{{#Wiki_filter:UNITE D STA TES NUCL EA R RE GULA TORY C OMMIS SI ON REGION I 475 AL LENDAL E ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-141 5 March 2, 2 006 Mr. Christo pher M. C rane President and CNO Exelon N uclear Exelon Ge neration Compa ny, LLC 200 Exel on Way Kennett Square, P A 19348 SUBJE CT: ANNU AL AS SESSM ENT LE TTER - LI MER ICK GE NERA TING STATION (REPORT 050003 52/2006001 A ND 0500035 3/2006001)
{{#Wiki_filter:March 2, 2006
Dear Mr. C rane: On February 6 , 2006, the NR C staff completed its performance revie w of Limerick Gen erating Station. Our tec hnical staff revi ewed performance indicators (PIs) for the most recent quarter and inspecti on results for the period from January 1 through Decembe r 31, 2005. The purpose of this letter i s to inform you of our assessment of y our safety performance during this pe riod and our pla ns for futur e inspect ions at your facilit y.This performance rev iew and enclosed i nspection pl an do not i nclude phy sical protec tion information. A se parate letter de signated and marked as "Official Use Onl y - Securi ty-Related Information" wil l includ e the phys ical protecti on review and resultan t inspection plan.Overal l, Li merick U nits 1 and 2 opera ted in a mann er that prese rved publi c heal th and safety and fully met all cornerstone object ives. Plant performance f or the most recent q uarter, as well as for the first three quarters of the assessment cy cle, was within the Licensee Response column of the NR C's Action Matrix , based on al l inspecti on findings bei ng classified a s having very lo w safety si gnificance (Green) an d all PIs indicating p erformance at a lev el requiring no additional NRC ov ersight (Green). Therefore, w e plan to c onduct reactor o versight proces s (ROP) baseline in spectio ns at your facilit y.The enclosed inspection plan detai ls the insp ections, les s those relate d to physi cal protectio n scheduled th rough September 30, 2007. The ins pection pla n is prov ided to al low for the resolution o f any schedul ing conflicts an d personnel availab ility i ssues wel l in adv ance of inspector arri val onsi te. Routine resident ins pections are not listed d ue to their o ngoing and continu ous natu re. The inspect ions in the last nine m onths of the inspe ction pla n are ten tative and m ay be r evise d at t he mi d-cyc le rev iew.In acco rdance wit h 10 C FR 2.3 90 of th e NRC's "Ru les o f Practi ce," a copy of this lette r and i ts enclosure will be made available electronically for public inspection in the NRC Public Docume nt Roo m or from t he Pub licl y Av aila ble R ecords (PARS) compo nent o f NRC's document syste m (ADAMS).


ADAMS is accessi ble from the NRC Web site at http://w ww.nrc.gov/readi ng-rm/ada ms.html (the P ubli c Ele ctroni c Read ing Ro om).
==SUBJECT:==
ANNUAL ASSESSMENT LETTER - LIMERICK GENERATING STATION (REPORT 05000352/2006001 AND 05000353/2006001)


2 C. Crane If circu mstance s aris e wh ich ca use us to cha nge thi s insp ectio n pla n, we wil l con tact y ou to discuss the c hange as soon as possibl e. Please contact me at 610-337-5186 w ith any questions yo u may hav e regarding this l etter or the ins pection pla n.Sincere ly,/R A/Jam es M. Tr app , Ch ie f Reactor Projects Branch 4 Divi sion of Reac tor Pro jects Docket Nos. 50-3 52, 50-353 License No s. NPF-39, N PF-85 Enclosure: Li merick Inspection/
==Dear Mr. Crane:==
Activity Plan cc.Chief Operating Officer, Ex elon Generati on Company , LLC Site Vice President - L imerick Generating S tation Plant M anager, Limerick Genera ting Station Regulatory A ssurance M anager - Limerick Senior Vi ce President - Nuclear Se rvices Vice Presi dent - Mi d-Atlantic Ope rations Vice Presi dent - Operati ons Su pport Vice Presi dent - Licen sing an d Regul atory Affairs Director - Licensing and Regulato ry Affairs, Exelon Generat ion Company, LLC Manager, Lic ensing - Limeri ck Generating Station Vice Presi dent, Ge neral Couns el an d Secr etary Associate Gene ral Counsel , Exelon Generation Compa ny Correspondence Control De sk Director, Burea u of Radiatio n Protection, P A Department of Env ironmental Pro tection J. Johnsrud, Na tional Ene rgy Committee Chairman, Board of Supervisors of Limerick Township J. Bradley Fewell , Assistant Gene ral Counsel , Exelon Nuclear 3 C. Crane Distribution w/encl: (via E-mail)S. Collins, RA M. Dapas, DRA B. Holian, DRP A. Blough, DRS D. Lew, DRP M. Gamberoni, DRS S. Lee , RI OED O D. Roberts, NRR T. Valentine, PM (Interim), NRR E. Mil ler, PM, B ackup J. Trapp, DRP A. Burritt, DRP S. Hansell , DRP - Seni or Resident Inspector C. Bi ckett, D RP - R eside nt Insp ector K. Hea ter - R eside nt OA D. Screnci, ORA N. Sheehan, ORA DRS Branch Chiefs (5)
On February 6, 2006, the NRC staff completed its performance review of Limerick Generating Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2005. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
Instit ute of N uclea r Pow er Oper ation s (INP O)RidsNrrDirsIp ab@nrc.gov ROPreport s@nrc.gov (All IRs)Region I Docket R oom (with c oncurrences)
DOCUM ENT NAM E: S:\RO P-6 EOC R eview\R OP-6 Annual Assessment Letters\LI M EOC.wpd SISP Rev iew Complete:
A LB (Reviewer's Initials)
After de clari ng this docume nt "An Official Agency Recor d" it will be released to the Publ ic.To re ceive a cop y of thi s docu ment, i ndicat e in t he box: " C" = Copy w ithout attachment/enclo sure " E" = Copy w ith attachment/enclosur e " N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME SHansell/ALB for ABurritt/ALB JTrapp/JMT DATE 02/21/06 02/21/06 02/28/06 OFFICIAL RECORD COPY Limerick Inspection / Activity Plan 03/01/2006-09/30/2007 Inspection Type Inspection Activit y Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2006 11:49:29 Report 22 1 7111108G-U1 IN-SERVICE INSPECTION Baseline Inspections 03/06/2006 03/10/2006 1 7111108G IP Inservice Inspection Activities - BWR 1 7112102-OCC RAD SAFETY - ALAR A Baseline Inspections 03/13/2006 03/17/2006 1 7112102 IP A LARA Planning and Controls 3 7111111B-LSRO REQUAL. AN.OPTEST@ LM-P/F RSLTS.


Baseline Inspections 05/30/2006 06/02/2006 1, 2 7111111B IP Licensed Operator Requalification Program 4 71152B-PI&R Baseline Inspections 06/05/2006 06/09/2006 1, 2 71152B IP Identification and Resolution of Problems Baseline Inspections 06/19/2006 06/23/2006 1, 2 71152B IP Identification and Resolution of Problems 1 7112202-PUB RAD SAFETY - RADWAST E Baseline Inspections 07/10/2006 07/14/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation 1 71151-EP PI VERIFICATION Baseline Inspections 08/07/2006 08/11/2006 1, 2 71151 IP Performance Indicator Verification 2 7111107B-HEAT SIN K Baseline Inspections 08/21/2006 08/25/2006 1, 2 7111107B IP Heat Sink Performance 1 7111112B-MAINTENANCE RULE Baseline Inspections 09/18/2006 09/22/2006 1, 2 7111112B IP Maintenance Effectiveness 3 10/23EXM-OPERATOR LICENSE INIITAL EXAMS Not Applicable 09/25/2006 09/29/2006 1 U01664 FY07-LIMERICK INITIAL OPERATOR EXAM Not Applicable 10/23/2006 11/03/2006 1 U01664 FY07-LIMERICK INITIAL OPERATOR EXAM 3 MODS-MODS AND 50.59 Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111117B IP Permanent Plant Modifications 1 7112103-OCC RAD SAFETY - INSTRUMENTS Baseline Inspections 11/27/2006 12/01/2006 1, 2 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 1 7112101-OCC RAD SAFET Y Baseline Inspections 01/08/2007 01/12/2007 1, 2 7112101 IP A ccess Control to Radiologically Significant Areas 1 7111108G-U2 IN-SERVICE INSPECTION Baseline Inspections 03/12/2007 03/16/2007 2 7111108G IP Inservice Inspection Activities - BWR 1 7112102-OCC RAD SAFET Y Baseline Inspections 03/19/2007 03/23/2007 1, 2 7112102 IP A LARA Planning and Controls 2 6/2 EXAM-INITIAL LSRO OPERATOR EXAM Not Applicable 04/30/2007 05/04/2007 1 U01659 FY07 - LIMERICK (UNIT 1&2) INITIAL LSRO EXAM Not Applicable 06/02/2007 06/06/2007 1 U01659 FY07 - LIMERICK (UNIT 1&2) INITIAL LSRO EXAM This report does not include INPO and OUTAGE activities.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.


This report shows only on-site and announced inspection procedures.
Overall, Limerick Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.


Limerick Inspection / Activity Plan 03/01/2006-09/30/2007 Inspection Type Inspection Activit y Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2006 11:49:29 Report 22 3 7111111B-L.O.(PWR.) REQUAL. PROG. + P/F REVIE W Baseline Inspections 09/24/2007 09/28/2007 1, 2 7111111B IP Licensed Operator Requalification Program 1 7112201-PUB RAD SAFETY - RETS Baseline Inspections 07/09/2007 07/13/2007 1, 2 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 3 TRI FIRE-TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 07/16/2007 07/20/2007 1, 2 7111105T IP Fire Protection [Triennial]
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
Baseline Inspections 07/30/2007 08/03/2007 1, 2 7111105T IP Fire Protection [Triennial]
1 71114-EP PRGM INSP Baseline Inspections 07/16/2007 07/20/2007 1, 2 7111402 IP A lert and Notification System Testing Baseline Inspections 07/16/2007 07/20/2007 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 07/16/2007 07/20/2007 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 07/16/2007 07/20/2007 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 07/16/2007 07/20/2007 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 07/16/2007 07/20/2007 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 07/16/2007 07/20/2007 1, 2 71151-EP03 IP A lert & Notification System 4 7111401-EP EXERCISE & PI VERIFICATION Baseline Inspections 08/06/2007 08/10/2007 1, 2 7111401 IP Exercise Evaluation Baseline Inspections 08/06/2007 08/10/2007 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 08/06/2007 08/10/2007 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 08/06/2007 08/10/2007 1, 2 71151-EP03 IP A lert & Notification System This report does not include INPO and OUTAGE activities.


This report shows only on-site and announced inspection procedures.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
2 If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5186 with any questions you may have regarding this letter or the inspection plan.
 
Sincerely,
/RA/
James M. Trapp, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 50-352, 50-353 License Nos. NPF-39, NPF-85 Enclosure: Limerick Inspection/ Activity Plan cc.
 
Chief Operating Officer, Exelon Generation Company, LLC Site Vice President - Limerick Generating Station Plant Manager, Limerick Generating Station Regulatory Assurance Manager - Limerick Senior Vice President - Nuclear Services Vice President - Mid-Atlantic Operations Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs, Exelon Generation Company, LLC Manager, Licensing - Limerick Generating Station Vice President, General Counsel and Secretary Associate General Counsel, Exelon Generation Company Correspondence Control Desk Director, Bureau of Radiation Protection, PA Department of Environmental Protection J. Johnsrud, National Energy Committee Chairman, Board of Supervisors of Limerick Township J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear
 
3
}}
}}

Latest revision as of 11:10, 15 January 2025

Annual Assessment Letter - Limerick Generating Station (Report 05000352/2006001 and 05000353/2006001)
ML060620421
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/02/2006
From: James Trapp
Reactor Projects Region 1 Branch 4
To: Crane C
Exelon Generation Co, Exelon Nuclear
Trapp J RGN-I/DRP/PB1/610-337-5186
References
IR-06-001
Download: ML060620421 (5)


Text

March 2, 2006

SUBJECT:

ANNUAL ASSESSMENT LETTER - LIMERICK GENERATING STATION (REPORT 05000352/2006001 AND 05000353/2006001)

Dear Mr. Crane:

On February 6, 2006, the NRC staff completed its performance review of Limerick Generating Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2005. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.

Overall, Limerick Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

2 If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5186 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

James M. Trapp, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 50-352, 50-353 License Nos. NPF-39, NPF-85 Enclosure: Limerick Inspection/ Activity Plan cc.

Chief Operating Officer, Exelon Generation Company, LLC Site Vice President - Limerick Generating Station Plant Manager, Limerick Generating Station Regulatory Assurance Manager - Limerick Senior Vice President - Nuclear Services Vice President - Mid-Atlantic Operations Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs, Exelon Generation Company, LLC Manager, Licensing - Limerick Generating Station Vice President, General Counsel and Secretary Associate General Counsel, Exelon Generation Company Correspondence Control Desk Director, Bureau of Radiation Protection, PA Department of Environmental Protection J. Johnsrud, National Energy Committee Chairman, Board of Supervisors of Limerick Township J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear