ML081970323: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (2 intermediate revisions by the same user not shown) | |||
| Line 3: | Line 3: | ||
| issue date = 07/11/2008 | | issue date = 07/11/2008 | ||
| title = Facility Change Report for the Period from March 1, 2006 to February 29, 2008 | | title = Facility Change Report for the Period from March 1, 2006 to February 29, 2008 | ||
| author name = Reilly J | | author name = Reilly J | ||
| author affiliation = Southern California Edison Co | | author affiliation = Southern California Edison Co | ||
| addressee name = | | addressee name = | ||
| Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:SOUTHERN CALIFORNIA EDISON°An EDISON INTERNATIONAL Company James T. Reilly Vice President July 11, 2008 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 | {{#Wiki_filter:SOUTHERN CALIFORNIA EDISON° An EDISON INTERNATIONAL Company James T. Reilly Vice President July 11, 2008 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 | ||
==Subject:== | ==Subject:== | ||
Docket No. 50-206 Facility Change Report San Onofre Nuclear Generating Station Unit 1 | Docket No. 50-206 Facility Change Report San Onofre Nuclear Generating Station Unit 1 | ||
==Dear Sir or Madam:== | ==Dear Sir or Madam:== | ||
This letter provides the Facility Change Report required by 10 CFR 50.59(d)(2) for San Onofre Unit 1 for the period from March 1, 2006 to February 29, 2008. There were no 50.59 evaluations identified for Unit 1 in this reporting period.There are no regulatory commitments made in this letter.If you would like any additional information, please contact Ms. L. T. Conklin at (949) 368-9443.cc: E. E. Collins, Regional Administrator, NRC Region IV J. C. Shepherd, NRC Project Manager, San Onofre Unit 1 J. E. Whitten, NRC Region IV, San Onofre Unit 1 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemente, CA 92674-0128 949-368-3780 Fax 949-368-3770-IGL7}} | This letter provides the Facility Change Report required by 10 CFR 50.59(d)(2) for San Onofre Unit 1 for the period from March 1, 2006 to February 29, 2008. There were no 50.59 evaluations identified for Unit 1 in this reporting period. | ||
There are no regulatory commitments made in this letter. | |||
If you would like any additional information, please contact Ms. L. T. Conklin at (949) 368-9443. | |||
cc: | |||
E. E. Collins, Regional Administrator, NRC Region IV J. C. Shepherd, NRC Project Manager, San Onofre Unit 1 J. E. Whitten, NRC Region IV, San Onofre Unit 1 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemente, CA 92674-0128 949-368-3780 Fax 949-368-3770 | |||
-IGL7}} | |||
Latest revision as of 16:05, 14 January 2025
| ML081970323 | |
| Person / Time | |
|---|---|
| Site: | San Onofre |
| Issue date: | 07/11/2008 |
| From: | Reilly J Southern California Edison Co |
| To: | Document Control Desk, NRC/FSME |
| References | |
| Download: ML081970323 (1) | |
Text
SOUTHERN CALIFORNIA EDISON° An EDISON INTERNATIONAL Company James T. Reilly Vice President July 11, 2008 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555
Subject:
Docket No. 50-206 Facility Change Report San Onofre Nuclear Generating Station Unit 1
Dear Sir or Madam:
This letter provides the Facility Change Report required by 10 CFR 50.59(d)(2) for San Onofre Unit 1 for the period from March 1, 2006 to February 29, 2008. There were no 50.59 evaluations identified for Unit 1 in this reporting period.
There are no regulatory commitments made in this letter.
If you would like any additional information, please contact Ms. L. T. Conklin at (949) 368-9443.
cc:
E. E. Collins, Regional Administrator, NRC Region IV J. C. Shepherd, NRC Project Manager, San Onofre Unit 1 J. E. Whitten, NRC Region IV, San Onofre Unit 1 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P.O. Box 128 San Clemente, CA 92674-0128 949-368-3780 Fax 949-368-3770
-IGL7