ML20065H772: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
(3 intermediate revisions by the same user not shown)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:..         .            .-                -
{{#Wiki_filter:..
e Omaha Public Power District 1623 HARNEY a   OMAHA, NE8RASMA 66102 a TELEPHONE 536 4000 AREA CODE 402 September 30, 1982 LIC-82-341 Mr. Robert A. Clark, Chief                                                         .
e Omaha Public Power District 1623 HARNEY a OMAHA, NE8RASMA 66102 a TELEPHONE 536 4000 AREA CODE 402 September 30, 1982 LIC-82-341 Mr. Robert A. Clark, Chief U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Licensing Operating Reactors Branch No. 3 Washington, D.C.
U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Licensing Operating Reactors Branch No. 3 Washington, D.C. 20555
20555


==Reference:==
==Reference:==
Line 25: Line 25:


==Dear fir. Clark:==
==Dear fir. Clark:==
 
Fort Calhoun Station Post Accident Sampling System (PASS)
Fort Calhoun Station Post Accident                             .
NUREG-0737, Item II.B.3 to Omaha Public Power District's {{letter dated|date=June 30, 1982|text=letter dated June 30, 1982}} identified the remaining work and expected schedule for completing the subject TMI Action Plan modification. At that time, the District expected the Fort Calhoun Station PASS to be declared fully operational by September 30, 1982.
Sampling System (PASS)
However, additional unanticipated equipment and hardware problems have resulted in delays that have prevented us from meeting this schedule. A status update, explanation of the work that remains to be completed, and a revised completion schedule are attached.
NUREG-0737, Item II.B.3 Attachment 1 to Omaha Public Power District's letter dated June 30, 1982 identified the remaining work and expected schedule for completing the subject TMI Action Plan modification. At that time, the District expected the Fort Calhoun Station PASS to be declared fully operational by September 30, 1982. However, additional unanticipated equipment and hardware problems have resulted in delays that have prevented us from meeting this schedule. A status update, explanation of the work that remains to be completed, and a revised completion schedule are attached.
Sincerely, hO i
Sincerely, i
W. C.
W. C.
hO ones Divis n Manager Production Operations WCJ/TLP:jmm Attachment cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.
ones Divis n Manager Production Operations WCJ/TLP:jmm Attachment cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.
Washington, D.C. 20036 oYb 0210050247 820930 PDR ADOCK 05000285 P                 PDR
Washington, D.C.
20036 oYb 0210050247 820930 PDR ADOCK 05000285 P
PDR


1 -
1 POST ACCIDENT SAMPLING SYSTEM (PASS) NUREG-0737, ITEM II.B.3 (MR-FC T91)_
POST ACCIDENT SAMPLING SYSTEM (PASS) NUREG-0737, ITEM II.B.3 (MR-FC     T91)_
NRC Required Completion Date: January 1,1982 Promised Completion Date:
NRC Required Completion Date: January 1,1982 Promised Completion Date:         September 30, 1982 Present Status and Reasons for Delay:
September 30, 1982 Present Status and Reasons for Delay:
The installation and. testing for this modification was expected to be complete September 30, 1982. During the testing phase, several unanti-cipated equipment and design problems were encountered, and these have delayed the completion of this system. The District would like to emphasize that the Post Accident Sampling System for the Fort Calhoun Station is a unique system which will be used for sampling during both
The installation and. testing for this modification was expected to be complete September 30, 1982.
              ~
During the testing phase, several unanti-cipated equipment and design problems were encountered, and these have delayed the completion of this system.
post accident and normal conditions. This has required the purchase and installation of several state-of-the-art instruments and has required a lengthy pre-operational testing procedure to simulate both nonnal and post accident conditions. With the exception of those items detailed       '
The District would like to emphasize that the Post Accident Sampling System for the Fort Calhoun Station is a unique system which will be used for sampling during both
below, the necessary actions have been completed to correct the problems encountered during system testing conducted in July and August.
~
: 1)   During pre-operational testing, the District determined that the waterbath drain line for SL-24 (Gross Dissolved Gas Analyzer) was too small. The District has decided to replace it with a larger line. The required parts were received September 29, 1982 and installation is presently underway.
post accident and normal conditions.
: 2)   A replacement for pressure transmitter PT-6703 is required since the wrong transmitter was delivered initially. A new component was ordered and it arrived on September 27, 1982 and will be installed in the near future.
This has required the purchase and installation of several state-of-the-art instruments and has required a lengthy pre-operational testing procedure to simulate both nonnal and post accident conditions. With the exception of those items detailed below, the necessary actions have been completed to correct the problems encountered during system testing conducted in July and August.
: 3)   There are still problems with the Ion Chromatograph that will 'be used to determine boron and chloride levels. The District is still investigating the problems found, which involve an inability of the instrument to discriminate between boron and chloride. In the interim, boron and chloride levels can be determined using a diluted grab sample from the Post Accident Sampling System.
1)
: 4)   During pre-operational testing, the District determined that-there is still 'a discrepancy involving the application of pressure con-trol valve PCV-2560 on the supply line to the~pH meter. -After discussing the discrepancy with the valve manufacturer, it was determined that although the valve had a safe working pressure of.
During pre-operational testing, the District determined that the waterbath drain line for SL-24 (Gross Dissolved Gas Analyzer) was too small. The District has decided to replace it with a larger line. The required parts were received September 29, 1982 and installation is presently underway.
2)
A replacement for pressure transmitter PT-6703 is required since the wrong transmitter was delivered initially. A new component was ordered and it arrived on September 27, 1982 and will be installed in the near future.
3)
There are still problems with the Ion Chromatograph that will 'be used to determine boron and chloride levels.
The District is still investigating the problems found, which involve an inability of the instrument to discriminate between boron and chloride.
In the interim, boron and chloride levels can be determined using a diluted grab sample from the Post Accident Sampling System.
4)
During pre-operational testing, the District determined that-there is still 'a discrepancy involving the application of pressure con-trol valve PCV-2560 on the supply line to the~pH meter. -After discussing the discrepancy with the valve manufacturer, it was determined that although the valve had a safe working pressure of.
3000 psig, " dead heading" of the valve on the downstream side risked failure of the valve diaphram,.thus providing a vent path to the room atmosphere. Resolution of this problem is still under review by the District's consultant. The anticipated corrective.
3000 psig, " dead heading" of the valve on the downstream side risked failure of the valve diaphram,.thus providing a vent path to the room atmosphere. Resolution of this problem is still under review by the District's consultant. The anticipated corrective.
action will. require either replacement of-the pit cell or install-ation of a relief valve and overpressure alarm.
action will. require either replacement of-the pit cell or install-ation of a relief valve and overpressure alarm.
Assuming that no further problems are encountered, the above changes should be done in approximately four weeks, Allowing two' weeks for
Assuming that no further problems are encountered, the above changes should be done in approximately four weeks, Allowing two' weeks for
    < testing and an additional two weeks for contingencies,.the system should be fully operational by November 30, 1982.
< testing and an additional two weeks for contingencies,.the system should be fully operational by November 30, 1982.


n Expected Completion Date:
n
- Expected Completion Date:
November 30, 1982 Interim Measures:
November 30, 1982 Interim Measures:
In accordance with the requirements of NUREG-0578, Item 2.1.8.a. Interim Post Accident Sampling procedures were developed and have been accepted by the Comission as detailed in the Comission's letter to the District dated April 7, 1980.
In accordance with the requirements of NUREG-0578, Item 2.1.8.a. Interim Post Accident Sampling procedures were developed and have been accepted by the Comission as detailed in the Comission's letter to the District dated April 7, 1980.
J l
J l
l
l
                                              . _ _ _ _ -    - _ _ -}}
- _ _ -}}

Latest revision as of 19:41, 16 December 2024

Forwards post-accident Sampling Sys Status Update & Revised Completion Schedule Per NUREG-0737,Item II.B.3. Reasons for Delay of TMI Action Plan Mod Discussed
ML20065H772
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 09/30/1982
From: William Jones
OMAHA PUBLIC POWER DISTRICT
To: Clark R
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-TM LIC-82-341, NUDOCS 8210050247
Download: ML20065H772 (3)


Text

..

e Omaha Public Power District 1623 HARNEY a OMAHA, NE8RASMA 66102 a TELEPHONE 536 4000 AREA CODE 402 September 30, 1982 LIC-82-341 Mr. Robert A. Clark, Chief U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Licensing Operating Reactors Branch No. 3 Washington, D.C.

20555

Reference:

Docket No. 50-285

Dear fir. Clark:

Fort Calhoun Station Post Accident Sampling System (PASS)

NUREG-0737, Item II.B.3 to Omaha Public Power District's letter dated June 30, 1982 identified the remaining work and expected schedule for completing the subject TMI Action Plan modification. At that time, the District expected the Fort Calhoun Station PASS to be declared fully operational by September 30, 1982.

However, additional unanticipated equipment and hardware problems have resulted in delays that have prevented us from meeting this schedule. A status update, explanation of the work that remains to be completed, and a revised completion schedule are attached.

Sincerely, hO i

W. C.

ones Divis n Manager Production Operations WCJ/TLP:jmm Attachment cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.

Washington, D.C.

20036 oYb 0210050247 820930 PDR ADOCK 05000285 P

PDR

1 POST ACCIDENT SAMPLING SYSTEM (PASS) NUREG-0737, ITEM II.B.3 (MR-FC T91)_

NRC Required Completion Date: January 1,1982 Promised Completion Date:

September 30, 1982 Present Status and Reasons for Delay:

The installation and. testing for this modification was expected to be complete September 30, 1982.

During the testing phase, several unanti-cipated equipment and design problems were encountered, and these have delayed the completion of this system.

The District would like to emphasize that the Post Accident Sampling System for the Fort Calhoun Station is a unique system which will be used for sampling during both

~

post accident and normal conditions.

This has required the purchase and installation of several state-of-the-art instruments and has required a lengthy pre-operational testing procedure to simulate both nonnal and post accident conditions. With the exception of those items detailed below, the necessary actions have been completed to correct the problems encountered during system testing conducted in July and August.

1)

During pre-operational testing, the District determined that the waterbath drain line for SL-24 (Gross Dissolved Gas Analyzer) was too small. The District has decided to replace it with a larger line. The required parts were received September 29, 1982 and installation is presently underway.

2)

A replacement for pressure transmitter PT-6703 is required since the wrong transmitter was delivered initially. A new component was ordered and it arrived on September 27, 1982 and will be installed in the near future.

3)

There are still problems with the Ion Chromatograph that will 'be used to determine boron and chloride levels.

The District is still investigating the problems found, which involve an inability of the instrument to discriminate between boron and chloride.

In the interim, boron and chloride levels can be determined using a diluted grab sample from the Post Accident Sampling System.

4)

During pre-operational testing, the District determined that-there is still 'a discrepancy involving the application of pressure con-trol valve PCV-2560 on the supply line to the~pH meter. -After discussing the discrepancy with the valve manufacturer, it was determined that although the valve had a safe working pressure of.

3000 psig, " dead heading" of the valve on the downstream side risked failure of the valve diaphram,.thus providing a vent path to the room atmosphere. Resolution of this problem is still under review by the District's consultant. The anticipated corrective.

action will. require either replacement of-the pit cell or install-ation of a relief valve and overpressure alarm.

Assuming that no further problems are encountered, the above changes should be done in approximately four weeks, Allowing two' weeks for

< testing and an additional two weeks for contingencies,.the system should be fully operational by November 30, 1982.

n

- Expected Completion Date:

November 30, 1982 Interim Measures:

In accordance with the requirements of NUREG-0578, Item 2.1.8.a. Interim Post Accident Sampling procedures were developed and have been accepted by the Comission as detailed in the Comission's letter to the District dated April 7, 1980.

J l

l

- _ _ -