ML052030339: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (One intermediate revision by the same user not shown) | |||
| Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:}} | {{#Wiki_filter:FENOC Perry Nuclear Power Plant I _ | ||
10 Center Road FrstEnergy Nuclear Operating Company Perry, Ohio 44081 Richard Anderson 440-280-5579 Vice President-Nuclear Fax: 440-280-8029 July 14, 2005 PY-CEI/NRR-2890L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen: | |||
Attached is the June 2005 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report." | |||
If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660. | |||
Very truly yours, Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector | |||
OPERATING DATA REPORT UNIT: | |||
EprrY DATE: | |||
7/6/05 | |||
: 1. | |||
Docket: 50-440 | |||
: 2. | |||
Unit Name: Perry Nuclear Power Plant | |||
: 3. | |||
Reporting Period June 2005 | |||
: 4. | |||
Utility | |||
==Contact:== | |||
T. Phelps | |||
: 5. | |||
Telephone: 440-280-7660 | |||
: 6. | |||
Design Electrical Rating (Net MWe): | |||
: 7. | |||
Maximum Dependable Capacity (Net MWe): | |||
1260 1235 | |||
: 8. | |||
H | |||
: 9. | |||
H | |||
: 10. | |||
U | |||
: 11. | |||
N This Month Yr-to-Date ours Reactor was Critical 720.0 2.051.9 ours Generator On-Line 720.0 1.946.5 nit Reserve Shutdown Hours 0.0 0.0 et Electrical Enerav (MWeH) 888.993.0 2.200.275.0 Cumulative 122.721.3 119.837.8 0.0 137.556.032.0 Page 1 | |||
I in UNIT SHUTDOWNS REPORT MONTH - June 2005 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 716105 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 Il No. | |||
Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence LHours 2 | |||
3 k | |||
==SUMMARY== | |||
: The Perry Nuclear Power Plant was on line the entire month of June 2005. | |||
: 1. TYPE: | |||
F: Forced S: Scheduled | |||
: 2. REASON: | |||
A-Equipment Failure (explain) 8 - Maintenance or Test C - Refueling D - Regulatory E - Operating Training & | |||
License Examination F - Administrative G - Operational Error (explain) | |||
H -Other (explain) | |||
: 3. METHOD: | |||
I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2 I}} | |||
Latest revision as of 17:07, 15 January 2025
| ML052030339 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 07/14/2005 |
| From: | Richard Anderson FirstEnergy Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| PY-CEI/NRR-2890L | |
| Download: ML052030339 (3) | |
Text
FENOC Perry Nuclear Power Plant I _
10 Center Road FrstEnergy Nuclear Operating Company Perry, Ohio 44081 Richard Anderson 440-280-5579 Vice President-Nuclear Fax: 440-280-8029 July 14, 2005 PY-CEI/NRR-2890L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:
Attached is the June 2005 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."
If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.
Very truly yours, Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector
OPERATING DATA REPORT UNIT:
EprrY DATE:
7/6/05
- 1.
Docket: 50-440
- 2.
Unit Name: Perry Nuclear Power Plant
- 3.
Reporting Period June 2005
- 4.
Utility
Contact:
T. Phelps
- 5.
Telephone: 440-280-7660
- 6.
Design Electrical Rating (Net MWe):
- 7.
Maximum Dependable Capacity (Net MWe):
1260 1235
- 8.
H
- 9.
H
- 10.
U
- 11.
N This Month Yr-to-Date ours Reactor was Critical 720.0 2.051.9 ours Generator On-Line 720.0 1.946.5 nit Reserve Shutdown Hours 0.0 0.0 et Electrical Enerav (MWeH) 888.993.0 2.200.275.0 Cumulative 122.721.3 119.837.8 0.0 137.556.032.0 Page 1
I in UNIT SHUTDOWNS REPORT MONTH - June 2005 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 716105 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 Il No.
Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence LHours 2
3 k
SUMMARY
- The Perry Nuclear Power Plant was on line the entire month of June 2005.
- 1. TYPE:
F: Forced S: Scheduled
- 2. REASON:
A-Equipment Failure (explain) 8 - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &
License Examination F - Administrative G - Operational Error (explain)
H -Other (explain)
- 3. METHOD:
I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2 I