{{#Wiki_filter:March 20, 2015 EN 15-009 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Exelon Generation Company, LLC    EA-15-001  Dresden Nuclear Power Station, Unit 3 Docket No.:  50-249  
{{#Wiki_filter:March 20, 2015 EN 15-009 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Exelon Generation Company, LLC    EA-15-001  Dresden Nuclear Power Station, Unit 3 Docket No.:  50-249  


==Subject:==
==Subject:==
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation (NOV) associated with a White Significance Determination Process finding will be issued on or about March 26, 2015, to Exelon Generation Company, LLC (licensee) as a result of an inspection at Dresden Nuclear Power Station, Unit 3 (Dresden 3). The White finding, an issue of low to moderate safety significance, will result in additional NRC inspection and potentially other NRC action.
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation (NOV) associated with a White Significance Determination Process finding will be issued on or about March 26, 2015, to Exelon Generation Company, LLC (licensee) as a result of an inspection at Dresden Nuclear Power Station, Unit 3 (Dresden 3). The White finding, an issue of low to moderate safety significance, will result in additional NRC inspection and potentially other NRC action.  
The White finding involved the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components involving the Dresden 3 Automatic Depressurization System (ADS). Specifically, from November 29, 2010, to November 6, 2014, the licensee failed to establish measures to ensure that the application of the ADS electromatic relief valve (ERV) actuators remained suitable for operation. This resulted in multiple failures of the ERV 3E during testing prior to operating cycle D3C23, and an indeterminate period of inoperability and unavailability greater than allowed by Technical Specifications during operating cycle D3C23. The ERV 3E inoperability during the operating cycle was identified after the failure of the valve during its first operational test following unit shutdown for refueling. A NOV is included based on the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components in accordance with 10 CFR 50, Appendix B, Criterion III, "Design Control".
On March 2, 2015, the licensee declined the opportunity to discuss this issue in a Regulatory Conference or to provide a position on the finding and violation in writing. The licensee has not yet been informed of the specific nature of the enforcement action. The schedule of issuance and notification is:  Mailing of Final Significance Determination  March 26, 2015  Telephone Notification of Licensee  March 26, 2015 The State of Illinois will be notified.
CONTACTS:  Kyle Hanley, OE, (301) 415-1975 John Wray, OE, (301) 415-1288 Distribution: EN-15-009, March 20, 2015  OWFN  Chairman Burns Comm. Svinicki Comm. Ostendorff Comm. Baran SECY OCA OPA OIP OWFN EDO DEDR DEDMRT OE OGC NRR OI OIG TWFN  OCFO OIS RES ACRS NRO  3WFN NMSS NSIR OP Center Regional Offices RI          RII RIII        RIV


MAIL ADAMS OE staff 
The White finding involved the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components involving the Dresden 3 Automatic Depressurization System (ADS). Specifically, from November 29, 2010, to November 6, 2014, the licensee failed to establish measures to ensure that the application of the ADS electromatic relief valve (ERV) actuators remained suitable for operation. This resulted in multiple failures of the ERV 3E during testing prior to operating cycle D3C23, and an indeterminate period of inoperability and unavailability greater than allowed by Technical Specifications during operating cycle D3C23. The ERV 3E inoperability during the operating cycle was identified after the failure of the valve during its first operational test following unit shutdown for refueling.
A NOV is included based on the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components in accordance with 10 CFR 50, Appendix B, Criterion III, "Design Control".   


Electronic DISTRIBUTION:  P. Holahan, OE N. Hilton, OE J. Wray, OE K. Hanley, OE OE r/f EN binder  
On March 2, 2015, the licensee declined the opportunity to discuss this issue in a Regulatory Conference or to provide a position on the finding and violation in writing. The licensee has not yet been informed of the specific nature of the enforcement action. The schedule of issuance and notification is:  Mailing of Final Significance Determination  March 26, 2015 Telephone Notification of Licensee  March 26, 2015


X  PUBLIC      X NON-SENSITIVE 
The State of Illinois will be notified.


ADAMS ML15079A066 OFFICE OE:ES  OE: BC  NAME KHanley JWray DATE 3/17/2015 3/18/2015   OFFICIAL RECORD COPY}}
CONTACTS:  Kyle Hanley, OE, (301) 415-1975 John Wray, OE, (301) 415-1288 Distribution: EN-15-009, March 20, 2015 OWFN  Chairman Burns Comm. Svinicki Comm. Ostendorff
 
Comm. Baran SECY OCA OPA OIP OWFN EDO DEDR DEDMRT OE OGC NRR OI OIG TWFN  OCFO OIS RES ACRS NRO  3WFN NMSS NSIR OP Center
 
Regional Offices RI          RII
 
RIII        RIV
 
MAIL ADAMS OE staff
 
Electronic DISTRIBUTION:  P. Holahan, OE N. Hilton, OE J. Wray, OE
 
K. Hanley, OE OE r/f EN binder
 
X  PUBLIC      X NON-SENSITIVE
 
ADAMS ML15079A066 OFFICE OE:ES  OE: BC  NAME KHanley JWray DATE 3/17/2015 3/18/2015 OFFICIAL RECORD COPY}}

Revision as of 02:53, 1 July 2018

EN-15-009, Issuance of Final Significance Determination and Notice of Violation for Exelon Generation Company, LLC, Dresden Nuclear Power Station, Unit 3, (EA-15-001)
ML15079A066
Person / Time
Site: Dresden Constellation icon.png
Issue date: 03/20/2015
From: Hanley K, Wray J R
NRC/OE
To:
Hanley K
References
EA-15-001 EN-15-009
Download: ML15079A066 (2)


Text

March 20, 2015 EN 15-009 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Exelon Generation Company, LLC EA-15-001 Dresden Nuclear Power Station, Unit 3 Docket No.: 50-249

Subject:

ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation (NOV) associated with a White Significance Determination Process finding will be issued on or about March 26, 2015, to Exelon Generation Company, LLC (licensee) as a result of an inspection at Dresden Nuclear Power Station, Unit 3 (Dresden 3). The White finding, an issue of low to moderate safety significance, will result in additional NRC inspection and potentially other NRC action.

The White finding involved the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components involving the Dresden 3 Automatic Depressurization System (ADS). Specifically, from November 29, 2010, to November 6, 2014, the licensee failed to establish measures to ensure that the application of the ADS electromatic relief valve (ERV) actuators remained suitable for operation. This resulted in multiple failures of the ERV 3E during testing prior to operating cycle D3C23, and an indeterminate period of inoperability and unavailability greater than allowed by Technical Specifications during operating cycle D3C23. The ERV 3E inoperability during the operating cycle was identified after the failure of the valve during its first operational test following unit shutdown for refueling.

A NOV is included based on the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components in accordance with 10 CFR 50, Appendix B, Criterion III, "Design Control".

On March 2, 2015, the licensee declined the opportunity to discuss this issue in a Regulatory Conference or to provide a position on the finding and violation in writing. The licensee has not yet been informed of the specific nature of the enforcement action. The schedule of issuance and notification is: Mailing of Final Significance Determination March 26, 2015 Telephone Notification of Licensee March 26, 2015

The State of Illinois will be notified.

CONTACTS: Kyle Hanley, OE, (301) 415-1975 John Wray, OE, (301) 415-1288 Distribution: EN-15-009, March 20, 2015 OWFN Chairman Burns Comm. Svinicki Comm. Ostendorff

Comm. Baran SECY OCA OPA OIP OWFN EDO DEDR DEDMRT OE OGC NRR OI OIG TWFN OCFO OIS RES ACRS NRO 3WFN NMSS NSIR OP Center

Regional Offices RI RII

RIII RIV

MAIL ADAMS OE staff

Electronic DISTRIBUTION: P. Holahan, OE N. Hilton, OE J. Wray, OE

K. Hanley, OE OE r/f EN binder

X PUBLIC X NON-SENSITIVE

ADAMS ML15079A066 OFFICE OE:ES OE: BC NAME KHanley JWray DATE 3/17/2015 3/18/2015 OFFICIAL RECORD COPY