads capable of reducing
RPV pressure.
11


                                                                                                            -
-
    '
'
  .
.
  '
'
                .
.
          *
*
  .
.
      9)   BWROG EPG, step RC-1, required a manual scran of the reactor if a reactor
9)
            scram has not been already initiated. The corresponding PSTG step
BWROG EPG, step RC-1, required a manual scran of the reactor if a reactor
            deviated from the BWROG EPGs by deleting this conditional action. In the
scram has not been already initiated.
            justification for the deviation, the licensee indicated that the
The corresponding PSTG step
            conditional statement was deleted because the flowcharts were entered for
deviated from the BWROG EPGs by deleting this conditional action.
            the initial scram and were not re-entered for any subsequent scrams. The
In the
            inspection team was concerned that re-entry into the flowcharts would be
justification for the deviation, the licensee indicated that the
            required if plant conditions changed and a new entry condition occurred.
conditional statement was deleted because the flowcharts were entered for
!           Under these conditions, re-insertion of a scram signal was undesirable and
the initial scram and were not re-entered for any subsequent scrams.
            could adversely affect ongoing recovery actions such as alternate rod
The
            insertion techniques.                                                                             l
inspection team was concerned that re-entry into the flowcharts would be
      3.2.2 PSTG/EOP Comparison
required if plant conditions changed and a new entry condition occurred.
      Four differences were identified in which the PSTGs steps were not accurately
!
      incorporated into the E0Ps and were therefore unjustified deviations from the
Under these conditions, re-insertion of a scram signal was undesirable and
      BWROG EPGs.     Further licensee action is necessary to accurately incorporate
could adversely affect ongoing recovery actions such as alternate rod
      these PSTG steps.
insertion techniques.
      1)   Paths 1, 2, 3, 4, and 5 included conditional action steps which precluded
l
            the use of the feedwater system in the event of high condensate
3.2.2 PSTG/EOP Comparison
            conductivity. These actions were not included in either the BWROG EPGs or
Four differences were identified in which the PSTGs steps were not accurately
            the PSTGs. The effect of these steps was to prevent the use of an
incorporated into the E0Ps and were therefore unjustified deviations from the
            available high pressure injection system during a low RPV water level
BWROG EPGs.
            emergency.     In addition, Path 5 failed to consider the use of the
Further licensee action is necessary to accurately incorporate
            feedwater system as a high pressure injection source until after the high
these PSTG steps.
            pressurecoreinjection(HPCI)andreactorcoreisolationcooling(RCIC)
1)
            systems were attempted. The SWROG EPGs assumed that the feedwater system
Paths 1, 2, 3, 4, and 5 included conditional action steps which precluded
            would be the first and primary method of level restoration, regardless of
the use of the feedwater system in the event of high condensate
            the condensate conductivity, until after the RPV water level emergency was
conductivity.
            controlled. The prerequisites for use of the feedwater system and the
These actions were not included in either the BWROG EPGs or
            failure to attempt its use are considered to be significant deviations
the PSTGs. The effect of these steps was to prevent the use of an
            from the BWROG EPGs.
available high pressure injection system during a low RPV water level
      2)   PSTG, step RC/P-2, contained a conditional action step which placed the
emergency.
            control switch for each SRV in the CLOSE or AUTO position if the
In addition, Path 5 failed to consider the use of the
            continuous SRV pneumatic supply became unavailable. The intent was to
feedwater system as a high pressure injection source until after the high
            reserve operating air for subsequent necessary cycles of the SRVs. PSTG,
pressurecoreinjection(HPCI)andreactorcoreisolationcooling(RCIC)
            step RC/P-3, required emergency RPV depressurization with sustained
systems were attempted. The SWROG EPGs assumed that the feedwater system
            opening of the SRVs if one or more SRVs were being used to depressurize
would be the first and primary method of level restoration, regardless of
            the RPV and the continuous SRV pneumatic supply became unavailable. The
the condensate conductivity, until after the RPV water level emergency was
            intent was to continue the cooldown by leaving the appropriate valves open
controlled. The prerequisites for use of the feedwater system and the
            continuously to maintain the proper cooldown rate. However, the E0Ps in
failure to attempt its use are considered to be significant deviations
            End Path Procedure, step 76, required using the SRVs for RPV pressure
from the BWROG EPGs.
            control only when a continuous pneumatic supply was available to the SRVs.
2)
            This was a deviation from the BWROG EPGs, in that sustained opening of the
PSTG, step RC/P-2, contained a conditional action step which placed the
            SRVs was not attempted before operating pressure of the emergency
control switch for each SRV in the CLOSE or AUTO position if the
            depressurization system was no longer available.
continuous SRV pneumatic supply became unavailable. The intent was to
      3)   PSTG, step DW/T-1, directed the operators to operate all available drywell
reserve operating air for subsequent necessary cycles of the SRVs.
            cooling, defeating isolation interlocks if necessary. However, the
PSTG,
            Primary Containment Control Procedure, step DW/T6, prohibited operation of
step RC/P-3, required emergency RPV depressurization with sustained
            the drywell coolers if drywell pressure was above 2.0 psig. The licensee
opening of the SRVs if one or more SRVs were being used to depressurize
              indicated that the operation of the drywell coolers was prohibited at 2.0
the RPV and the continuous SRV pneumatic supply became unavailable. The
                                                  12
intent was to continue the cooldown by leaving the appropriate valves open
                                                                      _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -
continuously to maintain the proper cooldown rate.
However, the E0Ps in
End Path Procedure, step 76, required using the SRVs for RPV pressure
control only when a continuous pneumatic supply was available to the SRVs.
This was a deviation from the BWROG EPGs, in that sustained opening of the
SRVs was not attempted before operating pressure of the emergency
depressurization system was no longer available.
3)
PSTG, step DW/T-1, directed the operators to operate all available drywell
cooling, defeating isolation interlocks if necessary.
However, the
Primary Containment Control Procedure, step DW/T6, prohibited operation of
the drywell coolers if drywell pressure was above 2.0 psig. The licensee
indicated that the operation of the drywell coolers was prohibited at 2.0
12
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -


    *
*
.
.
'
.
'
.
psig because the fans had previously tripped on thennal overloads at this
pressure.
This rationalization did not justify the restriction on the
primary method available to mitigate the high drywell temperature
condition.
Further licensee action is necessary to investigate and
correct the drywell cooler fan problems in order to fully utilize the
drywell coolers for primary containment temperature control.
4)
PSTG, step RC/P-1, directed the operators to manually open the SRVs if any
SRVs were cycling, until reactor pressure dropped to 950 psig, the
pressure at which all turbine bypass valves would remain fully open.
However, E0P Path-1, step 12, required that the operators open SRVs to
stabilize reactor pressure while maintaining maximum possible steam flow
to the main condenser, and did not specify a pressure setpoint. The
inspection team was concerned that the E0P omitted the parameter to which
the RPV pressure should be lowered without justification.
3.2.3 Calculation Review
l
The inspection team reviewed the calculations for figures and setpoints used in
the E0Ps to determine if the values were correctly calculated based on the
plant specific differences and the guidance of the BWROG EPGs. At the time of
the inspection, the licensee's Nuclear Engineering Department (NED) was
completing an independent verification of all calculations used to support the
draft E0Ps in accordance with Special Procedure SP-87-079, Revision 001,
.
" Independent Review of BSEP E0P Numerical Limits and Graphs." Although several
l
calculations remained to be verified by the NED, the calculations reviewed by
'
'
                .
the inspection team had previously been completed by the NED. As evidenced by
          '
1
  .
the errors in the calculation of the hot shutdown boron weight discussed below,
            psig because the fans had previously tripped on thennal overloads at this
the verification of the draft E0P calculations was not completely effective.
            pressure.  This rationalization did not justify the restriction on the
Further licensee action is necessary to ensure the accuracy of the calculations
            primary method available to mitigate the high drywell temperature
and associated assumptions. The following deficiencies were noted.
            condition. Further licensee action is necessary to investigate and
1)
            correct the drywell cooler fan problems in order to fully utilize the
Worksheet WS-09 determined the maximum primary containment water level
            drywell coolers for primary containment temperature control.
limit that would not cover the highest primary containment vent capable of
      4)    PSTG, step RC/P-1, directed the operators to manually open the SRVs if any
rejecting all decay heat, and calculated the maximum primary containment
            SRVs were cycling, until reactor pressure dropped to 950 psig, the
pressure capability.
            pressure at which all turbine bypass valves would remain fully open.
In a report entitled " Calculation of Vent Flows for
            However, E0P Path-1, step 12, required that the operators open SRVs to
the BSEP," dated July 29, 1988, the licensee reviewed four primary
            stabilize reactor pressure while maintaining maximum possible steam flow
containment vont flow paths and concluded that three of the four paths
            to the main condenser, and did not specify a pressure setpoint. The
would pass the anticipated design decay heat load.
            inspection team was concerned that the E0P omitted the parameter to which
Each of the three
            the RPV pressure should be lowered without justification.
acceptable paths vented the primary containment from the suppression
      3.2.3 Calculation Review
chamber. Although a vent path from an elevated location in the drywell
                                                                                      l
was not considered in the study, the licensee calculated the maximum
      The inspection team reviewed the calculations for figures and setpoints used in
containment water level based on a vent path from the drywell (i.e.,
      the E0Ps to determine if the values were correctly calculated based on the
through valves V-9 ard V-10). The licensee indicated that the path was
      plant specific differences and the guidance of the BWROG EPGs. At the time of
equivalent to the suppression pool vent path and, therefore, was
      the inspection, the licensee's Nuclear Engineering Department (NED) was
technically adequate for not exceeding the maximum pressure limit;
      completing an independent verification of all calculations used to support the
however, a technical justification that the drywell vent path had
      draft E0Ps in accordance with Special Procedure SP-87-079, Revision 001,        .
sufficient capacity to pass the decay heat load was not performed.
      " Independent Review of BSEP E0P Numerical Limits and Graphs." Although several  l
The calculated value for the maximum primary containment water level limit
      calculations remained to be verified by the NED, the calculations reviewed by    '
was the elevation of the drywell vent elevation (i.e., 69.67 feet to the
      the inspection team had previously been completed by the NED. As evidenced by   1
center line of an 18-inch diameter vent pipe). A more conservative value
      the errors in the calculation of the hot shutdown boron weight discussed below,   i
of 68.5 feet was used in the PSTG to ensure that water would not enter the
      the verification of the draft E0P calculations was not completely effective.
13
      Further licensee action is necessary to ensure the accuracy of the calculations
      and associated assumptions. The following deficiencies were noted.
      1)   Worksheet WS-09 determined the maximum primary containment water level
            limit that would not cover the highest primary containment vent capable of
            rejecting all decay heat, and calculated the maximum primary containment
            pressure capability. In a report entitled " Calculation of Vent Flows for
            the BSEP," dated July 29, 1988, the licensee reviewed four primary
            containment vont flow paths and concluded that three of the four paths
            would pass the anticipated design decay heat load. Each of the three
            acceptable paths vented the primary containment from the suppression
            chamber. Although a vent path from an elevated location in the drywell
            was not considered in the study, the licensee calculated the maximum
            containment water level based on a vent path from the drywell (i.e.,
            through valves V-9 ard V-10). The licensee indicated that the path was
            equivalent to the suppression pool vent path and, therefore, was
            technically adequate for not exceeding the maximum pressure limit;
            however, a technical justification that the drywell vent path had
            sufficient capacity to pass the decay heat load was not performed.
            The calculated value for the maximum primary containment water level limit
            was the elevation of the drywell vent elevation (i.e., 69.67 feet to the
            center line of an 18-inch diameter vent pipe). A more conservative value
            of 68.5 feet was used in the PSTG to ensure that water would not enter the
                                                13


                                                                                        -                           _ _ - _ _ _ _ _
-
      *
_ _ - _ _ _ _ _
    .
*
  '
.
                  .
'
          '
.
    .
'
            vent piping and inhibit primary containment venting; however, this
.
            conservatism was not included in the calculation.
vent piping and inhibit primary containment venting; however, this
            The inspection team was concerned that the method of primary containment
conservatism was not included in the calculation.
            water level measurement developed by the licensee did not have sufficient
The inspection team was concerned that the method of primary containment
            accuracy to support controlling primary containment water level. The
water level measurement developed by the licensee did not have sufficient
            Primary Containment Flooding Procedure, section 9, provided a method for
accuracy to support controlling primary containment water level. The
            the operators to estimate the primary containment water level by using the
Primary Containment Flooding Procedure, section 9, provided a method for
            pressure instruments in the suppression chamber and at the bottom of the
the operators to estimate the primary containment water level by using the
            drywell to trend the drywell pressure as a function of time during primary
pressure instruments in the suppression chamber and at the bottom of the
            containment flooding. Trending was required Secause the drywell pressure
drywell to trend the drywell pressure as a function of time during primary
            instrument would be submerged at low primary containment water levels and
containment flooding. Trending was required Secause the drywell pressure
            could not be used for measuring differential pressure and primary
instrument would be submerged at low primary containment water levels and
            containment watcr level. After adding the expected pressure head of the
could not be used for measuring differential pressure and primary
            water in the primary containment to the extrapolated pressure obtained
containment watcr level. After adding the expected pressure head of the
            from trending, RPV injection was secured at the estimated total pressure
water in the primary containment to the extrapolated pressure obtained
            corresponding to the maximum primary containment water level. This
from trending, RPV injection was secured at the estimated total pressure
            methodology was unreliable because it incorrectly assumed that the
corresponding to the maximum primary containment water level. This
            pressure increase would be linear. In addition, the inaccuracies involved
methodology was unreliable because it incorrectly assumed that the
            in this methodology would not support controlling primary containment
pressure increase would be linear.
            water level within an accuracy of 1.17 feet (i.e., the conservatism used
In addition, the inaccuracies involved
            to prevent flooding the primary containment vent path).
in this methodology would not support controlling primary containment
            The lack of primary containment water level instrumentation was noted
water level within an accuracy of 1.17 feet (i.e., the conservatism used
            during the Detailed Control Room Design Review (DCRDR) in HED 206X-5093.
to prevent flooding the primary containment vent path).
            This deficiency will eventually be corrected by the installation of a                                                   i
The lack of primary containment water level instrumentation was noted
            drywell pressure instrument above the maximum water level, thus supporting                                               i
during the Detailed Control Room Design Review (DCRDR) in HED 206X-5093.
            accurate primary containment water level measurement. Further licensee                                                   I
This deficiency will eventually be corrected by the installation of a
            action is necessary to revise the current procedures to ensure that the                                                 1
i
            primary containment water level measurement procedures can be implemented                                               l
drywell pressure instrument above the maximum water level, thus supporting
l           effectively by the operators. In addition, the new pressure instrumentation                                             j
i
            should be installed as soon as possible.                                                                                 I
accurate primary containment water level measurement.
        2)  Worksheets WS-15 and WS-16 and plant-specific data package PSD-17
Further licensee
            calculated the cold and hot shutdown boron weights required to poison the
I
            reactor in the event of an ATWS. In PSD-17, the licensee erroneously
action is necessary to revise the current procedures to ensure that the
            calculatad the concentration of boron required due to several errors in
1
            the conversion of the reference values provided by the vendor. This
primary containment water level measurement procedures can be implemented
              incorrect conversion resulted in a calculation of the hot shutdown boren
l
            weight which was 14.46 pounds too low. This incorrect value adversely
l
            affected the calculations for: (1) time to inject boron (100 seconds
effectively by the operators.
              longer),  (2) volume
In addition, the new pressure instrumentation
              to hot shutdown    (68.5ofgallons
j
                                          the standby)  liquid
should be installed as soon as possible.
                                                more , (3) SLCcontrol
                                                                tank level          (SLC)      tank corresponding
                                                                                      indication              for hot
            shutdown (0.43 percent lower), and (4) the amount of borax required for
            hot shutdown (127.6 pounds more). Although these errors resulted in                                                      !
              non-conservative values for the hot shutdown boron weights, the difference                                              !
              (i.e., less that 5 percent) was unlikely to prevent the emergency shutdown                                              ;
            of the reactor due to the conservatism of the calculation. Nevertheless,
                                                                                                                                      ~
              these errors were not identified by the licensee's verification of the                                                  i
              calculation, including the independent verification by the NED. Further                                                ;
                                                                                                                                      '
i            licensee action is necessary to correct this error and ensure that all the
I
I
              draft calculations are correct.
2)
Worksheets WS-15 and WS-16 and plant-specific data package PSD-17
calculated the cold and hot shutdown boron weights required to poison the
reactor in the event of an ATWS.
In PSD-17, the licensee erroneously
calculatad the concentration of boron required due to several errors in
the conversion of the reference values provided by the vendor. This
incorrect conversion resulted in a calculation of the hot shutdown boren
weight which was 14.46 pounds too low. This incorrect value adversely
affected the calculations for: (1) time to inject boron (100 seconds
longer), (2) volume of the standby) liquid control (SLC) tank corresponding
to hot shutdown (68.5 gallons more , (3) SLC tank level indication for hot
shutdown (0.43 percent lower), and (4) the amount of borax required for
hot shutdown (127.6 pounds more). Although these errors resulted in
!
non-conservative values for the hot shutdown boron weights, the difference
!
(i.e., less that 5 percent) was unlikely to prevent the emergency shutdown
;
of the reactor due to the conservatism of the calculation.
Nevertheless,
~
these errors were not identified by the licensee's verification of the
i
calculation, including the independent verification by the NED. Further
;
'
i
licensee action is necessary to correct this error and ensure that all the
I
I
                                                  14
draft calculations are correct.
                                      _             ._         . _ _ _ _ _ _ - -       _ _ _ _ _ _____ - -
I
14
_
._
. _ _ _ _ _ _ - -
_ _ _ _ _ _____ - -


                              '
'
          .
.
          ,
,
                                                  .
.
                                            -
-
            .
.
                                    3)       Worksheet WS-AC4 detailed the calculation of the plant specific value for   i
3)
                                              drywell scram pressure. The numerical limit value was listed as 2.0 psig;
Worksheet WS-AC4 detailed the calculation of the plant specific value for
                                              however, no calculation was provided to support the parameter. The basis
i
                                              was listed as technical specifications 2.2.1-1 and 3.3-1 with an
drywell scram pressure. The numerical limit value was listed as 2.0 psig;
                                              amplifying comment that 2.0 psig was the scram setpoint for high drywell
however, no calculation was provided to support the parameter. The basis
                                              pressure. As discussed in Section 3.3.1.1, the latter statement was
was listed as technical specifications 2.2.1-1 and 3.3-1 with an
                                              incorrect in that the high drywell pressure scram was set at 1.8 psig.
amplifying comment that 2.0 psig was the scram setpoint for high drywell
                                              Further licensee action is necessary to ensure that the setpoint
pressure. As discussed in Section 3.3.1.1, the latter statement was
                                              documentation corresponds to values actually used.
incorrect in that the high drywell pressure scram was set at 1.8 psig.
                                    4)       Worksheet WS-12 calculated the lowest suppression chamber pressure which
Further licensee action is necessary to ensure that the setpoint
                                              could occur when 95 percent of the non-condensables in the drywell had
documentation corresponds to values actually used.
                                              been transferred to the suppression chamber. A minor discrepancy was
4)
                                              identified in that the computed value was 13.07 psig, but the cover sheet   i
Worksheet WS-12 calculated the lowest suppression chamber pressure which
                                              of the calculation indicated 13 psig without explanation. PSTG, step
could occur when 95 percent of the non-condensables in the drywell had
                                                                                                                          '
been transferred to the suppression chamber.
                                              PC/P-1, also incorporated the value of 13.0 psig. The PSTG should reflect
A minor discrepancy was
                                              the calculations and any differences between the PSTG and the calculations
identified in that the computed value was 13.07 psig, but the cover sheet
                                              should be explained in the PSTG deviation documentation.
i
                                    5)       Worksheet WS-8 calculated the highest suppression chamber pressure as a
of the calculation indicated 13 psig without explanation.
                                              function of the primary containment water level that would permit the
PSTG, step
                                              primary containment to maintain its pressure suppression function while     l
'
PC/P-1, also incorporated the value of 13.0 psig.
The PSTG should reflect
the calculations and any differences between the PSTG and the calculations
should be explained in the PSTG deviation documentation.
5)
Worksheet WS-8 calculated the highest suppression chamber pressure as a
function of the primary containment water level that would permit the
primary containment to maintain its pressure suppression function while
l
.
.
                                              the RPV was at normal operating pressure. Several administrative errors     I
the RPV was at normal operating pressure.
l                                             that did not affect the technical adequacy of the calculation were noted.   '
Several administrative errors
                                              Examples included differences between values which were transferred into
I
                                              subsequent calculations.
l
l                                   3.2.4 Adequacy of Writer's Guide
that did not affect the technical adequacy of the calculation were noted.
                                    A review of the PSWG was conducted to determine wbether it described acceptable
'
                                    methods for accomplishing the objectives stated in NUREG-0899. The inspection         :
Examples included differences between values which were transferred into
                                    tet.m concluded that the PSWG was incomplete and should be supplemented with
subsequent calculations.
                                    detailed guidance in the following areas.
l
                                    1)       Referencing Supporting Material - All figures, tables, and other
3.2.4 Adequacy of Writer's Guide
                                              supporting materials that may be required in the performance of a
A review of the PSWG was conducted to determine wbether it described acceptable
i                                             procedural step should be referenced explicitly in the E0P at the point at
methods for accomplishing the objectives stated in NUREG-0899. The inspection
:
tet.m concluded that the PSWG was incomplete and should be supplemented with
detailed guidance in the following areas.
1)
Referencing Supporting Material - All figures, tables, and other
supporting materials that may be required in the performance of a
i
procedural step should be referenced explicitly in the E0P at the point at
!
!
                                              which the information is needed. For ex. ample, the "RPV Pressure Range for
which the information is needed.
                                              System Operation Table," was not referenced or included in step 27 of the
For ex. ample, the "RPV Pressure Range for
                                              End Path Procedure. Similarily, although Primary Containment Control
System Operation Table," was not referenced or included in step 27 of the
                                              Procedure, step PC/P-9, required controlling suppression chamber pressure
End Path Procedure.
                                              in the safe region of the pressure suppression pressure, no reference was
Similarily, although Primary Containment Control
                                              made in this step for the graph or figure to be used. Guidance for
Procedure, step PC/P-9, required controlling suppression chamber pressure
                                              referencing supporting materials within the procedural steps should be
in the safe region of the pressure suppression pressure, no reference was
                                              part of the PSWG.
made in this step for the graph or figure to be used.
                                    2)       Referencing Other E0Ps - Several E0Ps directed the performance of a series
Guidance for
                                              ~Tsleps
referencing supporting materials within the procedural steps should be
                                              o        in accordance with other procedures. In order to reduce
part of the PSWG.
                                              transition errors, the complete title of the procedure and its reference   ,
2)
                                              number should be included in the procedural step. In addition, a complete
Referencing Other E0Ps - Several E0Ps directed the performance of a series
                                              technique that will aid the operator in making a correct identification of
~Tsleps in accordance with other procedures.
                                              these other procedures should be included in the PSWG.
In order to reduce
                                                                                                                          l
o
                                                                                                                          !
transition errors, the complete title of the procedure and its reference
                                                                                                                          I
,
                                                                                15
number should be included in the procedural step.
  - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _
In addition, a complete
technique that will aid the operator in making a correct identification of
these other procedures should be included in the PSWG.
l
!
I
15
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _


    *
*
,
,
'
'
                .
.
          *
*
  ,
,
      3)   Step Identification - The PSWG described a technique for identifying
3)
            critical action steps which required placing the symbol for a decision
Step Identification - The PSWG described a technique for identifying
            block over the symbol of an action block. This methodology was not an
critical action steps which required placing the symbol for a decision
            effective method of identifying override requirements. As discussed in
block over the symbol of an action block.
            Section 3.4.3.3, a critical step was overlooked during the simulator
This methodology was not an
            exercise because the operator did not recognize that the critical step
effective method of identifying override requirements. As discussed in
            represented an override condition. A more discernible shape coding
Section 3.4.3.3, a critical step was overlooked during the simulator
            technique should be employed for deignating critical steps in the E0Ps.
exercise because the operator did not recognize that the critical step
      4)   Operator Aids - Operating Instruction 01-41 discussed procedures and
represented an override condition. A more discernible shape coding
            methodologies for implementing operator aids at BSEP; however, this
technique should be employed for deignating critical steps in the E0Ps.
            instruction was not referenced by the PSWG. Reference to this document,
4)
            including the basic criteria for design and control of operator aids,
Operator Aids - Operating Instruction 01-41 discussed procedures and
            should be incorporated into the PSWG.     The need for training operators on
methodologies for implementing operator aids at BSEP; however, this
            the use of the operator aids should also be addressed.
instruction was not referenced by the PSWG.
      5)   _ Color Coding - The PSWG contained no criteria for color coding the E0Ps;
Reference to this document,
            however, the draft E0Ps employed a color coding scheme. Guidelines and
including the basic criteria for design and control of operator aids,
            direction on the uses of color should be included in the PSWG.
should be incorporated into the PSWG.
      6)   Titles - The operators should be able to identify the basic scope of each
The need for training operators on
            E0P by reading the title. The E0P titles Path-1 through Path-5 failed to
the use of the operator aids should also be addressed.
            indicate what the procedure was intended to accomplish. Guidance for
5)
            constructing meaningful and unique titles for the E0Ps should be included
_ Color Coding - The PSWG contained no criteria for color coding the E0Ps;
            in the PSWG .
however, the draft E0Ps employed a color coding scheme.
      7)   Consistency of Step Numbering - Some steps within the E0P flow charts
Guidelines and
            applied the BWROG EPG convention for designating steps (i.e., PC/H-9),
direction on the uses of color should be included in the PSWG.
            while others employed a three digit system (i.e., 027). A consistent
6)
            method for numbering the E0P steps should be incorporated and documented
Titles - The operators should be able to identify the basic scope of each
            in the PSWG.
E0P by reading the title.
      3.2.5 Writer's Guide Implementation
The E0P titles Path-1 through Path-5 failed to
      The PSWG was independently verified to assess its implementation as a source
indicate what the procedure was intended to accomplish.
      document for the preparation of the E0Ps. The verification process consisted
Guidance for
      of comparing the E0P flowcharts and written procedures (e.g., LEPs, SEPs, etc.)
constructing meaningful and unique titles for the E0Ps should be included
      with the stated criteria and human factors guidance contained in the PSWG. The
in the PSWG .
      inspection team concluded that the PSWG was generally followed as a source
7)
      document for preparation of E0Ps; however, several minor deviations were
Consistency of Step Numbering - Some steps within the E0P flow charts
      ider,ti fied.   Further licensee action is necessary to ensure that the criteria
applied the BWROG EPG convention for designating steps (i.e., PC/H-9),
      and human factors guidance contained in the PSWG are reflected in the E0Ps.
while others employed a three digit system (i.e., 027).
      1)   Instrument Accuracy - Some of the values referenced in the E0Ps could not
A consistent
            be obtained from the displays. In Path-4 for example, the operators were
method for numbering the E0P steps should be incorporated and documented
            required to read the conductivity of the condensate booster pump to less
in the PSWG.
            than 0.3 umhos. The instrument display, 1-00 CR-3075, did not support       ;
3.2.5 Writer's Guide Implementation
            this level of accuracy. As demonstrated during the system walkthroughs,
The PSWG was independently verified to assess its implementation as a source
            the operators were unable to read the setpoint value of 0.3 mmhos from the   ]
document for the preparation of the E0Ps. The verification process consisted
            instrument scale. This deficiency was identified as a human engineering
of comparing the E0P flowcharts and written procedures (e.g., LEPs, SEPs, etc.)
            deficiency (HED 20X5-5015) during the DCRDR; however, no corrective action   l
with the stated criteria and human factors guidance contained in the PSWG.
            had been taken.     In addition, the resolution of the reactor building roof j
The
            radiation level instrument, CAC-AQH-1264-3, was unsuitable for reading the   i
inspection team concluded that the PSWG was generally followed as a source
            E0P-specified setpoints of 3446 cpm (setpoint 1) and 4213 cpm (setpoint
document for preparation of E0Ps; however, several minor deviations were
                                                16
ider,ti fied.
Further licensee action is necessary to ensure that the criteria
and human factors guidance contained in the PSWG are reflected in the E0Ps.
1)
Instrument Accuracy - Some of the values referenced in the E0Ps could not
be obtained from the displays.
In Path-4 for example, the operators were
required to read the conductivity of the condensate booster pump to less
than 0.3 umhos. The instrument display, 1-00 CR-3075, did not support
;
this level of accuracy.
As demonstrated during the system walkthroughs,
the operators were unable to read the setpoint value of 0.3 mmhos from the
]
instrument scale. This deficiency was identified as a human engineering
deficiency (HED 20X5-5015) during the DCRDR; however, no corrective action
had been taken.
In addition, the resolution of the reactor building roof
j
radiation level instrument, CAC-AQH-1264-3, was unsuitable for reading the
i
E0P-specified setpoints of 3446 cpm (setpoint 1) and 4213 cpm (setpoint
16


                                                                              - _ ___ _ _ _ _ _
- _ ___ _ _ _ _ _
    '
.
'
'
              ,
.
        '
'
  .
,
          2). Also, the E0P directed the operator to read the turbine building vent
'
          radiation levels on instrument D12-RM-23; however, no setpoints were
.
          identified on the instrument.
2). Also, the E0P directed the operator to read the turbine building vent
      2)   Instrument Labels - The E0Ps referenced different units than those
radiation levels on instrument D12-RM-23; however, no setpoints were
          inoicated on the instrument displays. For example, the E0P referenced the
identified on the instrument.
          radiation level for service water effluent in units of counts per minute;
2)
          however, the instrument in the control room (i.e., D12-K805) for obtaining
Instrument Labels - The E0Ps referenced different units than those
          this information was displayed in counts per second. In addition, the
inoicated on the instrument displays.
          digital readout for monitoring stack releases, located on the control room
For example, the E0P referenced the
          back panels, was not labeled and no units were identified. Only the                 !
radiation level for service water effluent in units of counts per minute;
                                                                                                I
however, the instrument in the control room (i.e., D12-K805) for obtaining
          value, 4.57E + 1, was displayed.
this information was displayed in counts per second.
      3)   location of Equipment - The E0Ps did not provide adequate location
In addition, the
          information for specific equipment, controls, or displays. For example,
digital readout for monitoring stack releases, located on the control room
          the action steps to start the diesel fire pump, open all battery room exit
back panels, was not labeled and no units were identified.
          doors, or open emergency core cooling system (ECCS) pipe tunnel doors were
Only the
          local operations. The PSWG did not establish a standard method for
!
          identifying the location of controls and displays external to the control
I
          room.
value, 4.57E + 1, was displayed.
      4)   System Nomenclature - The E0Ps used inconsistent nomenclature for
3)
          equipment and systems. For example, in the Level / Power Control Procedure,
location of Equipment - The E0Ps did not provide adequate location
          steps 76 and 30, LPCI was used instead of RHR.
information for specific equipment, controls, or displays.
                                                                                                .
For example,
      5)   Step Content - The E0Ps contained both decision and action steps or                   l
the action steps to start the diesel fire pump, open all battery room exit
          contained more than one action or subject. For example, in Path-3, steps             !
doors, or open emergency core cooling system (ECCS) pipe tunnel doors were
          175 and 93, and Path-1, step 12, the decision step required several
local operations.
          actions on the part of the operator.
The PSWG did not establish a standard method for
      6)   Change Identification - There was no identification of the location of
identifying the location of controls and displays external to the control
          recent changes in the written procedures. A change bar technique should
room.
          be used.
4)
      7)   Section Redundancy - PSWG, section 3.7, "Information/ Caution Steps," and
System Nomenclature - The E0Ps used inconsistent nomenclature for
          section 3.9, "Information Steps," appeared to be identical in content.
equipment and systems.
      8)   Vocabulary - The E0Ps used verbs such as downrange, monitor, cycle, and
For example, in the Level / Power Control Procedure,
          increase, which were not listed in Table 1 of the PSWG as approved verbs.
steps 76 and 30, LPCI was used instead of RHR.
      3.3 E0P Validation Using Plant Walkthroughs
.
      In order to ensure that the E0Ps could be accomplished successfully, plant
5)
      walkthroughs for all the E0Ps and referenced operational procedures were
Step Content - The E0Ps contained both decision and action steps or
      performed. The team verified that E0P instrument and control designations were
contained more than one action or subject.
      consistent with the installed equipment and that indicators, annunciators, and
For example, in Path-3, steps
      controls referenced by the E0Ps were available to the operators. The
!
      inspection team also verified the location and control of E0Ps-in the control
175 and 93, and Path-1, step 12, the decision step required several
      room. With the assistance of licensed operators, the team physically verified
actions on the part of the operator.
      that activities which would occur outside the control room during an accident
6)
      scenario could physically be accomplished and that tools, jumpers, and test
Change Identification - There was no identification of the location of
      equipment were available to the operators.
recent changes in the written procedures. A change bar technique should
                                              17
be used.
7)
Section Redundancy - PSWG, section 3.7, "Information/ Caution Steps," and
section 3.9, "Information Steps," appeared to be identical in content.
8)
Vocabulary - The E0Ps used verbs such as downrange, monitor, cycle, and
increase, which were not listed in Table 1 of the PSWG as approved verbs.
3.3 E0P Validation Using Plant Walkthroughs
In order to ensure that the E0Ps could be accomplished successfully, plant
walkthroughs for all the E0Ps and referenced operational procedures were
performed. The team verified that E0P instrument and control designations were
consistent with the installed equipment and that indicators, annunciators, and
controls referenced by the E0Ps were available to the operators. The
inspection team also verified the location and control of E0Ps-in the control
room. With the assistance of licensed operators, the team physically verified
that activities which would occur outside the control room during an accident
scenario could physically be accomplished and that tools, jumpers, and test
equipment were available to the operators.
17


                                                          - __             _ _ _ _ _ _ _ _ - - - - - - - - - - - - - - - - _ - - - - . - .
- __
                                                                                                                                              ,
_ _ _ _ _ _ _ _ - - - - - - - - - - - - - - - - _ - - - - . - .
      '
,
  .
'
  ,
.
                  e
,
            *
e
    .
*
                                                                                                                                                l
.
        3.3.1 Technical Adequacy of Procedures __                                                                                               !
l
        The inspection team identified several deficiencies with respect to the
!
        procedural completeness and technical adequacy of the E0Ps. Although the
3.3.1 Technical Adequacy of Procedures __
        inspection team concluded that the operators could adequately perform the                                                               ;
The inspection team identified several deficiencies with respect to the
                                                                                                                                                '
procedural completeness and technical adequacy of the E0Ps.
        procedures in spite of these deficiencies, further licensee action is necessary
Although the
        to correct these deficiencies and perform an adequate verification and valida-
inspection team concluded that the operators could adequately perform the
        tion of the E0Ps.
;
        1)   Path-1, steps 115 and 116, and Path-2, steps 165 and 166, directed the
procedures in spite of these deficiencies, further licensee action is necessary
              operators to maximize the flow from the operating control rod drive (CRD)
'
              system pumps by operating at the optimum pressure on the pump tead curve                                                           l
to correct these deficiencies and perform an adequate verification and valida-
                                                                                                                                                ,
tion of the E0Ps.
              The intent of these steps was to maximize CRD flow. However, the steps                                                             !
1)
              failed to accomplish the desired action because the operator was directed                                                         I
Path-1, steps 115 and 116, and Path-2, steps 165 and 166, directed the
              to throttle the pressure control valve to maintain pressure equal to or
operators to maximize the flow from the operating control rod drive (CRD)
              greater than 1000 psig and was never directed to increase CRD flow to the
l
              reactor. The steps should have directed the operator to maintain pressure
system pumps by operating at the optimum pressure on the pump tead curve
              equal to or greater than 1000 psig but as low as possible. Further
,
              licensee action is necessary te modify these steps to ensure that the
The intent of these steps was to maximize CRD flow.
              intended action is accomplished.
However, the steps
l       2)   Primary Containment Flooding Procedure, section 7, step 3.d (2),
!
              instructed the operators to lift wire number 25 from terminal 70, on
failed to accomplish the desired action because the operator was directed
              terminal board UU in control panel P601. A note preceding the step stated
I
              that the lead to be lifted was the lead entering from outside control
to throttle the pressure control valve to maintain pressure equal to or
l             panel P601. The operator could not detennine which wire entered from                                                               l
greater than 1000 psig and was never directed to increase CRD flow to the
              outside the panel because two wires with exactly the same number (i.e.,                                                           l
reactor.
              number 25) were on the tenninal and both wires entered the same wireway.                                                           l
The steps should have directed the operator to maintain pressure
              This condition was noted at three other steps in the same section.                                                                 l
equal to or greater than 1000 psig but as low as possible.
                                                                                                                                                l
Further
                                                                                                                                                '
licensee action is necessary te modify these steps to ensure that the
        3)   Primary Containment Flooding Procedure, sections 7 and 8, step C.3, failed
intended action is accomplished.
              to provide the operator with instructions concerning the level to which to                                                         l
l
              fill the primary containment.
2)
        4)   Primary Containment Flooding Procedure, section 2, did not list in the
Primary Containment Flooding Procedure, section 7, step 3.d (2),
              note for manpower required the radwaste operator required to take several
instructed the operators to lift wire number 25 from terminal 70, on
              actions necessary to support the evolution.
terminal board UU in control panel P601.
        5)   Primary Containment Control Procedure, step PC/P-4, directed the operators
A note preceding the step stated
              to vent the primary containment drywell through the standby gas treatment
that the lead to be lifted was the lead entering from outside control
              (SBGT) system in accordance with Operational Procedure OP-10. This
l
              procedure only permitted venting the SBGT through two 1/2-inch lines
panel P601. The operator could not detennine which wire entered from
              (valves V8 and V9) when drywell pressure was above 0.7 psig. In this mode
l
              of operation, the SBGT system vent path would have little or no effect on
outside the panel because two wires with exactly the same number (i.e.,
              controlling primary containment pressure. The licensee should use the
l
              10-inch ventilation damper (F-BFV-RP.) for venting, at least until the
number 25) were on the tenninal and both wires entered the same wireway.
              pressure in the SBGT train reaches the limiting operating pressure.
l
        6)   Primary Containment Control Procedure, steps PC/P-6 and PC/P-8, directed
This condition was noted at three other steps in the same section.
              the operator to initiate suppression pool and drywell sprays; however,
l
              during the walkthroughs the operators were confused as to whether or not
l
3)
Primary Containment Flooding Procedure, sections 7 and 8, step C.3, failed
'
to provide the operator with instructions concerning the level to which to
l
fill the primary containment.
4)
Primary Containment Flooding Procedure, section 2, did not list in the
note for manpower required the radwaste operator required to take several
actions necessary to support the evolution.
5)
Primary Containment Control Procedure, step PC/P-4, directed the operators
to vent the primary containment drywell through the standby gas treatment
(SBGT) system in accordance with Operational Procedure OP-10.
This
procedure only permitted venting the SBGT through two 1/2-inch lines
(valves V8 and V9) when drywell pressure was above 0.7 psig.
In this mode
of operation, the SBGT system vent path would have little or no effect on
controlling primary containment pressure.
The licensee should use the
10-inch ventilation damper (F-BFV-RP.) for venting, at least until the
pressure in the SBGT train reaches the limiting operating pressure.
6)
Primary Containment Control Procedure, steps PC/P-6 and PC/P-8, directed
the operator to initiate suppression pool and drywell sprays; however,
during the walkthroughs the operators were confused as to whether or not
to secure suppression pool sprays prior to initiating drywell sprays.
,
,
              to secure suppression pool sprays prior to initiating drywell sprays.
I
I
              Augmented training or clarification in the E0P should be provided to
Augmented training or clarification in the E0P should be provided to
              resolve this confusion.
resolve this confusion.
                                                  18
18
                                                                                                      _ ____ _____-___ _                   -
_ ____ _____-___ _
-


f   ,
f
) .'
,
                .
)
          '
.'
  .
.
      7)   Primary Containment Control Procedure, step SP/L-5.3, directed the
'
            operator to drain the suppression pool to radwaste to control suppression
.
            pool level. This step did not provide alternate instructions if these
7)
            valves were interlocked closed from an isolation signal.   Further licensee
Primary Containment Control Procedure, step SP/L-5.3, directed the
            action is necessary to account for this possibility.
operator to drain the suppression pool to radwaste to control suppression
      8)   Primary Containment Control Procedure, step SP/L-5.22 directed the
pool level.
            operators to maintain primary containment water level below 68.5 feet;
This step did not provide alternate instructions if these
            however, this step and subsequent steps did not reference the procedure to
valves were interlocked closed from an isolation signal.
            accomplish this measurement.
Further licensee
      9)   SEP-01, section 3, initiated primary containment venting before primary
action is necessary to account for this possibility.
            containment pressure reached 70 psig by using preferentially listed vent
8)
            paths. After opening the proper valve, the subsequent action step
Primary Containment Control Procedure, step SP/L-5.22 directed the
            required continued venting of the primary containment if the initial
operators to maintain primary containment water level below 68.5 feet;
            venting operation stabilized primary containment pressure below 70 psig.
however, this step and subsequent steps did not reference the procedure to
            The inspection team was concerned that the step provided inadequate
accomplish this measurement.
            guidance to the operator concerning action required if the vent path was
9)
            more than adequate and primary containment pressure started to fall below
SEP-01, section 3, initiated primary containment venting before primary
            70 psig. The licensee should ensure that an approved PSWG action verb is
containment pressure reached 70 psig by using preferentially listed vent
            used which properly implements the intent of the BWROG EPG concerning
paths. After opening the proper valve, the subsequent action step
            primary containment pressure control during venting.
required continued venting of the primary containment if the initial
      10) SEP-04, steps 3 and 4, directed opening of reactor building inboard and
venting operation stabilized primary containment pressure below 70 psig.
            outboard ventilation isolation valves. The terminology was incorrect in
The inspection team was concerned that the step provided inadequate
            that the procedure referred to the valves as reactor building inboard
guidance to the operator concerning action required if the vent path was
            (cutboard) isolation valve (s). The correct terminology was reactor
more than adequate and primary containment pressure started to fall below
            building vent inboard (outboard) isolation valve (s).
70 psig. The licensee should ensure that an approved PSWG action verb is
      11) SEP-06, included entry conditions of drywell pressure which were below 2.0
used which properly implements the intent of the BWROG EPG concerning
            psig. The procedure was actually implemented when the shutdown cooling     i
primary containment pressure control during venting.
            interlocks were fulfilled at the corresponding drywell pressure of 1.8     '
10) SEP-04, steps 3 and 4, directed opening of reactor building inboard and
            psig. As discussed in Section 3.2.3.3, further licensee action is
outboard ventilation isolation valves.
            necessary to ensure that procedural values are consistent with the plant
The terminology was incorrect in
            parameters used to initiate actions.
that the procedure referred to the valves as reactor building inboard
      12) SEP-06 cautioned the operators concerning reactor power excursions when
(cutboard) isolation valve (s). The correct terminology was reactor
            the residual heat removal (RHR) system pumps were started in step C.48.
building vent inboard (outboard) isolation valve (s).
            However, the correct reference for this precaution should have been a
11) SEP-06, included entry conditions of drywell pressure which were below 2.0
            subsequent action step which throttled open the injection valve. The
psig.
            licensee should ensure that the caution correctly references the operator
The procedure was actually implemented when the shutdown cooling
            action which actually affects reactor power level.
interlocks were fulfilled at the corresponding drywell pressure of 1.8
      3.3.2 Availability of Special Tools and Equipment
'
      The availability of special tools and equipment in the plant appeared to be
psig. As discussed in Section 3.2.3.3, further licensee action is
      adequate to accomplish the activities required by the E0Ps. The team verified
necessary to ensure that procedural values are consistent with the plant
      that the plant equipment was accessible and available to perform the identified
parameters used to initiate actions.
      task. A walkthrough was performed of the special tools and equipment used in
12) SEP-06 cautioned the operators concerning reactor power excursions when
      the E0Ps both in the control room and the plant. Because the draft E0Ps had
the residual heat removal (RHR) system pumps were started in step C.48.
      not been implemented, not all equipment could be verified. Nevertheless,
However, the correct reference for this precaution should have been a
      several specific examples were identified in which equipment or infonnation was
subsequent action step which throttled open the injection valve. The
      not available which could adversely affect the performance of the E0Ps and
licensee should ensure that the caution correctly references the operator
      their support procedures. Based on the training and experience of the
action which actually affects reactor power level.
                                                19
3.3.2 Availability of Special Tools and Equipment
The availability of special tools and equipment in the plant appeared to be
adequate to accomplish the activities required by the E0Ps. The team verified
that the plant equipment was accessible and available to perform the identified
task. A walkthrough was performed of the special tools and equipment used in
the E0Ps both in the control room and the plant.
Because the draft E0Ps had
not been implemented, not all equipment could be verified.
Nevertheless,
several specific examples were identified in which equipment or infonnation was
not available which could adversely affect the performance of the E0Ps and
their support procedures.
Based on the training and experience of the
19


  '
'
                                        .
.
                                    '
'
  .
.
                                operations staff, the inspection team concluded that the E0P actions could be
operations staff, the inspection team concluded that the E0P actions could be
                                accomplished satisfactorily. However, based on the need to provide procedures
accomplished satisfactorily. However, based on the need to provide procedures
                                which can be implemented correctly by a newly qualified operator, and on the
which can be implemented correctly by a newly qualified operator, and on the
                                guidance of NUREG-0899, the inspection team concluded that there was a
guidance of NUREG-0899, the inspection team concluded that there was a
                                potential for operator confusion or error which could affect the performance of
potential for operator confusion or error which could affect the performance of
                                the procedures. Further licensee action is required to provide the necessary
the procedures.
                                equipment or information to ensure that operator confusion will not exist
Further licensee action is required to provide the necessary
                                during the performance of the procedures.
equipment or information to ensure that operator confusion will not exist
during the performance of the procedures.
i
1)
LEP-02 provided an alternate control rod insertion method involving local
venting of the hydraulic control units (HCus). The venting operation used
control rod drive (CRD) vent hoses located in the toolbox on the 20-foot
elevation of the reactor building.
The toolbox contained two sets of
hoses with different types of connectors, only one of which would fit the
HCU vent block. The licensee could not determine the purpose of the
second set of hoses in the toolbox.
The inspection team was concerned
that in an emergency the presence of the incorrect hoses could delay the
performance of alternate control rod insertion. The inspection team also
noted that the toolbox did not contain any protective eouipment and that
the procedure did not warn the operators that HCU venting was a
potentially hazardous operation which could release contaminated, hot
reactor water.
In addition, the licensee indicated that the venting
procedure was a two-man job requiring one operator to perform the venting
operation in the overhead while a second operator coordinated the
activities with the control room and verified that the correct hydraulic
i
i
                                1)    LEP-02 provided an alternate control rod insertion method involving local
control unit was being vented from below.
                                      venting of the hydraulic control units (HCus). The venting operation used
However, the procedure only
                                      control rod drive (CRD) vent hoses located in the toolbox on the 20-foot
required the resources of one operator to perform the venting operation.
                                      elevation of the reactor building. The toolbox contained two sets of
2)
                                      hoses with different types of connectors, only one of which would fit the
The Primary Containment Flooding Procedure required the use of several
                                      HCU vent block. The licensee could not determine the purpose of the
electrical jumpers. Generic jumpers were available to the operators to
                                      second set of hoses in the toolbox. The inspection team was concerned
perform the E0P actions; however, these jumpers had closed-end
                                      that in an emergency the presence of the incorrect hoses could delay the
terminations. The use of closed-ended jumpers required the operator to
                                      performance of alternate control rod insertion. The inspection team also
(
                                      noted that the toolbox did not contain any protective eouipment and that
remove the terrrinal screw, install the additional terminal, recapture all
                                      the procedure did not warn the operators that HCU venting was a
i
                                      potentially hazardous operation which could release contaminated, hot
terminals, and re-install the terminal screw. The inspection team was
                                      reactor water. In addition, the licensee indicated that the venting
concerned that this task was unnecessarily complex for emergency
                                      procedure was a two-man job requiring one operator to perform the venting
conditions.
                                      operation in the overhead while a second operator coordinated the
The use of open-ended terminations, which could be slipped
                                      activities with the control room and verified that the correct hydraulic  i
under a loosened screw, would simplify the task.
                                      control unit was being vented from below. However, the procedure only
In addition, the
                                      required the resources of one operator to perform the venting operation.
inspection team noted that the procedure lacked direction concerning
                                2)   The Primary Containment Flooding Procedure required the use of several
insulation of lifted leads, and that insulating materials were not readily
                                      electrical jumpers. Generic jumpers were available to the operators to
                                      perform the E0P actions; however, these jumpers had closed-end
                                      terminations. The use of closed-ended jumpers required the operator to     (
                                      remove the terrrinal screw, install the additional terminal, recapture all i
                                      terminals, and re-install the terminal screw. The inspection team was
                                      concerned that this task was unnecessarily complex for emergency
                                      conditions. The use of open-ended terminations, which could be slipped
                                      under a loosened screw, would simplify the task. In addition, the
                                      inspection team noted that the procedure lacked direction concerning
,
,
                                      insulation of lifted leads, and that insulating materials were not readily
available.
                                      available.
The inspection team also observed that some electrical relays had wiring
                                      The inspection team also observed that some electrical relays had wiring
diagrams posted adjacent to the relays to aid the operators in identifying
                                      diagrams posted adjacent to the relays to aid the operators in identifying
the terminal locations; however, not all relays used in the E0Ps were
                                      the terminal locations; however, not all relays used in the E0Ps were
identified in this manner.
                                      identified in this manner. Further licensee action is necessary to
Further licensee action is necessary to
                                      provide installation specific jumpers for use in accomplishing the E0P
provide installation specific jumpers for use in accomplishing the E0P
                                      action steps and to provide consistent use of operator aids for the
action steps and to provide consistent use of operator aids for the
identification of relay terminal locations.
,
,
                                      identification of relay terminal locations.
3)
                                3)   During the E0P simulations, the control room operators directed the
During the E0P simulations, the control room operators directed the
                                      auxiliary operators to perform numerous actions in the plant. For
auxiliary operators to perform numerous actions in the plant.
                                      example, steps 67 and 68 in Path-1, required opening battery room exit
For
                                      doors and ECCS pipe tunnel doors. These actions were initiated by the
example, steps 67 and 68 in Path-1, required opening battery room exit
                                      control room operator using the public address (PA) system and required
doors and ECCS pipe tunnel doors. These actions were initiated by the
                                                                        20
control room operator using the public address (PA) system and required
    - _ _ - _ - - _ . _ - - _ -
20
- _ _ - _ - - _ . _ - - _ -


  '
'
,
,
              .
        '
.
.
          the auxiliary operators to find a PA station to report the completion of
'
          the directed actions. Alternate communications techniques, such as
.
          hand-held radios, were not available for communicating with the operators
the auxiliary operators to find a PA station to report the completion of
          perfonning local actions. The inspection team concluded that the licensee
the directed actions.
          should give further consideration to the use of hand-held radios to permit
Alternate communications techniques, such as
          reliable communication with the control room under emergency conditions.
hand-held radios, were not available for communicating with the operators
                                                                                                      i
perfonning local actions. The inspection team concluded that the licensee
    3.3.3 Station Material Condition
should give further consideration to the use of hand-held radios to permit
    The inspection team reviewed the material condition of the station during the
reliable communication with the control room under emergency conditions.
    plant walkthroughs and ensured that necessary equipment and components were
i
    dCCessible and functional. The overall material condition of the plant
3.3.3 Station Material Condition
    appeared good. The team did not observe any interferences in the reactor                           !
The inspection team reviewed the material condition of the station during the
    building which would adversely affect emergency actions. The inspection team                       l
plant walkthroughs and ensured that necessary equipment and components were
    noted that significant amounts of non-combustible material were located in the
dCCessible and functional.
    bottom of control panel P601; however, the licensee initiated corrective action
The overall material condition of the plant
    to clean the panel and inspected and cleaned other panels as required. The                         I
appeared good. The team did not observe any interferences in the reactor
    team verified that emergency lighting was available for E0P operator actions
building which would adversely affect emergency actions. The inspection team
    and noted that lighting was available within electrical cabinets requiring
noted that significant amounts of non-combustible material were located in the
    terminal manipulations. However, during the walkthroughs, the operators would
bottom of control panel P601; however, the licensee initiated corrective action
    not operate the switches to turn on the lights in the cabinets because the
to clean the panel and inspected and cleaned other panels as required.
    switches were not labeled. Further licensee action is necessary to correct
The
    this deficiency.
team verified that emergency lighting was available for E0P operator actions
    3.3.4 Reactor Building Accessibility
and noted that lighting was available within electrical cabinets requiring
    The licensee performed a design review entitled, " Post-Accident Control of
terminal manipulations.
    Radiation in Systems Outside Containment of PWRs and BWRs," to meet the
However, during the walkthroughs, the operators would
    requirements of paragraph 2.1.6 of NUREG-0578, "TMI-2 Lessons Learned Task
not operate the switches to turn on the lights in the cabinets because the
    Force Status Report and Short Term Recommendations." The inspection team noted
switches were not labeled.
    that the extent of the design review fulfilled the additional requirements of                     I
Further licensee action is necessary to correct
    NUREG-0737, paragraph II.B.2, concerning the same subject.   The inspection team
this deficiency.
    evaluated the results of this design review and its impact on the ability of
3.3.4 Reactor Building Accessibility
    operators to perform the emergency actions of the E0Ps.
The licensee performed a design review entitled, " Post-Accident Control of
    The ability of the operators to perform the E0P actions successfully would be
Radiation in Systems Outside Containment of PWRs and BWRs," to meet the
    dependent on access to the reactor and radwaste buildings. Access to the
requirements of paragraph 2.1.6 of NUREG-0578, "TMI-2 Lessons Learned Task
    reactor building was dependent on the specific accident scenario, and access to
Force Status Report and Short Term Recommendations." The inspection team noted
    the radwaste building was dependent on the location of primary system leakage.
that the extent of the design review fulfilled the additional requirements of
    Although the licensee's radiation protection procedures allowed operator entry
NUREG-0737, paragraph II.B.2, concerning the same subject.
    into high radiation level areas under the supervision of radiation protection
The inspection team
    personnel, the E0P contingency actions could not be performed if radiation
evaluated the results of this design review and its impact on the ability of
    levels prevented entry. The design review was based upon the source terms                         l
operators to perform the emergency actions of the E0Ps.
    specified by Pegulatory Guides 1.3 and 1.4 and the accidents of Chapter 14 of                     '
The ability of the operators to perform the E0P actions successfully would be
    the BSEP Final Safety Analysis Report (FSAR). The design review concluded that
dependent on access to the reactor and radwaste buildings. Access to the
    entries into unprotected areas or areas with prohibitively high dose rates
reactor building was dependent on the specific accident scenario, and access to
    would not be required for mitigation of the accidents. However, several areas
the radwaste building was dependent on the location of primary system leakage.
    were identified which could require operator entry during recuvery operations.
Although the licensee's radiation protection procedures allowed operator entry
    The inspection team concluded that multiple methods of implementing the E0P
into high radiation level areas under the supervision of radiation protection
    contingency actions had been adequately considered in the development of the
personnel, the E0P contingency actions could not be performed if radiation
    E0Ps. However, the inspection team identified two actions, during the
levels prevented entry.
    walkthrough of the plant, for which an alternative method of accomplishment had
The design review was based upon the source terms
                                                                                                      l
specified by Pegulatory Guides 1.3 and 1.4 and the accidents of Chapter 14 of
                                            21
'
                                                                          _-_ - _ _ _ _ _ _ _ - _ _ -
the BSEP Final Safety Analysis Report (FSAR). The design review concluded that
entries into unprotected areas or areas with prohibitively high dose rates
would not be required for mitigation of the accidents. However, several areas
were identified which could require operator entry during recuvery operations.
The inspection team concluded that multiple methods of implementing the E0P
contingency actions had been adequately considered in the development of the
E0Ps. However, the inspection team identified two actions, during the
walkthrough of the plant, for which an alternative method of accomplishment had
l
21
_-_
- _ _ _ _ _ _ _ - _ _ -


    _- -
_- -
        .
.
t
t
                      .
              -
.
.
          not been adequately considered.     Further licensee action is necessary to
-
          correct these discrepancies.
.
          1)     The LEP-01 and Primary Containment Flooding Procedure identified several
not been adequately considered.
                  local operator actions to inject service water and demineralized water
Further licensee action is necessary to
                  into the RPV. These actions included opening the residual heat removal
correct these discrepancies.
                  (RHR) loop cross tie valve, Ell F010, in the high pressure core injection
1)
                  (HPCI)systemmezzaninearea. This valve was a normally de-energized
The LEP-01 and Primary Containment Flooding Procedure identified several
                  motor-operated valve whose breaker was removed from its cubical to ensure
local operator actions to inject service water and demineralized water
                  separation of the two trains of RHR. A significant amount of time was
into the RPV.
                  required to operate this valve manually in area in which radiation levels
These actions included opening the residual heat removal
                  could be as high as 20000 R/HR one hour into an accident.   Since this
(RHR) loop cross tie valve, Ell F010, in the high pressure core injection
                  valve had the potential to be operated remotely, further licensee
(HPCI)systemmezzaninearea.
                  consideration should be given to reinstalling the valve breaker rather
This valve was a normally de-energized
                  than attempting manual operation.                                           !
motor-operated valve whose breaker was removed from its cubical to ensure
                                                                                            l
separation of the two trains of RHR.
          2)     SEP-06, step C.24, required the operator to monitor the RHR heat exchanger
A significant amount of time was
                  outlet conductivity at a local instrument in the south RHR room. This     ,
required to operate this valve manually in area in which radiation levels
                  area would have extremely high radiation levels in the accident conditions
could be as high as 20000 R/HR one hour into an accident.
                  during which performance of the step would be required. The inspection     I
Since this
                  team noted that control room panel alarm, A-03, tile 2-10, monitored the   i
valve had the potential to be operated remotely, further licensee
                  desired location and alarmed at the value specified in the E0P (i.e., 10
consideration should be given to reinstalling the valve breaker rather
                  umho/cm). Further licensee action is necessary to ensure that remote
than attempting manual operation.
                  instrumentation is used where possible in lieu of local monitoring in high
2)
                  radiation areas.                                                           ;
SEP-06, step C.24, required the operator to monitor the RHR heat exchanger
                                                                                            i
outlet conductivity at a local instrument in the south RHR room.
          3.4 E0P Validation Using Plant Simulator                                         j
This
                                                                                            i
,
          To ensure that the E0Ps could be implemented correctly under emergency           j
area would have extremely high radiation levels in the accident conditions
          conditions, the inspection team developed and performed four accident scenarios   l
during which performance of the step would be required.
          utilizing licensed operators. The accident scenarios determined whether the       )
The inspection
          E0Ps provided the operators with sufficient guidance and clearly outlined their
team noted that control room panel alarm, A-03, tile 2-10, monitored the
          required actions during an emergency; verified whether the E0Ps caused the
desired location and alarmed at the value specified in the E0P (i.e., 10
          operators to interfere physically with each other; verified that the procedures
umho/cm).
          did not duplicate operator actions unless required; and verified that
Further licensee action is necessary to ensure that remote
          transitions from one E0P to another or to other procedures were accomplished
instrumentation is used where possible in lieu of local monitoring in high
          satisfactorily.
radiation areas.
          3.4.1     Scenario Description
i
          The first scenario involved a rupture of the feedwater pump suction header from
3.4 E0P Validation Using Plant Simulator
          100% power with a spurious group 1 isolation signal inserted at the time of the
j
          reactor scram due to low RPV water level. The SRVs opened on high RPV pressure
To ensure that the E0Ps could be implemented correctly under emergency
          following the main steam isolation valve (MSIV) closure. One safety relief
j
          valve (SRV) stuck open and remained open throughout the scenario. One minute
conditions, the inspection team developed and performed four accident scenarios
          after the scram and MSIV isolation, a small steam leak was initiated into the
utilizing licensed operators. The accident scenarios determined whether the
          drywell . The high pressure core injection (HPCI) system, pump B of the control
)
          rod drive (CRD) system, and the loop B heat exchanger of the residual heat
E0Ps provided the operators with sufficient guidance and clearly outlined their
          removal (RHR) system were out of service throughout the event. Following the
required actions during an emergency; verified whether the E0Ps caused the
          reactor scram, the operators performed Path-4 when RPV water level decreased
operators to interfere physically with each other; verified that the procedures
          below +112 inches. The operators exited Path-4 and performed steps RC/L and
did not duplicate operator actions unless required; and verified that
          RC/P of the End Path Procedure concurrently to restore RPV water level and
transitions from one E0P to another or to other procedures were accomplished
          pressure. The operators performed the Primary Containment Control
satisfactorily.
          Procedure to control suppression pool temperature and drywell pressure and
3.4.1
                                                      22
Scenario Description
  _                   ___   _______________ _-
The first scenario involved a rupture of the feedwater pump suction header from
100% power with a spurious group 1 isolation signal inserted at the time of the
reactor scram due to low RPV water level.
The SRVs opened on high RPV pressure
following the main steam isolation valve (MSIV) closure.
One safety relief
valve (SRV) stuck open and remained open throughout the scenario. One minute
after the scram and MSIV isolation, a small steam leak was initiated into the
drywell . The high pressure core injection (HPCI) system, pump B of the control
rod drive (CRD) system, and the loop B heat exchanger of the residual heat
removal (RHR) system were out of service throughout the event.
Following the
reactor scram, the operators performed Path-4 when RPV water level decreased
below +112 inches.
The operators exited Path-4 and performed steps RC/L and
RC/P of the End Path Procedure concurrently to restore RPV water level and
pressure. The operators performed the Primary Containment Control
Procedure to control suppression pool temperature and drywell pressure and
22
_
___
_______________ _-


                                                                              --               __
--
      *
__
    .-
*
                .
.-
  4                                                                                                 i
.
        temperature, and depressurized the RPV in accordance with the End Path                     i
4
        Procedure, when drywell temperature exceeded 300 degrees F.
i
                                                                                                    l
temperature, and depressurized the RPV in accordance with the End Path
        The second scenario exercised the Level / Power Control Procedure with alternate
i
        boron injection. A spurious group 1 isolation signal initiated the event and
Procedure, when drywell temperature exceeded 300 degrees F.
        resulted in a failure of all control rods to scram. Failure of the standby
The second scenario exercised the Level / Power Control Procedure with alternate
        liquid control (SBLC) system to inject along with both reactor water cleanup
l
        (RWCU) system pumps being out of service required the use of the Alternate
boron injection. A spurious group 1 isolation signal initiated the event and
        Boron Injection Procedure using the CRD system. A small break loss of coolant
resulted in a failure of all control rods to scram.
        accident (LOCA) in the drywell required emergency depressurization when drywell
Failure of the standby
        temperature exceeded 300 degrees F. The scram condition required the
liquid control (SBLC) system to inject along with both reactor water cleanup
        performance of Path-1 and eventually the Level / Power Control Procedure for the           l
(RWCU) system pumps being out of service required the use of the Alternate
        ATWS condition. The Primary Containment Control Procedure was used to control
Boron Injection Procedure using the CRD system. A small break loss of coolant
        drywell and suppression pool temperature and pressure.
accident (LOCA) in the drywell required emergency depressurization when drywell
        The third scenario exercised the Secondary Contairiment Control Procedure and
temperature exceeded 300 degrees F.
i       the Radioactive Release Control Procedure. A loss of feedwater resulted in a
The scram condition required the
        reactor scram on low RPV water level coincident with a fuel element failure.
performance of Path-1 and eventually the Level / Power Control Procedure for the
        Maintenance. activities in the HPCI room required the reactor core isolation
l
        cooling (RCIC) to HPCI room door to remain open to allow passage of hoses.
ATWS condition. The Primary Containment Control Procedure was used to control
        When the RCIC system started on low RPV water level a steam leak occurred at
drywell and suppression pool temperature and pressure.
        the RCIC steam inlet valve (F0-45). The steam leak caused a RCIC system
The third scenario exercised the Secondary Contairiment Control Procedure and
        isolation signal. The RCIC steam supply containment isolation valves failed to
i
        isolate and caused a HPCI isolation signal several minutes later due to the
the Radioactive Release Control Procedure. A loss of feedwater resulted in a
        open door between the two rooms. The scram coincident with an RPV level below
reactor scram on low RPV water level coincident with a fuel element failure.
l       +112 inches required performance of Path-4. The radioactive steam leak in
Maintenance. activities in the HPCI room required the reactor core isolation
        secondary containment required performance of the Secondary Containment Control
cooling (RCIC) to HPCI room door to remain open to allow passage of hoses.
When the RCIC system started on low RPV water level a steam leak occurred at
the RCIC steam inlet valve (F0-45). The steam leak caused a RCIC system
isolation signal.
The RCIC steam supply containment isolation valves failed to
isolate and caused a HPCI isolation signal several minutes later due to the
open door between the two rooms. The scram coincident with an RPV level below
l
+112 inches required performance of Path-4. The radioactive steam leak in
'
'
        Procedure.   Exceeding the reactor building roof vent annunciator setpoint
secondary containment required performance of the Secondary Containment Control
        required performing the Radiological Release Control Procedure. When the
Procedure.
        operators determined that more than one area had exceeded its maximum safe
Exceeding the reactor building roof vent annunciator setpoint
        operating radiation level, the End Path Procedure required emergency
required performing the Radiological Release Control Procedure. When the
        depressurization.
operators determined that more than one area had exceeded its maximum safe
operating radiation level, the End Path Procedure required emergency
depressurization.
l
l
        The fourth scenario required venting primary containment to control primary
The fourth scenario required venting primary containment to control primary
.
.
        containment hydrogen concentrations. RHR loop B was out of service throughout
containment hydrogen concentrations.
RHR loop B was out of service throughout
l
l
        the scenario. A lar
emergency bus (E-3) ge break LOCA coincident with a failure of the 4160 vcit
        emergency bus (E-3)       ge break
the scenario. A lar
                              initiated     LOCA
initiated a reactor scram and an ECCS actuation. The A
                                        a reactor   coincident
loop RHR injection valve failed to open, leaving only one core spray (CS) pump
                                                  scram and an with
available for injection.
                                                                  ECCSa failure
The reactor core was uncovered, resulting in fuel
                                                                        actuation.of the
,
                                                                                      The4160
damage and the release of hydrogen to the primary containment. The scram with
                                                                                          A vcit
high drywell pressure required performance of Path-5 and the Primary
        loop RHR injection valve failed to open, leaving only one core spray (CS) pump             ,
Containment Control Procedure.
        available for injection.     The reactor core was uncovered, resulting in fuel
The loss of power to emergency bus E-3
        damage and the release of hydrogen to the primary containment. The scram with
unexpectedly resulted in the inability of the operators to perform the primary
        high drywell pressure required performance of Path-5 and the Primary
containment venting procedure because the torus purge exhaust valve, CAC V-8,
        Containment Control Procedure.     The loss of power to emergency bus E-3
was powered from emergency bus E-3.
        unexpectedly resulted in the inability of the operators to perform the primary
Further licensee action is necessary to
        containment venting procedure because the torus purge exhaust valve, CAC V-8,
ensure that an alternate method is available to vent the primary containment
        was powered from emergency bus E-3.     Further licensee action is necessary to
ouring a partial loss of power condition.
        ensure that an alternate method is available to vent the primary containment
3.4.2 Limitations of the Plant-Specific Simulator
        ouring a partial loss of power condition.
The plant-specific simulator located on-site was used for the E0P scenarios.
        3.4.2 Limitations of the Plant-Specific Simulator
The simulator demonstrated extremely poor modeling with respect to decay heat
        The plant-specific simulator located on-site was used for the E0P scenarios.
and RPV water level response.
        The simulator demonstrated extremely poor modeling with respect to decay heat
For example, during scenarios in which all high
        and RPV water level response. For example, during scenarios in which all high
pressure injection had failed and with mass being removed by open SRVs or a
        pressure injection had failed and with mass being removed by open SRVs or a
23
                                                  23                                               1
1


                                                                                                                                                                                              '
f
                    ,, .                                                                                                                                                                         f
'
                                                                              .
,, .
                                                                        *
.
.
                                                                    small break LOCA, RPV water level would continue to increase. Following
*
                                                                  MSIV isolations from 100 percent power with end of life (COL) decay heat
.
                                                                    loading and no steam being drawn off by the HPCI or RCIC systems, it was not
small break LOCA, RPV water level would continue to increase.
                                                                  necessary to use the SRVs to control RPV pressure. In fact, RPV pressure would
Following
                                                                  decrease with no external energy removal in progress. As a result, the RC/L
MSIV isolations from 100 percent power with end of life (COL) decay heat
                                                                  steps of Path-1 were not able to be simulated past the initial entry steps.
loading and no steam being drawn off by the HPCI or RCIC systems, it was not
                                                                  The inspection team concluded that the plant-specific simulator was not.an
necessary to use the SRVs to control RPV pressure.
                                                                  effective tool for operator training on the Level / Power Control Procedure, E0P
In fact, RPV pressure would
                                                                  Path-5, or any of the E0P steps requiring level control manipulations. As
decrease with no external energy removal in progress. As a result, the RC/L
                                                                  previously discussed in Section 3.1.2, the simulator modeling deficiencies also
steps of Path-1 were not able to be simulated past the initial entry steps.
                                                                  adversely affected the ability of the licensee to perform validation for any
The inspection team concluded that the plant-specific simulator was not.an
                                                                  E0P steps which required level manipulations.
effective tool for operator training on the Level / Power Control Procedure, E0P
                                                                  3.4.3 Observations and Conclusions
Path-5, or any of the E0P steps requiring level control manipulations. As
                                                                  The inspection team concluded that the operating crew could satisfactorily-
previously discussed in Section 3.1.2, the simulator modeling deficiencies also
                                                                    implement the E0Ps to shutdown the reactor and return the plant to a safe,
adversely affected the ability of the licensee to perform validation for any
                                                                  stable condition. Overall, the operators performed well and demonstrated a
E0P steps which required level manipulations.
                                                                  good understanding of the E0Ps which was indicative of a high level of training
3.4.3 Observations and Conclusions
                                                                  on the procedures. As discussed in Section 3.1.1, the inspection team
The inspection team concluded that the operating crew could satisfactorily-
                                                                  concluded that the timely implementation and execution of the E0Ps required the
implement the E0Ps to shutdown the reactor and return the plant to a safe,
                                                                  active participation and assistance of the STA because the licensee included
stable condition. Overall, the operators performed well and demonstrated a
                                                                  the post-trip actions in the E0Ps and developed overly complex procedures. The
good understanding of the E0Ps which was indicative of a high level of training
                                                                    inspection team identified concerns in the following two areas.
on the procedures. As discussed in Section 3.1.1, the inspection team
                                                                    1)   Control Room Responsibilities - During all four scenarios, the inspection
concluded that the timely implementation and execution of the E0Ps required the
                                                                          team observed that the shift foreman (SF) directly supervised the two                                                 ,
active participation and assistance of the STA because the licensee included
                                                                          control operators and directed the performance of the E0Ps and that the                                               l
the post-trip actions in the E0Ps and developed overly complex procedures. The
                                                                          shift operating supervisor (SOS) monitored the emergency plan and
inspection team identified concerns in the following two areas.
                                                                          performed the required notifications.                   The shift technical assistant (STA)
1)
                                                                          monitored the emergency response facility information system (ERFIS) and
Control Room Responsibilities - During all four scenarios, the inspection
                                                                          available control room indications for key parameters and trends. In                                                   I
team observed that the shift foreman (SF) directly supervised the two
                                                                          addition, the STA monitored changing plant conditions to identify E0P                                                 J
,
                                                                          entry conditions and to advise the SF regarding the required actions. The
control operators and directed the performance of the E0Ps and that the
                                                                          inspection team also noted that the STA performed E0P steps in legs which
l
                                                                          the SF did not have time to execute. This was particularly evident in the                                             <
shift operating supervisor (SOS) monitored the emergency plan and
                                                                          third scenario involving the Secondary Containment Control Procedure.                                                 1
performed the required notifications.
                                                                          The BSEP administrative instructions required the STA to provide an
The shift technical assistant (STA)
                                                                          overview of the plant conditions and ensure that all the required E0P
monitored the emergency response facility information system (ERFIS) and
                                                                          steps were completed. In actual practice, the STA independently performed
available control room indications for key parameters and trends.
                                                                          portions of the E0Ps in order to provide more time for the SF to read and
In
                                                                          complete the post-trip scram recovery actions of the E0Ps. The inspection
I
                                                                          team concluded that the level of detail of the BSEP E0Ps did not permit a
addition, the STA monitored changing plant conditions to identify E0P
                                                                          single individual sufficient time to direct the performance of all
J
                                                                          required actions of the E0Ps.
entry conditions and to advise the SF regarding the required actions. The
                                                                          The inspection team also observed that the SF was not able to perfom all
inspection team also noted that the STA performed E0P steps in legs which
                                                                          the parallel steps as required by the BWROG EPGs. This was clearly
the SF did not have time to execute.
                                                                          demonstrated in the first scenario involving the performance of the
This was particularly evident in the
                                                                          Primary Containment Control Procedure. During the scenario, the SF
<
                                                                          completed only two steps of the five required parallel flowpaths (i.e.,
third scenario involving the Secondary Containment Control Procedure.
                                                                          DW/T and PC/P). The remaining three flowpaths (i.e., SP/T, SP/L, and
1
                                                                          PC/H) were not performed. Another example occurred in the third scenario
The BSEP administrative instructions required the STA to provide an
                                                                                                                          24
overview of the plant conditions and ensure that all the required E0P
- _ _ _ - - _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ -                                         _ _ _ _ _ ______ _ __               -_       _ _ - _ _ - _ _ _ - _ _ _ - _ - _ _
steps were completed.
In actual practice, the STA independently performed
portions of the E0Ps in order to provide more time for the SF to read and
complete the post-trip scram recovery actions of the E0Ps.
The inspection
team concluded that the level of detail of the BSEP E0Ps did not permit a
single individual sufficient time to direct the performance of all
required actions of the E0Ps.
The inspection team also observed that the SF was not able to perfom all
the parallel steps as required by the BWROG EPGs. This was clearly
demonstrated in the first scenario involving the performance of the
Primary Containment Control Procedure.
During the scenario, the SF
completed only two steps of the five required parallel flowpaths (i.e.,
DW/T and PC/P).
The remaining three flowpaths (i.e., SP/T, SP/L, and
PC/H) were not performed. Another example occurred in the third scenario
24
- _ _ _ - - _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ -
_ _ _ _ _ ______ _ __
- _
_ _ - _ _ - _ _ _ - _ _ _ - _ - _ _


      *
*
    ,,
,,
                  .
.
            *
*
  .
+
                                                                                                +
.
              involving the Secondary Containment Control Procedure. During this
involving the Secondary Containment Control Procedure.
              scenario, the SF completed only one of the three required parallel
During this
              flowpaths (i .e. , SC/R). In this example, the SF directed the control
scenario, the SF completed only one of the three required parallel
              operator to obtain the area radiation levels from the back panel, but not
flowpaths (i .e. , SC/R).
          -
In this example, the SF directed the control
              the area temperature and level readings. The failure to execute all legs
operator to obtain the area radiation levels from the back panel, but not
              of the E0Ps potentially prevents monitoring and control of all symptoms
the area temperature and level readings. The failure to execute all legs
              indicative of an accident condition. As discussed in Section 3.1.1,
-
              further licensee action is necessary to (1) accurately define and
of the E0Ps potentially prevents monitoring and control of all symptoms
              implement the control room responsibilities of the STA and SF during E0P.
indicative of an accident condition. As discussed in Section 3.1.1,
              performance, (2) remove the event-based actions from the E0Ps, and (3)
further licensee action is necessary to (1) accurately define and
              reduce the level of complexity of the E0Ps.
implement the control room responsibilities of the STA and SF during E0P.
        2)   Critical Action Steps - Critical action step RR-5 in the Radioactive
performance, (2) remove the event-based actions from the E0Ps, and (3)
                                                                    -                                 ,
reduce the level of complexity of the E0Ps.
              Release Control Procedure required the operators to execute the subsequent              )
2)
              actions of the flowpath only if an ALERT was not declared as a result of a              i
Critical Action Steps - Critical action step RR-5 in the Radioactive
              radioactive release. As discussed in Section 3.1.1, these actions were                  l
-
l            event-based and not appropriate for inclusion in the E0Ps. Durir.g the                    l
              third scenario, the_ STA and SF performed these action steps after an ALERT
              had been declared. Although in direct conflict with the procedural
              requirement of step RR-5, the licensee's training staff indicated that it
              was desirable to perform these action steps even after an ALERT had been
              declared. Further licensee action is required to correctly train and
              implement the critical actlon of step RR-5.
,
,
              During the third scenario, the operators incorrectly performed emergency
Release Control Procedure required the operators to execute the subsequent
!            depressurization in accordance with the End Path Procedure because they
)
              missed critical action step 64 of the Level / Power Control Procedure. As a
actions of the flowpath only if an ALERT was not declared as a result of a
              result, the operators bypassed the cautions concerning power oscillations
i
              during an ATWS contained in the procedure. Although, the SF correctly                   i
radioactive release. As discussed in Section 3.1.1, these actions were
              controlled injection flows and reactor power level, he subsequently
l
              indicated that he did so as a result of his previous training and had
l
              missed the precautions of the critical action step.
event-based and not appropriate for inclusion in the E0Ps. Durir.g the
l
third scenario, the_ STA and SF performed these action steps after an ALERT
had been declared. Although in direct conflict with the procedural
requirement of step RR-5, the licensee's training staff indicated that it
was desirable to perform these action steps even after an ALERT had been
declared.
Further licensee action is required to correctly train and
implement the critical actlon of step RR-5.
During the third scenario, the operators incorrectly performed emergency
,
depressurization in accordance with the End Path Procedure because they
!
missed critical action step 64 of the Level / Power Control Procedure. As a
result, the operators bypassed the cautions concerning power oscillations
during an ATWS contained in the procedure.
Although, the SF correctly
i
controlled injection flows and reactor power level, he subsequently
indicated that he did so as a result of his previous training and had
missed the precautions of the critical action step.
'
The operators used a marker to maintain peacekeeping within the E0Ps and
to note critical action steps and, as a result, were able to explain
accurately where they were in each of the flowcharts.
However, the
scenarios demonstrated that they experienced difficulty in identifying and
'
'
              The operators used a marker to maintain peacekeeping within the E0Ps and
              to note critical action steps and, as a result, were able to explain
              accurately where they were in each of the flowcharts. However, the
,
,
              scenarios demonstrated that they experienced difficulty in identifying and                '
monitoring the override requirements of critical action steps.
              monitoring the override requirements of critical action steps. Because
Because
              missing a critical action step has a significant potential to result in                   .
missing a critical action step has a significant potential to result in
              severe core damage, the inspection team concluded that further licensee                 l
.
              action is necessary to identify, train, and procedurally support a more
severe core damage, the inspection team concluded that further licensee
              effective method for monitoring the critical action steps.
l
        3.5 Operator Interviews
action is necessary to identify, train, and procedurally support a more
                                                                                                      i
effective method for monitoring the critical action steps.
        The inspection team conducted interviews with three shift operating                         '
3.5 Operator Interviews
                                                                                                      -
i
        supervisors, four control operators, and one auxiliary operator. These
The inspection team conducted interviews with three shift operating
        interviews developed information on the effectiveness of the E0Ps and did not               ;
-'
        examine the qualifications of the operators. Each interview lasted                           !
supervisors, four control operators, and one auxiliary operator. These
        approximately one hour. The following observations summarize the comments                     i
interviews developed information on the effectiveness of the E0Ps and did not
        volunteered by the operators.
;
                                                  25
examine the qualifications of the operators.
                                                      __- _ _ - _ - _ _ _- __-_ _ ____-__ _ ___   ___
Each interview lasted
!
approximately one hour. The following observations summarize the comments
i
volunteered by the operators.
25
__- _ _ - _ - _ _ _- __-_ _ ____-__ _ ___
___


      *
*
    ..
..
                  *
*
                .
.
  e                         .                 .
e
        3.5.1 Observations and Conclusions
.
        1)   Equi   ament Design - The operators experienced difficulty in locating and
.
              reacaing several valves outside the control room. For example, the
3.5.1 Observations and Conclusions
              operators suggested cutting a manhole in the grate that covered the
1)
              condensate header valve, C0-V304, to enhance the accessibility from above.
Equi ament Design - The operators experienced difficulty in locating and
              In addition, the operators also suggested implementing hardware
reacaing several valves outside the control room.
              modifications to make the valve more easily accessible and labeling the       .
For example, the
              RCIC CST suction valve, CO-V301, on a nearby wall to clarify its location. !
operators suggested cutting a manhole in the grate that covered the
              Although the E0P provided location information, the operators indicated     )
condensate header valve, C0-V304, to enhance the accessibility from above.
              that the use of signs would' aid performance of the E0Ps.
In addition, the operators also suggested implementing hardware
        2)   Assignment of Duties - The E0Ps clearly defined the number and
modifications to make the valve more easily accessible and labeling the
              qualifications of operations personnel required for executing the E0Ps.
.
              Major tasks and duty assignments were clearly delineated and unambiguous.   j
!
              The operating instructions delineated the basic philosophy and established i
RCIC CST suction valve, CO-V301, on a nearby wall to clarify its location.
              practices for personnel assignments.                                       l
Although the E0P provided location information, the operators indicated
        3)   0)erator Training - All SFs and C0s had received preliminary training on
)
              tie use of the draft EOPs. Approximately two weeks of combined classroom   l
that the use of signs would' aid performance of the E0Ps.
              and simulator training were devoted to the use of E0PS; however, formal     !
2)
              training on the E0Ps for the A0s had not yet been accomplished. The
Assignment of Duties - The E0Ps clearly defined the number and
              operators indicated that additional training was scheduled before the
qualifications of operations personnel required for executing the E0Ps.
              draft E0Ps would be implemented. Ir general, the operators considered
Major tasks and duty assignments were clearly delineated and unambiguous.
              their training on the E0Ps to be adequate; however, more training would be
j
              beneficial. Some operators expresseii concern regarding the transfer of
The operating instructions delineated the basic philosophy and established
              training betweer. the new procedures end the old procedures.
i
        4)   Validation and Verification of E0Ps - The verification and validation of
practices for personnel assignments.
              the E0Ps included a combination of system walkthroughs and simulator
l
              exercises. In addition, operator training accomplished portions of the
3)
l             verification and validation process.     For example, verification of the
0)erator Training - All SFs and C0s had received preliminary training on
              technical adequacy for selected E0Ps was performed during classroom       .
tie use of the draft EOPs. Approximately two weeks of combined classroom
                                                                                          '
l
              discussions.
and simulator training were devoted to the use of E0PS; however, formal
        5)   System for Making Changes to E0Ps - A fonnal system existed for making
!
              changes to the E0Ps. The operators submitted changes to the E0Ps in
training on the E0Ps for the A0s had not yet been accomplished.
              accordance with Operating Instruction 01-28.
The
        6)   Calculations - The E0Ps required the operators to perform very few
operators indicated that additional training was scheduled before the
              calculations and did not require complex calculations.
draft E0Ps would be implemented.
        7)   E0P Availability - All the E0Ps were located within the control room and
Ir general, the operators considered
i             were inraediately accessible by the operators. All of the operators
their training on the E0Ps to be adequate; however, more training would be
              reported that there were no problems in locating and retrieving the
beneficial. Some operators expresseii concern regarding the transfer of
training betweer. the new procedures end the old procedures.
4)
Validation and Verification of E0Ps - The verification and validation of
the E0Ps included a combination of system walkthroughs and simulator
exercises.
In addition, operator training accomplished portions of the
l
verification and validation process.
For example, verification of the
technical adequacy for selected E0Ps was performed during classroom
'
discussions.
.
5)
System for Making Changes to E0Ps - A fonnal system existed for making
changes to the E0Ps.
The operators submitted changes to the E0Ps in
accordance with Operating Instruction 01-28.
6)
Calculations - The E0Ps required the operators to perform very few
calculations and did not require complex calculations.
7)
E0P Availability - All the E0Ps were located within the control room and
i
were inraediately accessible by the operators. All of the operators
'
'
              required E0Ps needed to perform a spccific function. Nevertheless, the
reported that there were no problems in locating and retrieving the
              inspection team believed that further consideration should be given to
required E0Ps needed to perform a spccific function.
              locating the E0Ps which would be required to be performed outside the
Nevertheless, the
              control rocm at a locally accessible area. NVP.EG-0899 required that the
inspection team believed that further consideration should be given to
              procedures be available at all locations in the plant where equipment is
locating the E0Ps which would be required to be performed outside the
              to be manually operated under emergency conditions.
control rocm at a locally accessible area.
        8)   Communications - The operators considered the communications inside the
NVP.EG-0899 required that the
              control room to be adequate and reported no conditions where it was hard
procedures be available at all locations in the plant where equipment is
to be manually operated under emergency conditions.
8)
Communications - The operators considered the communications inside the
control room to be adequate and reported no conditions where it was hard
,
,
                                                  26
26
l
l


                                                                                          _
_
      *
*
    .i
.i
  ,
,
                  *
*
                .
.
            '
'
  .
.
              to hear or convey verbal instructions in the control room. All operators
to hear or convey verbal instructions in the control room. All operators
              expressed the need to keep the number of personnel in the control room to
expressed the need to keep the number of personnel in the control room to
              a minimum during en emergency. The operators identified that communica-
a minimum during en emergency. The operators identified that communica-
              tions would be difficult in the diesel building and the RHR pump room (-17
tions would be difficult in the diesel building and the RHR pump room (-17
              level) during an emergency. The inspection team noted that communications
level) during an emergency. The inspection team noted that communications
              from outside the control room were only available through the PA system
from outside the control room were only available through the PA system
              and that the availability of radios as an alternative mode for communica-
and that the availability of radios as an alternative mode for communica-
              tions would be a valuable asset.
tions would be a valuable asset.
        3.6 Primary Containment Venting Provisions
3.6 Primary Containment Venting Provisions
        The inspection team reviewed the " Primary Containment Venting Procedure,"
The inspection team reviewed the " Primary Containment Venting Procedure,"
        E0P-01-SEP-01, to determine the adequacy of the procedure and the feasibility
E0P-01-SEP-01, to determine the adequacy of the procedure and the feasibility
        of the vent paths. The inspection team also reviewed the results of the
of the vent paths.
        special Probabilistic Risk Assessment based operational safety inspection
The inspection team also reviewed the results of the
        cor. ducted by the NRC in March 1988. The inspection team performed a
special Probabilistic Risk Assessment based operational safety inspection
l       walkthrough of all primary containment vent paths which had not previously been
cor. ducted by the NRC in March 1988. The inspection team performed a
l       examined during the earlier inspection, and verified that all necessary
l
        equipment was available.
walkthrough of all primary containment vent paths which had not previously been
        The Primary Containment Control Procedure initiated venting of the primary
l
        containment, irrespective of the off-site release rate, for conditions of high       l
examined during the earlier inspection, and verified that all necessary
        pressure (i.e., 70 psig in step PC/P-12) and for conditions of high hydrogen or     i
equipment was available.
        oxygen (i.e., 6 percent and 5 percent, respectively, in step PC/H-16). The           i
The Primary Containment Control Procedure initiated venting of the primary
        shift foreman had the final authority for venting the primary containment under
containment, irrespective of the off-site release rate, for conditions of high
        these conditions.
l
                                                                                              4
pressure (i.e., 70 psig in step PC/P-12) and for conditions of high hydrogen or
        The licensee had established hard pipe vent paths which were capable of             l
i
        removing the decay heat load required by Revision 4AF of the BWROG EPGs.           I
oxygen (i.e., 6 percent and 5 percent, respectively, in step PC/H-16). The
        E0P-01-SEP-01 preferentially listed the vent paths from the small bore pipe to
i
        the large bore piping, to control the primary containment pressure. All the
shift foreman had the final authority for venting the primary containment under
        vent paths were monitored release paths that permitted off-site dose
these conditions.
        calculations to be performed. Although the vent paths used hard piping, low
4
        pressure ducting was installed at transitions to the standby gas treatment
The licensee had established hard pipe vent paths which were capable of
        (SBGT) system and the reactor building purge exhaust system fans. A recent
l
        study completed by the licensee concluded that the pressure at the fan duct
removing the decay heat load required by Revision 4AF of the BWROG EPGs.
        work could exceed acceptable limits and a further evaluation was in progress at
I
        the time of inspection. This evaluation should be completed in a timely manner
E0P-01-SEP-01 preferentially listed the vent paths from the small bore pipe to
        by the licensee.
the large bore piping, to control the primary containment pressure. All the
        The inspection team was also concerned about the ability of the operators to
vent paths were monitored release paths that permitted off-site dose
        establish a vent path during reduced power capability or station blackout
calculations to be performed. Although the vent paths used hard piping, low
        conditions. As discussed in Section 3.4.1, the inspection team noted during
pressure ducting was installed at transitions to the standby gas treatment
        the simulator exercises that the operators were unable to establish a vent path
(SBGT) system and the reactor building purge exhaust system fans. A recent
        to remove simulated excessive hydrogen with the loss of one division of
study completed by the licensee concluded that the pressure at the fan duct
        essential power. Contingency plans were under development by the licensee for
work could exceed acceptable limits and a further evaluation was in progress at
        the conditions of loss of power, including containment venting provisions.
the time of inspection. This evaluation should be completed in a timely manner
        This effort should be completed expeditiously by the licensee.
by the licensee.
        4.0 MANAGEMENT EXIT MEETING
The inspection team was also concerned about the ability of the operators to
        The inspection team conducted an exit meeting on October 7, 1988, with licensee
establish a vent path during reduced power capability or station blackout
        management.   During this meeting, the inspection team identified the inspection
conditions. As discussed in Section 3.4.1, the inspection team noted during
        findings and provided the licensee with an opportunity to question the
the simulator exercises that the operators were unable to establish a vent path
        observations. The inspection team also detailed the scope of the inspection
to remove simulated excessive hydrogen with the loss of one division of
                                                  27
essential power.
                                                                                            I
Contingency plans were under development by the licensee for
the conditions of loss of power, including containment venting provisions.
This effort should be completed expeditiously by the licensee.
4.0 MANAGEMENT EXIT MEETING
The inspection team conducted an exit meeting on October 7, 1988, with licensee
management.
During this meeting, the inspection team identified the inspection
findings and provided the licensee with an opportunity to question the
observations. The inspection team also detailed the scope of the inspection
27
I


f.,*
f.,*
,
,
  '           *
*
          ,,
'
        '
,,
  e
'
    and informed the licensee of the conclusions identified in this report. Mr.                           l
e
    Jim Konklin, Section Chief, Special Team Support and Integration Section,
and informed the licensee of the conclusions identified in this report. Mr.
    Office of Nuclear Reactor Regulation, and Mr. Caudie Julian, Branch Chief,
l
    Operations Branch, Region II, represented NRC management at the final exit
Jim Konklin, Section Chief, Special Team Support and Integration Section,
    meeting. Appendix A identifies the licensee personnel who participated in this
Office of Nuclear Reactor Regulation, and Mr. Caudie Julian, Branch Chief,
    meeting.
Operations Branch, Region II, represented NRC management at the final exit
l                                                                                                           l
meeting. Appendix A identifies the licensee personnel who participated in this
meeting.
l
l
1
1
                                                                                                            l
l
l                                           28
l
                                                                      _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ -
28
_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ -


                                        '
'
        .'
.'
  ,
,
                                                                '
'
  '
'
                                                            .,
.,
                                                          '
'
  e
e
                                                                                            APPENDIX A
APPENDIX A
                                                                                        PERSONNEL CONTACTED
PERSONNEL CONTACTED
                                                      A large number of people, including the following licensee personnel, were
A large number of people, including the following licensee personnel, were
                                                      contacted during the inspection.                                             I
contacted during the inspection.
                                                                                                                                    :
I
                                                            *J. Harness, Plant General Manager
:
                                                            *K. Enzor, Director, Regulatory Compliance                             ,
*J. Harness, Plant General Manager
                                                            *L. Jones, Director, Quality Assurance and Quality Control             i
*K. Enzor, Director, Regulatory Compliance
                                                            *C. Blackmon, Manager, Operations
,
                                                              A. Hegler, Superintendent, Operations
*L. Jones, Director, Quality Assurance and Quality Control
                                                            *W.   Martin, Principal Engineer, On-site Nuclear Safety
i
                                                            *J. Titrington, Principal Engineer, Operations
*C. Blackmon, Manager, Operations
                                                            *M. Sawtschenko, Operations
A. Hegler, Superintendent, Operations
                                                              S. Reynolds, Operations                                             J
*W. Martin, Principal Engineer, On-site Nuclear Safety
                                                              M. Amato, Operations                                                 l
*J. Titrington, Principal Engineer, Operations
                                                            *M.   Williams, Senior Specialist, Operations
*M. Sawtschenko, Operations
l                                                             D. LaBelle, Shift Supervisor, Operations
S. Reynolds, Operations
l                                                             M. Schall, Shift Foreman, Operations
J
M. Amato, Operations
l
*M. Williams, Senior Specialist, Operations
l
D. LaBelle, Shift Supervisor, Operations
l
M. Schall, Shift Foreman, Operations
l
E. Hutt, Shift Foreman, Operations
l
l
                                                              E. Hutt, Shift Foreman, Operations                                  l
l
l
                                                              K. Chism, Shift Foreman, Operations                                 i
K. Chism, Shift Foreman, Operations
i
K. Horn, Shift Foreman, Operations
'
'
                                                              K. Horn, Shift Foreman, Operations
R. Gibbs, Shift Technical Advisor, Operations
                                                              R. Gibbs, Shift Technical Advisor, Operations
l
l                                                             H. Harrelson, Operations
H. Harrelson, Operations
                                                              R. Mullis, Operations
R. Mullis, Operations
                                                              D. Best, Operations
D. Best, Operations
                                                              B. Jones, Operations
B. Jones, Operations
                                                              D. Jenkins, Operations
D. Jenkins, Operations
                                                              R. Blair, Operations
R. Blair, Operations
                                                              R. Knight, Operations
R. Knight, Operations
                                                              R. Poulk, Regulatory Compliance
R. Poulk, Regulatory Compliance
                                                            *T. Jones, Regulatory Compliance
*T. Jones, Regulatory Compliance
                                                            *J. Moyer, Manager, Training                                           l
*J. Moyer, Manager, Training
                                                              E. Hawkins, Training
l
                                                            *M.   Shealy, Project Specialist', Training
E. Hawkins, Training
                                                            *B. Strickland, Project Specialist, Operations
*M. Shealy, Project Specialist', Training
                                                            *A. Schmich, Senior Specialist, Corporate Nuclear Licensing
*B. Strickland, Project Specialist, Operations
                                                      * Denotes those personnel present at the exit meeting on October 7, 1988.
*A. Schmich, Senior Specialist, Corporate Nuclear Licensing
* Denotes those personnel present at the exit meeting on October 7, 1988.
I
I
                                                                                                A-1
A-1
                                                                                                                                  ,
,
h   _ . _ . _ _ _ . _ _ _ _ _ _ _ _ _ - . _ . . _ _ _
h
_ . _ . _ _ _ . _ _ _ _ _ _ _ _ _ - . _ . . _ _ _


      *
*
  &*.
&*.
                                                                                                                  .
.
                                                                                                                  I
I
  a
*
                *
a
            ,,
,,
          '
'
  e
e
                                            APPENDIX B                                                           l
APPENDIX B
                                        DOCUMENTS REVIEWED
l
                                                                                                                  l
DOCUMENTS REVIEWED
                                                                                                                  l
l
        Emergency Procedure Guidelines (EPGs), Revision 4AF, March 1987                                           l
l
        Plant Specific Technical Guideline (PSTG) for EPG Revision 4, Draft D                                     i
Emergency Procedure Guidelines (EPGs), Revision 4AF, March 1987
        EPG/PSTG Step Documentation, Draft D                                                                     l
l
        Appendix A PSTG/EOP Step Documentation, Draft C                                                           l
Plant Specific Technical Guideline (PSTG) for EPG Revision 4, Draft D
        Procedures Generation Package (PGP), August 17, 1983
i
        Administrative Instruction AI-95, " Verification and Validation Program for
EPG/PSTG Step Documentation, Draft D
            EPG, Revision 4, based Emergency Operating Procedures," Draft A
l
        MST-RPS-26R, "Drywell Pressure Setpoint Calibration," Revision 2
Appendix A PSTG/EOP Step Documentation, Draft C
        Engineering Evaluation Report No. 85-0231, Revision 0                                                     l
l
        General Area Personnel Dose Rates Versus Time (post-LOCA)                                                 l
Procedures Generation Package (PGP), August 17, 1983
        Emergency Operating Procedures (E0Ps):
Administrative Instruction AI-95, " Verification and Validation Program for
            E0P-01-UG, " User's Guide," Draft B                                                                 l
EPG, Revision 4, based Emergency Operating Procedures," Draft A
            E0P-01-FP-1, " Path-1," Draft 0                                                                     l
MST-RPS-26R, "Drywell Pressure Setpoint Calibration," Revision 2
            E0P-01-FP-2, " Path-2," Draft E
Engineering Evaluation Report No. 85-0231, Revision 0
            E0P-01-FP-3, " Path-3," Draft E
l
            E0P-01-FP-4, " Path-4," Draft D                                                                     l
General Area Personnel Dose Rates Versus Time (post-LOCA)
            E0P-01-FP-5, " Path-3," Draft D
l
            E0P-0 rPP-5, "End Path Procedure," Draft H
Emergency Operating Procedures (E0Ps):
            E0P-01-LPC-1, " Level / Power Control Procedure," Draft E                                           I
E0P-01-UG, " User's Guide," Draft B
            E0P-02-PCCF, " Primary Containment Contml Procedure," Draft F
l
,            '0P-03-SCCF, " Secondary Containment C   .rol Procedure," Draft G                                   l'
E0P-01-FP-1, " Path-1," Draft 0
l
E0P-01-FP-2, " Path-2," Draft E
E0P-01-FP-3, " Path-3," Draft E
E0P-01-FP-4, " Path-4," Draft D
l
E0P-01-FP-5, " Path-3," Draft D
E0P-0 rPP-5, "End Path Procedure," Draft H
E0P-01-LPC-1, " Level / Power Control Procedure," Draft E
I
E0P-02-PCCF, " Primary Containment Contml Procedure," Draft F
'0P-03-SCCF, " Secondary Containment C
.rol Procedure," Draft G
l
,
l
l
            E0P-04-RRCP, " Radioactivity Release Co.. trol," Draft D
            E0P-01-ALC, " Alternate Level Control," Revision E                                                  i
            E0P-01-AEDP, " Alternate Emergency Depressurization Procedure,"
                        Revision D
            E0P-01-StCP, " Steam Cooling Procedure," Revision A
            E0P-01-FP, "RPV Flooding Procedure," Revision E
            E0P-01-PCFP, " Primary Containment Flooding Procedure," Revision B
            E0P-01-LEP-01, " Alternate Coolant Injection," Revision 005
            E0P-01-LEP-02, " Alternate Control Rod Insertion," Revision 005
            E0P-01-LEP-03, " Alternate Boron Injection," Revision 004
            E0P-01-SEP-01, " Primary Containment Venting," Draft D
            E0P-01-SEP-02, "Drywell Spray Procedure," Draft C                                                  .
                                                                                                                '
            E0P-01-SEP-03, " Suppression Pool Spray Procedure," Draft C
            E0P-01-SEP-04, " Reactor Building HVAC Restart Procedure," Draft C
            E0P-01-SEP-05, " Primary Containment Purging," Draft C
            E0P-01-SEP-06, " Shutdown Following Boron Injection," Draft B
            E0P-01-SEP-07, " Bypassing RWCU Filter Domineralizers," Draft B
            E0P-01-SEP-09, "CRD Flow Maximization," Draft B
        Operating Instructions and Procedures:
            01-28, " Appendix C Writer's Guide for Emergency Operating Procedures
                  (EOPs)," Revision 6
            01-37, " Preparation and Review of the Plant-Specific Technical Guideline
i                  for EPG Revision 2," Revision 001
                                                B-1
'
'
                                                                                _ _ _ _ _ _ _ _ _ - _ _ _ _-_ -
E0P-04-RRCP, " Radioactivity Release Co.. trol," Draft D
E0P-01-ALC, " Alternate Level Control," Revision E
i
E0P-01-AEDP, " Alternate Emergency Depressurization Procedure,"
Revision D
E0P-01-StCP, " Steam Cooling Procedure," Revision A
E0P-01-FP, "RPV Flooding Procedure," Revision E
E0P-01-PCFP, " Primary Containment Flooding Procedure," Revision B
E0P-01-LEP-01, " Alternate Coolant Injection," Revision 005
E0P-01-LEP-02, " Alternate Control Rod Insertion," Revision 005
E0P-01-LEP-03, " Alternate Boron Injection," Revision 004
E0P-01-SEP-01, " Primary Containment Venting," Draft D
E0P-01-SEP-02, "Drywell Spray Procedure," Draft C
.
E0P-01-SEP-03, " Suppression Pool Spray Procedure," Draft C
'
E0P-01-SEP-04, " Reactor Building HVAC Restart Procedure," Draft C
E0P-01-SEP-05, " Primary Containment Purging," Draft C
E0P-01-SEP-06, " Shutdown Following Boron Injection," Draft B
E0P-01-SEP-07, " Bypassing RWCU Filter Domineralizers," Draft B
E0P-01-SEP-09, "CRD Flow Maximization," Draft B
Operating Instructions and Procedures:
01-28, " Appendix C Writer's Guide for Emergency Operating Procedures
(EOPs)," Revision 6
01-37, " Preparation and Review of the Plant-Specific Technical Guideline
i
for EPG Revision 2,"
Revision 001
B-1
'
_ _ _ _ _ _ _ _ _ - _ _ _ _-_ -


l
l
                                                                                1
1
        ,
,
  g,*
g,*
  *               *
*
                ,,
*
              '
,,
  a
'
                PT-16.2, " Primary Containment Volumetric Average Temperature,"
a
                    Revision 20
PT-16.2, " Primary Containment Volumetric Average Temperature,"
                CP-05, " Unit Shutdown," Revision 28
Revision 20
                OP-10. " Standby Gas Treatnient System," Revision 32 (Unit 2)
CP-05, " Unit Shutdown," Revision 28
                OP-17, " Residual Heat Removal System," Revision 77 (Unit 2)
OP-10. " Standby Gas Treatnient System," Revision 32 (Unit 2)
                OP-24, " Containment Atmosphere Control," Revision 26 (Unit 1)
OP-17, " Residual Heat Removal System," Revision 77 (Unit 2)
OP-24, " Containment Atmosphere Control," Revision 26 (Unit 1)
i
i
,
,
)
)
                                                    B-2
B-2
L-______-____-_________________-     _ _ _ _ _ _
L-______-____-_________________-
_ _ _ _ _ _
}}
}}

Latest revision as of 01:29, 23 May 2025

Insp Repts 50-324/88-200 & 50-325/88-200 on 880926-1007. Technical Inaccuracies Noted.Major Areas Inspected:Emergency Operating Procedures,Procedures & Plant Operations Re Human Factors & Primary Containment Venting Procedures
ML20235R342
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 01/25/1989
From: Haughney C, Konklin J, Vandenburgh C
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20235R333 List:
References
50-324-88-200, 50-325-88-200, NUDOCS 8903030263
Download: ML20235R342 (35)


See also: IR 05000324/1988200

Text

_ _ .

.

.

t

"

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

Division of Reactor Inspection and Safeguards

Report Nos.:

50-325/88-200 and 50-324/88-200

Docket Nos.:

50-325 and 50-324

Licensee:

Carolina Power and Light Company

P.O. Box 1551

Raleigh, NC 27602

Inspection At:

Brunswick Steam Electric Plant, Units 1 and 2

Inspection Dates:

September 26 through October 7, 1988

l

~ b' ^-

Team Leader:

l -T5- @

-

C. A. VanDenburgh, Senior Operations

Date Signed

I

Engineer, NRR

.

l

,

Team Members:

G.T. Hopper, Region II

P.R. Farron, Nuclear Engineers and Consultants

D.H. Schultz, Comex Corporation

J.F. Hanek, EG&G Idaho, Incorporated

W.E. Gilmore, EG&G Idaho, Incorporated

Other NRC Personnel Attending Exit Meetings:

J. Konklin, Section Chief NRR;

C. Julian, Branch Chief, Region II; B. Buckley, Project Manager, NRR; and

W. Ruland, Senior Resident Inspector.

l

Reviewed By:

w

/

//ET//f'(

ames E. Konklin, Chief

Ddte Signed

'

Special Team Support

& Integration Section, NRR

Approved By:

(164/4t(

//2Md7

Unarles p. Haughney, Chief

Ddte Signed

Special inspection Branch, NRR

i

8903030263 890223

PDR

ADOCK 03000324

O

PDC

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _

-

-

.

'

,

~

.

Scope:

1

From September 26 through October 7,1988 an NRC inspection team conducted an

'

inspection of the Emergency Operating Procedures (E0Ps) for the Brunswick Steam

Electric Plant (BSEP), Units 1 and 2.

BSEP Units 1 and 2 are General Electric

i

BWR-4 plants with Mark I containments.

The objective of the inspection was to

determine if the E0Ps (1) were technically correct (2) could be physically

carried out in the plant, and (3) could be performed correctly by the

operators.

The inspection team compared Revision 4AF of the BWR Owner's Group (BWROG)

Emergency Procedure Guidelines (EPGs) to the Plant Specific Technical

Guidelines (PSTGs); compared the PSTGs to the E0Ps; reviewed the calculations

performed to develop the plant specific curves, values and setpoints utilized

in the E0Ps; performed a plant walkthrough of all the E0Ps and the Local

l

Emergency Procedures (LEPs) and Supplemental Emergency Procedures (SEPs)

'

referenced by the E0Ps; observed a simulation of four emergency scenarios using

the plant-specific simulator; performed a human factors review of the

procedures and plant operations; interviewed licensed and non-licensed

personnel who utilize the E0Ps; and reviewed the primary containment venting

procedures.

Results:

The inspection was based on a draft of the E0Ps which were in the final stages

of development and were expected to be implemented on December 15, 1988.

The

draft E0Ps incorporated Revision 4AF of the BWROG EPGs.

They corrected

i

l

deficiencies which had been identified during an Operational Safety Assessment

'

and a Probabilistic Risk Assessment based inspection [ Inspection Reports

50-325(324)/88-19 and 50-325(324)/88-11] performed by Region II to evaluate the

E0Ps presently in use.

The inspectors were impressed with the scope of the corrective actions taken in

response to the deficiencies identified during the previous inspections and

with the licensee's controls for the development of the E0Ps. All of the

previous deficiencies had been corrected, and the development process was well

documented and defined.

l

The BSEP E0Ps were developed as post-trip recovery procedures and integrated

the post-trip operator actions with the required actions of the EPGs and the

l

station blackout actions.

The E0Ps provided a high level of detail and

l

prioritized the operators' actions based on the significance of the event. As

a result, however, the E0Ps had a significant potential to delay the required

accident mitigation actions as post-trip recovery actions were accomplished.

The inspection team concluded, based on the simulator scenarios, that the

required EPG actions could not be accomplished in a timely manner without the

direct involvement of both the shift foreman and the shift technical adviscr to

read and perform the E0P action steps. The active participation of both these

individuals was not in accordance with the licensee's administrative

instructions, but was considered by the team to be an adequate method of E0P

accomplishment.

l

The inspection team determined that the draft E0Ps did not in every instance

represent an accurate incorporation of the BWROG EPGs and would not adequately

1

m___._______________.___.__..______________._

_ _ _ _ _ _ _ _ _

.

.

'

.

.

.

assure the successful accomplishment of all specified actions because several

procedures had a low probability of success and several calculational errors

were identified.

Several of the inspection teams' concerns affected the E0P3

which were presently implemented. The licensee was requested to take innediate

action to evaluate and correct these operational concerns.

J

l

l

- _ _ _ . _ . - _ _ . - _ _ _ _ - _ _ _ . . _ _ _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ . _ _ - - . . _ . - -

,-.

-_- _ _ . - , . - _ . . . , - -

_

- - _ - . . . . - _ . , - - _

- - - - . - _

- - , . . - _ - - _ . -

.

.

t

.

-

.

TABLE OF CONTENTS

EMERGENCY OPEP.ATING PROCEDURE INSPECTION at

Brunswick Steam Electric Plant, Units 1 and 2

(Inspection Reports 50-325/88-200and50-324/88-200)

Page

1.0 INSPECTION 0BJECTIVE.........................................

1

2.0

BACKGR0VND.......................................

4

1

..........

3.0 DETAILED INSPECTION

FINDINGS.................................

3

3.1 Emergency Operation Procedure (E0P) Program Evaluation..

3

3.1.1

E0P Development..................................

3

3.1.2 Licensee Verification and Validation of E0Ps.....

4

i

3.1.3

E0P Operator Training............................

5

1

3.1.4 Maintenance of E0Ps..............................

6

3.1.5 Quality Assurance Involvement in PSTG

l

1

Maintenance......................................

6

3.1.6 Licensee Response to IE Information Notice 86-64.

7

3.2 E0P P rocedu re Ve ri fi ca t i on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7

!

3.2.1

EPG/PSTG Comparison..............................

7

I

3.2.2 PSTG/EOP Comparison..............................

12

3.2.3 Calculation Review...............................

13

3.2.4 Adequacy of Writer's

Guide.......................

15

3.2.5 Writer's Guide Implementation....................

16

3.3 E0P Validation Using Plant Walkthroughs.................

17

j

3.3.1 Technical Adequacy of Procedures.................

18

3.3.2 Availability of Special Tools and Equipment......

19

3.3.3 Station Material

Condition.......................

21

3.3.4 Reactor Building Accessibility...................

21

l

3.4 C0P Validation Using Plant Simulator....................

22

3.4.1

Scena rio Des c ri pti on. . . . . . . . . . . . . . . . . . . . . . . . . . . . .

22

,

3.4.2 Limitations of the Plant-Specific Simulator......

23

'

3.4.3 Observations and Conclusions.....................

24

'

3.5 Operator Interviews.....................................

25

3.5.1 Observations and Conclusions.....................

26

3.6 Prima ry Contai nment Venting Provi sions. . . . . . . . . . . . . . . . . .

27

4.0 MANAGEMENT EXIT MEETING......................................

27

Appendix A - PERSONNEL C0NTACTED..................................

A-1

Appendix B - DOCUMENTS REVIEWED...................................

B-1

_ _ .

--

.

- .

. .

!

-

.

'

.

.

.

1.0 INSPECTION OBJECTIVE

l

'

A special team inspection reviewed the licensee's Emergency Operating

Procedures (E0Ps), operator training and plant systems in accordance with NRC

Temporary Instruction (TI) 2515/92 to accomplish the following objectives:

1)

Determine whether the E0Ps conformed to the BWP Owner's Group (BWROG)

Emergency Procedure Guidelines EPGs) and were technically correct for the

BrunswickSteamElectricPlantg{BSEP), Units 1and2.

,

2)

Assess whether the E0Ps could be physically carried out in the plant using

existing equipment, controls, and instrumentation, under the expected

environmental conditions.

3)

Evaluate whether the plant staff could correctly perform the E0P actions

in the time available.

2.0 BACKGROUND

Following the Three Mile Island (TMI) accident, the Office of Nuclear Reactor

Regulation (NRR) developed the "TMI Action Plan," (NUREG-0660 and NUREG-0737).

Item I.C.1 of this plan required licensees of operating plants to reanalyze

transients and accidents and to upgrade E0Ps.

In addition, Item I.C.9 of the

plan required the NRC staff to develop a long-term plan that integrated and

expanded efforts for the writing, reviewing, and monitoring of plant

procedures.

NUREG-0899, " Guidelines for the Preparation of Emergency Operating

and describes the use of a Procedures Generition Package (PGP) pgrading E0Ps,

Procedures," represents the NRC staff's long-term program for u

to prepare E0Ps.

l

The licensees formed four vendor owners groups corresponding to the four major

reactor vendor types in the United States: Westinghouse, General Electric,

Babcock & Wilcox, and Combustion Engineering. Working with the vendor

companies and the NRC, the owner's groups developed generic procedures that set

forth the desired accident mitigation strategy.

For General Electric plants,

the generic guidelines are referred to as the BWR0G EPGs. These guidelines

were to be used by the licensees in developing their PGPs.

Generic Letter 82-33, " Supplement I to NUREG-0737 - Requirements for Emergency

Response Capability," required each licensee to submit to the NRC a PGP which

included, (1) Plant Specific Technical Guidelines (PSTGs) with justification

,

for safety significant differences from the BWROG EPGs, (2) a Plant Specific

Writer's Guideline (PSWG), (3) a description of the program to be used for the

verification and validation of E0Ps, and (4) a description of the training

program for the upgraded E0Ps. The generic letter required the development of

plant-specific E0Ps which would provide the operators with directions to

mitigate the consequences of a broad range of initiating events and subsequent

multiple failures or operator errors.

In addition, the upgraded E0Ps were

required to be symptom-based procedures which would not require the operators

j

to diagnose specific events.

I

Although various circumstances caused long delays in achieving NRC approval of

J

many of the PGPs, the licensees have all implemented their upgraded E0Ps.

To

determine the success of this implementation, a series of NRC inspections was

performed to examine the final product of the program - the E0Ps.

!

i

1

!

.

.

-

l

l

Representative samples of each of the four vendor types were selected for

j

review by four inspection teams from Regions I, II, III and IV.

An additional 13 inspections were identified at facilities with General

Electric Mark I type containments. These inspections were conducted by the

Office of Nuclear Reactor Regulation and included a detailed review of the

primary containment venting provisions of the E0Ps.

This inspection is the

final inspection in this series.

3.0 DETAILED INSPECTION FINDINGS

j

I

3.1 Emergency Operating Procedure (EOP) Program Evaluation

l

3.1.1

E0P Development

A Confirmatory Order dated February 22, 1984, identified that the licensee had

submitted a PGP on August 17, 1983, and implemented upgraded E0Ps.

The PSTG

submitted and the E0Ps currently implemented at the facility were based upon

l

Revision 2 of the BWROG EPGs.

l

l

The inspection team reviewed a draft version of the E0Ps which were based upon

Revision 4AF of the BWROG EPGs.

This revision incorporated a revised accident

mitigation strategy and calculational methods which were approved by the NRC in

a generic safety evaluation report (SER) issued on September 12, 1988.

The

inspection team reviewed the draft E0Ps because the licensee was in the final

stages of implementing this revision and had scheduled full implementation by

December 15, 1988.

Although the inspection was based upon the draft E0Ps, the

l

inspection team verified whether identified deficiencies affected the approved

'

ECPs.

Two operational concerns were identified and are discussed in Sections

3.2.1.1 and 3.2.1.2 of this report.

Both the currently implemented E0Ps and '.he draft E0Ps had been developed in

flowchart format with the post-trip recovery actions and the station blackout

actions integrated with the steps of the BWROG EPG accident mitigation

strategy. The post-trip recovery actions are event-based actions which are

normally provided in separate procedures and are not appropriate for the

symptom-based E0Ps.

The BWROG EPGs and the SER indicated that additional

auxiliary event-specific procedures intended for use in conjunction with the

symptomatic procedures must not contradict or subvert the symptomatic operator

actions specified in the BWROG EPGs.

The inspection team was concerned that the inclusion of the event-based actions

into the E0Ps delayed the accomplishment of the actions directed by the BWROG

EPGs, had the potential to result in incorrect event diagnosis, and affected

l

the ability of the operators to implement the E0Ps and thereby respond to the

emergency in a timely manner. As discussed in Section 3.4.3.1, the simulator

scenarios demonstrated that the shift foreman could not implement the E0Ps, as

required by the licensee's administrative procedures, without the assistance of

the shif t technical advisor to directly monitor and control the specified E0P

actions involving primary containment and radiological release control.

Although operation in this manner was not in accordance with the administrative

procedures, the inspection team concluded that the operating crew could

implement the specified E0P actions to shutdown the reactor and return the

plant to a safe, stable condition. However, the inspection team identified

2

_ _ _ -

_-

_ - _ _ _ _ - _

. _ _ - _ _ _ - _ _ _ _ .

.

.

.

-

.

several examples as a result of this method of implementation, in which

specified E0P actions were not accomplished or were misinterpreted because the

shift foreman and the STA were involved in separate areas of the E0Ps and did

not have the opportunity to consult and review each others actions.

The inspection team identified the following additional examples in which the

E0Ps included event-based actions not related to post-trip recovery actions.

1)

Path-2, steps 35, 60 and 170, precluded the use of the feedwater or

condensate system for reactor pressure vessel (RPV) injection if the

feedwater conductivity was greater than 0.3 mmhos. This was an

event-based action for condenser tube leakaoe which potentially delayed or

prevented recovery from a low RPV water level condition.

2)

Primary Containment Control Procedure, steps PC/P-19 through 22, were

event-based actions for recirculation pump seal failure which were not

related to primary containment control.

3)

In the Radiological Release Control Procedure, all the steps in the five

flowpaths below step RR-6 were event-based actions for identification and

mitigation of primary leakage. Although these steps were necessary in the

event of a primary leak, they wv.e not specified in the BWROG EPG for the

response to a radiological release.

Further licensee action is necessary to ensure that the E0Ps do not contain

event-based actions and to implement the E0Ps in a manner consistent with the

administrative procedures.

,

In addition to including event-based actions in the E0Ps, the licensee

developed the E0Ps with a high level of detail and complexity.

The inspection

team was concerned that the additional detail and unnecessary complexity

represented by the following examples, had the potential to delay the

i

operator's response to an actual emergency.

Further licensee action'is

I

necessary to reduce the level of complexity of the E0Ps.

l

l

1)

Primary Containment Control Procedure, step C.9.e (1), and section 1,

!

included reference to the head spray system, which was no longer

'

applicable because of a plant modification.

The reference should be

'

deleted.

2)

Primary Containment Control Procedure, step PC/M-4, indicated that the

hydrogen monitor readings must be compensated for primary containment

conditions in accordance with operational procedure OP-24.

In practice,

as evidenced by the simulator scenarios, the operators did not consult

OP-24 to determine correction values and there was inadequate time to

perform these calculations.

3)

Path-2 and Path-3 provided multiple steps for initiating suppression pool

cooling. As demonstrated in the simulator exercises, the operators placed

suppression pool cooling into operation without working through each of

these steps.

By contrast, the SP/T path of primary containment control

for operating suppression pool cooling provided direction to the operator

using only a single step.

3

'

.

'

,

.

.

4)

Path-2 was entered following a reactor scram from a condition where the

reactor mode switch was not in RUN. The power level at this condition is

anticipated to be less than approximately eight percent power.

Steps 12,

13 and 17 of this procedure represented actions for tripping the main

turbine, ensuring that turbine auxiliaries started, and tripping the

heater drain pumps. These actions were not appropriate for this power

level and diverted the operators attention from more important activities.

5)

Path-3, step 26, required the operator to set the reactor re irculation

pump speed controllers to minimum; however, this step was not required for

the pump logi: involved.

6)

Radiological Release Control Procedure, steps RR/PB-9 through 11,

identified core cooling systems which -ay be the source of a primary leak;

,

however, these systems were not located in the turbine building and were

therefore not applicable.

7)

Path-3, steps 61 and 85, and Path-2, steps 61 and 85, provided redundant

action steps for RPV pressure control.

P)

Throughout the E0Ps, there were several examples in which multiple action

steps were used to accomplish a single action.

For example, in each leg

of the Primary Containment Control Procedure, the generic monitor and

control steps of the PSTG were restated in one step and the specific

direction on how to accomplish the referenced action was provided in the

subsequent step.

In addition, if a scram was required during the

performance of the Primary Containment Control Procedure, two action steps

were required. The first stated that a reactor scram was required and the

second executed the scram.

,

l

9)

Path-2, steps 80, 90, 91, 99 and 100, and Path-3, steps 79 through 84,

j

provided detailed steps for the operation of the suppression pool cooling

system which were more appropriate for operational procedures.

In

,

addition, these actions should have been covered in a single action step

as accomplished by procedure SP/T-3.

.

3.1.2 Licensee Verification and Validation of E0Ps

i

NUREG-0899, section 3.3.5, indicated that after E0Ps are written they must

i

undergo a process of verification and validation. This process was used to

l

establish the accuracy of information and instructions, to determine that the

'

procedures could be carried out accurately and efficiently, and to demonstrate

that the procedures were adequate to mitigate transients and accidents.

Both

technical and human engineering adequacy were required to be addressed in the

review process.

i

Administrative Instruction AI-95, " Verification and Validation Program for EPG,

Revision 4, based Emergency Operating Procedures," defined the program for

verification and validation of the E0Ps at BSEP.

BSEP administrative

procedures (Volume 1, Book 1, sectic' 5.7.4.1, paragraph A.III.c) required that

all E0P changes receive the review and approval of the E0P Review Committee.

i

The membership of the committee included operations, quality assurance,

technical support, off-site nuclear safet.;, and the licensed training

!

departments.

4

!

!

'

.

.

4

j

lhe verification and validation required for implementation of Revision 4AF of

the BWROG EPGs was identified in an untitled supplement to AI-95. The licensee

indicated that this methodology was reviewed and approved by the E0P Review

Committee on December 14, 1987.

The team was concerned that the specific

methodology for the verification and validation of the substantial changes

represented by the incorporation of Revision 4AF of the BWROG EPGs had not been

specifically identified and approved by the E0P Review Committee.

Further

licensee action is necessary to ensure that the verification and validation

program approved by the E0P Review Comittee is successfully completed prior to

the implementation of the draft E0Ps.

The inspection team's review of the verification and validation program

determined that a mechanism existed for ensuring that all portions of the E0Ps

could be validated using either the plant-specific simulator, plant

l

walkthroughs, or desk top reviews. The preferred validation method was to

perform the E0Ps on the plant simulator.

In instances in which the E0P steps

exceeded the capability of the simulator, a combination plant walkthrough and

desk top review was employed.

In order to ensure that the full complement of

E0Ps were validated, a list of functional objectives to be accomplished by

performing the E0P was developed. The licensee defined the functional

objective of each E0P step and developed exercises to satisfy each functional

objective. The exercises were performed on the plant simulator or by some

combination of simulator exercises and plant walkthroughs.

Problems idantified

during the demonstration of the functional objectives were resolved by the E0P

revision process as described in Al-95.

l

The inspection team was concerned that the identified verification and

I

validation methodology did not indicate that appropriate consideration had been

l

given to the necessity of performing all steps of the E0Ps on the plant

simulator or in table top exercises rather than evaluating them through plant

walkthroughs. Based on the inability of the simulator to accurately model RPV

level and decay heat (previously identified by the licensee and discussed in

Section 3.4.2), it is extremely important to ensure that all steps of the E0Ps

would be effective in fulfilling the actions intended by the BWROG EPGs.

Further licensee action is necessary to ensure that all E0P steps are validated

on a simulator or by an equally acceptable methodology.

3.1.3

E0P Operator Training

A review of the licensee's training program was conducted to determine the

adequacy of operator training prior to implementation of Revision 4 of the

.

EWP0G EPGs.

The inspection team compared the requirements of NUREG-0899, the

l

Procedures Generation Package (PGP), and the operator training program

l

developed for Revision 4.

The PGP contained a detailed description of the initial operator training which

was conducted prior to the initial implementation of the upgraded E0Ps. The

extent of the initial operator training met the requirements of NUREG-0899,

section 3.4

Although the PGP did not specify the operator training require-

ments for revisions to the E0Ps, the licensee required all revisions to be

performed in accordance with Administrative Instruction Al-95, " Verification

and Validation Program for EPG, Revision 4, based Emergency Operating

Procedures." This procedure required that an E0P Review Comittee review

proposed E0P revisions and determine the implementation requirements.

5

___- _ _ _ _ -

_____-

'

.

'

.

.

The inspection team was concerned that these instructions contained no guidance

concerning the scope of operator training required prior to implementation of

revisions to the E0Ps.

Nevertheless, the licensee developed and incorporated a

satisfactory training program into the E0P verification and validation process.

This program was outlined in an untitled supplement to AI-95. The licensee

recognized the need for ongoing operator training on the E0Ps and had

accomplished this goal with periodic licensed operator retraining and the

,

Operator Real Time Training Program described in Operating Instruction 01-33.

This latter program served to complement the annual operator retraining by

accomplishing immediate training needs on a continuing basis.

Interviews with training supervisors indicated that two of the three phases of

training had been completed prior to the time of the inspection. Phase IA was

completed in April 1988 and consisted of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of classroom instruction on

i

the content and use of the new E0Ps.

Phase IB was completed in June 1988 and

l

consisted of 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of classroom instruction cambined with 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> of

simulator training designed to exercise the major branching points within the

E0P flowcharts.

Phase 11 training was conducted in September 1988 and involved

l

four hours of classroom instruction followed by four hours of simulator

exercises.

This brief session served to update operators on changes made to

the E0Ps since completion of Phase IB training.

The final phase of training

(Phase III) was accomplished in December 1988 and served as the final operator

training update prior to implementation of the revised E0Ps.

3.1.4 Maintenance of E0Ps

During the review of the PSTGs and the E0Ps, the team determined that the PSTGs

j

and BWROG EPG Appendix C calculations were being maintained up-to-date as a

basis document ar.d were properly controlled as a plant record by the document

control center.

The E0P calculations based on Revision 2 of the BWROG EPGs

were reviewed and documented in a study entitled ENSA 84-038, "EOP Numerical

Limits and Graphs," and the PSTG was contained in Operating Instruction 01-37,

" Preparation and Review of the Plant Specific Technical Guideline for EPG

Revision 2."

The E0P calculations based on Revision 4 of the BWROG EPGs were

under review by the Nuclear Engineering Department and were scheduled to be

published and the PSTG documented in a similar manner.

3.1.5 Quality Assurance Involvement in PSTG Maintenance

NUREG-0899, section 4.4, indicated that as a primary basis of the E0Ps, the

PS1Gs should be subject to examination under the plants' overall quality

assurance (QA) program.

Because the licensee was responsible for ensuring that

the PSTGs were accurate and up-to-date, the review and control of the PSTGs

shculd be included in the established QA program.

The licensee indicated that QA surveillance 86-067 was performed in December

1986 as a result of E0P development deficiencies identified by the NRC in IE

Information Notice (IEN) 86-64.

In addition, QA Audit QAA/0021-88-05, was

performed in August 1988 on Revision 4 of the E0Ps and identified one follow-up

item concerning justification 'of BWROG EPG deviations.

Future audit schedules

included a site QA surveillance, similar in scope to surveillance 86-067,

scheduled for the first quarter of 1989 and annually thereafter.

6

_

___ _

-

-

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

'

.

'

.

.

.

3.1.6 Licensee Response to IE Information Notice 86-64

IEN 86-64 was issued on August 14, 1986, followed by IEN 86-64, Supplement 1,

issued on April 20, 1987.

IEN 86-64 alerted the licensee to problems found in

review and audits of Procedure Generation Packages (PGPs) and E0Ps. The IEN

indicated that many utilities had not appropriately developed or implemented

upgraded E0Ps.

In addition, the IEN identified deficiencies in the development

and implementation of each of the four major aspects of the upgrade program.

These deficiencies included undocumented deviations from and inappropriate

adaptation of BWROG EPGs, failure to adhere to the PSWG and the verification

and validation programs, and deficient training programs.

Supplement 1 to IEN

86-64 alerted the licensee's to significant problems that were continuing with

plant E0Ps. Deficiencies were identified in all the major aspects of the E0P

upgrade program.

The licensee's were requested to review the information for

applicability to their facility and consider actions to correct or preclude

similar problems from occurring.

The licensee's evaluation process for IENs was performed in accordance with

Corporate huclear Safety Instruction CNSI-I and On-Site Nuclear Safety

Instruction ONSI-1.

The IENs were reviewed by the nuclear safety coordinator

,

and assigned to responsible engineers for evaluation.

IEN 86-64 and Supplement

1 were evaluated by the coordinator and closed because a OA surveillance,

'

discussed in Section 3.1.5, had already been initiated and had identified

similar deficiencies. The inspection team concluded that the licensee's

actions in response to IEN 86-64 were satisfactory.

.

3.2 E0P Procedure Verification

This portion of the inspection was performed to determine whether the E0Ps had

been prepared in accordance with the BWROG EPGs, the PSTGs, and the PGP.

l

The inspection ccmpared Revision 4AF of the BWR0G EPGs to the PSTGs, and the

PSTGs to the E0Ps.

All differences were evaluated to ensure that safety

significant deviations were identified and that a documented basis existed for

all deviations. A review of selected calculations was performed to ensure that

plant-specific values utilized in the E0Ps were correct and had been performed

in accordance with a documented engineering analysis. Appendix B of this

report lists the procedures reviewed.

3.2.I

FPG/PSTG Comparison

Nine differences were identified between the BWROG EPGs and the PSTGs as

detailed below.

Based on these discrepancies, the inspection team concluded

that the draft PSTGs did not accurately incorporate the guidance of Revision

4AF of the BWROG EPGs. The inspection team identified technical concerns

relating to the measurement of RPV water level, which adversely affected the

I

operator's ability to perform the level / power control procedure, and technical

I

concerns relating to the measurement of primary containment drywell temperature,

which potentially raasked a valid entry condition.

These concerns affected both

the E0Ps which were currently implemented at the facility (Revision 2) and the

draft E0Ps.

In addition, numerous discrepancies were identified in the draft

i

'

E0Ps in which the entry conditions of the PWROG EPGs were changed without

sufficient technical justification.

Further licensee action is necessary to

l

evaluate and correct the E0Ps presently in use and to ensure that the draft

!

E0Ps accurately incorporate the technical guidance of the BWROG EPGs.

7

. _ _ - - _ _ _ _

___

_

,

'

.

S

-

.

1)

BWROG EPG Contingency No. 7 provided a methodology to control reactor

power following an anticipated transient without scram (ATWS).

This

methodology involved lowering the RPV water level to the top of active

fuel (TAF) or to the minimum steam cooling water level (MSCWL).

The

licensee implemented these actions in the Level / Power Control Procedure.

BWROG EPG Caution ho. 1 provided operator precautions related to the

nieasurement of RPV water level and the accuracy of various water level

instruments. The licensee implemented these precautions in Caution No. 1

of the User's Guide. The inspection team reviewed the methodology and

precautions for ATWS power level control implemented by the licensee and

identified several undocumented and unjustified deviations which adversely

affected the ability of the operators to control reactor power.

These

deviations involved (1) the equivalency between the instrument zero

indication and the TAF, (2) the restrictions on the use of the wide range

level instruments, and (3) the calibration of the fuel zone level

instrument.

These conditions, detailed in the following paragraphs,

affected the E0Ps which were presently in use at the facility.

a)

Instrument Zero - Based on the location of the instrument taps, the

wide range level instruments (N0-26A and NO-26B) indicate 0 inches

when the actual RPV water level is +8.44 inches above the top of

active fuel (TAF).

In an attempt to simplify the E0Ps, the licensee

,

used this instrument zero indication as the TAF; however, the

licensee did not document this deviation from the BWROG EPGs and did

not evaluate the difference to ensure that there were no adverse

effects on the Level / Power Control Procedure. This deviation was

significant because water levels higher than the TAF result in higher

reactor power levels during an ATWS condition.

Higher power levels

increase the amount of energy deposited in the primary containment

and reduce the time until primary containment venting is t equired.

In addition, a larger primary containment vent path may bt. required

to remove this excess energy. The inspection team also noted that

this condition affected the E0Ps which were presently in use at the

facility.

Further licensee action is necessary to ensure that the

higher power levels resulting from this deviation are technically

acceptable and appropriately documented for the approved and draft

E0Ps.

b)

Wide Range Level Instrument Restrictions - Caution No. 1 in the

User's Guide restricted the use of the wide range level instruments

(N0-26A and NO-268) as a function of level. The caution required

that the instruments not be used when the indicated water level was

below +10 inches (i.e., +18.44 inches actual) on both Units 1 and 2.

In addition, the caution precluded use of the Unit 2 instruments when

the water level was below +40 inches (i.e., +48.44 inches actual)

when conditions indicative of a high energy line break (HELB) were

present.

These restrictions were based upon the location of the

reference le.gs of the wide range instruments and the lack of

temperature compensation methods in the E0Ps.

The +40 inch

precaution was not applicable on Unit 1 because the reference legs

were in a different location.

The licensee had not developed a method to compensate the level

instruments when indication was below +10 inches and did not have a

8

'

.

'

.

+

.

method to compensate the instruments during a HELB because

temperature instruments were not installed in the secondary

containment. The level instrument restrictions adversely affected

the performance of the Level / Power Control Procedure because the

operators did not have an accurate level instrument with which to

control the RPV level below an actual level of +18.44 inches or

+48.44 inches. This potentially degraded the control of reactor

power during an ATWS condition and, as such, was an undocumented and

unjustified deviation from the BWROG EPGs. The inspection team also

noted that these conditions affected the E0Ps which were presently in

use at the facility.

Further licensee action is necessary to

evaluate this deviation from the BWR0G EPGs and to provide an

accurate method to control reactor power by means of water level

during the ATWS condition for the approved and draft E0Ps.

c)

Fuel Zone Level Instruments Calibration - The fuel zone level

instruments (N0-36 and NO-37) were calibrated under cold conditions

of 212 degrees F in the reactor building and the drywell, and 0 psig

in the RPV. Under cold conditions, these instruments normally

indicate accurately from -150 to +150 inches. However, this cold

calibration resulted in a wide variance in actual versus indicated

level for the drywell temperatures, RPV pressure, and reactor

building temperature anticipated during an ATWS.

Because no

compensation method was available to the operators, the fuel zone

instruments would be grossly inaccurate under the conditions in which

they will be required to be used.

The following level deviations

would result if the fuel zone indicators were used at 1100 psig

during ATWS conditions in accordance with the Level / Power Control

Procedure. With actual RPV water level at the actual TAF (i.e.,

-8.44" indicated on the wide range instruments), RPV pressure,

reactor building temperature at 200 degrees F, and drywell

temperature in the area of the reference legs as indicated below, the

fuel zone instruments would indicate the following levels.

Drywell Temperature

Indicated Level

l

(degrees F)

(inches)

1

180

a,09

l

200

-61.45

250

57.06

300

-51.94

400

-39.60

500

-23.24

Since both units precluded the use of the wide range level

instruments below an indication of +10 inches, the fuel zone

indicators would be indicating approximately -42 inches below TAF at

the time when they became the only level indicators available.

The inspection team also noted that the E0Ps and associated cautions

did not preclude the use of the fuel zone instruments in preference

to the wide range instruments for water level control.

If the wide

range instruments were not available, the operators were required to

use the fuel zone instruments to control RPV water level. Under

I

9

_ - _

_ _ _ -

1

j

a

'

.

-

.

these conditions, and in the absence of compensation techniques, the

operators would control RPV water level to an indicativa of TAF

(i.e., an indication of 0 inches on the fuel zone instruments),

which would correspond to an actual RPV water level of approximately

+60 inches. Control of reactor power during an ATWS would not be

effective at these elevated levels.

The licensee's failure to provide a method of compensating the fuel

zone instruments for use in conditions other than their calibration

condition effectively prevented their use and had the potential to

adversely affect the performance of the Level / Power Control

Procedure.

This was a significant deviation from the BWROG EPGs

which was not documented or justified.

The inspection team also

noted that this condition affected the E0Ps which were presently in

use at the facility.

Further licensee action is necessary to provide

an effective method of controlling water level under the conditions

when use of the Level / Power Control Procedure is anticipated.

2)

The BWROG EPG drywell temperature entry condition was established at the

drywell technical. specification (TS) limiting condition for operation

(LCO) or the maximum normal operating temperature, whichever was higher.

The PSTG entry condition was set at the primary containment volumetric

average temperature LC0 of 135 degrees. The BSEP TS did not contain a LC0

for drywell temperature.

The PSTG justified this deviation based on the

assuinption that the values for drywell temperature LC0 and primary

containment temperature LC0 were equivalent even though the primary

containment volumetric average included the suppression pool air space in

addition to the drywell airspace.

Because the suppression pool air space

contributed 43 percent to the volumetric average of the primary contain-

ment, the potential existed for the relatively cool suppression pool air

temperature to mask a high temperature in the drywell.

In addition, the

PSTG justification indicated that the normal maximum operating temperature

was lower than 135 degrees; however, there were times throughout the year

when the maximum operating temperature exceeded 135 degrees.

The inssec-

tion team determined that this deficiency also affected the E0Ps whici

were presently in use at the facility.

Further licensee action is

necessary to correct this operational concern.

3)

The BWROG EPG entry conditions for the RPV control guideline were: (1) RPV

water level at the low level scram setpoint, (2) RPV pressure above the

scram setpoint, (3) drywell pressure above the scram setpoint, and (4)

reactor power above the average power range monitor (APRM) down scale trip

for any scram.

The entry conditions in the PSTG deviated from the BWROG

EPCs in that the PSTG entry condition was any plant condition requiring or

causing a scram.

The PSTG justification stated that this conservative

approach permitted execution of any of five scram recovery paths which

would lead the operator to the End Path Procedure where the entry

conditions of the BWR0G EPG would be assessed.

The inspection team was concerned that this methodology delayed essential

operator actions. The potential existed for plant parameters indicative

of an emergency (i.e., the BWROG EPG entry conditions), to remain

unmonitored and therefore uncontrolled pending completion of the post-trip

actions. These post-trip actions were event-based and are normally

10

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

_

_ _ _ _ .

,

'

o

.

4

-

.

controlled as immediate, memorized actions' of the control room operators.

As discussed in Section 3.1.1, the inspection team was concerned that the

inclusion of these post-trip recovery actions into the E0Ps delayed the

accomplishment of the directed actions of the BWROG EPGs, had the

potential to result in incorrect event diagnosis, and affected the ability

of the operators to implement the E0Ps and thereby respond.to the

i

emergency in a timely manner. The licensee's method of satisfying the

1

BWROG EPG entry conditions and including event-based actions in the E0Ps

was a significant deviation from the BWROG EPGs and had the potential to

adversely affect the satisfactory performance of the E0Ps.

4)

The BWROG EPG entry condition for drywell pressure was the high drywell

pressure scram setpoint. The PSTG entry condition for drywell pressure

was established at the maximum pressure allowed by the plant technical

specifications of 2.0 psig, while the actual scram setpoint was 1.83 psig

+/- 0.076 psig. This deviation was not justified and was potentially

significant because a scram could occur at a high drywell pressure before

the Primary Containment Control Procedure entry conditions were satisfied.

5)

The BWROG EPG entry condition for the Radiological Release Control-

Procedure was limited to an ALERT condition from a radioactivity release

off-site. The PSTG entry conditions were more conservative than the BWROG

abnormal operating procedures (A0Fs) y conditions and actions for several

EPG entry conditions because the entr

were incorporated into the PSTG. As

discussed in Section 3.1.1, these additional actions diverted the

attention of the shift foreman during the simulator demonstration and

increased the complexity of the E0Ps.

6)

BWROG EPG, step C6-3, vented the RPV to permit flooding of primary

containment with a flow path through the RPV.

The specified vent paths

prevented pressurizing the primary containment during the Primary

Containment Flooding Procedure.

PSTG, step C6-2, improperly listed the

reactor head vent valves which vented to the floor of the primary

containment drywell. The vent lines did not accomplish the intent of the

BWROG EPGs because they were only 1/4 inch in diameter and were directed

inside primary containment. The same problem was noted at step C.7.a of

the Primary Containment Flooding Procedure.

7)

The BWR0G EPG entry condition for primary containment hydrogen

concentration was the high alarm setpoint for hydrogen concentration

(i.e., 2 percent). The PSTG entry condition was set at the minimum

detectable hydrogen concentration of 1 percent.

This value was

conservative with respect to the alarm, but relied on the operators to

monitor the concentration in order to identify the entry condition.

During an emergency this entry condition could be missed and could

potentially delay the operator actions required to mitigate the emergency.

8)

BWROG EPG, step C2-1.4, performed an emergency depressurization of the RPV

with other steam-driven equipment if the proper number of safety relief

valves (SRVs) could not be opened. The PSTG did not reference equipment,

such as the reactor feed pump turbines and steam jet air ejectors which

were also available at BSEP as additional steam loads capable of reducing

RPV pressure.

11

-

'

.

'

.

.

9)

BWROG EPG, step RC-1, required a manual scran of the reactor if a reactor

scram has not been already initiated.

The corresponding PSTG step

deviated from the BWROG EPGs by deleting this conditional action.

In the

justification for the deviation, the licensee indicated that the

conditional statement was deleted because the flowcharts were entered for

the initial scram and were not re-entered for any subsequent scrams.

The

inspection team was concerned that re-entry into the flowcharts would be

required if plant conditions changed and a new entry condition occurred.

!

Under these conditions, re-insertion of a scram signal was undesirable and

could adversely affect ongoing recovery actions such as alternate rod

insertion techniques.

l

3.2.2 PSTG/EOP Comparison

Four differences were identified in which the PSTGs steps were not accurately

incorporated into the E0Ps and were therefore unjustified deviations from the

BWROG EPGs.

Further licensee action is necessary to accurately incorporate

these PSTG steps.

1)

Paths 1, 2, 3, 4, and 5 included conditional action steps which precluded

the use of the feedwater system in the event of high condensate

conductivity.

These actions were not included in either the BWROG EPGs or

the PSTGs. The effect of these steps was to prevent the use of an

available high pressure injection system during a low RPV water level

emergency.

In addition, Path 5 failed to consider the use of the

feedwater system as a high pressure injection source until after the high

pressurecoreinjection(HPCI)andreactorcoreisolationcooling(RCIC)

systems were attempted. The SWROG EPGs assumed that the feedwater system

would be the first and primary method of level restoration, regardless of

the condensate conductivity, until after the RPV water level emergency was

controlled. The prerequisites for use of the feedwater system and the

failure to attempt its use are considered to be significant deviations

from the BWROG EPGs.

2)

PSTG, step RC/P-2, contained a conditional action step which placed the

control switch for each SRV in the CLOSE or AUTO position if the

continuous SRV pneumatic supply became unavailable. The intent was to

reserve operating air for subsequent necessary cycles of the SRVs.

PSTG,

step RC/P-3, required emergency RPV depressurization with sustained

opening of the SRVs if one or more SRVs were being used to depressurize

the RPV and the continuous SRV pneumatic supply became unavailable. The

intent was to continue the cooldown by leaving the appropriate valves open

continuously to maintain the proper cooldown rate.

However, the E0Ps in

End Path Procedure, step 76, required using the SRVs for RPV pressure

control only when a continuous pneumatic supply was available to the SRVs.

This was a deviation from the BWROG EPGs, in that sustained opening of the

SRVs was not attempted before operating pressure of the emergency

depressurization system was no longer available.

3)

PSTG, step DW/T-1, directed the operators to operate all available drywell

cooling, defeating isolation interlocks if necessary.

However, the

Primary Containment Control Procedure, step DW/T6, prohibited operation of

the drywell coolers if drywell pressure was above 2.0 psig. The licensee

indicated that the operation of the drywell coolers was prohibited at 2.0

12

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -

.

'

.

'

.

psig because the fans had previously tripped on thennal overloads at this

pressure.

This rationalization did not justify the restriction on the

primary method available to mitigate the high drywell temperature

condition.

Further licensee action is necessary to investigate and

correct the drywell cooler fan problems in order to fully utilize the

drywell coolers for primary containment temperature control.

4)

PSTG, step RC/P-1, directed the operators to manually open the SRVs if any

SRVs were cycling, until reactor pressure dropped to 950 psig, the

pressure at which all turbine bypass valves would remain fully open.

However, E0P Path-1, step 12, required that the operators open SRVs to

stabilize reactor pressure while maintaining maximum possible steam flow

to the main condenser, and did not specify a pressure setpoint. The

inspection team was concerned that the E0P omitted the parameter to which

the RPV pressure should be lowered without justification.

3.2.3 Calculation Review

l

The inspection team reviewed the calculations for figures and setpoints used in

the E0Ps to determine if the values were correctly calculated based on the

plant specific differences and the guidance of the BWROG EPGs. At the time of

the inspection, the licensee's Nuclear Engineering Department (NED) was

completing an independent verification of all calculations used to support the

draft E0Ps in accordance with Special Procedure SP-87-079, Revision 001,

.

" Independent Review of BSEP E0P Numerical Limits and Graphs." Although several

l

calculations remained to be verified by the NED, the calculations reviewed by

'

the inspection team had previously been completed by the NED. As evidenced by

1

the errors in the calculation of the hot shutdown boron weight discussed below,

the verification of the draft E0P calculations was not completely effective.

Further licensee action is necessary to ensure the accuracy of the calculations

and associated assumptions. The following deficiencies were noted.

1)

Worksheet WS-09 determined the maximum primary containment water level

limit that would not cover the highest primary containment vent capable of

rejecting all decay heat, and calculated the maximum primary containment

pressure capability.

In a report entitled " Calculation of Vent Flows for

the BSEP," dated July 29, 1988, the licensee reviewed four primary

containment vont flow paths and concluded that three of the four paths

would pass the anticipated design decay heat load.

Each of the three

acceptable paths vented the primary containment from the suppression

chamber. Although a vent path from an elevated location in the drywell

was not considered in the study, the licensee calculated the maximum

containment water level based on a vent path from the drywell (i.e.,

through valves V-9 ard V-10). The licensee indicated that the path was

equivalent to the suppression pool vent path and, therefore, was

technically adequate for not exceeding the maximum pressure limit;

however, a technical justification that the drywell vent path had

sufficient capacity to pass the decay heat load was not performed.

The calculated value for the maximum primary containment water level limit

was the elevation of the drywell vent elevation (i.e., 69.67 feet to the

center line of an 18-inch diameter vent pipe). A more conservative value

of 68.5 feet was used in the PSTG to ensure that water would not enter the

13

-

_ _ - _ _ _ _ _

.

'

.

'

.

vent piping and inhibit primary containment venting; however, this

conservatism was not included in the calculation.

The inspection team was concerned that the method of primary containment

water level measurement developed by the licensee did not have sufficient

accuracy to support controlling primary containment water level. The

Primary Containment Flooding Procedure, section 9, provided a method for

the operators to estimate the primary containment water level by using the

pressure instruments in the suppression chamber and at the bottom of the

drywell to trend the drywell pressure as a function of time during primary

containment flooding. Trending was required Secause the drywell pressure

instrument would be submerged at low primary containment water levels and

could not be used for measuring differential pressure and primary

containment watcr level. After adding the expected pressure head of the

water in the primary containment to the extrapolated pressure obtained

from trending, RPV injection was secured at the estimated total pressure

corresponding to the maximum primary containment water level. This

methodology was unreliable because it incorrectly assumed that the

pressure increase would be linear.

In addition, the inaccuracies involved

in this methodology would not support controlling primary containment

water level within an accuracy of 1.17 feet (i.e., the conservatism used

to prevent flooding the primary containment vent path).

The lack of primary containment water level instrumentation was noted

during the Detailed Control Room Design Review (DCRDR) in HED 206X-5093.

This deficiency will eventually be corrected by the installation of a

i

drywell pressure instrument above the maximum water level, thus supporting

i

accurate primary containment water level measurement.

Further licensee

I

action is necessary to revise the current procedures to ensure that the

1

primary containment water level measurement procedures can be implemented

l

l

effectively by the operators.

In addition, the new pressure instrumentation

j

should be installed as soon as possible.

I

2)

Worksheets WS-15 and WS-16 and plant-specific data package PSD-17

calculated the cold and hot shutdown boron weights required to poison the

reactor in the event of an ATWS.

In PSD-17, the licensee erroneously

calculatad the concentration of boron required due to several errors in

the conversion of the reference values provided by the vendor. This

incorrect conversion resulted in a calculation of the hot shutdown boren

weight which was 14.46 pounds too low. This incorrect value adversely

affected the calculations for: (1) time to inject boron (100 seconds

longer), (2) volume of the standby) liquid control (SLC) tank corresponding

to hot shutdown (68.5 gallons more , (3) SLC tank level indication for hot

shutdown (0.43 percent lower), and (4) the amount of borax required for

hot shutdown (127.6 pounds more). Although these errors resulted in

!

non-conservative values for the hot shutdown boron weights, the difference

!

(i.e., less that 5 percent) was unlikely to prevent the emergency shutdown

of the reactor due to the conservatism of the calculation.

Nevertheless,

~

these errors were not identified by the licensee's verification of the

i

calculation, including the independent verification by the NED. Further

'

i

licensee action is necessary to correct this error and ensure that all the

I

draft calculations are correct.

I

14

_

._

. _ _ _ _ _ _ - -

_ _ _ _ _ _____ - -

'

.

,

.

-

.

3)

Worksheet WS-AC4 detailed the calculation of the plant specific value for

i

drywell scram pressure. The numerical limit value was listed as 2.0 psig;

however, no calculation was provided to support the parameter. The basis

was listed as technical specifications 2.2.1-1 and 3.3-1 with an

amplifying comment that 2.0 psig was the scram setpoint for high drywell

pressure. As discussed in Section 3.3.1.1, the latter statement was

incorrect in that the high drywell pressure scram was set at 1.8 psig.

Further licensee action is necessary to ensure that the setpoint

documentation corresponds to values actually used.

4)

Worksheet WS-12 calculated the lowest suppression chamber pressure which

could occur when 95 percent of the non-condensables in the drywell had

been transferred to the suppression chamber.

A minor discrepancy was

identified in that the computed value was 13.07 psig, but the cover sheet

i

of the calculation indicated 13 psig without explanation.

PSTG, step

'

PC/P-1, also incorporated the value of 13.0 psig.

The PSTG should reflect

the calculations and any differences between the PSTG and the calculations

should be explained in the PSTG deviation documentation.

5)

Worksheet WS-8 calculated the highest suppression chamber pressure as a

function of the primary containment water level that would permit the

primary containment to maintain its pressure suppression function while

l

.

the RPV was at normal operating pressure.

Several administrative errors

I

l

that did not affect the technical adequacy of the calculation were noted.

'

Examples included differences between values which were transferred into

subsequent calculations.

l

3.2.4 Adequacy of Writer's Guide

A review of the PSWG was conducted to determine wbether it described acceptable

methods for accomplishing the objectives stated in NUREG-0899. The inspection

tet.m concluded that the PSWG was incomplete and should be supplemented with

detailed guidance in the following areas.

1)

Referencing Supporting Material - All figures, tables, and other

supporting materials that may be required in the performance of a

i

procedural step should be referenced explicitly in the E0P at the point at

!

which the information is needed.

For ex. ample, the "RPV Pressure Range for

System Operation Table," was not referenced or included in step 27 of the

End Path Procedure.

Similarily, although Primary Containment Control

Procedure, step PC/P-9, required controlling suppression chamber pressure

in the safe region of the pressure suppression pressure, no reference was

made in this step for the graph or figure to be used.

Guidance for

referencing supporting materials within the procedural steps should be

part of the PSWG.

2)

Referencing Other E0Ps - Several E0Ps directed the performance of a series

~Tsleps in accordance with other procedures.

In order to reduce

o

transition errors, the complete title of the procedure and its reference

,

number should be included in the procedural step.

In addition, a complete

technique that will aid the operator in making a correct identification of

these other procedures should be included in the PSWG.

l

!

I

15

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _

,

'

.

,

3)

Step Identification - The PSWG described a technique for identifying

critical action steps which required placing the symbol for a decision

block over the symbol of an action block.

This methodology was not an

effective method of identifying override requirements. As discussed in

Section 3.4.3.3, a critical step was overlooked during the simulator

exercise because the operator did not recognize that the critical step

represented an override condition. A more discernible shape coding

technique should be employed for deignating critical steps in the E0Ps.

4)

Operator Aids - Operating Instruction 01-41 discussed procedures and

methodologies for implementing operator aids at BSEP; however, this

instruction was not referenced by the PSWG.

Reference to this document,

including the basic criteria for design and control of operator aids,

should be incorporated into the PSWG.

The need for training operators on

the use of the operator aids should also be addressed.

5)

_ Color Coding - The PSWG contained no criteria for color coding the E0Ps;

however, the draft E0Ps employed a color coding scheme.

Guidelines and

direction on the uses of color should be included in the PSWG.

6)

Titles - The operators should be able to identify the basic scope of each

E0P by reading the title.

The E0P titles Path-1 through Path-5 failed to

indicate what the procedure was intended to accomplish.

Guidance for

constructing meaningful and unique titles for the E0Ps should be included

in the PSWG .

7)

Consistency of Step Numbering - Some steps within the E0P flow charts

applied the BWROG EPG convention for designating steps (i.e., PC/H-9),

while others employed a three digit system (i.e., 027).

A consistent

method for numbering the E0P steps should be incorporated and documented

in the PSWG.

3.2.5 Writer's Guide Implementation

The PSWG was independently verified to assess its implementation as a source

document for the preparation of the E0Ps. The verification process consisted

of comparing the E0P flowcharts and written procedures (e.g., LEPs, SEPs, etc.)

with the stated criteria and human factors guidance contained in the PSWG.

The

inspection team concluded that the PSWG was generally followed as a source

document for preparation of E0Ps; however, several minor deviations were

ider,ti fied.

Further licensee action is necessary to ensure that the criteria

and human factors guidance contained in the PSWG are reflected in the E0Ps.

1)

Instrument Accuracy - Some of the values referenced in the E0Ps could not

be obtained from the displays.

In Path-4 for example, the operators were

required to read the conductivity of the condensate booster pump to less

than 0.3 umhos. The instrument display, 1-00 CR-3075, did not support

this level of accuracy.

As demonstrated during the system walkthroughs,

the operators were unable to read the setpoint value of 0.3 mmhos from the

]

instrument scale. This deficiency was identified as a human engineering

deficiency (HED 20X5-5015) during the DCRDR; however, no corrective action

had been taken.

In addition, the resolution of the reactor building roof

j

radiation level instrument, CAC-AQH-1264-3, was unsuitable for reading the

i

E0P-specified setpoints of 3446 cpm (setpoint 1) and 4213 cpm (setpoint

16

- _ ___ _ _ _ _ _

'

.

'

,

'

.

2). Also, the E0P directed the operator to read the turbine building vent

radiation levels on instrument D12-RM-23; however, no setpoints were

identified on the instrument.

2)

Instrument Labels - The E0Ps referenced different units than those

inoicated on the instrument displays.

For example, the E0P referenced the

radiation level for service water effluent in units of counts per minute;

however, the instrument in the control room (i.e., D12-K805) for obtaining

this information was displayed in counts per second.

In addition, the

digital readout for monitoring stack releases, located on the control room

back panels, was not labeled and no units were identified.

Only the

!

I

value, 4.57E + 1, was displayed.

3)

location of Equipment - The E0Ps did not provide adequate location

information for specific equipment, controls, or displays.

For example,

the action steps to start the diesel fire pump, open all battery room exit

doors, or open emergency core cooling system (ECCS) pipe tunnel doors were

local operations.

The PSWG did not establish a standard method for

identifying the location of controls and displays external to the control

room.

4)

System Nomenclature - The E0Ps used inconsistent nomenclature for

equipment and systems.

For example, in the Level / Power Control Procedure,

steps 76 and 30, LPCI was used instead of RHR.

.

5)

Step Content - The E0Ps contained both decision and action steps or

contained more than one action or subject.

For example, in Path-3, steps

!

175 and 93, and Path-1, step 12, the decision step required several

actions on the part of the operator.

6)

Change Identification - There was no identification of the location of

recent changes in the written procedures. A change bar technique should

be used.

7)

Section Redundancy - PSWG, section 3.7, "Information/ Caution Steps," and

section 3.9, "Information Steps," appeared to be identical in content.

8)

Vocabulary - The E0Ps used verbs such as downrange, monitor, cycle, and

increase, which were not listed in Table 1 of the PSWG as approved verbs.

3.3 E0P Validation Using Plant Walkthroughs

In order to ensure that the E0Ps could be accomplished successfully, plant

walkthroughs for all the E0Ps and referenced operational procedures were

performed. The team verified that E0P instrument and control designations were

consistent with the installed equipment and that indicators, annunciators, and

controls referenced by the E0Ps were available to the operators. The

inspection team also verified the location and control of E0Ps-in the control

room. With the assistance of licensed operators, the team physically verified

that activities which would occur outside the control room during an accident

scenario could physically be accomplished and that tools, jumpers, and test

equipment were available to the operators.

17

- __

_ _ _ _ _ _ _ _ - - - - - - - - - - - - - - - - _ - - - - . - .

,

'

.

,

e

.

l

!

3.3.1 Technical Adequacy of Procedures __

The inspection team identified several deficiencies with respect to the

procedural completeness and technical adequacy of the E0Ps.

Although the

inspection team concluded that the operators could adequately perform the

procedures in spite of these deficiencies, further licensee action is necessary

'

to correct these deficiencies and perform an adequate verification and valida-

tion of the E0Ps.

1)

Path-1, steps 115 and 116, and Path-2, steps 165 and 166, directed the

operators to maximize the flow from the operating control rod drive (CRD)

l

system pumps by operating at the optimum pressure on the pump tead curve

,

The intent of these steps was to maximize CRD flow.

However, the steps

!

failed to accomplish the desired action because the operator was directed

I

to throttle the pressure control valve to maintain pressure equal to or

greater than 1000 psig and was never directed to increase CRD flow to the

reactor.

The steps should have directed the operator to maintain pressure

equal to or greater than 1000 psig but as low as possible.

Further

licensee action is necessary te modify these steps to ensure that the

intended action is accomplished.

l

2)

Primary Containment Flooding Procedure, section 7, step 3.d (2),

instructed the operators to lift wire number 25 from terminal 70, on

terminal board UU in control panel P601.

A note preceding the step stated

that the lead to be lifted was the lead entering from outside control

l

panel P601. The operator could not detennine which wire entered from

l

outside the panel because two wires with exactly the same number (i.e.,

l

number 25) were on the tenninal and both wires entered the same wireway.

l

This condition was noted at three other steps in the same section.

l

l

3)

Primary Containment Flooding Procedure, sections 7 and 8, step C.3, failed

'

to provide the operator with instructions concerning the level to which to

l

fill the primary containment.

4)

Primary Containment Flooding Procedure, section 2, did not list in the

note for manpower required the radwaste operator required to take several

actions necessary to support the evolution.

5)

Primary Containment Control Procedure, step PC/P-4, directed the operators

to vent the primary containment drywell through the standby gas treatment

(SBGT) system in accordance with Operational Procedure OP-10.

This

procedure only permitted venting the SBGT through two 1/2-inch lines

(valves V8 and V9) when drywell pressure was above 0.7 psig.

In this mode

of operation, the SBGT system vent path would have little or no effect on

controlling primary containment pressure.

The licensee should use the

10-inch ventilation damper (F-BFV-RP.) for venting, at least until the

pressure in the SBGT train reaches the limiting operating pressure.

6)

Primary Containment Control Procedure, steps PC/P-6 and PC/P-8, directed

the operator to initiate suppression pool and drywell sprays; however,

during the walkthroughs the operators were confused as to whether or not

to secure suppression pool sprays prior to initiating drywell sprays.

,

I

Augmented training or clarification in the E0P should be provided to

resolve this confusion.

18

_ ____ _____-___ _

-

f

,

)

.'

.

'

.

7)

Primary Containment Control Procedure, step SP/L-5.3, directed the

operator to drain the suppression pool to radwaste to control suppression

pool level.

This step did not provide alternate instructions if these

valves were interlocked closed from an isolation signal.

Further licensee

action is necessary to account for this possibility.

8)

Primary Containment Control Procedure, step SP/L-5.22 directed the

operators to maintain primary containment water level below 68.5 feet;

however, this step and subsequent steps did not reference the procedure to

accomplish this measurement.

9)

SEP-01, section 3, initiated primary containment venting before primary

containment pressure reached 70 psig by using preferentially listed vent

paths. After opening the proper valve, the subsequent action step

required continued venting of the primary containment if the initial

venting operation stabilized primary containment pressure below 70 psig.

The inspection team was concerned that the step provided inadequate

guidance to the operator concerning action required if the vent path was

more than adequate and primary containment pressure started to fall below

70 psig. The licensee should ensure that an approved PSWG action verb is

used which properly implements the intent of the BWROG EPG concerning

primary containment pressure control during venting.

10) SEP-04, steps 3 and 4, directed opening of reactor building inboard and

outboard ventilation isolation valves.

The terminology was incorrect in

that the procedure referred to the valves as reactor building inboard

(cutboard) isolation valve (s). The correct terminology was reactor

building vent inboard (outboard) isolation valve (s).

11) SEP-06, included entry conditions of drywell pressure which were below 2.0

psig.

The procedure was actually implemented when the shutdown cooling

interlocks were fulfilled at the corresponding drywell pressure of 1.8

'

psig. As discussed in Section 3.2.3.3, further licensee action is

necessary to ensure that procedural values are consistent with the plant

parameters used to initiate actions.

12) SEP-06 cautioned the operators concerning reactor power excursions when

the residual heat removal (RHR) system pumps were started in step C.48.

However, the correct reference for this precaution should have been a

subsequent action step which throttled open the injection valve. The

licensee should ensure that the caution correctly references the operator

action which actually affects reactor power level.

3.3.2 Availability of Special Tools and Equipment

The availability of special tools and equipment in the plant appeared to be

adequate to accomplish the activities required by the E0Ps. The team verified

that the plant equipment was accessible and available to perform the identified

task. A walkthrough was performed of the special tools and equipment used in

the E0Ps both in the control room and the plant.

Because the draft E0Ps had

not been implemented, not all equipment could be verified.

Nevertheless,

several specific examples were identified in which equipment or infonnation was

not available which could adversely affect the performance of the E0Ps and

their support procedures.

Based on the training and experience of the

19

'

.

'

.

operations staff, the inspection team concluded that the E0P actions could be

accomplished satisfactorily. However, based on the need to provide procedures

which can be implemented correctly by a newly qualified operator, and on the

guidance of NUREG-0899, the inspection team concluded that there was a

potential for operator confusion or error which could affect the performance of

the procedures.

Further licensee action is required to provide the necessary

equipment or information to ensure that operator confusion will not exist

during the performance of the procedures.

i

1)

LEP-02 provided an alternate control rod insertion method involving local

venting of the hydraulic control units (HCus). The venting operation used

control rod drive (CRD) vent hoses located in the toolbox on the 20-foot

elevation of the reactor building.

The toolbox contained two sets of

hoses with different types of connectors, only one of which would fit the

HCU vent block. The licensee could not determine the purpose of the

second set of hoses in the toolbox.

The inspection team was concerned

that in an emergency the presence of the incorrect hoses could delay the

performance of alternate control rod insertion. The inspection team also

noted that the toolbox did not contain any protective eouipment and that

the procedure did not warn the operators that HCU venting was a

potentially hazardous operation which could release contaminated, hot

reactor water.

In addition, the licensee indicated that the venting

procedure was a two-man job requiring one operator to perform the venting

operation in the overhead while a second operator coordinated the

activities with the control room and verified that the correct hydraulic

i

control unit was being vented from below.

However, the procedure only

required the resources of one operator to perform the venting operation.

2)

The Primary Containment Flooding Procedure required the use of several

electrical jumpers. Generic jumpers were available to the operators to

perform the E0P actions; however, these jumpers had closed-end

terminations. The use of closed-ended jumpers required the operator to

(

remove the terrrinal screw, install the additional terminal, recapture all

i

terminals, and re-install the terminal screw. The inspection team was

concerned that this task was unnecessarily complex for emergency

conditions.

The use of open-ended terminations, which could be slipped

under a loosened screw, would simplify the task.

In addition, the

inspection team noted that the procedure lacked direction concerning

insulation of lifted leads, and that insulating materials were not readily

,

available.

The inspection team also observed that some electrical relays had wiring

diagrams posted adjacent to the relays to aid the operators in identifying

the terminal locations; however, not all relays used in the E0Ps were

identified in this manner.

Further licensee action is necessary to

provide installation specific jumpers for use in accomplishing the E0P

action steps and to provide consistent use of operator aids for the

identification of relay terminal locations.

,

3)

During the E0P simulations, the control room operators directed the

auxiliary operators to perform numerous actions in the plant.

For

example, steps 67 and 68 in Path-1, required opening battery room exit

doors and ECCS pipe tunnel doors. These actions were initiated by the

control room operator using the public address (PA) system and required

20

- _ _ - _ - - _ . _ - - _ -

'

,

.

'

.

the auxiliary operators to find a PA station to report the completion of

the directed actions.

Alternate communications techniques, such as

hand-held radios, were not available for communicating with the operators

perfonning local actions. The inspection team concluded that the licensee

should give further consideration to the use of hand-held radios to permit

reliable communication with the control room under emergency conditions.

i

3.3.3 Station Material Condition

The inspection team reviewed the material condition of the station during the

plant walkthroughs and ensured that necessary equipment and components were

dCCessible and functional.

The overall material condition of the plant

appeared good. The team did not observe any interferences in the reactor

building which would adversely affect emergency actions. The inspection team

noted that significant amounts of non-combustible material were located in the

bottom of control panel P601; however, the licensee initiated corrective action

to clean the panel and inspected and cleaned other panels as required.

The

team verified that emergency lighting was available for E0P operator actions

and noted that lighting was available within electrical cabinets requiring

terminal manipulations.

However, during the walkthroughs, the operators would

not operate the switches to turn on the lights in the cabinets because the

switches were not labeled.

Further licensee action is necessary to correct

this deficiency.

3.3.4 Reactor Building Accessibility

The licensee performed a design review entitled, " Post-Accident Control of

Radiation in Systems Outside Containment of PWRs and BWRs," to meet the

requirements of paragraph 2.1.6 of NUREG-0578, "TMI-2 Lessons Learned Task

Force Status Report and Short Term Recommendations." The inspection team noted

that the extent of the design review fulfilled the additional requirements of

NUREG-0737, paragraph II.B.2, concerning the same subject.

The inspection team

evaluated the results of this design review and its impact on the ability of

operators to perform the emergency actions of the E0Ps.

The ability of the operators to perform the E0P actions successfully would be

dependent on access to the reactor and radwaste buildings. Access to the

reactor building was dependent on the specific accident scenario, and access to

the radwaste building was dependent on the location of primary system leakage.

Although the licensee's radiation protection procedures allowed operator entry

into high radiation level areas under the supervision of radiation protection

personnel, the E0P contingency actions could not be performed if radiation

levels prevented entry.

The design review was based upon the source terms

specified by Pegulatory Guides 1.3 and 1.4 and the accidents of Chapter 14 of

'

the BSEP Final Safety Analysis Report (FSAR). The design review concluded that

entries into unprotected areas or areas with prohibitively high dose rates

would not be required for mitigation of the accidents. However, several areas

were identified which could require operator entry during recuvery operations.

The inspection team concluded that multiple methods of implementing the E0P

contingency actions had been adequately considered in the development of the

E0Ps. However, the inspection team identified two actions, during the

walkthrough of the plant, for which an alternative method of accomplishment had

l

21

_-_

- _ _ _ _ _ _ _ - _ _ -

_- -

.

t

.

-

.

not been adequately considered.

Further licensee action is necessary to

correct these discrepancies.

1)

The LEP-01 and Primary Containment Flooding Procedure identified several

local operator actions to inject service water and demineralized water

into the RPV.

These actions included opening the residual heat removal

(RHR) loop cross tie valve, Ell F010, in the high pressure core injection

(HPCI)systemmezzaninearea.

This valve was a normally de-energized

motor-operated valve whose breaker was removed from its cubical to ensure

separation of the two trains of RHR.

A significant amount of time was

required to operate this valve manually in area in which radiation levels

could be as high as 20000 R/HR one hour into an accident.

Since this

valve had the potential to be operated remotely, further licensee

consideration should be given to reinstalling the valve breaker rather

than attempting manual operation.

2)

SEP-06, step C.24, required the operator to monitor the RHR heat exchanger

outlet conductivity at a local instrument in the south RHR room.

This

,

area would have extremely high radiation levels in the accident conditions

during which performance of the step would be required.

The inspection

team noted that control room panel alarm, A-03, tile 2-10, monitored the

desired location and alarmed at the value specified in the E0P (i.e., 10

umho/cm).

Further licensee action is necessary to ensure that remote

instrumentation is used where possible in lieu of local monitoring in high

radiation areas.

i

3.4 E0P Validation Using Plant Simulator

j

To ensure that the E0Ps could be implemented correctly under emergency

j

conditions, the inspection team developed and performed four accident scenarios

utilizing licensed operators. The accident scenarios determined whether the

)

E0Ps provided the operators with sufficient guidance and clearly outlined their

required actions during an emergency; verified whether the E0Ps caused the

operators to interfere physically with each other; verified that the procedures

did not duplicate operator actions unless required; and verified that

transitions from one E0P to another or to other procedures were accomplished

satisfactorily.

3.4.1

Scenario Description

The first scenario involved a rupture of the feedwater pump suction header from

100% power with a spurious group 1 isolation signal inserted at the time of the

reactor scram due to low RPV water level.

The SRVs opened on high RPV pressure

following the main steam isolation valve (MSIV) closure.

One safety relief

valve (SRV) stuck open and remained open throughout the scenario. One minute

after the scram and MSIV isolation, a small steam leak was initiated into the

drywell . The high pressure core injection (HPCI) system, pump B of the control

rod drive (CRD) system, and the loop B heat exchanger of the residual heat

removal (RHR) system were out of service throughout the event.

Following the

reactor scram, the operators performed Path-4 when RPV water level decreased

below +112 inches.

The operators exited Path-4 and performed steps RC/L and

RC/P of the End Path Procedure concurrently to restore RPV water level and

pressure. The operators performed the Primary Containment Control

Procedure to control suppression pool temperature and drywell pressure and

22

_

___

_______________ _-

--

__

.-

.

4

i

temperature, and depressurized the RPV in accordance with the End Path

i

Procedure, when drywell temperature exceeded 300 degrees F.

The second scenario exercised the Level / Power Control Procedure with alternate

l

boron injection. A spurious group 1 isolation signal initiated the event and

resulted in a failure of all control rods to scram.

Failure of the standby

liquid control (SBLC) system to inject along with both reactor water cleanup

(RWCU) system pumps being out of service required the use of the Alternate

Boron Injection Procedure using the CRD system. A small break loss of coolant

accident (LOCA) in the drywell required emergency depressurization when drywell

temperature exceeded 300 degrees F.

The scram condition required the

performance of Path-1 and eventually the Level / Power Control Procedure for the

l

ATWS condition. The Primary Containment Control Procedure was used to control

drywell and suppression pool temperature and pressure.

The third scenario exercised the Secondary Contairiment Control Procedure and

i

the Radioactive Release Control Procedure. A loss of feedwater resulted in a

reactor scram on low RPV water level coincident with a fuel element failure.

Maintenance. activities in the HPCI room required the reactor core isolation

cooling (RCIC) to HPCI room door to remain open to allow passage of hoses.

When the RCIC system started on low RPV water level a steam leak occurred at

the RCIC steam inlet valve (F0-45). The steam leak caused a RCIC system

isolation signal.

The RCIC steam supply containment isolation valves failed to

isolate and caused a HPCI isolation signal several minutes later due to the

open door between the two rooms. The scram coincident with an RPV level below

l

+112 inches required performance of Path-4. The radioactive steam leak in

'

secondary containment required performance of the Secondary Containment Control

Procedure.

Exceeding the reactor building roof vent annunciator setpoint

required performing the Radiological Release Control Procedure. When the

operators determined that more than one area had exceeded its maximum safe

operating radiation level, the End Path Procedure required emergency

depressurization.

l

The fourth scenario required venting primary containment to control primary

.

containment hydrogen concentrations.

RHR loop B was out of service throughout

l

emergency bus (E-3) ge break LOCA coincident with a failure of the 4160 vcit

the scenario. A lar

initiated a reactor scram and an ECCS actuation. The A

loop RHR injection valve failed to open, leaving only one core spray (CS) pump

available for injection.

The reactor core was uncovered, resulting in fuel

,

damage and the release of hydrogen to the primary containment. The scram with

high drywell pressure required performance of Path-5 and the Primary

Containment Control Procedure.

The loss of power to emergency bus E-3

unexpectedly resulted in the inability of the operators to perform the primary

containment venting procedure because the torus purge exhaust valve, CAC V-8,

was powered from emergency bus E-3.

Further licensee action is necessary to

ensure that an alternate method is available to vent the primary containment

ouring a partial loss of power condition.

3.4.2 Limitations of the Plant-Specific Simulator

The plant-specific simulator located on-site was used for the E0P scenarios.

The simulator demonstrated extremely poor modeling with respect to decay heat

and RPV water level response.

For example, during scenarios in which all high

pressure injection had failed and with mass being removed by open SRVs or a

23

1

f

'

,, .

.

.

small break LOCA, RPV water level would continue to increase.

Following

MSIV isolations from 100 percent power with end of life (COL) decay heat

loading and no steam being drawn off by the HPCI or RCIC systems, it was not

necessary to use the SRVs to control RPV pressure.

In fact, RPV pressure would

decrease with no external energy removal in progress. As a result, the RC/L

steps of Path-1 were not able to be simulated past the initial entry steps.

The inspection team concluded that the plant-specific simulator was not.an

effective tool for operator training on the Level / Power Control Procedure, E0P

Path-5, or any of the E0P steps requiring level control manipulations. As

previously discussed in Section 3.1.2, the simulator modeling deficiencies also

adversely affected the ability of the licensee to perform validation for any

E0P steps which required level manipulations.

3.4.3 Observations and Conclusions

The inspection team concluded that the operating crew could satisfactorily-

implement the E0Ps to shutdown the reactor and return the plant to a safe,

stable condition. Overall, the operators performed well and demonstrated a

good understanding of the E0Ps which was indicative of a high level of training

on the procedures. As discussed in Section 3.1.1, the inspection team

concluded that the timely implementation and execution of the E0Ps required the

active participation and assistance of the STA because the licensee included

the post-trip actions in the E0Ps and developed overly complex procedures. The

inspection team identified concerns in the following two areas.

1)

Control Room Responsibilities - During all four scenarios, the inspection

team observed that the shift foreman (SF) directly supervised the two

,

control operators and directed the performance of the E0Ps and that the

l

shift operating supervisor (SOS) monitored the emergency plan and

performed the required notifications.

The shift technical assistant (STA)

monitored the emergency response facility information system (ERFIS) and

available control room indications for key parameters and trends.

In

I

addition, the STA monitored changing plant conditions to identify E0P

J

entry conditions and to advise the SF regarding the required actions. The

inspection team also noted that the STA performed E0P steps in legs which

the SF did not have time to execute.

This was particularly evident in the

<

third scenario involving the Secondary Containment Control Procedure.

1

The BSEP administrative instructions required the STA to provide an

overview of the plant conditions and ensure that all the required E0P

steps were completed.

In actual practice, the STA independently performed

portions of the E0Ps in order to provide more time for the SF to read and

complete the post-trip scram recovery actions of the E0Ps.

The inspection

team concluded that the level of detail of the BSEP E0Ps did not permit a

single individual sufficient time to direct the performance of all

required actions of the E0Ps.

The inspection team also observed that the SF was not able to perfom all

the parallel steps as required by the BWROG EPGs. This was clearly

demonstrated in the first scenario involving the performance of the

Primary Containment Control Procedure.

During the scenario, the SF

completed only two steps of the five required parallel flowpaths (i.e.,

DW/T and PC/P).

The remaining three flowpaths (i.e., SP/T, SP/L, and

PC/H) were not performed. Another example occurred in the third scenario

24

- _ _ _ - - _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ -

_ _ _ _ _ ______ _ __

- _

_ _ - _ _ - _ _ _ - _ _ _ - _ - _ _

,,

.

+

.

involving the Secondary Containment Control Procedure.

During this

scenario, the SF completed only one of the three required parallel

flowpaths (i .e. , SC/R).

In this example, the SF directed the control

operator to obtain the area radiation levels from the back panel, but not

the area temperature and level readings. The failure to execute all legs

-

of the E0Ps potentially prevents monitoring and control of all symptoms

indicative of an accident condition. As discussed in Section 3.1.1,

further licensee action is necessary to (1) accurately define and

implement the control room responsibilities of the STA and SF during E0P.

performance, (2) remove the event-based actions from the E0Ps, and (3)

reduce the level of complexity of the E0Ps.

2)

Critical Action Steps - Critical action step RR-5 in the Radioactive

-

,

Release Control Procedure required the operators to execute the subsequent

)

actions of the flowpath only if an ALERT was not declared as a result of a

i

radioactive release. As discussed in Section 3.1.1, these actions were

l

l

event-based and not appropriate for inclusion in the E0Ps. Durir.g the

l

third scenario, the_ STA and SF performed these action steps after an ALERT

had been declared. Although in direct conflict with the procedural

requirement of step RR-5, the licensee's training staff indicated that it

was desirable to perform these action steps even after an ALERT had been

declared.

Further licensee action is required to correctly train and

implement the critical actlon of step RR-5.

During the third scenario, the operators incorrectly performed emergency

,

depressurization in accordance with the End Path Procedure because they

!

missed critical action step 64 of the Level / Power Control Procedure. As a

result, the operators bypassed the cautions concerning power oscillations

during an ATWS contained in the procedure.

Although, the SF correctly

i

controlled injection flows and reactor power level, he subsequently

indicated that he did so as a result of his previous training and had

missed the precautions of the critical action step.

'

The operators used a marker to maintain peacekeeping within the E0Ps and

to note critical action steps and, as a result, were able to explain

accurately where they were in each of the flowcharts.

However, the

scenarios demonstrated that they experienced difficulty in identifying and

'

,

monitoring the override requirements of critical action steps.

Because

missing a critical action step has a significant potential to result in

.

severe core damage, the inspection team concluded that further licensee

l

action is necessary to identify, train, and procedurally support a more

effective method for monitoring the critical action steps.

3.5 Operator Interviews

i

The inspection team conducted interviews with three shift operating

-'

supervisors, four control operators, and one auxiliary operator. These

interviews developed information on the effectiveness of the E0Ps and did not

examine the qualifications of the operators.

Each interview lasted

!

approximately one hour. The following observations summarize the comments

i

volunteered by the operators.

25

__- _ _ - _ - _ _ _- __-_ _ ____-__ _ ___

___

..

.

e

.

.

3.5.1 Observations and Conclusions

1)

Equi ament Design - The operators experienced difficulty in locating and

reacaing several valves outside the control room.

For example, the

operators suggested cutting a manhole in the grate that covered the

condensate header valve, C0-V304, to enhance the accessibility from above.

In addition, the operators also suggested implementing hardware

modifications to make the valve more easily accessible and labeling the

.

!

RCIC CST suction valve, CO-V301, on a nearby wall to clarify its location.

Although the E0P provided location information, the operators indicated

)

that the use of signs would' aid performance of the E0Ps.

2)

Assignment of Duties - The E0Ps clearly defined the number and

qualifications of operations personnel required for executing the E0Ps.

Major tasks and duty assignments were clearly delineated and unambiguous.

j

The operating instructions delineated the basic philosophy and established

i

practices for personnel assignments.

l

3)

0)erator Training - All SFs and C0s had received preliminary training on

tie use of the draft EOPs. Approximately two weeks of combined classroom

l

and simulator training were devoted to the use of E0PS; however, formal

!

training on the E0Ps for the A0s had not yet been accomplished.

The

operators indicated that additional training was scheduled before the

draft E0Ps would be implemented.

Ir general, the operators considered

their training on the E0Ps to be adequate; however, more training would be

beneficial. Some operators expresseii concern regarding the transfer of

training betweer. the new procedures end the old procedures.

4)

Validation and Verification of E0Ps - The verification and validation of

the E0Ps included a combination of system walkthroughs and simulator

exercises.

In addition, operator training accomplished portions of the

l

verification and validation process.

For example, verification of the

technical adequacy for selected E0Ps was performed during classroom

'

discussions.

.

5)

System for Making Changes to E0Ps - A fonnal system existed for making

changes to the E0Ps.

The operators submitted changes to the E0Ps in

accordance with Operating Instruction 01-28.

6)

Calculations - The E0Ps required the operators to perform very few

calculations and did not require complex calculations.

7)

E0P Availability - All the E0Ps were located within the control room and

i

were inraediately accessible by the operators. All of the operators

'

reported that there were no problems in locating and retrieving the

required E0Ps needed to perform a spccific function.

Nevertheless, the

inspection team believed that further consideration should be given to

locating the E0Ps which would be required to be performed outside the

control rocm at a locally accessible area.

NVP.EG-0899 required that the

procedures be available at all locations in the plant where equipment is

to be manually operated under emergency conditions.

8)

Communications - The operators considered the communications inside the

control room to be adequate and reported no conditions where it was hard

,

26

l

_

.i

,

.

'

.

to hear or convey verbal instructions in the control room. All operators

expressed the need to keep the number of personnel in the control room to

a minimum during en emergency. The operators identified that communica-

tions would be difficult in the diesel building and the RHR pump room (-17

level) during an emergency. The inspection team noted that communications

from outside the control room were only available through the PA system

and that the availability of radios as an alternative mode for communica-

tions would be a valuable asset.

3.6 Primary Containment Venting Provisions

The inspection team reviewed the " Primary Containment Venting Procedure,"

E0P-01-SEP-01, to determine the adequacy of the procedure and the feasibility

of the vent paths.

The inspection team also reviewed the results of the

special Probabilistic Risk Assessment based operational safety inspection

cor. ducted by the NRC in March 1988. The inspection team performed a

l

walkthrough of all primary containment vent paths which had not previously been

l

examined during the earlier inspection, and verified that all necessary

equipment was available.

The Primary Containment Control Procedure initiated venting of the primary

containment, irrespective of the off-site release rate, for conditions of high

l

pressure (i.e., 70 psig in step PC/P-12) and for conditions of high hydrogen or

i

oxygen (i.e., 6 percent and 5 percent, respectively, in step PC/H-16). The

i

shift foreman had the final authority for venting the primary containment under

these conditions.

4

The licensee had established hard pipe vent paths which were capable of

l

removing the decay heat load required by Revision 4AF of the BWROG EPGs.

I

E0P-01-SEP-01 preferentially listed the vent paths from the small bore pipe to

the large bore piping, to control the primary containment pressure. All the

vent paths were monitored release paths that permitted off-site dose

calculations to be performed. Although the vent paths used hard piping, low

pressure ducting was installed at transitions to the standby gas treatment

(SBGT) system and the reactor building purge exhaust system fans. A recent

study completed by the licensee concluded that the pressure at the fan duct

work could exceed acceptable limits and a further evaluation was in progress at

the time of inspection. This evaluation should be completed in a timely manner

by the licensee.

The inspection team was also concerned about the ability of the operators to

establish a vent path during reduced power capability or station blackout

conditions. As discussed in Section 3.4.1, the inspection team noted during

the simulator exercises that the operators were unable to establish a vent path

to remove simulated excessive hydrogen with the loss of one division of

essential power.

Contingency plans were under development by the licensee for

the conditions of loss of power, including containment venting provisions.

This effort should be completed expeditiously by the licensee.

4.0 MANAGEMENT EXIT MEETING

The inspection team conducted an exit meeting on October 7, 1988, with licensee

management.

During this meeting, the inspection team identified the inspection

findings and provided the licensee with an opportunity to question the

observations. The inspection team also detailed the scope of the inspection

27

I

f.,*

,

'

,,

'

e

and informed the licensee of the conclusions identified in this report. Mr.

l

Jim Konklin, Section Chief, Special Team Support and Integration Section,

Office of Nuclear Reactor Regulation, and Mr. Caudie Julian, Branch Chief,

Operations Branch, Region II, represented NRC management at the final exit

meeting. Appendix A identifies the licensee personnel who participated in this

meeting.

l

l

1

l

l

28

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ -

'

.'

,

'

'

.,

'

e

APPENDIX A

PERSONNEL CONTACTED

A large number of people, including the following licensee personnel, were

contacted during the inspection.

I

  • J. Harness, Plant General Manager
  • K. Enzor, Director, Regulatory Compliance

,

  • L. Jones, Director, Quality Assurance and Quality Control

i

  • C. Blackmon, Manager, Operations

A. Hegler, Superintendent, Operations

  • W. Martin, Principal Engineer, On-site Nuclear Safety
  • J. Titrington, Principal Engineer, Operations
  • M. Sawtschenko, Operations

S. Reynolds, Operations

J

M. Amato, Operations

l

  • M. Williams, Senior Specialist, Operations

l

D. LaBelle, Shift Supervisor, Operations

l

M. Schall, Shift Foreman, Operations

l

E. Hutt, Shift Foreman, Operations

l

l

K. Chism, Shift Foreman, Operations

i

K. Horn, Shift Foreman, Operations

'

R. Gibbs, Shift Technical Advisor, Operations

l

H. Harrelson, Operations

R. Mullis, Operations

D. Best, Operations

B. Jones, Operations

D. Jenkins, Operations

R. Blair, Operations

R. Knight, Operations

R. Poulk, Regulatory Compliance

  • T. Jones, Regulatory Compliance
  • J. Moyer, Manager, Training

l

E. Hawkins, Training

  • M. Shealy, Project Specialist', Training
  • B. Strickland, Project Specialist, Operations
  • A. Schmich, Senior Specialist, Corporate Nuclear Licensing
  • Denotes those personnel present at the exit meeting on October 7, 1988.

I

A-1

,

h

_ . _ . _ _ _ . _ _ _ _ _ _ _ _ _ - . _ . . _ _ _

&*.

.

I

a

,,

'

e

APPENDIX B

l

DOCUMENTS REVIEWED

l

l

Emergency Procedure Guidelines (EPGs), Revision 4AF, March 1987

l

Plant Specific Technical Guideline (PSTG) for EPG Revision 4, Draft D

i

EPG/PSTG Step Documentation, Draft D

l

Appendix A PSTG/EOP Step Documentation, Draft C

l

Procedures Generation Package (PGP), August 17, 1983

Administrative Instruction AI-95, " Verification and Validation Program for

EPG, Revision 4, based Emergency Operating Procedures," Draft A

MST-RPS-26R, "Drywell Pressure Setpoint Calibration," Revision 2

Engineering Evaluation Report No. 85-0231, Revision 0

l

General Area Personnel Dose Rates Versus Time (post-LOCA)

l

Emergency Operating Procedures (E0Ps):

E0P-01-UG, " User's Guide," Draft B

l

E0P-01-FP-1, " Path-1," Draft 0

l

E0P-01-FP-2, " Path-2," Draft E

E0P-01-FP-3, " Path-3," Draft E

E0P-01-FP-4, " Path-4," Draft D

l

E0P-01-FP-5, " Path-3," Draft D

E0P-0 rPP-5, "End Path Procedure," Draft H

E0P-01-LPC-1, " Level / Power Control Procedure," Draft E

I

E0P-02-PCCF, " Primary Containment Contml Procedure," Draft F

'0P-03-SCCF, " Secondary Containment C

.rol Procedure," Draft G

l

,

l

'

E0P-04-RRCP, " Radioactivity Release Co.. trol," Draft D

E0P-01-ALC, " Alternate Level Control," Revision E

i

E0P-01-AEDP, " Alternate Emergency Depressurization Procedure,"

Revision D

E0P-01-StCP, " Steam Cooling Procedure," Revision A

E0P-01-FP, "RPV Flooding Procedure," Revision E

E0P-01-PCFP, " Primary Containment Flooding Procedure," Revision B

E0P-01-LEP-01, " Alternate Coolant Injection," Revision 005

E0P-01-LEP-02, " Alternate Control Rod Insertion," Revision 005

E0P-01-LEP-03, " Alternate Boron Injection," Revision 004

E0P-01-SEP-01, " Primary Containment Venting," Draft D

E0P-01-SEP-02, "Drywell Spray Procedure," Draft C

.

E0P-01-SEP-03, " Suppression Pool Spray Procedure," Draft C

'

E0P-01-SEP-04, " Reactor Building HVAC Restart Procedure," Draft C

E0P-01-SEP-05, " Primary Containment Purging," Draft C

E0P-01-SEP-06, " Shutdown Following Boron Injection," Draft B

E0P-01-SEP-07, " Bypassing RWCU Filter Domineralizers," Draft B

E0P-01-SEP-09, "CRD Flow Maximization," Draft B

Operating Instructions and Procedures:

01-28, " Appendix C Writer's Guide for Emergency Operating Procedures

(EOPs)," Revision 6

01-37, " Preparation and Review of the Plant-Specific Technical Guideline

i

for EPG Revision 2,"

Revision 001

B-1

'

_ _ _ _ _ _ _ _ _ - _ _ _ _-_ -

l

1

,

g,*

,,

'

a

PT-16.2, " Primary Containment Volumetric Average Temperature,"

Revision 20

CP-05, " Unit Shutdown," Revision 28

OP-10. " Standby Gas Treatnient System," Revision 32 (Unit 2)

OP-17, " Residual Heat Removal System," Revision 77 (Unit 2)

OP-24, " Containment Atmosphere Control," Revision 26 (Unit 1)

i

,

)

B-2

L-______-____-_________________-

_ _ _ _ _ _