ML070300881: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 20: Line 20:
Tennessee Valley Authority
Tennessee Valley Authority
ATTN: Mr. Karl W. Singer
ATTN: Mr. Karl W. Singer
        Chief Nuclear Officer and
Chief Nuclear Officer and
          Executive Vice President
  Executive Vice President
6A Lookout Place
6A Lookout Place
1101 Market Street
1101 Market Street
Chattanooga, TN 37402-2801
Chattanooga, TN 37402-2801
SUBJECT:       SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT
SUBJECT:
                05000327/2006005, 05000328/2006005 AND 07200034/2006002
SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT
05000327/2006005, 05000328/2006005 AND 07200034/2006002
Dear Mr. Singer:
Dear Mr. Singer:
On December 31, 2006, the United States Nuclear Regulatory Commission (NRC) completed
On December 31, 2006, the United States Nuclear Regulatory Commission (NRC) completed
an inspection at your Sequoyah Nuclear Plant, Units 1 and 2. The enclosed integrated
an inspection at your Sequoyah Nuclear Plant, Units 1 and 2. The enclosed integrated
inspection report documents the inspection results, which were discussed on January 3, 2007,
inspection report documents the inspection results, which were discussed on January 3, 2007,
with Mr. R. Duet and other members of your staff.
with Mr. R. Duet and other members of your staff.
The inspection examined activities conducted under your licenses as they relate to safety and
The inspection examined activities conducted under your licenses as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your
compliance with the Commissions rules and regulations and with the conditions of your
licenses. The inspectors reviewed selected procedures and records, observed activities, and
licenses. The inspectors reviewed selected procedures and records, observed activities, and
interviewed personnel.
interviewed personnel.
The report documents one NRC-identified finding of very low safety significance. This finding
The report documents one NRC-identified finding of very low safety significance. This finding
was determined to involve a violation of NRC requirements. Additionally, a licensee-identified
was determined to involve a violation of NRC requirements. Additionally, a licensee-identified
violation which was determined to be of very low safety significance is listed in this report.
violation which was determined to be of very low safety significance is listed in this report.  
However, because of their very low safety significance and because they are entered into your
However, because of their very low safety significance and because they are entered into your
corrective action program, the NRC is treating these findings as non-cited violations (NCVs)
corrective action program, the NRC is treating these findings as non-cited violations (NCVs)
consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest any NCV in this
consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest any NCV in this
report, you should provide a response within 30 days of the date of this inspection report, with
report, you should provide a response within 30 days of the date of this inspection report, with
the basis for your denial, to the United States Nuclear Regulatory Commission, ATTN.:
the basis for your denial, to the United States Nuclear Regulatory Commission, ATTN.:
Line 50: Line 51:
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
enclosure, and your response (if any) will be available electronically for public inspection in the
enclosure, and your response (if any) will be available electronically for public inspection in the
NRC Public Document Room or from the Publically Available Records (PARS) component of
NRC Public Document Room or from the Publically Available Records (PARS) component of  


                                              2
2
NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at
NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                          Sincerely,
Sincerely,
                                          /RA/
/RA/
                                          Malcolm T. Widmann, Chief
Malcolm T. Widmann, Chief
                                          Reactor Projects Branch 6
Reactor Projects Branch 6
                                          Division of Reactor Projects
Division of Reactor Projects
Docket Nos.: 50-327, 50-328, 72-034
Docket Nos.: 50-327, 50-328, 72-034
License Nos.: DPR-77, DPR-79
License Nos.: DPR-77, DPR-79
Enclosure: Inspection Report 05000327/2006005 and 05000328/2006005 and
Enclosure: Inspection Report 05000327/2006005 and 05000328/2006005 and
              07200034/2006002 w/Attachment: Supplemental Information
07200034/2006002 w/Attachment: Supplemental Information
cc: w/encl: (See page 3)
cc: w/encl: (See page 3)




____ML070300881 __
____ML070300881 __
OFFICE             RII:DRP       RII:DRP       RII:DRP         RII:DRP         RII:DRS       RII:DRS       RII:DRS
OFFICE
SIGNATURE         LXG /RA/       WTM /RA/     JBB via email   MES via email   JXD /RA/     FJE /RA/     LFL /RA/
RII:DRP
NAME               LGarner       MWidmann     JBaptist         MSpeck         JDiaz-Velez   FEhrhardt     LLake
RII:DRP
DATE                 01/30/2007     01/30/2007   01/30/2007       01/30/2007     01/30/2007   01/30/2007   01/30/2007
RII:DRP
E-MAIL COPY?         YES      NO  YES       NO YES       NO     YES       NO   YES       NO YES       NO YES       NO
RII:DRP
OFFICE             RII:DRS       RII:DRS       RII:DRS         RII:DRS         RII:DRS       RII:DRS       RII:DRS
RII:DRS
SIGNATURE         GWL /RA/       DLM /RA/     ECM /RA/         BWM /RA/       CRO for       SDR /RA/     CRO for
RII:DRS
NAME               GLaska         DMasPenaranda EMichel         BMiller         RMoore       SRose         CSmith
RII:DRS
DATE                 01/30/2007     01/30/2007   01/30/2007       01/30/2007     01/30/2007   01/30/2007   01/30/2007
SIGNATURE
E-MAIL COPY?         YES      NO  YES       NO YES       NO     YES       NO   YES       NO YES       NO YES       NO
LXG /RA/
OFFICE             RII:DRS
WTM /RA/
SIGNATURE         CRS /RA/
JBB via email
NAME               CStancil
MES via email
DATE                 01/30/2007
JXD /RA/
E-MAIL COPY?         YES      NO  YES       NO YES       NO     YES       NO   YES       NO YES       NO YES       NO
FJE /RA/
       
LFL /RA/
                                  3
NAME
LGarner
MWidmann
JBaptist
MSpeck
JDiaz-Velez
FEhrhardt
LLake
DATE
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
E-MAIL COPY?
    YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO  
OFFICE
RII:DRS
RII:DRS
RII:DRS
RII:DRS
RII:DRS
RII:DRS
RII:DRS
SIGNATURE
GWL /RA/
DLM /RA/
ECM /RA/
BWM /RA/
CRO for
SDR /RA/
CRO for
NAME
GLaska
DMasPenaranda EMichel
BMiller
RMoore
SRose
CSmith
DATE
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
01/30/2007
E-MAIL COPY?
    YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO  
OFFICE
RII:DRS
SIGNATURE
CRS /RA/
NAME
CStancil
DATE
01/30/2007
E-MAIL COPY?
    YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO     YES
NO  
 
3
cc w/encls:
cc w/encls:
Ashok S. Bhatnagar                   Beth A. Wetzel, Manager
Ashok S. Bhatnagar
Senior Vice President               Corporate Nuclear Licensing and
Senior Vice President
Nuclear Operations                   Industry Affairs
Nuclear Operations
Tennessee Valley Authority          Tennessee Valley Authority
Tennessee Valley Authority
Electronic Mail Distribution         4X Blue Ridge
Electronic Mail Distribution
                                    1101 Market Street
Preston D. Swafford
Preston D. Swafford                 Chattanooga, TN 37402-2801
Senior Vice President
Senior Vice President
Nuclear Support                     Robert H. Bryan, Jr., General Manager
Nuclear Support
Tennessee Valley Authority           Licensing and Industry Affairs
Tennessee Valley Authority
Electronic Mail Distribution         Sequoyah Nuclear Plant
Electronic Mail Distribution
                                    Tennessee Valley Authority
Larry S. Bryant, Vice President
Larry S. Bryant, Vice President     4X Blue Ridge
Nuclear Engineering &
Nuclear Engineering &               1101 Market Street
Technical Services
Technical Services                   Chattanooga, TN 37402-2801
Tennessee Valley Authority
Electronic Mail Distribution
Randy Douet
Site Vice President
Sequoyah Nuclear Plant
Electronic Mail Distribution
General Counsel
Tennessee Valley Authority
Electronic Mail Distribution
John C. Fornicola, General Manager
Nuclear Assurance
Tennessee Valley Authority
Tennessee Valley Authority
Electronic Mail Distribution         David A. Kulisek, Plant Manager
Electronic Mail Distribution
                                    Sequoyah Nuclear Plant
Glenn W. Morris, Manager
Randy Douet                          Tennessee Valley Authority
Licensing and Industry Affairs
Site Vice President                  Electronic Mail Distribution
Sequoyah Nuclear Plant
Sequoyah Nuclear Plant
Electronic Mail Distribution        Lawrence E. Nanney, Director
Tennessee Valley Authority
                                    TN Dept. of Environment & Conservation
General Counsel                      Division of Radiological Health
Tennessee Valley Authority           Electronic Mail Distribution
Electronic Mail Distribution
Electronic Mail Distribution
                                    County Mayor
Beth A. Wetzel, Manager
John C. Fornicola, General Manager   Hamilton County Courthouse
Corporate Nuclear Licensing and
Nuclear Assurance                    Chattanooga, TN 37402-2801
  Industry Affairs
Tennessee Valley Authority
Tennessee Valley Authority
Electronic Mail Distribution        Ann Harris
4X Blue Ridge
                                    341 Swing Loop
1101 Market Street
Glenn W. Morris, Manager             Rockwood, TN 37854
Chattanooga, TN 37402-2801
Robert H. Bryan, Jr., General  Manager
Licensing and Industry Affairs
Licensing and Industry Affairs
Sequoyah Nuclear Plant               James H. Bassham, Director
Sequoyah Nuclear Plant
Tennessee Valley Authority          Tennessee Emergency Management
Tennessee Valley Authority
Electronic Mail Distribution        Agency
4X Blue Ridge
                                    Electronic Mail Distribution
1101 Market Street
                                    Distribution w/encl: (See page 4)
Chattanooga, TN 37402-2801
David A. Kulisek, Plant Manager
Sequoyah Nuclear Plant
Tennessee Valley Authority
Electronic Mail Distribution
Lawrence E. Nanney, Director
TN Dept. of Environment & Conservation
Division of Radiological Health
Electronic Mail Distribution
County Mayor
Hamilton County Courthouse
Chattanooga, TN  37402-2801
Ann Harris
341 Swing Loop
Rockwood, TN  37854
James H. Bassham, Director
Tennessee Emergency Management
Agency
Electronic Mail Distribution
Distribution w/encl: (See page 4)


                                            4
4
Letter to Karl W. Singer from Malcolm T. Widmann dated January 30, 2007
Letter to Karl W. Singer from Malcolm T. Widmann dated January 30, 2007
SUBJECT:       SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT
SUBJECT:
                05000327/2006005, 05000328/2006005 AND 07200034/2006002
SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT
05000327/2006005, 05000328/2006005 AND 07200034/2006002
Distribution w/encl:
Distribution w/encl:
Bob Pascarelli, NRR
Bob Pascarelli, NRR
Line 139: Line 249:
PUBLIC
PUBLIC


                                            TABLE OF CONTENTS
TABLE OF CONTENTS
SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
        1R01 Adverse Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1R01
        1R02 Evaluations of Changes, Tests or Experiments . . . . . . . . . . . . . . . . . . . . . . . . . 4
Adverse Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
        1R04 Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1R02
        1R05 Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Evaluations of Changes, Tests or Experiments . . . . . . . . . . . . . . . . . . . . . . . . . 4
        1R07 Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1R04
        1R08 Inservice Inspection (ISI) Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
        1R11 Licensed Operator Requalification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1R05
        1R12 Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
        1R13 Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . 12
1R07
        1R15 Operability Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
        1R17 Permanent Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
1R08
        1R19 Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Inservice Inspection (ISI) Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
        1R20 Refueling and Other Outage Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
1R11
        1R22 Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Licensed Operator Requalification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
        1EP6 Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
1R12
Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
1R13
Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . 12
1R15
Operability Evaluations
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1R17
Permanent Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
1R19
Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1R20
Refueling and Other Outage Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
1R22
Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
1EP6
Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
RADIATION SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
RADIATION SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
        2OS1 Access Control To Radiologically Significant Areas . . . . . . . . . . . . . . . . . . . . . 20
2OS1 Access Control To Radiologically Significant Areas . . . . . . . . . . . . . . . . . . . . . 20
OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .     21
OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
        4OA2 Identification & Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                   21
4OA2 Identification & Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
        4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .     23
4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
        4OA6 Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             29
4OA6 Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
        4OA7 Licensee Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             29
4OA7 Licensee Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
ATTACHMENT: SUPPLEMENTARY INFORMATION
ATTACHMENT: SUPPLEMENTARY INFORMATION
Key Points of Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
Key Points of Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
Line 171: Line 297:
List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-14
List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-14


            U. S. NUCLEAR REGULATORY COMMISSION
Enclosure
                                REGION II
U. S. NUCLEAR REGULATORY COMMISSION
Docket Nos:       50-327, 50-328, 72-034
REGION II
License Nos:       DPR-77, DPR-79
Docket Nos:
Report No:         05000327/2006005 and 05000328/2006005 and
50-327, 50-328, 72-034
                  07200034/2006002
License Nos:
Licensee:         Tennessee Valley Authority (TVA)
DPR-77, DPR-79
Facility:         Sequoyah Nuclear Plant
Report No:
Location:         Sequoyah Access Road
05000327/2006005 and 05000328/2006005 and
                  Soddy-Daisy, TN 37379
07200034/2006002
Dates:             October 1, 2006 - December 31, 2006
Licensee:
Inspectors:       J. Baptist, Acting Senior Resident Inspector
Tennessee Valley Authority (TVA)
                  J. Diaz-Velez, Health Physicist (Section 2OS1)
Facility:
                  F. Ehrhardt, Operations Engineer (Section 1R11.2)
Sequoyah Nuclear Plant
                  L. Lake, Reactor Inspector (Section 1R08)
Location:
                  G. Laska, Senior Operations Examiner (Section 1R11.3)
Sequoyah Access Road
                  D. Mas-Penaranda, Reactor Inspector (Sections 1R02, 1R17)
Soddy-Daisy, TN 37379
                  E. Michel, Reactor Inspector (Section 4OA5.3)
Dates:
                  B. Miller, Reactor Inspector (Sections 1R08, 4OA5.2)
October 1, 2006 - December 31, 2006
                  R. Moore, Senior Reactor Inspector (Section 4OA5.3)
Inspectors:
                  S. Rose, Senior Operations Engineer (Section 1R11.3)
J. Baptist, Acting Senior Resident Inspector
                  C. Smith Senior Reactor Inspector (Sections 1R02, 1R17)
J. Diaz-Velez, Health Physicist (Section 2OS1)
                  M. Speck, Resident Inspector
F. Ehrhardt, Operations Engineer (Section 1R11.2)
                  C. Stancil, Resident Inspector (Section 1EP6)
L. Lake, Reactor Inspector (Section 1R08)
Approved by:       M. Widmann, Chief
G. Laska, Senior Operations Examiner (Section 1R11.3)  
                  Reactor Projects Branch 6
D. Mas-Penaranda, Reactor Inspector (Sections 1R02, 1R17)
                  Division of Reactor Projects
E. Michel, Reactor Inspector (Section 4OA5.3)
                                                                        Enclosure
B. Miller, Reactor Inspector (Sections 1R08, 4OA5.2)
R. Moore, Senior Reactor Inspector (Section 4OA5.3)
S. Rose, Senior Operations Engineer (Section 1R11.3)
C. Smith Senior Reactor Inspector (Sections 1R02, 1R17)
M. Speck, Resident Inspector
C. Stancil, Resident Inspector (Section 1EP6)
Approved by:
M. Widmann, Chief  
Reactor Projects Branch 6
Division of Reactor Projects


                                SUMMARY OF FINDINGS
Enclosure
  IR 05000327/2006005, IR 05000328/2006005; IR 07200034/2006002; 10/01/2006 -
SUMMARY OF FINDINGS
  12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification
IR 05000327/2006005, IR 05000328/2006005; IR 07200034/2006002; 10/01/2006 -
  Program.
12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification
  The report covered a three-month period of inspection by resident inspectors and
Program.
  announced inspections by 10 regional inspectors and one resident inspector from
The report covered a three-month period of inspection by resident inspectors and
  another site. One NRC-identified Green finding, which was also a non-cited violation,
announced inspections by 10 regional inspectors and one resident inspector from
  was identified. The significance of most findings is indicated by their color (Green,
another site. One NRC-identified Green finding, which was also a non-cited violation,
  White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance
was identified. The significance of most findings is indicated by their color (Green,
  Determination Process" (SDP). Findings for which the SDP does not apply may be
White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance
  Green or be assigned a severity level after NRC management review. The NRC's
Determination Process" (SDP). Findings for which the SDP does not apply may be
  program for overseeing the safe operation of commercial nuclear power reactors is
Green or be assigned a severity level after NRC management review. The NRC's
  described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.
program for overseeing the safe operation of commercial nuclear power reactors is
A. NRC-Identified and Self-Revealing Findings
described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.
  Cornerstone: Mitigating Systems
A.
  Green. The inspectors identified a Green, non-cited violation (NCV) of 10 CFR 55.53,
NRC-Identified and Self-Revealing Findings
  Conditions of Licenses for failure to certify the qualifications and status of licensed
Cornerstone: Mitigating Systems
  operators were current and valid prior to their resumption of license duties. Specific
Green. The inspectors identified a Green, non-cited violation (NCV) of 10 CFR 55.53,
  aspects of the requalification program that were not valid included plant tours that were
Conditions of Licenses for failure to certify the qualifications and status of licensed
  not completed with another licensed operator and not completing all shift functions in
operators were current and valid prior to their resumption of license duties. Specific
  positions to which the individuals will be assigned. The licensee entered the finding into
aspects of the requalification program that were not valid included plant tours that were
  the corrective action program as PER No.112004.
not completed with another licensed operator and not completing all shift functions in  
  The finding is greater than minor because it is associated with the human performance
positions to which the individuals will be assigned. The licensee entered the finding into
  attribute of the Mitigating Systems Cornerstone that affects the cornerstone objective of
the corrective action program as PER No.112004.
  ensuring the availability, reliability, and capability of operators to respond to initiating
The finding is greater than minor because it is associated with the human performance
  events to prevent undesirable consequences that could pose a potential risk to
attribute of the Mitigating Systems Cornerstone that affects the cornerstone objective of
  operations. The finding was evaluated using the Operator Requalification Human
ensuring the availability, reliability, and capability of operators to respond to initiating
  Performance Significance Determination Process. Under this SDP, record deficiencies
events to prevent undesirable consequences that could pose a potential risk to
  can be either minor or of very low safety significance (Green). This finding was
operations. The finding was evaluated using the Operator Requalification Human
  determined to be Green because it was related to the program for maintaining active
Performance Significance Determination Process. Under this SDP, record deficiencies
  licenses and more than 20% of the records reviewed had deficiencies. (Section 1R11.3).
can be either minor or of very low safety significance (Green). This finding was
B. Licensee-Identified Violations
determined to be Green because it was related to the program for maintaining active
  A violation of very low safety significance, which was identified by the licensee, was
licenses and more than 20% of the records reviewed had deficiencies. (Section 1R11.3).
  reviewed by the inspectors. Corrective actions taken or planned by the licensee have
B.
  been entered into the licensees corrective action program. This violation and corrective
Licensee-Identified Violations
  action are listed in Section 4OA7.
A violation of very low safety significance, which was identified by the licensee, was
                                                                                        Enclosure
reviewed by the inspectors. Corrective actions taken or planned by the licensee have
been entered into the licensees corrective action program. This violation and corrective
action are listed in Section 4OA7.


                                      REPORT DETAILS
Enclosure
      Summary of Plant Status:
REPORT DETAILS
      Unit 1 operated at or near 100% rated thermal power (RTP) for the duration of the
Summary of Plant Status:
      reporting period.
Unit 1 operated at or near 100% rated thermal power (RTP) for the duration of the
      Unit 2 operated at or near 100% RTP until November 27, 2006 when it shut down for a
reporting period.
      refueling outage. Unit 2 achieved criticality on December 24, 2006, and reached 100%
Unit 2 operated at or near 100% RTP until November 27, 2006 when it shut down for a
      RTP on December 29, 2006, where it remained for the duration of the reporting period.
refueling outage. Unit 2 achieved criticality on December 24, 2006, and reached 100%
1.   REACTOR SAFETY
RTP on December 29, 2006, where it remained for the duration of the reporting period.
      Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1.
1R01 Adverse Weather Protection
REACTOR SAFETY
  a. Inspection Scope
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
      The inspectors reviewed design features and licensee preparations for protecting the
1R01
      essential raw cooling water (ERCW) intake structure and both Unit 1 and 2 refueling
Adverse Weather Protection
      water storage tanks (RWSTs) from extreme cold and freezing conditions. The
    a.
      inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), and Technical
Inspection Scope
      Specifications (TS), reviewed and observed implementation of licensee freeze protection
The inspectors reviewed design features and licensee preparations for protecting the
      procedures, and walked down portions of the systems to assess the status of system
essential raw cooling water (ERCW) intake structure and both Unit 1 and 2 refueling
      deficiencies and the system readiness for extreme cold weather. Inspectors performed
water storage tanks (RWSTs) from extreme cold and freezing conditions. The
      corrective action program keyword searches to verify deficiencies were being identified
inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), and Technical
      at an appropriate level and that actions were taken to correct problems. Documents
Specifications (TS), reviewed and observed implementation of licensee freeze protection
      reviewed are listed in the Attachment to this report.
procedures, and walked down portions of the systems to assess the status of system
  b. Findings
deficiencies and the system readiness for extreme cold weather. Inspectors performed
      No findings of significance were identified.
corrective action program keyword searches to verify deficiencies were being identified
1R02 Evaluations of Changes, Tests or Experiments
at an appropriate level and that actions were taken to correct problems. Documents
  a. Inspection Scope
reviewed are listed in the Attachment to this report.
      The inspectors reviewed selected samples of 10 CFR 50.59 evaluations to verify that
    b.
      the licensee had appropriately considered the conditions under which changes to the
Findings
      facility, Updated Final Safety Analysis Report (UFSAR), or procedures may be made,
No findings of significance were identified.
      and tests conducted, without prior NRC approval. The inspectors reviewed ten
1R02
      evaluations completed for changes made by the licensee without prior NRC approval.
Evaluations of Changes, Tests or Experiments
      The inspectors also reviewed documents prepared in connection with the changes.
    a.
      Documents reviewed included supporting analyses, the UFSAR, and drawings to verify
Inspection Scope
      that the licensee had correctly concluded that the changes could be made without
      obtaining a license amendment. The ten evaluations reviewed are listed in the
The inspectors reviewed selected samples of 10 CFR 50.59 evaluations to verify that
      Attachment to this report.
the licensee had appropriately considered the conditions under which changes to the
                                                                                    Enclosure
facility, Updated Final Safety Analysis Report (UFSAR), or procedures may be made,
and tests conducted, without prior NRC approval. The inspectors reviewed ten
evaluations completed for changes made by the licensee without prior NRC approval.  
The inspectors also reviewed documents prepared in connection with the changes.
Documents reviewed included supporting analyses, the UFSAR, and drawings to verify
that the licensee had correctly concluded that the changes could be made without
obtaining a license amendment. The ten evaluations reviewed are listed in the
Attachment to this report.


                                              4
4
    Additionally, the inspectors reviewed samples of changes for which the licensee had
Enclosure
    determined that evaluations were not required. The reviews were performed to verify
Additionally, the inspectors reviewed samples of changes for which the licensee had
    that the licensees conclusions to screen out these changes were correct, and the
determined that evaluations were not required. The reviews were performed to verify
    changes were made in compliance with the requirements of 10 CFR 50.59. The sixteen
that the licensees conclusions to screen out these changes were correct, and the
    screened out changes reviewed are listed in the Attachment to this report.
changes were made in compliance with the requirements of 10 CFR 50.59. The sixteen  
    The inspectors also reviewed selected problem evaluation reports (PERs) to verify that
screened out changes reviewed are listed in the Attachment to this report.
    plant problems were evaluated for root/apparent causes; extent of condition; and that
The inspectors also reviewed selected problem evaluation reports (PERs) to verify that
    the developed corrective actions were adequate to ensure recurrence control of the
plant problems were evaluated for root/apparent causes; extent of condition; and that
    identified plant problem.
the developed corrective actions were adequate to ensure recurrence control of the
  b. Findings
identified plant problem.  
    No findings of significance were identified.
    b.
1R04 Equipment Alignment
Findings
  a. Inspection Scope
No findings of significance were identified.
    Partial System Walkdowns. The inspectors performed a partial walkdown of the
1R04
    following three systems to verify the operability of redundant or diverse trains and
Equipment Alignment
    components when safety equipment was inoperable. The inspectors attempted to
    a.
    identify any discrepancies that could impact the function of the system, and, therefore,
Inspection Scope
    potentially increase risk. The inspectors reviewed applicable operating procedures,
Partial System Walkdowns. The inspectors performed a partial walkdown of the
    walked down control system components and verified that selected breakers, valves,
following three systems to verify the operability of redundant or diverse trains and
    and support equipment were in the correct position to support system operation. The
components when safety equipment was inoperable. The inspectors attempted to
    inspectors also verified that the licensee had properly identified and resolved equipment
identify any discrepancies that could impact the function of the system, and, therefore,
    alignment problems that could cause initiating events or impact the capability of
potentially increase risk. The inspectors reviewed applicable operating procedures,
    mitigating systems or barriers and entered them into the corrective action program.
walked down control system components and verified that selected breakers, valves,
    Documents reviewed are listed in the Attachment to this report.
and support equipment were in the correct position to support system operation. The
    *       Residual Heat Removal (RHR) Train 2B during maintenance on Train 2A
inspectors also verified that the licensee had properly identified and resolved equipment
    *       Emergency Diesels 1A, 1B, and 2A during diesel 2B Outage
alignment problems that could cause initiating events or impact the capability of
    *       Unit 2 Spent Fuel Pool Cooling during full core offload
mitigating systems or barriers and entered them into the corrective action program.  
  b. Findings
Documents reviewed are listed in the Attachment to this report.
    No findings of significance were identified.
*
1R05 Fire Protection
Residual Heat Removal (RHR) Train 2B during maintenance on Train 2A
  a. Inspection Scope
*
    The inspectors conducted a tour of the eight areas listed below to assess the material
Emergency Diesels 1A, 1B, and 2A during diesel 2B Outage
    condition and operational status of fire protection features. The inspectors verified that
*
    combustibles and ignition sources were controlled in accordance with the licensees
Unit 2 Spent Fuel Pool Cooling during full core offload
    administrative procedures, fire detection and suppression equipment was available for
    b.
    use; that passive fire barriers were maintained in good material condition; and that
Findings
    compensatory measures for out-of-service, degraded, or inoperable fire protection
No findings of significance were identified.
                                                                                      Enclosure
1R05
Fire Protection
    a.
Inspection Scope
The inspectors conducted a tour of the eight areas listed below to assess the material
condition and operational status of fire protection features. The inspectors verified that
combustibles and ignition sources were controlled in accordance with the licensees
administrative procedures, fire detection and suppression equipment was available for
use; that passive fire barriers were maintained in good material condition; and that
compensatory measures for out-of-service, degraded, or inoperable fire protection


                                                5
5
    equipment were implemented in accordance with the licensees fire plan. Documents
Enclosure
    reviewed are listed in the Attachment to this report.
equipment were implemented in accordance with the licensees fire plan. Documents
    *       Control Building Elevation 669 (Mechanical Equipment Room, 250-VDC Battery
reviewed are listed in the Attachment to this report.
              and Battery Board Rooms)
*
    *       Control Building Elevation 706 (Cable Spreading Room)
Control Building Elevation 669 (Mechanical Equipment Room, 250-VDC Battery
    *       Control Building Elevation 685 (Auxiliary Instrument Rooms)
and Battery Board Rooms)
    *       Auxiliary Building Elevation 690 (Corridor)
*
    *       Emergency Diesel Generator Building
Control Building Elevation 706 (Cable Spreading Room)
    *       Control Building Elevation 732 (Mechanical Equipment Room and Relay Room)
*
    *       Auxiliary Building Elevation 714 (Corridor)
Control Building Elevation 685 (Auxiliary Instrument Rooms)
    *       Unit 2 Residual Heat Removal/Containment Spray Heat Exchanger Rooms
*
    The inspectors observed the performance of the site fire brigade during unannounced
Auxiliary Building Elevation 690 (Corridor)
    drills on March 29, 2006, and September 30, 23006, and reviewed the drill critique
*
    report for an unannounced drill on October 3, 2006, to evaluate the readiness of the fire
Emergency Diesel Generator Building
    brigade to fight fires and to assess the drill against the requirements of the Sequoyah
*
    Nuclear Plant Fire Protection Report, Revision 17. The observed drills simulated fires at
Control Building Elevation 732 (Mechanical Equipment Room and Relay Room)  
    the 480-volt Reactor Motor Operated Valve Board 1B1-B and the Motor-driven Auxiliary
*
    Feedwater Pump 2A-A. The reviewed drill critique was for fire brigade response to a fire
Auxiliary Building Elevation 714 (Corridor)
    alarm report from the Unit 1 RWST. Specifically, the inspectors reviewed the following
*
    aspects of the drills: use of protective clothing, use of breathing apparatus, proper use
Unit 2 Residual Heat Removal/Containment Spray Heat Exchanger Rooms
    of fire hoses, control of the drill scenario, and recurrence of identified deficiencies.
The inspectors observed the performance of the site fire brigade during unannounced
  b. Findings
drills on March 29, 2006, and September 30, 23006, and reviewed the drill critique
    No findings of significance were identified.
report for an unannounced drill on October 3, 2006, to evaluate the readiness of the fire
1R07 Heat Sink Performance
brigade to fight fires and to assess the drill against the requirements of the Sequoyah
  a. Inspection Scope
Nuclear Plant Fire Protection Report, Revision 17. The observed drills simulated fires at
    The inspectors observed performance and reviewed the results of the following activity
the 480-volt Reactor Motor Operated Valve Board 1B1-B and the Motor-driven Auxiliary
    to verify the heat exchangers readiness and availability. Inspectors interviewed
Feedwater Pump 2A-A. The reviewed drill critique was for fire brigade response to a fire
    maintenance and testing personnel and the system engineer, reviewed corrective action
alarm report from the Unit 1 RWST. Specifically, the inspectors reviewed the following
    program documents, previous heat exchanger flow rate data, and inspected the heat
aspects of the drills: use of protective clothing, use of breathing apparatus, proper use
    exchanger internals for cleanliness. Inspectors also walked down the system while in
of fire hoses, control of the drill scenario, and recurrence of identified deficiencies.
    operation looking for evidence of leaks following system restoration. Documents
    b.
    reviewed are listed in the Attachment to this report.
Findings
    *       WO 06-777564-000, Open 2B Containment Spray Heat Exchanger for Eddy
No findings of significance were identified.
              Current Inspection
1R07
  b. Findings
Heat Sink Performance
    No findings of significance were identified.
    a.
                                                                                        Enclosure
Inspection Scope
The inspectors observed performance and reviewed the results of the following activity
to verify the heat exchangers readiness and availability. Inspectors interviewed
maintenance and testing personnel and the system engineer, reviewed corrective action
program documents, previous heat exchanger flow rate data, and inspected the heat
exchanger internals for cleanliness. Inspectors also walked down the system while in
operation looking for evidence of leaks following system restoration. Documents
reviewed are listed in the Attachment to this report.
*  
WO 06-777564-000, Open 2B Containment Spray Heat Exchanger for Eddy
Current Inspection
    b.
Findings
No findings of significance were identified.


                                                6
6
1R08 Inservice Inspection (ISI) Activities (71111.08)
Enclosure
.1   Piping and Pressure Boundary Systems ISI
1R08
  a. Inspection Scope
Inservice Inspection (ISI) Activities (71111.08)
      From December 4 - December 8, 2006, the inspectors observed and reviewed the
.1
      licensees implementation of their ISI program for monitoring degradation of the reactor
Piping and Pressure Boundary Systems ISI
      coolant system (RCS) boundary and other risk significant piping system boundaries for
    a.
      Unit 2. The inspectors observed and reviewed a sample of American Society of
Inspection Scope
      Mechanical Engineers (ASME), Section XI, Section III, and Risk Informed ISI required
From December 4 - December 8, 2006, the inspectors observed and reviewed the
      examinations, in order of risk priority, as identified in Section 71111.08-03 of inspection
licensees implementation of their ISI program for monitoring degradation of the reactor
      procedure 71111.08, Inservice Inspection Activities based upon the ISI activities
coolant system (RCS) boundary and other risk significant piping system boundaries for
      available for review during the onsite inspection period.
Unit 2. The inspectors observed and reviewed a sample of American Society of
      The inspectors conducted an on-site review of nondestructive examination (NDE)
Mechanical Engineers (ASME), Section XI, Section III, and Risk Informed ISI required
      activities to evaluate compliance with TSs and the applicable editions of ASME Section
examinations, in order of risk priority, as identified in Section 71111.08-03 of inspection
      V and Section XI to verify that indications and defects (if present) were appropriately
procedure 71111.08, Inservice Inspection Activities based upon the ISI activities
      evaluated and dispositioned in accordance with the requirements of ASME Section XI
available for review during the onsite inspection period.
      acceptance standards.
The inspectors conducted an on-site review of nondestructive examination (NDE)
      The inspectors observed the following examinations:
activities to evaluate compliance with TSs and the applicable editions of ASME Section
      Manual Ultrasonic Examination:
V and Section XI to verify that indications and defects (if present) were appropriately
      *       13SIF-142
evaluated and dispositioned in accordance with the requirements of ASME Section XI
      Visual (VT3) examination of the following Hangers:
acceptance standards.
      *       2-CVCH-004
The inspectors observed the following examinations:
      *       2-CVCH-007
Manual Ultrasonic Examination:
      *       2-CVCH-010
*
      *       2-CVCH-037
13SIF-142
      Qualification and certification records for examiners, inspection equipment, and
Visual (VT3) examination of the following Hangers:
      consumables along with the applicable NDE procedures for the above ISI examination
*
      activities were reviewed and compared to requirements stated in ASME Section V and
2-CVCH-004
      Section XI.
*
      The inspectors observed in-process welding activities for the following ASME pressure
2-CVCH-007
      boundary locations. Inspectors reviewed quality records for welding procedures,
*
      procedure qualification, welder qualification, and filler metal certification.
2-CVCH-010
      The inspectors observed a sample of in-process weld-overlay activities for the following
*
      Pressurizer nozzles:
2-CVCH-037
      *       Pressurizer Spray Nozzle
Qualification and certification records for examiners, inspection equipment, and
      *       Pressurizer Surge Nozzle
consumables along with the applicable NDE procedures for the above ISI examination
                                                                                        Enclosure
activities were reviewed and compared to requirements stated in ASME Section V and
Section XI.
The inspectors observed in-process welding activities for the following ASME pressure
boundary locations. Inspectors reviewed quality records for welding procedures,
procedure qualification, welder qualification, and filler metal certification.  
The inspectors observed a sample of in-process weld-overlay activities for the following
Pressurizer nozzles:
*
Pressurizer Spray Nozzle
*
Pressurizer Surge Nozzle


                                                7
7
  b. Findings
Enclosure
      No findings of significance were identified.
    b.
.2   Reactor Vessel Upper Head Penetrations
Findings
      The inspectors completed TI2515/150, Reactor Pressure Vessel Head and Head
No findings of significance were identified.  
      Penetration Nozzles (NRC Order EA-03009) (Unit2), this outage. See Section 4OA5.2.
.2
.3   Boric Acid Corrosion Control (BACC) ISI
Reactor Vessel Upper Head Penetrations
  a. Inspection Scope
The inspectors completed TI2515/150, Reactor Pressure Vessel Head and Head
      The inspectors reviewed the licensees BACC activities to ensure implementation with
Penetration Nozzles (NRC Order EA-03009) (Unit2), this outage. See Section 4OA5.2.
      commitments made in response to NRC Generic Letter 88-05 Boric Acid Corrosion of
.3
      Carbon Steel Reactor Pressure Boundary and Bulletin 2002-01 Reactor Pressure
Boric Acid Corrosion Control (BACC) ISI
      Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity.
    a.
      The inspectors conducted an on-site record review as well as an independent walkdown
Inspection Scope
      of parts of the reactor building that are not normally accessible during at-power
The inspectors reviewed the licensees BACC activities to ensure implementation with
      operations to evaluate compliance with licensee BACC program requirements. In
commitments made in response to NRC Generic Letter 88-05 Boric Acid Corrosion of
      particular, the inspectors assessed whether the visual examinations focused on
Carbon Steel Reactor Pressure Boundary and Bulletin 2002-01 Reactor Pressure
      locations where boric acid leaks can cause degradation of safety significant components
Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity.  
      and that degraded or non-conforming conditions were properly identified in the
The inspectors conducted an on-site record review as well as an independent walkdown
      licensees corrective action program.
of parts of the reactor building that are not normally accessible during at-power
      The inspectors reviewed a sample of engineering evaluations completed for boric acid
operations to evaluate compliance with licensee BACC program requirements. In
      found on reactor coolant system piping and components. The inspectors also reviewed
particular, the inspectors assessed whether the visual examinations focused on
      licensee corrective actions implemented for evidence of boric acid leakage to confirm
locations where boric acid leaks can cause degradation of safety significant components
      that they were consistent with requirements of Section XI of the ASME Code and 10
and that degraded or non-conforming conditions were properly identified in the
      CFR 50 Appendix B Criterion XVI.
licensees corrective action program.
  b. Findings
The inspectors reviewed a sample of engineering evaluations completed for boric acid
      No findings of significance were identified.
found on reactor coolant system piping and components. The inspectors also reviewed
.4   Steam Generator ISI
licensee corrective actions implemented for evidence of boric acid leakage to confirm
  a. Inspection Scope
that they were consistent with requirements of Section XI of the ASME Code and 10
      From December 11-15, 2006, the inspectors reviewed the Unit 2 Steam Generator (SG)
CFR 50 Appendix B Criterion XVI.  
      tube eddy current testing (ECT) examination activities to ensure compliance with TSs,
    b.  
      applicable industry operating experience and technical guidance documents, and ASME
Findings
      Code Section XI requirements.
No findings of significance were identified.
      The inspectors reviewed licensee SG inspection activities to ensure that ECT
.4
      inspections were conducted in accordance with the licensees SG Program and
Steam Generator ISI
      applicable industry standards. The inspectors reviewed the SG examination scope,
    a.
                                                                                      Enclosure
Inspection Scope
From December 11-15, 2006, the inspectors reviewed the Unit 2 Steam Generator (SG)
tube eddy current testing (ECT) examination activities to ensure compliance with TSs,
applicable industry operating experience and technical guidance documents, and ASME
Code Section XI requirements.
The inspectors reviewed licensee SG inspection activities to ensure that ECT
inspections were conducted in accordance with the licensees SG Program and
applicable industry standards. The inspectors reviewed the SG examination scope,


                                                8
8
      ECT acquisition procedures, Examination Technique Specification Sheets (ETSS), ECT
Enclosure
      analysis guidelines, the most recent SG degradation assessment and operational
ECT acquisition procedures, Examination Technique Specification Sheets (ETSS), ECT
      assessment, and also the condition monitoring results as they became available. The
analysis guidelines, the most recent SG degradation assessment and operational
      inspectors reviewed documentation to ensure that the ECT probes and equipment
assessment, and also the condition monitoring results as they became available. The
      configurations used were qualified to detect the expected types of SG tube degradation.
inspectors reviewed documentation to ensure that the ECT probes and equipment
      The inspectors ensured that all tubes evaluated in condition monitoring were
configurations used were qualified to detect the expected types of SG tube degradation.
      appropriately screened for in-situ testing. No tubes met the criteria for in-situ testing. In
The inspectors ensured that all tubes evaluated in condition monitoring were
      addition, the inspectors ensured that the licensee had appropriately implemented the
appropriately screened for in-situ testing. No tubes met the criteria for in-situ testing. In
      NRC-approved Alternate Repair Criteria (ARC) applicable to tubes that experienced
addition, the inspectors ensured that the licensee had appropriately implemented the
      outer diameter stress corrosion cracking (ODSCC) at tube support plates.
NRC-approved Alternate Repair Criteria (ARC) applicable to tubes that experienced
      The inspectors monitored the licensees secondary side activities, which included a
outer diameter stress corrosion cracking (ODSCC) at tube support plates.
      foreign object search and recovery (FOSAR) for loose parts, and sludge lancing. As
The inspectors monitored the licensees secondary side activities, which included a
      part of an industry commitment, the licensee was required to remove a tube from
foreign object search and recovery (FOSAR) for loose parts, and sludge lancing. As
      service for destructive testing. The inspectors monitored this evolution to ensure there
part of an industry commitment, the licensee was required to remove a tube from
      was no damage to other tubes or other parts of the SG.
service for destructive testing. The inspectors monitored this evolution to ensure there
  b. Findings
was no damage to other tubes or other parts of the SG.
      No findings of significance were identified.
    b.  
.5   Identification and Resolution of Problems
Findings
  a. Inspection Scope
No findings of significance were identified.
      The inspectors performed a review of piping system ISI related problems that were
.5  
      identified by the licensee and entered into the corrective action program. The inspectors
Identification and Resolution of Problems
      reviewed corrective action documents to confirm that the licensee had appropriately
    a.
      described the scope of the problems. Additionally, the inspectors review included
Inspection Scope
      confirmation that the licensee had an appropriate threshold for identifying issues and
The inspectors performed a review of piping system ISI related problems that were
      had implemented effective corrective actions. The inspectors evaluated the threshold
identified by the licensee and entered into the corrective action program. The inspectors
      for identifying issues through interviews with licensee staff and review of licensee
reviewed corrective action documents to confirm that the licensee had appropriately
      actions to incorporate lessons learned from industry issues related to the ISI program.
described the scope of the problems. Additionally, the inspectors review included
      The inspectors performed these reviews to ensure compliance with 10 CFR Part 50,
confirmation that the licensee had an appropriate threshold for identifying issues and
      Appendix B, Criterion XVI, Corrective Action, requirements. The corrective action
had implemented effective corrective actions. The inspectors evaluated the threshold
      documents reviewed by the inspectors are listed in the Attachment to this report.
for identifying issues through interviews with licensee staff and review of licensee
  b. Findings
actions to incorporate lessons learned from industry issues related to the ISI program.  
      No findings of significance were identified.
The inspectors performed these reviews to ensure compliance with 10 CFR Part 50,  
                                                                                        Enclosure
Appendix B, Criterion XVI, Corrective Action, requirements. The corrective action
documents reviewed by the inspectors are listed in the Attachment to this report.
    b.  
Findings
No findings of significance were identified.


                                                  9
9
1R11 Licensed Operator Requalification Program
Enclosure
.1   Quarterly Inspection
1R11
  a. Inspection Scope
Licensed Operator Requalification Program
      The inspectors observed licensed operator requalification simulator testing on October
.1
      24, 2006. The testing involved a failed impulse pressure transmitter failure followed by
Quarterly Inspection
      loss of condenser vacuum and automatic turbine trip. The reactor failed to automatically
    a.
      trip and resulted in an anticipated transient without scram (ATWS). The ATWS was
Inspection Scope
      compounded by the inability to trip the reactor from the Main Control Room, auxiliary
The inspectors observed licensed operator requalification simulator testing on October
      feedwater control valves failed to operate automatically for Steam Generators Number 1
24, 2006. The testing involved a failed impulse pressure transmitter failure followed by
      and 2, and the Turbine Driven Auxiliary Feedwater Pump (TDAFP) was unable to supply
loss of condenser vacuum and automatic turbine trip. The reactor failed to automatically
      feedwater, all of which required operator action. As plant conditions were being
trip and resulted in an anticipated transient without scram (ATWS). The ATWS was
      stabilized, a pressurizer power operated relief valve (PORV) failed open and required
compounded by the inability to trip the reactor from the Main Control Room, auxiliary
      operators to shut its blocking valve.
feedwater control valves failed to operate automatically for Steam Generators Number 1
      The inspectors observed crew performance in terms of communications; ability to take
and 2, and the Turbine Driven Auxiliary Feedwater Pump (TDAFP) was unable to supply
      timely and proper actions; prioritizing, interpreting and verifying alarms; correct use and
feedwater, all of which required operator action. As plant conditions were being
      implementation of procedures, including the alarm response procedures and emergency
stabilized, a pressurizer power operated relief valve (PORV) failed open and required
      plan event classification; timely control board operation and manipulation, including high
operators to shut its blocking valve.
      risk operator actions; oversight and direction provided by shift manager, including the
The inspectors observed crew performance in terms of communications; ability to take
      ability to identify and implement appropriate TS actions; independent event classification
timely and proper actions; prioritizing, interpreting and verifying alarms; correct use and
      by the Shift Technical Advisor; and group dynamics involved in crew performance. The
implementation of procedures, including the alarm response procedures and emergency
      inspectors also observed the examining staffs assessment of the crews performance
plan event classification; timely control board operation and manipulation, including high
      and compared them to inspector observations. Documents reviewed are listed in the
risk operator actions; oversight and direction provided by shift manager, including the
      Attachment to this report.
ability to identify and implement appropriate TS actions; independent event classification
  b. Findings
by the Shift Technical Advisor; and group dynamics involved in crew performance. The
      No findings of significance were identified.
inspectors also observed the examining staffs assessment of the crews performance
.2   Annual Review of Licensee Requalification Examination Results
and compared them to inspector observations. Documents reviewed are listed in the
  a. Inspection Scope
Attachment to this report.
      On November 17, 2006, the licensee completed the comprehensive requalification
    b.
      biennial written examinations and annual operating tests required to be given to all
Findings
      licensed operators by 10 CFR 55.59(a)(2). The inspectors performed an in-office review
No findings of significance were identified.
      of the overall pass/fail results of the written examinations, individual operating tests, and
.2
      the crew simulator operating tests. These results were compared to the thresholds
Annual Review of Licensee Requalification Examination Results
      established in Manual Chapter 609 Appendix I, Operator Requalification Human
    a.
      Performance Significance Determination Process.
Inspection Scope
  b. Findings
On November 17, 2006, the licensee completed the comprehensive requalification
      No findings of significance were identified.
biennial written examinations and annual operating tests required to be given to all
                                                                                          Enclosure
licensed operators by 10 CFR 55.59(a)(2). The inspectors performed an in-office review
of the overall pass/fail results of the written examinations, individual operating tests, and
the crew simulator operating tests. These results were compared to the thresholds
established in Manual Chapter 609 Appendix I, Operator Requalification Human
Performance Significance Determination Process.
    b.
Findings
No findings of significance were identified.


                                                  10
10
.3   Licensed Operator Requalification Program - Biennial Review
Enclosure
  a. Inspection Scope
.3
      The inspectors reviewed facility operating history and associated documents in
Licensed Operator Requalification Program - Biennial Review
      preparation for this inspection. While onsite the inspectors reviewed documentation,
    a.
      interviewed licensee personnel, and observed the administration of operating tests and
Inspection Scope
      written examinations associated with the licensees operator requalification program.
The inspectors reviewed facility operating history and associated documents in
      Each of the activities performed by the inspectors was done to assess the effectiveness
preparation for this inspection. While onsite the inspectors reviewed documentation,
      of the licensee in implementing requalification requirements identified in 10 CFR 55,
interviewed licensee personnel, and observed the administration of operating tests and
      Operators Licenses. The evaluations were also performed to determine if the licensee
written examinations associated with the licensees operator requalification program.  
      effectively implemented operator requalification guidelines established in NUREG 1021,
Each of the activities performed by the inspectors was done to assess the effectiveness
      Operator Licensing Examination Standards for Power Reactors, and Inspection
of the licensee in implementing requalification requirements identified in 10 CFR 55,
      Procedure 71111.11, Licensed Operator Requalification Program. The inspectors also
Operators Licenses. The evaluations were also performed to determine if the licensee
      evaluated the licensees simulation facility for adequacy for use in operator licensing
effectively implemented operator requalification guidelines established in NUREG 1021,
      examinations using ANSI/ANS-3.5-1985, American National Standard for Nuclear
Operator Licensing Examination Standards for Power Reactors, and Inspection
      Power Plant Simulators for use in Operator Training and Examination. The inspectors
Procedure 71111.11, Licensed Operator Requalification Program. The inspectors also
      observed two crews during the performance of the operating tests. Documentation
evaluated the licensees simulation facility for adequacy for use in operator licensing
      reviewed included written examinations, job performance measures, simulator
examinations using ANSI/ANS-3.5-1985, American National Standard for Nuclear
      scenarios, licensee procedures, on-shift records, licensed operator qualification records,
Power Plant Simulators for use in Operator Training and Examination. The inspectors
      watchstanding and medical records, simulator modification request records and
observed two crews during the performance of the operating tests. Documentation
      performance test records, the feedback process, and remediation plans. Documents
reviewed included written examinations, job performance measures, simulator
      reviewed during the inspection are listed in the Attachment to this report.
scenarios, licensee procedures, on-shift records, licensed operator qualification records,
  b. Findings
watchstanding and medical records, simulator modification request records and
      Introduction: A Green NCV was identified for failure to certify that the qualifications and
performance test records, the feedback process, and remediation plans.   Documents
      status of licensed operators were current and valid prior to their resumption of license
reviewed during the inspection are listed in the Attachment to this report.
      duties. The applicable requirements of 10 CFR 55.53, Conditions of Licenses for
    b.
      license reactivation were not met. Specific aspects of the requalification program that
Findings
      were not valid included plant tours that were not completed with another licensed
Introduction: A Green NCV was identified for failure to certify that the qualifications and
      operator and not completing all shift functions in the position to which the individual will
status of licensed operators were current and valid prior to their resumption of license
      be assigned.
duties. The applicable requirements of 10 CFR 55.53, Conditions of Licenses for
      Description: The inspectors identified problems with several aspects of the reactivation
license reactivation were not met. Specific aspects of the requalification program that
      process for licensed operators who had been reactivated between October 1, 2004 and
were not valid included plant tours that were not completed with another licensed
      September 30, 2006. The inspectors performed a detailed review for 5 of the 15
operator and not completing all shift functions in the position to which the individual will
      individuals who had licenses reactivated during this time period.
be assigned.  
      The inspectors identified that complete tours of the plant were not being conducted in
Description: The inspectors identified problems with several aspects of the reactivation
      accordance with OPDP-1 Operations Department Procedure, Revision 6 and 10 CFR
process for licensed operators who had been reactivated between October 1, 2004 and
      55.53 requirements. Some individuals reactivating their licenses were performing the
September 30, 2006. The inspectors performed a detailed review for 5 of the 15
      required plant tours without being accompanied by another licensed individual. The
individuals who had licenses reactivated during this time period.  
      inspectors also identified that some individuals reactivating their licenses had
The inspectors identified that complete tours of the plant were not being conducted in
      documented standing watch in non-TS positions, i.e., those positions that TSs do not
accordance with OPDP-1 Operations Department Procedure, Revision 6 and 10 CFR
      require a licensed operator to fill. 10 CFR 55.53, requires that an authorized
55.53 requirements. Some individuals reactivating their licenses were performing the
      representative of the facility certify that individuals reactivating their license must
required plant tours without being accompanied by another licensed individual. The
      complete a minimum of 40 hours of shift functions in the position to which the individual
inspectors also identified that some individuals reactivating their licenses had
                                                                                          Enclosure
documented standing watch in non-TS positions, i.e., those positions that TSs do not
require a licensed operator to fill. 10 CFR 55.53, requires that an authorized
representative of the facility certify that individuals reactivating their license must
complete a minimum of 40 hours of shift functions in the position to which the individual


                                          11
11
Enclosure
will be assigned and under the direction of a reactor operator or senior reactor operator
will be assigned and under the direction of a reactor operator or senior reactor operator
as appropriate. The 40 hours shall also include a complete tour of the plant.
as appropriate. The 40 hours shall also include a complete tour of the plant.
The inspectors noted that the licensee performed a self assessment of the licensed
The inspectors noted that the licensee performed a self assessment of the licensed
operator requalification program on September 11-26, 2006. The assessment identified
operator requalification program on September 11-26, 2006. The assessment identified
problems in several different areas related to operator license reactivation and
problems in several different areas related to operator license reactivation and
maintenance of active license process. Specifically, one licensed operators reactivation
maintenance of active license process. Specifically, one licensed operators reactivation
documents could not be located, two licensed operators were returned to active status
documents could not be located, two licensed operators were returned to active status
without all required training completed, and one inactive licensed operator assumed
without all required training completed, and one inactive licensed operator assumed
licensed duties without being reactivated.
licensed duties without being reactivated.  
Analysis: The inspectors determined that the licensees failure to properly certify and
Analysis: The inspectors determined that the licensees failure to properly certify and
maintain the reactivation records of licensed operators and the failure to perform plant
maintain the reactivation records of licensed operators and the failure to perform plant
Line 563: Line 761:
the individual will be assigned is a performance deficiency because the licensee must
the individual will be assigned is a performance deficiency because the licensee must
satisfy the requirements of 10 CFR 55.53 for license reactivation.
satisfy the requirements of 10 CFR 55.53 for license reactivation.
The finding is more than minor because it is associated with the human performance
The finding is more than minor because it is associated with the human performance  
attribute of the Mitigating Systems Cornerstone and adversely affects the cornerstone
attribute of the Mitigating Systems Cornerstone and adversely affects the cornerstone
objective of ensuring the availability, reliability, and capability of operators to response to
objective of ensuring the availability, reliability, and capability of operators to response to
initiating events to prevent undesirable consequences. The failure to properly reactivate
initiating events to prevent undesirable consequences. The failure to properly reactivate
the licenses of operators could adversely impact their performance. The finding was
the licenses of operators could adversely impact their performance. The finding was
evaluated using the Operator Requalification Human Performance Significance
evaluated using the Operator Requalification Human Performance Significance
Determination Process. Under this SDP, record deficiencies can be either minor or of
Determination Process. Under this SDP, record deficiencies can be either minor or of
very low safety significance (Green). This finding was determined to be Green because
very low safety significance (Green). This finding was determined to be Green because
it was related to the program for maintaining active licenses and more than 20% of the
it was related to the program for maintaining active licenses and more than 20% of the
records reviewed had deficiencies.
records reviewed had deficiencies.
Enforcement: 10 CFR 55.53.(f) Conditions of Licenses requires, in part, that an
Enforcement: 10 CFR 55.53.(f) Conditions of Licenses requires, in part, that an
authorized representative of the facility licensee shall certify that qualifications and
authorized representative of the facility licensee shall certify that qualifications and
status of operator licensees are current and valid prior to the resumption of license
status of operator licensees are current and valid prior to the resumption of license
duties. Included in the certification required by 10 CRF 55.53 is that the individual
duties. Included in the certification required by 10 CRF 55.53 is that the individual
complete a minimum of 40 hours of shift functions in the position to be assigned and
complete a minimum of 40 hours of shift functions in the position to be assigned and
also complete a plant tour while accompanied by a licensed operator. Contrary to the
also complete a plant tour while accompanied by a licensed operator. Contrary to the
above, the licensee did not properly certify that qualifications and status were current
above, the licensee did not properly certify that qualifications and status were current
and valid prior to allowing operators to perform licensed duties.
and valid prior to allowing operators to perform licensed duties.
The failure to properly reactivate licensed operators was determined to be of very low
The failure to properly reactivate licensed operators was determined to be of very low
safety significance (Green) and has been entered into the licensees corrective action
safety significance (Green) and has been entered into the licensees corrective action
program as PER No.112004. The finding is being treated as an NCV consistent with
program as PER No.112004. The finding is being treated as an NCV consistent with
Section VI.A of the NRC Enforcement Policy: NCV 05000327,328/2006005-01, Failure
Section VI.A of the NRC Enforcement Policy: NCV 05000327,328/2006005-01, Failure
to certify qualifications and status of licensed operators were current and valid in
to certify qualifications and status of licensed operators were current and valid in
accordance with 10CFR 55.53.
accordance with 10CFR 55.53.
                                                                                      Enclosure


                                                12
12
1R12 Maintenance Effectiveness
Enclosure
  a. Inspection Scope
1R12
    The inspectors reviewed the following three maintenance activities to verify the
Maintenance Effectiveness
    effectiveness of the activities in terms of: 1) appropriate work practices; 2) identifying
    a.
    and addressing common cause failures; 3) scoping in accordance with 10 CFR 50.65
Inspection Scope
    (b); 4) characterizing reliability issues for performance; 5) trending key parameters for
The inspectors reviewed the following three maintenance activities to verify the
    condition monitoring; 6) charging unavailability for performance; 7) classification in
effectiveness of the activities in terms of: 1) appropriate work practices; 2) identifying
    accordance with 10 CFR 50.65(a)(1) or (a)(2); 8) appropriateness of performance
and addressing common cause failures; 3) scoping in accordance with 10 CFR 50.65
    criteria for Systems, Structures, and Components (SSCs) and functions classified as
(b); 4) characterizing reliability issues for performance; 5) trending key parameters for
    (a)(2); and 9) appropriateness of goals and corrective actions for SSCs and functions
condition monitoring; 6) charging unavailability for performance; 7) classification in
    classified as (a)(1). Documents reviewed are listed in the Attachment to this report.
accordance with 10 CFR 50.65(a)(1) or (a)(2); 8) appropriateness of performance
    *       PER 115421, B-B Main Control Room Ventilation
criteria for Systems, Structures, and Components (SSCs) and functions classified as
    *       PER 115780, 2B Residual Heat Removal HX Outlet Valve 74-28 Failure
(a)(2); and 9) appropriateness of goals and corrective actions for SSCs and functions
    *       PER 85481, Repeated Packing Leaks of Safety Injection (SI) Valve 2-FCV-63-156
classified as (a)(1). Documents reviewed are listed in the Attachment to this report.  
  b. Findings
*
    No findings of significance were identified.
PER 115421, B-B Main Control Room Ventilation
1R13 Maintenance Risk Assessments and Emergent Work Control
*
  a. Inspection Scope
PER 115780, 2B Residual Heat Removal HX Outlet Valve 74-28 Failure  
    The inspectors reviewed the following six activities to verify that the appropriate risk
*
    assessments were performed prior to removing equipment from service for
PER 85481, Repeated Packing Leaks of Safety Injection (SI) Valve 2-FCV-63-156
    maintenance. The inspectors verified that risk assessments were performed as
    b.
    required by 10 CFR 50.65 (a)(4), and were accurate and complete. When emergent
Findings
    work was performed, the inspectors verified that the plant risk was promptly reassessed
No findings of significance were identified.
    and managed. The inspectors verified the appropriate use of the licensees risk
1R13
    assessment tool and risk categories in accordance with Procedure SPP-7.1, On-Line
Maintenance Risk Assessments and Emergent Work Control
    Work Management, Revision 8, and Instruction 0-TI-DSM-000-007.1, Risk Assessment
    a.
    Guidelines, Revision 8. Documents reviewed are listed in the Attachment to this report.
Inspection Scope
    *       Unit 2 ECCS Train A Room Cooler Outage
The inspectors reviewed the following six activities to verify that the appropriate risk
    *       Unplanned EDG 2B Inoperability
assessments were performed prior to removing equipment from service for
    *       2-SI-OPS-082-26A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35
maintenance. The inspectors verified that risk assessments were performed as
    *       ORAM Orange risk condition from Unit 2 midloop activities prior to vacuum refill
required by 10 CFR 50.65 (a)(4), and were accurate and complete. When emergent
    *       Franklin 500KV line tripped resulting in Technical Specification 3.8.1.1 entry
work was performed, the inspectors verified that the plant risk was promptly reassessed
    *       Unit 2 initial RCS level drain to partial draindown condition
and managed. The inspectors verified the appropriate use of the licensees risk
  b. Findings
assessment tool and risk categories in accordance with Procedure SPP-7.1, On-Line
    No findings of significance were identified.
Work Management, Revision 8, and Instruction 0-TI-DSM-000-007.1, Risk Assessment
                                                                                        Enclosure
Guidelines, Revision 8. Documents reviewed are listed in the Attachment to this report.  
*
Unit 2 ECCS Train A Room Cooler Outage
*
Unplanned EDG 2B Inoperability
*
2-SI-OPS-082-26A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35  
*
ORAM Orange risk condition from Unit 2 midloop activities prior to vacuum refill
*
Franklin 500KV line tripped resulting in Technical Specification 3.8.1.1 entry
*
Unit 2 initial RCS level drain to partial draindown condition
    b.
Findings
No findings of significance were identified.


                                              13
13
1R15 Operability Evaluations
Enclosure
  a. Inspection Scope
1R15
    For the five operability evaluations described in the PERs listed below, the inspectors
Operability Evaluations
    evaluated the technical adequacy of the evaluations to ensure that TS operability was
    a.
    properly justified and the subject component or system remained available, such that no
Inspection Scope
    unrecognized increase in risk occurred. The inspectors reviewed the UFSAR to verify
For the five operability evaluations described in the PERs listed below, the inspectors
    that the system or component remained available to perform its intended function. In
evaluated the technical adequacy of the evaluations to ensure that TS operability was
    addition, the inspectors reviewed compensatory measures implemented to verify that
properly justified and the subject component or system remained available, such that no
    the compensatory measures worked as stated and the measures were adequately
unrecognized increase in risk occurred. The inspectors reviewed the UFSAR to verify
    controlled. The inspectors also reviewed a sampling of PERs to verify that the licensee
that the system or component remained available to perform its intended function. In
    was identifying and correcting any deficiencies associated with operability evaluations.
addition, the inspectors reviewed compensatory measures implemented to verify that
    Documents reviewed are listed in the Attachment to this report.
the compensatory measures worked as stated and the measures were adequately
    *       PER 111814, Train A MCR Air-Conditioning System Air Flow Greater Than
controlled. The inspectors also reviewed a sampling of PERs to verify that the licensee
              Acceptance Criteria
was identifying and correcting any deficiencies associated with operability evaluations.  
    *       PERs 114769, 114941, Emergency Diesel Generator 2B Feeder Breaker Failed
Documents reviewed are listed in the Attachment to this report.
              to Close When Required
*
    *       PER 109326, ERCW Screen Wash Pump B-B Failed Pump Performance Test
PER 111814, Train A MCR Air-Conditioning System Air Flow Greater Than
    *       PER 115490, Charging Pump Discharge Manual Isolation Valve Appendix R
Acceptance Criteria
              Operability
*
    *       PER 117113, Unit 1 Steam Generator Levels Exhibited Lowering Trend
PERs 114769, 114941, Emergency Diesel Generator 2B Feeder Breaker Failed
  b. Findings
to Close When Required  
    No findings of significance were identified. An unresolved item (URI) is discussed
*
    below.
PER 109326, ERCW Screen Wash Pump B-B Failed Pump Performance Test
    Inability to Perform Actions Required by AOP-N.08, Appendix R Fire Safe Shutdown
*
    Introduction: The inspectors identified an Unresolved Item (URI) for not promptly
PER 115490, Charging Pump Discharge Manual Isolation Valve Appendix R
    identifying and correcting problems associated with manual valve 2-62-527. These
Operability
    problems resulted in operators not being able to comply with licensee procedure AOP-
*
    N.08, Appendix R Fire Safe Shutdown due to manual valve 2-62-527 not being able to
PER 117113, Unit 1 Steam Generator Levels Exhibited Lowering Trend
    be closed within the 13 minutes required.
    b.
    Description: On October 28, 2005, a procedure change to AOP-N.08, Appendix R Fire
Findings
    Safe Shutdown, was implemented. This change incorporated updated guidance
No findings of significance were identified. An unresolved item (URI) is discussed
    provided by a Westinghouse technical bulletin (TB -04-022) concerning RCP seal
below.
    performance during Appendix R fires and a loss of all pump seal cooling. This change
Inability to Perform Actions Required by AOP-N.08, Appendix R Fire Safe Shutdown
    reduced the time available to perform manual actions and restore RCP seal flow from 24
Introduction: The inspectors identified an Unresolved Item (URI) for not promptly
    minutes to 13 minutes. In the event of an Appendix R fire resulting in a spurious safety
identifying and correcting problems associated with manual valve 2-62-527. These
    injection signal, plant procedures required that all RCS injection sources be stopped to
problems resulted in operators not being able to comply with licensee procedure AOP-
    prevent filling the pressurizer solid. The vendor guidance stated that actions taken to
N.08, Appendix R Fire Safe Shutdown due to manual valve 2-62-527 not being able to
    prevent this condition and restore RCP seal flow should be completed within 13 minutes
be closed within the 13 minutes required.
    to prevent seal damage. The actions outlined by AOP-N.08 required an auxiliary unit
Description: On October 28, 2005, a procedure change to AOP-N.08, Appendix R Fire
    operator (AUO) to manipulate several valves in the appropriate Charging Pump room
Safe Shutdown, was implemented. This change incorporated updated guidance
                                                                                      Enclosure
provided by a Westinghouse technical bulletin (TB -04-022) concerning RCP seal
performance during Appendix R fires and a loss of all pump seal cooling. This change
reduced the time available to perform manual actions and restore RCP seal flow from 24
minutes to 13 minutes. In the event of an Appendix R fire resulting in a spurious safety
injection signal, plant procedures required that all RCS injection sources be stopped to
prevent filling the pressurizer solid. The vendor guidance stated that actions taken to
prevent this condition and restore RCP seal flow should be completed within 13 minutes
to prevent seal damage. The actions outlined by AOP-N.08 required an auxiliary unit
operator (AUO) to manipulate several valves in the appropriate Charging Pump room


                                        14
14
and then a CCP restarted to restore seal flow. Specifically, the AUO was to open a
Enclosure
and then a CCP restarted to restore seal flow. Specifically, the AUO was to open a
dedicated flow path to the RCP seals using manual valve 62-526 (A-train), or 62-534 (B-
dedicated flow path to the RCP seals using manual valve 62-526 (A-train), or 62-534 (B-
train) and close the associated CCP manual discharge valve, 62-527 (A-train) or 62-533
train) and close the associated CCP manual discharge valve, 62-527 (A-train) or 62-533
(B-train) to the CCP Injection Tank (CCPIT). To support the procedure change, these
(B-train) to the CCP Injection Tank (CCPIT). To support the procedure change, these
manipulations were subjected to a manual action validation that consisted of a table top
manipulations were subjected to a manual action validation that consisted of a table top
review of the necessary steps. The licensee determined that the CCP manual
review of the necessary steps. The licensee determined that the CCP manual
discharge valves to the CCPIT could be closed by an individual AUO in 5 minutes and
discharge valves to the CCPIT could be closed by an individual AUO in 5 minutes and
20 seconds.
20 seconds.
Prior to the procedure being approved, PER 91383 was written on October 24, 2005.
Prior to the procedure being approved, PER 91383 was written on October 24, 2005.  
The PER addressed concerns by at least one plant AUO that the manual actions
The PER addressed concerns by at least one plant AUO that the manual actions
required by the change to procedure AOP-N.08 may not be able to be completed within
required by the change to procedure AOP-N.08 may not be able to be completed within
the time required. PER 91383 requested the need to further evaluate the time
the time required. PER 91383 requested the need to further evaluate the time
necessary to perform the manual actions by actual valve manipulations, or whether
necessary to perform the manual actions by actual valve manipulations, or whether
additional procedure changes were needed to provide more margin to the required time.
additional procedure changes were needed to provide more margin to the required time.  
The corrective action planned was to perform a timed valve stroke of CCP discharge
The corrective action planned was to perform a timed valve stroke of CCP discharge
valve 2-62-527 to validate procedural change assumptions. Work Order (WO) 06-
valve 2-62-527 to validate procedural change assumptions. Work Order (WO) 06-
771729-000 was written to implement and track this action during an appropriate CCP
771729-000 was written to implement and track this action during an appropriate CCP
maintenance period. PER 91383 was closed as completed on February 24, 2006 based
maintenance period. PER 91383 was closed as completed on February 24, 2006 based
on the WO being written. On November 9, 2006, during a self-assessment, the licensee
on the WO being written. On November 9, 2006, during a self-assessment, the licensee
determined that the WO had not been completed and was not scheduled for
determined that the WO had not been completed and was not scheduled for
performance until January 22, 2007. PER 114455 was written to document the
performance until January 22, 2007. PER 114455 was written to document the
incomplete corrective action. Upon review of PER 114455, the inspectors questioned
incomplete corrective action. Upon review of PER 114455, the inspectors questioned
the licensee on the valves history, the status of corrective actions, and whether a valid
the licensee on the valves history, the status of corrective actions, and whether a valid
safety concern existed if the valve could not be operated within the prescribed time.
safety concern existed if the valve could not be operated within the prescribed time.  
Prior to resolution by the licensee, on November 27, 2006, during Unit 2 refueling
Prior to resolution by the licensee, on November 27, 2006, during Unit 2 refueling
outage activities, operators closed valve 2-62-527 to support maintenance. The
outage activities, operators closed valve 2-62-527 to support maintenance. The
operators reported that the valve was very difficult to operate and required
operators reported that the valve was very difficult to operate and required
approximately 30 minutes for two AUOs to shut the valve. This observation was
approximately 30 minutes for two AUOs to shut the valve. This observation was
documented in in PER 115490 and supported the initial concern expressed in PER
documented in in PER 115490 and supported the initial concern expressed in PER
91383.
91383.  
This information prompted the license to evaluate the consequences of the additional
This information prompted the license to evaluate the consequences of the additional
time needed to operate valve 2-62-527 with plant Appendix R procedures. Functional
time needed to operate valve 2-62-527 with plant Appendix R procedures. Functional
Evaluation (FE) 41722 was drafted and the licensee determined that RCP seal
Evaluation (FE) 41722 was drafted and the licensee determined that RCP seal
degradation would not occur if RCP seal flow was restored with a CCP prior to
degradation would not occur if RCP seal flow was restored with a CCP prior to
completing of the Appendix R Fire safe shutdown manual actions The licensee also
completing of the Appendix R Fire safe shutdown manual actions The licensee also
evaluated whether the same problems were likely for other Appendix R manual valves. .
evaluated whether the same problems were likely for other Appendix R manual valves. .
The licensee drafted a document to support the determination that other valves in both
The licensee drafted a document to support the determination that other valves in both
units could be operated in adequate time in the event of an Appendix R fire.
units could be operated in adequate time in the event of an Appendix R fire.        
Analysis: The inspectors determined that the delay in implementing the WO resulted in
Analysis: The inspectors determined that the delay in implementing the WO resulted in
not promptly identifying and correcting problems with manual valve 2-62-527 resulting in
not promptly identifying and correcting problems with manual valve 2-62-527 resulting in
operators not being able to comply with procedure AOP-N.08, Appendix R Fire Safe
operators not being able to comply with procedure AOP-N.08, Appendix R Fire Safe
Shutdown. The corrective action for PER 91383 was closed to a WO and rescheduled
Shutdown. The corrective action for PER 91383 was closed to a WO and rescheduled
several times in the work control process with a performance date of January 22, 2007.
several times in the work control process with a performance date of January 22, 2007.  
The inspectors referenced Inspection Manual Chapter (IMC) 0612 and determined the
The inspectors referenced Inspection Manual Chapter (IMC) 0612 and determined the
finding is more than minor because if left uncorrected, the licensee would not be able to
finding is more than minor because if left uncorrected, the licensee would not be able to
                                                                                Enclosure


                                                15
15
    comply with AOP-N.08. The finding is associated with the mitigating system
Enclosure
    cornerstone and could be reasonably viewed as affecting the cornerstone objective to
comply with AOP-N.08. The finding is associated with the mitigating system
    ensure the availability, reliability, and capability of systems that respond to initiating
cornerstone and could be reasonably viewed as affecting the cornerstone objective to
    events to prevent undesirable consequences. This finding is unresolved pending the
ensure the availability, reliability, and capability of systems that respond to initiating
    review of supporting documentation and completion of the significance determination.
events to prevent undesirable consequences. This finding is unresolved pending the
    Enforcement: Pending additional information involving the circumstances surrounding
review of supporting documentation and completion of the significance determination.  
    the event, its extent of condition and completion of the significance determination, this
Enforcement: Pending additional information involving the circumstances surrounding
    finding is identified as URI 05000328/2006005-02, Inability to Perform Required Actions
the event, its extent of condition and completion of the significance determination, this
    of AOP-N.08, Appendix R Fire Safe Shutdown.
finding is identified as URI 05000328/2006005-02, Inability to Perform Required Actions
1R17 Permanent Plant Modifications
of AOP-N.08, Appendix R Fire Safe Shutdown.
  a. Inspection Scope
1R17
    The inspectors performed independent design reviews of six plant modifications in the
Permanent Plant Modifications
    Initiating Events, Mitigating Systems, and Barrier Integrity cornerstone areas, to verify
    a.
    that the plant modifications did not have any adverse effects on system availability,
Inspection Scope
    reliability, and functional capability. Documents reviewed included procedures,
The inspectors performed independent design reviews of six plant modifications in the
    engineering calculations, modification design and implementation packages, work
Initiating Events, Mitigating Systems, and Barrier Integrity cornerstone areas, to verify
    orders, Condition Reports (CRs), applicable sections of the UFSAR, TSs, and design
that the plant modifications did not have any adverse effects on system availability,
    basis information. The plant modifications and the associated attributes reviewed are as
reliability, and functional capability. Documents reviewed included procedures,
    follows:
engineering calculations, modification design and implementation packages, work
    DCN D22050, Pressurizer Relief Tank Level Transmitter Removed (Barrier Integrity)
orders, Condition Reports (CRs), applicable sections of the UFSAR, TSs, and design
    *         Control Signal
basis information. The plant modifications and the associated attributes reviewed are as
    *         Energy Needs
follows:  
    *         Process Medium
DCN D22050, Pressurizer Relief Tank Level Transmitter Removed (Barrier Integrity)
    *         Update of Licensee Documents
*
    DCN D21781, Change Steam Generator Narrow Range Level Transmitter Scaling
Control Signal
    (Mitigating System)
*
    *         Control Signal
Energy Needs
    *         Energy Needs
*
    *         Process Medium
Process Medium
    *         Update of Licensee Documents
*
    *         Operations
Update of Licensee Documents
    DCN D21911, Replace Containment Isolation Valve 2-FCV-030-0014(Barrier Integrity)
DCN D21781, Change Steam Generator Narrow Range Level Transmitter Scaling
    *         Pressure Boundary
(Mitigating System)
    *         Structural
*
    *         Process Medium
Control Signal
    *         Update of Licensee Documents
*
    *         Materials/Replacement Components
Energy Needs
    DCN 21900, Replace Unit 1B Main Bank Transformer and Associated Fire Protection
*
    Ring Header, Revision A.(Initiating Event)
Process Medium
    *         Energy Needs
*
    *         Control Signals
Update of Licensee Documents
    *         Post-Installation Testing
*
                                                                                          Enclosure
Operations
DCN D21911, Replace Containment Isolation Valve 2-FCV-030-0014(Barrier Integrity)
*
Pressure Boundary
*
Structural
*
Process Medium
*
Update of Licensee Documents
*
Materials/Replacement Components
DCN 21900, Replace Unit 1B Main Bank Transformer and Associated Fire Protection
Ring Header, Revision A.(Initiating Event)
*
Energy Needs
*
Control Signals
*
Post-Installation Testing


                                              16
16
    *       Update of Licensee Documents
Enclosure
    *       Functional Testing Adequacy and Results
*
    DCN D21971, Replace Cable PP351A for D/G 1A-A, Revision A. (Mitigating Systems)
Update of Licensee Documents
    *       Materials/ Replacement
*
    *       Failure Modes
Functional Testing Adequacy and Results
    *       Post-Installation Testing
DCN D21971, Replace Cable PP351A for D/G 1A-A, Revision A. (Mitigating Systems)
    *       Update of Licensee Documents
*
    *       Functional Testing Adequacy and Results
Materials/ Replacement
    DCN D21827, Revise Setting on Raw Cooling Water Pump Breaker, Revision A.
*
    *       Control Signals
Failure Modes
    *       Response Time
*
    *       Post-Insulation Testing
Post-Installation Testing
    *       Update of Licensee Documents
*
    *       Functional Testing Adequacy and Results
Update of Licensee Documents
    The inspectors also performed field inspections of selected plant modifications to verify
*
    that the as-built installation complied with design requirements delineated in approved
Functional Testing Adequacy and Results
    design documents. Additionally, the inspectors reviewed selected PERs to verify that
DCN D21827, Revise Setting on Raw Cooling Water Pump Breaker, Revision A.
    plant problems were evaluated for root/apparent causes, extent of condition, and that
*
    the developed corrective actions were adequate to ensure recurrence control of the
Control Signals
    identified plant problem.
*
  b. Findings
Response Time
    No findings of significance were identified.
*
1R19 Post-Maintenance Testing
Post-Insulation Testing
  a. Inspection Scope
*
    The inspectors reviewed the five post-maintenance tests listed below to verify that
Update of Licensee Documents
    procedures and test activities ensured system operability and functional capability. The
*
    inspectors reviewed the licensees test procedure to verify that the procedure
Functional Testing Adequacy and Results
    adequately tested the safety function(s) that may have been affected by the
The inspectors also performed field inspections of selected plant modifications to verify
    maintenance activity, that the acceptance criteria in the procedure were consistent with
that the as-built installation complied with design requirements delineated in approved
    information in the applicable licensing basis and/or design basis documents, and that
design documents. Additionally, the inspectors reviewed selected PERs to verify that
    the procedure had been properly reviewed and approved. The inspectors also
plant problems were evaluated for root/apparent causes, extent of condition, and that
    witnessed the test or reviewed the test data, to verify that test results adequately
the developed corrective actions were adequate to ensure recurrence control of the
    demonstrated restoration of the affected safety function(s). Documents reviewed are
identified plant problem.
    listed in the Attachment to this report.
    b.
    *       WO 05-782379-000, Breaker Changeout for Motor-driven Auxiliary Feedwater
Findings
              (AFW) Pump 2B
No findings of significance were identified.
    *       2-SI-OPS-000-009.0, Actuation of Emergency Core Cooling Systems (ECCS)
1R19
              and Boron Injection Flowpath Valves Via SI Signal, Revision 1
Post-Maintenance Testing
    *       WO 05-777912-001, Repack SI system Hot Leg Injection Valve, 2-FCV-63-156
    a.
                                                                                      Enclosure
Inspection Scope
The inspectors reviewed the five post-maintenance tests listed below to verify that
procedures and test activities ensured system operability and functional capability. The
inspectors reviewed the licensees test procedure to verify that the procedure
adequately tested the safety function(s) that may have been affected by the
maintenance activity, that the acceptance criteria in the procedure were consistent with
information in the applicable licensing basis and/or design basis documents, and that
the procedure had been properly reviewed and approved. The inspectors also
witnessed the test or reviewed the test data, to verify that test results adequately
demonstrated restoration of the affected safety function(s). Documents reviewed are
listed in the Attachment to this report.
*
WO 05-782379-000, Breaker Changeout for Motor-driven Auxiliary Feedwater
(AFW) Pump 2B
*
2-SI-OPS-000-009.0, Actuation of Emergency Core Cooling Systems (ECCS)
and Boron Injection Flowpath Valves Via SI Signal, Revision 1
*
WO 05-777912-001, Repack SI system Hot Leg Injection Valve, 2-FCV-63-156


                                              17
17
    *       WO 06-780773-000, Calibrate FCV and Limit Switches on 2-FCV-074-28
Enclosure
    *       2-SI-SLT-088-156.0, Containment Integrated Leak Rate Test, Revision 2
*
  b. Findings
WO 06-780773-000, Calibrate FCV and Limit Switches on 2-FCV-074-28  
    No findings of significance were identified.
*
1R20 Refueling and Other Outage Activities
2-SI-SLT-088-156.0, Containment Integrated Leak Rate Test, Revision 2
  a. Inspection Scope
    b.
    For the Unit 2 refueling outage that began on November 27, 2006, the inspectors
Findings
    evaluated licensee activities to verify that the licensee considered risk in developing
No findings of significance were identified.
    outage schedules, followed risk reduction methods developed to control plant
1R20
    configuration, developed mitigation strategies for the loss of key safety functions, and
Refueling and Other Outage Activities
    adhered to operating license and TS requirements that ensure defense-in-depth. The
    a.
    inspectors also walked down portions of Unit 2 not normally accessible during at-power
Inspection Scope
    operations to verify that safety-related and risk-significant SSCs were maintained in an
For the Unit 2 refueling outage that began on November 27, 2006, the inspectors
    operable condition. Specifically, between November 27, 2006, and December 26, 2006,
evaluated licensee activities to verify that the licensee considered risk in developing
    the inspectors performed inspections and reviews of the following outage activities.
outage schedules, followed risk reduction methods developed to control plant
    Documents reviewed are listed in the Attachment to this report.
configuration, developed mitigation strategies for the loss of key safety functions, and
    *       Outage Plan. The inspectors reviewed the outage safety plan and contingency
adhered to operating license and TS requirements that ensure defense-in-depth. The
            plans to confirm that the licensee had appropriately considered risk, industry
inspectors also walked down portions of Unit 2 not normally accessible during at-power
            experience, and previous site-specific problems in developing and implementing
operations to verify that safety-related and risk-significant SSCs were maintained in an
            a plan that assured maintenance of defense-in-depth.
operable condition. Specifically, between November 27, 2006, and December 26, 2006,
    *       Reactor Shutdown. The inspectors observed the shutdown in the control room
the inspectors performed inspections and reviews of the following outage activities.  
            from the time the reactor was tripped until operators placed it on the RHR
Documents reviewed are listed in the Attachment to this report.
            system for decay heat removal to verify that TS cooldown restrictions were
*
            followed. The inspectors also toured the lower containment as soon as
Outage Plan. The inspectors reviewed the outage safety plan and contingency
            practicable after reactor shutdown to observe the general condition of the RCS
plans to confirm that the licensee had appropriately considered risk, industry
            and emergency core cooling system components and to look for indications of
experience, and previous site-specific problems in developing and implementing
            previously unidentified leakage inside the polar crane wall.
a plan that assured maintenance of defense-in-depth.
    *       Licensee Control of Outage Activities. On a daily basis, the inspectors attended
*
            the licensee outage turnover meeting, reviewed PERs, and reviewed the
Reactor Shutdown. The inspectors observed the shutdown in the control room
            defense-in-depth status sheets to verify that status control was commensurate
from the time the reactor was tripped until operators placed it on the RHR
            with the outage safety plan and in compliance with the applicable TS when
system for decay heat removal to verify that TS cooldown restrictions were
            taking equipment out-of-service. The inspectors further toured the main control
followed. The inspectors also toured the lower containment as soon as
            room and areas of the plant daily to ensure that the following key safety
practicable after reactor shutdown to observe the general condition of the RCS
            functions were maintained in accordance with the outage safety plan and TS:
and emergency core cooling system components and to look for indications of
            electrical power, decay heat removal, spent fuel cooling, inventory control,
previously unidentified leakage inside the polar crane wall.
            reactivity control, and containment closure. The inspectors also observed a
*
            tagout of the containment spray heat exchanger to verify that the equipment was
Licensee Control of Outage Activities. On a daily basis, the inspectors attended
            appropriately configured to safely support the work or testing. To ensure that
the licensee outage turnover meeting, reviewed PERs, and reviewed the
            RCS level instrumentation was properly installed and configured to give accurate
defense-in-depth status sheets to verify that status control was commensurate
            information, the inspectors reviewed the installation of the Mansell level
with the outage safety plan and in compliance with the applicable TS when
                                                                                        Enclosure
taking equipment out-of-service. The inspectors further toured the main control
room and areas of the plant daily to ensure that the following key safety
functions were maintained in accordance with the outage safety plan and TS:
electrical power, decay heat removal, spent fuel cooling, inventory control,
reactivity control, and containment closure. The inspectors also observed a
tagout of the containment spray heat exchanger to verify that the equipment was
appropriately configured to safely support the work or testing. To ensure that
RCS level instrumentation was properly installed and configured to give accurate
information, the inspectors reviewed the installation of the Mansell level


                                            18
18
          monitoring system. Specifically, the inspectors discussed the system with
Enclosure
          engineering, walked it down to verify that it was installed in accordance with
monitoring system. Specifically, the inspectors discussed the system with
          procedures and adequately protected from inadvertent damage, verified that
engineering, walked it down to verify that it was installed in accordance with
          Mansell indication properly overlapped with pressurizer level instruments during
procedures and adequately protected from inadvertent damage, verified that
          pressurizer draindown, verified that operators properly set level alarms to
Mansell indication properly overlapped with pressurizer level instruments during
          procedurally required setpoints, and verified that the system consistently tracked
pressurizer draindown, verified that operators properly set level alarms to
          while lowering RCS level to reduced inventory conditions. The inspectors also
procedurally required setpoints, and verified that the system consistently tracked  
          observed operators compare the Mansell indications with locally-installed
while lowering RCS level to reduced inventory conditions. The inspectors also
          ultrasonic level indicators during entry into mid-loop conditions.
observed operators compare the Mansell indications with locally-installed
  *     Refueling Activities. The inspectors observed fuel movement at the spent fuel
ultrasonic level indicators during entry into mid-loop conditions.
          pool and at the refueling cavity in order to verify compliance with TS and that
*
          each assembly was properly tracked from core offload to core reload. In order to
Refueling Activities. The inspectors observed fuel movement at the spent fuel
          verify proper licensee control of foreign material, the inspectors verified that
pool and at the refueling cavity in order to verify compliance with TS and that
          personnel were properly checked before entering any foreign material exclusion
each assembly was properly tracked from core offload to core reload. In order to
          (FME) areas, reviewed FME procedures, and verified that the licensee followed
verify proper licensee control of foreign material, the inspectors verified that
          the procedures. To ensure that fuel assemblies were loaded in the core
personnel were properly checked before entering any foreign material exclusion
          locations specified by the design, the inspectors independently reviewed the
(FME) areas, reviewed FME procedures, and verified that the licensee followed
          recording of the licensees final core verification.
the procedures. To ensure that fuel assemblies were loaded in the core
  *     Reduced Inventory and Mid-Loop Conditions. Prior to the outage, the inspectors
locations specified by the design, the inspectors independently reviewed the
          reviewed the licensees commitments to Generic 88-17, Loss of Decay Heat
recording of the licensees final core verification.
          Removal. Before entering reduced inventory conditions the inspectors verified
*
          that these commitments were in place, that plant configuration was in
Reduced Inventory and Mid-Loop Conditions. Prior to the outage, the inspectors
          accordance with those commitments, and that distractions from unexpected
reviewed the licensees commitments to Generic 88-17, Loss of Decay Heat
          conditions or emergent work did not affect operator ability to maintain the
Removal. Before entering reduced inventory conditions the inspectors verified
          required reactor vessel level. While in mid-loop conditions, the inspectors
that these commitments were in place, that plant configuration was in
          verified that licensee procedures for closing the containment upon a loss of
accordance with those commitments, and that distractions from unexpected
          decay heat removal were in effect, that operators were aware of how to
conditions or emergent work did not affect operator ability to maintain the
          implement the procedures, and that other personnel were available to close
required reactor vessel level. While in mid-loop conditions, the inspectors
          containment penetrations if needed.
verified that licensee procedures for closing the containment upon a loss of
  *     Heatup and Startup Activities. The inspectors toured the containment prior to
decay heat removal were in effect, that operators were aware of how to
          reactor startup to verify that debris that could affect the performance of the
implement the procedures, and that other personnel were available to close
          containment sump had not been left in the containment. The inspectors
containment penetrations if needed.
          reviewed the licensees mode change checklists to verify that appropriate
*
          prerequisites were met prior to changing TS modes. To verify RCS integrity and
Heatup and Startup Activities. The inspectors toured the containment prior to
          containment integrity, the inspectors further reviewed the licensees RCS
reactor startup to verify that debris that could affect the performance of the
          leakage calculations and containment isolation valve lineups. In order to verify
containment sump had not been left in the containment. The inspectors
          that core operating limit parameters were consistent with core design, the
reviewed the licensees mode change checklists to verify that appropriate
          inspectors also reviewed low power physics testing results and the Core
prerequisites were met prior to changing TS modes. To verify RCS integrity and
          Operating Limits Report.
containment integrity, the inspectors further reviewed the licensees RCS
b. Findings
leakage calculations and containment isolation valve lineups. In order to verify
  No findings of significance were identified.
that core operating limit parameters were consistent with core design, the
                                                                                    Enclosure
inspectors also reviewed low power physics testing results and the Core
Operating Limits Report.
    b.
Findings
No findings of significance were identified.


                                                19
19
1R22 Surveillance Testing
Enclosure
  a. Inspection Scope
1R22
    For the seven surveillance tests identified below, by witnessing testing and/or reviewing
Surveillance Testing
    the test data, the inspectors verified that the SSCs involved in these tests satisfied the
    a.
    requirements described in the TS surveillance requirements, the UFSAR, applicable
Inspection Scope
    licensee procedures, and that the tests demonstrated that the SSCs were capable of
For the seven surveillance tests identified below, by witnessing testing and/or reviewing
    performing their intended safety functions. Documents reviewed are listed in the
the test data, the inspectors verified that the SSCs involved in these tests satisfied the
    Attachment to this report. Those tests included the following:
requirements described in the TS surveillance requirements, the UFSAR, applicable  
    *       1-SI-MIN-061-108.0, Ice Condenser Intermediate Deck Door Weekly Inspection,
licensee procedures, and that the tests demonstrated that the SSCs were capable of  
              Revision 2
performing their intended safety functions. Documents reviewed are listed in the
    *       2-SI-ICC-090-106.0, Channel Calibration of Containment Building Lower
Attachment to this report. Those tests included the following:
              Compartment Air Monitor 2-R-90-106, Revision 9***
*
    *       0-SI-SXV-001-859.0, Testing and Setting of Main Steam Safety Valves, Revision 9
1-SI-MIN-061-108.0, Ice Condenser Intermediate Deck Door Weekly Inspection,
    *       2-SI-OPS-082-026.A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35
Revision 2
    *       0-SI-MIN-061-109.0, Ice Condenser Intermediate and Lower Inlet Doors and
*
              Vent Curtains, Revision 4*
2-SI-ICC-090-106.0, Channel Calibration of Containment Building Lower
    *       2-SI-OPS-003-118.0 AFW pump and Valve Auto Actuation, Revision 18
Compartment Air Monitor 2-R-90-106, Revision 9***
    *       2-SI-SXP-003-003-202.S, Turbine Driven Auxiliary Feedwater Pump 2A-S
*
              Comprehensive Performance Test, Revision 4**
0-SI-SXV-001-859.0, Testing and Setting of Main Steam Safety Valves, Revision 9
    *This procedure included an outage ice condenser system surveillance
*
    **This procedure included inservice testing requirements
2-SI-OPS-082-026.A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35
    ***This procedure included a RCS leakage detection surveillance
*
  b. Findings
0-SI-MIN-061-109.0, Ice Condenser Intermediate and Lower Inlet Doors and
    No findings of significance were identified.
Vent Curtains, Revision 4*
    Cornerstone: Emergency Preparedness
*
1EP6 Drill Evaluation
2-SI-OPS-003-118.0 AFW pump and Valve Auto Actuation, Revision 18
  a. Inspection Scope
*
    Resident inspectors evaluated the conduct of a routine licensee emergency drill on
2-SI-SXP-003-003-202.S, Turbine Driven Auxiliary Feedwater Pump 2A-S
    October 3, 2006, to identify any weaknesses and deficiencies in classification,
Comprehensive Performance Test, Revision 4**  
    notification, and protective action recommendation (PARs) development activities. The
*This procedure included an outage ice condenser system surveillance
    inspectors observed emergency response operations in the simulated control room to
**This procedure included inservice testing requirements
    verify that event classification and notifications were done in accordance with EPIP-1,
***This procedure included a RCS leakage detection surveillance
    Emergency Plan Classification Matrix, Revision 38. The inspectors also attended the
    b.
    licensee critique of the drill to compare any inspector-observed weakness with those
Findings
    identified by the licensee in order to verify whether the licensee was properly identifying
No findings of significance were identified.
    failures. Documents reviewed are listed in the Attachment to this report.
Cornerstone: Emergency Preparedness
                                                                                      Enclosure
1EP6
Drill Evaluation
    a.
Inspection Scope
Resident inspectors evaluated the conduct of a routine licensee emergency drill on
October 3, 2006, to identify any weaknesses and deficiencies in classification,
notification, and protective action recommendation (PARs) development activities. The
inspectors observed emergency response operations in the simulated control room to
verify that event classification and notifications were done in accordance with EPIP-1,
Emergency Plan Classification Matrix, Revision 38. The inspectors also attended the
licensee critique of the drill to compare any inspector-observed weakness with those
identified by the licensee in order to verify whether the licensee was properly identifying
failures. Documents reviewed are listed in the Attachment to this report.


                                              20
20
  b. Findings
Enclosure
      No findings of significance were identified.
    b.
2.   RADIATION SAFETY
Findings
      Cornerstone: Occupational Radiation Safety (OS)
No findings of significance were identified.
2.
RADIATION SAFETY
Cornerstone: Occupational Radiation Safety (OS)
2OS1 Access Control To Radiologically Significant Areas
2OS1 Access Control To Radiologically Significant Areas
  a. Inspection Scope
    a.
      Access Control Licensee program activities for monitoring workers and controlling
Inspection Scope
      access to radiologically significant areas and tasks were inspected. The inspector
Access Control Licensee program activities for monitoring workers and controlling
      evaluated procedural guidance; directly observed implementation of administrative and
access to radiologically significant areas and tasks were inspected. The inspector
      established physical controls; assessed worker exposures to radiation and radioactive
evaluated procedural guidance; directly observed implementation of administrative and
      material; and appraised radiation worker and technician knowledge of, and proficiency
established physical controls; assessed worker exposures to radiation and radioactive  
      in, the implementation of Radiation Protection (RP) program activities.
material; and appraised radiation worker and technician knowledge of, and proficiency
      During the inspection, radiological controls for ongoing refueling activities for Unit 2 were
in, the implementation of Radiation Protection (RP) program activities.
      observed and discussed. Reviewed tasks included steam generator non-destructive
During the inspection, radiological controls for ongoing refueling activities for Unit 2 were
      testing, containment sump modifications, and refueling activities. In addition, licensee
observed and discussed. Reviewed tasks included steam generator non-destructive
      controls for selected tasks scheduled and on-going during the current refueling outage
testing, containment sump modifications, and refueling activities. In addition, licensee
      were assessed. The evaluations included, as applicable, Radiation Work Permit (RWP)
controls for selected tasks scheduled and on-going during the current refueling outage
      details; use and placement of dosimetry and air sampling equipment; electronic
were assessed. The evaluations included, as applicable, Radiation Work Permit (RWP)
      dosimeter set-points, and monitoring and assessment of worker dose from direct
details; use and placement of dosimetry and air sampling equipment; electronic
      radiation and airborne radioactivity source terms. Effectiveness of established controls
dosimeter set-points, and monitoring and assessment of worker dose from direct
      was assessed against area radiation and contamination survey results, and
radiation and airborne radioactivity source terms. Effectiveness of established controls
      occupational doses received. Physical and administrative controls and their
was assessed against area radiation and contamination survey results, and
      implementation for locked high radiation areas (LHRAs) and very high radiation areas
occupational doses received. Physical and administrative controls and their
      were evaluated through discussions with cognizant licensee representatives, direct field
implementation for locked high radiation areas (LHRAs) and very high radiation areas
      observations, and record reviews.
were evaluated through discussions with cognizant licensee representatives, direct field
      Occupational workers adherence to selected radiation work permits (RWPs) and Health
observations, and record reviews.
      Physics Technician proficiency in providing job coverage were evaluated through direct
Occupational workers adherence to selected radiation work permits (RWPs) and Health
      observations of staff performance during job coverage and routine surveillance
Physics Technician proficiency in providing job coverage were evaluated through direct
      activities, review of selected exposure records, and interviews with cognizant licensee
observations of staff performance during job coverage and routine surveillance
      staff. Radiological postings and physical controls for access to designated high
activities, review of selected exposure records, and interviews with cognizant licensee
      radiation (HRA) and LHRA locations within the Unit 2 Containment, Auxiliary Building,
staff. Radiological postings and physical controls for access to designated high
      and Refuel Floor areas were evaluated during facility tours. In addition, the inspectors
radiation (HRA) and LHRA locations within the Unit 2 Containment, Auxiliary Building,
      independently measured radiation dose rates and evaluated established posting and
and Refuel Floor areas were evaluated during facility tours. In addition, the inspectors
      access controls for selected Auxiliary Building locations. Occupational exposures
independently measured radiation dose rates and evaluated established posting and
      associated with direct radiation and potential radioactive material intakes for were
access controls for selected Auxiliary Building locations. Occupational exposures
      reviewed and discussed with cognizant licensee representatives.
associated with direct radiation and potential radioactive material intakes for were
      RP program activities were evaluated against 10 CFR 19.12; 10 CFR 20, Subparts B, C,
reviewed and discussed with cognizant licensee representatives.
      F, G, H, and J; UFSAR details in Section 12, RP; TSs Section 6.11, High Radiation
RP program activities were evaluated against 10 CFR 19.12; 10 CFR 20, Subparts B, C,
      Area; and approved licensee procedures. Licensee procedures, guidance documents,
F, G, H, and J; UFSAR details in Section 12, RP; TSs Section 6.11, High Radiation
                                                                                        Enclosure
Area; and approved licensee procedures. Licensee procedures, guidance documents,


                                                21
21
      records, and data reviewed within this inspection area are listed in Section 2OS1 of the
Enclosure
      Attachment to this report.
records, and data reviewed within this inspection area are listed in Section 2OS1 of the
      Problem Identification and Resolution Licensee Corrective Action Program documents
Attachment to this report.
      associated with access control to radiologically significant areas were reviewed and
Problem Identification and Resolution Licensee Corrective Action Program documents
      assessed. The inspectors evaluated the licensees ability to identify, characterize,
associated with access control to radiologically significant areas were reviewed and
      prioritize, and resolve the identified issues in accordance with Standard Programs and
assessed. The inspectors evaluated the licensees ability to identify, characterize,
      Processes procedure SPP-3.1, Corrective Action Program. Licensee self-assessments
prioritize, and resolve the identified issues in accordance with Standard Programs and
      and PER documents related to access control that were reviewed and evaluated in
Processes procedure SPP-3.1, Corrective Action Program. Licensee self-assessments
      detail during inspection of this program area are identified in Section 2OS1 of the
and PER documents related to access control that were reviewed and evaluated in
      Attachment to this report.
detail during inspection of this program area are identified in Section 2OS1 of the
      The inspector completed 21 of the required 21 samples for Inspection Procedure (IP)
Attachment to this report.
      71121.01. All samples have now been completed for this IP.
The inspector completed 21 of the required 21 samples for Inspection Procedure (IP)
  b. Findings
71121.01. All samples have now been completed for this IP.
      No findings of significance were identified.
    b.
4.   OTHER ACTIVITIES
Findings
No findings of significance were identified.
4.
OTHER ACTIVITIES
4OA2 Identification and Resolution of Problems
4OA2 Identification and Resolution of Problems
.1   Daily Review
.1
      As required by Inspection Procedure 71152, Identification and Resolution of Problems,
Daily Review  
      and in order to help identify repetitive equipment failures or specific human performance
As required by Inspection Procedure 71152, Identification and Resolution of Problems,
      issues for follow-up, the inspectors performed a daily screening of items entered into the
and in order to help identify repetitive equipment failures or specific human performance
      licensees corrective action program. This was accomplished by reviewing the
issues for follow-up, the inspectors performed a daily screening of items entered into the
      description of each new PER and attending daily management review committee
licensees corrective action program. This was accomplished by reviewing the
      meetings.
description of each new PER and attending daily management review committee
.2   Semi-Annual Trend Review
meetings.
  a. Inspection Scope
.2
      As required by Inspection Procedure 71152, the inspectors performed a review of the
Semi-Annual Trend Review  
      licensees corrective action program and associated documents to identify trends that
    a.
      could indicate the existence of a more significant safety issue. The inspectors review
Inspection Scope
      was focused on procedure quality and compliance issues, but also included licensee
As required by Inspection Procedure 71152, the inspectors performed a review of the
      trending efforts and licensee human performance results. The inspectors review
licensees corrective action program and associated documents to identify trends that
      nominally considered the six-month period of July 2006 through December 2006,
could indicate the existence of a more significant safety issue. The inspectors review
      although some examples expanded beyond those dates when the scope of the trend
was focused on procedure quality and compliance issues, but also included licensee
      warranted.
trending efforts and licensee human performance results. The inspectors review
      Specifically, the inspectors consolidated the results of daily inspector screening
nominally considered the six-month period of July 2006 through December 2006,
      discussed in Section 4OA2.1 into a log, reviewed the log, and compared it to licensee
although some examples expanded beyond those dates when the scope of the trend
      integrated quarterly trend reports for the period from July 2006 through September 2006
warranted.
                                                                                        Enclosure
Specifically, the inspectors consolidated the results of daily inspector screening
discussed in Section 4OA2.1 into a log, reviewed the log, and compared it to licensee
integrated quarterly trend reports for the period from July 2006 through September 2006


                                                22
22
      in order to determine the existence of any adverse trends that the licensee may not
Enclosure
      have previously identified.
in order to determine the existence of any adverse trends that the licensee may not
  b. Assessment and Observations
have previously identified.
      The inspectors identified issues with procedure quality and compliance over the period
    b.
      of assessment. Noteworthy examples of deficient procedure quality or compliance
Assessment and Observations
      were:
The inspectors identified issues with procedure quality and compliance over the period
      *       PER 114003, Incorrect Procedure Revision used on 6.9kV Shutdown Board relay
of assessment. Noteworthy examples of deficient procedure quality or compliance
              testing
were:
      *       PER 115490, Inability to manually operate Appendix R valves within the required
*
              time.
PER 114003, Incorrect Procedure Revision used on 6.9kV Shutdown Board relay
      *       PER 115539, Emergency Gas Treatment System procedure cloning resulting in
testing
              failure of Unit 2 Phase A testing requirements.
*
      *       PER 115534, Loss of RCS inventory during Unit 2 refueling outage Mansell
PER 115490, Inability to manually operate Appendix R valves within the required
              alignment.
time.
      *       PER 117008, Missed firewatch through plant areas with disabled fire detection.
*
      No findings of significance were identified. In general, the licensee had identified trends
PER 115539, Emergency Gas Treatment System procedure cloning resulting in
      and appropriately communicated them to plant senior management. The inspectors
failure of Unit 2 Phase A testing requirements.
      evaluated the licensee trending methodology and observed that the licensee had
*
      performed a summary review of issues which were inputs to the plant Human
PER 115534, Loss of RCS inventory during Unit 2 refueling outage Mansell
      Performance Index. The licensee reviewed cause codes, involved organizations, key
alignment.
      words, and system links to identify potential trends in the data. The inspectors
*
      compared the licensee process results with the results of the inspectors daily
PER 117008, Missed firewatch through plant areas with disabled fire detection.
      screenings and did not identify any significant discrepancies or potential trends that the
No findings of significance were identified. In general, the licensee had identified trends
      licensee had failed to identify. The specifics surrounding PER 115490, regarding the
and appropriately communicated them to plant senior management. The inspectors
      inability to manually operate Appendix R valves within the required time, are further
evaluated the licensee trending methodology and observed that the licensee had
      addressed in Section 1R15, Operability Evaluations.
performed a summary review of issues which were inputs to the plant Human
.3   Annual Sample Review of Problems with Plant Venting Operations
Performance Index. The licensee reviewed cause codes, involved organizations, key
  a. Inspection Scope
words, and system links to identify potential trends in the data. The inspectors
      The inspectors reviewed licensee actions to resolve issues surrounding plant venting
compared the licensee process results with the results of the inspectors daily
      operations. This review began as a look at how the licensee addressed problems
screenings and did not identify any significant discrepancies or potential trends that the
      associated with two potentially significant events that had occurred during the venting of
licensee had failed to identify. The specifics surrounding PER 115490, regarding the
      plant systems. These events are common to nuclear plant operations and often are
inability to manually operate Appendix R valves within the required time, are further
      required in restoration of a system after it has been removed from service or opened for
addressed in Section 1R15, Operability Evaluations.
      maintenance. PER 92485 was written on November 21, 2005, and identified that
.3
      operators had discovered the collapse of the A Chemical Volume Control System
Annual Sample Review of Problems with Plant Venting Operations
      (CVCS) Holdup Tank (HUT) due to the lack of an adequate vent path during drain down.
    a.
      The licensee subsequently suspended use of the A CVCS HUT, performed a root
Inspection Scope
      cause analysis, and implemented corrective actions to prevent a recurrence of this
The inspectors reviewed licensee actions to resolve issues surrounding plant venting
      activity. The inspectors reviewed the completion of required actions items spawned
operations. This review began as a look at how the licensee addressed problems
      from this event for timeliness, accuracy and adequacy. PER 102591 was written on
associated with two potentially significant events that had occurred during the venting of
      May 7, 2006, to address an event during drain down of the RCS to midloop conditions.
plant systems. These events are common to nuclear plant operations and often are
      While making preparations for vacuum refill of the RCS, the evolution had to be
required in restoration of a system after it has been removed from service or opened for
                                                                                        Enclosure
maintenance. PER 92485 was written on November 21, 2005, and identified that
operators had discovered the collapse of the A Chemical Volume Control System
(CVCS) Holdup Tank (HUT) due to the lack of an adequate vent path during drain down.  
The licensee subsequently suspended use of the A CVCS HUT, performed a root
cause analysis, and implemented corrective actions to prevent a recurrence of this
activity. The inspectors reviewed the completion of required actions items spawned
from this event for timeliness, accuracy and adequacy. PER 102591 was written on
May 7, 2006, to address an event during drain down of the RCS to midloop conditions.  
While making preparations for vacuum refill of the RCS, the evolution had to be


                                                23
23
      suspended when it was identified that a required reactor vessel head vent path was not
Enclosure
      properly aligned. The licensee immediately vented the RCS and verified that the RCS
suspended when it was identified that a required reactor vessel head vent path was not
      was not under vacuum conditions based on no observed change in RCS level indication
properly aligned. The licensee immediately vented the RCS and verified that the RCS
      when the head vent was opened. The licensee declared that the apparent cause of the
was not under vacuum conditions based on no observed change in RCS level indication
      event was due to failure to follow procedure, inadequate procedural guidance, and
when the head vent was opened. The licensee declared that the apparent cause of the
      inadequate scheduling. The event associated with PER 102591 was dispositioned as a
event was due to failure to follow procedure, inadequate procedural guidance, and
      licensee-identified violation in Inspection Report 05000327, 328/2006003. The
inadequate scheduling. The event associated with PER 102591 was dispositioned as a
      inspectors reviewed the PER action items for adequacy and the associated procedures
licensee-identified violation in Inspection Report 05000327, 328/2006003. The
      to ensure changes were implemented to preclude repetition of this event. The
inspectors reviewed the PER action items for adequacy and the associated procedures
      inspectors utilized these examples during the inspection period to observe similar
to ensure changes were implemented to preclude repetition of this event. The
      activities that had the potential to degrade in risk significant systems. The inspectors
inspectors utilized these examples during the inspection period to observe similar
      were able to observe RCS drain down and refill activities during the Unit 2 Cycle 14
activities that had the potential to degrade in risk significant systems. The inspectors
      refueling outage, as well as, the venting operations of support systems during
were able to observe RCS drain down and refill activities during the Unit 2 Cycle 14
      restoration to their normal mode of operation.
refueling outage, as well as, the venting operations of support systems during
  b. Findings and Observations
restoration to their normal mode of operation.  
      No findings of significance were identified. The inspectors noted that the licensee
    b.
      appeared to have an adequate sensitivity to operational experience, procedural
Findings and Observations
      guidance, scheduling conflicts, and foreign material exclusion. The licensee was
No findings of significance were identified. The inspectors noted that the licensee
      successful in properly performing the necessary venting activities associated with the
appeared to have an adequate sensitivity to operational experience, procedural
      multiple system drain and refill operations accompanying Unit 2 refueling outage
guidance, scheduling conflicts, and foreign material exclusion. The licensee was
      maintenance.
successful in properly performing the necessary venting activities associated with the  
multiple system drain and refill operations accompanying Unit 2 refueling outage
maintenance.
4OA5 Other Activities
4OA5 Other Activities
.1   Review of the Operation of an Independent Spent Fuel Storage Installation (ISFSI)
.1
      (60855.1)
Review of the Operation of an Independent Spent Fuel Storage Installation (ISFSI)
  a. Inspection Scope
(60855.1)
      The inspectors reviewed ISFSI document control practices to verify that changes to the
    a.
      required ISFSI procedures and equipment were performed in accordance with
Inspection Scope
      guidelines established in licensee procedures and 10 CFR 72.48. Documents reviewed
The inspectors reviewed ISFSI document control practices to verify that changes to the
      are listed in the Attachment to this report.
required ISFSI procedures and equipment were performed in accordance with
  b. Findings
guidelines established in licensee procedures and 10 CFR 72.48. Documents reviewed
      No findings of significance were identified.
are listed in the Attachment to this report.
.2   (Open) NRC Temporary Instruction 2515/150, Rev. 2, Reactor Pressure Vessel Head
    b.
      and Vessel Head Penetration Nozzles (NRC Order EA-03-009) - Unit 2
Findings
  a. Inspection Scope
No findings of significance were identified.
      From December 4 - 8, 2006, the inspectors reviewed the licensees activities associated
.2
      with the NDE of the reactor pressure vessel head (RPVH) penetration nozzles, the bare
(Open) NRC Temporary Instruction 2515/150, Rev. 2, Reactor Pressure Vessel Head
      metal visual examination of the top surface of the RPVH, and the visual examination to
and Vessel Head Penetration Nozzles (NRC Order EA-03-009) - Unit 2
      identify potential boric acid leaks from pressure-retaining components above the RPVH.
    a.
                                                                                        Enclosure
Inspection Scope  
From December 4 - 8, 2006, the inspectors reviewed the licensees activities associated
with the NDE of the reactor pressure vessel head (RPVH) penetration nozzles, the bare
metal visual examination of the top surface of the RPVH, and the visual examination to
identify potential boric acid leaks from pressure-retaining components above the RPVH.


                                            24
24
  These activities were performed in response to NRC Bulletins 2001-01, 2002-01, 2002-
Enclosure
  02, and the first revision of NRC Order EA-03-009 Modifying Licenses dated February
These activities were performed in response to NRC Bulletins 2001-01, 2002-01, 2002-
  20, 2004 (hereafter referred to as the NRC Order).
02, and the first revision of NRC Order EA-03-009 Modifying Licenses dated February
  The inspectors review of the NDE of RPVH penetration nozzles included independent
20, 2004 (hereafter referred to as the NRC Order).
  observation and evaluation of ultrasonic testing (UT) examinations (for both data
The inspectors review of the NDE of RPVH penetration nozzles included independent
  acquisition and analysis), review of NDE procedures, personnel qualifications and
observation and evaluation of ultrasonic testing (UT) examinations (for both data
  training, and NDE equipment certifications. The inspectors also held interviews with
acquisition and analysis), review of NDE procedures, personnel qualifications and
  contractor representatives (Areva) and other licensee personnel involved with the RPVH
training, and NDE equipment certifications. The inspectors also held interviews with
  examination. The activities were reviewed to verify licensee compliance with the NRC
contractor representatives (Areva) and other licensee personnel involved with the RPVH
  Order and to gather information to help the NRC staff identify possible further regulatory
examination. The activities were reviewed to verify licensee compliance with the NRC
  positions and generic communications.
Order and to gather information to help the NRC staff identify possible further regulatory
  The inspectors reviewed a sample of the results from the volumetric UT examinations of
positions and generic communications.
  RPVH penetration nozzles. Specifically, the inspectors reviewed or observed the
The inspectors reviewed a sample of the results from the volumetric UT examinations of
  following:
RPVH penetration nozzles. Specifically, the inspectors reviewed or observed the
  *       Observed in-process UT data acquisition scanning of RPVH penetration nozzles
following:
          57 and 52 (both with thermal sleeves)
*
  *       Reviewed the UT electronic data with the Level III analyst for RPVH nozzles 4,
Observed in-process UT data acquisition scanning of RPVH penetration nozzles
          36, 43, 50, 56, 61, 69, 77, 126 and the calibration block (this included nozzles
57 and 52 (both with thermal sleeves)
          both with and without thermal sleeves)
*
  *       Reviewed the results of the UT examination performed to assess for leakage into
Reviewed the UT electronic data with the Level III analyst for RPVH nozzles 4,
          the annulus (interference fit zone) between the RPVH penetration nozzle and the
36, 43, 50, 56, 61, 69, 77, 126 and the calibration block (this included nozzles
          RPVH low-alloy steel for all penetration numbers listed in the previous bullet
both with and without thermal sleeves)
  *       Reviewed the procedures and results for the visual exam performed to identify
*
          potential boric acid leaks from pressure-retaining components above the RPVH
Reviewed the results of the UT examination performed to assess for leakage into
  *       Reviewed the RPVH susceptibility ranking and calculation of effective
the annulus (interference fit zone) between the RPVH penetration nozzle and the
          degradation years (EDY), including the basis for the RPVH temperature used in
RPVH low-alloy steel for all penetration numbers listed in the previous bullet  
          the calculation
*
b. Observations and Findings
Reviewed the procedures and results for the visual exam performed to identify
  In accordance with the requirements of TI 2515/150, the inspectors evaluated and
potential boric acid leaks from pressure-retaining components above the RPVH
  answered the following questions:
*
  1)     Were the examinations performed by qualified and knowledgeable personnel?
Reviewed the RPVH susceptibility ranking and calculation of effective
  Yes. All personnel involved with the RPVH inspections were appropriately qualified in
degradation years (EDY), including the basis for the RPVH temperature used in
  accordance with the ASME Code, and most far exceeded the minimum requirements for
the calculation
  experience and training hours. The contractor (Areva) personnel responsible for
  b.  
  equipment manipulation, data acquisition, and data analysis frequently perform these
Observations and Findings
  types of inspections nationwide.
In accordance with the requirements of TI 2515/150, the inspectors evaluated and
                                                                                    Enclosure
answered the following questions:
1)  
Were the examinations performed by qualified and knowledgeable personnel?
Yes. All personnel involved with the RPVH inspections were appropriately qualified in
accordance with the ASME Code, and most far exceeded the minimum requirements for
experience and training hours. The contractor (Areva) personnel responsible for
equipment manipulation, data acquisition, and data analysis frequently perform these
types of inspections nationwide.


                                        25
25
2)       Were the examinations performed in accordance with demonstrated
Enclosure
        procedures?
2)  
Yes. The Sequoyah Unit 2 RPVH has 57 control rod drive mechanism (CRDM) nozzles
Were the examinations performed in accordance with demonstrated
procedures?
Yes. The Sequoyah Unit 2 RPVH has 57 control rod drive mechanism (CRDM) nozzles
with thermal sleeves, 13 with open housings (including 5 instrument column nozzles), 8
with thermal sleeves, 13 with open housings (including 5 instrument column nozzles), 8
with part lengths, 4 upper head injection (UHI) nozzles, and 1 vent line nozzle, for a total
with part lengths, 4 upper head injection (UHI) nozzles, and 1 vent line nozzle, for a total
of 83 nozzles. All nozzles were subject to remote automated UT examination using one
of 83 nozzles. All nozzles were subject to remote automated UT examination using one
of two types of probes. The blade probe was used for sleeved penetrations and the
of two types of probes. The blade probe was used for sleeved penetrations and the
open housing CRDMs using a dummy sleeve. The rotating probe was used for the
open housing CRDMs using a dummy sleeve. The rotating probe was used for the
other open housing penetrations (UHI and instrument columns). A liquid penetrant
other open housing penetrations (UHI and instrument columns). A liquid penetrant
exam on the surface of the J-groove weld of the vent line was also performed to satisfy
exam on the surface of the J-groove weld of the vent line was also performed to satisfy
the NRC Order.
the NRC Order.  
Procedures 54-ISI-603-002 (UT with thermal sleeves), 54-ISI-604-001 (UT of open
Procedures 54-ISI-603-002 (UT with thermal sleeves), 54-ISI-604-001 (UT of open
housings), 54-ISI-605-02 (UT of vent line), and 54-ISI-240-44 (liquid penetrant) were
housings), 54-ISI-605-02 (UT of vent line), and 54-ISI-240-44 (liquid penetrant) were
implemented to complete the exams described above. Further, the inspectors verified
implemented to complete the exams described above. Further, the inspectors verified
that the 54-ISI-603-002 and 54-ISI-604-001 procedures were used during the Areva
that the 54-ISI-603-002 and 54-ISI-604-001 procedures were used during the Areva
demonstration to EPRIs Materials Reliability Program (MRP) to show flaw detection
demonstration to EPRIs Materials Reliability Program (MRP) to show flaw detection
capability in RPVH penetrations. By letter dated October 3, 2006, from Jack Spanner of
capability in RPVH penetrations. By letter dated October 3, 2006, from Jack Spanner of
EPRI to Joel Whitaker of TVA (the licensee), EPRI stated that Arevas demonstration of
EPRI to Joel Whitaker of TVA (the licensee), EPRI stated that Arevas demonstration of
flaw detection techniques could reliably detect flaws in CRDM penetrations.
flaw detection techniques could reliably detect flaws in CRDM penetrations.
3)       Was the examination able to identify, disposition, and resolve deficiencies?
3)  
Yes. All indications of cracks or interference fit zone leakage are required to be
Was the examination able to identify, disposition, and resolve deficiencies?
reported for further examination and disposition. Based on observation of the
Yes. All indications of cracks or interference fit zone leakage are required to be
reported for further examination and disposition. Based on observation of the
examination process, the inspectors considered deficiencies would be appropriately
examination process, the inspectors considered deficiencies would be appropriately
identified, dispositioned, and resolved. UT indications associated with the geometry of
identified, dispositioned, and resolved. UT indications associated with the geometry of
the examined volume were identified in several penetration tubes. None of the
the examined volume were identified in several penetration tubes. None of the
indications exhibited crack-like characteristics and were appropriately dispositioned in
indications exhibited crack-like characteristics and were appropriately dispositioned in
accordance with procedures.
accordance with procedures.
4)       Was the examination capable of identifying the primary water stress corrosion
4)  
        cracking (PWSCC) and/or RPVH corrosion phenomena described in the NRC
Was the examination capable of identifying the primary water stress corrosion
        Order?
cracking (PWSCC) and/or RPVH corrosion phenomena described in the NRC
Yes. The NDE techniques employed for the examination of RPVH nozzles had been
Order?
Yes. The NDE techniques employed for the examination of RPVH nozzles had been
previously demonstrated under the EPRI MRP/Inspection Demonstration Program as
previously demonstrated under the EPRI MRP/Inspection Demonstration Program as
capable of detecting PWSCC-type manufactured cracks as well as cracks from actual
capable of detecting PWSCC-type manufactured cracks as well as cracks from actual
samples from another site. Based on the demonstration, observation of in-process
samples from another site. Based on the demonstration, observation of in-process
examinations, and review of NDE data, the inspectors determined that the licensee was
examinations, and review of NDE data, the inspectors determined that the licensee was
capable of identifying PWSCC and/or corrosion as required by the NRC Order.
capable of identifying PWSCC and/or corrosion as required by the NRC Order.  
5)       What was the physical condition of the RPVH (e.g. debris, insulation, dirt, boron
5)  
        from other sources, physical layout, viewing obstructions)?
What was the physical condition of the RPVH (e.g. debris, insulation, dirt, boron
from other sources, physical layout, viewing obstructions)?
The licensee performed a 100% bare metal visual (BMV) inspection of the top of the
The licensee performed a 100% bare metal visual (BMV) inspection of the top of the
RPVH, including 360E around each penetration using a remote visual robotic crawler for
RPVH, including 360E around each penetration using a remote visual robotic crawler for
areas inside the lead shielding and underneath the raised insulation package. The
areas inside the lead shielding and underneath the raised insulation package. The
                                                                                  Enclosure


                                          26
26
Enclosure
surface sloping down from the shielding to the flange was visually inspected directly by a
surface sloping down from the shielding to the flange was visually inspected directly by a
Level III VT-2 examiner. The inspectors independently reviewed portions of the remote
Level III VT-2 examiner. The inspectors independently reviewed portions of the remote
inspection video which revealed no insulation, dirt, or other general debris that caused
inspection video which revealed no insulation, dirt, or other general debris that caused
viewing obstructions in the areas of interest. Some small, loose particles of debris were
viewing obstructions in the areas of interest. Some small, loose particles of debris were
easily cleared from the surface with a low-pressure air stream mounted on the remote
easily cleared from the surface with a low-pressure air stream mounted on the remote  
crawler. The inspectors determined that the physical condition of the head was
crawler. The inspectors determined that the physical condition of the head was
adequate to meet the inspection requirements mandated by the NRC Order.
adequate to meet the inspection requirements mandated by the NRC Order.
6)     Could small boron deposits, as described in NRC Bulletin 2001-01, be identified
6)  
        and characterized?
Could small boron deposits, as described in NRC Bulletin 2001-01, be identified
Yes. The BMV examination was determined by the inspectors to be capable of
and characterized?
Yes. The BMV examination was determined by the inspectors to be capable of
identifying and characterizing small boron deposits as described in NRC Bulletin 2001-
identifying and characterizing small boron deposits as described in NRC Bulletin 2001-
01. The remote exam was VT-2 qualified and able to resolve, at a minimum, the 0.105-
01. The remote exam was VT-2 qualified and able to resolve, at a minimum, the 0.105-
inch characters on an ASME IWA-2210-1 Visual Illumination Card.
inch characters on an ASME IWA-2210-1 Visual Illumination Card.
7)     What material deficiencies (i.e., cracks, corrosion, etc.) were identified that
7)  
        required repair?
What material deficiencies (i.e., cracks, corrosion, etc.) were identified that
required repair?
There were no identified examples of RPVH penetration cracks, leakage, material
There were no identified examples of RPVH penetration cracks, leakage, material
deficiencies, head corrosion, or other flaws that required repair. As discussed
deficiencies, head corrosion, or other flaws that required repair. As discussed
previously, there were some UT indications at J-groove welds that were dispositioned as
previously, there were some UT indications at J-groove welds that were dispositioned as
metallurgical/geometric indications (not service related). One metallurgical indication on
metallurgical/geometric indications (not service related). One metallurgical indication on
tube 56 actually extended below the J-groove weld, and the inspector verified that
tube 56 actually extended below the J-groove weld, and the inspector verified that
adequate coverage below this metallurgical indication was obtained. These indications
adequate coverage below this metallurgical indication was obtained. These indications
were likely due to weld repairs performed during initial RPVH fabrication.
were likely due to weld repairs performed during initial RPVH fabrication.
8)     What, if any, impediments to effective examinations, for each of the applied
8)  
        methods, were identified (e.g., centering rings, insulation, thermal sleeves,
What, if any, impediments to effective examinations, for each of the applied
        instrumentation, nozzle distortion)?
methods, were identified (e.g., centering rings, insulation, thermal sleeves,
instrumentation, nozzle distortion)?
The penetration nozzles with thermal sleeves and centering pads did not impede
The penetration nozzles with thermal sleeves and centering pads did not impede
effective examination. Concerning examination coverage, the NRC Order requires that
effective examination. Concerning examination coverage, the NRC Order requires that
each tubes volume is inspected from a minimum of 2 inches above the highest point of
each tubes volume is inspected from a minimum of 2 inches above the highest point of
the J-groove weld to 2 inches below the lowest point of the J-groove weld, or 1 inch with
the J-groove weld to 2 inches below the lowest point of the J-groove weld, or 1 inch with
a stress analysis. The licensee had performed a stress analysis and the inspectors
a stress analysis. The licensee had performed a stress analysis and the inspectors
verified that the minimum examination coverages required by the NRC Order were met.
verified that the minimum examination coverages required by the NRC Order were met.
9)     What was the basis for the temperature used in the susceptibility ranking
9)  
        calculation?
What was the basis for the temperature used in the susceptibility ranking
calculation?  
NRC Order EA-03-009 requires that licensees calculate the EDY of the RPVH to
NRC Order EA-03-009 requires that licensees calculate the EDY of the RPVH to
determine its susceptibility category, which subsequently determines the scope and
determine its susceptibility category, which subsequently determines the scope and
frequency of required RPVH examinations. The operating temperature of the RPVH is
frequency of required RPVH examinations. The operating temperature of the RPVH is
an input to this calculation. Therefore, an incorrect temperature input could result in
an input to this calculation. Therefore, an incorrect temperature input could result in
placing the RPVH in an incorrect susceptibility category. The licensee uses the cold leg
placing the RPVH in an incorrect susceptibility category. The licensee uses the cold leg
temperature in this calculation.
temperature in this calculation.  
                                                                                  Enclosure


                                                27
27
      In Supplement No. 1 to the NRCs Safety Evaluation Report (SER) dated February
Enclosure
      1980, the NRC concluded that scale model tests provided reasonable assurance that
In Supplement No. 1 to the NRCs Safety Evaluation Report (SER) dated February
      the upper head would operate at the cold leg temperature. However, the NRC staff also
1980, the NRC concluded that scale model tests provided reasonable assurance that
      required that plant data be acquired to confirm the head temperature. This data was
the upper head would operate at the cold leg temperature. However, the NRC staff also
      acquired for Unit 1 to satisfy both units because Unit 2 is considered a sister plant. The
required that plant data be acquired to confirm the head temperature. This data was
      inspectors reviewed this data which confirmed that the head operated at approximately
acquired for Unit 1 to satisfy both units because Unit 2 is considered a sister plant. The
      cold leg temperature with some minor thermocouple variations. In addition, both units
inspectors reviewed this data which confirmed that the head operated at approximately
      underwent a modification since this testing to increase bypass flow to the head from 4%
cold leg temperature with some minor thermocouple variations. In addition, both units
      to about 7%. This gives further assurance that the RPVH operates at cold leg
underwent a modification since this testing to increase bypass flow to the head from 4%
      temperature. For these reasons, the inspectors concluded that the licensee had an
to about 7%. This gives further assurance that the RPVH operates at cold leg
      adequate basis for their temperature input to the susceptibility ranking calculation, which
temperature. For these reasons, the inspectors concluded that the licensee had an
      results in Unit 2 being placed in the Low category.
adequate basis for their temperature input to the susceptibility ranking calculation, which
      10)     During non-visual examinations, was the disposition of indications consistent with
results in Unit 2 being placed in the Low category.
              the NRC flaw evaluation guidance?
10)  
      There were no indications considered to be flaws found during the RPVH examination.
During non-visual examinations, was the disposition of indications consistent with
      11)     Did procedures exist to identify potential boric acid leaks from pressure-retaining
the NRC flaw evaluation guidance?
              components above the RPVH?
There were no indications considered to be flaws found during the RPVH examination.  
      Yes. Procedure 0-PI-DXX-068-100.R, Monitoring of Reactor Head Canopy Seal Welds
11)  
      for Leakage, is implemented every outage and meets the requirements of the NRC
Did procedures exist to identify potential boric acid leaks from pressure-retaining
      Order. However, inspection of conoseals and other bolted connections above the
components above the RPVH?
      RPVH, such as the RVLIS line, are covered under the Boric Acid Program. The
Yes. Procedure 0-PI-DXX-068-100.R, Monitoring of Reactor Head Canopy Seal Welds
      inspectors determined that the program and procedure implementation met the
for Leakage, is implemented every outage and meets the requirements of the NRC
      requirements of the NRC Order, however, the licensee also initiated actions to enhance
Order. However, inspection of conoseals and other bolted connections above the
      the method in which compliance with the NRC Order is documented. The inspectors
RPVH, such as the RVLIS line, are covered under the Boric Acid Program. The
      reviewed the inspection results for this outage and found that no indications of active or
inspectors determined that the program and procedure implementation met the
      recent boric acid leakage from pressure-retaining components above the RPVH were
requirements of the NRC Order, however, the licensee also initiated actions to enhance
      identified.
the method in which compliance with the NRC Order is documented. The inspectors  
      12)     Did the licensee perform appropriate follow-on examinations for indications of
reviewed the inspection results for this outage and found that no indications of active or
              boric acid leaks from pressure-retaining components above the RPVH?
recent boric acid leakage from pressure-retaining components above the RPVH were
      Yes. The licensee identified some boric acid residue that was later determined by
identified.  
      chemical analysis to be older than the recent operating cycle. The residue was
12)
      attributed to a conoseal leak in 2002. No other indications of boric acid leakage were
Did the licensee perform appropriate follow-on examinations for indications of
      found during this outage.
boric acid leaks from pressure-retaining components above the RPVH?
.3   (Open) Temporary Instruction (TI) 2515/166, Pressurized Water Reactor Containment
Yes. The licensee identified some boric acid residue that was later determined by
      Sump Blockage (NRC Generic Letter 2004-02) - Unit 2
chemical analysis to be older than the recent operating cycle. The residue was
  a. Inspection Scope
attributed to a conoseal leak in 2002. No other indications of boric acid leakage were
      The inspectors verified the Unit 2 implementation of the licensees commitments
found during this outage.
      documented in their September 1, 2005, response to Generic Letter 2004-02, Potential
.3
      Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents
(Open) Temporary Instruction (TI) 2515/166, Pressurized Water Reactor Containment
                                                                                        Enclosure
Sump Blockage (NRC Generic Letter 2004-02) - Unit 2
    a.
Inspection Scope
The inspectors verified the Unit 2 implementation of the licensees commitments
documented in their September 1, 2005, response to Generic Letter 2004-02, Potential
Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents


                                                28
28
      at Pressurized Water Reactors. The commitments included a permanent screen
Enclosure
      assembly modification, a license amendment request to change the UFSAR description
at Pressurized Water Reactors. The commitments included a permanent screen
      of the sump screen analysis methodology, and submittal of a supplemental response to
assembly modification, a license amendment request to change the UFSAR description
      GL 2004-02. This review included the sump screen assembly installation procedure,
of the sump screen analysis methodology, and submittal of a supplemental response to
      screen assembly modification 10 CFR 50.59 evaluation, structural (debris) loading
GL 2004-02. This review included the sump screen assembly installation procedure,
      calculation, and validation testing of the modified sump screen design. The inspectors
screen assembly modification 10 CFR 50.59 evaluation, structural (debris) loading
      also reviewed the foreign materials exclusion controls and the completed Quality
calculation, and validation testing of the modified sump screen design. The inspectors
      Assurance/Quality Control records for the screen assembly installation. The inspectors
also reviewed the foreign materials exclusion controls and the completed Quality
      conducted a visual walkdown to verify the installed screen assembly configuration was
Assurance/Quality Control records for the screen assembly installation. The inspectors
      consistent with drawings and the tested configuration and verified the design criteria for
conducted a visual walkdown to verify the installed screen assembly configuration was
      screen gap.
consistent with drawings and the tested configuration and verified the design criteria for
  b. Findings and Observations
screen gap.  
      No findings of significance were identified.
    b.
      Unit 2 permanent modifications completed at the time of this inspection were
Findings and Observations
      implemented in accordance with Sequoyah Generic Letter 2004-02 response and
No findings of significance were identified.  
      supporting evaluations. The license amendment request to change the UFSAR screen
Unit 2 permanent modifications completed at the time of this inspection were
      analysis methodology description had been submitted and approved. No modifications
implemented in accordance with Sequoyah Generic Letter 2004-02 response and
      were required to address downstream effects. TI 2515/166 will remain open pending
supporting evaluations. The license amendment request to change the UFSAR screen
      completion and NRC review of the licensees GL 2004-02 commitments for Unit 1 which
analysis methodology description had been submitted and approved. No modifications
      are scheduled for the fall 2007.
were required to address downstream effects. TI 2515/166 will remain open pending
.4   (Closed) NRC Temporary Instruction (TI) 2515/169, Mitigating Systems Performance
completion and NRC review of the licensees GL 2004-02 commitments for Unit 1 which
      Index (MSPI) Verification
are scheduled for the fall 2007.  
  a. Inspection Scope
 
      During this inspection period, the inspectors completed a review of the licensees
.4
      implementation of the Mitigating Systems Performance Index (MSPI) guidance for
(Closed) NRC Temporary Instruction (TI) 2515/169, Mitigating Systems Performance
      reporting unavailability and unreliability of monitored safety systems in accordance with
Index (MSPI) Verification  
      TI 2515/169.
    a.
      The inspectors examined surveillances that the licensee determined would not render
Inspection Scope
      the train unavailable for greater than 15 minutes or during which the system could be
During this inspection period, the inspectors completed a review of the licensees
      promptly restored through operator action and therefore, are not included in
implementation of the Mitigating Systems Performance Index (MSPI) guidance for
      unavailability calculations. As part of this review, the recovery actions were verified to
reporting unavailability and unreliability of monitored safety systems in accordance with
      be uncomplicated and contained in written procedures.
TI 2515/169.  
      On a sample basis, the inspectors reviewed operating logs, work history information,
The inspectors examined surveillances that the licensee determined would not render
      maintenance rule information, corrective action program documents, and surveillance
the train unavailable for greater than 15 minutes or during which the system could be
      procedures to determine the actual time periods the MSPI systems were not available
promptly restored through operator action and therefore, are not included in
      due to planned and unplanned activities. The results were then compared to the
unavailability calculations. As part of this review, the recovery actions were verified to
      baseline planned unavailability and actual planned and unplanned unavailability
be uncomplicated and contained in written procedures.
      determined by the licensee to ensure the datas accuracy and completeness. Likewise,
On a sample basis, the inspectors reviewed operating logs, work history information,
      these documents were reviewed to ensure MSPI component unreliability data
maintenance rule information, corrective action program documents, and surveillance
      determined by the licensee identified and properly characterized all failures of monitored
procedures to determine the actual time periods the MSPI systems were not available
      components. The unavailability and unreliability data were then compared with
due to planned and unplanned activities. The results were then compared to the
                                                                                      Enclosure
baseline planned unavailability and actual planned and unplanned unavailability
determined by the licensee to ensure the datas accuracy and completeness. Likewise,
these documents were reviewed to ensure MSPI component unreliability data
determined by the licensee identified and properly characterized all failures of monitored
components. The unavailability and unreliability data were then compared with


                                                29
29
      performance indicator data submitted to the NRC to ensure it accurately reflected the
Enclosure
      performance history of these systems.
performance indicator data submitted to the NRC to ensure it accurately reflected the
  b. Findings and Observations
performance history of these systems.
      No findings of significance were identified. The licensee accurately documented the
    b.
      baseline planned unavailability hours, the actual unavailability hours and the actual
Findings and Observations
      unreliability information for the MSPI systems. No significant errors in the reported data
No findings of significance were identified. The licensee accurately documented the
      were identified, which resulted in a change to the indicated index color. No significant
baseline planned unavailability hours, the actual unavailability hours and the actual
      discrepancies were identified in the MSPI basis document which resulted in: (1) a
unreliability information for the MSPI systems. No significant errors in the reported data
      change to the system boundary, (2) an addition of a monitored component, or (3) a
were identified, which resulted in a change to the indicated index color. No significant
      change in the reported index color.
discrepancies were identified in the MSPI basis document which resulted in: (1) a
.5   Institute of Nuclear Power Operations (INPO) Plant Assessment Report Review
change to the system boundary, (2) an addition of a monitored component, or (3) a
  a. Inspection Scope
change in the reported index color.
      The inspectors reviewed the interim report for the INPO plant assessment report of
.5
      Sequoyah conducted in July 2006. The inspectors reviewed the report to ensure that
Institute of Nuclear Power Operations (INPO) Plant Assessment Report Review
      issues identified were consistent with the NRC perspectives of licensee performance
    a.
      and if any significant safety issues were identified that required further NRC follow-up.
Inspection Scope
  b. Findings
The inspectors reviewed the interim report for the INPO plant assessment report of
      No findings of significance were identified.
Sequoyah conducted in July 2006. The inspectors reviewed the report to ensure that
issues identified were consistent with the NRC perspectives of licensee performance
and if any significant safety issues were identified that required further NRC follow-up.
    b. Findings
No findings of significance were identified.
 
4OA6 Meetings, Including Exit
4OA6 Meetings, Including Exit
.1   Exit Meeting Summary
.1
      On January 3, 2007, the resident inspectors presented the inspection results to
Exit Meeting Summary
      Mr. R. Douet and other members of his staff, who acknowledged the findings. The
On January 3, 2007, the resident inspectors presented the inspection results to
      inspectors asked the licensee whether any of the material examined during the
Mr. R. Douet and other members of his staff, who acknowledged the findings. The
      inspection should be considered proprietary. No proprietary information was identified.
inspectors asked the licensee whether any of the material examined during the
4OA7 Licensee-Identified Violations
inspection should be considered proprietary. No proprietary information was identified.
      The following violation of very low safety significance (Green) was identified by the
4OA7 Licensee-Identified Violations
      licensee and is a violation of NRC requirements which meet the criteria of Section VI of
The following violation of very low safety significance (Green) was identified by the
      the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.
licensee and is a violation of NRC requirements which meet the criteria of Section VI of
      *       TS 6.8.1 requires that written procedures shall be established, implemented, and
the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.
              maintained covering the activities recommended in Appendix A of Regulatory
*
              Guide 1.33, Revision 2, February 1978. Contrary to this, on November 28, 2006,
TS 6.8.1 requires that written procedures shall be established, implemented, and
              an AUO improperly implemented 0-GO-13,Reactor Coolant System Drain and
maintained covering the activities recommended in Appendix A of Regulatory
              Fill Operations, Revision 54, Appendix AC by mispositioning an RCS loop 4 drain
Guide 1.33, Revision 2, February 1978. Contrary to this, on November 28, 2006,
              valve. This revealed itself through the subsequent transfer of RCS inventory to
an AUO improperly implemented 0-GO-13,Reactor Coolant System Drain and
              the Reactor Coolant Drain Tank and lowering of RCS pressurizer level. The
Fill Operations, Revision 54, Appendix AC by mispositioning an RCS loop 4 drain
                                                                                        Enclosure
valve. This revealed itself through the subsequent transfer of RCS inventory to
the Reactor Coolant Drain Tank and lowering of RCS pressurizer level. The


                                          30
30
          error was promptly corrected by operations staff and the event was identified in
Enclosure
          the licensees corrective action program as PER 115534. This finding is of very
error was promptly corrected by operations staff and the event was identified in
          low safety significance because it did not challenge RCS inventory control by
the licensees corrective action program as PER 115534. This finding is of very
          exceeding available makeup capacity.
low safety significance because it did not challenge RCS inventory control by
ATTACHMENT: SUPPLEMENTAL INFORMATION
exceeding available makeup capacity.
                                                                                Enclosure
ATTACHMENT: SUPPLEMENTAL INFORMATION


                                  SUPPLEMENTAL INFORMATION
Attachment
                                    KEY POINTS OF CONTACT
SUPPLEMENTAL INFORMATION
Licensee personnel
KEY POINTS OF CONTACT
Licensee personnel    
J. Adams, Boric Acid
J. Adams, Boric Acid
D. Bodine, Chemistry/Environmental Manager
D. Bodine, Chemistry/Environmental Manager
Line 1,383: Line 1,718:
R. Bernhard, Region II, Senior Reactor Analyst
R. Bernhard, Region II, Senior Reactor Analyst
D. Pickett, Project Manager, Office of Nuclear Reactor Regulation
D. Pickett, Project Manager, Office of Nuclear Reactor Regulation
                      LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened and Closed
Opened and Closed
05000327,328/2006005-01               NCV         Failure to Certify Qualifications and Status
05000327,328/2006005-01
                                                  of Licensed Operators Were Current and
NCV
                                                  Valid (Section 1R11.3)
Failure to Certify Qualifications and Status
of Licensed Operators Were Current and
Valid (Section 1R11.3)
Opened
Opened
05000328/2006005-02                   URI         Appendix R Manual Isolation Valve Failure
05000328/2006005-02
                                                  to Close Within the Required Time text
URI
                                                  (Section 1R15)
Appendix R Manual Isolation Valve Failure
to Close Within the Required Time text
(Section 1R15)
Closed
Closed
05000327,328/2515/169                   TI         Mitigating Systems Performance Index
05000327,328/2515/169
                                                  Verification (Section 4OA5.4)
TI
                                                                                      Attachment
Mitigating Systems Performance Index
Verification (Section 4OA5.4)


                          A-2
A-2
Attachment
Discussed
Discussed
05000327, 328/2515/150 TI     Reactor Pressure Vessel Head and Vessel
05000327, 328/2515/150
                              Head Penetration Nozzles (NRC Order EA-
TI
                              03-009) - Unit 2 (Section 4OA5.2)
Reactor Pressure Vessel Head and Vessel
05000327, 328/2515/166 TI     Pressurized Water Reactor Containment
Head Penetration Nozzles (NRC Order EA-
                              Sump Blockage (NRC Generic Letter 2004-
03-009) - Unit 2 (Section 4OA5.2)
                              02) - Unit 2 Section 4OA5.3)
05000327, 328/2515/166  
                                                              Attachment
TI
Pressurized Water Reactor Containment
Sump Blockage (NRC Generic Letter 2004-
02) - Unit 2 Section 4OA5.3)


                              LIST OF DOCUMENTS REVIEWED
Attachment
LIST OF DOCUMENTS REVIEWED
Section 1R01: Adverse Weather Protection
Section 1R01: Adverse Weather Protection
SPP-10.14, Freeze Protection, Revision 0
SPP-10.14, Freeze Protection, Revision 0
M&AI-27, Freeze Protection, Revision 12
M&AI-27, Freeze Protection, Revision 12
0-PI-OPS-000-006.0, Freeze Protection, Revision 45
0-PI-OPS-000-006.0, Freeze Protection, Revision 45
1-PI-EFT-234-706.0, Freeze Protection Heat Trace Functional Test, Revision 30
1-PI-EFT-234-706.0, Freeze Protection Heat Trace Functional Test, Revision 30  
Section 1R02: Evaluation of Changes, Tests, or Experiments
Section 1R02: Evaluation of Changes, Tests, or Experiments
Full Evaluations:
Full Evaluations:
Line 1,419: Line 1,764:
DCN D21854A, DG Starting Air PCV Modification.
DCN D21854A, DG Starting Air PCV Modification.
DCN D21247A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C
DCN D21247A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C
Condensing Units With Digital Controls.
Condensing Units With Digital Controls.  
DCN D21248A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C
DCN D21248A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C
Condensing Units with Digital Controls.
Condensing Units with Digital Controls.
FSAR Section 15.2.10, Revision to Section 15.2.10 of the FSAR containing the transient
FSAR Section 15.2.10, Revision to Section 15.2.10 of the FSAR containing the transient
analysis for feed water malfunction event.
analysis for feed water malfunction event.
TACF 1-05-013-R1, Temporary configuration change involving installation of non-nuclear safety
TACF 1-05-013-R1, Temporary configuration change involving installation of non-nuclear safety
low volume high pressure pump into the SI System.
low volume high pressure pump into the SI System.  
TACF 1-05-002-063, R1, Temporary installation of TVA Class B piping/tubing and check valve
TACF 1-05-002-063, R1, Temporary installation of TVA Class B piping/tubing and check valve
downstream of 1-VLV-63-834 to provide RHRS pressure relief leakage.
downstream of 1-VLV-63-834 to provide RHRS pressure relief leakage.
FSAR Section 10.4.7 and 10.4.8, Proposed FSAR change to allow Steam Generator Blowdown
FSAR Section 10.4.7 and 10.4.8, Proposed FSAR change to allow Steam Generator Blowdown
to remain in service for various reasons.
to remain in service for various reasons.
ES-1.3, R12, Revised ES-1.3 to modify guidance on stopping and restarting SI pump (PER 04-
ES-1.3, R12, Revised ES-1.3 to modify guidance on stopping and restarting SI pump (PER 04-
000344-000).
000344-000).  
Screened Out Items:
Screened Out Items:
1-SI-OPS-000-003.M R32, Add Glycol Valves In Accordance With 06-NSS-061-035.
1-SI-OPS-000-003.M R32, Add Glycol Valves In Accordance With 06-NSS-061-035.
TI-28 REV 198, Procedure Revision On Unit 1 NIS Power Range Calibration Data
TI-28 REV 198, Procedure Revision On Unit 1 NIS Power Range Calibration Data  
0-SI-OPS-068-137.0, Added Precaution And Limitation G To Section 3.2.
0-SI-OPS-068-137.0, Added Precaution And Limitation G To Section 3.2.
0-SO-14-4 Rev 10, Added Section 8.5 To Provide Instructions For Manual Operation Of
0-SO-14-4 Rev 10, Added Section 8.5 To Provide Instructions For Manual Operation Of
Line 1,440: Line 1,785:
0-SO-77-11 R15, Revised To Add A Precaution To Monitor Waste Gas Vent Header
0-SO-77-11 R15, Revised To Add A Precaution To Monitor Waste Gas Vent Header
Frequently.
Frequently.
1-SO-63-1, Rev. 45, Revised section 8.1 step 6 of procedure to make the step conditional.
1-SO-63-1, Rev. 45, Revised section 8.1 step 6 of procedure to make the step conditional.
2-SI-OPS-000-003.M, Rev. 26, Added note 5 to exempt monthly valve stroke of the glycol valve
2-SI-OPS-000-003.M, Rev. 26, Added note 5 to exempt monthly valve stroke of the glycol valve
when the valve was stroked in the previous 7 days.
when the valve was stroked in the previous 7 days.  
0-GO-14-4, R12, Revised to incorporate changes in accordance with NB 060785.
0-GO-14-4, R12, Revised to incorporate changes in accordance with NB 060785.
0-GO-5, Rev. 47, Revised step in section 5.4 concerning control rods, ref. NB 060297; added
0-GO-5, Rev. 47, Revised step in section 5.4 concerning control rods, ref. NB 060297; added
step to section 5.1 concerning MFPT master controller output, ref. PER 100196-03.
step to section 5.1 concerning MFPT master controller output, ref. PER 100196-03.
1-AR-M1-A, Rev. 38, Revised in response to 060738 which provided additional information
1-AR-M1-A, Rev. 38, Revised in response to 060738 which provided additional information
regarding the inputs for Window A-5.
regarding the inputs for Window A-5.
DCN D20960A, Sequoyah Independent Spent Fuel Storage Installation, (ISFSI).
DCN D20960A, Sequoyah Independent Spent Fuel Storage Installation, (ISFSI).
0-SO-30-10, R31, Revised section 8.15 to provide guidance for Auxiliary Building Chill Water
0-SO-30-10, R31, Revised section 8.15 to provide guidance for Auxiliary Building Chill Water
Feed and Bleed when system is set up for winter operation.
Feed and Bleed when system is set up for winter operation.
                                                                                  Attachment


                                                  A-4
A-4
Attachment
2-SI-TDC-068-254, Rev. 5, Surveillance instruction is being changed from 18 months to
2-SI-TDC-068-254, Rev. 5, Surveillance instruction is being changed from 18 months to
conditional.
conditional.  
0-SO-70-1, R34, Added a step and caution to sections 8.5.2 and 8.5.4 to initiate a Work Order
0-SO-70-1, R34, Added a step and caution to sections 8.5.2 and 8.5.4 to initiate a Work Order
to backfill affected flow transmitter following restoration of CCCS HX. 0B1 or 0B2 after
to backfill affected flow transmitter following restoration of CCCS HX. 0B1 or 0B2 after
maintenance.
maintenance.
0-SO-77-1, Rev.40, Revised to provide guidance on the transfer of the Laundry and Hot
0-SO-77-1, Rev.40, Revised to provide guidance on the transfer of the Laundry and Hot
Shower Tank to the CDCT; moved guidance on re-circulation of the CDCT to new appendix E.
Shower Tank to the CDCT; moved guidance on re-circulation of the CDCT to new appendix E.  
1-SI-OPS-000-003.M, R33, Revise note 18 in Appendix A of surveillance instruction to show
1-SI-OPS-000-003.M, R33, Revise note 18 in Appendix A of surveillance instruction to show
allowable channel deviation of less than or equal to 5%.
allowable channel deviation of less than or equal to 5%.
Problem Evaluation Reports (PERs):
Problem Evaluation Reports (PERs):
84897, 0-PI-ECC-313-595.0 Cannot Be Performed As Currently Written
84897, 0-PI-ECC-313-595.0 Cannot Be Performed As Currently Written
Line 1,472: Line 1,817:
76900, S/G Blowdown Isolation of AFWP Start.
76900, S/G Blowdown Isolation of AFWP Start.
20195, ES 1.3, Transfer to RHR Containment Sump requires stopping the SI Pumps if RCS
20195, ES 1.3, Transfer to RHR Containment Sump requires stopping the SI Pumps if RCS
pressure is greater than 1500 psig.
pressure is greater than 1500 psig.  
Work Orders:
Work Orders:
6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE
6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE  
6-771384-000, Replace the Oil Cooler TCV for the B MCR Chiller
6-771384-000, Replace the Oil Cooler TCV for the B MCR Chiller
Procedures:
Procedures:
Line 1,485: Line 1,830:
0-PI-ECC-313-595.0, Rev. 4, Periodic Calibration of Auxiliary Building Heating, Ventilating and
0-PI-ECC-313-595.0, Rev. 4, Periodic Calibration of Auxiliary Building Heating, Ventilating and
Air Conditioning
Air Conditioning
SPP - 9.4, 10 CFR 50.59 Evaluations of Changes, Tests and Experiments, Revision 7.
SPP - 9.4, 10 CFR 50.59 Evaluations of Changes, Tests and Experiments, Revision 7.  
EN-1-102, 10 CFR 50.59 / 10 CFR 72.48, Reviews, Revision 7.
EN-1-102, 10 CFR 50.59 / 10 CFR 72.48, Reviews, Revision 7.
Miscellaneous Documents:
Miscellaneous Documents:
PMTI-SQN-21854, DG 1A-A Starting Air 5 Start Capacity Verification
PMTI-SQN-21854, DG 1A-A Starting Air 5 Start Capacity Verification
SSD 1- L - 68-325, Low RCS Pressurizer Level
SSD 1- L - 68-325, Low RCS Pressurizer Level  
SSD 1 L - 68-326, High RCS Pressurizer Level.
SSD 1 L - 68-326, High RCS Pressurizer Level.
SSD 2 -L -68-325, Low RCS Pressurizer Level
SSD 2 -L -68-325, Low RCS Pressurizer Level  
SSD 2- L - 68-326, High RCS Pressurizer Level.
SSD 2- L - 68-326, High RCS Pressurizer Level.
NEI 96-07, Nuclear Energy Institute, Guidelines for 10 CFR 50.59 Implementation, Revision 1.
NEI 96-07, Nuclear Energy Institute, Guidelines for 10 CFR 50.59 Implementation, Revision 1.
Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59 Changes, Tests and
Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59 Changes, Tests and
Experiments, November 2000.
Experiments, November 2000.
                                                                                      Attachment


                                              A-5
A-5
Attachment
Section 1R04: Equipment Alignment
Section 1R04: Equipment Alignment
1,2-47W810-1, Flow Diagram - Residual Heat Removal System, Revision 47
1,2-47W810-1, Flow Diagram - Residual Heat Removal System, Revision 47
Line 1,504: Line 1,849:
Section 1R05: Fire Protection
Section 1R05: Fire Protection
SQN Drawing 1,2-47W494-6 Fire Protection Compartmentation-Fire Cells Plan El. 669' & 685'
SQN Drawing 1,2-47W494-6 Fire Protection Compartmentation-Fire Cells Plan El. 669' & 685'
SQN Fire Protection Report Part II - Fire Protection Plan, Revision 20
SQN Fire Protection Report Part II - Fire Protection Plan, Revision 20  
SQN-26-D054/EPM-ABB-IMPFHA, SQN Fire Hazards Analysis Calculation, Appendix A
SQN-26-D054/EPM-ABB-IMPFHA, SQN Fire Hazards Analysis Calculation, Appendix A
Spp-10.10, Control of Transient Combustibles, Revision 4
Spp-10.10, Control of Transient Combustibles, Revision 4
Line 1,512: Line 1,857:
1995
1995
1,2-47W812-1, Flow Diagram Containment Spray System, Revision 42
1,2-47W812-1, Flow Diagram Containment Spray System, Revision 42
Section 1R08: Inservice Inspection Activities
Section 1R08: Inservice Inspection Activities  
Programs/Procedures/Reports
Programs/Procedures/Reports
2-SI-SXI-068-114.3, Steam Generator Tubing Inservice Inspection and Augmented Inspections,
2-SI-SXI-068-114.3, Steam Generator Tubing Inservice Inspection and Augmented Inspections,
Line 1,529: Line 1,874:
Proc. No. N-UT-64, Rev. 9, Generic Procedure For The UT Examination of Austenitic Pipe
Proc. No. N-UT-64, Rev. 9, Generic Procedure For The UT Examination of Austenitic Pipe
Welds
Welds
Proc. No. N-VT-1, Visual Examination Procedure for ASME Section XI Preservice and Inservice
Proc. No. N-VT-1, Visual Examination Procedure for ASME Section XI Preservice and Inservice  
Proc. No. N-VT-15, Rev. 5, Visual Examination of Class MC and Metallic Liners of Class CC
Proc. No. N-VT-15, Rev. 5, Visual Examination of Class MC and Metallic Liners of Class CC
Components of Light-Water Cooled Plants
Components of Light-Water Cooled Plants
Line 1,537: Line 1,882:
Vendor Instruction 0-VI-MOD-068-001
Vendor Instruction 0-VI-MOD-068-001
Welding Services Traveler 103804-001
Welding Services Traveler 103804-001
                                                                                    Attachment


                                              A-6
A-6
Attachment
Corrective Action (PERS)
Corrective Action (PERS)
03-017128-000, NRC inspectors concern that a GAP between the support steel and the pipe
03-017128-000, NRC inspectors concern that a GAP between the support steel and the pipe
Line 1,581: Line 1,926:
JPM 6 Perform Boration of the RCS From Outside the Main Control Room.
JPM 6 Perform Boration of the RCS From Outside the Main Control Room.
JPM 78 AP Respond to an ATWS Trip the Reactor Locally.
JPM 78 AP Respond to an ATWS Trip the Reactor Locally.
                                                                                Attachment


                                              A-7
A-7
Attachment
Simulator Scenarios:
Simulator Scenarios:
S-13 Uncontrolled Depressurization of All Steam Generators. Rev 12.
S-13 Uncontrolled Depressurization of All Steam Generators. Rev 12.
Line 1,594: Line 1,939:
FW20
FW20
ED08
ED08
ED10
ED10  
Transient Tests:
Transient Tests:
#2 Both Main Feedwater Pumps Trip , AFW fails to start.
#2 Both Main Feedwater Pumps Trip , AFW fails to start.
Line 1,622: Line 1,967:
B87 951205 003, ERCW Screen Wash System Hydraulic Analysis, Revisions 2 and 3
B87 951205 003, ERCW Screen Wash System Hydraulic Analysis, Revisions 2 and 3
0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test, Revision 8
0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test, Revision 8
                                                                                  Attachment


                                              A-8
A-8
Attachment
0-SO-67-1, Essential Raw Cooling Water, Revision 63
0-SO-67-1, Essential Raw Cooling Water, Revision 63
1,2-45N765-1, Wiring Diagram 6900V Shutdown Aux Power Schematic Diagram SH-1,
1,2-45N765-1, Wiring Diagram 6900V Shutdown Aux Power Schematic Diagram SH-1,
Line 1,638: Line 1,983:
31739, Westinghouse Advisory Letter NASL-02-3 Describes A Process Measurement Uncertain
31739, Westinghouse Advisory Letter NASL-02-3 Describes A Process Measurement Uncertain
65752, Specified Post Maintenance Testing Deficiencies
65752, Specified Post Maintenance Testing Deficiencies
84070, Diesel Generator 1A-A cable testing.
84070, Diesel Generator 1A-A cable testing.
103766, Main Bank Transformer 1B Hot Spots
103766, Main Bank Transformer 1B Hot Spots
104337, Main Bank Transformer 1B Hot Spot
104337, Main Bank Transformer 1B Hot Spot
Calculations:
Calculations:
Calculation No. SQN- APS - 042, 480 V Turbine Building Common Board Load Coordination,
Calculation No. SQN- APS - 042, 480 V Turbine Building Common Board Load Coordination,
Short Circuit, Circuit Protection and Voltage Drop Analysis, Revision 4.
Short Circuit, Circuit Protection and Voltage Drop Analysis, Revision 4.
Calculation No. SQN-APS-041, 480 VAC Unit Board Load Coordination Study, Revision 4.
Calculation No. SQN-APS-041, 480 VAC Unit Board Load Coordination Study, Revision 4.
Work Orders:
Work Orders:
6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE
6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE  
2-002298-000, Westinghouse Advisory Letter NSAL-02-3
2-002298-000, Westinghouse Advisory Letter NSAL-02-3
03-012340-001, Replace degraded portion of 6900 V Diesel Generator 1A-A power cable
03-012340-001, Replace degraded portion of 6900 V Diesel Generator 1A-A power cable
PP351A between Unit 1 Additional Equip. Bldg. And D/G exciter cubicle.
PP351A between Unit 1 Additional Equip. Bldg. And D/G exciter cubicle.  
03-012340-002, Install section of new replacement cable PP351A from AEB-1 to MH-14 via
03-012340-002, Install section of new replacement cable PP351A from AEB-1 to MH-14 via
existing conduit.
existing conduit.
Miscellaneous Documents:
Miscellaneous Documents:
Westinghouse Advisory Letter NSAL-03-9
Westinghouse Advisory Letter NSAL-03-9
ABB Power T&D- Sequoyah Nuclear Plant Final Report Main Generator Transformer Life
ABB Power T&D- Sequoyah Nuclear Plant Final Report Main Generator Transformer Life
Assessment.
Assessment.
Drawings:
Drawings:
Drawing No. 1, 2-3591A28, Breaker Setting Sheet 480 V Unit Board 1A, Revision 5
Drawing No. 1, 2-3591A28, Breaker Setting Sheet 480 V Unit Board 1A, Revision 5
Line 1,666: Line 2,011:
Revision 16.
Revision 16.
Drawing No. 1-45N1504, Wiring Diagrams - Main Single Line 500 KV Switchyard, Revision 29
Drawing No. 1-45N1504, Wiring Diagrams - Main Single Line 500 KV Switchyard, Revision 29
                                                                                Attachment


                                            A-9
A-9
Attachment
Drawing No. 1-45W1541, Wiring Diagrams AC Schematic Unit 1 Generator & transformer
Drawing No. 1-45W1541, Wiring Diagrams AC Schematic Unit 1 Generator & transformer
Circuits, Revision 14
Circuits, Revision 14
Line 1,674: Line 2,019:
TI-28, Rev. 198, Curve Book
TI-28, Rev. 198, Curve Book
PER Written Because of Inspection Finding
PER Written Because of Inspection Finding
114743, Superseded ARP revision found in ACR
114743, Superseded ARP revision found in ACR  
Section 1R19: Post Maintenance Testing
Section 1R19: Post Maintenance Testing
PER 115780, 2-FCV-74-28 Did Not Appear To Fully Open
PER 115780, 2-FCV-74-28 Did Not Appear To Fully Open
Line 1,691: Line 2,036:
Section 1R22: Surveillance Testing
Section 1R22: Surveillance Testing
SPP-8.1 Conduct of Testing, Rev 4
SPP-8.1 Conduct of Testing, Rev 4
Section 1EP6: Drill Evaluation
 
Section 1EP6: Drill Evaluation
NEI 99-02 Rev 0, March 2000
NEI 99-02 Rev 0, March 2000
Emergency Plan Implementing Procedure (EPIP) - 1, Emergency Plan Classification Matrix,
Emergency Plan Implementing Procedure (EPIP) - 1, Emergency Plan Classification Matrix,
Line 1,700: Line 2,046:
EPIP-6, Technical Support Center, Rev 41
EPIP-6, Technical Support Center, Rev 41
EPIP-7, Operations Support Center, Rev 25
EPIP-7, Operations Support Center, Rev 25
Section 2OS1: Access Control To Radiologically Significant Areas
Section 2OS1: Access Control To Radiologically Significant Areas
Procedures, Instructions, Guidance Documents, and Operating Manuals
Procedures, Instructions, Guidance Documents, and Operating Manuals
ANSI/ANS 3.1-1987, Selection, Qualification, and Training of Personnel for Nuclear Power
ANSI/ANS 3.1-1987, Selection, Qualification, and Training of Personnel for Nuclear Power
Plants
Plants
Tennessee Valley Authority (TVA), TVA Nuclear (TVAN), Standard Programs and
Tennessee Valley Authority (TVA), TVA Nuclear (TVAN), Standard Programs and
                                                                                  Attachment


                                                A-10
A-10
Attachment
Processes (SPP) - 3.1, Corrective Action Program, Rev. 11
Processes (SPP) - 3.1, Corrective Action Program, Rev. 11
Active Radiation Work Permits (RWPs) List, dated 12/11/2006
Active Radiation Work Permits (RWPs) List, dated 12/11/2006
RP Personnel Identification by Craft Report, dated 12/14/2006
RP Personnel Identification by Craft Report, dated 12/14/2006
Task Qualification List (selected individuals), dated December 14, 2006
Task Qualification List (selected individuals), dated December 14, 2006
LHRA Key Control Log Sheets (several pages)
LHRA Key Control Log Sheets (several pages)  
TVA, TVAN, TRN-20, Health Physics Technician Training, Rev. 13
TVA, TVAN, TRN-20, Health Physics Technician Training, Rev. 13
High Radiation Areas at Sequoyah List, document not dated
High Radiation Areas at Sequoyah List, document not dated
Line 1,753: Line 2,099:
PER 82027, High Radiation Readings on Valve
PER 82027, High Radiation Readings on Valve
PER 82643, Unexpected Radiation Level Change
PER 82643, Unexpected Radiation Level Change
                                                                                  Attachment


                                              A-11
A-11
Attachment
PER 84532, VHRA Key Inventory
PER 84532, VHRA Key Inventory
PER 99226, Locked High Radiation Door Locks Sticking
PER 99226, Locked High Radiation Door Locks Sticking
Line 1,789: Line 2,135:
Records/Reports/Engineering Documents
Records/Reports/Engineering Documents
Equipment Certification Records for the following NDE Equipment:
Equipment Certification Records for the following NDE Equipment:
        Blade Probes: S1035 NL, S5002 NL, and S5001 NL
Blade Probes: S1035 NL, S5002 NL, and S5001 NL
        Ultrasonic Transducers: 21GB-06001 and 2078-06001
Ultrasonic Transducers: 21GB-06001 and 2078-06001
Engineering Information Record 51-9027415-000, RPV Head Penetration Inspection Plan and
Engineering Information Record 51-9027415-000, RPV Head Penetration Inspection Plan and
Coverage Assessment for Sequoyah Units 1 and 2
Coverage Assessment for Sequoyah Units 1 and 2
Line 1,796: Line 2,142:
Analysis
Analysis
Letter L44 030227 801, Response to issuance of NRC Order
Letter L44 030227 801, Response to issuance of NRC Order
                                                                                Attachment


                                            A-12
A-12
Attachment
Corrective Action Documents
Corrective Action Documents
PER 115561, Evidence of leakage during canopy seal weld inspection
PER 115561, Evidence of leakage during canopy seal weld inspection
Line 1,804: Line 2,150:
PER 116165*, Transducer frequencies documented incorrectly
PER 116165*, Transducer frequencies documented incorrectly
*Problem Evaluation Reports generated as a result of this inspection
*Problem Evaluation Reports generated as a result of this inspection
Section 4OA5: Other Activities - TI 2515/166
Section 4OA5: Other Activities - TI 2515/166  
Surveillance Instruction 2-SI-SIN-063-009-02, Containment Sump Inspection, dated 11/08/06
Surveillance Instruction 2-SI-SIN-063-009-02, Containment Sump Inspection, dated 11/08/06
DCN 22023, Modify Containment Sump Screens as required by NEI Methodology, dated
DCN 22023, Modify Containment Sump Screens as required by NEI Methodology, dated
Line 1,830: Line 2,176:
Routine Work Order 06-774811-000, "Containment RHR Sump 48N919", Rev 5
Routine Work Order 06-774811-000, "Containment RHR Sump 48N919", Rev 5
FME Accountability Log, SPP 6.5.1
FME Accountability Log, SPP 6.5.1
Section 4OA5: Other Activities - TI 2515/169
Section 4OA5: Other Activities - TI 2515/169
Procedures, Manuals, and Guidance Documents
Procedures, Manuals, and Guidance Documents
NEI 99-02, Mitigating System Performance Index (MSPI) Basis Document, Revision 1
NEI 99-02, Mitigating System Performance Index (MSPI) Basis Document, Revision 1
Selected System Status Reports
Selected System Status Reports  
0-SI-SXV-063-266.0, ASME Section XI Valve Testing
0-SI-SXV-063-266.0, ASME Section XI Valve Testing
1,2-SI-SXV-000-201.0, Full Stroking of Category A and B Valves During Operation
1,2-SI-SXV-000-201.0, Full Stroking of Category A and B Valves During Operation
Line 1,842: Line 2,188:
0-SI-SXV-000-221.0, Full Stroking of the Common ERCW and CCS Category A and B
0-SI-SXV-000-221.0, Full Stroking of the Common ERCW and CCS Category A and B
Valves During Operation
Valves During Operation
                                                                                  Attachment


                                            A-13
A-13
Attachment
0-SI-OPS-067-682.Q, ERCW Non-Safety Related Flow Balance Valve Position Verification
0-SI-OPS-067-682.Q, ERCW Non-Safety Related Flow Balance Valve Position Verification
0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test
0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test
Line 1,850: Line 2,196:
Records and Data
Records and Data
Selected Control Room Logs, January 2004 through December 2006
Selected Control Room Logs, January 2004 through December 2006
EDG NRC Performance Indicators, 2002 - 2005
EDG NRC Performance Indicators, 2002 - 2005  
AFW NRC Performance Indicators, 2002 - 2005
AFW NRC Performance Indicators, 2002 - 2005  
HPSI NRC Performance Indicators, 2002 - 2005
HPSI NRC Performance Indicators, 2002 - 2005  
RHR NRC Performance Indicators, 2002 - 2005
RHR NRC Performance Indicators, 2002 - 2005  
Consolidated Data Entry MSPI Derivation Reports Generated November 2006
Consolidated Data Entry MSPI Derivation Reports Generated November 2006
MSPI Equipment Functional Failure Data Sheets
MSPI Equipment Functional Failure Data Sheets
Line 1,860: Line 2,206:
Corrective Action Program Documents
Corrective Action Program Documents
Selected Corrective Action Reports, 2005-2006
Selected Corrective Action Reports, 2005-2006
                                                                                Attachment


                              LIST OF ACRONYMS
Attachment
AFW   auxiliary feedwater
LIST OF ACRONYMS  
ANSI American National Standards Institute
AFW
AOP   abnormal operating procedures
auxiliary feedwater
ARC   alternate repair criteria
ANSI
ASME American Society of Mechanical Engineers
American National Standards Institute
ATWS anticipated transient without scram
AOP
AUO   auxiliary unit operator
abnormal operating procedures
BACC boric acid corrosion control
ARC
BMV   bare metal visual
alternate repair criteria
CCP   cooling charging pump
ASME
CCPIT cooling charging pump injection tank
American Society of Mechanical Engineers
CFR   Code of Federal Regulations
ATWS
CR   condition report
anticipated transient without scram
CRDM control rod drive mechanism
AUO
CVCS chemical volume control system
auxiliary unit operator
DCN   design change notice
BACC
ECCS emergency core cooling system
boric acid corrosion control
ECT   eddy current testing
BMV
EDY   effective degradation years
bare metal visual
ERCW essential raw cooling water
CCP
ETSS examination technique specifications sheet
cooling charging pump
FCV   flow control valve
CCPIT
FE   functional evaluation
cooling charging pump injection tank
FME   foreign material exclusion
CFR
FOSAR foreign object search and recovery
Code of Federal Regulations
HR   high radiation
CR
HUT   holdup tank
condition report
INPO Institute of Nuclear power Operations
CRDM
ISFSI independent spent fuel storage installation
control rod drive mechanism
ISI   inservice inspection
CVCS
LHRA locked high radiation area
chemical volume control system
MRP   materials reliability program
DCN
MSPI mitigating systems performance index
design change notice
NCV   non-cited violation
ECCS
NDE   non-destructive examination
emergency core cooling system
NRC   U.S. Nuclear Regulatory Commission
ECT
ODSCC outer diameter stress corrosion cracking
eddy current testing
OPDP operations department procedure
EDY
PAR   publically available records
effective degradation years
PER   problem evaluation report
ERCW
PER   protective action recommendation
essential raw cooling water
PORV power-operated relief valve
ETSS
PWSCC primary water stress corrosion cracking
examination technique specifications sheet
RCP   reactor coolant pump
FCV
RCS   reactor coolant system
flow control valve
RHR   residual heat removal
FE
RP   radiation protection
functional evaluation
                                                  Attachment
FME
foreign material exclusion
FOSAR
foreign object search and recovery
HR
high radiation
HUT
holdup tank
INPO
Institute of Nuclear power Operations
ISFSI
independent spent fuel storage installation
ISI
inservice inspection
LHRA
locked high radiation area
MRP
materials reliability program
MSPI
mitigating systems performance index
NCV
non-cited violation
NDE
non-destructive examination
NRC
U.S. Nuclear Regulatory Commission
ODSCC
outer diameter stress corrosion cracking
OPDP
operations department procedure
PAR
publically available records
PER
problem evaluation report
PER
protective action recommendation
PORV
power-operated relief valve
PWSCC
primary water stress corrosion cracking
RCP
reactor coolant pump
RCS
reactor coolant system
RHR
residual heat removal
RP
radiation protection


                                      A-15
A-15
RPVH reactor pressure vessel head
Attachment
RTP   rated thermal power
RPVH
RWP   radiation work permit
reactor pressure vessel head
RWST refueling water storage tank
RTP
SDP   significance determination process
rated thermal power
SER   safety evaluation report
RWP
SG   steam generator
radiation work permit
SI   safety injection
RWST
SI   surveillance instructions
refueling water storage tank
SSC   structure, system, or component
SDP
TDAFP turbine driven auxiliary feedwater pump
significance determination process
TI   temporary instruction
SER
TS   technical specification
safety evaluation report
TVA   Tennessee Valley Authority
SG
UFSAR updated final safety analysis report
steam generator
UHI   upper head injection
SI
URI   unresolved item
safety injection
UT   ultrasonic testing
SI
WOs   work orders
surveillance instructions
                                              Attachment
SSC
structure, system, or component
TDAFP
turbine driven auxiliary feedwater pump
TI
temporary instruction
TS
technical specification
TVA
Tennessee Valley Authority
UFSAR
updated final safety analysis report
UHI
upper head injection
URI
unresolved item
UT
ultrasonic testing
WOs
work orders
}}
}}

Latest revision as of 03:38, 15 January 2025

(Superceded-see ML070720224) IR 05000327-06-005, IR 05000328-06-005; IR 07200034-06-002; 10/01/06 - 12/31/06; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification Program
ML070300881
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 01/30/2007
From: Widmann M
Reactor Projects Region 2 Branch 6
To: Singer K
Tennessee Valley Authority
References
IR-06-002, IR-06-005
Download: ML070300881 (51)


See also: IR 05000327/2006005

Text

January 30, 2007

Tennessee Valley Authority

ATTN: Mr. Karl W. Singer

Chief Nuclear Officer and

Executive Vice President

6A Lookout Place

1101 Market Street

Chattanooga, TN 37402-2801

SUBJECT:

SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT

05000327/2006005, 05000328/2006005 AND 07200034/2006002

Dear Mr. Singer:

On December 31, 2006, the United States Nuclear Regulatory Commission (NRC) completed

an inspection at your Sequoyah Nuclear Plant, Units 1 and 2. The enclosed integrated

inspection report documents the inspection results, which were discussed on January 3, 2007,

with Mr. R. Duet and other members of your staff.

The inspection examined activities conducted under your licenses as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your

licenses. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel.

The report documents one NRC-identified finding of very low safety significance. This finding

was determined to involve a violation of NRC requirements. Additionally, a licensee-identified

violation which was determined to be of very low safety significance is listed in this report.

However, because of their very low safety significance and because they are entered into your

corrective action program, the NRC is treating these findings as non-cited violations (NCVs)

consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest any NCV in this

report, you should provide a response within 30 days of the date of this inspection report, with

the basis for your denial, to the United States Nuclear Regulatory Commission, ATTN.:

Document Control Desk, Washington, D.C. 20555-0001; with copies to the Regional

Administrator Region II; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Sequoyah

Nuclear Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publically Available Records (PARS) component of

2

NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Malcolm T. Widmann, Chief

Reactor Projects Branch 6

Division of Reactor Projects

Docket Nos.: 50-327, 50-328,72-034

License Nos.: DPR-77, DPR-79

Enclosure: Inspection Report 05000327/2006005 and 05000328/2006005 and

07200034/2006002 w/Attachment: Supplemental Information

cc: w/encl: (See page 3)

____ML070300881 __

OFFICE

RII:DRP

RII:DRP

RII:DRP

RII:DRP

RII:DRS

RII:DRS

RII:DRS

SIGNATURE

LXG /RA/

WTM /RA/

JBB via email

MES via email

JXD /RA/

FJE /RA/

LFL /RA/

NAME

LGarner

MWidmann

JBaptist

MSpeck

JDiaz-Velez

FEhrhardt

LLake

DATE

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

OFFICE

RII:DRS

RII:DRS

RII:DRS

RII:DRS

RII:DRS

RII:DRS

RII:DRS

SIGNATURE

GWL /RA/

DLM /RA/

ECM /RA/

BWM /RA/

CRO for

SDR /RA/

CRO for

NAME

GLaska

DMasPenaranda EMichel

BMiller

RMoore

SRose

CSmith

DATE

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

01/30/2007

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

OFFICE

RII:DRS

SIGNATURE

CRS /RA/

NAME

CStancil

DATE

01/30/2007

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

3

cc w/encls:

Ashok S. Bhatnagar

Senior Vice President

Nuclear Operations

Tennessee Valley Authority

Electronic Mail Distribution

Preston D. Swafford

Senior Vice President

Nuclear Support

Tennessee Valley Authority

Electronic Mail Distribution

Larry S. Bryant, Vice President

Nuclear Engineering &

Technical Services

Tennessee Valley Authority

Electronic Mail Distribution

Randy Douet

Site Vice President

Sequoyah Nuclear Plant

Electronic Mail Distribution

General Counsel

Tennessee Valley Authority

Electronic Mail Distribution

John C. Fornicola, General Manager

Nuclear Assurance

Tennessee Valley Authority

Electronic Mail Distribution

Glenn W. Morris, Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Beth A. Wetzel, Manager

Corporate Nuclear Licensing and

Industry Affairs

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

Robert H. Bryan, Jr., General Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

David A. Kulisek, Plant Manager

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Lawrence E. Nanney, Director

TN Dept. of Environment & Conservation

Division of Radiological Health

Electronic Mail Distribution

County Mayor

Hamilton County Courthouse

Chattanooga, TN 37402-2801

Ann Harris

341 Swing Loop

Rockwood, TN 37854

James H. Bassham, Director

Tennessee Emergency Management

Agency

Electronic Mail Distribution

Distribution w/encl: (See page 4)

4

Letter to Karl W. Singer from Malcolm T. Widmann dated January 30, 2007

SUBJECT:

SEQUOYAH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT

05000327/2006005, 05000328/2006005 AND 07200034/2006002

Distribution w/encl:

Bob Pascarelli, NRR

D. Pickett, NRR

C. Evans, RII

L. Slack, RII EICS

OE Mail

RIDSNRRDIRS

PUBLIC

TABLE OF CONTENTS

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

1R01

Adverse Weather Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R02

Evaluations of Changes, Tests or Experiments . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R04

Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R05

Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R07

Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1R08

Inservice Inspection (ISI) Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

1R11

Licensed Operator Requalification Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1R12

Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

1R13

Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . 12

1R15

Operability Evaluations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

1R17

Permanent Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

1R19

Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

1R20

Refueling and Other Outage Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

1R22

Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

1EP6

Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

RADIATION SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

2OS1 Access Control To Radiologically Significant Areas . . . . . . . . . . . . . . . . . . . . . 20

OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA2 Identification & Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

4OA6 Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

4OA7 Licensee Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

ATTACHMENT: SUPPLEMENTARY INFORMATION

Key Points of Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Items Opened, Closed, and Discussed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

List of Documents Reviewed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-3

List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-14

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos:

50-327, 50-328,72-034

License Nos:

DPR-77, DPR-79

Report No:

05000327/2006005 and 05000328/2006005 and

07200034/2006002

Licensee:

Tennessee Valley Authority (TVA)

Facility:

Sequoyah Nuclear Plant

Location:

Sequoyah Access Road

Soddy-Daisy, TN 37379

Dates:

October 1, 2006 - December 31, 2006

Inspectors:

J. Baptist, Acting Senior Resident Inspector

J. Diaz-Velez, Health Physicist (Section 2OS1)

F. Ehrhardt, Operations Engineer (Section 1R11.2)

L. Lake, Reactor Inspector (Section 1R08)

G. Laska, Senior Operations Examiner (Section 1R11.3)

D. Mas-Penaranda, Reactor Inspector (Sections 1R02, 1R17)

E. Michel, Reactor Inspector (Section 4OA5.3)

B. Miller, Reactor Inspector (Sections 1R08, 4OA5.2)

R. Moore, Senior Reactor Inspector (Section 4OA5.3)

S. Rose, Senior Operations Engineer (Section 1R11.3)

C. Smith Senior Reactor Inspector (Sections 1R02, 1R17)

M. Speck, Resident Inspector

C. Stancil, Resident Inspector (Section 1EP6)

Approved by:

M. Widmann, Chief

Reactor Projects Branch 6

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000327/2006005, IR 05000328/2006005; IR 07200034/2006002; 10/01/2006 -

12/31/2006; Sequoyah Nuclear Plant, Units 1 & 2; Licensed Operator Requalification

Program.

The report covered a three-month period of inspection by resident inspectors and

announced inspections by 10 regional inspectors and one resident inspector from

another site. One NRC-identified Green finding, which was also a non-cited violation,

was identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance

Determination Process" (SDP). Findings for which the SDP does not apply may be

Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors identified a Green, non-cited violation (NCV) of 10 CFR 55.53,

Conditions of Licenses for failure to certify the qualifications and status of licensed

operators were current and valid prior to their resumption of license duties. Specific

aspects of the requalification program that were not valid included plant tours that were

not completed with another licensed operator and not completing all shift functions in

positions to which the individuals will be assigned. The licensee entered the finding into

the corrective action program as PER No.112004.

The finding is greater than minor because it is associated with the human performance

attribute of the Mitigating Systems Cornerstone that affects the cornerstone objective of

ensuring the availability, reliability, and capability of operators to respond to initiating

events to prevent undesirable consequences that could pose a potential risk to

operations. The finding was evaluated using the Operator Requalification Human

Performance Significance Determination Process. Under this SDP, record deficiencies

can be either minor or of very low safety significance (Green). This finding was

determined to be Green because it was related to the program for maintaining active

licenses and more than 20% of the records reviewed had deficiencies. (Section 1R11.3).

B.

Licensee-Identified Violations

A violation of very low safety significance, which was identified by the licensee, was

reviewed by the inspectors. Corrective actions taken or planned by the licensee have

been entered into the licensees corrective action program. This violation and corrective

action are listed in Section 4OA7.

Enclosure

REPORT DETAILS

Summary of Plant Status:

Unit 1 operated at or near 100% rated thermal power (RTP) for the duration of the

reporting period.

Unit 2 operated at or near 100% RTP until November 27, 2006 when it shut down for a

refueling outage. Unit 2 achieved criticality on December 24, 2006, and reached 100%

RTP on December 29, 2006, where it remained for the duration of the reporting period.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01

Adverse Weather Protection

a.

Inspection Scope

The inspectors reviewed design features and licensee preparations for protecting the

essential raw cooling water (ERCW) intake structure and both Unit 1 and 2 refueling

water storage tanks (RWSTs) from extreme cold and freezing conditions. The

inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), and Technical

Specifications (TS), reviewed and observed implementation of licensee freeze protection

procedures, and walked down portions of the systems to assess the status of system

deficiencies and the system readiness for extreme cold weather. Inspectors performed

corrective action program keyword searches to verify deficiencies were being identified

at an appropriate level and that actions were taken to correct problems. Documents

reviewed are listed in the Attachment to this report.

b.

Findings

No findings of significance were identified.

1R02

Evaluations of Changes, Tests or Experiments

a.

Inspection Scope

The inspectors reviewed selected samples of 10 CFR 50.59 evaluations to verify that

the licensee had appropriately considered the conditions under which changes to the

facility, Updated Final Safety Analysis Report (UFSAR), or procedures may be made,

and tests conducted, without prior NRC approval. The inspectors reviewed ten

evaluations completed for changes made by the licensee without prior NRC approval.

The inspectors also reviewed documents prepared in connection with the changes.

Documents reviewed included supporting analyses, the UFSAR, and drawings to verify

that the licensee had correctly concluded that the changes could be made without

obtaining a license amendment. The ten evaluations reviewed are listed in the

Attachment to this report.

4

Enclosure

Additionally, the inspectors reviewed samples of changes for which the licensee had

determined that evaluations were not required. The reviews were performed to verify

that the licensees conclusions to screen out these changes were correct, and the

changes were made in compliance with the requirements of 10 CFR 50.59. The sixteen

screened out changes reviewed are listed in the Attachment to this report.

The inspectors also reviewed selected problem evaluation reports (PERs) to verify that

plant problems were evaluated for root/apparent causes; extent of condition; and that

the developed corrective actions were adequate to ensure recurrence control of the

identified plant problem.

b.

Findings

No findings of significance were identified.

1R04

Equipment Alignment

a.

Inspection Scope

Partial System Walkdowns. The inspectors performed a partial walkdown of the

following three systems to verify the operability of redundant or diverse trains and

components when safety equipment was inoperable. The inspectors attempted to

identify any discrepancies that could impact the function of the system, and, therefore,

potentially increase risk. The inspectors reviewed applicable operating procedures,

walked down control system components and verified that selected breakers, valves,

and support equipment were in the correct position to support system operation. The

inspectors also verified that the licensee had properly identified and resolved equipment

alignment problems that could cause initiating events or impact the capability of

mitigating systems or barriers and entered them into the corrective action program.

Documents reviewed are listed in the Attachment to this report.

Residual Heat Removal (RHR) Train 2B during maintenance on Train 2A

Emergency Diesels 1A, 1B, and 2A during diesel 2B Outage

Unit 2 Spent Fuel Pool Cooling during full core offload

b.

Findings

No findings of significance were identified.

1R05

Fire Protection

a.

Inspection Scope

The inspectors conducted a tour of the eight areas listed below to assess the material

condition and operational status of fire protection features. The inspectors verified that

combustibles and ignition sources were controlled in accordance with the licensees

administrative procedures, fire detection and suppression equipment was available for

use; that passive fire barriers were maintained in good material condition; and that

compensatory measures for out-of-service, degraded, or inoperable fire protection

5

Enclosure

equipment were implemented in accordance with the licensees fire plan. Documents

reviewed are listed in the Attachment to this report.

Control Building Elevation 669 (Mechanical Equipment Room, 250-VDC Battery

and Battery Board Rooms)

Control Building Elevation 706 (Cable Spreading Room)

Control Building Elevation 685 (Auxiliary Instrument Rooms)

Auxiliary Building Elevation 690 (Corridor)

Emergency Diesel Generator Building

Control Building Elevation 732 (Mechanical Equipment Room and Relay Room)

Auxiliary Building Elevation 714 (Corridor)

Unit 2 Residual Heat Removal/Containment Spray Heat Exchanger Rooms

The inspectors observed the performance of the site fire brigade during unannounced

drills on March 29, 2006, and September 30, 23006, and reviewed the drill critique

report for an unannounced drill on October 3, 2006, to evaluate the readiness of the fire

brigade to fight fires and to assess the drill against the requirements of the Sequoyah

Nuclear Plant Fire Protection Report, Revision 17. The observed drills simulated fires at

the 480-volt Reactor Motor Operated Valve Board 1B1-B and the Motor-driven Auxiliary

Feedwater Pump 2A-A. The reviewed drill critique was for fire brigade response to a fire

alarm report from the Unit 1 RWST. Specifically, the inspectors reviewed the following

aspects of the drills: use of protective clothing, use of breathing apparatus, proper use

of fire hoses, control of the drill scenario, and recurrence of identified deficiencies.

b.

Findings

No findings of significance were identified.

1R07

Heat Sink Performance

a.

Inspection Scope

The inspectors observed performance and reviewed the results of the following activity

to verify the heat exchangers readiness and availability. Inspectors interviewed

maintenance and testing personnel and the system engineer, reviewed corrective action

program documents, previous heat exchanger flow rate data, and inspected the heat

exchanger internals for cleanliness. Inspectors also walked down the system while in

operation looking for evidence of leaks following system restoration. Documents

reviewed are listed in the Attachment to this report.

WO 06-777564-000, Open 2B Containment Spray Heat Exchanger for Eddy

Current Inspection

b.

Findings

No findings of significance were identified.

6

Enclosure

1R08

Inservice Inspection (ISI) Activities (71111.08)

.1

Piping and Pressure Boundary Systems ISI

a.

Inspection Scope

From December 4 - December 8, 2006, the inspectors observed and reviewed the

licensees implementation of their ISI program for monitoring degradation of the reactor

coolant system (RCS) boundary and other risk significant piping system boundaries for

Unit 2. The inspectors observed and reviewed a sample of American Society of

Mechanical Engineers (ASME),Section XI, Section III, and Risk Informed ISI required

examinations, in order of risk priority, as identified in Section 71111.08-03 of inspection

procedure 71111.08, Inservice Inspection Activities based upon the ISI activities

available for review during the onsite inspection period.

The inspectors conducted an on-site review of nondestructive examination (NDE)

activities to evaluate compliance with TSs and the applicable editions of ASME Section

V and Section XI to verify that indications and defects (if present) were appropriately

evaluated and dispositioned in accordance with the requirements of ASME Section XI

acceptance standards.

The inspectors observed the following examinations:

Manual Ultrasonic Examination:

13SIF-142

Visual (VT3) examination of the following Hangers:

2-CVCH-004

2-CVCH-007

2-CVCH-010

2-CVCH-037

Qualification and certification records for examiners, inspection equipment, and

consumables along with the applicable NDE procedures for the above ISI examination

activities were reviewed and compared to requirements stated in ASME Section V and

Section XI.

The inspectors observed in-process welding activities for the following ASME pressure

boundary locations. Inspectors reviewed quality records for welding procedures,

procedure qualification, welder qualification, and filler metal certification.

The inspectors observed a sample of in-process weld-overlay activities for the following

Pressurizer nozzles:

Pressurizer Spray Nozzle

Pressurizer Surge Nozzle

7

Enclosure

b.

Findings

No findings of significance were identified.

.2

Reactor Vessel Upper Head Penetrations

The inspectors completed TI2515/150, Reactor Pressure Vessel Head and Head

Penetration Nozzles (NRC Order EA-03009) (Unit2), this outage. See Section 4OA5.2.

.3

Boric Acid Corrosion Control (BACC) ISI

a.

Inspection Scope

The inspectors reviewed the licensees BACC activities to ensure implementation with

commitments made in response to NRC Generic Letter 88-05 Boric Acid Corrosion of

Carbon Steel Reactor Pressure Boundary and Bulletin 2002-01 Reactor Pressure

Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity.

The inspectors conducted an on-site record review as well as an independent walkdown

of parts of the reactor building that are not normally accessible during at-power

operations to evaluate compliance with licensee BACC program requirements. In

particular, the inspectors assessed whether the visual examinations focused on

locations where boric acid leaks can cause degradation of safety significant components

and that degraded or non-conforming conditions were properly identified in the

licensees corrective action program.

The inspectors reviewed a sample of engineering evaluations completed for boric acid

found on reactor coolant system piping and components. The inspectors also reviewed

licensee corrective actions implemented for evidence of boric acid leakage to confirm

that they were consistent with requirements of Section XI of the ASME Code and 10 CFR 50 Appendix B Criterion XVI.

b.

Findings

No findings of significance were identified.

.4

Steam Generator ISI

a.

Inspection Scope

From December 11-15, 2006, the inspectors reviewed the Unit 2 Steam Generator (SG)

tube eddy current testing (ECT) examination activities to ensure compliance with TSs,

applicable industry operating experience and technical guidance documents, and ASME

Code Section XI requirements.

The inspectors reviewed licensee SG inspection activities to ensure that ECT

inspections were conducted in accordance with the licensees SG Program and

applicable industry standards. The inspectors reviewed the SG examination scope,

8

Enclosure

ECT acquisition procedures, Examination Technique Specification Sheets (ETSS), ECT

analysis guidelines, the most recent SG degradation assessment and operational

assessment, and also the condition monitoring results as they became available. The

inspectors reviewed documentation to ensure that the ECT probes and equipment

configurations used were qualified to detect the expected types of SG tube degradation.

The inspectors ensured that all tubes evaluated in condition monitoring were

appropriately screened for in-situ testing. No tubes met the criteria for in-situ testing. In

addition, the inspectors ensured that the licensee had appropriately implemented the

NRC-approved Alternate Repair Criteria (ARC) applicable to tubes that experienced

outer diameter stress corrosion cracking (ODSCC) at tube support plates.

The inspectors monitored the licensees secondary side activities, which included a

foreign object search and recovery (FOSAR) for loose parts, and sludge lancing. As

part of an industry commitment, the licensee was required to remove a tube from

service for destructive testing. The inspectors monitored this evolution to ensure there

was no damage to other tubes or other parts of the SG.

b.

Findings

No findings of significance were identified.

.5

Identification and Resolution of Problems

a.

Inspection Scope

The inspectors performed a review of piping system ISI related problems that were

identified by the licensee and entered into the corrective action program. The inspectors

reviewed corrective action documents to confirm that the licensee had appropriately

described the scope of the problems. Additionally, the inspectors review included

confirmation that the licensee had an appropriate threshold for identifying issues and

had implemented effective corrective actions. The inspectors evaluated the threshold

for identifying issues through interviews with licensee staff and review of licensee

actions to incorporate lessons learned from industry issues related to the ISI program.

The inspectors performed these reviews to ensure compliance with 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, requirements. The corrective action

documents reviewed by the inspectors are listed in the Attachment to this report.

b.

Findings

No findings of significance were identified.

9

Enclosure

1R11

Licensed Operator Requalification Program

.1

Quarterly Inspection

a.

Inspection Scope

The inspectors observed licensed operator requalification simulator testing on October

24, 2006. The testing involved a failed impulse pressure transmitter failure followed by

loss of condenser vacuum and automatic turbine trip. The reactor failed to automatically

trip and resulted in an anticipated transient without scram (ATWS). The ATWS was

compounded by the inability to trip the reactor from the Main Control Room, auxiliary

feedwater control valves failed to operate automatically for Steam Generators Number 1

and 2, and the Turbine Driven Auxiliary Feedwater Pump (TDAFP) was unable to supply

feedwater, all of which required operator action. As plant conditions were being

stabilized, a pressurizer power operated relief valve (PORV) failed open and required

operators to shut its blocking valve.

The inspectors observed crew performance in terms of communications; ability to take

timely and proper actions; prioritizing, interpreting and verifying alarms; correct use and

implementation of procedures, including the alarm response procedures and emergency

plan event classification; timely control board operation and manipulation, including high

risk operator actions; oversight and direction provided by shift manager, including the

ability to identify and implement appropriate TS actions; independent event classification

by the Shift Technical Advisor; and group dynamics involved in crew performance. The

inspectors also observed the examining staffs assessment of the crews performance

and compared them to inspector observations. Documents reviewed are listed in the

Attachment to this report.

b.

Findings

No findings of significance were identified.

.2

Annual Review of Licensee Requalification Examination Results

a.

Inspection Scope

On November 17, 2006, the licensee completed the comprehensive requalification

biennial written examinations and annual operating tests required to be given to all

licensed operators by 10 CFR 55.59(a)(2). The inspectors performed an in-office review

of the overall pass/fail results of the written examinations, individual operating tests, and

the crew simulator operating tests. These results were compared to the thresholds

established in Manual Chapter 609 Appendix I, Operator Requalification Human

Performance Significance Determination Process.

b.

Findings

No findings of significance were identified.

10

Enclosure

.3

Licensed Operator Requalification Program - Biennial Review

a.

Inspection Scope

The inspectors reviewed facility operating history and associated documents in

preparation for this inspection. While onsite the inspectors reviewed documentation,

interviewed licensee personnel, and observed the administration of operating tests and

written examinations associated with the licensees operator requalification program.

Each of the activities performed by the inspectors was done to assess the effectiveness

of the licensee in implementing requalification requirements identified in 10 CFR 55,

Operators Licenses. The evaluations were also performed to determine if the licensee

effectively implemented operator requalification guidelines established in NUREG 1021,

Operator Licensing Examination Standards for Power Reactors, and Inspection

Procedure 71111.11, Licensed Operator Requalification Program. The inspectors also

evaluated the licensees simulation facility for adequacy for use in operator licensing

examinations using ANSI/ANS-3.5-1985, American National Standard for Nuclear

Power Plant Simulators for use in Operator Training and Examination. The inspectors

observed two crews during the performance of the operating tests. Documentation

reviewed included written examinations, job performance measures, simulator

scenarios, licensee procedures, on-shift records, licensed operator qualification records,

watchstanding and medical records, simulator modification request records and

performance test records, the feedback process, and remediation plans. Documents

reviewed during the inspection are listed in the Attachment to this report.

b.

Findings

Introduction: A Green NCV was identified for failure to certify that the qualifications and

status of licensed operators were current and valid prior to their resumption of license

duties. The applicable requirements of 10 CFR 55.53, Conditions of Licenses for

license reactivation were not met. Specific aspects of the requalification program that

were not valid included plant tours that were not completed with another licensed

operator and not completing all shift functions in the position to which the individual will

be assigned.

Description: The inspectors identified problems with several aspects of the reactivation

process for licensed operators who had been reactivated between October 1, 2004 and

September 30, 2006. The inspectors performed a detailed review for 5 of the 15

individuals who had licenses reactivated during this time period.

The inspectors identified that complete tours of the plant were not being conducted in

accordance with OPDP-1 Operations Department Procedure, Revision 6 and 10 CFR 55.53 requirements. Some individuals reactivating their licenses were performing the

required plant tours without being accompanied by another licensed individual. The

inspectors also identified that some individuals reactivating their licenses had

documented standing watch in non-TS positions, i.e., those positions that TSs do not

require a licensed operator to fill. 10 CFR 55.53, requires that an authorized

representative of the facility certify that individuals reactivating their license must

complete a minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions in the position to which the individual

11

Enclosure

will be assigned and under the direction of a reactor operator or senior reactor operator

as appropriate. The 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> shall also include a complete tour of the plant.

The inspectors noted that the licensee performed a self assessment of the licensed

operator requalification program on September 11-26, 2006. The assessment identified

problems in several different areas related to operator license reactivation and

maintenance of active license process. Specifically, one licensed operators reactivation

documents could not be located, two licensed operators were returned to active status

without all required training completed, and one inactive licensed operator assumed

licensed duties without being reactivated.

Analysis: The inspectors determined that the licensees failure to properly certify and

maintain the reactivation records of licensed operators and the failure to perform plant

tours with another licensed operator and complete shift functions in the position to which

the individual will be assigned is a performance deficiency because the licensee must

satisfy the requirements of 10 CFR 55.53 for license reactivation.

The finding is more than minor because it is associated with the human performance

attribute of the Mitigating Systems Cornerstone and adversely affects the cornerstone

objective of ensuring the availability, reliability, and capability of operators to response to

initiating events to prevent undesirable consequences. The failure to properly reactivate

the licenses of operators could adversely impact their performance. The finding was

evaluated using the Operator Requalification Human Performance Significance

Determination Process. Under this SDP, record deficiencies can be either minor or of

very low safety significance (Green). This finding was determined to be Green because

it was related to the program for maintaining active licenses and more than 20% of the

records reviewed had deficiencies.

Enforcement: 10 CFR 55.53.(f) Conditions of Licenses requires, in part, that an

authorized representative of the facility licensee shall certify that qualifications and

status of operator licensees are current and valid prior to the resumption of license

duties. Included in the certification required by 10 CRF 55.53 is that the individual

complete a minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions in the position to be assigned and

also complete a plant tour while accompanied by a licensed operator. Contrary to the

above, the licensee did not properly certify that qualifications and status were current

and valid prior to allowing operators to perform licensed duties.

The failure to properly reactivate licensed operators was determined to be of very low

safety significance (Green) and has been entered into the licensees corrective action

program as PER No.112004. The finding is being treated as an NCV consistent with

Section VI.A of the NRC Enforcement Policy: NCV 05000327,328/2006005-01, Failure

to certify qualifications and status of licensed operators were current and valid in

accordance with 10CFR 55.53.

12

Enclosure

1R12

Maintenance Effectiveness

a.

Inspection Scope

The inspectors reviewed the following three maintenance activities to verify the

effectiveness of the activities in terms of: 1) appropriate work practices; 2) identifying

and addressing common cause failures; 3) scoping in accordance with 10 CFR 50.65

(b); 4) characterizing reliability issues for performance; 5) trending key parameters for

condition monitoring; 6) charging unavailability for performance; 7) classification in

accordance with 10 CFR 50.65(a)(1) or (a)(2); 8) appropriateness of performance

criteria for Systems, Structures, and Components (SSCs) and functions classified as

(a)(2); and 9) appropriateness of goals and corrective actions for SSCs and functions

classified as (a)(1). Documents reviewed are listed in the Attachment to this report.

PER 115421, B-B Main Control Room Ventilation

PER 115780, 2B Residual Heat Removal HX Outlet Valve 74-28 Failure

PER 85481, Repeated Packing Leaks of Safety Injection (SI) Valve 2-FCV-63-156

b.

Findings

No findings of significance were identified.

1R13

Maintenance Risk Assessments and Emergent Work Control

a.

Inspection Scope

The inspectors reviewed the following six activities to verify that the appropriate risk

assessments were performed prior to removing equipment from service for

maintenance. The inspectors verified that risk assessments were performed as

required by 10 CFR 50.65 (a)(4), and were accurate and complete. When emergent

work was performed, the inspectors verified that the plant risk was promptly reassessed

and managed. The inspectors verified the appropriate use of the licensees risk

assessment tool and risk categories in accordance with Procedure SPP-7.1, On-Line

Work Management, Revision 8, and Instruction 0-TI-DSM-000-007.1, Risk Assessment

Guidelines, Revision 8. Documents reviewed are listed in the Attachment to this report.

Unit 2 ECCS Train A Room Cooler Outage

Unplanned EDG 2B Inoperability

2-SI-OPS-082-26A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35

ORAM Orange risk condition from Unit 2 midloop activities prior to vacuum refill

Franklin 500KV line tripped resulting in Technical Specification 3.8.1.1 entry

Unit 2 initial RCS level drain to partial draindown condition

b.

Findings

No findings of significance were identified.

13

Enclosure

1R15

Operability Evaluations

a.

Inspection Scope

For the five operability evaluations described in the PERs listed below, the inspectors

evaluated the technical adequacy of the evaluations to ensure that TS operability was

properly justified and the subject component or system remained available, such that no

unrecognized increase in risk occurred. The inspectors reviewed the UFSAR to verify

that the system or component remained available to perform its intended function. In

addition, the inspectors reviewed compensatory measures implemented to verify that

the compensatory measures worked as stated and the measures were adequately

controlled. The inspectors also reviewed a sampling of PERs to verify that the licensee

was identifying and correcting any deficiencies associated with operability evaluations.

Documents reviewed are listed in the Attachment to this report.

PER 111814, Train A MCR Air-Conditioning System Air Flow Greater Than

Acceptance Criteria

PERs 114769, 114941, Emergency Diesel Generator 2B Feeder Breaker Failed

to Close When Required

PER 109326, ERCW Screen Wash Pump B-B Failed Pump Performance Test

PER 115490, Charging Pump Discharge Manual Isolation Valve Appendix R

Operability

PER 117113, Unit 1 Steam Generator Levels Exhibited Lowering Trend

b.

Findings

No findings of significance were identified. An unresolved item (URI) is discussed

below.

Inability to Perform Actions Required by AOP-N.08, Appendix R Fire Safe Shutdown

Introduction: The inspectors identified an Unresolved Item (URI) for not promptly

identifying and correcting problems associated with manual valve 2-62-527. These

problems resulted in operators not being able to comply with licensee procedure AOP-

N.08, Appendix R Fire Safe Shutdown due to manual valve 2-62-527 not being able to

be closed within the 13 minutes required.

Description: On October 28, 2005, a procedure change to AOP-N.08, Appendix R Fire

Safe Shutdown, was implemented. This change incorporated updated guidance

provided by a Westinghouse technical bulletin (TB -04-022) concerning RCP seal

performance during Appendix R fires and a loss of all pump seal cooling. This change

reduced the time available to perform manual actions and restore RCP seal flow from 24

minutes to 13 minutes. In the event of an Appendix R fire resulting in a spurious safety

injection signal, plant procedures required that all RCS injection sources be stopped to

prevent filling the pressurizer solid. The vendor guidance stated that actions taken to

prevent this condition and restore RCP seal flow should be completed within 13 minutes

to prevent seal damage. The actions outlined by AOP-N.08 required an auxiliary unit

operator (AUO) to manipulate several valves in the appropriate Charging Pump room

14

Enclosure

and then a CCP restarted to restore seal flow. Specifically, the AUO was to open a

dedicated flow path to the RCP seals using manual valve 62-526 (A-train), or 62-534 (B-

train) and close the associated CCP manual discharge valve,62-527 (A-train) or 62-533

(B-train) to the CCP Injection Tank (CCPIT). To support the procedure change, these

manipulations were subjected to a manual action validation that consisted of a table top

review of the necessary steps. The licensee determined that the CCP manual

discharge valves to the CCPIT could be closed by an individual AUO in 5 minutes and

20 seconds.

Prior to the procedure being approved, PER 91383 was written on October 24, 2005.

The PER addressed concerns by at least one plant AUO that the manual actions

required by the change to procedure AOP-N.08 may not be able to be completed within

the time required. PER 91383 requested the need to further evaluate the time

necessary to perform the manual actions by actual valve manipulations, or whether

additional procedure changes were needed to provide more margin to the required time.

The corrective action planned was to perform a timed valve stroke of CCP discharge

valve 2-62-527 to validate procedural change assumptions. Work Order (WO) 06-

771729-000 was written to implement and track this action during an appropriate CCP

maintenance period. PER 91383 was closed as completed on February 24, 2006 based

on the WO being written. On November 9, 2006, during a self-assessment, the licensee

determined that the WO had not been completed and was not scheduled for

performance until January 22, 2007. PER 114455 was written to document the

incomplete corrective action. Upon review of PER 114455, the inspectors questioned

the licensee on the valves history, the status of corrective actions, and whether a valid

safety concern existed if the valve could not be operated within the prescribed time.

Prior to resolution by the licensee, on November 27, 2006, during Unit 2 refueling

outage activities, operators closed valve 2-62-527 to support maintenance. The

operators reported that the valve was very difficult to operate and required

approximately 30 minutes for two AUOs to shut the valve. This observation was

documented in in PER 115490 and supported the initial concern expressed in PER

91383.

This information prompted the license to evaluate the consequences of the additional

time needed to operate valve 2-62-527 with plant Appendix R procedures. Functional

Evaluation (FE) 41722 was drafted and the licensee determined that RCP seal

degradation would not occur if RCP seal flow was restored with a CCP prior to

completing of the Appendix R Fire safe shutdown manual actions The licensee also

evaluated whether the same problems were likely for other Appendix R manual valves. .

The licensee drafted a document to support the determination that other valves in both

units could be operated in adequate time in the event of an Appendix R fire.

Analysis: The inspectors determined that the delay in implementing the WO resulted in

not promptly identifying and correcting problems with manual valve 2-62-527 resulting in

operators not being able to comply with procedure AOP-N.08, Appendix R Fire Safe

Shutdown. The corrective action for PER 91383 was closed to a WO and rescheduled

several times in the work control process with a performance date of January 22, 2007.

The inspectors referenced Inspection Manual Chapter (IMC) 0612 and determined the

finding is more than minor because if left uncorrected, the licensee would not be able to

15

Enclosure

comply with AOP-N.08. The finding is associated with the mitigating system

cornerstone and could be reasonably viewed as affecting the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. This finding is unresolved pending the

review of supporting documentation and completion of the significance determination.

Enforcement: Pending additional information involving the circumstances surrounding

the event, its extent of condition and completion of the significance determination, this

finding is identified as URI 05000328/2006005-02, Inability to Perform Required Actions

of AOP-N.08, Appendix R Fire Safe Shutdown.

1R17

Permanent Plant Modifications

a.

Inspection Scope

The inspectors performed independent design reviews of six plant modifications in the

Initiating Events, Mitigating Systems, and Barrier Integrity cornerstone areas, to verify

that the plant modifications did not have any adverse effects on system availability,

reliability, and functional capability. Documents reviewed included procedures,

engineering calculations, modification design and implementation packages, work

orders, Condition Reports (CRs), applicable sections of the UFSAR, TSs, and design

basis information. The plant modifications and the associated attributes reviewed are as

follows:

DCN D22050, Pressurizer Relief Tank Level Transmitter Removed (Barrier Integrity)

Control Signal

Energy Needs

Process Medium

Update of Licensee Documents

DCN D21781, Change Steam Generator Narrow Range Level Transmitter Scaling

(Mitigating System)

Control Signal

Energy Needs

Process Medium

Update of Licensee Documents

Operations

DCN D21911, Replace Containment Isolation Valve 2-FCV-030-0014(Barrier Integrity)

Pressure Boundary

Structural

Process Medium

Update of Licensee Documents

Materials/Replacement Components

DCN 21900, Replace Unit 1B Main Bank Transformer and Associated Fire Protection

Ring Header, Revision A.(Initiating Event)

Energy Needs

Control Signals

Post-Installation Testing

16

Enclosure

Update of Licensee Documents

Functional Testing Adequacy and Results

DCN D21971, Replace Cable PP351A for D/G 1A-A, Revision A. (Mitigating Systems)

Materials/ Replacement

Failure Modes

Post-Installation Testing

Update of Licensee Documents

Functional Testing Adequacy and Results

DCN D21827, Revise Setting on Raw Cooling Water Pump Breaker, Revision A.

Control Signals

Response Time

Post-Insulation Testing

Update of Licensee Documents

Functional Testing Adequacy and Results

The inspectors also performed field inspections of selected plant modifications to verify

that the as-built installation complied with design requirements delineated in approved

design documents. Additionally, the inspectors reviewed selected PERs to verify that

plant problems were evaluated for root/apparent causes, extent of condition, and that

the developed corrective actions were adequate to ensure recurrence control of the

identified plant problem.

b.

Findings

No findings of significance were identified.

1R19

Post-Maintenance Testing

a.

Inspection Scope

The inspectors reviewed the five post-maintenance tests listed below to verify that

procedures and test activities ensured system operability and functional capability. The

inspectors reviewed the licensees test procedure to verify that the procedure

adequately tested the safety function(s) that may have been affected by the

maintenance activity, that the acceptance criteria in the procedure were consistent with

information in the applicable licensing basis and/or design basis documents, and that

the procedure had been properly reviewed and approved. The inspectors also

witnessed the test or reviewed the test data, to verify that test results adequately

demonstrated restoration of the affected safety function(s). Documents reviewed are

listed in the Attachment to this report.

WO 05-782379-000, Breaker Changeout for Motor-driven Auxiliary Feedwater

(AFW) Pump 2B

2-SI-OPS-000-009.0, Actuation of Emergency Core Cooling Systems (ECCS)

and Boron Injection Flowpath Valves Via SI Signal, Revision 1

WO 05-777912-001, Repack SI system Hot Leg Injection Valve, 2-FCV-63-156

17

Enclosure

WO 06-780773-000, Calibrate FCV and Limit Switches on 2-FCV-074-28

2-SI-SLT-088-156.0, Containment Integrated Leak Rate Test, Revision 2

b.

Findings

No findings of significance were identified.

1R20

Refueling and Other Outage Activities

a.

Inspection Scope

For the Unit 2 refueling outage that began on November 27, 2006, the inspectors

evaluated licensee activities to verify that the licensee considered risk in developing

outage schedules, followed risk reduction methods developed to control plant

configuration, developed mitigation strategies for the loss of key safety functions, and

adhered to operating license and TS requirements that ensure defense-in-depth. The

inspectors also walked down portions of Unit 2 not normally accessible during at-power

operations to verify that safety-related and risk-significant SSCs were maintained in an

operable condition. Specifically, between November 27, 2006, and December 26, 2006,

the inspectors performed inspections and reviews of the following outage activities.

Documents reviewed are listed in the Attachment to this report.

Outage Plan. The inspectors reviewed the outage safety plan and contingency

plans to confirm that the licensee had appropriately considered risk, industry

experience, and previous site-specific problems in developing and implementing

a plan that assured maintenance of defense-in-depth.

Reactor Shutdown. The inspectors observed the shutdown in the control room

from the time the reactor was tripped until operators placed it on the RHR

system for decay heat removal to verify that TS cooldown restrictions were

followed. The inspectors also toured the lower containment as soon as

practicable after reactor shutdown to observe the general condition of the RCS

and emergency core cooling system components and to look for indications of

previously unidentified leakage inside the polar crane wall.

Licensee Control of Outage Activities. On a daily basis, the inspectors attended

the licensee outage turnover meeting, reviewed PERs, and reviewed the

defense-in-depth status sheets to verify that status control was commensurate

with the outage safety plan and in compliance with the applicable TS when

taking equipment out-of-service. The inspectors further toured the main control

room and areas of the plant daily to ensure that the following key safety

functions were maintained in accordance with the outage safety plan and TS:

electrical power, decay heat removal, spent fuel cooling, inventory control,

reactivity control, and containment closure. The inspectors also observed a

tagout of the containment spray heat exchanger to verify that the equipment was

appropriately configured to safely support the work or testing. To ensure that

RCS level instrumentation was properly installed and configured to give accurate

information, the inspectors reviewed the installation of the Mansell level

18

Enclosure

monitoring system. Specifically, the inspectors discussed the system with

engineering, walked it down to verify that it was installed in accordance with

procedures and adequately protected from inadvertent damage, verified that

Mansell indication properly overlapped with pressurizer level instruments during

pressurizer draindown, verified that operators properly set level alarms to

procedurally required setpoints, and verified that the system consistently tracked

while lowering RCS level to reduced inventory conditions. The inspectors also

observed operators compare the Mansell indications with locally-installed

ultrasonic level indicators during entry into mid-loop conditions.

Refueling Activities. The inspectors observed fuel movement at the spent fuel

pool and at the refueling cavity in order to verify compliance with TS and that

each assembly was properly tracked from core offload to core reload. In order to

verify proper licensee control of foreign material, the inspectors verified that

personnel were properly checked before entering any foreign material exclusion

(FME) areas, reviewed FME procedures, and verified that the licensee followed

the procedures. To ensure that fuel assemblies were loaded in the core

locations specified by the design, the inspectors independently reviewed the

recording of the licensees final core verification.

Reduced Inventory and Mid-Loop Conditions. Prior to the outage, the inspectors

reviewed the licensees commitments to Generic 88-17, Loss of Decay Heat

Removal. Before entering reduced inventory conditions the inspectors verified

that these commitments were in place, that plant configuration was in

accordance with those commitments, and that distractions from unexpected

conditions or emergent work did not affect operator ability to maintain the

required reactor vessel level. While in mid-loop conditions, the inspectors

verified that licensee procedures for closing the containment upon a loss of

decay heat removal were in effect, that operators were aware of how to

implement the procedures, and that other personnel were available to close

containment penetrations if needed.

Heatup and Startup Activities. The inspectors toured the containment prior to

reactor startup to verify that debris that could affect the performance of the

containment sump had not been left in the containment. The inspectors

reviewed the licensees mode change checklists to verify that appropriate

prerequisites were met prior to changing TS modes. To verify RCS integrity and

containment integrity, the inspectors further reviewed the licensees RCS

leakage calculations and containment isolation valve lineups. In order to verify

that core operating limit parameters were consistent with core design, the

inspectors also reviewed low power physics testing results and the Core

Operating Limits Report.

b.

Findings

No findings of significance were identified.

19

Enclosure

1R22

Surveillance Testing

a.

Inspection Scope

For the seven surveillance tests identified below, by witnessing testing and/or reviewing

the test data, the inspectors verified that the SSCs involved in these tests satisfied the

requirements described in the TS surveillance requirements, the UFSAR, applicable

licensee procedures, and that the tests demonstrated that the SSCs were capable of

performing their intended safety functions. Documents reviewed are listed in the

Attachment to this report. Those tests included the following:

1-SI-MIN-061-108.0, Ice Condenser Intermediate Deck Door Weekly Inspection,

Revision 2

2-SI-ICC-090-106.0, Channel Calibration of Containment Building Lower

Compartment Air Monitor 2-R-90-106, Revision 9***

0-SI-SXV-001-859.0, Testing and Setting of Main Steam Safety Valves, Revision 9

2-SI-OPS-082-026.A, Loss of Offsite Power with SI - DG 2A-A Test, Revision 35

0-SI-MIN-061-109.0, Ice Condenser Intermediate and Lower Inlet Doors and

Vent Curtains, Revision 4*

2-SI-OPS-003-118.0 AFW pump and Valve Auto Actuation, Revision 18

2-SI-SXP-003-003-202.S, Turbine Driven Auxiliary Feedwater Pump 2A-S

Comprehensive Performance Test, Revision 4**

  • This procedure included an outage ice condenser system surveillance
    • This procedure included inservice testing requirements
      • This procedure included a RCS leakage detection surveillance

b.

Findings

No findings of significance were identified.

Cornerstone: Emergency Preparedness

1EP6

Drill Evaluation

a.

Inspection Scope

Resident inspectors evaluated the conduct of a routine licensee emergency drill on

October 3, 2006, to identify any weaknesses and deficiencies in classification,

notification, and protective action recommendation (PARs) development activities. The

inspectors observed emergency response operations in the simulated control room to

verify that event classification and notifications were done in accordance with EPIP-1,

Emergency Plan Classification Matrix, Revision 38. The inspectors also attended the

licensee critique of the drill to compare any inspector-observed weakness with those

identified by the licensee in order to verify whether the licensee was properly identifying

failures. Documents reviewed are listed in the Attachment to this report.

20

Enclosure

b.

Findings

No findings of significance were identified.

2.

RADIATION SAFETY

Cornerstone: Occupational Radiation Safety (OS)

2OS1 Access Control To Radiologically Significant Areas

a.

Inspection Scope

Access Control Licensee program activities for monitoring workers and controlling

access to radiologically significant areas and tasks were inspected. The inspector

evaluated procedural guidance; directly observed implementation of administrative and

established physical controls; assessed worker exposures to radiation and radioactive

material; and appraised radiation worker and technician knowledge of, and proficiency

in, the implementation of Radiation Protection (RP) program activities.

During the inspection, radiological controls for ongoing refueling activities for Unit 2 were

observed and discussed. Reviewed tasks included steam generator non-destructive

testing, containment sump modifications, and refueling activities. In addition, licensee

controls for selected tasks scheduled and on-going during the current refueling outage

were assessed. The evaluations included, as applicable, Radiation Work Permit (RWP)

details; use and placement of dosimetry and air sampling equipment; electronic

dosimeter set-points, and monitoring and assessment of worker dose from direct

radiation and airborne radioactivity source terms. Effectiveness of established controls

was assessed against area radiation and contamination survey results, and

occupational doses received. Physical and administrative controls and their

implementation for locked high radiation areas (LHRAs) and very high radiation areas

were evaluated through discussions with cognizant licensee representatives, direct field

observations, and record reviews.

Occupational workers adherence to selected radiation work permits (RWPs) and Health

Physics Technician proficiency in providing job coverage were evaluated through direct

observations of staff performance during job coverage and routine surveillance

activities, review of selected exposure records, and interviews with cognizant licensee

staff. Radiological postings and physical controls for access to designated high

radiation (HRA) and LHRA locations within the Unit 2 Containment, Auxiliary Building,

and Refuel Floor areas were evaluated during facility tours. In addition, the inspectors

independently measured radiation dose rates and evaluated established posting and

access controls for selected Auxiliary Building locations. Occupational exposures

associated with direct radiation and potential radioactive material intakes for were

reviewed and discussed with cognizant licensee representatives.

RP program activities were evaluated against 10 CFR 19.12; 10 CFR 20, Subparts B, C,

F, G, H, and J; UFSAR details in Section 12, RP; TSs Section 6.11, High Radiation

Area; and approved licensee procedures. Licensee procedures, guidance documents,

21

Enclosure

records, and data reviewed within this inspection area are listed in Section 2OS1 of the

Attachment to this report.

Problem Identification and Resolution Licensee Corrective Action Program documents

associated with access control to radiologically significant areas were reviewed and

assessed. The inspectors evaluated the licensees ability to identify, characterize,

prioritize, and resolve the identified issues in accordance with Standard Programs and

Processes procedure SPP-3.1, Corrective Action Program. Licensee self-assessments

and PER documents related to access control that were reviewed and evaluated in

detail during inspection of this program area are identified in Section 2OS1 of the

Attachment to this report.

The inspector completed 21 of the required 21 samples for Inspection Procedure (IP) 71121.01. All samples have now been completed for this IP.

b.

Findings

No findings of significance were identified.

4.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.1

Daily Review

As required by Inspection Procedure 71152, Identification and Resolution of Problems,

and in order to help identify repetitive equipment failures or specific human performance

issues for follow-up, the inspectors performed a daily screening of items entered into the

licensees corrective action program. This was accomplished by reviewing the

description of each new PER and attending daily management review committee

meetings.

.2

Semi-Annual Trend Review

a.

Inspection Scope

As required by Inspection Procedure 71152, the inspectors performed a review of the

licensees corrective action program and associated documents to identify trends that

could indicate the existence of a more significant safety issue. The inspectors review

was focused on procedure quality and compliance issues, but also included licensee

trending efforts and licensee human performance results. The inspectors review

nominally considered the six-month period of July 2006 through December 2006,

although some examples expanded beyond those dates when the scope of the trend

warranted.

Specifically, the inspectors consolidated the results of daily inspector screening

discussed in Section 4OA2.1 into a log, reviewed the log, and compared it to licensee

integrated quarterly trend reports for the period from July 2006 through September 2006

22

Enclosure

in order to determine the existence of any adverse trends that the licensee may not

have previously identified.

b.

Assessment and Observations

The inspectors identified issues with procedure quality and compliance over the period

of assessment. Noteworthy examples of deficient procedure quality or compliance

were:

PER 114003, Incorrect Procedure Revision used on 6.9kV Shutdown Board relay

testing

PER 115490, Inability to manually operate Appendix R valves within the required

time.

PER 115539, Emergency Gas Treatment System procedure cloning resulting in

failure of Unit 2 Phase A testing requirements.

PER 115534, Loss of RCS inventory during Unit 2 refueling outage Mansell

alignment.

PER 117008, Missed firewatch through plant areas with disabled fire detection.

No findings of significance were identified. In general, the licensee had identified trends

and appropriately communicated them to plant senior management. The inspectors

evaluated the licensee trending methodology and observed that the licensee had

performed a summary review of issues which were inputs to the plant Human

Performance Index. The licensee reviewed cause codes, involved organizations, key

words, and system links to identify potential trends in the data. The inspectors

compared the licensee process results with the results of the inspectors daily

screenings and did not identify any significant discrepancies or potential trends that the

licensee had failed to identify. The specifics surrounding PER 115490, regarding the

inability to manually operate Appendix R valves within the required time, are further

addressed in Section 1R15, Operability Evaluations.

.3

Annual Sample Review of Problems with Plant Venting Operations

a.

Inspection Scope

The inspectors reviewed licensee actions to resolve issues surrounding plant venting

operations. This review began as a look at how the licensee addressed problems

associated with two potentially significant events that had occurred during the venting of

plant systems. These events are common to nuclear plant operations and often are

required in restoration of a system after it has been removed from service or opened for

maintenance. PER 92485 was written on November 21, 2005, and identified that

operators had discovered the collapse of the A Chemical Volume Control System

(CVCS) Holdup Tank (HUT) due to the lack of an adequate vent path during drain down.

The licensee subsequently suspended use of the A CVCS HUT, performed a root

cause analysis, and implemented corrective actions to prevent a recurrence of this

activity. The inspectors reviewed the completion of required actions items spawned

from this event for timeliness, accuracy and adequacy. PER 102591 was written on

May 7, 2006, to address an event during drain down of the RCS to midloop conditions.

While making preparations for vacuum refill of the RCS, the evolution had to be

23

Enclosure

suspended when it was identified that a required reactor vessel head vent path was not

properly aligned. The licensee immediately vented the RCS and verified that the RCS

was not under vacuum conditions based on no observed change in RCS level indication

when the head vent was opened. The licensee declared that the apparent cause of the

event was due to failure to follow procedure, inadequate procedural guidance, and

inadequate scheduling. The event associated with PER 102591 was dispositioned as a

licensee-identified violation in Inspection Report 05000327, 328/2006003. The

inspectors reviewed the PER action items for adequacy and the associated procedures

to ensure changes were implemented to preclude repetition of this event. The

inspectors utilized these examples during the inspection period to observe similar

activities that had the potential to degrade in risk significant systems. The inspectors

were able to observe RCS drain down and refill activities during the Unit 2 Cycle 14

refueling outage, as well as, the venting operations of support systems during

restoration to their normal mode of operation.

b.

Findings and Observations

No findings of significance were identified. The inspectors noted that the licensee

appeared to have an adequate sensitivity to operational experience, procedural

guidance, scheduling conflicts, and foreign material exclusion. The licensee was

successful in properly performing the necessary venting activities associated with the

multiple system drain and refill operations accompanying Unit 2 refueling outage

maintenance.

4OA5 Other Activities

.1

Review of the Operation of an Independent Spent Fuel Storage Installation (ISFSI)

(60855.1)

a.

Inspection Scope

The inspectors reviewed ISFSI document control practices to verify that changes to the

required ISFSI procedures and equipment were performed in accordance with

guidelines established in licensee procedures and 10 CFR 72.48. Documents reviewed

are listed in the Attachment to this report.

b.

Findings

No findings of significance were identified.

.2

(Open) NRC Temporary Instruction 2515/150, Rev. 2, Reactor Pressure Vessel Head

and Vessel Head Penetration Nozzles (NRC Order EA-03-009) - Unit 2

a.

Inspection Scope

From December 4 - 8, 2006, the inspectors reviewed the licensees activities associated

with the NDE of the reactor pressure vessel head (RPVH) penetration nozzles, the bare

metal visual examination of the top surface of the RPVH, and the visual examination to

identify potential boric acid leaks from pressure-retaining components above the RPVH.

24

Enclosure

These activities were performed in response to NRC Bulletins 2001-01, 2002-01, 2002-

02, and the first revision of NRC Order EA-03-009 Modifying Licenses dated February

20, 2004 (hereafter referred to as the NRC Order).

The inspectors review of the NDE of RPVH penetration nozzles included independent

observation and evaluation of ultrasonic testing (UT) examinations (for both data

acquisition and analysis), review of NDE procedures, personnel qualifications and

training, and NDE equipment certifications. The inspectors also held interviews with

contractor representatives (Areva) and other licensee personnel involved with the RPVH

examination. The activities were reviewed to verify licensee compliance with the NRC

Order and to gather information to help the NRC staff identify possible further regulatory

positions and generic communications.

The inspectors reviewed a sample of the results from the volumetric UT examinations of

RPVH penetration nozzles. Specifically, the inspectors reviewed or observed the

following:

Observed in-process UT data acquisition scanning of RPVH penetration nozzles

57 and 52 (both with thermal sleeves)

Reviewed the UT electronic data with the Level III analyst for RPVH nozzles 4,

36, 43, 50, 56, 61, 69, 77, 126 and the calibration block (this included nozzles

both with and without thermal sleeves)

Reviewed the results of the UT examination performed to assess for leakage into

the annulus (interference fit zone) between the RPVH penetration nozzle and the

RPVH low-alloy steel for all penetration numbers listed in the previous bullet

Reviewed the procedures and results for the visual exam performed to identify

potential boric acid leaks from pressure-retaining components above the RPVH

Reviewed the RPVH susceptibility ranking and calculation of effective

degradation years (EDY), including the basis for the RPVH temperature used in

the calculation

b.

Observations and Findings

In accordance with the requirements of TI 2515/150, the inspectors evaluated and

answered the following questions:

1)

Were the examinations performed by qualified and knowledgeable personnel?

Yes. All personnel involved with the RPVH inspections were appropriately qualified in

accordance with the ASME Code, and most far exceeded the minimum requirements for

experience and training hours. The contractor (Areva) personnel responsible for

equipment manipulation, data acquisition, and data analysis frequently perform these

types of inspections nationwide.

25

Enclosure

2)

Were the examinations performed in accordance with demonstrated

procedures?

Yes. The Sequoyah Unit 2 RPVH has 57 control rod drive mechanism (CRDM) nozzles

with thermal sleeves, 13 with open housings (including 5 instrument column nozzles), 8

with part lengths, 4 upper head injection (UHI) nozzles, and 1 vent line nozzle, for a total

of 83 nozzles. All nozzles were subject to remote automated UT examination using one

of two types of probes. The blade probe was used for sleeved penetrations and the

open housing CRDMs using a dummy sleeve. The rotating probe was used for the

other open housing penetrations (UHI and instrument columns). A liquid penetrant

exam on the surface of the J-groove weld of the vent line was also performed to satisfy

the NRC Order.

Procedures 54-ISI-603-002 (UT with thermal sleeves), 54-ISI-604-001 (UT of open

housings), 54-ISI-605-02 (UT of vent line), and 54-ISI-240-44 (liquid penetrant) were

implemented to complete the exams described above. Further, the inspectors verified

that the 54-ISI-603-002 and 54-ISI-604-001 procedures were used during the Areva

demonstration to EPRIs Materials Reliability Program (MRP) to show flaw detection

capability in RPVH penetrations. By letter dated October 3, 2006, from Jack Spanner of

EPRI to Joel Whitaker of TVA (the licensee), EPRI stated that Arevas demonstration of

flaw detection techniques could reliably detect flaws in CRDM penetrations.

3)

Was the examination able to identify, disposition, and resolve deficiencies?

Yes. All indications of cracks or interference fit zone leakage are required to be

reported for further examination and disposition. Based on observation of the

examination process, the inspectors considered deficiencies would be appropriately

identified, dispositioned, and resolved. UT indications associated with the geometry of

the examined volume were identified in several penetration tubes. None of the

indications exhibited crack-like characteristics and were appropriately dispositioned in

accordance with procedures.

4)

Was the examination capable of identifying the primary water stress corrosion

cracking (PWSCC) and/or RPVH corrosion phenomena described in the NRC

Order?

Yes. The NDE techniques employed for the examination of RPVH nozzles had been

previously demonstrated under the EPRI MRP/Inspection Demonstration Program as

capable of detecting PWSCC-type manufactured cracks as well as cracks from actual

samples from another site. Based on the demonstration, observation of in-process

examinations, and review of NDE data, the inspectors determined that the licensee was

capable of identifying PWSCC and/or corrosion as required by the NRC Order.

5)

What was the physical condition of the RPVH (e.g. debris, insulation, dirt, boron

from other sources, physical layout, viewing obstructions)?

The licensee performed a 100% bare metal visual (BMV) inspection of the top of the

RPVH, including 360E around each penetration using a remote visual robotic crawler for

areas inside the lead shielding and underneath the raised insulation package. The

26

Enclosure

surface sloping down from the shielding to the flange was visually inspected directly by a

Level III VT-2 examiner. The inspectors independently reviewed portions of the remote

inspection video which revealed no insulation, dirt, or other general debris that caused

viewing obstructions in the areas of interest. Some small, loose particles of debris were

easily cleared from the surface with a low-pressure air stream mounted on the remote

crawler. The inspectors determined that the physical condition of the head was

adequate to meet the inspection requirements mandated by the NRC Order.

6)

Could small boron deposits, as described in NRC Bulletin 2001-01, be identified

and characterized?

Yes. The BMV examination was determined by the inspectors to be capable of

identifying and characterizing small boron deposits as described in NRC Bulletin 2001-

01. The remote exam was VT-2 qualified and able to resolve, at a minimum, the 0.105-

inch characters on an ASME IWA-2210-1 Visual Illumination Card.

7)

What material deficiencies (i.e., cracks, corrosion, etc.) were identified that

required repair?

There were no identified examples of RPVH penetration cracks, leakage, material

deficiencies, head corrosion, or other flaws that required repair. As discussed

previously, there were some UT indications at J-groove welds that were dispositioned as

metallurgical/geometric indications (not service related). One metallurgical indication on

tube 56 actually extended below the J-groove weld, and the inspector verified that

adequate coverage below this metallurgical indication was obtained. These indications

were likely due to weld repairs performed during initial RPVH fabrication.

8)

What, if any, impediments to effective examinations, for each of the applied

methods, were identified (e.g., centering rings, insulation, thermal sleeves,

instrumentation, nozzle distortion)?

The penetration nozzles with thermal sleeves and centering pads did not impede

effective examination. Concerning examination coverage, the NRC Order requires that

each tubes volume is inspected from a minimum of 2 inches above the highest point of

the J-groove weld to 2 inches below the lowest point of the J-groove weld, or 1 inch with

a stress analysis. The licensee had performed a stress analysis and the inspectors

verified that the minimum examination coverages required by the NRC Order were met.

9)

What was the basis for the temperature used in the susceptibility ranking

calculation?

NRC Order EA-03-009 requires that licensees calculate the EDY of the RPVH to

determine its susceptibility category, which subsequently determines the scope and

frequency of required RPVH examinations. The operating temperature of the RPVH is

an input to this calculation. Therefore, an incorrect temperature input could result in

placing the RPVH in an incorrect susceptibility category. The licensee uses the cold leg

temperature in this calculation.

27

Enclosure

In Supplement No. 1 to the NRCs Safety Evaluation Report (SER) dated February

1980, the NRC concluded that scale model tests provided reasonable assurance that

the upper head would operate at the cold leg temperature. However, the NRC staff also

required that plant data be acquired to confirm the head temperature. This data was

acquired for Unit 1 to satisfy both units because Unit 2 is considered a sister plant. The

inspectors reviewed this data which confirmed that the head operated at approximately

cold leg temperature with some minor thermocouple variations. In addition, both units

underwent a modification since this testing to increase bypass flow to the head from 4%

to about 7%. This gives further assurance that the RPVH operates at cold leg

temperature. For these reasons, the inspectors concluded that the licensee had an

adequate basis for their temperature input to the susceptibility ranking calculation, which

results in Unit 2 being placed in the Low category.

10)

During non-visual examinations, was the disposition of indications consistent with

the NRC flaw evaluation guidance?

There were no indications considered to be flaws found during the RPVH examination.

11)

Did procedures exist to identify potential boric acid leaks from pressure-retaining

components above the RPVH?

Yes. Procedure 0-PI-DXX-068-100.R, Monitoring of Reactor Head Canopy Seal Welds

for Leakage, is implemented every outage and meets the requirements of the NRC

Order. However, inspection of conoseals and other bolted connections above the

RPVH, such as the RVLIS line, are covered under the Boric Acid Program. The

inspectors determined that the program and procedure implementation met the

requirements of the NRC Order, however, the licensee also initiated actions to enhance

the method in which compliance with the NRC Order is documented. The inspectors

reviewed the inspection results for this outage and found that no indications of active or

recent boric acid leakage from pressure-retaining components above the RPVH were

identified.

12)

Did the licensee perform appropriate follow-on examinations for indications of

boric acid leaks from pressure-retaining components above the RPVH?

Yes. The licensee identified some boric acid residue that was later determined by

chemical analysis to be older than the recent operating cycle. The residue was

attributed to a conoseal leak in 2002. No other indications of boric acid leakage were

found during this outage.

.3

(Open) Temporary Instruction (TI) 2515/166, Pressurized Water Reactor Containment

Sump Blockage (NRC Generic Letter 2004-02) - Unit 2

a.

Inspection Scope

The inspectors verified the Unit 2 implementation of the licensees commitments

documented in their September 1, 2005, response to Generic Letter 2004-02, Potential

Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents

28

Enclosure

at Pressurized Water Reactors. The commitments included a permanent screen

assembly modification, a license amendment request to change the UFSAR description

of the sump screen analysis methodology, and submittal of a supplemental response to

GL 2004-02. This review included the sump screen assembly installation procedure,

screen assembly modification 10 CFR 50.59 evaluation, structural (debris) loading

calculation, and validation testing of the modified sump screen design. The inspectors

also reviewed the foreign materials exclusion controls and the completed Quality

Assurance/Quality Control records for the screen assembly installation. The inspectors

conducted a visual walkdown to verify the installed screen assembly configuration was

consistent with drawings and the tested configuration and verified the design criteria for

screen gap.

b.

Findings and Observations

No findings of significance were identified.

Unit 2 permanent modifications completed at the time of this inspection were

implemented in accordance with Sequoyah Generic Letter 2004-02 response and

supporting evaluations. The license amendment request to change the UFSAR screen

analysis methodology description had been submitted and approved. No modifications

were required to address downstream effects. TI 2515/166 will remain open pending

completion and NRC review of the licensees GL 2004-02 commitments for Unit 1 which

are scheduled for the fall 2007.

.4

(Closed) NRC Temporary Instruction (TI) 2515/169, Mitigating Systems Performance

Index (MSPI) Verification

a.

Inspection Scope

During this inspection period, the inspectors completed a review of the licensees

implementation of the Mitigating Systems Performance Index (MSPI) guidance for

reporting unavailability and unreliability of monitored safety systems in accordance with

TI 2515/169.

The inspectors examined surveillances that the licensee determined would not render

the train unavailable for greater than 15 minutes or during which the system could be

promptly restored through operator action and therefore, are not included in

unavailability calculations. As part of this review, the recovery actions were verified to

be uncomplicated and contained in written procedures.

On a sample basis, the inspectors reviewed operating logs, work history information,

maintenance rule information, corrective action program documents, and surveillance

procedures to determine the actual time periods the MSPI systems were not available

due to planned and unplanned activities. The results were then compared to the

baseline planned unavailability and actual planned and unplanned unavailability

determined by the licensee to ensure the datas accuracy and completeness. Likewise,

these documents were reviewed to ensure MSPI component unreliability data

determined by the licensee identified and properly characterized all failures of monitored

components. The unavailability and unreliability data were then compared with

29

Enclosure

performance indicator data submitted to the NRC to ensure it accurately reflected the

performance history of these systems.

b.

Findings and Observations

No findings of significance were identified. The licensee accurately documented the

baseline planned unavailability hours, the actual unavailability hours and the actual

unreliability information for the MSPI systems. No significant errors in the reported data

were identified, which resulted in a change to the indicated index color. No significant

discrepancies were identified in the MSPI basis document which resulted in: (1) a

change to the system boundary, (2) an addition of a monitored component, or (3) a

change in the reported index color.

.5

Institute of Nuclear Power Operations (INPO) Plant Assessment Report Review

a.

Inspection Scope

The inspectors reviewed the interim report for the INPO plant assessment report of

Sequoyah conducted in July 2006. The inspectors reviewed the report to ensure that

issues identified were consistent with the NRC perspectives of licensee performance

and if any significant safety issues were identified that required further NRC follow-up.

b. Findings

No findings of significance were identified.

4OA6 Meetings, Including Exit

.1

Exit Meeting Summary

On January 3, 2007, the resident inspectors presented the inspection results to

Mr. R. Douet and other members of his staff, who acknowledged the findings. The

inspectors asked the licensee whether any of the material examined during the

inspection should be considered proprietary. No proprietary information was identified.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.

TS 6.8.1 requires that written procedures shall be established, implemented, and

maintained covering the activities recommended in Appendix A of Regulatory

Guide 1.33, Revision 2, February 1978. Contrary to this, on November 28, 2006,

an AUO improperly implemented 0-GO-13,Reactor Coolant System Drain and

Fill Operations, Revision 54, Appendix AC by mispositioning an RCS loop 4 drain

valve. This revealed itself through the subsequent transfer of RCS inventory to

the Reactor Coolant Drain Tank and lowering of RCS pressurizer level. The

30

Enclosure

error was promptly corrected by operations staff and the event was identified in

the licensees corrective action program as PER 115534. This finding is of very

low safety significance because it did not challenge RCS inventory control by

exceeding available makeup capacity.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

J. Adams, Boric Acid

D. Bodine, Chemistry/Environmental Manager

R. Bruno, Training Manager

R. Douet, Site Vice President

B. Dungan, Outage and Site Scheduling Manager

J. Epperson, Licensed Operator Requal Lead

J. Goulart, ISI

K. Jones, Site Engineering Manager

Z. Kitts, Licensing Engineer

D. Kulisek, Plant Manager

G. Morris, Licensing and Industry Affairs Manager

T. Niessen, Site Quality Manager

M. A. Palmer, Radiation Protection Manager

M. H. Palmer, Operations Manager

K. Parker, Maintenance and Modifications Manager

J. Proffitt, (Acting) Site Licensing Supervisor

J. Reisenbuechler, Operations Training Manager

R. Reynolds, Site Security Manager

N. Thomas, Licensing Engineer

S. Tuthill, Chemistry Operations Manager

J. Whitaker, ISI

K. Wilkes, Emergency Preparedness Manager

NRC personnel:

R. Bernhard, Region II, Senior Reactor Analyst

D. Pickett, Project Manager, Office of Nuclear Reactor Regulation

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000327,328/2006005-01

NCV

Failure to Certify Qualifications and Status

of Licensed Operators Were Current and

Valid (Section 1R11.3)

Opened

05000328/2006005-02

URI

Appendix R Manual Isolation Valve Failure

to Close Within the Required Time text

(Section 1R15)

Closed

05000327,328/2515/169

TI

Mitigating Systems Performance Index

Verification (Section 4OA5.4)

A-2

Attachment

Discussed

05000327, 328/2515/150

TI

Reactor Pressure Vessel Head and Vessel

Head Penetration Nozzles (NRC Order EA-

03-009) - Unit 2 (Section 4OA5.2)

05000327, 328/2515/166

TI

Pressurized Water Reactor Containment

Sump Blockage (NRC Generic Letter 2004-

02) - Unit 2 Section 4OA5.3)

Attachment

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

SPP-10.14, Freeze Protection, Revision 0

M&AI-27, Freeze Protection, Revision 12

0-PI-OPS-000-006.0, Freeze Protection, Revision 45

1-PI-EFT-234-706.0, Freeze Protection Heat Trace Functional Test, Revision 30

Section 1R02: Evaluation of Changes, Tests, or Experiments

Full Evaluations:

DCN D21640A, Radiation Monitors Are Being Deleted/Abandoned On Unit 1.

DCN D21641A, Radiation Monitors Are Being Deleted/Abandoned On Unit 2.

DCN D21854A, DG Starting Air PCV Modification.

DCN D21247A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C

Condensing Units With Digital Controls.

DCN D21248A, Replace The Existing Electrotechnical Controls For The MCR And EBR A/C

Condensing Units with Digital Controls.

FSAR Section 15.2.10, Revision to Section 15.2.10 of the FSAR containing the transient

analysis for feed water malfunction event.

TACF 1-05-013-R1, Temporary configuration change involving installation of non-nuclear safety

low volume high pressure pump into the SI System.

TACF 1-05-002-063, R1, Temporary installation of TVA Class B piping/tubing and check valve

downstream of 1-VLV-63-834 to provide RHRS pressure relief leakage.

FSAR Section 10.4.7 and 10.4.8, Proposed FSAR change to allow Steam Generator Blowdown

to remain in service for various reasons.

ES-1.3, R12, Revised ES-1.3 to modify guidance on stopping and restarting SI pump (PER 04-

000344-000).

Screened Out Items:

1-SI-OPS-000-003.M R32, Add Glycol Valves In Accordance With 06-NSS-061-035.

TI-28 REV 198, Procedure Revision On Unit 1 NIS Power Range Calibration Data

0-SI-OPS-068-137.0, Added Precaution And Limitation G To Section 3.2.

0-SO-14-4 Rev 10, Added Section 8.5 To Provide Instructions For Manual Operation Of

Temporary Sump Pump.

0-SO-77-11 R15, Revised To Add A Precaution To Monitor Waste Gas Vent Header

Frequently.

1-SO-63-1, Rev. 45, Revised section 8.1 step 6 of procedure to make the step conditional.

2-SI-OPS-000-003.M, Rev. 26, Added note 5 to exempt monthly valve stroke of the glycol valve

when the valve was stroked in the previous 7 days.

0-GO-14-4, R12, Revised to incorporate changes in accordance with NB 060785.

0-GO-5, Rev. 47, Revised step in section 5.4 concerning control rods, ref. NB 060297; added

step to section 5.1 concerning MFPT master controller output, ref. PER 100196-03.

1-AR-M1-A, Rev. 38, Revised in response to 060738 which provided additional information

regarding the inputs for Window A-5.

DCN D20960A, Sequoyah Independent Spent Fuel Storage Installation, (ISFSI).

0-SO-30-10, R31, Revised section 8.15 to provide guidance for Auxiliary Building Chill Water

Feed and Bleed when system is set up for winter operation.

A-4

Attachment

2-SI-TDC-068-254, Rev. 5, Surveillance instruction is being changed from 18 months to

conditional.

0-SO-70-1, R34, Added a step and caution to sections 8.5.2 and 8.5.4 to initiate a Work Order

to backfill affected flow transmitter following restoration of CCCS HX. 0B1 or 0B2 after

maintenance.

0-SO-77-1, Rev.40, Revised to provide guidance on the transfer of the Laundry and Hot

Shower Tank to the CDCT; moved guidance on re-circulation of the CDCT to new appendix E.

1-SI-OPS-000-003.M, R33, Revise note 18 in Appendix A of surveillance instruction to show

allowable channel deviation of less than or equal to 5%.

Problem Evaluation Reports (PERs):

84897, 0-PI-ECC-313-595.0 Cannot Be Performed As Currently Written

31739, Westinghouse Advisory Letter NASL-02-3 Describes A Process Measurement Uncertain

99597, Water In Waste Gas Vent Header During Resin Transfer

64337, DG 2-PCV-082-262 Blow Down

98255, MCR B Chiller Oil Temperature Swinging

65752, Specified Post Maintenance Testing Deficiencies

76900, S/G Blowdown Isolation of AFWP Start.

20195, ES 1.3, Transfer to RHR Containment Sump requires stopping the SI Pumps if RCS

pressure is greater than 1500 psig.

Work Orders:

6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE

6-771384-000, Replace the Oil Cooler TCV for the B MCR Chiller

Procedures:

TI-28, Rev. 198, Curve Book

0-SI-OPS-068-137.0, Rev. 19, Reactor Coolant System Water Inventory

1-SI-OPS-000-003.M, Rev. 32, Monthly Shift Log

1-SI-OPS-000-003.W, Rev. 37, Weekly Shift Log

0-SO-14-4, Rev. 10, Condensate Demineralizer waste Disposal

0-SO-77-11, Rev. 15, Waste Gas Compressor Operation

0-PI-ECC-313-595.0, Rev. 4, Periodic Calibration of Auxiliary Building Heating, Ventilating and

Air Conditioning

SPP - 9.4, 10 CFR 50.59 Evaluations of Changes, Tests and Experiments, Revision 7.

EN-1-102, 10 CFR 50.59 / 10 CFR 72.48, Reviews, Revision 7.

Miscellaneous Documents:

PMTI-SQN-21854, DG 1A-A Starting Air 5 Start Capacity Verification

SSD 1- L - 68-325, Low RCS Pressurizer Level

SSD 1 L - 68-326, High RCS Pressurizer Level.

SSD 2 -L -68-325, Low RCS Pressurizer Level

SSD 2- L - 68-326, High RCS Pressurizer Level.

NEI 96-07, Nuclear Energy Institute, Guidelines for 10 CFR 50.59 Implementation, Revision 1.

Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59 Changes, Tests and

Experiments, November 2000.

A-5

Attachment

Section 1R04: Equipment Alignment

1,2-47W810-1, Flow Diagram - Residual Heat Removal System, Revision 47

2-47W811-1, Flow Diagram - SI System, Revision 57

Section 1R05: Fire Protection

SQN Drawing 1,2-47W494-6 Fire Protection Compartmentation-Fire Cells Plan El. 669' & 685'

SQN Fire Protection Report Part II - Fire Protection Plan, Revision 20

SQN-26-D054/EPM-ABB-IMPFHA, SQN Fire Hazards Analysis Calculation, Appendix A

Spp-10.10, Control of Transient Combustibles, Revision 4

Section 1R07: Heat Sink Performance

PER 116021, Containment Spray Heat Exchangers Not in Chemical Layup

TVA Letter S64 950922 800, Program Update Regarding NRC GL 89-13 dated September 22,

1995

1,2-47W812-1, Flow Diagram Containment Spray System, Revision 42

Section 1R08: Inservice Inspection Activities

Programs/Procedures/Reports

2-SI-SXI-068-114.3, Steam Generator Tubing Inservice Inspection and Augmented Inspections,

Revision 2

Degradation Assessment for Sequoyah Unit 2 Cycle 14

Operational Assessment Report for Unit 2 Cycle 13 Refueling Outage

Self Assessment CRP-ENG-009 SQN ASME Section XI Program

Self Assessment 06SQN-12-ENG-XI ASME Section XI Inservice Inspection (ISI) Program

SQN-ENG-03-007 Boric Acid Program Effectiveness Assessment

SPP-9.7, Corrosion Control Program, Rev. 13

Technical Instruction 0-TI-DXX-000-097.1, Rev. 01, Boric Acid Corrosion Control Program

BP-257, Rev. 5, TVA Business Practice, Integrated Material Issues Management Plan,

Appendix A

Proc. No. N-UT-76, Rev. 6, Generic Procedure for Ultrasonic Examination of Ferritic Pipe

Welds.

Proc. No. N-UT-64, Rev. 9, Generic Procedure For The UT Examination of Austenitic Pipe

Welds

Proc. No. N-VT-1, Visual Examination Procedure for ASME Section XI Preservice and Inservice

Proc. No. N-VT-15, Rev. 5, Visual Examination of Class MC and Metallic Liners of Class CC

Components of Light-Water Cooled Plants

SQN Unit 2 Examination Schedule 0-SI-DXI-115.3, Att.5

Design Change Package 22061, Pressurizer Safe End Weld Overlays

WO # 06-775288-002, Pressurizer Safe End Weld Overlays

Vendor Instruction 0-VI-MOD-068-001

Welding Services Traveler 103804-001

A-6

Attachment

Corrective Action (PERS)

03-017128-000, NRC inspectors concern that a GAP between the support steel and the pipe

indicated that the dead weight was not being supported.

20732, NRC inspector expressed concern that the NDE procedure N-VT-1 does not address

GAPS observed during hanger inspections.

107387, Borated Water Leak on lower flange of 20LCV-62-1`8, Boron is dry

100794, 2A Containment Spray Pump outboard Seal leak.

106740, Boric Acid Corrosion on support for SQN-2-VLV-063-0578

90714, 2-FCV-63-156 packing leak

81632, Leakage observed on pressurizer safe-ends RCW-25-SE and RCW-26-SE.

Section 1R11: Licensed Operator Requalification

Quarterly Review

AOP-I.08, Turbine Impulse Pressure Instrument Malfunction, Revision 8

FR-S.1, Function Restoration Procedure - Nuclear power Generation/ATWS, Revision 20

E-0, Reactor Trip or SI, Revision 27

ES-0.1, Reactor Trip Response, Revision 30

Biennial Review

Procedures and Records

TRN 11.4 Continuing Training For Licensed Personnel, Rev. 11.

TRN 1 Administering Training, Rev 17.

OPDP-1 Conduct of Operations, Appendix 0, License Status-Active/Inactive License, Rev. 6.

Operations Directive Manual, Appendix B-Qualifications Tracking Requirements, Rev. 2.

Badge Access Transaction Reports

Licensed Operator Medical Records

Remedial Training Records

Written Exams: A3 RO Exam and A3 SRO Exam.

Simulator Work Request - PR4542

LER 2005-001-00 Units 1 and 2

LER 2005-002-00 Unit 2

LER 2006-001-00 Units 1and 2

Job Performance Measures

JPM 163 Steam line Pressure Transmitter fails low.

JPM 33AP Manual Control of AFW Following a Reactor Trip.

JPM 12 Pressurizer Level Control Malfunction.

JPM 59 Establish Excess Letdown.

JPM 80" Local Control of Charging Flow.

JPM 61A2 Transfer 480V SD Board 2A1-A From Normal to Alternate Supply.

JPM 72 Local Alignment of 1-RM-90-112 to Lower Containment.

JPM 32AP Local Manual Control of S/G PORV.

JPM 6 Perform Boration of the RCS From Outside the Main Control Room.

JPM 78 AP Respond to an ATWS Trip the Reactor Locally.

A-7

Attachment

Simulator Scenarios:

S-13 Uncontrolled Depressurization of All Steam Generators. Rev 12.

S-7 Pressurizer Vapor Space Accident. Rev 15.

S-11 LOCA with Loss of RHR Recirculation. Rev 13.

Simulator Malfunction Tests:

ED15 Loss of 250VDC Battery Board.

IA03

FW23

FW20

ED08

ED10

Transient Tests:

  1. 2 Both Main Feedwater Pumps Trip , AFW fails to start.
  1. 5 Trip of Any Single Reactor Coolant Pump.
  1. 8 Loop 2 Cold-Leg Large Break LOCA with Loss of Offsite Power.
  1. 9 Main Steam Line Break Inside Containment.
  1. 10 Slow RCS Depressurization to Saturation.

Normal Tests:

2005 Steady State Operation Drift Test

2005 Steady State Operation Static Test for 100%, 66%, and 44% power.

Section 1R12: Maintenance Effectiveness

TI-4, Maintenance Rule Performance Indicator Monitoring, Trending, and Reporting - 10 CFR 50.65, Revision 19

Section 1R13: Maintenance Risk Assessments and Emergent Work Evaluation

Sentinel Run, October 23 to November 12, 2006

SQN Plan-of-the-Day, October 26, 2006

SQN MSS-OPS Daily Schedule Report 24 Hour Look-Ahead, October 25, 2006

Sentinel Risk Assessment for Failed EDG 2B-B

Section 1R15: Operability Evaluations

0-SI-SFT-311-001.A, Control Room Air-Conditioning System Train A, Revision 1

UFSAR Section 6.4, Habitability Systems

UFSAR Section 9.4, Heating, Ventilating, and Air-Conditioning

FE 41643, Observed Air Flow Above Design Flow For MCR A Air Handling Unit

1,2-47W866-4, Flow Diagram Heating, Ventilation and Air-Conditioning - Control Building,

Revision 3

1,2-47W867-2, Mechanical Air-Conditioning Control Diagram - Control Building, Revision 12

B87 951205 003, ERCW Screen Wash System Hydraulic Analysis, Revisions 2 and 3

0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test, Revision 8

A-8

Attachment

0-SO-67-1, Essential Raw Cooling Water, Revision 63

1,2-45N765-1, Wiring Diagram 6900V Shutdown Aux Power Schematic Diagram SH-1,

Revision 14

1,2-45N765-2, Wiring Diagram 6900V Shutdown Aux Power Schematic Diagram SH-2,

Revision 20

WO 04-774974-000, Replace Emergency Diesel Generator 2B-B Breaker

1,2-47W809-1, Flow Diagram Chemical & Volume Control System

1-108D273-18, Process Control Block Diagram Turbine Impulse Pressure Protection Sets I and

II, Revision 0

Section 1R17: Permanent Plant Modifications

Problem Evaluation Reports (PERs):

31739, Westinghouse Advisory Letter NASL-02-3 Describes A Process Measurement Uncertain

65752, Specified Post Maintenance Testing Deficiencies

84070, Diesel Generator 1A-A cable testing.

103766, Main Bank Transformer 1B Hot Spots

104337, Main Bank Transformer 1B Hot Spot

Calculations:

Calculation No. SQN- APS - 042, 480 V Turbine Building Common Board Load Coordination,

Short Circuit, Circuit Protection and Voltage Drop Analysis, Revision 4.

Calculation No. SQN-APS-041, 480 VAC Unit Board Load Coordination Study, Revision 4.

Work Orders:

6-771849-000, Check TE Accuracy, if unsatisfactory, Then Replace the TE

2-002298-000, Westinghouse Advisory Letter NSAL-02-3

03-012340-001, Replace degraded portion of 6900 V Diesel Generator 1A-A power cable

PP351A between Unit 1 Additional Equip. Bldg. And D/G exciter cubicle.

03-012340-002, Install section of new replacement cable PP351A from AEB-1 to MH-14 via

existing conduit.

Miscellaneous Documents:

Westinghouse Advisory Letter NSAL-03-9

ABB Power T&D- Sequoyah Nuclear Plant Final Report Main Generator Transformer Life

Assessment.

Drawings:

Drawing No. 1, 2-3591A28, Breaker Setting Sheet 480 V Unit Board 1A, Revision 5

Drawing No. 1, 2-3591A30, Breaker Setting Sheet 480 V Unit Board 1B, Revision 6.

Drawing No. 1, 2-3591A32, Breaker Setting Sheet 480 V Unit Board 2A, Revision 6.

Drawing No. 1, 2-3591A34, Breaker Setting Sheet 480 V Unit Board 2B, Revision 5

Drawing No. 1, 2-3591A36, Breaker Setting Sheet 480 V Turb. Building Common Board,

Revision 9 Drawing No. 1, 2-15E500-1, Key Diagram Station Auxiliary Power, Revision 25

Drawing No. 1, 2-15E500-3, Transformer Taps and Voltage Limits - Auxiliary Power System,

Revision 16.

Drawing No. 1-45N1504, Wiring Diagrams - Main Single Line 500 KV Switchyard, Revision 29

A-9

Attachment

Drawing No. 1-45W1541, Wiring Diagrams AC Schematic Unit 1 Generator & transformer

Circuits, Revision 14

Procedures:

TI-28, Rev. 198, Curve Book

PER Written Because of Inspection Finding

114743, Superseded ARP revision found in ACR

Section 1R19: Post Maintenance Testing

PER 115780, 2-FCV-74-28 Did Not Appear To Fully Open

2-SI-SXP-074-202.A, RHR Pump 2A-A Performance and Discharge Check Valve Test,

Revision 0

WO 06-780773-000, Calibrate 2-FCV-74-28 and Limit Switches

Section 1R20: Refueling and Outage Activities

0-GO-6, Power Reduction from 30& Reactor Power to Hot Standby, Revision 32

0-GO-7, Unit Shutdown From Hot Standby to Cold Shutdown, Revision 47

0-GO-15, Containment Closure Control, Revision 21

DVD Recording of U2C14 Core Load Verification

1,2-47W812-1, Flow Diagram Containment Spray System, Revision 42

Tagout Clearance 2-72-2406-RFO, Motor Operated Valve Maintenance on 2-FCV-72-21

0-GO-13, Reactor Coolant System Drain and Fill Operations, Revision 54

Sequoyah Nuclear Plant Unit 2 Cycle 15 Core Operating Limits Report

Section 1R22: Surveillance Testing

SPP-8.1 Conduct of Testing, Rev 4

Section 1EP6: Drill Evaluation

NEI 99-02 Rev 0, March 2000

Emergency Plan Implementing Procedure (EPIP) - 1, Emergency Plan Classification Matrix,

Rev 37

EPIP-3, Alert, Rev 29

EPIP-4, Site Area Emergency, Rev 29

EPIP-5, General Emergency, Rev 36

EPIP-6, Technical Support Center, Rev 41

EPIP-7, Operations Support Center, Rev 25

Section 2OS1: Access Control To Radiologically Significant Areas

Procedures, Instructions, Guidance Documents, and Operating Manuals

ANSI/ANS 3.1-1987, Selection, Qualification, and Training of Personnel for Nuclear Power

Plants

Tennessee Valley Authority (TVA), TVA Nuclear (TVAN), Standard Programs and

A-10

Attachment

Processes (SPP) - 3.1, Corrective Action Program, Rev. 11

Active Radiation Work Permits (RWPs) List, dated 12/11/2006

RP Personnel Identification by Craft Report, dated 12/14/2006

Task Qualification List (selected individuals), dated December 14, 2006

LHRA Key Control Log Sheets (several pages)

TVA, TVAN, TRN-20, Health Physics Technician Training, Rev. 13

High Radiation Areas at Sequoyah List, document not dated

SNP RP Organizational Chart (current and proposed changes), document not dated.

TVAN Radiation Protection Peer Team Challenge Update (MS Power Point presentation),

dated 12/13/2006

TVA, TVAN, SPP-5.2, ALARA Program, Rev. 3

RWP 06027010, Rev. 0, Routine Plant Maintenance-Lower Containment All Areas

RWP 06027035, Rev. 0, Routine Plant Maintenance-Inside Polar Crane All Areas

RWP 06027390, Rev. 1, Routine Plant Maintenance-Accumulator 1-4

RWP 06037020, Rev. 0, Inservice Inspection-Steam Generator Primary Side 1-4

RWP 06047141, Rev. 0, Refueling-U-2 Reactor Cavity

TVA, Sequoyah Nuclear Plant (SNP), Radiological Control Instruction (RCI)-01, Radiation

Protection Program

TVA, SNP, RCI-01, Training and Qualification of Health Physics Technicians-Radiation

Operations Technicians, effective date 02/24/05

TVA, SNP, RCI-14, Radiation Work Permit (RWP) Program, Rev. 37

TVA, SNP, RCI-15, Radiological Postings, Rev. 15

TVA, SNP, RCI-24, Control of Very High Radiation Areas, Rev. 7

TVA, SNP, RCI-28, Control of Locked High Radiation Areas, Rev. 5

TVA, SNP, RCI-29, Control of Radiation Protection Keys, Rev. 4

Records and Data Reviewed

SNS VSDS Survey Nos. 120506-2, 120606-8, 120506-15, 120606-10, 120606-7, 120706-2,

120106-10, 120606-6, and 120306-4

Air Sample Survey Nos. 120406018, 120506021, 120506024, 120506034, 120506037,

120506045, 120506048, 120506053, 120606020, 120706010,120406024, 120606028,

120506012, and 120606043

Corrective Action Program Documents

Nuclear Assurance (NA) - TVAN-Wide - Audit Report No. SSA0502 - Radiological Protection

and Control Audit, dated January 19, 2006

SQN-RP-05-001, Self-Assessment Report, dated 12/22/04

SQN-RP-05-003, Self-Assessment Report, dated 7/29/05

Problem Evaluation Report (PER) 82569, Presently U-1 Lower Containment Has a Ladder.

PER 115944, The Total Nozzle Dam Jumpers Dose Was Greater than the ALARA estimate

PER 101211, Posting and Control of Filter Cubicles...

PER 113913, Lock Box for Lifting Device Control

PER 109603, Radiation Posting

PER 109604, Radcon Use of Industry Information

PER 87610, Key Taken Home

PER 82027, High Radiation Readings on Valve

PER 82643, Unexpected Radiation Level Change

A-11

Attachment

PER 84532, VHRA Key Inventory

PER 99226, Locked High Radiation Door Locks Sticking

Section 4OA5: Other Activities - Operation of ISFSI

NEI 96-07, Guidelines for 10 CFR 72.48 Implementation, Appendix B

SPP-9.9, 10 CFR 72.48 Evaluations of Changes, Tests, and Experiments for Independent

Spent Fuel Storage Installation, Revision 1

Regulatory Guide 3.72 - Guidance for Implementation of 10 CFR 72.48, Changes, Tests and

Experiments

PER 95624, MPC-0011 Lid Did Not Fully Seat Due to Upper Fuel Spacers Not Vertical or

Plumb

10 CFR 48 Evaluation, Response to NRC IN 2003-16

10 CFR 48 Procedure Change Evaluation, Revision of NFTP-100, Fuel Selection for Dry MPC

Storage

10 CFR 48 Screening, Auxiliary Building Crane Truck Repairs

10 CFR 48 Screening, Auxiliary Building Crane Truck Replacements

10 CFR 48 Screening, Revision to Welding Procedures

10 CFR 48 Screening, Procedure Change to Fuel Handling Instruction FHI-14

10 CFR 48 Screening, Procedure Change to Fuel Handling Instruction FHI-3

Section 4OA5: Other Activities - TI 2515/150

Procedures

0-PI-DXX-068-100.R, Monitoring of Reactor Head Canopy Seal Welds For Leakage, Rev. 1

54-ISI-603-002, Automated Ultrasonic Examination of RPV Closure Head Penetrations

Containing Thermal Sleeves

54-ISI-604-001, Automated Ultrasonic Examination of Open Tube RPV Closure Head

Penetrations

54-ISI-605-02, Automated Ultrasonic Examination of RPV Closure Head Small Bore

Penetrations

54-ISI-240-44, Visible Solvent Removable Liquid Penetrant Examination Procedure

N-VT-17, Visual Examination for Leakage of PWR Reactor Head Penetrations, Rev. 4

SPP-9.7, Corrosion Control Program, Appendix D, Technical Requirements for the Boric Acid

Corrosion Control Program, Rev. 13

Records/Reports/Engineering Documents

Equipment Certification Records for the following NDE Equipment:

Blade Probes: S1035 NL, S5002 NL, and S5001 NL

Ultrasonic Transducers: 21GB-06001 and 2078-06001

Engineering Information Record 51-9027415-000, RPV Head Penetration Inspection Plan and

Coverage Assessment for Sequoyah Units 1 and 2

Calculation C-3217-00-02, Sequoyah 1 and 2 CRDM and Instrument Column Nozzle Stress

Analysis

Letter L44 030227 801, Response to issuance of NRC Order

A-12

Attachment

Corrective Action Documents

PER 115561, Evidence of leakage during canopy seal weld inspection

PER 116540*, EDY calculation not performed every outage

PER 116165*, Transducer frequencies documented incorrectly

  • Problem Evaluation Reports generated as a result of this inspection

Section 4OA5: Other Activities - TI 2515/166

Surveillance Instruction 2-SI-SIN-063-009-02, Containment Sump Inspection, dated 11/08/06

DCN 22023, Modify Containment Sump Screens as required by NEI Methodology, dated

11/22/06

Amendment to Facility Operating License No. 302, DPR-79, Revised Transport Analysis

Methodology for Containment Debris Transport, dated 11/07/06

TVA letter to NRC, Sequoyah Response to GL 2004-02. dated 9/01/05

AREVA document No. 51-9008500-003, Test Report for Sure-Flow strainer (Prototype)

Headloss Evaluation for Sequoyah 1 & 2 ECCS Containment Sumps, dated 7/26/06

AREVA document No. 51-9008506-001, Sequoyah Advanced Design Reactor Building Sump

Strainer Test Results Summary, Units 1 & 2, dated 1/31/06

GL 2004-02 Supplemental Response, Sequoyah Nuclear Plant Units 1 & 2, - NRC GL 2004-02,

Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis

Accidents at PWRs (Draft dated 12/15/06)

Calculation ALION-CAL-TVA-2740-05, SQN Units 1 & 2 Containment Sump Debris

Accumulation and Head Loss, dated 6/28/05

Calculation TDI-6009-02, SFS Surface Area Flow Volume - TVA/Sequoyah 1 & 2, dated

9/21/06

MDQ0072980034, "CCP, SIP, CSP, and RHR Pump NPSH Evaluation", Rev 1, 11/19/2006

DCN # D22023, "Modify Containment Sump Screens as Required by NEI Methodology", Rev A,

11/22/2006

Calculation TDI-6009-004, "Module Debris Weight - TVA/Sequoyah - 1/2", Rev 2, 10/13/2006

Calculation PCI-5465-S01, "Structural Evaluation of Advanced Design Containment Building

Sump Strainers", Rev 0, 10/20/2006

Routine Work Order 06-774811-000, "Containment RHR Sump 48N919", Rev 5

FME Accountability Log, SPP 6.5.1

Section 4OA5: Other Activities - TI 2515/169

Procedures, Manuals, and Guidance Documents

NEI 99-02, Mitigating System Performance Index (MSPI) Basis Document, Revision 1

Selected System Status Reports

0-SI-SXV-063-266.0, ASME Section XI Valve Testing

1,2-SI-SXV-000-201.0, Full Stroking of Category A and B Valves During Operation

0-SI-SXV-074-266.0, ASME Section XI Valve Testing

1,2-SI-OPS-074-128.0, RHR Discharge Piping Vent

1-SI-SXP-074-074-201.B, RHR Pump 1B-B Performance Test

2-SI-SXP-074-074-201.B, RHR Pump 1B-B Performance Test

0-SI-SXV-000-221.0, Full Stroking of the Common ERCW and CCS Category A and B

Valves During Operation

A-13

Attachment

0-SI-OPS-067-682.Q, ERCW Non-Safety Related Flow Balance Valve Position Verification

0-SI-SXP-067-202.B, ERCW Traveling Screen Wash Pump B-B Performance Test

2-SI-OPS-070-32.A, Component Cooling Water Valves Position Verification Train A

Records and Data

Selected Control Room Logs, January 2004 through December 2006

EDG NRC Performance Indicators, 2002 - 2005

AFW NRC Performance Indicators, 2002 - 2005

HPSI NRC Performance Indicators, 2002 - 2005

RHR NRC Performance Indicators, 2002 - 2005

Consolidated Data Entry MSPI Derivation Reports Generated November 2006

MSPI Equipment Functional Failure Data Sheets

Maintenance Rule Unavailability Data Sheets, 2002-2006

Maintenance Rule Unreliability Data Sheets, 2002-2006

Corrective Action Program Documents

Selected Corrective Action Reports, 2005-2006

Attachment

LIST OF ACRONYMS

AFW

auxiliary feedwater

ANSI

American National Standards Institute

AOP

abnormal operating procedures

ARC

alternate repair criteria

ASME

American Society of Mechanical Engineers

ATWS

anticipated transient without scram

AUO

auxiliary unit operator

BACC

boric acid corrosion control

BMV

bare metal visual

CCP

cooling charging pump

CCPIT

cooling charging pump injection tank

CFR

Code of Federal Regulations

CR

condition report

CRDM

control rod drive mechanism

CVCS

chemical volume control system

DCN

design change notice

ECCS

emergency core cooling system

ECT

eddy current testing

EDY

effective degradation years

ERCW

essential raw cooling water

ETSS

examination technique specifications sheet

FCV

flow control valve

FE

functional evaluation

FME

foreign material exclusion

FOSAR

foreign object search and recovery

HR

high radiation

HUT

holdup tank

INPO

Institute of Nuclear power Operations

ISFSI

independent spent fuel storage installation

ISI

inservice inspection

LHRA

locked high radiation area

MRP

materials reliability program

MSPI

mitigating systems performance index

NCV

non-cited violation

NDE

non-destructive examination

NRC

U.S. Nuclear Regulatory Commission

ODSCC

outer diameter stress corrosion cracking

OPDP

operations department procedure

PAR

publically available records

PER

problem evaluation report

PER

protective action recommendation

PORV

power-operated relief valve

PWSCC

primary water stress corrosion cracking

RCP

reactor coolant pump

RCS

reactor coolant system

RHR

residual heat removal

RP

radiation protection

A-15

Attachment

RPVH

reactor pressure vessel head

RTP

rated thermal power

RWP

radiation work permit

RWST

refueling water storage tank

SDP

significance determination process

SER

safety evaluation report

SG

steam generator

SI

safety injection

SI

surveillance instructions

SSC

structure, system, or component

TDAFP

turbine driven auxiliary feedwater pump

TI

temporary instruction

TS

technical specification

TVA

Tennessee Valley Authority

UFSAR

updated final safety analysis report

UHI

upper head injection

URI

unresolved item

UT

ultrasonic testing

WOs

work orders