ML12229A537: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (5 intermediate revisions by the same user not shown) | |||
| Line 3: | Line 3: | ||
| issue date = 08/16/2012 | | issue date = 08/16/2012 | ||
| title = Operating Corporation - Notification of Inspection (NRC Inspection Report 05000482-12-005 and Request for Information | | title = Operating Corporation - Notification of Inspection (NRC Inspection Report 05000482-12-005 and Request for Information | ||
| author name = Haire M | | author name = Haire M | ||
| author affiliation = NRC/RGN-IV/DRS/OB | | author affiliation = NRC/RGN-IV/DRS/OB | ||
| addressee name = Sunseri M | | addressee name = Sunseri M | ||
| addressee affiliation = Wolf Creek Nuclear Operating Corp | | addressee affiliation = Wolf Creek Nuclear Operating Corp | ||
| docket = 05000482 | | docket = 05000482 | ||
| license number = NPF-042 | | license number = NPF-042 | ||
| contact person = Osterholtz | | contact person = Osterholtz C /vlm | ||
| document report number = IR-12-005 | | document report number = IR-12-005 | ||
| document type = Letter | | document type = Letter | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:August 16, 2012 | {{#Wiki_filter:August 16, 2012 | ||
Matthew W. Sunseri, President and | |||
Chief Executive Officer | |||
Wolf Creek Nuclear Operating Corporation | |||
P.O. Box 411 | |||
Burlington, KS | |||
SUBJECT: WOLF CREEK NUCLEAR OPERATING CORPORATION - NOTIFICATION OF | |||
INSPECTION (NRC INSPECTION REPORT 05000482/2012005 AND REQUEST | |||
FOR INFORMATION) | |||
Dear Mr. Sunseri: | |||
From October 1, 2012 to October 5, 2012, inspectors from the Nuclear Regulatory | |||
Commissions (NRC) Region IV office will perform the baseline biennial requalification | |||
inspection at Wolf Creek Nuclear Operating Corporation, using NRC Inspection | |||
Procedure 71111.11B, Licensed Operator Requalification Program. Experience has shown | |||
that this inspection is a resource intensive inspection both for the NRC inspectors and your staff. | |||
In order to minimize the impact to your onsite resources and to ensure a productive inspection, | |||
we have enclosed a request for documents needed for this inspection. These documents have | |||
been divided into three groups. The first group (Section A of the enclosure) identifies | |||
information to be provided prior to the inspection to ensure that the inspectors are adequately | |||
prepared. The second group (Section B of the enclosure) identifies the information the | |||
inspectors will need upon arrival at the site. The third group (Section C of this enclosure) | |||
identifies the items which are necessary to close out the inspection and are usually sent a few | |||
weeks after the team has left the site. It is important that all of these documents are up to date | |||
and complete in order to minimize the number of additional documents requested during the | |||
preparation and/or the onsite portions of the inspection. | |||
We have discussed the schedule for these inspection activities with your staff and understand | |||
that our regulatory contact for this inspection will be Mr. J. Knapp of your operations training | |||
organization. Our inspection dates are subject to change based on your updated schedule of | |||
examination activities. | |||
UNITED STATES | |||
NUCLEAR REGULATORY COMMISSION | |||
RE GIO N I V | |||
1600 EAST LAMAR BLVD | |||
ARLINGTON, TEXAS 76011-4511 | |||
Mr. Sunseri | |||
- 2 - | |||
If there are any questions about this inspection or the material requested, please contact the | |||
lead inspector Mr. C. Osterholtz at (817)-200-1269 (Clyde.Osterholtz@nrc.gov) or | |||
Ms. T. Buchanan at (817)-200-1503 (Theresa.Buchanan@nrc.gov). | |||
This letter does not contain new or amended information collection requirements subject to the | |||
If there are any questions about this inspection or the material requested, please contact the lead inspector Mr. C. Osterholtz at (817)-200-1269 (Clyde.Osterholtz@nrc.gov) or Ms. T. Buchanan at (817)-200-1503 (Theresa.Buchanan@nrc.gov | Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | ||
). This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | requirements were approved by the Office of Management and Budget, control number 3150- | ||
requirements were approved by the Office of Management and Budget, control number 3150-0018. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. | 0018. The NRC may not conduct or sponsor, and a person is not required to respond to, a | ||
request for information or an information collection requirement unless the requesting document | |||
displays a currently valid Office of Management and Budget control number. | |||
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRCs document | |||
system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ C. Osterholtz for | |||
Mark S. Haire, Chief | |||
Operations Branch | |||
Division of Reactor Safety | |||
Docket: 50-482 | |||
Docket: 50-482 | License: NPF-42 | ||
License: NPF-42 50-313 License: DPDR-51 | 50-313 | ||
Enclosure: | License: DPDR-51 | ||
Enclosure: | |||
Inservice Inspection Document Request | Inservice Inspection Document Request | ||
Electronic Distribution for Wolf Creek Nuclear Operating Corporation | |||
Electronic Distribution for Wolf Creek Nuclear Operating Corporation | |||
ML12229A537 ADAMS: | ML12229A537 | ||
# Publicly Available | ADAMS:
No # Yes | ||
# SUNSI Review Complete | |||
Reviewer Initials: CCO | |||
# Publicly Available | |||
# Non-Sensitive | # Non-Sensitive | ||
Non-publicly Available | |||
Sensitive | |||
RIV/DRS/OPS | |||
DRS/OPS/Chief | |||
C. Osterholtz | |||
M. Haire | |||
/RA/ | |||
/RA/COsterholtz for | |||
8/16/2012 | |||
8/16/2012 | |||
Attachment 2 BRQ Info Request Template (remove this text before use) | Attachment 2 BRQ Info Request Template (remove this text before use) | ||
BIENNIAL REQUALIFICATION INSPECTION DOCUMENT REQUEST | |||
From: C. Osterholtz Senior Operations Engineer, NRC RIV 817-200-1269 | |||
To: J. Knapp Licensed Supervising Instructor/simulator, Wolf Creek Nuclear Operating Corporation | - 1 - | ||
Enclosure | |||
BIENNIAL REQUALIFICATION INSPECTION DOCUMENT REQUEST | |||
From: C. Osterholtz | |||
Senior Operations Engineer, NRC RIV | |||
817-200-1269 | |||
To: | |||
J. Knapp | |||
Licensed Supervising Instructor/simulator, Wolf Creek Nuclear Operating Corporation | |||
620-364-8831 | 620-364-8831 | ||
A. The following information is requested in order to support inspection preparation activities. These items are listed by section as they appear in the inspection module | Subj: Information Request to Support October 1-5, 2012, Licensed Operator Requalification | ||
(ie 2.02, 2.04, etc). Requested materials should be sent either electronically or hardcopy in order to arrive at the Region IV office no later than September 21, 2012. | Program Inspection (IP 71111.11B) | ||
* Electronically To: e-mail address (Clyde.Osterholtz@nrc.gov) Cc: email address (Theresa.Buchanan@nrc.gov) | |||
* Hardcopy to: US Nuclear Regulatory Commission, Region IV 1600 E. Lamar Blvd Arlington, TX 76011 | A. The following information is requested in order to support inspection preparation | ||
activities. These items are listed by section as they appear in the inspection module | |||
(ie 2.02, 2.04, etc). Requested materials should be sent either electronically or | |||
hardcopy in order to arrive at the Region IV office no later than September 21, 2012. | |||
* | |||
Electronically To: e-mail address (Clyde.Osterholtz@nrc.gov) Cc: email address | |||
(Theresa.Buchanan@nrc.gov) | |||
* | |||
Hardcopy to: US Nuclear Regulatory Commission, Region IV | |||
1600 E. Lamar Blvd | |||
Arlington, TX 76011 | |||
ATTN: C. Osterholtz | ATTN: C. Osterholtz | ||
General Requests: | |||
General Requests: | |||
* Training and Operations Department organization charts (with qualified LOR evaluators identified) | * | ||
* Procedures that identify process for revising and maintaining LO continuing training program up to date | List of licensed operators (SRO & RO) by crew (operating & staff) | ||
* List of outstanding LOR program changes | * | ||
* List of plant events and industry operating experience incorporated into LOR program since last BRQ | Training and Operations Department organization charts (with qualified LOR | ||
* Audits and/or self-assessment reports addressing the licensed operator requalification training program | evaluators identified) | ||
* Last two years of simulator review committee (or equivalent) meeting minutes | * | ||
* Last two years of CRC (or equivalent) meeting minutes | Procedures that identify process for revising and maintaining LO continuing training | ||
02.03: Biennial Requalification Written Examination Quality | program up to date | ||
* | |||
* The current requalification cycle written examination results for both SRO & RO that have already been administered up to the week prior to the inspection team arrival onsite. | List of outstanding LOR program changes | ||
* | |||
List of plant events and industry operating experience incorporated into LOR | |||
program since last BRQ | |||
* | |||
Audits and/or self-assessment reports addressing the licensed operator | |||
requalification training program | |||
* | |||
Last two years of simulator review committee (or equivalent) meeting minutes | |||
* | |||
Last two years of CRC (or equivalent) meeting minutes | |||
02.03: Biennial Requalification Written Examination Quality | |||
* | |||
The current and approved biennial written examination schedule | |||
* | |||
The current requalification cycle written examination results for both SRO & RO that | |||
have already been administered up to the week prior to the inspection team arrival | |||
onsite. | |||
Attachment 2 BRQ Info Request Template (remove this text before use) | Attachment 2 BRQ Info Request Template (remove this text before use) | ||
* All written examinations that have been approved for administration up to and including the week before the inspection team is onsite. This will need to have | |||
adequate password protection if e-mailed or double envelope protection if mailed via regular mail per NUREG-1021. | |||
* The current requalification cycle examination methodology (sample plan) | - 2 - | ||
02.04: Annual Requalification Operating Test Quality | Enclosure | ||
* | |||
* The operating tests (JPMs & scenarios) (password protected and provide separately via telephone at later date) to be given the week of October 1, 2012 (week team is onsite) * Current requalification cycle operating tests (SRO & RO) and results up to the week prior to the inspection team arrival onsite. | All written examinations that have been approved for administration up to and | ||
* All of the previous | including the week before the inspection team is onsite. This will need to have | ||
* Current requalification cycle operating test methodology (sample plan) | adequate password protection if e-mailed or double envelope protection if mailed via | ||
* All portions of the UFSAR that identify operator response times for time critical operator actions | regular mail per NUREG-1021. | ||
02.05: Licensee Admin of Requal Exams | * | ||
The current requalification cycle examination methodology (sample plan) | |||
* All procedures used to assess operator performance | |||
* All procedures that describe conduct of simulator training | 02.04: Annual Requalification Operating Test Quality | ||
* All Procedures used to test, operate, and maintain the simulator | * | ||
02.06: Requalification Examination Security | The schedule for the operating tests (JPMs & scenarios) to be given the week of | ||
October 1, 2012 (week team is onsite) | |||
* Submit any tracking tools that you use as a means to prevent excessive overlap on the operating tests and also meet the intent of sampling all required malfunctions (including major events, instrument/component malfunctions, TS calls, etc) on a | * | ||
The operating tests (JPMs & scenarios) (password protected and provide separately | |||
via telephone at later date) to be given the week of October 1, 2012 (week team is | |||
onsite) | |||
* | |||
Current requalification cycle operating tests (SRO & RO) and results up to the week | |||
prior to the inspection team arrival onsite. | |||
* | |||
All of the previous years NRC required annual operating tests. | |||
* | |||
Current requalification cycle operating test methodology (sample plan) | |||
* | |||
All portions of the UFSAR that identify operator response times for time critical | |||
operator actions | |||
02.05: Licensee Admin of Requal Exams | |||
* | |||
All procedures used to administer the annual operating test | |||
* | |||
All procedures used to assess operator performance | |||
* | |||
All procedures that describe conduct of simulator training | |||
* | |||
All Procedures used to test, operate, and maintain the simulator | |||
02.06: Requalification Examination Security | |||
* | |||
Submit any tracking tools that you use as a means to prevent excessive overlap on | |||
the written examinations and also meet the intent of sampling all required topics on a | |||
periodic basis. | |||
* | |||
Submit any tracking tools that you use as a means to prevent excessive overlap on | |||
the operating tests and also meet the intent of sampling all required malfunctions | |||
(including major events, instrument/component malfunctions, TS calls, etc) on a | |||
periodic basis. | periodic basis. | ||
* All Procedures that describe examination security, including procedures used to develop the examinations that include guidelines on overlap between examinations in current exam cycle tests and prior year examinations. | * | ||
* List of all Condition Reports since the last biennial requal inspection related to examination security and overlap. | All Procedures that describe examination security, including procedures used to | ||
02.07: Licensee Remedial Training Program | develop the examinations that include guidelines on overlap between examinations | ||
in current exam cycle tests and prior year examinations. | |||
cycle). * Remediation plans (lesson plans, reference materials, and attendance documentation) | * | ||
List of all Condition Reports since the last biennial requal inspection related to | |||
examination security and overlap. | |||
02.07: Licensee Remedial Training Program | |||
* | |||
List of remedial training conducted or planned since last requal exams (includes | |||
training provided to operators to enable passing requal exams and training provided | |||
to correct generic or individual weaknesses observed during previous requal exam | |||
cycle). | |||
* | |||
Remediation plans (lesson plans, reference materials, and attendance | |||
documentation) | |||
Attachment 2 BRQ Info Request Template (remove this text before use) | Attachment 2 BRQ Info Request Template (remove this text before use) | ||
* All Procedures and associated documentation that supports reactivation of any SRO/RO license (operating or staff crew) since the last biennial inspection | - 3 - | ||
02.09: Simulator Performance | Enclosure | ||
02.08: Conformance with Operator License Conditions | |||
* | |||
All Procedures and Program documentation for maintaining active operator licenses, | |||
tracking training attendance, and ensuring medical fitness of licensed operators | |||
* | |||
All Procedures and associated documentation that supports reactivation of any | |||
SRO/RO license (operating or staff crew) since the last biennial inspection | |||
02.09: Simulator Performance | |||
* | |||
For the following cases, send the most recent transient test packages, which may be | |||
electronic or in paper single test packages and shall be complete with test | |||
procedures for each test, the acceptance criteria, and results. For each transient | |||
test, the reference chart should be included or an equivalent subject matter expert | |||
review versus the simulator results with a write-up for any differences beyond the | |||
ANSI 3.5 standard requirements: | |||
o Transient test 9, Maximum size unisolable steam line rupture | o Transient test 9, Maximum size unisolable steam line rupture | ||
o Transient test 10, Stuck open PORV | o Transient test 10, Stuck open PORV | ||
o Transient test 11, Maximum design load rejection | o Transient test 11, Maximum design load rejection | ||
o Steady state tests for low power levels | o Steady state tests for low power levels | ||
* All Simulator Management and Configuration Procedures if not already provided for section 02.05 above. | * | ||
* Simulator Discrepancy Report summary list for all open | All Simulator Management and Configuration Procedures if not already provided for | ||
* Malfunction Test Package | section 02.05 above. | ||
* Primary parameters tested in order to verify core physics parameters (such as MTC, IRW). The applicable reference graphs from the Plant physics data book (electronic or other means as available) should also be included as well as the test procedures used and the acceptance criteria with results. | * | ||
02.10: Problem Identification and Resolution | Simulator Discrepancy Report summary list for all open DRs. For closed DRs, | ||
summary list for those items closed between September 2010 and September 2012. | |||
* Any revised requalification training that was based on licensed operator performance | * | ||
issues | Malfunction Test Package | ||
B. The following information is requested in order to support the onsite inspection activities. Requested materials should be available to the inspection team, either | * | ||
Primary parameters tested in order to verify core physics parameters (such as MTC, | |||
IRW). The applicable reference graphs from the Plant physics data book (electronic | |||
or other means as available) should also be included as well as the test procedures | |||
used and the acceptance criteria with results. | |||
02.10: Problem Identification and Resolution | |||
* | |||
A summary report of all condition reports related to operator actions/errors in the | |||
control room | |||
* | |||
Any revised requalification training that was based on licensed operator performance | |||
issues | |||
B. The following information is requested in order to support the onsite inspection | |||
activities. Requested materials should be available to the inspection team, either | |||
electronically or hardcopy, upon site arrival on October 1, 2012. | electronically or hardcopy, upon site arrival on October 1, 2012. | ||
02.02: Exam Results / 02.03 and 02.04: Written Exam and Op Test Quality | |||
02.02: Exam Results / 02.03 and 02.04: Written Exam and Op Test Quality | |||
* All results up to the day the team leaves the site. | * | ||
All Operating tests (JPMs & scenarios) to be given in all subsequent weeks after | |||
onsite week | |||
* | |||
All results up to the day the team leaves the site. | |||
Attachment 2 BRQ Info Request Template (remove this text before use) | Attachment 2 BRQ Info Request Template (remove this text before use) | ||
* Access to licensed operators | |||
* Access to licensed operators | - 4 - | ||
02.09: Simulator Performance | Enclosure | ||
02.08: Conformance with Operator License Conditions | |||
* Acceptance test documentation, including hardware and software model revisions at the time of acceptance (as available). | * | ||
* Documentation that validates current models, including the thermal-hydraulics and neutronics models, to the actual plant. | Access to licensed operators records (operating and staff crews) | ||
* All current model deficiencies, including FSAR vs Design differences in the simulator (any documentation on this) | * | ||
* Summary list of modifications from September 2010 to September 2012. | Access to licensed operators training attendance records | ||
* Plant Modifications (both hardware and software) completed on the Simulator by due date from September 2010 to September 2012. | * | ||
* Simulator Differences Lesson plan used in training (current to October 1, 2012). | Access to licensed operators medical records | ||
* The complete book of all Simulator annual performance test packages (usually in a single book, but may be electronic or in single test packages), complete with all transient tests, steady state tests, and malfunction tests. This should also include the test procedures for each test, the acceptance criteria, and results. For each transient test, the reference chart should be included or an equivalent subject matter expert review versus the simulator results with a write-up for any differences beyond the ANSI standard requirements. | |||
* All test packages used to verify core physics parameters (such as MTC, IRW). The applicable reference graphs from the Plant physics data book (electronic or other means as available) should also be included as well as the test procedures used and the acceptance criteria with results. | 02.09: Simulator Performance | ||
* All Simulator test, configuration management, and related documents available in the room for inspectors to review. This includes training needs analysis packages, simulator review committee meeting minutes, etc. | * | ||
* Current copy of ANSI 3.5 standard you are committed to for Simulator testing. | Simulator discrepancies (DRs) from September 2010 to September 2012. This | ||
02.10: Problem Identification and Resolution | should include all open DRs and DRs that have been closed, including the | ||
documentation/justification for closure. | |||
C. Wolf Creek Nuclear Operating Corporation is required to send the final results summary and any remaining exams and operating tests that have not been reviewed to the regional office lead inspector for this inspection for final review and comparison against the Significance Determination Tools in order to communicate the exit results for the inspection. | * | ||
Acceptance test documentation, including hardware and software model revisions at | |||
the time of acceptance (as available). | |||
* | |||
Documentation that validates current models, including the thermal-hydraulics and | |||
neutronics models, to the actual plant. | |||
* | |||
All current model deficiencies, including FSAR vs Design differences in the simulator | |||
(any documentation on this) | |||
* | |||
Summary list of modifications from September 2010 to September 2012. | |||
* | |||
Plant Modifications (both hardware and software) completed on the Simulator by due | |||
date from September 2010 to September 2012. | |||
* | |||
Simulator Differences Lesson plan used in training (current to October 1, 2012). | |||
* | |||
The complete book of all Simulator annual performance test packages (usually in a | |||
single book, but may be electronic or in single test packages), complete with all | |||
transient tests, steady state tests, and malfunction tests. This should also include | |||
the test procedures for each test, the acceptance criteria, and results. For each | |||
transient test, the reference chart should be included or an equivalent subject matter | |||
expert review versus the simulator results with a write-up for any differences beyond | |||
the ANSI standard requirements. | |||
* | |||
All test packages used to verify core physics parameters (such as MTC, IRW). The | |||
applicable reference graphs from the Plant physics data book (electronic or other | |||
means as available) should also be included as well as the test procedures used and | |||
the acceptance criteria with results. | |||
* | |||
All Simulator test, configuration management, and related documents available in the | |||
room for inspectors to review. This includes training needs analysis packages, | |||
simulator review committee meeting minutes, etc. | |||
* | |||
Current copy of ANSI 3.5 standard you are committed to for Simulator testing. | |||
02.10: Problem Identification and Resolution | |||
* | |||
All condition reports related to operator actions/errors in the control room | |||
C. Wolf Creek Nuclear Operating Corporation is required to send the final results | |||
summary and any remaining exams and operating tests that have not been reviewed | |||
to the regional office lead inspector for this inspection for final review and | |||
comparison against the Significance Determination Tools in order to communicate | |||
the exit results for the inspection. | |||
}} | }} | ||
Latest revision as of 22:55, 11 January 2025
| ML12229A537 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek |
| Issue date: | 08/16/2012 |
| From: | Mark Haire Operations Branch IV |
| To: | Matthew Sunseri Wolf Creek |
| Osterholtz C /vlm | |
| References | |
| IR-12-005 | |
| Download: ML12229A537 (7) | |
See also: IR 05000482/2012005
Text
August 16, 2012
Matthew W. Sunseri, President and
Chief Executive Officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS
SUBJECT: WOLF CREEK NUCLEAR OPERATING CORPORATION - NOTIFICATION OF
INSPECTION (NRC INSPECTION REPORT 05000482/2012005 AND REQUEST
FOR INFORMATION)
Dear Mr. Sunseri:
From October 1, 2012 to October 5, 2012, inspectors from the Nuclear Regulatory
Commissions (NRC) Region IV office will perform the baseline biennial requalification
inspection at Wolf Creek Nuclear Operating Corporation, using NRC Inspection
Procedure 71111.11B, Licensed Operator Requalification Program. Experience has shown
that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.
In order to minimize the impact to your onsite resources and to ensure a productive inspection,
we have enclosed a request for documents needed for this inspection. These documents have
been divided into three groups. The first group (Section A of the enclosure) identifies
information to be provided prior to the inspection to ensure that the inspectors are adequately
prepared. The second group (Section B of the enclosure) identifies the information the
inspectors will need upon arrival at the site. The third group (Section C of this enclosure)
identifies the items which are necessary to close out the inspection and are usually sent a few
weeks after the team has left the site. It is important that all of these documents are up to date
and complete in order to minimize the number of additional documents requested during the
preparation and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Mr. J. Knapp of your operations training
organization. Our inspection dates are subject to change based on your updated schedule of
examination activities.
UNITED STATES
NUCLEAR REGULATORY COMMISSION
RE GIO N I V
1600 EAST LAMAR BLVD
ARLINGTON, TEXAS 76011-4511
Mr. Sunseri
- 2 -
If there are any questions about this inspection or the material requested, please contact the
lead inspector Mr. C. Osterholtz at (817)-200-1269 (Clyde.Osterholtz@nrc.gov) or
Ms. T. Buchanan at (817)-200-1503 (Theresa.Buchanan@nrc.gov).
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0018. The NRC may not conduct or sponsor, and a person is not required to respond to, a
request for information or an information collection requirement unless the requesting document
displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ C. Osterholtz for
Mark S. Haire, Chief
Operations Branch
Division of Reactor Safety
Docket: 50-482
License: NPF-42
50-313
License: DPDR-51
Enclosure:
Inservice Inspection Document Request
Electronic Distribution for Wolf Creek Nuclear Operating Corporation
ADAMS: No # Yes
- SUNSI Review Complete
Reviewer Initials: CCO
- Publicly Available
- Non-Sensitive
Non-publicly Available
Sensitive
RIV/DRS/OPS
DRS/OPS/Chief
C. Osterholtz
M. Haire
/RA/
/RA/COsterholtz for
8/16/2012
8/16/2012
Attachment 2 BRQ Info Request Template (remove this text before use)
- 1 -
Enclosure
BIENNIAL REQUALIFICATION INSPECTION DOCUMENT REQUEST
From: C. Osterholtz
Senior Operations Engineer, NRC RIV
817-200-1269
To:
J. Knapp
Licensed Supervising Instructor/simulator, Wolf Creek Nuclear Operating Corporation
620-364-8831
Subj: Information Request to Support October 1-5, 2012, Licensed Operator Requalification
Program Inspection (IP 71111.11B)
A. The following information is requested in order to support inspection preparation
activities. These items are listed by section as they appear in the inspection module
(ie 2.02, 2.04, etc). Requested materials should be sent either electronically or
hardcopy in order to arrive at the Region IV office no later than September 21, 2012.
Electronically To: e-mail address (Clyde.Osterholtz@nrc.gov) Cc: email address
(Theresa.Buchanan@nrc.gov)
Hardcopy to: US Nuclear Regulatory Commission, Region IV
1600 E. Lamar Blvd
Arlington, TX 76011
ATTN: C. Osterholtz
General Requests:
List of licensed operators (SRO & RO) by crew (operating & staff)
Training and Operations Department organization charts (with qualified LOR
evaluators identified)
Procedures that identify process for revising and maintaining LO continuing training
program up to date
List of outstanding LOR program changes
List of plant events and industry operating experience incorporated into LOR
program since last BRQ
Audits and/or self-assessment reports addressing the licensed operator
requalification training program
Last two years of simulator review committee (or equivalent) meeting minutes
Last two years of CRC (or equivalent) meeting minutes
02.03: Biennial Requalification Written Examination Quality
The current and approved biennial written examination schedule
The current requalification cycle written examination results for both SRO & RO that
have already been administered up to the week prior to the inspection team arrival
onsite.
Attachment 2 BRQ Info Request Template (remove this text before use)
- 2 -
Enclosure
All written examinations that have been approved for administration up to and
including the week before the inspection team is onsite. This will need to have
adequate password protection if e-mailed or double envelope protection if mailed via
regular mail per NUREG-1021.
The current requalification cycle examination methodology (sample plan)
02.04: Annual Requalification Operating Test Quality
The schedule for the operating tests (JPMs & scenarios) to be given the week of
October 1, 2012 (week team is onsite)
The operating tests (JPMs & scenarios) (password protected and provide separately
via telephone at later date) to be given the week of October 1, 2012 (week team is
onsite)
Current requalification cycle operating tests (SRO & RO) and results up to the week
prior to the inspection team arrival onsite.
All of the previous years NRC required annual operating tests.
Current requalification cycle operating test methodology (sample plan)
All portions of the UFSAR that identify operator response times for time critical
operator actions
02.05: Licensee Admin of Requal Exams
All procedures used to administer the annual operating test
All procedures used to assess operator performance
All procedures that describe conduct of simulator training
All Procedures used to test, operate, and maintain the simulator
02.06: Requalification Examination Security
Submit any tracking tools that you use as a means to prevent excessive overlap on
the written examinations and also meet the intent of sampling all required topics on a
periodic basis.
Submit any tracking tools that you use as a means to prevent excessive overlap on
the operating tests and also meet the intent of sampling all required malfunctions
(including major events, instrument/component malfunctions, TS calls, etc) on a
periodic basis.
All Procedures that describe examination security, including procedures used to
develop the examinations that include guidelines on overlap between examinations
in current exam cycle tests and prior year examinations.
List of all Condition Reports since the last biennial requal inspection related to
examination security and overlap.
02.07: Licensee Remedial Training Program
List of remedial training conducted or planned since last requal exams (includes
training provided to operators to enable passing requal exams and training provided
to correct generic or individual weaknesses observed during previous requal exam
cycle).
Remediation plans (lesson plans, reference materials, and attendance
documentation)
Attachment 2 BRQ Info Request Template (remove this text before use)
- 3 -
Enclosure
02.08: Conformance with Operator License Conditions
All Procedures and Program documentation for maintaining active operator licenses,
tracking training attendance, and ensuring medical fitness of licensed operators
All Procedures and associated documentation that supports reactivation of any
SRO/RO license (operating or staff crew) since the last biennial inspection
02.09: Simulator Performance
For the following cases, send the most recent transient test packages, which may be
electronic or in paper single test packages and shall be complete with test
procedures for each test, the acceptance criteria, and results. For each transient
test, the reference chart should be included or an equivalent subject matter expert
review versus the simulator results with a write-up for any differences beyond the
ANSI 3.5 standard requirements:
o Transient test 9, Maximum size unisolable steam line rupture
o Transient test 10, Stuck open PORV
o Transient test 11, Maximum design load rejection
o Steady state tests for low power levels
All Simulator Management and Configuration Procedures if not already provided for
section 02.05 above.
Simulator Discrepancy Report summary list for all open DRs. For closed DRs,
summary list for those items closed between September 2010 and September 2012.
Malfunction Test Package
Primary parameters tested in order to verify core physics parameters (such as MTC,
IRW). The applicable reference graphs from the Plant physics data book (electronic
or other means as available) should also be included as well as the test procedures
used and the acceptance criteria with results.
02.10: Problem Identification and Resolution
A summary report of all condition reports related to operator actions/errors in the
control room
Any revised requalification training that was based on licensed operator performance
issues
B. The following information is requested in order to support the onsite inspection
activities. Requested materials should be available to the inspection team, either
electronically or hardcopy, upon site arrival on October 1, 2012.
02.02: Exam Results / 02.03 and 02.04: Written Exam and Op Test Quality
All Operating tests (JPMs & scenarios) to be given in all subsequent weeks after
onsite week
All results up to the day the team leaves the site.
Attachment 2 BRQ Info Request Template (remove this text before use)
- 4 -
Enclosure
02.08: Conformance with Operator License Conditions
Access to licensed operators records (operating and staff crews)
Access to licensed operators training attendance records
Access to licensed operators medical records
02.09: Simulator Performance
Simulator discrepancies (DRs) from September 2010 to September 2012. This
should include all open DRs and DRs that have been closed, including the
documentation/justification for closure.
Acceptance test documentation, including hardware and software model revisions at
the time of acceptance (as available).
Documentation that validates current models, including the thermal-hydraulics and
neutronics models, to the actual plant.
All current model deficiencies, including FSAR vs Design differences in the simulator
(any documentation on this)
Summary list of modifications from September 2010 to September 2012.
Plant Modifications (both hardware and software) completed on the Simulator by due
date from September 2010 to September 2012.
Simulator Differences Lesson plan used in training (current to October 1, 2012).
The complete book of all Simulator annual performance test packages (usually in a
single book, but may be electronic or in single test packages), complete with all
transient tests, steady state tests, and malfunction tests. This should also include
the test procedures for each test, the acceptance criteria, and results. For each
transient test, the reference chart should be included or an equivalent subject matter
expert review versus the simulator results with a write-up for any differences beyond
the ANSI standard requirements.
All test packages used to verify core physics parameters (such as MTC, IRW). The
applicable reference graphs from the Plant physics data book (electronic or other
means as available) should also be included as well as the test procedures used and
the acceptance criteria with results.
All Simulator test, configuration management, and related documents available in the
room for inspectors to review. This includes training needs analysis packages,
simulator review committee meeting minutes, etc.
Current copy of ANSI 3.5 standard you are committed to for Simulator testing.
02.10: Problem Identification and Resolution
All condition reports related to operator actions/errors in the control room
C. Wolf Creek Nuclear Operating Corporation is required to send the final results
summary and any remaining exams and operating tests that have not been reviewed
to the regional office lead inspector for this inspection for final review and
comparison against the Significance Determination Tools in order to communicate
the exit results for the inspection.