| number = ML043500645 | | number = ML043500645 | ||
| issue date = 12/16/2004 | | issue date = 12/16/2004 | ||
| title = | | title = PSEGs Preliminary Responses to NRC Staff Questions Regarding B Recirculation Pump Vibration | ||
| author name = Collins D | | author name = Collins D | ||
| author affiliation = NRC/NRR/DLPM/LPD1 | | author affiliation = NRC/NRR/DLPM/LPD1 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:December 16, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: | {{#Wiki_filter:December 16, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: | ||
Daniel S. Collins, Senior Project Manager, Section Project Directorate I | |||
/RA by R. Fretz for/ | |||
Division of Licensing Project Management Office of Nuclear Reactor Regulation | Division of Licensing Project Management Office of Nuclear Reactor Regulation | ||
| Line 29: | Line 31: | ||
As stated CONTACT: D. Collins, NRR 301-415-1427 | As stated CONTACT: D. Collins, NRR 301-415-1427 | ||
December 17, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: | December 17, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: | ||
Daniel S. Collins, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation | |||
==SUBJECT:== | ==SUBJECT:== | ||
| Line 37: | Line 40: | ||
==Attachment:== | ==Attachment:== | ||
As stated CONTACT: D. Collins, NRR 301-415-1427 DISTRIBUTION PUBLIC | As stated CONTACT: D. Collins, NRR 301-415-1427 DISTRIBUTION PUBLIC PDI-2 R/F D. Collins C. Raynor Accession No: ML043500645 Office PDI-2/LA PDI-2/PM PDI-2/SC Name CRaynor RFretz for DCollins DRoberts Date 12/16/04 12/16/04 12/16/04 OFFICIAL RECORD COPY}} | ||
Latest revision as of 23:21, 15 January 2025
| ML043500645 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 12/16/2004 |
| From: | Dan Collins NRC/NRR/DLPM/LPD1 |
| To: | Darrell Roberts NRC/NRR/DLPM/LPD1 |
| Collins D, NRR/DLPM, 415-1427 | |
| References | |
| TAC MC5111 | |
| Download: ML043500645 (2) | |
Text
December 16, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM:
Daniel S. Collins, Senior Project Manager, Section Project Directorate I
/RA by R. Fretz for/
Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
HOPE CREEK GENERATING STATION - PSEGS PRELIMINARY RESPONSES TO NRC STAFF QUESTIONS REGARDING B RECIRCULATION PUMP VIBRATION (TAC MC5111)
On December 17, 2004, NRC staff will be conducting a public meeting with representatives of PSEG, the licensed owner and operator of the Hope Creek Generating Station. The purpose of the meeting is to discuss PSEGs responses to NRC staff questions regarding Hope Creek B recirculation pump high vibrations and high pressure coolant injection system exhaust pipe damage issues. The document attached to this memo was provided informally by the licensee to assist the NRC staff in its inspection activities regarding the pump vibration issue and to facilitate technical discussions between NRC and PSEG. The document provides preliminary responses to NRC staff questions that had been verbally transmitted to the licensee. This memorandum and the attachment do not convey a formal response by the licensee or represent an NRC staff position.
Docket No. 50-354
Attachment:
As stated CONTACT: D. Collins, NRR 301-415-1427
December 17, 2004 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM:
Daniel S. Collins, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
HOPE CREEK GENERATING STATION - PSEGS PRELIMINARY RESPONSES TO NRC STAFF QUESTIONS REGARDING B RECIRCULATION PUMP VIBRATION (TAC MC5111)
On December 17, 2004, NRC staff will be conducting a public meeting with representatives of PSEG, the licensed owner and operator of the Hope Creek Generating Station. The purpose of the meeting is to discuss PSEGs responses to NRC staff questions regarding Hope Creek B recirculation pump high vibrations and high pressure coolant injection system exhaust pipe damage issues. The document attached to this memo was provided informally by the licensee to assist the NRC staff in its inspection activities regarding the pump vibration issue and to facilitate technical discussions between NRC and PSEG. The document provides preliminary responses to NRC staff questions that had been verbally transmitted to the licensee. This memorandum and the attachment do not convey a formal response by the licensee or represent an NRC staff position.
Docket No. 50-354
Attachment:
As stated CONTACT: D. Collins, NRR 301-415-1427 DISTRIBUTION PUBLIC PDI-2 R/F D. Collins C. Raynor Accession No: ML043500645 Office PDI-2/LA PDI-2/PM PDI-2/SC Name CRaynor RFretz for DCollins DRoberts Date 12/16/04 12/16/04 12/16/04 OFFICIAL RECORD COPY