ML080310073: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (One intermediate revision by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML080310073 | | number = ML080310073 | ||
| issue date = 02/28/2008 | | issue date = 02/28/2008 | ||
| title = Technical Specifications, Issuance of Amendments Safety Limit Minimum Critical Power Ratio | | title = Technical Specifications, Issuance of Amendments Safety Limit Minimum Critical Power Ratio | ||
| author name = | | author name = | ||
| author affiliation = NRC/NRR/ADRO/DORL/LPLIII-2 | | author affiliation = NRC/NRR/ADRO/DORL/LPLIII-2 | ||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:SLs 2.0 2.0 | {{#Wiki_filter:SLs 2.0 Quad Cities 1 and 2 2.0-1 Amendment No. | ||
THERMAL POWER shall be | 2.0 SAFETY LIMITS (SLs) 2.1 SLs 2.1.1 Reactor Core SLs 2.1.1.1 With the reactor steam dome pressure < 785 psig or core flow < 10% rated core flow: | ||
2.1.1.2 | THERMAL POWER shall be 25% RTP. | ||
For two recirculation loop operation, MCPR shall be 1.11, or for single recirculation loop operation, MCPR shall be | 2.1.1.2 With the reactor steam dome pressure 785 psig and core flow 10% rated core flow: | ||
2.1.1.3 | For two recirculation loop operation, MCPR shall be 1.11, or for single recirculation loop operation, MCPR shall be 1.13. | ||
2.1.2 | 2.1.1.3 Reactor vessel water level shall be greater than the top of active irradiated fuel. | ||
2.2 | 2.1.2 Reactor Coolant System Pressure SL Reactor steam dome pressure shall be 1345 psig. | ||
2.2.1 | 2.2 SL Violations With any SL violation, the following actions shall be completed within 2 hours: | ||
2.2.1 Restore compliance with all SLs; and 2.2.2 Insert all insertable control rods.}} | |||
Latest revision as of 18:27, 14 January 2025
| ML080310073 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 02/28/2008 |
| From: | NRC/NRR/ADRO/DORL/LPLIII-2 |
| To: | |
| Wiebe, J | |
| Shared Package | |
| ML080280231 | List: |
| References | |
| TAC MD7374, TAC MD7375 | |
| Download: ML080310073 (1) | |
Text
SLs 2.0 Quad Cities 1 and 2 2.0-1 Amendment No.
2.0 SAFETY LIMITS (SLs) 2.1 SLs 2.1.1 Reactor Core SLs 2.1.1.1 With the reactor steam dome pressure < 785 psig or core flow < 10% rated core flow:
THERMAL POWER shall be 25% RTP.
2.1.1.2 With the reactor steam dome pressure 785 psig and core flow 10% rated core flow:
For two recirculation loop operation, MCPR shall be 1.11, or for single recirculation loop operation, MCPR shall be 1.13.
2.1.1.3 Reactor vessel water level shall be greater than the top of active irradiated fuel.
2.1.2 Reactor Coolant System Pressure SL Reactor steam dome pressure shall be 1345 psig.
2.2 SL Violations With any SL violation, the following actions shall be completed within 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />s:
2.2.1 Restore compliance with all SLs; and 2.2.2 Insert all insertable control rods.