ML070670259: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (One intermediate revision by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML070670259 | | number = ML070670259 | ||
| issue date = 03/01/2007 | | issue date = 03/01/2007 | ||
| title = | | title = Public Meeting Slides, Re Regulatory Conference, Duane Arnold Exercise Critique Finding | ||
| author name = | | author name = | ||
| author affiliation = NRC/RGN-III | | author affiliation = NRC/RGN-III | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Regulatory Conference Duane Arnold Exercise Critique Finding Nuclear Regulatory Commission - Region III Lisle, Illinois March 1, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | {{#Wiki_filter:Regulatory Conference Regulatory Conference Duane Arnold Exercise Critique Finding Duane Arnold Exercise Critique Finding Nuclear Regulatory Commission Nuclear Regulatory Commission -- Region III Region III Lisle, Illinois Lisle, Illinois March 1, 2007 March 1, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | ||
Agenda Introduction and Opening Remarks | Agenda Agenda Introduction and Opening Remarks Introduction and Opening Remarks A. Boland A. Boland Overview of Inspection Finding Overview of Inspection Finding K. | ||
* Performance Deficiency | K. Riemer Riemer | ||
* Significance Determination Process | ** Performance Deficiency Performance Deficiency | ||
* Apparent Violation Licensee Presentation | ** Significance Determination Process Significance Determination Process | ||
** Apparent Violation Apparent Violation Licensee Presentation Licensee Presentation G. | |||
G. VanMiddlesworth VanMiddlesworth NRC Caucus NRC Caucus Closing Remarks Closing Remarks A. Boland A. Boland Public Comments Public Comments A. Boland A. Boland The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | |||
Performance Deficiency October 18, 2006, NRC Evaluated Full Scale Exercise | Performance Deficiency Performance Deficiency October 18, 2006, NRC Evaluated Full Scale October 18, 2006, NRC Evaluated Full Scale Exercise Exercise | ||
* The Licensees Critique Failed To Identify The Operators Performance Weakness | ** The Licensees Critique Failed To Identify The Operators The Licensees Critique Failed To Identify The Operators Performance Weakness Performance Weakness | ||
* Inspectors Observed Indications Were Available In The Simulator At 10:50 am That SAE EAL Threshold Had Been Met | ** Inspectors Observed Indications Were Available In The Inspectors Observed Indications Were Available In The Simulator At 10:50 am That SAE EAL Threshold Had Been Met Simulator At 10:50 am That SAE EAL Threshold Had Been Met | ||
* Indications Were That Two Valve Indications Changed, Were Potentially Not Closed, And A Pathway To The Environment Existed | ** Indications Were That Two Valve Indications Changed, Were Indications Were That Two Valve Indications Changed, Were Potentially Not Closed, And A Pathway To The Environment Potentially Not Closed, And A Pathway To The Environment Existed Existed | ||
* TSC Called The Simulator To Verify An Increase In The Stack Vent Radiological Release Rate And A Possible Release Path | ** TSC Called The Simulator To Verify An Increase In The Stack TSC Called The Simulator To Verify An Increase In The Stack Vent Radiological Release Rate And A Possible Release Path Vent Radiological Release Rate And A Possible Release Path | ||
* The Licensees SAE Declaration was delayed until 11:11 a.m. | ** The Licensees SAE Declaration was delayed until 11:11 a.m. | ||
The Licensees SAE Declaration was delayed until 11:11 a.m. | |||
The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | ||
Safety Significance Determination (Preliminary) | Safety Significance Determination Safety Significance Determination (Preliminary) | ||
Significance Determination Process, IMC 0609 App. B | (Preliminary) | ||
* A loss of planning standard function occurred when the exercise critique process failed to identify the operators performance as a weakness associated with a risk significant planning standard | Significance Determination Process, IMC 0609 App. B Significance Determination Process, IMC 0609 App. B | ||
* The identification and correction of weaknesses is fundamentally important to the EP Cornerstone Objective | ** A loss of planning standard function occurred when the A loss of planning standard function occurred when the exercise critique process failed to identify the operators exercise critique process failed to identify the operators performance as a weakness associated with a risk significant performance as a weakness associated with a risk significant planning standard planning standard | ||
* Unsuccessful DEP PI Opportunity For The SAE Classification Preliminary White Finding and Apparent Violation of 10 CFR 50.47(b)(14) & Appendix E, Section IV.F.2.g, issued on January 19, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | ** The identification and correction of weaknesses is The identification and correction of weaknesses is fundamentally important to the EP Cornerstone Objective fundamentally important to the EP Cornerstone Objective | ||
** Unsuccessful DEP PI Opportunity For The SAE Classification Unsuccessful DEP PI Opportunity For The SAE Classification Preliminary White Finding and Apparent Violation of Preliminary White Finding and Apparent Violation of 10 CFR 50.47(b)(14) & Appendix E, Section IV.F.2.g, 10 CFR 50.47(b)(14) & Appendix E, Section IV.F.2.g, issued on January 19, 2007 issued on January 19, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action | |||
Apparent Violation Failure to meet requirement | Apparent Violation Apparent Violation Failure to Failure to meet meet requirement requirement | ||
* 10 CFR 50.47(b)(14), requires exercises to be conducted | ** 10 CFR 50.47(b)(14), requires exercises to be 10 CFR 50.47(b)(14), requires exercises to be conducted and deficiencies identified to be corrected conducted and deficiencies identified to be corrected | ||
* 10 CFR 50, App. E, Section IV.F.2.g, requires exercises to provide formal critiques to identify weak or deficient areas that need correction | ** 10 CFR 50, App. E, Section IV.F.2.g, requires exercises 10 CFR 50, App. E, Section IV.F.2.g, requires exercises to provide formal critiques to identify weak or deficient to provide formal critiques to identify weak or deficient areas that need correction areas that need correction | ||
* 10 CFR 50.47(b)(4), requires a standard EAL scheme to be in in use by the licensee and State and local response plans call for reliance on licensee information for initial offsite response measures | ** 10 CFR 50.47(b)(4), requires a standard EAL scheme to 10 CFR 50.47(b)(4), requires a standard EAL scheme to be in in use by the licensee and State and local response be in in use by the licensee and State and local response plans call for reliance on licensee information for initial plans call for reliance on licensee information for initial offsite response measures offsite response measures | ||
* Failure to identify the performance weakness during the critique The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action}} | ** Failure to identify the performance weakness during the Failure to identify the performance weakness during the critique critique The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action}} | ||
Latest revision as of 02:53, 15 January 2025
| ML070670259 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 03/01/2007 |
| From: | NRC/RGN-III |
| To: | |
| References | |
| EA-07-001 | |
| Download: ML070670259 (5) | |
Text
Regulatory Conference Regulatory Conference Duane Arnold Exercise Critique Finding Duane Arnold Exercise Critique Finding Nuclear Regulatory Commission Nuclear Regulatory Commission -- Region III Region III Lisle, Illinois Lisle, Illinois March 1, 2007 March 1, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action
Agenda Agenda Introduction and Opening Remarks Introduction and Opening Remarks A. Boland A. Boland Overview of Inspection Finding Overview of Inspection Finding K.
K. Riemer Riemer
- Performance Deficiency Performance Deficiency
- Significance Determination Process Significance Determination Process
- Apparent Violation Apparent Violation Licensee Presentation Licensee Presentation G.
G. VanMiddlesworth VanMiddlesworth NRC Caucus NRC Caucus Closing Remarks Closing Remarks A. Boland A. Boland Public Comments Public Comments A. Boland A. Boland The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action
Performance Deficiency Performance Deficiency October 18, 2006, NRC Evaluated Full Scale October 18, 2006, NRC Evaluated Full Scale Exercise Exercise
- The Licensees Critique Failed To Identify The Operators The Licensees Critique Failed To Identify The Operators Performance Weakness Performance Weakness
- Indications Were That Two Valve Indications Changed, Were Indications Were That Two Valve Indications Changed, Were Potentially Not Closed, And A Pathway To The Environment Potentially Not Closed, And A Pathway To The Environment Existed Existed
- The Licensees SAE Declaration was delayed until 11:11 a.m.
The Licensees SAE Declaration was delayed until 11:11 a.m.
The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action
Safety Significance Determination Safety Significance Determination (Preliminary)
(Preliminary)
Significance Determination Process, IMC 0609 App. B Significance Determination Process, IMC 0609 App. B
- A loss of planning standard function occurred when the A loss of planning standard function occurred when the exercise critique process failed to identify the operators exercise critique process failed to identify the operators performance as a weakness associated with a risk significant performance as a weakness associated with a risk significant planning standard planning standard
- Unsuccessful DEP PI Opportunity For The SAE Classification Unsuccessful DEP PI Opportunity For The SAE Classification Preliminary White Finding and Apparent Violation of Preliminary White Finding and Apparent Violation of 10 CFR 50.47(b)(14) & Appendix E,Section IV.F.2.g, 10 CFR 50.47(b)(14) & Appendix E,Section IV.F.2.g, issued on January 19, 2007 issued on January 19, 2007 The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action
Apparent Violation Apparent Violation Failure to Failure to meet meet requirement requirement
- 10 CFR 50.47(b)(14), requires exercises to be 10 CFR 50.47(b)(14), requires exercises to be conducted and deficiencies identified to be corrected conducted and deficiencies identified to be corrected
- 10 CFR 50, App. E,Section IV.F.2.g, requires exercises 10 CFR 50, App. E,Section IV.F.2.g, requires exercises to provide formal critiques to identify weak or deficient to provide formal critiques to identify weak or deficient areas that need correction areas that need correction
- 10 CFR 50.47(b)(4), requires a standard EAL scheme to 10 CFR 50.47(b)(4), requires a standard EAL scheme to be in in use by the licensee and State and local response be in in use by the licensee and State and local response plans call for reliance on licensee information for initial plans call for reliance on licensee information for initial offsite response measures offsite response measures
- Failure to identify the performance weakness during the Failure to identify the performance weakness during the critique critique The apparent violations discussed in this predecisional regulatory conference are subject to further review and are subject to change prior to any resulting enforcement action