{{#Wiki_filter:October 31, 2012 | {{#Wiki_filter:October 31, 2012 | ||
==SUBJECT:== | |||
NRC INSPECTION REPORT 05000151/12005(DNMS) UNIVERSITY OF ILLINOIS NUCLEAR REACTOR | |||
Urbana, | ==Dear Mr. Holm:== | ||
On October 15, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the permanently shut down University of Illinois Advanced Teaching Research Isotope General Atomic (TRIGA) Nuclear Research Reactor, Urbana, Illinois. The purpose of the inspection was to determine whether decommissioning activities were conducted safely and in accordance with NRC requirements. Specifically, during an on-site inspection on July 23, 2012, and subsequent in-office review through October 15, 2012, the inspectors conducted independent confirmatory radiation surveys and sampling, and evaluated your contractors decommissioning performance. At the conclusion of the on-site inspection, the inspectors discussed the interim inspection results with your decommissioning contractor. At the conclusion of the in-office review, a final telephone exit meeting was conducted with you on October 15, 2012. | |||
This inspection consisted of an examination of decommissioning activities at the site as they relate to safety and compliance with the Commissions rules and regulations. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection included the performance of confirmatory surveys and a selective examination of decommissioning documents. | |||
Based on the results of this inspection, no violations were identified. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), | |||
accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection. | |||
Sincerely, | |||
/RA/ | |||
Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety | |||
Docket No. 050-00151 License No. R-115 | |||
Enclosure: | |||
NRC Inspection Report No. 05000151/12005(DNMS) | |||
cc w/encl: J. Klinger, Illinois Emergency Management Agency (IEMA) | |||
K. Horn, IEMA | |||
C. Settles, IEMA | |||
L. Prussing, Mayor, City of Urbana | |||
J. Stubbins, University of Illinois | |||
}} | }} | ||
Latest revision as of 21:21, 11 January 2025
| ML12307A330 | |
| Person / Time | |
|---|---|
| Site: | University of Illinois |
| Issue date: | 10/31/2012 |
| From: | Christine Lipa NRC/RGN-III/DNMS/MCID |
| To: | Holm R University of Illinois |
| Rodriguez L | |
| References | |
| IR-12-005 | |
| Download: ML12307A330 (12) | |
Text
October 31, 2012
SUBJECT:
NRC INSPECTION REPORT 05000151/12005(DNMS) UNIVERSITY OF ILLINOIS NUCLEAR REACTOR
Dear Mr. Holm:
On October 15, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the permanently shut down University of Illinois Advanced Teaching Research Isotope General Atomic (TRIGA) Nuclear Research Reactor, Urbana, Illinois. The purpose of the inspection was to determine whether decommissioning activities were conducted safely and in accordance with NRC requirements. Specifically, during an on-site inspection on July 23, 2012, and subsequent in-office review through October 15, 2012, the inspectors conducted independent confirmatory radiation surveys and sampling, and evaluated your contractors decommissioning performance. At the conclusion of the on-site inspection, the inspectors discussed the interim inspection results with your decommissioning contractor. At the conclusion of the in-office review, a final telephone exit meeting was conducted with you on October 15, 2012.
This inspection consisted of an examination of decommissioning activities at the site as they relate to safety and compliance with the Commissions rules and regulations. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection included the performance of confirmatory surveys and a selective examination of decommissioning documents.
Based on the results of this inspection, no violations were identified.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS),
accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety
Docket No. 050-00151 License No. R-115
Enclosure:
NRC Inspection Report No. 05000151/12005(DNMS)
cc w/encl: J. Klinger, Illinois Emergency Management Agency (IEMA)
K. Horn, IEMA
C. Settles, IEMA
L. Prussing, Mayor, City of Urbana
J. Stubbins, University of Illinois