{{#Wiki_filter:February 14, 2008  
{{#Wiki_filter:February 14, 2008  
 
Rick A. Muench, President and   Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS  66839  
 
SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000482/2008003) AND REQUEST FOR INFORMATION  
Rick A. Muench, President and
  Chief Executive Officer  
Wolf Creek Nuclear Operating Corporation  
P.O. Box 411  
Burlington, KS  66839  
SUBJECT:  
WOLF CREEK GENERATING STATION - NOTIFICATION OF INSPECTION  
(NRC INSPECTION REPORT 05000482/2008003) AND REQUEST FOR  
INFORMATION  
   
   
Dear Mr. Muench:  
Dear Mr. Muench:  
  From March 31 to April 11, 2008, reactor inspectors from the Nuclear Regulatory Commission's (NRC) Region IV office will perform the baseline inservice inspection at Wolf Creek Generating Station using NRC Inspection Procedure 71111.08.  Experience has shown  
   
that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.  In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.  These documents have been divided into two groups.  The first group (Section A of the enclosure) identified information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.  The second group (Section B of the enclosure) identifies the information the inspectors will need upon arrival at the site.  It is important that all of these documents are up to date and complete  
From March 31 to April 11, 2008, reactor inspectors from the Nuclear Regulatory  
in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.  
Commissions (NRC) Region IV office will perform the baseline inservice inspection at Wolf  
  We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. W. Muilenburg of your licensing  
Creek Generating Station using NRC Inspection Procedure 71111.08.  Experience has shown  
organization.  Our inspection dates are subject to change based on your updated schedule of outage activities.  If there are any questions about this inspection or the material requested, please contact the lead inspector Lee Ellershaw at (817) 860-8127 (lee1@nrc.gov).   UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV611 RYAN PLAZA DRIVE, SUITE 400ARLINGTON, TEXAS 76011-4005  
that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.   
Wolf Creek Nuclear Operating Corp. - 2 -
In order to minimize the impact to your onsite resources and to ensure a productive inspection,  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
we have enclosed a request for documents needed for this inspection.  These documents have  
  Sincerely,  /RA/ 
been divided into two groups.  The first group (Section A of the enclosure) identified information  
Russell L. Bywater, Chief  Engineering Branch 1  Division of Reactor Safety
to be provided prior to the inspection to ensure that the inspectors are adequately prepared.   
Docket:    50-482 License:    NPF-42
The second group (Section B of the enclosure) identifies the information the inspectors will need  
upon arrival at the site.  It is important that all of these documents are up to date and complete  
in order to minimize the number of additional documents requested during the preparation  
and/or the onsite portions of the inspection.  
   
We have discussed the schedule for these inspection activities with your staff and understand  
that our regulatory contact for this inspection will be Mr. W. Muilenburg of your licensing  
organization.  Our inspection dates are subject to change based on your updated schedule of  
outage activities.  If there are any questions about this inspection or the material requested,  
please contact the lead inspector Lee Ellershaw at (817) 860-8127 (lee1@nrc.gov).
UNITED STATES
NUCLEAR REGULATORY COMMISSION
R E GI ON  I V
611 RYAN PLAZA DRIV E, SUITE 400
ARLINGTON, TEXAS 76011-4005


  Enclosure: Inservice Inspection Document Request  
Wolf Creek Nuclear Operating Corp.
  cc w/enclosure:  
- 2 -
Vice President Operations/Plant Manager Wolf Creek Nuclear Operating Corp. P.O. Box 411 Burlington, KS  66839  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Russell L. Bywater, Chief
Engineering Branch 1
Division of Reactor Safety
   
Docket:    50-482
License:    NPF-42
Enclosure:  
Inservice Inspection Document Request  
   
cc w/enclosure:  
Vice President Operations/Plant Manager  
Wolf Creek Nuclear Operating Corp.
P.O. Box 411
Burlington, KS  66839
Jay Silberg, Esq.
Pillsbury Winthrop Shaw Pittman LLP
2300 N Street, NW
Washington, DC  20037
Supervisor Licensing
Wolf Creek Nuclear Operating Corp.  
P.O. Box 411  
Burlington, KS  66839  
   
   
Jay Silberg, Esq. Pillsbury Winthrop Shaw Pittman LLP 2300 N Street, NW Washington, DC 20037
Chief Engineer
Utilities Division
Kansas Corporation Commission
1500 SW Arrowhead Road
Topeka, KS 66604-4027
   
   
Supervisor Licensing Wolf Creek Nuclear Operating Corp. P.O. Box 411 Burlington, KS  66839
Office of the Governor
State of Kansas
Topeka, KS  66612
   
   
Chief Engineer Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS  66604-4027
Attorney General  
Office of the Governor
120 S.W. 10th Avenue, 2nd Floor  
State of Kansas Topeka, KS  66612
Topeka, KS  66612-1597  
Attorney General 120 S.W. 10th Avenue, 2nd Floor  
 
Topeka, KS  66612-1597
Wolf Creek Nuclear Operating Corp.  
Wolf Creek Nuclear Operating Corp. - 3 -  
- 3 -  
  County Clerk Coffey County Courthouse 110 South 6th Street  
County Clerk  
Coffey County Courthouse  
110 South 6th Street  
Burlington, KS  66839-1798  
Burlington, KS  66839-1798  
Chief, Radiation and Asbestos    Control Section Kansas Department of Health and 
  Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS  66612-1366
Ronald L. McCabe, Chief Technological Hazards Branch
National Preparedness Division DHS/FEMA 9221 Ward Parkway Suite 300 Kansas City, MO
  64114-3372 
Wolf Creek Nuclear Operating Corp. - 4 -
  Electronic distribution by RIV:
Regional Administrator (EEC) DRP Director (DDC) DRS Director (RJC1) DRS Deputy Director (ACC) Senior Resident Inspector (SDC) SRI, Callaway (DED) Branch Chief, DRP/B (VGG) Senior Project Engineer, (RWD) Team Leader, DRP/TSS (CJP) RITS Coordinator (MSH3) DRS STA (DAP) D. Pelton, OEDO RIV Coordinator (DLP1) ROPreports
WC Site Secretary (SLA2) 
   
   
   
   
  SUNSI Review Completed:  __RLB____ADAMS:  Yes G  No            Initials: _RLB_____    Publicly Available     
G  Non-Publicly Available     
G  Sensitive    Non-Sensitive
  RI:EB1 C:EB1    LEEllershaw:lar RLBywater    /RA/ /RA/
  2/13/08 2/14/08    OFFICIAL RECORD COPY  T=Telephone          E=E-mail        F=Fax
 
  - 1 - Enclosure INSERVICE INSPECTION DOCUMENT REQUEST
  Inspection Dates: March 31, 2008 - April 11, 2008
   
   
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" TI 2515/166 "Pressurized Water Reactor Containment Sump Blockage" TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds"
Chief, Radiation and Asbestos 
  Control Section
Kansas Department of Health and 
  Environment
Bureau of Air and Radiation
1000 SW Jackson, Suite 310
Topeka, KS  66612-1366
Ronald L. McCabe, Chief
Technological Hazards Branch
National Preparedness Division
DHS/FEMA
9221 Ward Parkway
Suite 300
Kansas City, MO  64114-3372
 
Wolf Creek Nuclear Operating Corp.
- 4 -
Electronic distribution by RIV:  
Regional Administrator (EEC)
DRP Director (DDC)
DRS Director (RJC1)
DRS Deputy Director (ACC)
Senior Resident Inspector (SDC)
SRI, Callaway (DED)
Branch Chief, DRP/B (VGG)
Senior Project Engineer, (RWD)
Team Leader, DRP/TSS (CJP)
RITS Coordinator (MSH3)
DRS STA (DAP)
D. Pelton, OEDO RIV Coordinator (DLP1)
ROPreports
WC Site Secretary (SLA2)  
SUNSI Review Completed:  __RLB____ADAMS:  Yes
G  No            Initials: _RLB_____ 
  Publicly Available      G  Non-Publicly Available      G  Sensitive
  Non-Sensitive
RI:EB1
C:EB1
LEEllershaw:lar
RLBywater
/RA/  
/RA/
2/13/08
2/14/08
OFFICIAL RECORD COPY 
T=Telephone          E=E-mail        F=Fax
 
   
   
Inspectors: L. Ellershaw, Senior Reactor Inspector (Lead Inspector - ISI) J. Drake, Senior Reactor Inspector K. Clayton, Reactor Inspector  
  A. Information Requested for the In-Office Preparation Week  
- 1 -
  The following information should be sent to the Region IV office in hard copy or  
Enclosure
electronic format (ims.certrec.com preferred), in care of L. E. Ellershaw, by March 11, 2008, to facilitate the selection of specific items that will be reviewed during the onsite inspection week.  The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure).  We ask that the specific items selected  
INSERVICE INSPECTION DOCUMENT REQUEST
from the lists be available and ready for review on the first day of inspection.  *Please provide requested documentation electronically if possible.  If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection.  If you have any questions regarding this information request, please call the inspector as soon as  
Inspection Dates:
March 31, 2008 - April 11, 2008
Inspection Procedures:
IP 71111.08 Inservice Inspection (ISI) Activities
TI 2515/166 Pressurized Water Reactor Containment Sump
Blockage
TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds
Inspectors:  
L. Ellershaw, Senior Reactor Inspector (Lead Inspector - ISI)  
J. Drake, Senior Reactor Inspector  
K. Clayton, Reactor Inspector  
   
A.  
Information Requested for the In-Office Preparation Week  
   
The following information should be sent to the Region IV office in hard copy or  
electronic format (ims.certrec.com preferred), in care of L. E. Ellershaw, by March 11,  
2008, to facilitate the selection of specific items that will be reviewed during the onsite  
inspection week.  The inspector will select specific items from the information requested  
below and then request from your staff additional documents needed during the onsite  
inspection week (Section B of this enclosure).  We ask that the specific items selected  
from the lists be available and ready for review on the first day of inspection.  *Please  
provide requested documentation electronically if possible.  If requested documents are  
large and only hard copy formats are available, please inform the inspector(s), and  
provide subject documentation during the first day of the onsite inspection.  If you have  
any questions regarding this information request, please call the inspector as soon as  
possible.  
possible.  
  A.1 ISI/Welding Programs and Schedule Information
   
  a) A detailed schedule (including preliminary dates) of:  
A.1  
  i)  Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, Risk Informed (if applicable), and augmented ISI programs during the upcoming outage.  
ISI/Welding Programs and Schedule Information  
  Provide a status summary of the NDE inspection activities vs. the required inspection period percentages for this Interval by category per ASME Section XI, IWX-2400 (Do not provide separately if other documentation requested contains this information)  
  ii)  Reactor pressure vessel head (RPVH) examinations planned for the upcoming outage.  
a)  
  iii) Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope. (If applicable)   
A detailed schedule (including preliminary dates) of:  
  - 2 - Enclosure  
   
  iv) Examinations planned as part of your Boric Acid Corrosion Control Program (Mode 3 walkdowns, bolted connection walkdowns, etc.)  
i)   
  v) Welding activities that are scheduled to be completed during the upcoming outage (ASME Class 1, 2, or 3 structures, systems, or components (SSCs))  
Nondestructive examinations (NDEs) planned for Class 1 & 2 systems  
  b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations identified above.   
and containment, performed as part of your ASME Section XI, Risk  
  c) A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate, Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code Class 1 & 2 systems since the beginning of the last refueling outage.  This should include the previous Section XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.  Also, include in the list the NDE reports with relevant conditions in the RPVH penetration nozzles  
Informed (if applicable), and augmented ISI programs during the  
which have been accepted for continued service.  The list of NDE reports should include a brief description of the SSC where the relevant condition was identified.  
upcoming outage.  
  d) A list with a brief description (e.g., system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1 and 2 systems which have been  
   
fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage.   
Provide a status summary of the NDE inspection activities vs. the  
  e) If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to  
required inspection period percentages for this Interval by category per  
be examined and the extent of the planned examination.  Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.  
ASME Section XI, IWX-2400 (Do not provide separately if other  
  f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.  
documentation requested contains this information)  
  g)  A list of any temporary non-code repairs in service (e.g., pinhole leaks).  
   
  h) Please provide copies of the most recent self assessments for the ISI, Welding, and Alloy 600 Programs.   
ii)   
  A.2 Reactor Pressure Vessel Head (RPVH)
Reactor pressure vessel head (RPVH) examinations planned for the  
  a)  Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the  
upcoming outage.  
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02 and NRC Order EA-03-009.  Also, include examination scope expansion criteria and planned expansion sample sizes if relevant conditions are identified. (If applicable)   
   
  - 3 - Enclosure  
iii)  
  b)  A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g., the specific industry or procedural standards which will be used to evaluate potential leakage and/or flaw indications).  
Examinations planned for Alloy 82/182/600 components that are not  
  A.3 Boric Acid Corrosion Control Program (BACCP)
included in the Section XI scope. (If applicable)  
  a)  Copy of the procedures that govern the scope, equipment and implementation of the inspections required to identify boric acid leakage and the procedures for  
 
   
- 2 -  
Enclosure  
   
iv)  
Examinations planned as part of your Boric Acid Corrosion Control  
Program (Mode 3 walkdowns, bolted connection walkdowns, etc.)  
   
v)  
Welding activities that are scheduled to be completed during the  
upcoming outage (ASME Class 1, 2, or 3 structures, systems, or  
components (SSCs))  
   
b)  
A copy of ASME Section XI Code Relief Requests and associated NRC Safety  
Evaluations applicable to the examinations identified above.   
c)  
A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate,  
Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code  
Class 1 & 2 systems since the beginning of the last refueling outage.  This should  
include the previous Section XI pressure test(s) conducted during start up and  
any evaluations associated with the results of the pressure tests.  Also, include in  
the list the NDE reports with relevant conditions in the RPVH penetration nozzles  
which have been accepted for continued service.  The list of NDE reports should  
include a brief description of the SSC where the relevant condition was identified.  
   
d)  
A list with a brief description (e.g., system, material, pipe size, weld number, and  
NDE performed) of the welds in Code Class 1 and 2 systems which have been  
fabricated due to component repair/replacement activities since the beginning of  
the last refueling outage, or are planned to be fabricated this refueling outage.   
   
e)  
If reactor vessel weld examinations required by the ASME Code are scheduled to  
occur during the upcoming outage, provide a detailed description of the welds to  
be examined and the extent of the planned examination.  Please also provide  
reference numbers for applicable procedures that will be used to conduct these  
examinations.  
   
f)  
Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of  
Section XI of the ASME Code that have been identified since the beginning of the  
last refueling outage.  
   
g)   
A list of any temporary non-code repairs in service (e.g., pinhole leaks).  
   
h)  
Please provide copies of the most recent self assessments for the ISI, Welding,  
and Alloy 600 Programs.   
   
A.2  
Reactor Pressure Vessel Head (RPVH)  
a)   
Provide the detailed scope of the planned NDE of the reactor vessel head which  
identifies the types of NDE methods to be used on each specific part of the  
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02  
and NRC Order EA-03-009.  Also, include examination scope expansion criteria  
and planned expansion sample sizes if relevant conditions are identified. (If  
applicable)  
 
   
- 3 -  
Enclosure  
   
b)   
A list of the standards and/or requirements that will be used to evaluate  
indications identified during NDE of the reactor vessel head (e.g., the specific  
industry or procedural standards which will be used to evaluate potential leakage  
and/or flaw indications).  
   
A.3  
Boric Acid Corrosion Control Program (BACCP)  
a)   
Copy of the procedures that govern the scope, equipment and implementation of  
the inspections required to identify boric acid leakage and the procedures for  
boric acid leakage/corrosion evaluation.  
boric acid leakage/corrosion evaluation.  
  b) Please provide a list of leaks (including Code class of the components) that have been identified since the last refueling outage and associated corrective action documentation.  If during the last cycle, the Unit was shutdown, please provide documentation of containment walkdown inspections performed as part of the BACCP.  c) Please provide a copy of the most recent self-assessment performed for the BACCP.  A.4 Steam Generator Tube (SGT) Inspections
   
  a) A detailed schedule of:  
b)  
  i)  SGT inspection, data analyses, and repair activities for the upcoming outage. (If occurring)  
Please provide a list of leaks (including Code class of the components) that have  
  ii)  SG secondary side inspection activities for the upcoming outage. (If occurring)  
been identified since the last refueling outage and associated corrective action  
  b) Please provide a copy of your SG ISI Inspection Program and Plan.  Please include a copy of the Operational Assessment from last outage and a copy of the following documents as they become available:   
documentation.  If during the last cycle, the Unit was shutdown, please provide  
  i) Degradation Assessment ii) Condition Monitoring Assessment   
documentation of containment walkdown inspections performed as part of the  
  c) If you are planning on modifying your Technical Specifications such that they are consistent with TSTF-449, please provide copies of your correspondence with the NRC regarding deviations from the STS.  
BACCP.  
  d) Copy of SG history documentation given to vendors performing eddy current (ET) testing of the SGs during the upcoming outage.  
   
  e) Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy Current Technique Specification Sheets (ETSS).  Additionally, please provide a copy of EPRI Appendix H ETSS Qualification Records.   
c)  
  - 4 - Enclosure  
Please provide a copy of the most recent self-assessment performed for the  
  f) Identify and quantify any SGT leakage experienced during the previous operating cycle.  Also provide documentation identifying which SG was leaking and corrective actions completed or planned for this condition (If applicable).  
BACCP.  
  g)  Provide past history of the condition and issues pertaining to the secondary side of the steam generators (including items such as loose parts, fouling, top of tube sheet condition, crud removal amounts, etc.)  
   
  h) Please provide copies of your most recent self assessments of the SG monitoring, loose parts monitoring, and secondary side water chemistry control programs.  
A.4  
  i) Please also indicate where the primary, secondary, and resolution analyses are scheduled to take place.  
Steam Generator Tube (SGT) Inspections  
  j) Please provide a summary of the scope of the SGT examinations, including examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the percentage of tubes to be examined. *Do not provide these documents separately if already included in other information requested.   A.5 Materials Reliability (MRP-139) Program Activities
  a) A list of, with verification, that the baseline inspections of all applicable Dissimilar Metal Butt Welds (DMBWs) have been completed by December 31, 2007.  
a)  
  b) Verification that baseline inspection of hot leg and cold leg temperature DMBWs have been included in the inspection program and that the schedules for the baseline inspections are consistent with the baseline schedules in MRP-139.  
A detailed schedule of:  
  c) A list and schedule (examination dates) of all DMBW examinations planned for the upcoming refueling outage.  If none are scheduled, then data from previous  
   
i)   
SGT inspection, data analyses, and repair activities for the upcoming  
outage. (If occurring)  
   
ii)   
SG secondary side inspection activities for the upcoming outage. (If  
occurring)  
   
b)  
Please provide a copy of your SG ISI Inspection Program and Plan.  Please  
include a copy of the Operational Assessment from last outage and a copy of the  
following documents as they become available:   
   
i)  
Degradation Assessment  
ii)  
Condition Monitoring Assessment   
   
c)  
If you are planning on modifying your Technical Specifications such that they are  
consistent with TSTF-449, please provide copies of your correspondence with  
the NRC regarding deviations from the STS.  
   
d)  
Copy of SG history documentation given to vendors performing eddy current (ET)  
testing of the SGs during the upcoming outage.  
   
e)  
Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy  
Current Technique Specification Sheets (ETSS).  Additionally, please provide a  
copy of EPRI Appendix H ETSS Qualification Records.  
 
   
- 4 -  
Enclosure  
   
f)  
Identify and quantify any SGT leakage experienced during the previous operating  
cycle.  Also provide documentation identifying which SG was leaking and  
corrective actions completed or planned for this condition (If applicable).  
   
g)   
Provide past history of the condition and issues pertaining to the secondary side  
of the steam generators (including items such as loose parts, fouling, top of tube  
sheet condition, crud removal amounts, etc.)  
   
h)  
Please provide copies of your most recent self assessments of the SG  
monitoring, loose parts monitoring, and secondary side water chemistry control  
programs.  
   
i)  
Please also indicate where the primary, secondary, and resolution analyses are  
scheduled to take place.  
   
j)  
Please provide a summary of the scope of the SGT examinations, including  
examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the  
percentage of tubes to be examined. *Do not provide these documents  
separately if already included in other information requested.
A.5  
Materials Reliability (MRP-139) Program Activities  
a)  
A list of, with verification, that the baseline inspections of all applicable Dissimilar  
Metal Butt Welds (DMBWs) have been completed by December 31, 2007.  
   
b)  
Verification that baseline inspection of hot leg and cold leg temperature DMBWs  
have been included in the inspection program and that the schedules for the  
baseline inspections are consistent with the baseline schedules in MRP-139.  
   
c)  
A list and schedule (examination dates) of all DMBW examinations planned for  
the upcoming refueling outage.  If none are scheduled, then data from previous  
examinations should be available for review.  
examinations should be available for review.  
  d) A list and schedule for any welding to be performed on DMBWs in the upcoming outage.  If no welding will be performed then records of previous welding on DMBWs and postweld NDE documentation.  
   
  e) A list and schedule of any stress improvement (SI) activities planned for the upcoming refueling outage.  If none are scheduled then have qualification reports for any SIs previously performed.  
d)  
  f) Documentation and description of how the baseline and inservice inspection specifications in MRP-139 are satisfied at your facility.  
A list and schedule for any welding to be performed on DMBWs in the upcoming  
  A.6 Additional information related to all ISI activities
outage.  If no welding will be performed then records of previous welding on  
 
DMBWs and postweld NDE documentation.  
  - 5 - Enclosure a)  A list with a brief description of ISI, BACCP, and SGT inspection related issues (e.g., condition reports) entered into your corrective action program since the beginning of the last refueling outage (for Unit 2).  For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust,  
   
e)  
A list and schedule of any stress improvement (SI) activities planned for the  
upcoming refueling outage.  If none are scheduled then have qualification reports  
for any SIs previously performed.  
   
f)  
Documentation and description of how the baseline and inservice inspection  
specifications in MRP-139 are satisfied at your facility.  
   
A.6  
Additional information related to all ISI activities  
 
- 5 -  
Enclosure  
a)   
A list with a brief description of ISI, BACCP, and SGT inspection related issues  
(e.g., condition reports) entered into your corrective action program since the  
beginning of the last refueling outage (for Unit 2).  For example, a list based upon  
data base searches using key words related to piping or SG tube degradation  
such as: ISI, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust,  
corrosion, boric acid, or errors in piping/SGT examinations.  
corrosion, boric acid, or errors in piping/SGT examinations.  
  b)  Please provide names and phone numbers for the following program leads:  
   
  ISI contacts (Examination, planning)  
b)   
Containment Exams RPVH Exams Snubbers and Supports Repair and Replacement Program Manager Licensing Contact Site Welding Engineer Boric Acid Corrosion Control Program  
Please provide names and phone numbers for the following program leads:  
   
ISI contacts (Examination, planning)  
Containment Exams  
RPVH Exams  
Snubbers and Supports  
Repair and Replacement Program Manager  
Licensing Contact  
Site Welding Engineer  
Boric Acid Corrosion Control Program  
SG Inspection Activities (site lead and vendor contact)  
SG Inspection Activities (site lead and vendor contact)  
  B. Information to be provided onsite to the inspector(s) at the entrance meeting (March 31, 2008):   
   
B.1 ISI / Welding Programs and Schedule Information
B.  
  a) Updated schedules for ISI/NDE activities, including SGT inspections, planned welding activities, and schedule showing contingency repair plans, if available.  
Information to be provided onsite to the inspector(s) at the entrance meeting (March 31,  
  b) For ASME Code Class 1 and 2 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:  
2008):  
  i) Weld data sheet (traveler)  
   
ii) Weld configuration and system location iii) Applicable Code Edition and Addenda for weldment iv) Applicable Code Edition and Addenda for welding procedures v) Applicable weld procedures (WPS) used to fabricate the welds vi) Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii) Copies of mechanical test reports identified in the PQRs above viii) Copies of the nonconformance reports for the selected welds (If applicable) ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed) x) Copies of the preservice examination records for the selected welds.  
B.1  
xi) Copies of welder performance qualifications records applicable to the selected welds, including documentation that welder maintained proficiency in the applicable welding processes specified in the WPS (at least six months prior to the date of subject work)   
ISI / Welding Programs and Schedule Information  
  - 6 - Enclosure xii) Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable  
  c) For the ISI related corrective action issues selected by the inspector(s) from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.  
a)  
  d) For the NDE reports with relevant conditions on Code Class 1 & 2 systems selected by the inspector from section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.  
Updated schedules for ISI/NDE activities, including SGT inspections, planned  
  e) A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.   
welding activities, and schedule showing contingency repair plans, if available.  
  f) For the NDEs selected by the inspector from section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures).  For ultrasonic  
   
examination procedures qualified in accordance with ASME Code, Section XI, Appendix VIII, provide documentation supporting the procedure qualification (e.g., the EPRI performance demonstration qualification summary sheets).  Also, include qualification documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and NDE  
b)  
For ASME Code Class 1 and 2 welds selected by the inspector from the lists  
provided from section A of this enclosure, please provide copies of the following  
documentation for each subject weld:  
   
i)  
Weld data sheet (traveler)  
ii)  
Weld configuration and system location  
iii)  
Applicable Code Edition and Addenda for weldment  
iv)  
Applicable Code Edition and Addenda for welding procedures  
v)  
Applicable weld procedures (WPS) used to fabricate the welds  
vi)  
Copies of procedure qualification records (PQRs) supporting the WPS  
from B.1.b.v  
vii)  
Copies of mechanical test reports identified in the PQRs above  
viii)  
Copies of the nonconformance reports for the selected welds (If  
applicable)  
ix)  
Radiographs of the selected welds and access to equipment to allow  
viewing radiographs (If RT was performed)  
x)  
Copies of the preservice examination records for the selected welds.  
xi)  
Copies of welder performance qualifications records applicable to the  
selected welds, including documentation that welder maintained  
proficiency in the applicable welding processes specified in the WPS (at  
least six months prior to the date of subject work)  
 
   
- 6 -  
Enclosure  
xii)  
Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable  
   
c)  
For the ISI related corrective action issues selected by the inspector(s) from  
section A of this enclosure, provide a copy of the corrective actions and  
supporting documentation.  
   
d)  
For the NDE reports with relevant conditions on Code Class 1 & 2 systems  
selected by the inspector from section A above, provide a copy of the  
examination records, examiner qualification records, and associated corrective  
action documents.  
   
e)  
A copy of (or ready access to) most current revision of the ISI Program Manual  
and Plan for the current Interval.   
   
f)  
For the NDEs selected by the inspector from section A of this enclosure, provide  
copy of the NDE procedures used to perform the examinations (including  
calibration and flaw characterization/sizing procedures).  For ultrasonic  
examination procedures qualified in accordance with ASME Code, Section XI,  
Appendix VIII, provide documentation supporting the procedure qualification  
(e.g., the EPRI performance demonstration qualification summary sheets).  Also,  
include qualification documentation of the specific equipment to be used (e.g.,  
ultrasonic unit, cables, and transducers including serial numbers) and NDE  
personnel qualification records.  
personnel qualification records.  
B.2 Reactor Pressure Vessel Head (RPVH)
  a) Provide the NDE personnel qualification records for the examiners who will perform examinations of the RPVH. 
b) Provide drawings showing the following: (If a visual examination is planned for the upcoming refueling outage)
i) RPVH and CRDM nozzle configurations  ii) RPVH insulation configuration 
The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable. 
c) Copy of NDE reports from the last RPVH examination.
d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95% minimum coverage required by NRC Order EA-03-009 (If a visual examination is planned for the upcoming refueling outage).
e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH.  If no explicit procedures exist which 
  - 7 - Enclosure govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations. 
f)  Provide a copy of the updated calculation of effective degradation years (EDY) for the RPVH susceptibility ranking.
g)  Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the NDE equipment used for the RPVH examinations.  Also, identify any changes in equipment configurations used for the RPVH examinations which differ from that used in the vendor qualification report(s).
B.3 Boric Acid Corrosion Control Program (BACCP)
  a) Please provide boric acid walkdown inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections. 
   
   
b) Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage.  Please include a status of corrective actions to repair and/or clean these boric acid leaks.  Please identify specifically which known leaks, if any, have remained in service or will remain in service as active leaks.   
B.2
  B.4 Steam Generator Tube (SGT) Inspections
Reactor Pressure Vessel Head (RPVH)
  a) Copies of the Examination Technique Specification Sheets (ETSS) and associated justification for any revisions.  
  b) Copy of the guidance to be followed if a loose part or foreign material is identified in the SGs.  
a)
  c) Please provide a copy of the ET procedures used to perform the SGT inspections (specifically calibration and flaw characterization/sizing procedures, etc.).  Also include documentation for the specific equipment to be used.  
Provide the NDE personnel qualification records for the examiners who will
  d) Please provide copies of your responses to NRC and industry operating experience communications such as Generic Letters, Information Notices, etc.  
perform examinations of the RPVH. 
(as applicable to SGT inspections) *Do not provide these documents separately if already included in other information requested such as the degradation assessment.  
  e) List of corrective action documents generated by the vendor and/or site with respect to SG inspection activities.  
b)  
 
Provide drawings showing the following: (If a visual examination is planned for
B.5 Codes and Standards
the upcoming refueling outage)
 
  - 8 - Enclosure a) Ready access to (i.e., copies provided to the inspector(s) for use during the inspection at the onsite inspection location, or room number and location where available):  
i)
  i)  Applicable Editions of the ASME Code (Sections V, IX and XI) for the inservice inspection program and the repair/replacement program.   
RPVH and CRDM nozzle configurations 
  ii)  EPRI and industry standards referenced in the procedures used to perform the SGT eddy current examination.  
ii)
RPVH insulation configuration 
The drawings listed above should include fabrication drawings for the nozzle attachment
welds as applicable. 
c)
Copy of NDE reports from the last RPVH examination.
d)
Copy of evaluation or calculation demonstrating that the scope of the visual
examination of the upper head will meet the 95% minimum coverage required by
NRC Order EA-03-009 (If a visual examination is planned for the upcoming
refueling outage).
e)
Provide a copy of the procedures that will be used to identify the source of any
boric acid deposits identified on the RPVH.  If no explicit procedures exist which
 
- 7 -
Enclosure
govern this activity, provide a description of the process to be followed including
personnel responsibilities and expectations. 
f) 
Provide a copy of the updated calculation of effective degradation years (EDY)
for the RPVH susceptibility ranking.
g) 
Provide copy of the vendor qualification report(s) that demonstrates the detection
capability of the NDE equipment used for the RPVH examinations.  Also, identify
any changes in equipment configurations used for the RPVH examinations which
differ from that used in the vendor qualification report(s).
B.3
Boric Acid Corrosion Control Program (BACCP)
a)
Please provide boric acid walkdown inspection results, an updated list of boric
acid leaks identified so far this outage, associated corrective action
documentation, and overall status of planned boric acid inspections. 
b)
Please provide any engineering evaluations completed for boric acid leaks  
identified since the end of the last refueling outage.  Please include a status of  
corrective actions to repair and/or clean these boric acid leaks.  Please identify  
specifically which known leaks, if any, have remained in service or will remain in  
service as active leaks.   
   
B.4  
Steam Generator Tube (SGT) Inspections  
a)  
Copies of the Examination Technique Specification Sheets (ETSS) and  
associated justification for any revisions.  
   
b)  
Copy of the guidance to be followed if a loose part or foreign material is identified  
in the SGs.  
   
c)  
Please provide a copy of the ET procedures used to perform the SGT  
inspections (specifically calibration and flaw characterization/sizing procedures,  
etc.).  Also include documentation for the specific equipment to be used.  
   
d)  
Please provide copies of your responses to NRC and industry operating  
experience communications such as Generic Letters, Information Notices, etc.  
(as applicable to SGT inspections) *Do not provide these documents separately if  
already included in other information requested such as the degradation  
assessment.  
   
e)  
List of corrective action documents generated by the vendor and/or site with  
respect to SG inspection activities.  
B.5  
Codes and Standards  
 
- 8 -  
Enclosure  
a)  
Ready access to (i.e., copies provided to the inspector(s) for use during the  
inspection at the onsite inspection location, or room number and location where  
available):  
   
i)   
Applicable Editions of the ASME Code (Sections V, IX and XI) for the  
inservice inspection program and the repair/replacement program.   
   
ii)   
EPRI and industry standards referenced in the procedures used to  
perform the SGT eddy current examination.  
Inspector Contact Information:
L. E. Ellershaw
Senior Reactor Inspector
817-860-8127
lee1@nrc.gov
   
   
Inspector Contact Information:
Mailing Address:  
L. E. Ellershaw Senior Reactor Inspector 817-860-8127 lee1@nrc.gov
US NRC Region IV  
  Mailing Address: US NRC Region IV Attn: L. E. Ellershaw  
Attn: L. E. Ellershaw  
611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011
611 Ryan Plaza Drive, Suite 400  
Arlington, TX 76011
}}
}}

Latest revision as of 18:03, 14 January 2025

Notification of Inspection (NRC Inspection Report 05000482/2008003) and Request for Information
ML080450603
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 02/14/2008
From: Russ Bywater
Region 4 Engineering Branch 1
To: Muench R
Wolf Creek
References
IR-08-003
Download: ML080450603 (13)


See also: IR 05000482/2008003

Text

February 14, 2008

Rick A. Muench, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, KS 66839

SUBJECT:

WOLF CREEK GENERATING STATION - NOTIFICATION OF INSPECTION

(NRC INSPECTION REPORT 05000482/2008003) AND REQUEST FOR

INFORMATION

Dear Mr. Muench:

From March 31 to April 11, 2008, reactor inspectors from the Nuclear Regulatory

Commissions (NRC) Region IV office will perform the baseline inservice inspection at Wolf

Creek Generating Station using NRC Inspection Procedure 71111.08. Experience has shown

that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.

In order to minimize the impact to your onsite resources and to ensure a productive inspection,

we have enclosed a request for documents needed for this inspection. These documents have

been divided into two groups. The first group (Section A of the enclosure) identified information

to be provided prior to the inspection to ensure that the inspectors are adequately prepared.

The second group (Section B of the enclosure) identifies the information the inspectors will need

upon arrival at the site. It is important that all of these documents are up to date and complete

in order to minimize the number of additional documents requested during the preparation

and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Mr. W. Muilenburg of your licensing

organization. Our inspection dates are subject to change based on your updated schedule of

outage activities. If there are any questions about this inspection or the material requested,

please contact the lead inspector Lee Ellershaw at (817) 860-8127 (lee1@nrc.gov).

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

611 RYAN PLAZA DRIV E, SUITE 400

ARLINGTON, TEXAS 76011-4005

Wolf Creek Nuclear Operating Corp.

- 2 -

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document

system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Russell L. Bywater, Chief

Engineering Branch 1

Division of Reactor Safety

Docket: 50-482

License: NPF-42

Enclosure:

Inservice Inspection Document Request

cc w/enclosure:

Vice President Operations/Plant Manager

Wolf Creek Nuclear Operating Corp.

P.O. Box 411

Burlington, KS 66839

Jay Silberg, Esq.

Pillsbury Winthrop Shaw Pittman LLP

2300 N Street, NW

Washington, DC 20037

Supervisor Licensing

Wolf Creek Nuclear Operating Corp.

P.O. Box 411

Burlington, KS 66839

Chief Engineer

Utilities Division

Kansas Corporation Commission

1500 SW Arrowhead Road

Topeka, KS 66604-4027

Office of the Governor

State of Kansas

Topeka, KS 66612

Attorney General

120 S.W. 10th Avenue, 2nd Floor

Topeka, KS 66612-1597

Wolf Creek Nuclear Operating Corp.

- 3 -

County Clerk

Coffey County Courthouse

110 South 6th Street

Burlington, KS 66839-1798

Chief, Radiation and Asbestos

Control Section

Kansas Department of Health and

Environment

Bureau of Air and Radiation

1000 SW Jackson, Suite 310

Topeka, KS 66612-1366

Ronald L. McCabe, Chief

Technological Hazards Branch

National Preparedness Division

DHS/FEMA

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

Wolf Creek Nuclear Operating Corp.

- 4 -

Electronic distribution by RIV:

Regional Administrator (EEC)

DRP Director (DDC)

DRS Director (RJC1)

DRS Deputy Director (ACC)

Senior Resident Inspector (SDC)

SRI, Callaway (DED)

Branch Chief, DRP/B (VGG)

Senior Project Engineer, (RWD)

Team Leader, DRP/TSS (CJP)

RITS Coordinator (MSH3)

DRS STA (DAP)

D. Pelton, OEDO RIV Coordinator (DLP1)

ROPreports

WC Site Secretary (SLA2)

SUNSI Review Completed: __RLB____ADAMS: Yes

G No Initials: _RLB_____

Publicly Available G Non-Publicly Available G Sensitive

Non-Sensitive

RI:EB1

C:EB1

LEEllershaw:lar

RLBywater

/RA/

/RA/

2/13/08

2/14/08

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

- 1 -

Enclosure

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates:

March 31, 2008 - April 11, 2008

Inspection Procedures:

IP 71111.08 Inservice Inspection (ISI) Activities

TI 2515/166 Pressurized Water Reactor Containment Sump

Blockage

TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds

Inspectors:

L. Ellershaw, Senior Reactor Inspector (Lead Inspector - ISI)

J. Drake, Senior Reactor Inspector

K. Clayton, Reactor Inspector

A.

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or

electronic format (ims.certrec.com preferred), in care of L. E. Ellershaw, by March 11,

2008, to facilitate the selection of specific items that will be reviewed during the onsite

inspection week. The inspector will select specific items from the information requested

below and then request from your staff additional documents needed during the onsite

inspection week (Section B of this enclosure). We ask that the specific items selected

from the lists be available and ready for review on the first day of inspection. *Please

provide requested documentation electronically if possible. If requested documents are

large and only hard copy formats are available, please inform the inspector(s), and

provide subject documentation during the first day of the onsite inspection. If you have

any questions regarding this information request, please call the inspector as soon as

possible.

A.1

ISI/Welding Programs and Schedule Information

a)

A detailed schedule (including preliminary dates) of:

i)

Nondestructive examinations (NDEs) planned for Class 1 & 2 systems

and containment, performed as part of your ASME Section XI, Risk

Informed (if applicable), and augmented ISI programs during the

upcoming outage.

Provide a status summary of the NDE inspection activities vs. the

required inspection period percentages for this Interval by category per

ASME Section XI, IWX-2400 (Do not provide separately if other

documentation requested contains this information)

ii)

Reactor pressure vessel head (RPVH) examinations planned for the

upcoming outage.

iii)

Examinations planned for Alloy 82/182/600 components that are not

included in the Section XI scope. (If applicable)

- 2 -

Enclosure

iv)

Examinations planned as part of your Boric Acid Corrosion Control

Program (Mode 3 walkdowns, bolted connection walkdowns, etc.)

v)

Welding activities that are scheduled to be completed during the

upcoming outage (ASME Class 1, 2, or 3 structures, systems, or

components (SSCs))

b)

A copy of ASME Section XI Code Relief Requests and associated NRC Safety

Evaluations applicable to the examinations identified above.

c)

A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate,

Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code

Class 1 & 2 systems since the beginning of the last refueling outage. This should

include the previousSection XI pressure test(s) conducted during start up and

any evaluations associated with the results of the pressure tests. Also, include in

the list the NDE reports with relevant conditions in the RPVH penetration nozzles

which have been accepted for continued service. The list of NDE reports should

include a brief description of the SSC where the relevant condition was identified.

d)

A list with a brief description (e.g., system, material, pipe size, weld number, and

NDE performed) of the welds in Code Class 1 and 2 systems which have been

fabricated due to component repair/replacement activities since the beginning of

the last refueling outage, or are planned to be fabricated this refueling outage.

e)

If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to

be examined and the extent of the planned examination. Please also provide

reference numbers for applicable procedures that will be used to conduct these

examinations.

f)

Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of

Section XI of the ASME Code that have been identified since the beginning of the

last refueling outage.

g)

A list of any temporary non-code repairs in service (e.g., pinhole leaks).

h)

Please provide copies of the most recent self assessments for the ISI, Welding,

and Alloy 600 Programs.

A.2

Reactor Pressure Vessel Head (RPVH)

a)

Provide the detailed scope of the planned NDE of the reactor vessel head which

identifies the types of NDE methods to be used on each specific part of the

vessel head to fulfill commitments made in response to NRC Bulletin 2002-02

and NRC Order EA-03-009. Also, include examination scope expansion criteria

and planned expansion sample sizes if relevant conditions are identified. (If

applicable)

- 3 -

Enclosure

b)

A list of the standards and/or requirements that will be used to evaluate

indications identified during NDE of the reactor vessel head (e.g., the specific

industry or procedural standards which will be used to evaluate potential leakage

and/or flaw indications).

A.3

Boric Acid Corrosion Control Program (BACCP)

a)

Copy of the procedures that govern the scope, equipment and implementation of

the inspections required to identify boric acid leakage and the procedures for

boric acid leakage/corrosion evaluation.

b)

Please provide a list of leaks (including Code class of the components) that have

been identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the Unit was shutdown, please provide

documentation of containment walkdown inspections performed as part of the

BACCP.

c)

Please provide a copy of the most recent self-assessment performed for the

BACCP.

A.4

Steam Generator Tube (SGT) Inspections

a)

A detailed schedule of:

i)

SGT inspection, data analyses, and repair activities for the upcoming

outage. (If occurring)

ii)

SG secondary side inspection activities for the upcoming outage. (If

occurring)

b)

Please provide a copy of your SG ISI Inspection Program and Plan. Please

include a copy of the Operational Assessment from last outage and a copy of the

following documents as they become available:

i)

Degradation Assessment

ii)

Condition Monitoring Assessment

c)

If you are planning on modifying your Technical Specifications such that they are

consistent with TSTF-449, please provide copies of your correspondence with

the NRC regarding deviations from the STS.

d)

Copy of SG history documentation given to vendors performing eddy current (ET)

testing of the SGs during the upcoming outage.

e)

Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy

Current Technique Specification Sheets (ETSS). Additionally, please provide a

copy of EPRI Appendix H ETSS Qualification Records.

- 4 -

Enclosure

f)

Identify and quantify any SGT leakage experienced during the previous operating

cycle. Also provide documentation identifying which SG was leaking and

corrective actions completed or planned for this condition (If applicable).

g)

Provide past history of the condition and issues pertaining to the secondary side

of the steam generators (including items such as loose parts, fouling, top of tube

sheet condition, crud removal amounts, etc.)

h)

Please provide copies of your most recent self assessments of the SG

monitoring, loose parts monitoring, and secondary side water chemistry control

programs.

i)

Please also indicate where the primary, secondary, and resolution analyses are

scheduled to take place.

j)

Please provide a summary of the scope of the SGT examinations, including

examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the

percentage of tubes to be examined. *Do not provide these documents

separately if already included in other information requested.

A.5

Materials Reliability (MRP-139) Program Activities

a)

A list of, with verification, that the baseline inspections of all applicable Dissimilar

Metal Butt Welds (DMBWs) have been completed by December 31, 2007.

b)

Verification that baseline inspection of hot leg and cold leg temperature DMBWs

have been included in the inspection program and that the schedules for the

baseline inspections are consistent with the baseline schedules in MRP-139.

c)

A list and schedule (examination dates) of all DMBW examinations planned for

the upcoming refueling outage. If none are scheduled, then data from previous

examinations should be available for review.

d)

A list and schedule for any welding to be performed on DMBWs in the upcoming

outage. If no welding will be performed then records of previous welding on

DMBWs and postweld NDE documentation.

e)

A list and schedule of any stress improvement (SI) activities planned for the

upcoming refueling outage. If none are scheduled then have qualification reports

for any SIs previously performed.

f)

Documentation and description of how the baseline and inservice inspection

specifications in MRP-139 are satisfied at your facility.

A.6

Additional information related to all ISI activities

- 5 -

Enclosure

a)

A list with a brief description of ISI, BACCP, and SGT inspection related issues

(e.g., condition reports) entered into your corrective action program since the

beginning of the last refueling outage (for Unit 2). For example, a list based upon

data base searches using key words related to piping or SG tube degradation

such as: ISI, ASME Code,Section XI, NDE, cracks, wear, thinning, leakage, rust,

corrosion, boric acid, or errors in piping/SGT examinations.

b)

Please provide names and phone numbers for the following program leads:

ISI contacts (Examination, planning)

Containment Exams

RPVH Exams

Snubbers and Supports

Repair and Replacement Program Manager

Licensing Contact

Site Welding Engineer

Boric Acid Corrosion Control Program

SG Inspection Activities (site lead and vendor contact)

B.

Information to be provided onsite to the inspector(s) at the entrance meeting (March 31,

2008):

B.1

ISI / Welding Programs and Schedule Information

a)

Updated schedules for ISI/NDE activities, including SGT inspections, planned

welding activities, and schedule showing contingency repair plans, if available.

b)

For ASME Code Class 1 and 2 welds selected by the inspector from the lists

provided from section A of this enclosure, please provide copies of the following

documentation for each subject weld:

i)

Weld data sheet (traveler)

ii)

Weld configuration and system location

iii)

Applicable Code Edition and Addenda for weldment

iv)

Applicable Code Edition and Addenda for welding procedures

v)

Applicable weld procedures (WPS) used to fabricate the welds

vi)

Copies of procedure qualification records (PQRs) supporting the WPS

from B.1.b.v

vii)

Copies of mechanical test reports identified in the PQRs above

viii)

Copies of the nonconformance reports for the selected welds (If

applicable)

ix)

Radiographs of the selected welds and access to equipment to allow

viewing radiographs (If RT was performed)

x)

Copies of the preservice examination records for the selected welds.

xi)

Copies of welder performance qualifications records applicable to the

selected welds, including documentation that welder maintained

proficiency in the applicable welding processes specified in the WPS (at

least six months prior to the date of subject work)

- 6 -

Enclosure

xii)

Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable

c)

For the ISI related corrective action issues selected by the inspector(s) from

section A of this enclosure, provide a copy of the corrective actions and

supporting documentation.

d)

For the NDE reports with relevant conditions on Code Class 1 & 2 systems

selected by the inspector from section A above, provide a copy of the

examination records, examiner qualification records, and associated corrective

action documents.

e)

A copy of (or ready access to) most current revision of the ISI Program Manual

and Plan for the current Interval.

f)

For the NDEs selected by the inspector from section A of this enclosure, provide

copy of the NDE procedures used to perform the examinations (including

calibration and flaw characterization/sizing procedures). For ultrasonic

examination procedures qualified in accordance with ASME Code,Section XI,

Appendix VIII, provide documentation supporting the procedure qualification

(e.g., the EPRI performance demonstration qualification summary sheets). Also,

include qualification documentation of the specific equipment to be used (e.g.,

ultrasonic unit, cables, and transducers including serial numbers) and NDE

personnel qualification records.

B.2

Reactor Pressure Vessel Head (RPVH)

a)

Provide the NDE personnel qualification records for the examiners who will

perform examinations of the RPVH.

b)

Provide drawings showing the following: (If a visual examination is planned for

the upcoming refueling outage)

i)

RPVH and CRDM nozzle configurations

ii)

RPVH insulation configuration

The drawings listed above should include fabrication drawings for the nozzle attachment

welds as applicable.

c)

Copy of NDE reports from the last RPVH examination.

d)

Copy of evaluation or calculation demonstrating that the scope of the visual

examination of the upper head will meet the 95% minimum coverage required by

NRC Order EA-03-009 (If a visual examination is planned for the upcoming

refueling outage).

e)

Provide a copy of the procedures that will be used to identify the source of any

boric acid deposits identified on the RPVH. If no explicit procedures exist which

- 7 -

Enclosure

govern this activity, provide a description of the process to be followed including

personnel responsibilities and expectations.

f)

Provide a copy of the updated calculation of effective degradation years (EDY)

for the RPVH susceptibility ranking.

g)

Provide copy of the vendor qualification report(s) that demonstrates the detection

capability of the NDE equipment used for the RPVH examinations. Also, identify

any changes in equipment configurations used for the RPVH examinations which

differ from that used in the vendor qualification report(s).

B.3

Boric Acid Corrosion Control Program (BACCP)

a)

Please provide boric acid walkdown inspection results, an updated list of boric

acid leaks identified so far this outage, associated corrective action

documentation, and overall status of planned boric acid inspections.

b)

Please provide any engineering evaluations completed for boric acid leaks

identified since the end of the last refueling outage. Please include a status of

corrective actions to repair and/or clean these boric acid leaks. Please identify

specifically which known leaks, if any, have remained in service or will remain in

service as active leaks.

B.4

Steam Generator Tube (SGT) Inspections

a)

Copies of the Examination Technique Specification Sheets (ETSS) and

associated justification for any revisions.

b)

Copy of the guidance to be followed if a loose part or foreign material is identified

in the SGs.

c)

Please provide a copy of the ET procedures used to perform the SGT

inspections (specifically calibration and flaw characterization/sizing procedures,

etc.). Also include documentation for the specific equipment to be used.

d)

Please provide copies of your responses to NRC and industry operating

experience communications such as Generic Letters, Information Notices, etc.

(as applicable to SGT inspections) *Do not provide these documents separately if

already included in other information requested such as the degradation

assessment.

e)

List of corrective action documents generated by the vendor and/or site with

respect to SG inspection activities.

B.5

Codes and Standards

- 8 -

Enclosure

a)

Ready access to (i.e., copies provided to the inspector(s) for use during the

inspection at the onsite inspection location, or room number and location where

available):

i)

Applicable Editions of the ASME Code (Sections V, IX and XI) for the

inservice inspection program and the repair/replacement program.

ii)

EPRI and industry standards referenced in the procedures used to

perform the SGT eddy current examination.

Inspector Contact Information:

L. E. Ellershaw

Senior Reactor Inspector

817-860-8127

lee1@nrc.gov

Mailing Address:

US NRC Region IV

Attn: L. E. Ellershaw

611 Ryan Plaza Drive, Suite 400

Arlington, TX 76011