ML20205A160: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:. . .
{{#Wiki_filter:. . .
                                                                  -         _       _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _
-
  .
_
_ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _
.
'~
'~
)'
)
                                            ENCLOSURE
'
                        U.S. NUCLEAR REGULATORY COMMISSION
ENCLOSURE
                                            REGION IV
U.S. NUCLEAR REGULATORY COMMISSION
        Docket Nos.:   50-498;50-499
REGION IV
        License Nos.:   NPF-76; NPF-80
Docket Nos.:
        Report No.:     50-498/99-04;50-499/99-04
50-498;50-499
        Licensee:       STP Nuclear Operating Company
License Nos.:
        Facility:       South Texas Project Electric Generating Station, Units 1 and 2
NPF-76; NPF-80
        Location:       FM 521 - 8 miles west of Wadsworth
Report No.:
                        Wadsworth, Texas
50-498/99-04;50-499/99-04
        Dates:         February 22 to 25,1999
Licensee:
        Inspectors:     P. Gage, Senior Reactor inspector, Operations Granch
STP Nuclear Operating Company
                        P. Balmain, Operations Engineer, Office of Nuuoar Reactor Regulation
Facility:
                        P. Wilson, Senior Reactor Analyst, Office of Nuclear Reactor Regulation
South Texas Project Electric Generating Station, Units 1 and 2
        Approved By:   Dr. Dale A. Powers, Chief, Engineering and Maintenance Branch
Location:
                        Division of Reactor Safety
FM 521 - 8 miles west of Wadsworth
        ATTACHMENT:   Supplemental Information
Wadsworth, Texas
                                                                                                                        i
Dates:
                                    "
February 22 to 25,1999
    9903300300 990324
Inspectors:
    PDR   ADOCK 05000498
P. Gage, Senior Reactor inspector, Operations Granch
    G               PDR
P. Balmain, Operations Engineer, Office of Nuuoar Reactor Regulation
P. Wilson, Senior Reactor Analyst, Office of Nuclear Reactor Regulation
Approved By:
Dr. Dale A. Powers, Chief, Engineering and Maintenance Branch
Division of Reactor Safety
ATTACHMENT:
Supplemental Information
i
9903300300 990324
"
PDR
ADOCK 05000498
G
PDR


                                                                                                            __
,
,
__
    .
.
  .
.
                                                          2
2
                                              EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
                        South Texas Project Electric Generating Station, Units 1 and 2
South Texas Project Electric Generating Station, Units 1 and 2
                            NRC Inspection Report No. 50-498/99-04; 50-499/99-04
NRC Inspection Report No. 50-498/99-04; 50-499/99-04
      The licensee had developed and implemented a prograrn in accordance with 10 CFR 50.65,
The licensee had developed and implemented a prograrn in accordance with 10 CFR 50.65,
      " Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." One
" Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." One
      Non-Cited Violation of the Maintenance Rule was identified.
Non-Cited Violation of the Maintenance Rule was identified.
      Maintenance
Maintenance
      a
!nspectors identified inadequate reliability performance measures for eight plant risk-
              !nspectors identified inadequate reliability performance measures for eight plant risk-
a
              significant systems. As a result of the inadequate performance measures, the 480Vac
significant systems. As a result of the inadequate performance measures, the 480Vac
              load center system for both units was allowed to degrade beyond the probabilistic risk
load center system for both units was allowed to degrade beyond the probabilistic risk
              assessment assumed performance without the licensee having provided Odequate
assessment assumed performance without the licensee having provided Odequate
              technical justification for not having established goals, or appropriate corrective actions.
technical justification for not having established goals, or appropriate corrective actions.
              This was a Severity Level IV violation of the Maintenance Rule and is being treated as a
This was a Severity Level IV violation of the Maintenance Rule and is being treated as a
              Non-Cited Violation, consistent with Appendix C of the NRC enforcement policy
Non-Cited Violation, consistent with Appendix C of the NRC enforcement policy
              (EA 99-058). This violation is in the licensee's corrective action program as documented
(EA 99-058). This violation is in the licensee's corrective action program as documented
              by Condition Record 99-2925 (Section M1.2).
by Condition Record 99-2925 (Section M1.2).
                                                                                                              i
i
3
3
                                                                                                              l
1
                                                                                                              1
u
u


,
,
    -
-
                                                                                                            i
i
                                                                                                            j
j
                                                            3-
3-
                                                    Report Details                                         !
Report Details
      Summarv of Plant Status
Summarv of Plant Status
      During the inspection week, Units 1 and 2 operated at or near full power.                           t
During the inspection week, Units 1 and 2 operated at or near full power.
                                                                                                            i
t
      Backaround
i
      The licensee had implemented a Maintenance Rule program that endorsed the guidance of               q
Backaround
      Regulatory Guide 1.160," Monitoring the Effectiveness of Maintenance at Nuclear Power               1
The licensee had implemented a Maintenance Rule program that endorsed the guidance of
      Plants," and NUMARC 93-01 " Industry Guideline for Monitoring the Effectiveness of
q
      Maintenance at Nuclear Power Plants," with some exceptions noted. NRC Inspection                     h
Regulatory Guide 1.160," Monitoring the Effectiveness of Maintenance at Nuclear Power
      Report 50-498;-499/98-01 documented the results of the Maintenance Rule baseline team
1
      inspection.
Plants," and NUMARC 93-01 " Industry Guideline for Monitoring the Effectiveness of
                                                    II. Maintenance
Maintenance at Nuclear Power Plants," with some exceptions noted. NRC Inspection
      M1       Conduct of Maintenance
h
      M1.2 Safety or Risk Determination
Report 50-498;-499/98-01 documented the results of the Maintenance Rule baseline team
      a.       Insoection Scope (62706 and 92902)
inspection.
                The inspectors reviewed sensitivity studies that tb       nsee had completed to assess
II. Maintenance
                the risk contribution from the postulated unavailatt, .I 9 of the 21 risk significant
M1
                systems that were the subject of this inspection. The licensee representative had stated
Conduct of Maintenance
                that the postulated unavailability of these systems would not significantly contribute to
M1.2 Safety or Risk Determination
                the overall core damage frequency and, therefore, provided an additional basis for not
a.
                monitoring unavailability for these systems. The inspectors also reviewed the adequacy       i
Insoection Scope (62706 and 92902)
                of reliability performance criteria for several systems to determine if the licensee's     f
The inspectors reviewed sensitivity studies that tb
                probabilistic risk assessment reliability assumptions were preserved.                       J
nsee had completed to assess
      b.       Observations and Findinas                                                                   I
the risk contribution from the postulated unavailatt, .I 9 of the 21 risk significant
      b.1     Unavailability Sensitivity Studies
systems that were the subject of this inspection. The licensee representative had stated
                The licensee performed unavailability sensitivity studies on nine risk-significant systems. I
that the postulated unavailability of these systems would not significantly contribute to
                These studies were documented in the licensee's Analysis / Assessment Sequence
the overall core damage frequency and, therefore, provided an additional basis for not
                Numbers PSA-98-05, PSA-98-06, PSA-98-10, and PSA-99-01. The plant systems
monitoring unavailability for these systems. The inspectors also reviewed the adequacy
                included in these studies were as follows:                                                   ,
i
                .        Qualified Display Processing System (AM)
of reliability performance criteria for several systems to determine if the licensee's
                .
f
                        125Vdc Class 1E (DJ)
probabilistic risk assessment reliability assumptions were preserved.
                .       Main Steam Syctem (MS)
J
                .       4.16kVac Class 1E Power System (PK)
b.
                -      Reactor Coolant System (RC)
Observations and Findinas
              ,
b.1
  ..
Unavailability Sensitivity Studies
The licensee performed unavailability sensitivity studies on nine risk-significant systems.
I
These studies were documented in the licensee's Analysis / Assessment Sequence
Numbers PSA-98-05, PSA-98-06, PSA-98-10, and PSA-99-01. The plant systems
included in these studies were as follows:
Qualified Display Processing System (AM)
.
125Vdc Class 1E (DJ)
.
Main Steam Syctem (MS)
.
4.16kVac Class 1E Power System (PK)
.
Reactor Coolant System (RC)
-
,
..


r
r
  ,
,
                                                  -4-
-4-
        .          Reactor Control System (RS)
Reactor Control System (RS)
        -          Engineered Safety Features System (SF)
.
        .          Solid State Protection System (SP)
Engineered Safety Features System (SF)
        .         120Vac Class 1E Power System (VA)
-
        The inspectors noted that these studies evaluated the potential change in core damage
Solid State Protection System (SP)
        frequency if the probabilistic risk assessment assumptions for unavailability of these
.
        systems were doubled. In each study, the inspectors found that the licensee had
120Vac Class 1E Power System (VA)
        performed full probabilistic risk assessment requantifications. The inspectors reviewed
.
        one additional sensitivity study where the licensee requantified their probabilistic risk
The inspectors noted that these studies evaluated the potential change in core damage
        assessment with a postulated solid state protection system unavailability that was
frequency if the probabilistic risk assessment assumptions for unavailability of these
        17 times greater than the nominal probabilistic risk assessment solid state protection
systems were doubled. In each study, the inspectors found that the licensee had
        system unavailability. The inspectors observed that in all instances, the change in core
performed full probabilistic risk assessment requantifications. The inspectors reviewed
        damage frequency was small (less than 1 percent).
one additional sensitivity study where the licensee requantified their probabilistic risk
        The inspectors also compared recent actual maintenance unavailability for these
assessment with a postulated solid state protection system unavailability that was
        systems with the values assumed in the licensee's probabilistic risk assessment and
17 times greater than the nominal probabilistic risk assessment solid state protection
        found them to be reasonably close in value. Based on the inspectors' review of the
system unavailability. The inspectors observed that in all instances, the change in core
        licensee's sensitivity studies, the inspectors concluded that the licensee had adequately
damage frequency was small (less than 1 percent).
        demonstrated that the postulated unavailability of these systems did not significantly
The inspectors also compared recent actual maintenance unavailability for these
        contribute to the overall core damage frequency.
systems with the values assumed in the licensee's probabilistic risk assessment and
    b.2 Reliability Performance Criteria
found them to be reasonably close in value. Based on the inspectors' review of the
        NUMARC 93-01," Industry Guideline For Monitoring the Effectiveness of Maintenance at
licensee's sensitivity studies, the inspectors concluded that the licensee had adequately
        Nuclear Power Plants," Revision 2, Section 9.3.2, states, in part, ". . . that performance
demonstrated that the postulated unavailability of these systems did not significantly
        criteria for risk-significant SSCs should be established to assure that reliability and
contribute to the overall core damage frequency.
        availability assumptions used in the plant-specific PRA, IPE, IPEEE, or other risk           I
b.2
        determining analysis are maintained or adjusted when determined necessary by the
Reliability Performance Criteria
        utility." In general, the inspectors found that the licensee nad established two reliability
NUMARC 93-01," Industry Guideline For Monitoring the Effectiveness of Maintenance at
        performance criteria for each plant system. These were Maintenance Rule functional           i
Nuclear Power Plants," Revision 2, Section 9.3.2, states, in part, ". . . that performance
        failures and probabilistic safety assessment functional failures. The licensee               )
criteria for risk-significant SSCs should be established to assure that reliability and
        representative stated that the probabilistic safety assessment functional failure was the
availability assumptions used in the plant-specific PRA, IPE, IPEEE, or other risk
        criterion that assured that the probabilistic risk assessment reliability assumptions were
I
        maintained. The inspectors observed that there were eight risk-significant systems
determining analysis are maintained or adjusted when determined necessary by the
        where the licensee had not established probabilistic safety assessment functional failure   ,
utility." In general, the inspectors found that the licensee nad established two reliability
        performance criteria, in addition, the inspectors noted that the Maintenance Rule           I
performance criteria for each plant system. These were Maintenance Rule functional
        functional failure performance criteria established for those systems did not appear to
)
        preserve the probabilistic risk assessment reliability assumptions. As a result of this
failures and probabilistic safety assessment functional failures. The licensee
        observation, the licensee initiated corrective action and documented the problem in
representative stated that the probabilistic safety assessment functional failure was the
          Condition Record 99-2r48. The licensee promptly performed the necessary analyses to
criterion that assured that the probabilistic risk assessment reliability assumptions were
        establish appropriate probabilistic safety assessment functional failures for these
maintained. The inspectors observed that there were eight risk-significant systems
          systems. The results nf these analyses along with the Maintenance Rule functional
where the licensee had not established probabilistic safety assessment functional failure
          failure performance criteria are documented in the table below.
,
performance criteria, in addition, the inspectors noted that the Maintenance Rule
I
functional failure performance criteria established for those systems did not appear to
preserve the probabilistic risk assessment reliability assumptions. As a result of this
observation, the licensee initiated corrective action and documented the problem in
Condition Record 99-2r48. The licensee promptly performed the necessary analyses to
establish appropriate probabilistic safety assessment functional failures for these
systems. The results nf these analyses along with the Maintenance Rule functional
failure performance criteria are documented in the table below.
L
L


e ,     _
e ,
      +
_
    .
+
                                                            5-
.
          x
5-
                      System                         MRFF Criteria                       New PSAFFs
x
                Instrument Air :           5/ unit /18 months                         3/ unit /18 months
System
                Qualified Display         6/ unit /18 months                         3/ unit /18 months
MRFF Criteria
                Processing -                                 '-
New PSAFFs
                480Vac 1E Load             5/ train /18 months or 7/ unit /18 months   1/ unit /18 months
Instrument Air :
                Centers .
5/ unit /18 months
                480Vac Non-Class           2/ unit /18 months                         1/ unit /18 months
3/ unit /18 months
                1E Load Center
Qualified Display
                480Vac Class 1E           8/ train /18 months or 15/ unit /18 months 4/ unit /18 months
6/ unit /18 months
                Motor Control
3/ unit /18 months
                Centers
Processing -
                Reactor Control -         2/ unit /18 months                         1/ unit /18 months
' -
                System
480Vac 1E Load
                Solid State Protection     3/ unit /18 months                         1/ unit /18 months
5/ train /18 months or 7/ unit /18 months
                120Vac Vital Power'       3/ unit /18 months                         2/ unit /18 months
1/ unit /18 months
              Based on the results of the licensee's analyses, the inspectors concluded that the
Centers .
              Maintenance Rule functional failure reliability performance criteria did not assure that the
480Vac Non-Class
            '
2/ unit /18 months
              licensee's probabilistic risk assessment reliability assumptions were maintained and,
1/ unit /18 months
              therefore, the reliability performance criteria established for these systems were
1E Load Center
              inadequate.
480Vac Class 1E
              10 CFR 50.65 (a)(1) states, in part, that ". . . licensees shall monitor the performance or
8/ train /18 months or 15/ unit /18 months
              conditions of SSCs against licensee established goals, in a manner sufficient to provide
4/ unit /18 months
              reasonable assurance that such SSCs, as defined in paragraph (b), are capable of -
Motor Control
            . fulfilling their intended functions. Such goals shall be established commensurate with
Centers
              safety and where practical, take into account industry-wide operating experience. When
Reactor Control -
              the performance or condition of a SSC does not meet established goals, appropriate
2/ unit /18 months
              . corrective actions shall be taken." The inspectors reviewed the recent performance of       !
1/ unit /18 months
              the above systems and found that there had been six probabilistic safety assessment         i
System
              functional failures in Unit 1's 480Vac load centers and three probabilistic safety
Solid State Protection
              assessment functional failures in Unit 2's 480Vac load centers in the most recent 18
3/ unit /18 months
              ' months. However, since the licensee had not established probabilistic safety
1/ unit /18 months
              assessment functional failure performance criteria for these systems, the licensee had -     j
120Vac Vital Power'
                not evaluated these systems for Category (a)(1) nor established system performance
3/ unit /18 months
                goals and taken appropriate corrective action as required by the Maintenance Rule. As       i
2/ unit /18 months
                a result of this observation, the licensee initiated corrective action and documented the
Based on the results of the licensee's analyses, the inspectors concluded that the
                problem in Condition Record 99-2925.
Maintenance Rule functional failure reliability performance criteria did not assure that the
                                                                                                            ,
licensee's probabilistic risk assessment reliability assumptions were maintained and,
therefore, the reliability performance criteria established for these systems were
'
inadequate.
10 CFR 50.65 (a)(1) states, in part, that ". . . licensees shall monitor the performance or
conditions of SSCs against licensee established goals, in a manner sufficient to provide
reasonable assurance that such SSCs, as defined in paragraph (b), are capable of -
. fulfilling their intended functions. Such goals shall be established commensurate with
safety and where practical, take into account industry-wide operating experience. When
the performance or condition of a SSC does not meet established goals, appropriate
. corrective actions shall be taken." The inspectors reviewed the recent performance of
i
the above systems and found that there had been six probabilistic safety assessment
functional failures in Unit 1's 480Vac load centers and three probabilistic safety
assessment functional failures in Unit 2's 480Vac load centers in the most recent 18
' months. However, since the licensee had not established probabilistic safety
assessment functional failure performance criteria for these systems, the licensee had -
j
not evaluated these systems for Category (a)(1) nor established system performance
goals and taken appropriate corrective action as required by the Maintenance Rule. As
i
a result of this observation, the licensee initiated corrective action and documented the
problem in Condition Record 99-2925.
,
L.
L.


n
n
  .
.
                                                    6-
6-
    c.   Conclusiong                                                                               {
c.
          The inspectors concluded that the licensee had adequately demonstrated that the
Conclusiong
          postulated unavailability of nine systems did not significantly contribute to the overall
{
          core damage frequency. However, the inspectors identified inadequate reliability
The inspectors concluded that the licensee had adequately demonstrated that the
          performance measures for eight plant risk-significant systems. As a result of the
postulated unavailability of nine systems did not significantly contribute to the overall
          inadequate performance measures, the 480Vac load center system for both units was
core damage frequency. However, the inspectors identified inadequate reliability
          allowed to degrade beyond the probabilistic risk assessment assumed performance
performance measures for eight plant risk-significant systems. As a result of the
          without the licensee having provided adequate technical justification for not having
inadequate performance measures, the 480Vac load center system for both units was
          established goals, or appropriate corrective actions. This was a Severity Level IV
allowed to degrade beyond the probabilistic risk assessment assumed performance
          violation of the Maintenance Rule and is being treated as a Non-Cited Violation,
without the licensee having provided adequate technical justification for not having
          consistent with A.ppendix C of the NRC enforcement policy (EA 99-058). This violation
established goals, or appropriate corrective actions. This was a Severity Level IV
          is in the licensee's corrective action program as documented by Condition Record
violation of the Maintenance Rule and is being treated as a Non-Cited Violation,
          99-2925.
consistent with A.ppendix C of the NRC enforcement policy (EA 99-058). This violation
    M1.6 Goal Settina and Monitorina and Preventive Maintenance
is in the licensee's corrective action program as documented by Condition Record
    a.   Inspection Scope (62706)
99-2925.
          The inspectors reviewed program documents and records in order to evaluate the             ,
M1.6 Goal Settina and Monitorina and Preventive Maintenance
          process that was in place to establish performance measures for monitoring systems         !
a.
          under Category (a)(1), or to verify that preventive maintenance was effective under
Inspection Scope (62706)
          Category (a)(2) of the Maintenance Rule.                                                   I
The inspectors reviewed program documents and records in order to evaluate the
          The inspectors reviewed in detail the systems described below to verify: that goals or
,
          performance criteria were established with safety taken into consideration; that industry-
process that was in place to establish performance measures for monitoring systems
          wide operating experience was considered where practical; that appropriate monitoring
under Category (a)(1), or to verify that preventive maintenance was effective under
          and trending was being performed; and that corrective action was taken when a
Category (a)(2) of the Maintenance Rule.
          structure, system, or component function failed to meet its goal or performance criteria,
The inspectors reviewed in detail the systems described below to verify: that goals or
          or when a structure, system, or component function experienced a Maintenance Rule
performance criteria were established with safety taken into consideration; that industry-
          functional failure.
wide operating experience was considered where practical; that appropriate monitoring
                  AM     Post Accident Monitoring (PAM)
and trending was being performed; and that corrective action was taken when a
                  BS     7300 Processor Support
structure, system, or component function failed to meet its goal or performance criteria,
                  DJ     125Vdc Class 1E
or when a structure, system, or component function experienced a Maintenance Rule
                  FW     Feedwater
functional failure.
                  HM     Mechanical Auxiliar/ Building HVAC
AM
                  HZ     HVAC - Miscellaneous
Post Accident Monitoring (PAM)
                  MS     Main Steam
BS
                  NI     Nuclear instrumentation
7300 Processor Support
                  PC     13.8kVac Auxiliary Power
DJ
                  PE     480Vac Non-Class 1E Load Center
125Vdc Class 1E
                  PK     4.16kVac Class 1E Power
FW
                  PL     480Vac 1E Load Centers
Feedwater
                  PM     480Vac Class 1E MCC and Distribution Panels
HM
                  RC     Reactor Coolant
Mechanical Auxiliar/ Building HVAC
                  RS     Reactor Control
HZ
HVAC - Miscellaneous
MS
Main Steam
NI
Nuclear instrumentation
PC
13.8kVac Auxiliary Power
PE
480Vac Non-Class 1E Load Center
PK
4.16kVac Class 1E Power
PL
480Vac 1E Load Centers
PM
480Vac Class 1E MCC and Distribution Panels
RC
Reactor Coolant
RS
Reactor Control
L
L


      .
.
    .
.
                                                      -7-
-7-
                    SF       Engineered Safety Features Actuation
SF
                    SG       Steam Generator Secondary Side
Engineered Safety Features Actuation
                    SP       Solid State Protection
SG
                    VA       120Vac Class 1E Vital Power
Steam Generator Secondary Side
SP
Solid State Protection
VA
120Vac Class 1E Vital Power
XC
Containment Building
<
<
                    XC      Containment Building
XS,
                    XS,     Switchyard System Auxiliary Feedwater
Switchyard System Auxiliary Feedwater
        b. Observations and Findinas
b.
            As described in NUMARC 93-01, Revision 2, performance includes ". . . to the maximum
Observations and Findinas
            extent possible both availability and reliability should be used since that provides the
As described in NUMARC 93-01, Revision 2, performance includes ". . . to the maximum
            maximum assurance that performance is being maintained." The inspectors noted that
extent possible both availability and reliability should be used since that provides the
            under the terms of the Maintenance Rule, preventive maintenance must be
maximum assurance that performance is being maintained." The inspectors noted that
            demonstrated to be effective in controlling the performance or condition of a structure,
under the terms of the Maintenance Rule, preventive maintenance must be
            system, or component such that the structure, system or component remains capable of     !
demonstrated to be effective in controlling the performance or condition of a structure,
            performing its intended function.
system, or component such that the structure, system or component remains capable of
            The inspectors acknowledged, as stated in NUMARC 93-01, instances where availability
!
            does not provide a meaningful measure of performance and should not be captured.
performing its intended function.
            Examples of accepted structures, systems, and components, such as reactor coolant
The inspectors acknowledged, as stated in NUMARC 93-01, instances where availability
            system piping or electrical buses, were those which were not taken out-of-service for
does not provide a meaningful measure of performance and should not be captured.
            any routine testing or surveillance activities during power operations because of their
Examples of accepted structures, systems, and components, such as reactor coolant
            absolute necessity for operation.
system piping or electrical buses, were those which were not taken out-of-service for
            The inspectors found that specific safety functions associated with the electrical loads
any routine testing or surveillance activities during power operations because of their
            were monitored by the corresponding system being supplied in lieu of monitoring the
absolute necessity for operation.
            distribution system. For analogous mechanical systems, such as heating, ventilation,
The inspectors found that specific safety functions associated with the electrical loads
            and air-conditioning systems, unavailability was appropriately monitored at the
were monitored by the corresponding system being supplied in lieu of monitoring the
            supported systems. During the inspectors' review of the facility's risk-significant
distribution system. For analogous mechanical systems, such as heating, ventilation,
            structures, systems, and components without specific unavailability criteria, several
and air-conditioning systems, unavailability was appropriately monitored at the
            systems were found to appropriately satisfy performance monitoring requirements for
supported systems. During the inspectors' review of the facility's risk-significant
            the associated structures, systems, and components, including mechanical auxiliary
structures, systems, and components without specific unavailability criteria, several
            building heating ventilation air conditioning, miscellaneous heating ventilation air     l
systems were found to appropriately satisfy performance monitoring requirements for
            conditioning,13.8kVac auxiliary power,480Vac non-class 1E load centers,4.16kVac           l
the associated structures, systems, and components, including mechanical auxiliary
            Class 1E power,480Vac Class 1E load centers,480Vac Class 1E motor-control centers
building heating ventilation air conditioning, miscellaneous heating ventilation air
            and distribution panels, steam generator secondary side, containment building, and the
l
            switchyard system. Based on the system reviews, the inspectors deM; mined that these
conditioning,13.8kVac auxiliary power,480Vac non-class 1E load centers,4.16kVac
            structures, systems, and components were being adequately monitored with appropriate
Class 1E power,480Vac Class 1E load centers,480Vac Class 1E motor-control centers
            plant level criteria and reliability performance measures.
and distribution panels, steam generator secondary side, containment building, and the
            The inspectors observed that the steam generator power-operated relief valves, safety
switchyard system. Based on the system reviews, the inspectors deM; mined that these
            valves, and auxiliary feedwater steam supply were the only high safety-significant
structures, systems, and components were being adequately monitored with appropriate
            structures, systems, and components in the main steam system that provide standby
plant level criteria and reliability performance measures.
            functions. The licensee had established availability performance criteria for the steam
The inspectors observed that the steam generator power-operated relief valves, safety
            generator power-operated relief valves and did not remove safety valves from service
valves, and auxiliary feedwater steam supply were the only high safety-significant
            while online. The inspectors noted that should a safety valve need to be removed from
structures, systems, and components in the main steam system that provide standby
            service, performance would be adequately monitored by the plant level criteria. In
functions. The licensee had established availability performance criteria for the steam
  .-
generator power-operated relief valves and did not remove safety valves from service
          _
while online. The inspectors noted that should a safety valve need to be removed from
service, performance would be adequately monitored by the plant level criteria. In
.-


,     . i
i
      .
,
                            4
.
    4
.
                                                        -8-
4
            - addition, the inspectors found that the availability of the auxiliary feedwater system
4
              .st eam suppl y was appropr   itla e y mon
-8-
                                                      it ored und er auxiliary f
- addition, the inspectors found that the availability of the auxiliary feedwater system
                                                                              ee dwa er
t
                                                                                      t sys tem -
l
          -
itl
            . performance criteria.
it
              The inspectors observed that the pressurizer power-operated relief valves and safety
d
              valves were the only high safety-significant components in the reactor coolant system
d
              that provide standby functions. The inspectors noted that online maintenance is not
ili
              performed on the pressurizer power-operated relief valves and safety' valves. Licensee       {
f d
              representatives considered removal of the power-operated relief valves from service as       l
t
          . a Maintenance Rule functional failure and would monitor this under the corresponding         l
t
              reactor coolant system reliability performance criteria. In addition, the inspectors noted   I
.s eam supp y was appropr a e y mon ore un er aux ary ee wa er sys em -
              that if power-operated relief valves were isolated for extended periods of time because
-
              of excessive seat leakage, as permitted by the licensee's technical specifications, that
. performance criteria.
              the licensee's staff considered the power-operated relief valves available. ,This was
The inspectors observed that the pressurizer power-operated relief valves and safety
              because only one action is needed to be performed by a dedicated operator to restore
valves were the only high safety-significant components in the reactor coolant system
              the valves to service for their risk-significant function (feed and bleed). The inspectors
that provide standby functions. The inspectors noted that online maintenance is not
          - found this monitoring approach acceptable.
performed on the pressurizer power-operated relief valves and safety' valves. Licensee
              The inspectors observed that the licensee did not formally establish specific criteria
{
              associated with unavailability for risk significant systems, which were rendered
representatives considered removal of the power-operated relief valves from service as
              unavailable for various routine maintenance testing and surveillance activities. The
l
            ' inspectors noted that the affected systems included post accident monitoring,7300 -
. a Maintenance Rule functional failure and would monitor this under the corresponding
              processor support,125Vdc class 1E, main feedwater, main steam, nuclear
reactor coolant system reliability performance criteria. In addition, the inspectors noted
              instrumentation, reactor coolant, reactor control, engineered safety features actuation,
I
              solid state protection, and the 120Vac class 1E vital power system. The inspectors
that if power-operated relief valves were isolated for extended periods of time because
              observed that online maintenance performed on these systems typically involved the
of excessive seat leakage, as permitted by the licensee's technical specifications, that
              removal or alteration of a normal automatic alignment, involving a channel or train for
the licensee's staff considered the power-operated relief valves available. ,This was
              relatively short durations of time. Licensee representatives presented the basis for the
because only one action is needed to be performed by a dedicated operator to restore
              program's adequacy as the application of plant level criteria to all risk-significant
the valves to service for their risk-significant function (feed and bleed). The inspectors
              systems, and three conservative application points including: (1) loss of redundancy of     !'
- found this monitoring approach acceptable.
              a scoped function is a Maintenance Rule functional failure even if the train or system
The inspectors observed that the licensee did not formally establish specific criteria
              function was not lost, (2) loss of a scoped function is a Maintenance Rule functional
associated with unavailability for risk significant systems, which were rendered
              failure even if the function is not needed in the current plant mode, and (3) failures were
unavailable for various routine maintenance testing and surveillance activities. The
                                                                                                          i
' inspectors noted that the affected systems included post accident monitoring,7300 -
              considered Maintenance Rule functional failures regardless of whether maintenance
processor support,125Vdc class 1E, main feedwater, main steam, nuclear
              related activities were involved or associated with the failures.
instrumentation, reactor coolant, reactor control, engineered safety features actuation,
            - The inspectors verified that all risk-significant structures, systems, and components       .
solid state protection, and the 120Vac class 1E vital power system. The inspectors
              (with those exceptions documented in Section M1.2) had Maintenance Rule functional           i
observed that online maintenance performed on these systems typically involved the
              failure criteria established, no repeat Maintenance Rule functional failures were           ;
removal or alteration of a normal automatic alignment, involving a channel or train for
            ^ permitted, and that probabilistic safety assessment functional failure criteria were
relatively short durations of time. Licensee representatives presented the basis for the
              established for those systems, which were modeled in the probabilistic safety
program's adequacy as the application of plant level criteria to all risk-significant
              assessment. Licensee representatives stated that all unplanned maintenance                   ,
systems, and three conservative application points including: (1) loss of redundancy of
              unavailability was captured as a Maintenance Rule functional failure even if the
'
                Maintenance Rule function had not been lost prior to taking it out-of-service, as
a scoped function is a Maintenance Rule functional failure even if the train or system
                referenced in the licensee's response letter to the NRC, NOC-AE-000132, dated
function was not lost, (2) loss of a scoped function is a Maintenance Rule functional
                April 14,1998.
failure even if the function is not needed in the current plant mode, and (3) failures were
  E
i
considered Maintenance Rule functional failures regardless of whether maintenance
related activities were involved or associated with the failures.
- The inspectors verified that all risk-significant structures, systems, and components
.
(with those exceptions documented in Section M1.2) had Maintenance Rule functional
i
failure criteria established, no repeat Maintenance Rule functional failures were
;
^ permitted, and that probabilistic safety assessment functional failure criteria were
established for those systems, which were modeled in the probabilistic safety
assessment. Licensee representatives stated that all unplanned maintenance
,
unavailability was captured as a Maintenance Rule functional failure even if the
Maintenance Rule function had not been lost prior to taking it out-of-service, as
referenced in the licensee's response letter to the NRC, NOC-AE-000132, dated
April 14,1998.
E


p
p
    /
/
  4
4
                                                        .g.
.g.
            In addition, the licensee management's expectation included that planned maintenance
In addition, the licensee management's expectation included that planned maintenance
            activities, su::h as routine testing and surveillances, which exceed planned allowed
activities, su::h as routine testing and surveillances, which exceed planned allowed
            outage times for completion be characterized as Maintenance Rule functional failures.
outage times for completion be characterized as Maintenance Rule functional failures.
            The inspectors noted that this was not a formally documented policy within the
The inspectors noted that this was not a formally documented policy within the
            licensee's Maintenance Rule program, but found no examples where these conditions
licensee's Maintenance Rule program, but found no examples where these conditions
            had not been captured as such. The inspectors were provided a copy of Condition             .
had not been captured as such. The inspectors were provided a copy of Condition
            Record 99-2894, which documented management's intention for capturing unavailability       l
.
            related functional failures and to make the necessary formal changes within their
Record 99-2894, which documented management's intention for capturing unavailability
            Maintenance Rule program procedures.
related functional failures and to make the necessary formal changes within their
            The inspectors reviewed Licensee Event Report 98-004, Revision 00, and Condition
Maintenance Rule program procedures.
            Record 98 204565 for the solid state protection system and determined that adequate
The inspectors reviewed Licensee Event Report 98-004, Revision 00, and Condition
            evaluations were performed in accordance with management's expectations and the
Record 98 204565 for the solid state protection system and determined that adequate
            requirements of the Maintenance Rule. The inspectors considered the capturing of
evaluations were performed in accordance with management's expectations and the
            maintenance performance activities as functional failures with unplanned or untimely
requirements of the Maintenance Rule. The inspectors considered the capturing of
            activities as an indirect method of monitoring the associated unavailability of structures,
maintenance performance activities as functional failures with unplanned or untimely
            systems, and components.
activities as an indirect method of monitoring the associated unavailability of structures,
      c.   Conclusions
systems, and components.
            The inspectors determined that the licensee's approach to monitoring risk-significant
c.
            structures, systems, and components to be acceptable.
Conclusions
      M8   Miscellaneous Maintenance issues (92902)
The inspectors determined that the licensee's approach to monitoring risk-significant
      M8.1 (Closed) Violation 50-498:-499/9801-01: Failure to include the digital rod position
structures, systems, and components to be acceptable.
            indication and a control room heating ventilation air conditioning function within the
M8
            Maintenance Rule program scope. The inspectors verified that the licensee's staff had
Miscellaneous Maintenance issues (92902)
            placed the digital rod position indication system and the control room ventilation smo'ke
M8.1 (Closed) Violation 50-498:-499/9801-01: Failure to include the digital rod position
            purge actuation function in the scope of their Maintenance Rule program. In addition,
indication and a control room heating ventilation air conditioning function within the
            the inspectors found that adequate historical review for the Maintenance Rule functional
Maintenance Rule program scope. The inspectors verified that the licensee's staff had
            failures resulted in an appropriate classification in accordance with the Maintenance
placed the digital rod position indication system and the control room ventilation smo'ke
            Rule.
purge actuation function in the scope of their Maintenance Rule program. In addition,
      M8.2 (Closed) Unresolved item 50-498:-499/9801-03: Failure to adequately monitor the solid
the inspectors found that adequate historical review for the Maintenance Rule functional
            state protection system. The inspectors verified that the licensee's staff had establ!shed
failures resulted in an appropriate classification in accordance with the Maintenance
            an indirect method of monitoring unavailability for risk-significant structures, systems,
Rule.
            and components through capturing unplanned maintenance activities or planned routine
M8.2 (Closed) Unresolved item 50-498:-499/9801-03: Failure to adequately monitor the solid
            maintenance (testing or surveillance) exceeding allowed outage times as Maintenance
state protection system. The inspectors verified that the licensee's staff had establ!shed
            Rule functional failures. In addition, the inspectors noted that appropriate unavailability
an indirect method of monitoring unavailability for risk-significant structures, systems,
            sensitivity studies for probabilistic safety assessment modeled structures, systems, and
and components through capturing unplanned maintenance activities or planned routine
            components showed minimal risk impact. The inspectors concluded that the licensee's
maintenance (testing or surveillance) exceeding allowed outage times as Maintenance
            actions were considered acceptable.
Rule functional failures. In addition, the inspectors noted that appropriate unavailability
L       __
sensitivity studies for probabilistic safety assessment modeled structures, systems, and
components showed minimal risk impact. The inspectors concluded that the licensee's
actions were considered acceptable.
L


p
p
      '
'
i.                                                                                                         ,
i.
  . *
,
I                                                         -10-
. *
                                              V. Manacement Meetinas                                       I
I
        X1       Exit Meeting Summary
-10-
                                                                                                            i
V. Manacement Meetinas
        The inspectors discussed the progress of the inspection on a daily basis and presented the         l
X1
        inspection results to members of licensee management at the conclusion of the inspection on       I
Exit Meeting Summary
        February 25,1999. The licensee's management acknowledged the findings presented.                   i
i
        The inspectors asked the licensee staff and management whether any materials examined
The inspectors discussed the progress of the inspection on a daily basis and presented the
        during the inspection should be considered proprietary. No proprietary information was         -
inspection results to members of licensee management at the conclusion of the inspection on
        identified.
February 25,1999. The licensee's management acknowledged the findings presented.
        During the exit meeting on February 25,1999, the Manager, Systems Engineering, stated STP
i
        Nuclear Operating Company would include the requirement to count as a Maintenance Rule
The inspectors asked the licensee staff and management whether any materials examined
        functional failure any instance where a high-risk system (or one of its trains) that does not have
during the inspection should be considered proprietary. No proprietary information was
        availability performance criteria is taken out-of service (not performing its risk-significant
-
        function) while at power for corrective maintenance, or any instance when its technical
identified.
        specification allowed outage time is exceeded, and that this will apply even if no Maintenance
During the exit meeting on February 25,1999, the Manager, Systems Engineering, stated STP
        Rule function had been lost prior to taking the system out-of-service.
Nuclear Operating Company would include the requirement to count as a Maintenance Rule
functional failure any instance where a high-risk system (or one of its trains) that does not have
availability performance criteria is taken out-of service (not performing its risk-significant
function) while at power for corrective maintenance, or any instance when its technical
specification allowed outage time is exceeded, and that this will apply even if no Maintenance
Rule function had been lost prior to taking the system out-of-service.
l
l
L
L
i-
i-
I
Iw..
w..


v
v
    .
.
                                                                                                      :
9
  9
ATTACHMENT
                                                ATTACHMENT                                           j
j
                                      SUPPLEMENTAL INFORMATION
SUPPLEMENTAL INFORMATION
  '
'
                                  PARTIAL LIST OF PERSONS CONTACTED
PARTIAL LIST OF PERSONS CONTACTED
      - Licensee
- Licensee
        P. Arrington, License Engineering
P. Arrington, License Engineering
      W. Cottle, President and Chief Executive Officer
W. Cottle, President and Chief Executive Officer
      R. Grantom, Administrator, Risk Management
R. Grantom, Administrator, Risk Management
      J. Groth, Vice President, Generation
J. Groth, Vice President, Generation
      R. Harris, Manager, Reliability Engineering
R. Harris, Manager, Reliability Engineering
      S. Head, Supervisor, License Engineering                                                       l
S. Head, Supervisor, License Engineering
      J. Johnson, Manager, Engineering Quality                                                       ;
J. Johnson, Manager, Engineering Quality
      T. Jordan, Manager, System Engineering
T. Jordan, Manager, System Engineering
      A. Moldenhauer, Probabilistic Risk Assessment Engineer
A. Moldenhauer, Probabilistic Risk Assessment Engineer
      B. Mookhoek, License Engineering
B. Mookhoek, License Engineering
      M. Murray, Supervisor, S stem Engineering
M. Murray, Supervisor, S stem Engineering
      T. Riccio, System Engir sering
T. Riccio, System Engir sering
      J. Sheppard, Vice Prec, dent and Special Assistant to the President
J. Sheppard, Vice Prec, dent and Special Assistant to the President
      T. Stroschein, Supervisor, Engineering
T. Stroschein, Supervisor, Engineering
      J. Winters, Maintenance Rule Coordinator                                                       j
J. Winters, Maintenance Rule Coordinator
                                                                                                      i
j
      NBC                                                                                             ,
i
                                                                                                      !
NBC
      N. O'Keefe, Senior Resident inspector
,
                                      INSPECTION PROCEDURES USED
N. O'Keefe, Senior Resident inspector
          IP 62706         Maintenance Rule
INSPECTION PROCEDURES USED
          IP 92902         Followup - Maintenance
IP 62706
                                ITEMS OPENED. CLOSED. AND DISCUSSED
Maintenance Rule
          Opened
IP 92902
          50-498;-499/9904-01     NCV     Inspectors identified inadequate reliability performance
Followup - Maintenance
                                          measures for eight plant risk-significant systems. As a
ITEMS OPENED. CLOSED. AND DISCUSSED
                                          result of the inadequate performance measures, the
Opened
                                          480Vac load center system for both units was allowed to
50-498;-499/9904-01
                                          degrade beyond the probabilistic risk assessment assumed
NCV
                                          perforrnance without the licensee having provided
Inspectors identified inadequate reliability performance
                                          adequate technical justification for not having established
measures for eight plant risk-significant systems. As a
                                          goals, or appropriate corrective actions.
result of the inadequate performance measures, the
480Vac load center system for both units was allowed to
degrade beyond the probabilistic risk assessment assumed
perforrnance without the licensee having provided
adequate technical justification for not having established
goals, or appropriate corrective actions.


n
n
    .
.
  1
1
                                                  -2-
-2-
        Closed
Closed
        50-498;-499/9904-01 NCV     inspectors identified inadequate reliability performance
50-498;-499/9904-01
                                      measures for eight plant risk-significant systems. As a
NCV
                                      result of the inadequate performance measures, the
inspectors identified inadequate reliability performance
                                      480Vac load center system for both units was allowed to
measures for eight plant risk-significant systems. As a
                                      degrade beyond the probabilistb risk assessment assumed
result of the inadequate performance measures, the
                                      performance without the licensee having provided
480Vac load center system for both units was allowed to
                                      adequa e technical justification for not having established
degrade beyond the probabilistb risk assessment assumed
                                      goals, or appropriate corrective actions.                     4
performance without the licensee having provided
                                                                                                  /
adequa e technical justification for not having established
        50-498;-499/9801-01 NOV     Failure to include the digital rod position indication and a
goals, or appropriate corrective actions.
                                      control room heating ventilation air conditioning function
4/
                                      within the Maintenance Rule Program scope.
50-498;-499/9801-01
        50-498;-499/9801-03 URI     Failure to adequately monitor the solid state protection       1
NOV
                                      system.
Failure to include the digital rod position indication and a
                            PARTIAL LIST OF DOCUMENTS REVIEWED
control room heating ventilation air conditioning function
      Condition Records:
within the Maintenance Rule Program scope.
      98-20456
50-498;-499/9801-03
      99 2743
URI
      99 2908
Failure to adequately monitor the solid state protection
      99-2916
1
      99 2925
system.
      99-2984
PARTIAL LIST OF DOCUMENTS REVIEWED
      Licensee Correspondence:
Condition Records:
                                  .
98-20456
      NOC-AE-000132
99 2743
      NOC-AE-000230
99 2908
      Procedures:
99-2916
      Procedure                 Title                                                   Revision
99 2925
      OPGP03-ZA-0090           Work Process Program                                     20
99-2984
      OPGP03-ZX-0002           Condition Reporting Process                             17
Licensee Correspondence:
      OPSP03-SP-0005R           SSPS Logic Train R Functional Test                     7
.
      OPSP03 SP-00088         . SSPS Train B Slave Relay Test (Outputs Blocked) 4
NOC-AE-000132
      OPSP03-SP-0006R           Train R Reactor Trip Breaker TADGT                     5
NOC-AE-000230
      OPGP04-ZE-0313 -           Maintenance Rule Program                                 1
Procedures:
                                                                                                      4
Procedure
      OPGP03-ZA-0091             Configuration Risk Management Program                   0
Title
Revision
OPGP03-ZA-0090
Work Process Program
20
OPGP03-ZX-0002
Condition Reporting Process
17
OPSP03-SP-0005R
SSPS Logic Train R Functional Test
7
OPSP03 SP-00088
. SSPS Train B Slave Relay Test (Outputs Blocked) 4
OPSP03-SP-0006R
Train R Reactor Trip Breaker TADGT
5
OPGP04-ZE-0313 -
Maintenance Rule Program
1
4
OPGP03-ZA-0091
Configuration Risk Management Program
0
}}
}}

Latest revision as of 23:02, 23 May 2025

Insp Repts 50-498/99-04 & 50-499/99-04 on 990222-25. Violations Noted.Major Areas Inspected:Maint
ML20205A160
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 03/24/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20205A123 List:
References
50-498-99-04, 50-498-99-4, 50-499-99-04, 50-499-99-4, NUDOCS 9903300308
Download: ML20205A160 (12)


See also: IR 05000498/1999004

Text

. . .

-

_

_ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _

.

'~

)

'

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.:

50-498;50-499

License Nos.:

NPF-76; NPF-80

Report No.:

50-498/99-04;50-499/99-04

Licensee:

STP Nuclear Operating Company

Facility:

South Texas Project Electric Generating Station, Units 1 and 2

Location:

FM 521 - 8 miles west of Wadsworth

Wadsworth, Texas

Dates:

February 22 to 25,1999

Inspectors:

P. Gage, Senior Reactor inspector, Operations Granch

P. Balmain, Operations Engineer, Office of Nuuoar Reactor Regulation

P. Wilson, Senior Reactor Analyst, Office of Nuclear Reactor Regulation

Approved By:

Dr. Dale A. Powers, Chief, Engineering and Maintenance Branch

Division of Reactor Safety

ATTACHMENT:

Supplemental Information

i

9903300300 990324

"

PDR

ADOCK 05000498

G

PDR

,

__

.

.

2

EXECUTIVE SUMMARY

South Texas Project Electric Generating Station, Units 1 and 2

NRC Inspection Report No. 50-498/99-04; 50-499/99-04

The licensee had developed and implemented a prograrn in accordance with 10 CFR 50.65,

" Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." One

Non-Cited Violation of the Maintenance Rule was identified.

Maintenance

!nspectors identified inadequate reliability performance measures for eight plant risk-

a

significant systems. As a result of the inadequate performance measures, the 480Vac

load center system for both units was allowed to degrade beyond the probabilistic risk

assessment assumed performance without the licensee having provided Odequate

technical justification for not having established goals, or appropriate corrective actions.

This was a Severity Level IV violation of the Maintenance Rule and is being treated as a

Non-Cited Violation, consistent with Appendix C of the NRC enforcement policy

(EA 99-058). This violation is in the licensee's corrective action program as documented

by Condition Record 99-2925 (Section M1.2).

i

3

1

u

,

-

i

j

3-

Report Details

Summarv of Plant Status

During the inspection week, Units 1 and 2 operated at or near full power.

t

i

Backaround

The licensee had implemented a Maintenance Rule program that endorsed the guidance of

q

Regulatory Guide 1.160," Monitoring the Effectiveness of Maintenance at Nuclear Power

1

Plants," and NUMARC 93-01 " Industry Guideline for Monitoring the Effectiveness of

Maintenance at Nuclear Power Plants," with some exceptions noted. NRC Inspection

h

Report 50-498;-499/98-01 documented the results of the Maintenance Rule baseline team

inspection.

II. Maintenance

M1

Conduct of Maintenance

M1.2 Safety or Risk Determination

a.

Insoection Scope (62706 and 92902)

The inspectors reviewed sensitivity studies that tb

nsee had completed to assess

the risk contribution from the postulated unavailatt, .I 9 of the 21 risk significant

systems that were the subject of this inspection. The licensee representative had stated

that the postulated unavailability of these systems would not significantly contribute to

the overall core damage frequency and, therefore, provided an additional basis for not

monitoring unavailability for these systems. The inspectors also reviewed the adequacy

i

of reliability performance criteria for several systems to determine if the licensee's

f

probabilistic risk assessment reliability assumptions were preserved.

J

b.

Observations and Findinas

b.1

Unavailability Sensitivity Studies

The licensee performed unavailability sensitivity studies on nine risk-significant systems.

I

These studies were documented in the licensee's Analysis / Assessment Sequence

Numbers PSA-98-05, PSA-98-06, PSA-98-10, and PSA-99-01. The plant systems

included in these studies were as follows:

Qualified Display Processing System (AM)

.

125Vdc Class 1E (DJ)

.

Main Steam Syctem (MS)

.

4.16kVac Class 1E Power System (PK)

.

Reactor Coolant System (RC)

-

,

..

r

,

-4-

Reactor Control System (RS)

.

Engineered Safety Features System (SF)

-

Solid State Protection System (SP)

.

120Vac Class 1E Power System (VA)

.

The inspectors noted that these studies evaluated the potential change in core damage

frequency if the probabilistic risk assessment assumptions for unavailability of these

systems were doubled. In each study, the inspectors found that the licensee had

performed full probabilistic risk assessment requantifications. The inspectors reviewed

one additional sensitivity study where the licensee requantified their probabilistic risk

assessment with a postulated solid state protection system unavailability that was

17 times greater than the nominal probabilistic risk assessment solid state protection

system unavailability. The inspectors observed that in all instances, the change in core

damage frequency was small (less than 1 percent).

The inspectors also compared recent actual maintenance unavailability for these

systems with the values assumed in the licensee's probabilistic risk assessment and

found them to be reasonably close in value. Based on the inspectors' review of the

licensee's sensitivity studies, the inspectors concluded that the licensee had adequately

demonstrated that the postulated unavailability of these systems did not significantly

contribute to the overall core damage frequency.

b.2

Reliability Performance Criteria

NUMARC 93-01," Industry Guideline For Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants," Revision 2, Section 9.3.2, states, in part, ". . . that performance

criteria for risk-significant SSCs should be established to assure that reliability and

availability assumptions used in the plant-specific PRA, IPE, IPEEE, or other risk

I

determining analysis are maintained or adjusted when determined necessary by the

utility." In general, the inspectors found that the licensee nad established two reliability

performance criteria for each plant system. These were Maintenance Rule functional

)

failures and probabilistic safety assessment functional failures. The licensee

representative stated that the probabilistic safety assessment functional failure was the

criterion that assured that the probabilistic risk assessment reliability assumptions were

maintained. The inspectors observed that there were eight risk-significant systems

where the licensee had not established probabilistic safety assessment functional failure

,

performance criteria, in addition, the inspectors noted that the Maintenance Rule

I

functional failure performance criteria established for those systems did not appear to

preserve the probabilistic risk assessment reliability assumptions. As a result of this

observation, the licensee initiated corrective action and documented the problem in

Condition Record 99-2r48. The licensee promptly performed the necessary analyses to

establish appropriate probabilistic safety assessment functional failures for these

systems. The results nf these analyses along with the Maintenance Rule functional

failure performance criteria are documented in the table below.

L

e ,

_

+

.

5-

x

System

MRFF Criteria

New PSAFFs

Instrument Air :

5/ unit /18 months

3/ unit /18 months

Qualified Display

6/ unit /18 months

3/ unit /18 months

Processing -

' -

480Vac 1E Load

5/ train /18 months or 7/ unit /18 months

1/ unit /18 months

Centers .

480Vac Non-Class

2/ unit /18 months

1/ unit /18 months

1E Load Center

480Vac Class 1E

8/ train /18 months or 15/ unit /18 months

4/ unit /18 months

Motor Control

Centers

Reactor Control -

2/ unit /18 months

1/ unit /18 months

System

Solid State Protection

3/ unit /18 months

1/ unit /18 months

120Vac Vital Power'

3/ unit /18 months

2/ unit /18 months

Based on the results of the licensee's analyses, the inspectors concluded that the

Maintenance Rule functional failure reliability performance criteria did not assure that the

licensee's probabilistic risk assessment reliability assumptions were maintained and,

therefore, the reliability performance criteria established for these systems were

'

inadequate.

10 CFR 50.65 (a)(1) states, in part, that ". . . licensees shall monitor the performance or

conditions of SSCs against licensee established goals, in a manner sufficient to provide

reasonable assurance that such SSCs, as defined in paragraph (b), are capable of -

. fulfilling their intended functions. Such goals shall be established commensurate with

safety and where practical, take into account industry-wide operating experience. When

the performance or condition of a SSC does not meet established goals, appropriate

. corrective actions shall be taken." The inspectors reviewed the recent performance of

i

the above systems and found that there had been six probabilistic safety assessment

functional failures in Unit 1's 480Vac load centers and three probabilistic safety

assessment functional failures in Unit 2's 480Vac load centers in the most recent 18

' months. However, since the licensee had not established probabilistic safety

assessment functional failure performance criteria for these systems, the licensee had -

j

not evaluated these systems for Category (a)(1) nor established system performance

goals and taken appropriate corrective action as required by the Maintenance Rule. As

i

a result of this observation, the licensee initiated corrective action and documented the

problem in Condition Record 99-2925.

,

L.

n

.

6-

c.

Conclusiong

{

The inspectors concluded that the licensee had adequately demonstrated that the

postulated unavailability of nine systems did not significantly contribute to the overall

core damage frequency. However, the inspectors identified inadequate reliability

performance measures for eight plant risk-significant systems. As a result of the

inadequate performance measures, the 480Vac load center system for both units was

allowed to degrade beyond the probabilistic risk assessment assumed performance

without the licensee having provided adequate technical justification for not having

established goals, or appropriate corrective actions. This was a Severity Level IV

violation of the Maintenance Rule and is being treated as a Non-Cited Violation,

consistent with A.ppendix C of the NRC enforcement policy (EA 99-058). This violation

is in the licensee's corrective action program as documented by Condition Record

99-2925.

M1.6 Goal Settina and Monitorina and Preventive Maintenance

a.

Inspection Scope (62706)

The inspectors reviewed program documents and records in order to evaluate the

,

process that was in place to establish performance measures for monitoring systems

under Category (a)(1), or to verify that preventive maintenance was effective under

Category (a)(2) of the Maintenance Rule.

The inspectors reviewed in detail the systems described below to verify: that goals or

performance criteria were established with safety taken into consideration; that industry-

wide operating experience was considered where practical; that appropriate monitoring

and trending was being performed; and that corrective action was taken when a

structure, system, or component function failed to meet its goal or performance criteria,

or when a structure, system, or component function experienced a Maintenance Rule

functional failure.

AM

Post Accident Monitoring (PAM)

BS

7300 Processor Support

DJ

125Vdc Class 1E

FW

Feedwater

HM

Mechanical Auxiliar/ Building HVAC

HZ

HVAC - Miscellaneous

MS

Main Steam

NI

Nuclear instrumentation

PC

13.8kVac Auxiliary Power

PE

480Vac Non-Class 1E Load Center

PK

4.16kVac Class 1E Power

PL

480Vac 1E Load Centers

PM

480Vac Class 1E MCC and Distribution Panels

RC

Reactor Coolant

RS

Reactor Control

L

.

.

-7-

SF

Engineered Safety Features Actuation

SG

Steam Generator Secondary Side

SP

Solid State Protection

VA

120Vac Class 1E Vital Power

XC

Containment Building

<

XS,

Switchyard System Auxiliary Feedwater

b.

Observations and Findinas

As described in NUMARC 93-01, Revision 2, performance includes ". . . to the maximum

extent possible both availability and reliability should be used since that provides the

maximum assurance that performance is being maintained." The inspectors noted that

under the terms of the Maintenance Rule, preventive maintenance must be

demonstrated to be effective in controlling the performance or condition of a structure,

system, or component such that the structure, system or component remains capable of

!

performing its intended function.

The inspectors acknowledged, as stated in NUMARC 93-01, instances where availability

does not provide a meaningful measure of performance and should not be captured.

Examples of accepted structures, systems, and components, such as reactor coolant

system piping or electrical buses, were those which were not taken out-of-service for

any routine testing or surveillance activities during power operations because of their

absolute necessity for operation.

The inspectors found that specific safety functions associated with the electrical loads

were monitored by the corresponding system being supplied in lieu of monitoring the

distribution system. For analogous mechanical systems, such as heating, ventilation,

and air-conditioning systems, unavailability was appropriately monitored at the

supported systems. During the inspectors' review of the facility's risk-significant

structures, systems, and components without specific unavailability criteria, several

systems were found to appropriately satisfy performance monitoring requirements for

the associated structures, systems, and components, including mechanical auxiliary

building heating ventilation air conditioning, miscellaneous heating ventilation air

l

conditioning,13.8kVac auxiliary power,480Vac non-class 1E load centers,4.16kVac

Class 1E power,480Vac Class 1E load centers,480Vac Class 1E motor-control centers

and distribution panels, steam generator secondary side, containment building, and the

switchyard system. Based on the system reviews, the inspectors deM; mined that these

structures, systems, and components were being adequately monitored with appropriate

plant level criteria and reliability performance measures.

The inspectors observed that the steam generator power-operated relief valves, safety

valves, and auxiliary feedwater steam supply were the only high safety-significant

structures, systems, and components in the main steam system that provide standby

functions. The licensee had established availability performance criteria for the steam

generator power-operated relief valves and did not remove safety valves from service

while online. The inspectors noted that should a safety valve need to be removed from

service, performance would be adequately monitored by the plant level criteria. In

.-

i

,

.

.

4

4

-8-

- addition, the inspectors found that the availability of the auxiliary feedwater system

t

l

itl

it

d

d

ili

f d

t

t

.s eam supp y was appropr a e y mon ore un er aux ary ee wa er sys em -

-

. performance criteria.

The inspectors observed that the pressurizer power-operated relief valves and safety

valves were the only high safety-significant components in the reactor coolant system

that provide standby functions. The inspectors noted that online maintenance is not

performed on the pressurizer power-operated relief valves and safety' valves. Licensee

{

representatives considered removal of the power-operated relief valves from service as

l

. a Maintenance Rule functional failure and would monitor this under the corresponding

reactor coolant system reliability performance criteria. In addition, the inspectors noted

I

that if power-operated relief valves were isolated for extended periods of time because

of excessive seat leakage, as permitted by the licensee's technical specifications, that

the licensee's staff considered the power-operated relief valves available. ,This was

because only one action is needed to be performed by a dedicated operator to restore

the valves to service for their risk-significant function (feed and bleed). The inspectors

- found this monitoring approach acceptable.

The inspectors observed that the licensee did not formally establish specific criteria

associated with unavailability for risk significant systems, which were rendered

unavailable for various routine maintenance testing and surveillance activities. The

' inspectors noted that the affected systems included post accident monitoring,7300 -

processor support,125Vdc class 1E, main feedwater, main steam, nuclear

instrumentation, reactor coolant, reactor control, engineered safety features actuation,

solid state protection, and the 120Vac class 1E vital power system. The inspectors

observed that online maintenance performed on these systems typically involved the

removal or alteration of a normal automatic alignment, involving a channel or train for

relatively short durations of time. Licensee representatives presented the basis for the

program's adequacy as the application of plant level criteria to all risk-significant

systems, and three conservative application points including: (1) loss of redundancy of

'

a scoped function is a Maintenance Rule functional failure even if the train or system

function was not lost, (2) loss of a scoped function is a Maintenance Rule functional

failure even if the function is not needed in the current plant mode, and (3) failures were

i

considered Maintenance Rule functional failures regardless of whether maintenance

related activities were involved or associated with the failures.

- The inspectors verified that all risk-significant structures, systems, and components

.

(with those exceptions documented in Section M1.2) had Maintenance Rule functional

i

failure criteria established, no repeat Maintenance Rule functional failures were

^ permitted, and that probabilistic safety assessment functional failure criteria were

established for those systems, which were modeled in the probabilistic safety

assessment. Licensee representatives stated that all unplanned maintenance

,

unavailability was captured as a Maintenance Rule functional failure even if the

Maintenance Rule function had not been lost prior to taking it out-of-service, as

referenced in the licensee's response letter to the NRC, NOC-AE-000132, dated

April 14,1998.

E

p

/

4

.g.

In addition, the licensee management's expectation included that planned maintenance

activities, su::h as routine testing and surveillances, which exceed planned allowed

outage times for completion be characterized as Maintenance Rule functional failures.

The inspectors noted that this was not a formally documented policy within the

licensee's Maintenance Rule program, but found no examples where these conditions

had not been captured as such. The inspectors were provided a copy of Condition

.

Record 99-2894, which documented management's intention for capturing unavailability

related functional failures and to make the necessary formal changes within their

Maintenance Rule program procedures.

The inspectors reviewed Licensee Event Report 98-004, Revision 00, and Condition

Record 98 204565 for the solid state protection system and determined that adequate

evaluations were performed in accordance with management's expectations and the

requirements of the Maintenance Rule. The inspectors considered the capturing of

maintenance performance activities as functional failures with unplanned or untimely

activities as an indirect method of monitoring the associated unavailability of structures,

systems, and components.

c.

Conclusions

The inspectors determined that the licensee's approach to monitoring risk-significant

structures, systems, and components to be acceptable.

M8

Miscellaneous Maintenance issues (92902)

M8.1 (Closed) Violation 50-498:-499/9801-01: Failure to include the digital rod position

indication and a control room heating ventilation air conditioning function within the

Maintenance Rule program scope. The inspectors verified that the licensee's staff had

placed the digital rod position indication system and the control room ventilation smo'ke

purge actuation function in the scope of their Maintenance Rule program. In addition,

the inspectors found that adequate historical review for the Maintenance Rule functional

failures resulted in an appropriate classification in accordance with the Maintenance

Rule.

M8.2 (Closed) Unresolved item 50-498:-499/9801-03: Failure to adequately monitor the solid

state protection system. The inspectors verified that the licensee's staff had establ!shed

an indirect method of monitoring unavailability for risk-significant structures, systems,

and components through capturing unplanned maintenance activities or planned routine

maintenance (testing or surveillance) exceeding allowed outage times as Maintenance

Rule functional failures. In addition, the inspectors noted that appropriate unavailability

sensitivity studies for probabilistic safety assessment modeled structures, systems, and

components showed minimal risk impact. The inspectors concluded that the licensee's

actions were considered acceptable.

L

p

'

i.

,

. *

I

-10-

V. Manacement Meetinas

X1

Exit Meeting Summary

i

The inspectors discussed the progress of the inspection on a daily basis and presented the

inspection results to members of licensee management at the conclusion of the inspection on

February 25,1999. The licensee's management acknowledged the findings presented.

i

The inspectors asked the licensee staff and management whether any materials examined

during the inspection should be considered proprietary. No proprietary information was

-

identified.

During the exit meeting on February 25,1999, the Manager, Systems Engineering, stated STP

Nuclear Operating Company would include the requirement to count as a Maintenance Rule

functional failure any instance where a high-risk system (or one of its trains) that does not have

availability performance criteria is taken out-of service (not performing its risk-significant

function) while at power for corrective maintenance, or any instance when its technical

specification allowed outage time is exceeded, and that this will apply even if no Maintenance

Rule function had been lost prior to taking the system out-of-service.

l

L

i-

Iw..

v

.

9

ATTACHMENT

j

SUPPLEMENTAL INFORMATION

'

PARTIAL LIST OF PERSONS CONTACTED

- Licensee

P. Arrington, License Engineering

W. Cottle, President and Chief Executive Officer

R. Grantom, Administrator, Risk Management

J. Groth, Vice President, Generation

R. Harris, Manager, Reliability Engineering

S. Head, Supervisor, License Engineering

J. Johnson, Manager, Engineering Quality

T. Jordan, Manager, System Engineering

A. Moldenhauer, Probabilistic Risk Assessment Engineer

B. Mookhoek, License Engineering

M. Murray, Supervisor, S stem Engineering

T. Riccio, System Engir sering

J. Sheppard, Vice Prec, dent and Special Assistant to the President

T. Stroschein, Supervisor, Engineering

J. Winters, Maintenance Rule Coordinator

j

i

NBC

,

N. O'Keefe, Senior Resident inspector

INSPECTION PROCEDURES USED

IP 62706

Maintenance Rule

IP 92902

Followup - Maintenance

ITEMS OPENED. CLOSED. AND DISCUSSED

Opened

50-498;-499/9904-01

NCV

Inspectors identified inadequate reliability performance

measures for eight plant risk-significant systems. As a

result of the inadequate performance measures, the

480Vac load center system for both units was allowed to

degrade beyond the probabilistic risk assessment assumed

perforrnance without the licensee having provided

adequate technical justification for not having established

goals, or appropriate corrective actions.

n

.

1

-2-

Closed

50-498;-499/9904-01

NCV

inspectors identified inadequate reliability performance

measures for eight plant risk-significant systems. As a

result of the inadequate performance measures, the

480Vac load center system for both units was allowed to

degrade beyond the probabilistb risk assessment assumed

performance without the licensee having provided

adequa e technical justification for not having established

goals, or appropriate corrective actions.

4/

50-498;-499/9801-01

NOV

Failure to include the digital rod position indication and a

control room heating ventilation air conditioning function

within the Maintenance Rule Program scope.

50-498;-499/9801-03

URI

Failure to adequately monitor the solid state protection

1

system.

PARTIAL LIST OF DOCUMENTS REVIEWED

Condition Records:

98-20456

99 2743

99 2908

99-2916

99 2925

99-2984

Licensee Correspondence:

.

NOC-AE-000132

NOC-AE-000230

Procedures:

Procedure

Title

Revision

OPGP03-ZA-0090

Work Process Program

20

OPGP03-ZX-0002

Condition Reporting Process

17

OPSP03-SP-0005R

SSPS Logic Train R Functional Test

7

OPSP03 SP-00088

. SSPS Train B Slave Relay Test (Outputs Blocked) 4

OPSP03-SP-0006R

Train R Reactor Trip Breaker TADGT

5

OPGP04-ZE-0313 -

Maintenance Rule Program

1

4

OPGP03-ZA-0091

Configuration Risk Management Program

0