ML081650090: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:June 13, 2008  
                                NUC LE AR RE G UL AT O RY C O M M I S S I O N
                                                    R E GI ON I V
                                        612 EAST LAMAR BLVD , SU I TE 400
                                        AR LI N GTON , TEXAS 76011-4125
EA 07-204  
                                            June 13, 2008
EA 07-204
Stewart B. Minahan
Stewart B. Minahan
Vice President-Nuclear and CNO
Vice President-Nuclear and CNO  
Nebraska Public Power District
Nebraska Public Power District  
P.O. Box 98
P.O. Box 98  
Brownville, NE 68321
Brownville, NE 68321  
SUBJECT:       FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND
SUBJECT:  
                NOTICE OF VIOLATION, NRC INSPECTION REPORT 05000298/2008008,
FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND  
                COOPER NUCLEAR STATION
NOTICE OF VIOLATION, NRC INSPECTION REPORT 05000298/2008008,  
Dear Mr. Minahan:
COOPER NUCLEAR STATION  
The purpose of this letter is to provide you the final results of our significance determination of
Dear Mr. Minahan:  
the preliminary Greater than Green finding identified in the Nuclear Regulatory Commission
The purpose of this letter is to provide you the final results of our significance determination of  
(NRC) Inspection Report 05000298/2008007. The inspection finding was assessed using the
the preliminary Greater than Green finding identified in the Nuclear Regulatory Commission  
significance determination process and was preliminarily characterized as a finding of greater
(NRC) Inspection Report 05000298/2008007. The inspection finding was assessed using the  
than very low safety significance resulting in the need for further evaluation to determine the
significance determination process and was preliminarily characterized as a finding of greater  
significance and, therefore, the need for additional NRC action.
than very low safety significance resulting in the need for further evaluation to determine the  
Our preliminary finding was discussed with your staff during an exit meeting on March 18, 2008.
significance and, therefore, the need for additional NRC action.
The finding involved two procedures used by operators to bring the plant to a safe shutdown
Our preliminary finding was discussed with your staff during an exit meeting on March 18, 2008.
condition in the event of certain postulated fire scenarios. The procedures could not be
The finding involved two procedures used by operators to bring the plant to a safe shutdown  
performed as written. This performance deficiency involved the failure to properly verify and
condition in the event of certain postulated fire scenarios. The procedures could not be  
validate these infrequently used procedures.
performed as written. This performance deficiency involved the failure to properly verify and  
The NRCs preliminary assessment of the safety significance of this inspection finding was a
validate these infrequently used procedures.  
modified bounding analysis based upon the best available information. This simplified analysis
The NRCs preliminary assessment of the safety significance of this inspection finding was a  
demonstrated that this finding did not have high importance to safety, but that additional
modified bounding analysis based upon the best available information. This simplified analysis  
information and analyses would be needed to determine the final significance. Therefore, the
demonstrated that this finding did not have high importance to safety, but that additional  
finding was issued with a preliminary safety significance of Greater than Green.
information and analyses would be needed to determine the final significance. Therefore, the  
At the request of Nebraska Public Power District, a regulatory conference was held on May 13,
finding was issued with a preliminary safety significance of Greater than Green.  
2008, to further discuss your views on this issue. A copy of the handout you provided is
At the request of Nebraska Public Power District, a regulatory conference was held on May 13,  
attached to the regulatory conference meeting summary (ML081550102). During the regulatory
2008, to further discuss your views on this issue. A copy of the handout you provided is  
conference, your staff described your assessment of the significance of the finding and your
attached to the regulatory conference meeting summary (ML081550102). During the regulatory  
views on the applicability of the Interim Enforcement Discretion Policy.
conference, your staff described your assessment of the significance of the finding and your  
views on the applicability of the Interim Enforcement Discretion Policy.  
UNITED STATES
NUCLEAR REGULATORY COMMISSION
R E GI ON  I V
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125


Nebraska Public Power District                   -2-
Nebraska Public Power District  
After considering the information developed during this inspection, the additional information
- 2 -  
you provided in your letter dated May 8, 2008 (ML081540362), and the information your staff
provided at the regulatory conference, the NRC has concluded that the inspection finding is
appropriately characterized as White, an issue with low to moderate increased importance to
After considering the information developed during this inspection, the additional information  
safety, which may require additional NRC inspections.
you provided in your letter dated May 8, 2008 (ML081540362), and the information your staff  
The final significance determination, described in Enclosure 2, was based on the significance
provided at the regulatory conference, the NRC has concluded that the inspection finding is  
determination process Phase 3 analysis performed by the NRC staff using multiple risk tools
appropriately characterized as White, an issue with low to moderate increased importance to  
including, a standardized plant analysis risk model simulation of the potential fires that would
safety, which may require additional NRC inspections.  
impact this finding, hand calculations, and a linked event tree model of the Cooper Nuclear
The final significance determination, described in Enclosure 2, was based on the significance  
Station's remote shutdown capabilities developed by NRC analysts. This evaluation considered
determination process Phase 3 analysis performed by the NRC staff using multiple risk tools  
insights and values provided by your staff. The results of your analyses and fire modeling
including, a standardized plant analysis risk model simulation of the potential fires that would  
provided important information needed for our staff to complete our significance determination
impact this finding, hand calculations, and a linked event tree model of the Cooper Nuclear  
process evaluation. Our final assessment of the change in risk due to this performance
Station's remote shutdown capabilities developed by NRC analysts. This evaluation considered  
deficiency has dropped an order of magnitude. For fire areas that would not have the potential
insights and values provided by your staff. The results of your analyses and fire modeling  
to cause a control room evacuation, the NRC results closely match your results. However, for
provided important information needed for our staff to complete our significance determination  
cases with the potential to cause control room evacuation, which dominated the safety impact,
process evaluation. Our final assessment of the change in risk due to this performance  
our results indicated greater safety significance than your results. The areas where the two
deficiency has dropped an order of magnitude. For fire areas that would not have the potential  
analyses differed significantly included the frequency with which operators would abandon the
to cause a control room evacuation, the NRC results closely match your results. However, for  
main control room, and the assessment of the human reliability associated with the expected
cases with the potential to cause control room evacuation, which dominated the safety impact,  
recovery actions. Your analysis did not adequately model the impact of spurious operations due
our results indicated greater safety significance than your results. The areas where the two  
to fire damage in alternate shutdown fire areas or treat them consistent with the plant operating
analyses differed significantly included the frequency with which operators would abandon the  
procedure, which would be expected to result in a higher evacuation frequency. In addition,
main control room, and the assessment of the human reliability associated with the expected  
your evaluation did not include core damage sequences that involved the failure of the high
recovery actions. Your analysis did not adequately model the impact of spurious operations due  
pressure coolant injection system early in the event. These sequences represented about
to fire damage in alternate shutdown fire areas or treat them consistent with the plant operating  
one fourth of the risk in our evaluation. We estimated the change in core damage frequency
procedure, which would be expected to result in a higher evacuation frequency. In addition,  
associated with this finding to be 8.1 x 10-6, as discussed in Enclosure 2 to this letter, compared
your evaluation did not include core damage sequences that involved the failure of the high  
to your final significance of 8.6 x 10-8.
pressure coolant injection system early in the event. These sequences represented about  
You have 30 calendar days from the date of this letter to appeal the staffs determination of
one fourth of the risk in our evaluation. We estimated the change in core damage frequency  
significance for the identified White finding. Such appeals will be considered to have merit only
associated with this finding to be 8.1 x 10-6, as discussed in Enclosure 2 to this letter, compared  
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Significance
to your final significance of 8.6 x 10-8.  
Determination Process, Attachment 2, Process for Appealing NRC Characterization of
Inspection Findings (Significance Determination Process Appeal Process).
You have 30 calendar days from the date of this letter to appeal the staffs determination of  
The NRC has also determined that the two examples of inadequate fire response operating
significance for the identified White finding. Such appeals will be considered to have merit only  
procedures involved a violation of NRC requirements as cited in the enclosed Notice of
if they meet the criteria given in NRC Inspection Manual Chapter 0609, Significance  
Violation (Notice). The circumstances surrounding the violation are described in detail in NRC
Determination Process, Attachment 2, Process for Appealing NRC Characterization of  
Inspection Report 05000298/2008007. This violation of 10 CFR Part 50, Appendix B,
Inspection Findings (Significance Determination Process Appeal Process).  
Criterion V, Instructions, Procedures, and Drawings involved steps contained in Emergency
Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire
The NRC has also determined that the two examples of inadequate fire response operating  
Induced Shutdown From Outside Control Room. Certain steps in the procedures intended to
procedures involved a violation of NRC requirements as cited in the enclosed Notice of  
reposition motor-operated valves locally, would not have worked as written because the steps
Violation (Notice). The circumstances surrounding the violation are described in detail in NRC  
were not appropriate for the configuration of the motor-starter circuits. As a consequence of this
Inspection Report 05000298/2008007. This violation of 10 CFR Part 50, Appendix B,  
violation, these quality-related procedures would have challenged the operators ability to bring
Criterion V, Instructions, Procedures, and Drawings involved steps contained in Emergency  
the plant to a safe shutdown condition in the event of certain fires. In accordance with the NRC
Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire  
Enforcement Policy, the Notice is considered escalated enforcement action because it is
Induced Shutdown From Outside Control Room. Certain steps in the procedures intended to  
associated with a White finding.
reposition motor-operated valves locally, would not have worked as written because the steps  
were not appropriate for the configuration of the motor-starter circuits. As a consequence of this  
violation, these quality-related procedures would have challenged the operators ability to bring  
the plant to a safe shutdown condition in the event of certain fires. In accordance with the NRC  
Enforcement Policy, the Notice is considered escalated enforcement action because it is  
associated with a White finding.


Nebraska Public Power District                 -3-
Nebraska Public Power District  
Because plant performance for this issue has been determined to be in the regulatory response
- 3 -  
band, we will use the NRC Action Matrix, as described in NRC Inspection Manual Chapter 0305,
Operating Reactor Assessment Program, to determine the most appropriate NRC response
and any increase in NRC oversight. We will notify you by separate correspondence of that
Because plant performance for this issue has been determined to be in the regulatory response  
determination.
band, we will use the NRC Action Matrix, as described in NRC Inspection Manual Chapter 0305,  
The staff has reviewed the position provided in your March 10, 2008, letter (ML080740507)
Operating Reactor Assessment Program, to determine the most appropriate NRC response  
concerning the circumstances surrounding this violation and how the Interim Enforcement Policy
and any increase in NRC oversight. We will notify you by separate correspondence of that  
Regarding Enforcement Discretion for Certain Fire Protection Issues related to this violation.
determination.  
During the regulatory conference, your presentation reiterated the position stated in your letter.
Our review has concluded that your letter and regulatory conference presentation provided no
The staff has reviewed the position provided in your March 10, 2008, letter (ML080740507)  
new information. Therefore, we maintain that all of the requirements of the Interim Enforcement
concerning the circumstances surrounding this violation and how the Interim Enforcement Policy  
Policy Regarding Enforcement Discretion for Certain Fire Protection Issues were not satisfied
Regarding Enforcement Discretion for Certain Fire Protection Issues related to this violation.
and enforcement discretion will not be granted for this violation.
During the regulatory conference, your presentation reiterated the position stated in your letter.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
Our review has concluded that your letter and regulatory conference presentation provided no  
enclosure(s), and your response, if you choose to provide one, will be made available
new information. Therefore, we maintain that all of the requirements of the Interim Enforcement  
electronically for public inspection in the NRC Public Document Room or from the NRCs
Policy Regarding Enforcement Discretion for Certain Fire Protection Issues were not satisfied  
and enforcement discretion will not be granted for this violation.  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its  
enclosure(s), and your response, if you choose to provide one, will be made available  
electronically for public inspection in the NRC Public Document Room or from the NRCs  
document system (ADAMS), accessible from the NRC website at www.nrc.gov/reading-
document system (ADAMS), accessible from the NRC website at www.nrc.gov/reading-
rm/pdr.html or www.nrc.gov/reading-rm/adams.html. To the extent possible, your response
rm/pdr.html or www.nrc.gov/reading-rm/adams.html. To the extent possible, your response  
should not include any personal privacy, proprietary, or safeguards information so that it can be
should not include any personal privacy, proprietary, or safeguards information so that it can be  
made available to the Public without redaction.
made available to the Public without redaction.  
                                              Sincerely,
                                                        /RA/
                                              Roy J. Caniano, Director
                                              Division of Reactor Safety
Docket: 50-298
License: DPR-46
Enclosures:
1. Notice of Violation
Sincerely,
2. Final Significance Determination
3. Supplemental Information
cc w/enclosures:
Gene Mace
/RA/  
Nuclear Asset Manager
Nebraska Public Power District
P.O. Box 98
Brownville, NE 68321
Roy J. Caniano, Director  
Division of Reactor Safety  
Docket:   50-298  
License: DPR-46  
Enclosures:  
1. Notice of Violation  
2. Final Significance Determination  
3. Supplemental Information  
cc w/enclosures:  
Gene Mace  
Nuclear Asset Manager  
Nebraska Public Power District  
P.O. Box 98  
Brownville, NE 68321  


Nebraska Public Power District           -4-
Nebraska Public Power District  
John C. McClure, Vice President
- 4 -  
   and General Counsel
Nebraska Public Power District
P.O. Box 499
John C. McClure, Vice President  
Columbus, NE 68602-0499
   and General Counsel  
David Van Der Kamp
Nebraska Public Power District  
  Licensing Manager
P.O. Box 499  
Nebraska Public Power District
Columbus, NE 68602-0499  
P.O. Box 98
Brownville, NE 68321
David Van Der Kamp  
Michael J. Linder, Director
  Licensing Manager  
Nebraska Department of
Nebraska Public Power District  
   Environmental Quality
P.O. Box 98  
P.O. Box 98922
Brownville, NE 68321  
Lincoln, NE 68509-8922
Chairman
Michael J. Linder, Director  
Nemaha County Board of Commissioners
Nebraska Department of
Nemaha County Courthouse
   Environmental Quality  
1824 N Street
P.O. Box 98922  
Auburn, NE 68305
Lincoln, NE 68509-8922  
Julia Schmitt, Manager
Radiation Control Program
Chairman  
Nebraska Health & Human Services
Nemaha County Board of Commissioners  
Dept. of Regulation & Licensing
Nemaha County Courthouse  
Division of Public Health Assurance
1824 N Street  
301 Centennial Mall, South
Auburn, NE 68305  
P.O. Box 95007
Lincoln, NE 68509-5007
Julia Schmitt, Manager  
H. Floyd Gilzow
Radiation Control Program  
Deputy Director for Policy
Nebraska Health & Human Services  
Missouri Department of Natural Resources
Dept. of Regulation & Licensing  
P. O. Box 176
Division of Public Health Assurance  
Jefferson City, MO 65102-0176
301 Centennial Mall, South  
Director, Missouri State Emergency
P.O. Box 95007  
   Management Agency
Lincoln, NE 68509-5007  
P.O. Box 116
Jefferson City, MO 65102-0116
H. Floyd Gilzow  
Deputy Director for Policy  
Missouri Department of Natural Resources  
P. O. Box 176  
Jefferson City, MO 65102-0176  
Director, Missouri State Emergency
   Management Agency  
P.O. Box 116  
Jefferson City, MO 65102-0116  


Nebraska Public Power District           -5-
Nebraska Public Power District  
Chief, Radiation and Asbestos
- 5 -  
   Control Section
Kansas Department of Health
   and Environment
Chief, Radiation and Asbestos  
Bureau of Air and Radiation
   Control Section  
1000 SW Jackson, Suite 310
Kansas Department of Health  
Topeka, KS 66612-1366
   and Environment  
Melanie Rasmussen, State Liaison Officer/
Bureau of Air and Radiation  
   Radiation Control Program Director
1000 SW Jackson, Suite 310  
Bureau of Radiological Health
Topeka, KS 66612-1366  
Iowa Department of Public Health
Lucas State Office Building, 5th Floor
Melanie Rasmussen, State Liaison Officer/  
321 East 12th Street
   Radiation Control Program Director  
Des Moines, IA 50319
Bureau of Radiological Health  
John F. McCann, Director, Licensing
Iowa Department of Public Health  
Entergy Nuclear Northeast
Lucas State Office Building, 5th Floor  
Entergy Nuclear Operations, Inc.
321 East 12th Street  
440 Hamilton Avenue
Des Moines, IA 50319  
White Plains, NY 10601-1813
Keith G. Henke, Planner
John F. McCann, Director, Licensing  
Division of Community and Public Health
Entergy Nuclear Northeast  
Office of Emergency Coordination
Entergy Nuclear Operations, Inc.  
930 Wildwood, P.O. Box 570
440 Hamilton Avenue  
Jefferson City, MO 65102
White Plains, NY 10601-1813  
Ronald L. McCabe, Chief
Technological Hazards Branch
Keith G. Henke, Planner  
National Preparedness Division
Division of Community and Public Health  
DHS/FEMA
Office of Emergency Coordination  
9221 Ward Parkway
930 Wildwood, P.O. Box 570  
Suite 300
Jefferson City, MO 65102  
Kansas City, MO 64114-3372
Daniel K. McGhee, State Liaison Officer
Ronald L. McCabe, Chief  
Bureau of Radiological Health
Technological Hazards Branch  
Iowa Department of Public Health
National Preparedness Division  
Lucas State Office Building, 5th Floor
DHS/FEMA  
321 East 12th Street
9221 Ward Parkway  
Des Moines, IA 50319
Suite 300  
Ronald D. Asche, President
Kansas City, MO 64114-3372  
   and Chief Executive Officer
Nebraska Public Power District
Daniel K. McGhee, State Liaison Officer  
1414 15th Street
Bureau of Radiological Health  
Iowa Department of Public Health  
Lucas State Office Building, 5th Floor  
321 East 12th Street  
Des Moines, IA 50319  
Ronald D. Asche, President
   and Chief Executive Officer  
Nebraska Public Power District  
1414 15th Street  
Columbus, NE 68601
Columbus, NE 68601


Nebraska Public Power District                 -6-
Nebraska Public Power District  
Electronic distribution by RIV:
- 6 -  
Regional Administrator (Elmo.Collins@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov
DRS Director (Roy.Caniano@nrc.gov )
Electronic distribution by RIV:  
DRS Deputy Director (Troy.Pruett@nrc.gov)
Regional Administrator (Elmo.Collins@nrc.gov)  
Senior Resident Inspector (Nick.Taylor@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov
Branch Chief, DRP/C (Rick.Deese@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov )  
Senior Project Engineer, DRP/C (Wayne.Walker@nrc.gov )
DRS Deputy Director (Troy.Pruett@nrc.gov)  
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )
Senior Resident Inspector (Nick.Taylor@nrc.gov)  
RITS Coordinator (Marisa.Herrera@nrc.gov )
Branch Chief, DRP/C (Rick.Deese@nrc.gov)  
DRS STA (Dale.Powers@nrc.gov )
Senior Project Engineer, DRP/C (Wayne.Walker@nrc.gov )  
J. Adams, OEDO RIV Coordinator (John.Adams@nrc.gov)
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )  
P. Lougheed, OEDO RIV Coordinator (Patricia.Lougheed@nrc.gov )
RITS Coordinator (Marisa.Herrera@nrc.gov )  
ROPreports
DRS STA (Dale.Powers@nrc.gov )  
CNS Site Secretary (Sue.Farmer@nrc.gov)
J. Adams, OEDO RIV Coordinator (John.Adams@nrc.gov)  
OEMail.Resource@nrc.gov                             Michael.Franovich@nrc.gov
P. Lougheed, OEDO RIV Coordinator (Patricia.Lougheed@nrc.gov )  
OEWeb.Resource@nrc.gov                             Jeff.Circle@nrc.gov
ROPreports  
Doug.Starkey@nrc.gov                               Joseph.Anderson@nrc.gov
CNS Site Secretary (Sue.Farmer@nrc.gov)  
Maryann.Ashley@nrc.gov                             Tim.Kobetz@nrc.gov
OEMail.Resource@nrc.gov
Michael.Vasquez@nrc.gov                             Thomas.Hiltz@nrc.gov
OEWeb.Resource@nrc.gov  
Victor.Dricks@nrc.gov                               Carl.Lyon@nrc.gov
Doug.Starkey@nrc.gov
Bill.Maier@nrc.gov                                 Undine.Shoop@nrc.gov
Maryann.Ashley@nrc.gov
Linda.Smith@nrc.gov                                 Richard.borchardt@nrc.gov
Michael.Vasquez@nrc.gov  
Neil.OKeefe@nrc.gov                                 Melissa.Wyatt@nrc.gov
Victor.Dricks@nrc.gov  
John.Mateychick@nrc.gov                             Paul.Lain@nrc.gov
Bill.Maier@nrc.gov  
Karla.Fuller@nrc.gov                               Bruce.Boger@nrc.gov
Linda.Smith@nrc.gov  
Nick.Taylor@nrc.gov                                 Harold.Barrett@nrc.gov
Neil.OKeefe@nrc.gov  
Michael.Cheok@nrc.gov                               Frederick.Brown@nrc.gov
John.Mateychick@nrc.gov  
John.Grobe@nrc.gov                                 Christine.Tucci@nrc.gov
Karla.Fuller@nrc.gov  
Mark.Cunningham@nrc.gov                             Amy.Powell@nrc.gov
Nick.Taylor@nrc.gov  
Alexander.Klein@nrc.gov
Michael.Cheok@nrc.gov  
Christi.Maier@nrc.gov
John.Grobe@nrc.gov  
SUNSI Review Completed: LJS ADAMS: Yes                    No    Initials: __________
Mark.Cunningham@nrc.gov  
Publicly Available        Non-Publicly Available      Sensitive        Non-Sensitive
Alexander.Klein@nrc.gov  
S:\DRS\REPORTS\CN 2008008 Final Significance ltr - NFO
Michael.Franovich@nrc.gov  
SRI/EB2          SRI/EB2      C:DRS/EB2   SRA/DRS      ACES        C:DRP/C          D:DRS
Jeff.Circle@nrc.gov  
JMMateychick      NFOKeefe    LJSmith    DLoveless    CMaier      DChamberlain    RJCaniano
Joseph.Anderson@nrc.gov  
E /RA/            /RA/          /RA/        /RA/        /RA/        /RA/            /RA/
Tim.Kobetz@nrc.gov  
6/7/08            6/5/08        6/5/08      6/5/08      6/5/08      6/5/08          6/13/08
Thomas.Hiltz@nrc.gov  
OFFICIAL RECORD COPY                  T=Telephone          E=E-mail                F=Fax
Carl.Lyon@nrc.gov  
Undine.Shoop@nrc.gov  
Richard.borchardt@nrc.gov  
Melissa.Wyatt@nrc.gov
Paul.Lain@nrc.gov  
Bruce.Boger@nrc.gov  
Harold.Barrett@nrc.gov  
Frederick.Brown@nrc.gov  
Christine.Tucci@nrc.gov  
Amy.Powell@nrc.gov  
Christi.Maier@nrc.gov
SUNSI Review Completed:     LJS     ADAMS:   


                                          NOTICE OF VIOLATION
Nebraska Public Power District                                                    Docket No. 50-298
Cooper Nuclear Station                                                            License No. DPR-46
                                                                                  EA-07-204
During an NRC inspection completed on March 18, 2008, a violation of NRC requirements was
identified. In accordance with the NRC Enforcement policy, the violation is listed below:
          Appendix B to 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings,
          requires, in part, that activities affecting quality shall be prescribed by documented
          instructions, procedures, or drawings, of a type appropriate to the circumstances and
          shall be accomplished in accordance with these instructions, procedures, or drawings.
          Procedure 0.4A, Procedure Change Process Supplement, Revision 0, implements
          measures to ensure the procedure quality required by Criterion V for procedures
          designated as quality-related. Attachment 2 to this procedure requires verification and
          validation to be performed periodically, when writing a new procedure, when significant
          changes are made to sequencing of complex steps in existing procedures, and when
          infrequently used procedures are written or changed. Verification and validation efforts
          are defined in this procedure as actions to confirm that the procedure steps: (1) are
          usable; (2) are accurate; (3) contain the appropriate level of detail; (3) use equipment
          nomenclature that corresponds to the actual hardware; and (4) satisfy plant design and
          licensing basis. Procedure 0.4A applies to changes to Emergency Procedures
          5.4POST-FIRE and 5.4FIRE-S/D.
          Contrary to the above, between 1997 and June, 2007, the licensee failed to ensure that
          two emergency operating procedures which controlled activities affecting quality were
          appropriate to the circumstances. Specifically, the licensee changed Emergency
          Procedures 5.4POST-FIRE and 5.4FIRE-S/D in 1997 to add steps that were
          inappropriate to the circumstances because they would not work as written. Additionally,
          the licensee failed to properly verify and validate procedure steps to ensure that they
          would work to accomplish the necessary actions.
This violation is associated with a White significance determination process finding.
The NRC has concluded that information regarding the reason for the violation, the corrective
actions taken and planned to correct the violation and prevent recurrence and the date when full
compliance was achieved is already adequately addressed on the docket in NRC Inspection
Reports 05000298/2007008, 05000298/2008007, and Licensee Event Report
05000298/2007005-00. However, you are required to submit a written statement or explanation
pursuant to 10 CFR 2.201 if the description therein does not accurately reflect your corrective
actions or your position. In that case, or if you choose to respond, clearly mark your response
as a "Reply to a Notice of Violation," include the EA number, and send it to the U.S. Nuclear
Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a
copy to the Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the
facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this
Notice of Violation (Notice).
                                                    E1-1                                  Enclosure 1


If you choose to respond, your response will be made available electronically for public
Yes
inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),
  No      Initials: __________
accessible from the NRC website at www.nrc.gov/reading-rm/pdr.html or www.nrc.gov/reading-
rm/adams.html. Therefore, to the extent possible, the response should not include any personal
privacy, proprietary, or safeguards information so that it can be made available to the Public
without redaction.
If you contest this enforcement action, you should also provide a copy of your response, with
the basis of your denial, to the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, DC 20555-0001.
Dated this 13th day of June 2008
                                                E1-2                                  Enclosure 1


                      FINAL SIGNIFICANCE DETERMINATION SUMMARY
Significance Determination Basis
a.    Phase 1 Screening Logic, Results, and Assumptions
        In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue
        Screening," the issue was determined to be more than minor because it was associated
        with the equipment performance attribute and affected the mitigating systems
        cornerstone objective to ensure the availability, reliability, or function of a system or train
        in a mitigating system in that 10 motor-operated valves would not have functioned
        following a postulated fire in multiple fire zones. The following summarizes the valves
        and fire areas affected:
                Valves Affected
                HPCI-MO-14              Steam Supply to High Pressure Coolant Injection (HPCI)
                                        Turbine Valve
                HPCI-MO-16              Steam Supply to HPCI Turbine Outboard Isolation Valve
                RHR-MO-17              Shutdown Cooling Suction Valve
                RHR-MO-25A              Residual Heat Removal (RHR) A Inboard Injection Valve
                RHR-MO-25B              RHR B Inboard Injection Valve
                RHR-MO-67              RHR Discharge to Radwaste Inboard Valve
                RHR-MO-921              Augmented Offgas Steam Supply Valve
                RWCU-MO-18              Outboard Reactor Water Cleanup Isolation Valve
                MS-MO-77                Outboard Main Steam Drain Line Isolation Valve
                RR-MO-53A              Reactor Recirculation Pump A Discharge Valve
                Fire Areas Affected
                CB-A          Control Building Reactor Protection System Room 1A, Seal Water
                              Pump Area, and Hallway
                CB-A-1        Control Building Division 1 Switchgear Room and Battery Room
                CB-B          Control Building Division 2 Switchgear Room and Battery Room
                CB-C          Control Building Reactor Protection System Room 1B
                CB-D          Control Room, Cable Spreading Room, Cable Expansion Room,
                              and Auxiliary Relay Room
                RB-CF          Reactor Building North/Northwest 903, Northwest Quad 889 and
                              859, and RHR Heat Exchanger Room A
                RB-DI (SW)    Reactor Building South/Southwest 903, Southwest Quad 889 and
                              859, and RHR Heat Exchanger Room B
                RB-DI (SE)    Reactor Building RHR Pump B/HPCI Pump Room
                RB-J          Reactor Building Critical Switchgear Room 1F
                RB-K          Reactor Building Critical Switchgear Room 1G
                RB-M          Reactor Building North/Northwest 931 and RHR Heat Exchanger
                              Room A
                                                  E2-1                                    Enclosure 2


            RB-N            Reactor Building South/Southwest 931 and RHR Heat Exchanger
                            Room B
            RB-FN          Reactor Building 903, Northeast Corner
            TB-A            Turbine Building (multiple areas)
  The significance determination process (SDP) Phase 1 Screening Worksheet (Manual
  Chapter 0609, Attachment 4), Table 3b directs the user to Manual Chapter 0609,
  Appendix F, Fire Protection Significance Determination Process, because it affected
  fire protection defense-in-depth strategies involving post fire safe shutdown systems.
  However, Manual Chapter 0308, Attachment 3, Appendix F, Technical Basis for Fire
  Protection Significance Determination Process for at Power Operations, states that
  Manual Chapter 0609, Appendix F, does not include explicit treatment of fires in the
  main control room. The Phase 2 process can be utilized in the treatment of main control
  room fires, but it is recommended that additional guidance be sought in the conduct of
  such an analysis.
b. Phase 2 Risk Estimation
  Based on the complexity and scope of the subject finding and the significance of the
  finding to main control room fires, the analyst determined that a Phase 2 estimation was
  not appropriate.
c. Phase 3 Analysis
  In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3
  analysis using input from the Nebraska Public Power District, Individual Plant
  Examination for External Events (IPEEE) Report - 10 CFR 50.54(f) Cooper Nuclear
  Station, NRC Docket No. 50-298, License No. DPR-46, dated October 30, 1996, the
  Standardized Plant Analysis Risk (SPAR) Model for Cooper, Revision 3.31, dated
  September 2007, licensee input (see documents reviewed list in Enclosure 3), a
  probabilistic risk assessment using a linked event tree model created by the analyst for
  evaluating main control room evacuation scenarios, and appropriate hand calculations.
  Assumptions:
  Following the regulatory conference, the analysts revised the Phase 3 analysis. To
  evaluate the change in risk caused by this performance deficiency, the analyst made the
  following assumptions:
            1. For fire zones that do not have the possibility for a fire to require the main
                control room to be abandoned, the ignition frequency identified in the IPEEE
                is an appropriate value.
            2. The fire ignition frequency for the main control room (PFIF) is best quantified
                by the licensees revised value of 6.88 x 10-3/yr.
            3. Of the original 64 fire scenarios evaluated, 18 were determined to be
                redundant and were eliminated, 41 of the remaining (documented in Table 1)
                                            E2-2                                      Enclosure 2


    were identified as the predominant sequences associated with fires that did
  Publicly Available        Non-Publicly Available        Sensitive
    not result in control room abandonment.
4. The baseline conditional core damage probability for a control room
    evacuation at the Cooper Nuclear Station is best represented by the creation
    of a new probabilistic risk assessment tool created by the analyst using a
    linked event tree method. The primary event tree used in this model is
    displayed as Figure 1 in the Attachment. The baseline conditional core
    damage probability as calculated by the linked event tree model was
    1.14 x 10-1, which is similar to the generic industry value of 0.1.
5. The analyst used an event tree, RECOVERY-PATH, shown in Figure 2 in the
    Attachment, to evaluate the likelihood of operator recovery via either
    restoration of HPCI or manually opening Valve RHR-MO-25B. The resulting
    non-recovery probability was 7.9 x 10-2.
6. The risk related to a failure of Valve RHR-MO-25B to open following an
    evacuation of the main control room was evaluated using the analysts linked
    event tree model. The conditional core damage probability calculated by the
    linked event tree model was 2.4 x 10-1.
7. Any fire in the main control room that is large enough to grow and that goes
    unsuppressed for 20 minutes will lead to a control room evacuation.
8. Any fire that is unsuppressed by automatic or manual means in the auxiliary
    relay room, the cable spreading room, the cable expansion room or
    Area RB-FN will result in a main control room evacuation.
9. The Cooper SPAR model, Revision 3.31, represents an appropriate tool for
    evaluation of the core damage probabilities associated with postulated fires
    that do not result in main control room evacuation.
10. All postulated fires in this analysis resulted in a reactor scram. In addition,
    the postulated fire in Fire Area RB-K resulted in a loss-of-offsite power.
11. Valves RHR-MO-25A and RHR-MO-25B are low pressure coolant injection
    system isolation valves. These valves can prevent one method of decay heat
    removal in the shutdown cooling mode of operation.
12. For Valves RHR-MO-25A and RHR-MO-25B, the subject performance
    deficiency only applies to the portion of the post fire procedures that direct the
    transition into shutdown cooling. Therefore, the low pressure injection
    function is not affected.
13. Valve RHR-MO-25B must open from the motor-control center for operators to
    initiate alternate shutdown cooling from the alternate shutdown panel
    following a main control room evacuation.
                                  E2-3                                    Enclosure 2


14. Valve RHR-MO-17 is one of two RHR system shutdown cooling cold-leg
    suction isolation valves. These valves can prevent decay heat removal in the
    shutdown cooling mode of operation.
15. Valve RWCU-MO-18 is the outboard isolation valve for the reactor water
    cleanup system. The system is a closed-loop system outside containment
    with piping rated at 1250 psig and 575°F. The isol ation of this system is
    designed to protect the system demineralizer resins and as an isolation for a
    piping break outside containment. The success or failure of the resins will not
    affect the likelihood of core damage. The failure of the system piping without
    isolation would contribute to an intersystem loss-of-coolant accident.
    However, the likelihood that the system piping fails and an automatic isolation
    is not generated would be very low.
16. Valve MS-MO-77 is a 3-inch main steam line drain. The valve isolates a high
    pressure drain line heading back to the main condenser. The licensee stated
    that the failure to isolate this line would not result in a high enough loss-of-
    reactor coolant to affect the core damage frequency. However, the failure to
    close this valve could result in a transient that would not have otherwise been
    caused by the postulated fire scenario.
17. Valve RR-MO-53A is the discharge isolation valve for Reactor Recirculation
    Pump 1-A. The failure to close either this valve or Valve RR-MO-43A would
    result in a short circuit of the shutdown cooling flow to the reactor vessel.
    The performance deficiency did not apply to Valve RR-MO-43A.
18. Valve RHR-MO-921 provides isolation of a 3-inch steam line heading to the
    augmented offgas system. Just downstream of the valve the piping reduces
    to a 1-inch diameter line. This line taps off the HPCI pump steam line and
    terminates in the main condenser high pressure drain header. Because this
    is a 1-inch line, the valve does not contribute to the large-early release
    frequency except for postulated seismic events. Additionally, inventory
    losses would be minimal and not affect mitigating systems necessary
    following the subject fire initiation. Finally, the line would be automatically
    isolated upon the isolation of the HPCI pump steam line. However, the failure
    to close this valve could result in a transient that would not have otherwise
    been caused by the postulated fire scenario.
19. Valve HPCI-MO-14 provides isolation of the HPCI system from the reactor
    coolant system. The failure to isolate this valve, when required, would result
    in reactor vessel level increasing in an uncontrolled manner, filling the steam
    lines and suppressing the steam to all steam-driven equipment. This
    increases the core damage probability because it results in the loss of all high
    pressure systems.
20. Valve HPCI-MO-16 provides isolation of the HPCI system from the reactor
    coolant system. The failure to isolate this valve, when required, would result
    in reactor vessel level increasing in an uncontrolled manner, filling the steam
                                  E2-4                                    Enclosure 2


              lines and suppressing the steam to all steam-driven equipment. This
              increases the core damage probability because it results in the loss of all high
              pressure systems.
        21. Valve RHR-MO-67 provides isolation of the RHR system from radwaste.
              Post-fire instructions affecting this valve are to assist in placing shutdown
              cooling in service. Failure of this valve would delay placing shutdown cooling
              in service and act as a distraction to operators placing the plant in a safe
              shutdown condition.
        22. The exposure time used for evaluating this finding should be determined in
              accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2,
              Site Specific Risk-Informed Inspection Notebook Usage Rules. Given that
              the performance deficiency was known to have existed for many years, the
              analyst used the 1-year of the current assessment cycle as the exposure
              period.
        23. Based on fire damage and/or procedures, equipment affected by a postulated
              fire in a given fire zone is unavailable for use as safe shutdown equipment.
        24. The performance deficiency would have resulted in each of the demanded
              valves failing to respond following a postulated fire.
        25. In accordance with the requirements of Procedure 5.4POST-FIRE, operators
              would perform the post-fire actions directed by the procedure following a fire
              in an applicable fire zone. Therefore, the size and duration of the fire would
              not be relevant to the failures caused by the performance deficiency.
        26. Given Assumption 25, severity factors and probabilities of non-
              suppression were not addressed for postulated fires that did not result in
              main control room evacuation.
Postulated Fires Not Involving Main Control Room Evacuation:
The senior reactor analyst used the SPAR model for Cooper Nuclear Station to estimate
the change in risk, associated with fires in each of the associated fire scenarios (Table 1,
Items 1 - 41) that was caused by the finding. Average unavailability for test and
maintenance of modeled equipment was assumed, and a cutset truncation of
1.0 x 10-13 was used. For each fire zone, the analyst calculated a baseline conditional
core damage probability consistent with Assumptions 9, 10, 25 and 26.
For areas where the postulated fire resulted in a reactor scram, the frequency of the
transient initiator, IE-TRANS, was set to 1.0. All other initiators were set to the house
event FALSE, indicating that these events would not occur at the same time as a
reactor scram. Likewise, for Fire Area RB-K, the frequency of the loss-of-offsite power
initiator, IE-LOOP, was set to 1.0 while other initiators were set to the house event
FALSE.
                                            E2-5                                    Enclosure 2


With input from the detailed IPEEE notebooks, maintained by the licensee, the analyst
  Non-Sensitive
was able to better assess the fire damage in each zone. This resulted in a more realistic
S:\\DRS\\REPORTS\\CN 2008008 Final Significance ltr - NFO
evaluation of the baseline fire risk for the zone, and lowering the change in risk for each
example.
Consistent with guidance in the Reactor Accident Sequence Precursor Handbook,
including NRC document, "Common-Cause Failure Analysis in Event Assessment,
SRI/EB2
(June 2007)," the baseline established for the fire zone, and Assumptions 22 through 26,
SRI/EB2
the analyst modeled the resulting condition following a postulated fire in each fire zone
C:DRS/EB2
by adjusting the appropriate basic events in the SPAR model. Both the baseline and
conditional values for each fire zone are documented in Table 1.
SRA/DRS
As shown in Table 1, the analyst calculated a change in core damage frequency (CDF)
ACES
associated with these 41 fire scenarios of 2.9 x 10-6/yr.
C:DRP/C
The analyst evaluated the licensees qualitative reviews of the 13 fire scenarios that
were impacted by the failure of the HPCI turbine to trip. In these scenarios, HPCI floods
D:DRS
the steam lines and prevents further injection by either HPCI or reactor core isolation
JMMateychick
cooling system. Qualitatively, not all fires will grow to a size that causes a loss of the trip
NFOKeefe
function due to spatial separation. Additionally, not all unsuppressed fires would cause a
LJSmith
failure of the HPCI trip function. Finally, no operator recovery was credited in these
DLoveless
evaluations.
CMaier
Given that these qualitative factors would all tend to decrease the significance of the
DChamberlain
finding, the analyst believed that the total change in risk would be significantly lower than
RJCaniano
the 2.9 x 10-6/yr documented above. Based on analyst judgment and an assessment of
E /RA/
the evidence provided by the licensee, an occurrence factor of 0.1 was applied to
/RA/
the13 fire scenarios. This resulted in a total CDF of 7.8 x 10-7/yr. Therefore, the
/RA/
analyst determined that this value was the best estimate of the safety significance for
/RA/
these 41 fire scenarios.
/RA/
                                          E2-6                                    Enclosure 2
/RA/
/RA/
6/7/08
6/5/08
6/5/08
6/5/08
6/5/08
6/5/08
6/13/08
OFFICIAL RECORD COPY 
T=Telephone 
E=E-mail
    F=Fax


                                              Table 1
            Postulated Fires Not Involving Main Control Room Evacuation
Fire Area/                                                              Estimated
          Area/ Scenario  Scenario    Ignition      Base    Case
E1-1  
Shutdown                                                                delta-CDF  Function Affected
Enclosure 1
          Zone Number  Description Frequency      CCDP    CCDP
NOTICE OF VIOLATION
  Strategy                                                              Contribution
                              RHR A
Nebraska Public Power District
            1C      1                  2.94E-03    8.82E-07 8.15E-05  2.37E-07
                          Pump Room
   
  RB-CF              2        MCC K    3.02E-03    2.76E-05 1.28E-04  3.03E-07
   
                    3      MCC Q      3.93E-03    2.76E-05 1.28E-04  3.95E-07
   
                    4      MCC R      3.43E-03    2.76E-05 1.28E-04  3.44E-07
                    5      MCC RB      1.62E-03    1.12E-03 1.21E-03  1.46E-07
Docket No. 50-298
                    6        MCC S    2.23E-03    1.12E-03 1.21E-03  2.01E-07   Shut HPCI-MO-14,
Cooper Nuclear Station
                    7        MCC Y    3.83E-03    1.12E-03 1.21E-03  3.45E-07    HPCI-MO-16,
                    8    Panel AA3    9.98E-04    2.76E-05 1.28E-04  1.00E-07    RHR-MO-921,
          2A/2C    9    Panel BB3    9.98E-04    1.12E-03 1.21E-03  8.98E-08  RWCU-MO-18 and
                          RCIC Starter                                                MS-MO-77
                    10                  1.32E-03    5.27E-06 8.27E-05  1.02E-07
                              Rack
                          250V Div 1
License No. DPR-46
                    11                  5.10E-04    2.76E-05 1.28E-04  5.12E-08
                              Rack
                          250V Div 2
                    12                  2.09E-04    1.12E-03 1.21E-03  1.88E-08
                              Rack
                    13    ASD Panels    3.02E-04    1.12E-03 1.21E-03  2.72E-08
            7A      14                  6.74E-03    7.64E-04 7.64E-04 0.00E+00
  CB-A    7B      15                  1.36E-03    2.61E-06 2.61E-06 0.00E+00
                          RPS Room
            8C      16                  4.15E-03    1.75E-07 1.75E-07 0.00E+00    Open RHR-MO-25B
                                1A
EA-07-204
            8D      17                  2.42E-03    3.57E-04 3.58E-04  4.84E-10    and RHR-MO-67
                            Hallway
During an NRC inspection completed on March 18, 2008, a violation of NRC requirements was
            10B    18      (used CB    1.09E-02    2.05E-05 2.85E-05  8.74E-08
identified. In accordance with the NRC Enforcement policy, the violation is listed below:
                            corridor)
                                                E2-7                                    Enclosure 2
Appendix B to 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings,
requires, in part, that activities affecting quality shall be prescribed by documented
instructions, procedures, or drawings, of a type appropriate to the circumstances and
shall be accomplished in accordance with these instructions, procedures, or drawings.  
Procedure 0.4A, Procedure Change Process Supplement, Revision 0, implements
measures to ensure the procedure quality required by Criterion V for procedures
designated as quality-related. Attachment 2 to this procedure requires verification and  
validation to be performed periodically, when writing a new procedure, when significant
changes are made to sequencing of complex steps in existing procedures, and when
infrequently used procedures are written or changed. Verification and validation efforts
are defined in this procedure as actions to confirm that the procedure steps:  (1) are
usable; (2) are accurate; (3) contain the appropriate level of detail; (3) use equipment
nomenclature that corresponds to the actual hardware; and (4) satisfy plant design and
licensing basis. Procedure 0.4A applies to changes to Emergency Procedures
5.4POST-FIRE and 5.4FIRE-S/D.
Contrary to the above, between 1997 and June, 2007, the licensee failed to ensure that
two emergency operating procedures which controlled activities affecting quality were
appropriate to the circumstances. Specifically, the licensee changed Emergency
Procedures 5.4POST-FIRE and 5.4FIRE-S/D in 1997 to add steps that were
inappropriate to the circumstances because they would not work as written. Additionally,
the licensee failed to properly verify and validate procedure steps to ensure that they
would work to accomplish the necessary actions.  
   
This violation is associated with a White significance determination process finding.  
   
The NRC has concluded that information regarding the reason for the violation, the corrective
actions taken and planned to correct the violation and prevent recurrence and the date when full
compliance was achieved is already adequately addressed on the docket in NRC Inspection
Reports 05000298/2007008, 05000298/2008007, and Licensee Event Report
05000298/2007005-00However, you are required to submit a written statement or explanation
pursuant to 10 CFR 2.201 if the description therein does not accurately reflect your corrective
actions or your position. In that case, or if you choose to respond, clearly mark your response
as a "Reply to a Notice of Violation," include the EA number, and send it to the U.S. Nuclear
Regulatory Commission, ATTN:  Document Control Desk, Washington, DC 20555-0001 with a
copy to the Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the
facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this
Notice of Violation (Notice).  


                        DC
            8H  19  Switchgear 4.27E-03    3.49E-04 3.49E-04 1.28E-09 Open RHR-MO-17,
   
  CB-A-1
   
                      Room 1A                                            RHR-MO-25B, and
E1-2  
                                                                            RHR-MO-67
Enclosure 1  
                      Battery
   
            8E  20              2.25E-03    8.74E-06 1.03E-05 3.51E-09
If you choose to respond, your response will be made available electronically for public
                      Room 1A
inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),
                        DC
accessible from the NRC website at www.nrc.gov/reading-rm/pdr.html or www.nrc.gov/reading-
  CB-B      8G  21  Switchgear  4.27E-03    1.82E-03 1.83E-03 3.42E-08
rm/adams.html. Therefore, to the extent possible, the response should not include any personal
                      Room 1B                                            Open RHR-MO-25A
privacy, proprietary, or safeguards information so that it can be made available to the Public
                      Battery
without redaction.  
            8F 22              2.25E-03    4.81E-06 5.73E-06 2.07E-09
                      Room 1B
If you contest this enforcement action, you should also provide a copy of your response, with
  CB-C      8B  23  RPS Room   4.15E-03    1.75E-07 1.77E-07 5.81E-12 Open RHR-MO-17,
the basis of your denial, to the Director, Office of Enforcement, United States Nuclear
                        1A                                              RHR-MO-25A, and
Regulatory Commission, Washington, DC 20555-0001.  
            8C  24              4.15E-03    1.75E-07 1.77E-07 5.81E-12
                                                                            RHR-MO-67
Dated this 13th day of June 2008
                    RHR Heat
RB-DI (SW)                                                               Shut HPCI-MO-14
            2D  25 Exchanger  6.70E-04    8.66E-05 8.68E-05 1.27E-10
                                                                          and RR-MO-53A.
                      Room B
                    RHR B/HPCI                                            Shut HPCI-MO-14
RB-DI (SE) 1D/1E 26              4.28E-03    6.48E-05 1.44E-04 3.37E-07
                    Pump Room                                              and RR-MO-53A.
                                                                        Open RHR-MO-17,
  RB-J              Switchgear
            3A  27              3.71E-03    5.28E-05 5.28E-05 0.00E+00 RHR-MO-25B, and
                      Room 1F
                                                                            RHR-MO-67
  RB-K              Switchgear
            3B  28              3.71E-03    1.77E-02 1.77E-02 0.00E+00 Open RHR-MO-25A
                      Room 1G
  RB-M    3C/3D    RB Elevation
                29              1.13E-02    7.06E-06 8.99E-06 2.18E-08 Open RHR-MO-17
            /3E        932
                      RHR Hx                                              and RHR-MO-25B
            2B  30              6.70E-04    7.06E-06 8.99E-06 1.29E-09
                      Rm A
                                          E2-8                                Enclosure 2


                                    Reactor
              3C/3D                Building
    RB-N                  31                    1.13E-02    1.22E-05 1.38E-05 1.81E-08
E2-1  
                /3E                Elevation
Enclosure 2
                                      932                                              Open RHR-MO-25A
FINAL SIGNIFICANCE DETERMINATION SUMMARY
                                  RHR Heat
                2D      32      Exchanger    6.70E-04    1.22E-05 1.38E-05 1.07E-09
                                    Room B
Significance Determination Basis
                                  Condenser
                11D      33                    3.10E-03    4.83E-06 6.20E-06 4.25E-09
  a.  
                                    Pit Area
Phase 1 Screening Logic, Results, and Assumptions
                                    Reactor
                11E      34      Feedwater    6.25E-03    4.83E-06 6.20E-06 8.56E-09
In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue
    TB-A                          Pump Area
Screening," the issue was determined to be more than minor because it was associated
                11L      35      Pipe Chase    6.70E-04    4.83E-06 6.20E-06 9.18E-10
with the equipment performance attribute and affected the mitigating systems
                                  Condenser
cornerstone objective to ensure the availability, reliability, or function of a system or train
                12C      36      and Heater    3.27E-03    4.83E-06 6.20E-06 4.48E-09
in a mitigating system in that 10 motor-operated valves would not have functioned
                                                                                        Open RHR-MO-17,
following a postulated fire in multiple fire zones. The following summarizes the valves
                                  Bay Area
and fire areas affected:
                                                                                        RHR-MO-25A, and
                12D      37    TB Floor 903  3.45E-03    4.83E-06 6.20E-06 4.73E-09    RHR-MO-67
                                    Turbine
Valves Affected
                13A      38      Operating    5.76E-03    4.83E-06 6.20E-06 7.89E-09
                                    Floor
HPCI-MO-14
                                  Non-critical
Steam Supply to High Pressure Coolant Injection (HPCI)
                13B      39      Switchgear    3.79E-03    4.83E-06 6.20E-06 5.19E-09
Turbine Valve
                                    Room
HPCI-MO-16 
                13C      40    Electric Shop  8.56E-04    4.83E-06 6.20E-06 1.17E-09
Steam Supply to HPCI Turbine Outboard Isolation Valve
                13D      41      I&C Shop    8.90E-04    4.83E-06 6.20E-06 1.22E-09
RHR-MO-17
Total Estimated CDF for 41 Postulated Fire Scenarios:                        2.91E-06
Shutdown Cooling Suction Valve
                                                        E2-9                                Enclosure 2
RHR-MO-25A
Residual Heat Removal (RHR) A Inboard Injection Valve
RHR-MO-25B 
RHR B Inboard Injection Valve
RHR-MO-67 
RHR Discharge to Radwaste Inboard Valve
RHR-MO-921 
Augmented Offgas Steam Supply Valve
RWCU-MO-18 
Outboard Reactor Water Cleanup Isolation Valve
MS-MO-77
Outboard Main Steam Drain Line Isolation Valve
RR-MO-53A 
Reactor Recirculation Pump A Discharge Valve
Fire Areas Affected
CB-A
Control Building Reactor Protection System Room 1A, Seal Water
Pump Area, and Hallway
CB-A-1  
Control Building Division 1 Switchgear Room and Battery Room
CB-
Control Building Division 2 Switchgear Room and Battery Room
CB-C
Control Building Reactor Protection System Room 1B
CB-D
Control Room, Cable Spreading Room, Cable Expansion Room,
and Auxiliary Relay Room
RB-CF
Reactor Building North/Northwest 903, Northwest Quad 889 and
859, and RHR Heat Exchanger Room A
RB-DI (SW)
Reactor Building South/Southwest 903, Southwest Quad 889 and
859, and RHR Heat Exchanger Room B
RB-DI (SE)
Reactor Building RHR Pump B/HPCI Pump Room
RB-
Reactor Building Critical Switchgear Room 1F
RB-
Reactor Building Critical Switchgear Room 1G
RB-M
Reactor Building North/Northwest 931 and RHR Heat Exchanger
Room A


Post-Fire Remote Shutdown Calculations:
As documented in Assumptions 4, 5, and 6, the analyst created a linked event tree
model, using the Systems Analysis Programs for Hand-on Integrated Reliability
E2-2
Evaluation (SAPHIRE) software provided by the Idaho National Laboratory, to evaluate
Enclosure 2
the risks related to fire-induced main control room abandonment at the Cooper Nuclear
RB-N
Station. This linked event tree was used to evaluate the increased risk from the subject
Reactor Building South/Southwest 931 and RHR Heat Exchanger
performance deficiency during the response to postulated fires in the main control room,
Room B
the auxiliary relay room, the cable spreading room, the cable expansion room or Fire
RB-FN
Area RB-FN. The primary event tree used in this model is displayed as Figure 1 in the
Reactor Building 903, Northeast Corner
Attachment.
TB-
As documented in Assumption 5, the analyst used an event tree to evaluate the
Turbine Building (multiple areas)  
likelihood of operator recovery via either restoration of HPCI or manually opening
Valve RHR-MO-25B. The resulting non-recovery probability was 7.9 x 10-2.
The significance determination process (SDP) Phase 1 Screening Worksheet (Manual
Using the linked event tree model described in Assumption 4, the analyst calculated the
Chapter 0609, Attachment 4), Table 3b directs the user to Manual Chapter 0609,  
CDF to be 7.3 x 10-6/yr. The dominant cutsets are shown below in Table 2.
Appendix F, Fire Protection Significance Determination Process, because it affected
                                          Table 2
fire protection defense-in-depth strategies involving post fire safe shutdown systems.
            Main Control Room Abandonment Cutsets
However, Manual Chapter 0308, Attachment 3, Appendix F, Technical Basis for Fire
              Postulated Fire      Sequence    Mitigating Functions          Results
Protection Significance Determination Process for at Power Operations, states that
          Auxiliary Relay Room    4-01-03      Failure to Reestablish HPCI
Manual Chapter 0609, Appendix F, does not include explicit treatment of fires in the
                                                Failure to Open MO-25B      1.7 x 10-6/yr
main control room. The Phase 2 process can be utilized in the treatment of main control
          Main Control Room        3-01-03      Failure to Reestablish HPCI
room fires, but it is recommended that additional guidance be sought in the conduct of
                                                Failure to Open MO-25B      4.5 x 10-7/yr
such an analysis.  
          Auxiliary Relay Room    4-01-12      Early HPCI Failure
                                                Failure to Open MO-25B      4.1 x 10-7/yr
  b.  
          Auxiliary Relay Room    4-01-12      HPCI Out of Service
Phase 2 Risk Estimation
                                                Failure to Open MO-25B      2.7 x 10-7/yr
          Main Control Room        4-01-12      Early HPCI Failure
Based on the complexity and scope of the subject finding and the significance of the
                                                Failure to Open MO-25B      1.1 x 10-7/yr
finding to main control room fires, the analyst determined that a Phase 2 estimation was
Control Room Abandonment Frequency
not appropriate.  
NUREG/CR-2258, Fire Risk Analysis for Nuclear Power Plants, provides that control
room evacuation would be required because of thick smoke if a fire went unsuppressed
  c.  
for 20 minutes. Given Assumption 6 and assuming that a fire takes 2 minutes to be
Phase 3 Analysis
detected by automatic detection and/or by the operators, there are 18 minutes remaining
in which to suppress the fire prior to main control room evacuation being required. NRC
In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3
Inspection Manual Chapter 0609, Appendix F, Table 2.7.1, Non-suppression Probability
analysis using input from the Nebraska Public Power District, Individual Plant
Values for Manual Fire Fighting Based on Fire Duration (Time to Damage after
Examination for External Events (IPEEE) Report - 10 CFR 50.54(f) Cooper Nuclear
Detection) and Fire Type Category, provides a manual non-suppression probability
Station, NRC Docket No. 50-298, License No. DPR-46, dated October 30, 1996, the
(PNS) for the control room of 1.3 x 10-2 given 18 minutes from time of detection until time
Standardized Plant Analysis Risk (SPAR) Model for Cooper, Revision 3.31, dated
of equipment damage. This is a reasonable approach, although fire modeling performed
September 2007, licensee input (see documents reviewed list in Enclosure 3), a  
by the licensee indicated that 16 minutes was the expected time to abandon the main
probabilistic risk assessment using a linked event tree model created by the analyst for
control room based on habitability.
evaluating main control room evacuation scenarios, and appropriate hand calculations.
                                        E2-10                                            Enclosure 2
Assumptions:
Following the regulatory conference, the analysts revised the Phase 3 analysis. To
evaluate the change in risk caused by this performance deficiency, the analyst made the
following assumptions:
1. For fire zones that do not have the possibility for a fire to require the main
control room to be abandoned, the ignition frequency identified in the IPEEE
is an appropriate value.
2. The fire ignition frequency for the main control room (PFIF) is best quantified
by the licensees revised value of 6.88 x 10-3/yr.
3. Of the original 64 fire scenarios evaluated, 18 were determined to be
redundant and were eliminated, 41 of the remaining (documented in Table 1)


        In accordance with Inspection Manual Chapter 0609, Appendix F, Task 2.3.2, the
        analyst used a severity factor of 0.1 for determining the probability that a postulated fire
        would be self sustaining and grow to a size that could affect plant equipment.
E2-3  
        Given these values, the analyst calculated the main control room evacuation frequency
Enclosure 2  
        for fires in the main control room (FEVAC) as follows:
were identified as the predominant sequences associated with fires that did
                          FEVAC = PFIF * SF * PNS
not result in control room abandonment.
                                  = 6.88 x 10-3/yr * 0.1 * 1.3 x 10-2
                                  = 8.94 x 10-6/yr
4. The baseline conditional core damage probability for a control room
        In accordance with Procedure 5.4FIRE-S/D, operators are directed to evacuate the main
evacuation at the Cooper Nuclear Station is best represented by the creation
        control room and conduct a remote shutdown, if a fire in the main control room or any of
of a new probabilistic risk assessment tool created by the analyst using a
        the four areas documented in Assumption 8, if plant equipment spuriously actuates/de-
linked event tree method.  The primary event tree used in this model is
        energizes equipment, or if instrumentation becomes unreliable. Therefore, for all
displayed as Figure 1 in the Attachment.  The baseline conditional core
        scenarios except a postulated fire in the main control room, the probability of non-
damage probability as calculated by the linked event tree model was
        suppression by automatic or manual means are documented in Table 3, below.
1.14 x 10-1, which is similar to the generic industry value of 0.1.  
                                            Table 3
                  Control Room Abandonment Frequency
5. The analyst used an event tree, RECOVERY-PATH, shown in Figure 2 in the
Fire Area                  Ignition  Severity    Automatic      Manual        Abandonment
Attachment, to evaluate the likelihood of operator recovery via either
                        Frequency                Suppression Suppression          Frequency
restoration of HPCI or manually opening Valve RHR-MO-25B.  The resulting
                        (per year)                                                (per year)
non-recovery probability was 7.9 x 10-2.
Main Control
                        6.88 x 10-3    0.1        none        1.3 x 10-2      8.94 x 10-6
6. The risk related to a failure of Valve RHR-MO-25B to open following an
Room
evacuation of the main control room was evaluated using the analysts linked
Auxiliary Relay
event tree model.  The conditional core damage probability calculated by the  
                        1.42 x 10-3    0.1        none          0.24          3.41 x 10-5
linked event tree model was 2.4 x 10-1.
Room
Cable Expansion
7. Any fire in the main control room that is large enough to grow and that goes
                        1.69 x 10-4    0.1        2 x 10-2        0.24          8.11 x 10-8
unsuppressed for 20 minutes will lead to a control room evacuation.
Room
Cable Spreading
8. Any fire that is unsuppressed by automatic or manual means in the auxiliary
                        4.27 x 10-3    0.1        5 x 10-2        0.24          5.12 x 10-6
relay room, the cable spreading room, the cable expansion room or
Room
Area RB-FN will result in a main control room evacuation.  
Reactor Building
                        1.43 x 10-3    0.1        2 x 10-2        0.24          6.86 x 10-7
9. The Cooper SPAR model, Revision 3.31, represents an appropriate tool for
903 (RB-FN)
evaluation of the core damage probabilities associated with postulated fires
Total MCR Abandonment:                                                            4.89 x 10-5
that do not result in main control room evacuation.
                                                  E2-11                                Enclosure 2
10. All postulated fires in this analysis resulted in a reactor scram. In addition,
the postulated fire in Fire Area RB-K resulted in a loss-of-offsite power.  
11. Valves RHR-MO-25A and RHR-MO-25B are low pressure coolant injection
system isolation valves. These valves can prevent one method of decay heat
removal in the shutdown cooling mode of operation.  
12. For Valves RHR-MO-25A and RHR-MO-25B, the subject performance
deficiency only applies to the portion of the post fire procedures that direct the
transition into shutdown cooling.  Therefore, the low pressure injection
function is not affected.
13. Valve RHR-MO-25B must open from the motor-control center for operators to
initiate alternate shutdown cooling from the alternate shutdown panel
following a main control room evacuation.  


The licensees total control room abandonment frequency was 1.75 x 10-5. For the main
control room fire, the licensees calculations were more in-depth than the analysts. The
remaining fire areas were assessed by the licensee using IPEEE data. However, the
E2-4
following issues were noted with the licensees assessment:
Enclosure 2
        Kitchen fires were not included in licensees evaluation
14. Valve RHR-MO-17 is one of two RHR system shutdown cooling cold-leg
                *        This would tend to increase the ignition frequency
suction isolation valves. These valves can prevent decay heat removal in the  
                *        This might add more heat input than the electrical cabinet fires
shutdown cooling mode of operation.
                        modeled by the licensee
        Habitability Forced Abandonment
15. Valve RWCU-MO-18 is the outboard isolation valve for the reactor water
                *        Non-suppression probability did not account for fire brigade
cleanup system. The system is a closed-loop system outside containment
                        response time or the expected time to damage.
with piping rated at 1250 psig and 575°F.  The isol ation of this system is
                *        Reduced risk based on 3 specific cabinets causing a loss of
designed to protect the system demineralizer resins and as an isolation for a
                        ventilation early, when it should have increased the risk. Fire
piping break outside containment. The success or failure of the resins will not
                        modeling showed that fires in these cabinets could damage
affect the likelihood of core damage.  The failure of the system piping without
                        nearby cables and cause ventilation damper(s) to close.
isolation would contribute to an intersystem loss-of-coolant accident. 
                *        Risk Assessment Calculation ES-91 uses an abandonment value
However, the likelihood that the system piping fails and an automatic isolation
                        of 9.93 x 10-7. However, the supporting calculation performed by
is not generated would be very low.
                        EPM used 3.02 x 10-6.
      Equipment Failure Control Room Abandonment
16. Valve MS-MO-77 is a 3-inch main steam line drain.  The valve isolates a high
                *        Criteria for leaving the control room did not accurately reflect the
pressure drain line heading back to the main condenser. The licensee stated
                        guidance that was proceduralized.
that the failure to isolate this line would not result in a high enough loss-of-
                *        The evaluation of the Cable Expansion Room stated that the only
reactor coolant to affect the core damage frequency.  However, the failure to
                        fire source was self-ignition of cables. This was modeled as a hot
close this valve could result in a transient that would not have otherwise been
                        work fire, and it included a probability that administrative controls
caused by the postulated fire scenario.  
                        for hot work and fire watches would prevent such fires from getting
                        large enough to require control room abandonment. This is
17. Valve RR-MO-53A is the discharge isolation valve for Reactor Recirculation
                        inappropriate for self-ignition of cables, since there would not
Pump 1-A. The failure to close either this valve or Valve RR-MO-43A would
                        really be any fire watch present. Adjusting for this would increase
result in a short circuit of the shutdown cooling flow to the reactor vessel.
                        the risk in this area by two orders of magnitude.
The performance deficiency did not apply to Valve RR-MO-43A.
                *        The licensee concluded that fires in equipment in the four
                        alternate shutdown fire areas outside the main control room (see
18. Valve RHR-MO-921 provides isolation of a 3-inch steam line heading to the  
                        Assumption 8) would not result in control room abandonment
augmented offgas system. Just downstream of the valve the piping reduces
                        without providing a technical basis. The licensees Appendix R
to a 1-inch diameter line. This line taps off the HPCI pump steam line and  
                        analysis concluded that fire damage in these rooms require main
terminates in the main condenser high pressure drain header.  Because this
                        control room evacuation to prevent core damage.
is a 1-inch line, the valve does not contribute to the large-early release
                                          E2-12                                    Enclosure 2
frequency except for postulated seismic events.  Additionally, inventory
losses would be minimal and not affect mitigating systems necessary
following the subject fire initiation. Finally, the line would be automatically
isolated upon the isolation of the HPCI pump steam line. However, the failure
to close this valve could result in a transient that would not have otherwise
been caused by the postulated fire scenario.
19. Valve HPCI-MO-14 provides isolation of the HPCI system from the reactor
coolant system.  The failure to isolate this valve, when required, would result  
in reactor vessel level increasing in an uncontrolled manner, filling the steam
lines and suppressing the steam to all steam-driven equipment. This
increases the core damage probability because it results in the loss of all high
pressure systems.  
20. Valve HPCI-MO-16 provides isolation of the HPCI system from the reactor
coolant system.  The failure to isolate this valve, when required, would result
in reactor vessel level increasing in an uncontrolled manner, filling the steam


The analyst used the main control room abandonment frequencies documented in
Table 3. In addition, sensitivities were run using the licensees values.
Recovery Following Failure of Valve RHR-MO-25B
E2-5
As documented in Assumption 5, the analyst calculated a combined non-recovery
Enclosure 2
probability using the event tree shown in Figure 2 in the Attachment.
lines and suppressing the steam to all steam-driven equipment.  This
Table 4 documents the final split fractions used in quantifying this event tree.
increases the core damage probability because it results in the loss of all high
                                          Table 4
pressure systems.  
                  Split Fractions for RECOVERY-PATH
Top Event                                  How Assessed                Failure Probability
21. Valve RHR-MO-67 provides isolation of the RHR system from radwaste. 
LEVEL-DOWN                                  SPAR-H (Diagnosis Only)      1.0 x 10-3
Post-fire instructions affecting this valve are to assist in placing shutdown
SRV-STATUS                                  Best Estimate of Fraction    1.0 x 10-1
cooling in service. Failure of this valve would delay placing shutdown cooling
  CLOSE-SRVS                                  SPAR-H (Action Only)        5.0 x 10-4
in service and act as a distraction to operators placing the plant in a safe
  RESTORE-HPCI                                SPAR-H (Combined)            5.1 x 10-3
shutdown condition.
OPEN-MO-25B-3                              SPAR-H (Combined)            5.0 x 10-1
  OPEN-MO-25B-5/7                            SPAR-H (Combined)            5.5 x 10-2
22. The exposure time used for evaluating this finding should be determined in
Using the event tree in Figure 2 and the split fractions in Table 4, the analyst calculated
accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2,
a combined non-recovery probability of 7.9 x 10-2. The licensees combined non-
Site Specific Risk-Informed Inspection Notebook Usage Rules. Given that
recovery probability was 4.0 x 10-3. The licensee used a similar approach to quantify this
the performance deficiency was known to have existed for many years, the
value. However, the licensee assumed that operators would always shut the safety-
analyst used the 1-year of the current assessment cycle as the exposure
relief valves upon determining that reactor pressure vessel water level was decreasing.
period.  
The analyst assumed that some percentage of operators would continue to follow the
   
procedure and attempt to recover from the failed RHR valve or try alternate methods of
23. Based on fire damage and/or procedures, equipment affected by a postulated
low-pressure injection. In addition, the analyst identified the following issues that
fire in a given fire zone is unavailable for use as safe shutdown equipment.  
impacted the licensees analysis:
   
      *  The inspectors determined that it would require 112 ft-lbs of force to manually
24. The performance deficiency would have resulted in each of the demanded
          open Valve RHR-MO-25B. The analyst determined that this affected the
valves failing to respond following a postulated fire.  
          ergonomics of this recovery. Some operators may assume that the valve is on
   
          the backseat when large forces are required to open it. Some operators might
25. In accordance with the requirements of Procedure 5.4POST-FIRE, operators
          be incapable of applying this force to a 2-foot diameter hand wheel.
would perform the post-fire actions directed by the procedure following a fire
      *  The analyst noted that the following valves would be potential reasons for lack
in an applicable fire zone.  Therefore, the size and duration of the fire would
          of injection flow and/or may distract operators from diagnosis that
not be relevant to the failures caused by the performance deficiency.  
          Valve RHR-MO-025B is closed:
                  *      RHR-81B, RHR Loop B Injection Shutoff Valve, could be closed.
26. Given Assumption 25, severity factors and probabilities of non-
                  *      RHR-27CV, RHR Loop B Injection Line Testable Check Valve,
suppression were not addressed for postulated fires that did not result in
                          could be stuck closed.
main control room evacuation.  
                                        E2-13                                  Enclosure 2
Postulated Fires Not Involving Main Control Room Evacuation:
The senior reactor analyst used the SPAR model for Cooper Nuclear Station to estimate
the change in risk, associated with fires in each of the associated fire scenarios (Table 1,
Items 1 - 41) that was caused by the finding. Average unavailability for test and
maintenance of modeled equipment was assumed, and a cutset truncation of
1.0 x 10-13 was used. For each fire zone, the analyst calculated a baseline conditional
core damage probability consistent with Assumptions 9, 10, 25 and 26.
For areas where the postulated fire resulted in a reactor scram, the frequency of the  
transient initiator, IE-TRANS, was set to 1.0. All other initiators were set to the house
event FALSE, indicating that these events would not occur at the same time as a
reactor scram. Likewise, for Fire Area RB-K, the frequency of the loss-of-offsite power
initiator, IE-LOOP, was set to 1.0 while other initiators were set to the house event
FALSE.  


          *    RHR-MO-274B, Injection Line Testable Check Valve Bypass
                Valve, could be opened as an alternative.
          *    Operators could search for an alternate flow path.
E2-6
* The licensees evaluation did not include sequences involving the failure of the
Enclosure 2
  HPCI system shortly after main control room evacuation in their risk evaluation.
With input from the detailed IPEEE notebooks, maintained by the licensee, the analyst
  These sequences represented approximately 26 percent of the CDF as
was able to better assess the fire damage in each zone. This resulted in a more realistic
  calculated by the analyst. These sequences are important for the following
evaluation of the baseline fire risk for the zone, and lowering the change in risk for each
  reasons:
example.
        *      Failure of HPCI leads to the need for operators to rapidly
                depressurize the reactor to establish alternate shutdown cooling.
Consistent with guidance in the Reactor Accident Sequence Precursor Handbook,
                Decay heat will be much higher than for sequences involving early
including NRC document, "Common-Cause Failure Analysis in Event Assessment,
                HPCI success. Also, depressurization under high decay heat and
(June 2007)," the baseline established for the fire zone, and Assumptions 22 through 26,
                high temperature result in greater water mass loss. This will
the analyst modeled the resulting condition following a postulated fire in each fire zone
                significantly reduce the time available for recovery actions.
by adjusting the appropriate basic events in the SPAR model. Both the baseline and
        *      HPCI success sequences provide long time frames available with
conditional values for each fire zone are documented in Table 1.  
                HPCI operating. This reduces decay heat, increases time for
                recovery, and permits the establishment of an emergency
As shown in Table 1, the analyst calculated a change in core damage frequency (CDF)
                response organization. Those factors are not applicable to early
associated with these 41 fire scenarios of 2.9 x 10-6/yr.  
                HPCI failure sequences.
* The basis for operating HPCI was not well documented by the licensee. During
The analyst evaluated the licensees qualitative reviews of the 13 fire scenarios that
  many of the extended sequences, suppression pool temperature went well
were impacted by the failure of the HPCI turbine to trip.  In these scenarios, HPCI floods
  above the operating limits for HPCI cooling and remained high for extended
the steam lines and prevents further injection by either HPCI or reactor core isolation
  periods of time. The following facts were determined through inspection:
cooling system. Qualitatively, not all fires will grow to a size that causes a loss of the trip
          *      The design temperature for operating HPCI is 140°F based on
function due to spatial separation.  Additionally, not all unsuppressed fires would cause a  
                  process flow providing oil cooling.
failure of the HPCI trip function.  Finally, no operator recovery was credited in these
          *      General Electric provided a transient operating temperature of
evaluations.  
                  170°F for up to 2 hours.
          *
Given that these qualitative factors would all tend to decrease the significance of the  
          *      In the licensees best case evaluation of the performance
finding, the analyst believed that the total change in risk would be significantly lower than
                  deficiency, the suppression pool would remain above 150°F for
the 2.9 x 10-6/yr documented above. Based on analyst judgment and an assessment of  
                  10.6 hours.
the evidence provided by the licensee, an occurrence factor of 0.1 was applied to
* The licensee used a case-specific combined recovery in assessing the risk of
the13 fire scenarios.  This resulted in a total CDF of 7.8 x 10-7/yr. Therefore, the  
  this performance deficiency. Most of the recoveries discussed by the licensee
analyst determined that this value was the best estimate of the safety significance for
  would have been available with or without the performance deficiency.
these 41 fire scenarios.  
  Therefore, these should be in the baseline model and portions of the
  sequences subtracted from the case evaluation. This is the approach used by
  the analyst in the linked event trees model.
                                E2-14                                  Enclosure 2


              * The licensee stated during the regulatory conference that credit should
   
                be given for diesel-driven fire water pump injection. This is one of the
                licensees alternate strategies. However, the inspectors determined, and the
                licensee concurred, that this alternate method of injection requires that
E2-7
                Valve RHR-MO-25B be open. Therefore, no credit was given for this alternate
Enclosure 2
                strategy.
Table 1
        Conclusions:
Postulated Fires Not Involving Main Control Room Evacuation
The analyst concluded that the subject performance deficiency was of low to moderate
Fire Area/
significance (White). As documented in Table 1, for a period of exposure of 1 year, the analyst
Shutdown
determined a best estimate CDF for fire scenarios that did not require evacuation of the main
Strategy
control room of 7.8 x 10-7 using both quantitative and qualitative techniques. Additionally, using
Area/
the linked event tree model described in Assumption 4, for a period of exposure of 1 year, the
Zone
analyst calculated the CDF to be 7.3 x 10-6 for postulated fires leading to the abandonment of
Scenario
the main control room. This resulted in a total best estimate CDF of 8.1 x 10-6.
Number
                                                E2-15                                  Enclosure 2
Scenario 
Description
Ignition 
Frequency
Base
CCDP
Case
CCDP
Estimated
delta-CDF
Contribution
Function Affected
1C
1
RHR A
Pump Room
2.94E-03
8.82E-07
8.15E-05
2.37E-07
2
MCC K
3.02E-03
2.76E-05
1.28E-04
3.03E-07
3
MCC Q
3.93E-03
2.76E-05
1.28E-04
3.95E-07
4
MCC R
3.43E-03
2.76E-05
1.28E-04
3.44E-07
5
MCC RB
1.62E-03
1.12E-03
1.21E-03
1.46E-07
6
MCC S
2.23E-03
1.12E-03
1.21E-03
2.01E-07
7  
MCC Y
3.83E-03
1.12E-03
1.21E-03
3.45E-07
8  
Panel AA3
9.98E-04
2.76E-05
1.28E-04
1.00E-07
9
Panel BB3
9.98E-04
1.12E-03
1.21E-03
8.98E-08
10  
RCIC Starter
Rack
1.32E-03
5.27E-06
8.27E-05
1.02E-07
11
250V Div 1
Rack
5.10E-04
2.76E-05
1.28E-04
5.12E-08
12
250V Div 2
Rack
2.09E-04
1.12E-03
1.21E-03
1.88E-08
RB-CF
 
 
 
 
 
 
 
 
 
 
 
 
 
2A/2C
13
ASD Panels
3.02E-04
1.12E-03
1.21E-03
2.72E-08
Shut HPCI-MO-14,  
HPCI-MO-16,  
RHR-MO-921,  
RWCU-MO-18 and
MS-MO-77
7A
14
 
6.74E-03
7.64E-04
7.64E-04
0.00E+00
7B
15
 
1.36E-03
2.61E-06
2.61E-06
0.00E+00
8C
16
RPS Room
1A
4.15E-03
1.75E-07
1.75E-07
0.00E+00
8D
17
 
2.42E-03
3.57E-04
3.58E-04
4.84E-10  
CB-A
 
 
 
 
 
10B
18
Hallway 
(used CB
corridor)
1.09E-02
2.05E-05
2.85E-05
8.74E-08
Open RHR-MO-25B 
and RHR-MO-67


                                                                                    Attachment
          Y    Y   ~      Y        C       I   Y   nY   Y ~   x   n   n   n   n
          0   0  0   0     0         0   0   0   0   0     0   0   0   0   0
                        --________                   -   -
E2-8
                                                                        m      m
Enclosure 2
          T-                                   m
8H
                                                          0
19
                                                          T-       2   ?      ?
DC
                                                J J
Switchgear
                                            T
Room 1A
4.27E-03
3.49E-04
3.49E-04
1.28E-09
CB-A-1
 
8E
20
Battery
Room 1A
2.25E-03
8.74E-06
1.03E-05
3.51E-09
Open RHR-MO-17,
RHR-MO-25B, and
RHR-MO-67 
8G
21
DC
Switchgear 
Room 1B
4.27E-03
1.82E-03
1.83E-03
3.42E-08
CB-B
 
    
8F
22
Battery
Room 1B
2.25E-03
4.81E-06
5.73E-06
2.07E-09
Open RHR-MO-25A
8B
23
4.15E-03
1.75E-07
1.77E-07
5.81E-12
CB-C  
 
 
8C
24
RPS Room
1A
4.15E-03
1.75E-07
1.77E-07
5.81E-12
Open RHR-MO-17,
RHR-MO-25A, and
RHR-MO-67 
RB-DI (SW)
 
2D
25
RHR Heat
Exchanger
Room B
6.70E-04
8.66E-05
8.68E-05
1.27E-10
Shut HPCI-MO-14
and RR-MO-53A.
RB-DI (SE)
1D/1E
26
RHR B/HPCI
Pump Room
4.28E-03
6.48E-05
1.44E-04
3.37E-07
Shut HPCI-MO-14
and RR-MO-53A.
RB-J
 
3A
27
Switchgear
Room 1F
3.71E-03
5.28E-05
5.28E-05
0.00E+00
Open RHR-MO-17,
RHR-MO-25B, and
RHR-MO-67 
RB-K
 
3B
28
Switchgear
Room 1G
3.71E-03
1.77E-02
1.77E-02
0.00E+00
Open RHR-MO-25A
3C/3D
/3E
29
RB Elevation
932
1.13E-02
7.06E-06
8.99E-06
2.18E-08
RB-M
 
 
2B
30
RHR Hx 
Rm A
6.70E-04
7.06E-06
8.99E-06
1.29E-09
Open RHR-MO-17
and RHR-MO-25B
 
E2-9
Enclosure 2
3C/3D
/3E
31
Reactor
Building
Elevation
932
1.13E-02
1.22E-05
1.38E-05
1.81E-08
RB-N
 
 
2D
32
RHR Heat
Exchanger
Room B
6.70E-04
1.22E-05
1.38E-05
1.07E-09
Open RHR-MO-25A
11D
33
Condenser
Pit Area
3.10E-03
4.83E-06
6.20E-06
4.25E-09
11E
34
Reactor
Feedwater
Pump Area
6.25E-03
4.83E-06
6.20E-06
8.56E-09
11L
35
Pipe Chase
6.70E-04
4.83E-06
6.20E-06
9.18E-10
12C
36
Condenser
and Heater
Bay Area
3.27E-03
4.83E-06
6.20E-06
4.48E-09
12D
37
TB Floor 903
3.45E-03
4.83E-06
6.20E-06
4.73E-09
13A
38
Turbine
Operating
Floor
5.76E-03
4.83E-06
6.20E-06
7.89E-09
13B
39
Non-critical
Switchgear
Room
3.79E-03
4.83E-06
6.20E-06
5.19E-09
13C
40
Electric Shop
8.56E-04
4.83E-06
6.20E-06
1.17E-09
TB-A
    
    
    
 
    
    
    
    
    
13D
41
I&C Shop
8.90E-04
4.83E-06
6.20E-06
1.22E-09
Open RHR-MO-17,
RHR-MO-25A, and
RHR-MO-67 
Total Estimated CDF for 41 Postulated Fire Scenarios:
2.91E-06
 
Enclosure 2
E2-10
Post-Fire Remote Shutdown Calculations:
As documented in Assumptions 4, 5, and 6, the analyst created a linked event tree
model, using the Systems Analysis Programs for Hand-on Integrated Reliability
Evaluation (SAPHIRE) software provided by the Idaho National Laboratory, to evaluate
the risks related to fire-induced main control room abandonment at the Cooper Nuclear
Station.  This linked event tree was used to evaluate the increased risk from the subject
performance deficiency during the response to postulated fires in the main control room,
the auxiliary relay room, the cable spreading room, the cable expansion room or Fire
Area RB-FN.  The primary event tree used in this model is displayed as Figure 1 in the
Attachment.
As documented in Assumption 5, the analyst used an event tree to evaluate the
likelihood of operator recovery via either restoration of HPCI or manually opening
Valve RHR-MO-25B.  The resulting non-recovery probability was 7.9 x 10-2.
Using the linked event tree model described in Assumption 4, the analyst calculated the
CDF to be 7.3 x 10-6/yr.  The dominant cutsets are shown below in Table 2.
Table 2
Main Control Room Abandonment Cutsets
Postulated Fire
Sequence
Mitigating Functions
Results
Auxiliary Relay Room
4-01-03
Failure to Reestablish HPCI
Failure to Open MO-25B
1.7 x 10-6/yr
Main Control Room
3-01-03
Failure to Reestablish HPCI
Failure to Open MO-25B
4.5 x 10-7/yr
Auxiliary Relay Room
4-01-12
Early HPCI Failure
Failure to Open MO-25B
4.1 x 10-7/yr
Auxiliary Relay Room
4-01-12
HPCI Out of Service
Failure to Open MO-25B
2.7 x 10-7/yr
Main Control Room
4-01-12
Early HPCI Failure
Failure to Open MO-25B
1.1 x 10-7/yr
Control Room Abandonment Frequency
NUREG/CR-2258, Fire Risk Analysis for Nuclear Power Plants, provides that control
room evacuation would be required because of thick smoke if a fire went unsuppressed
for 20 minutes.  Given Assumption 6 and assuming that a fire takes 2 minutes to be
detected by automatic detection and/or by the operators, there are 18 minutes remaining
in which to suppress the fire prior to main control room evacuation being required.  NRC
Inspection Manual Chapter 0609, Appendix F, Table 2.7.1, Non-suppression Probability
Values for Manual Fire Fighting Based on Fire Duration (Time to Damage after
Detection) and Fire Type Category, provides a manual non-suppression probability
(PNS) for the control room of 1.3 x 10-2 given 18 minutes from time of detection until time
of equipment damage.  This is a reasonable approach, although fire modeling performed
by the licensee indicated that 16 minutes was the expected time to abandon the main
control room based on habitability.
 
Enclosure 2
E2-11
In accordance with Inspection Manual Chapter 0609, Appendix F, Task 2.3.2, the
analyst used a severity factor of 0.1 for determining the probability that a postulated fire
would be self sustaining and grow to a size that could affect plant equipment.
Given these values, the analyst calculated the main control room evacuation frequency
for fires in the main control room (FEVAC) as follows:
FEVAC =  PFIF  *  SF  *  PNS
=  6.88 x 10-3/yr  *  0.1  *  1.3 x 10-2
=  8.94 x 10-6/yr    
In accordance with Procedure 5.4FIRE-S/D, operators are directed to evacuate the main
control room and conduct a remote shutdown, if a fire in the main control room or any of
the four areas documented in Assumption 8, if plant equipment spuriously actuates/de-
energizes equipment, or if instrumentation becomes unreliable.  Therefore, for all
scenarios except a postulated fire in the main control room, the probability of non-
suppression by automatic or manual means are documented in Table 3, below. 
Table 3
Control Room Abandonment Frequency
Fire Area
Ignition
Frequency
(per year)
Severity
Automatic
Suppression
Manual
Suppression
Abandonment
Frequency
(per year)
Main Control
Room
6.88 x 10-3
0.1
none
1.3 x 10-2
8.94 x 10-6
Auxiliary Relay
Room
1.42 x 10-3
0.1
none
0.24
3.41 x 10-5
Cable Expansion
Room
1.69 x 10-4
0.1
2 x 10-2
0.24
8.11 x 10-8
Cable Spreading
Room
4.27 x 10-3
0.1
5 x 10-2
0.24
5.12 x 10-6
Reactor Building
903 (RB-FN)
1.43 x 10-3
0.1
2 x 10-2
0.24
6.86 x 10-7
Total MCR Abandonment:
4.89 x 10-5
 
Enclosure 2
E2-12
The licensees total control room abandonment frequency was 1.75 x 10-5.  For the main
control room fire, the licensees calculations were more in-depth than the analysts.  The
remaining fire areas were assessed by the licensee using IPEEE data.  However, the
following issues were noted with the licensees assessment:
Kitchen fires were not included in licensees evaluation
*
This would tend to increase the ignition frequency
*
This might add more heat input than the electrical cabinet fires
modeled by the licensee
Habitability Forced Abandonment
*
Non-suppression probability did not account for fire brigade
response time or the expected time to damage.
*
Reduced risk based on 3 specific cabinets causing a loss of
ventilation early, when it should have increased the risk.  Fire
modeling showed that fires in these cabinets could damage
nearby cables and cause ventilation damper(s) to close.
*
Risk Assessment Calculation ES-91 uses an abandonment value
of 9.93 x 10-7.  However, the supporting calculation performed by
EPM used 3.02 x 10-6.
Equipment Failure Control Room Abandonment
*
Criteria for leaving the control room did not accurately reflect the
guidance that was proceduralized.
*
The evaluation of the Cable Expansion Room stated that the only
fire source was self-ignition of cables.  This was modeled as a hot
work fire, and it included a probability that administrative controls
for hot work and fire watches would prevent such fires from getting
large enough to require control room abandonment.  This is
inappropriate for self-ignition of cables, since there would not
really be any fire watch present.  Adjusting for this would increase
the risk in this area by two orders of magnitude.
*
The licensee concluded that fires in equipment in the four
alternate shutdown fire areas outside the main control room (see
Assumption 8) would not result in control room abandonment
without providing a technical basis.  The licensees Appendix R
analysis concluded that fire damage in these rooms require main
control room evacuation to prevent core damage.
 
Enclosure 2
E2-13
The analyst used the main control room abandonment frequencies documented in
Table 3.  In addition, sensitivities were run using the licensees values.
Recovery Following Failure of Valve RHR-MO-25B
As documented in Assumption 5, the analyst calculated a combined non-recovery
probability using the event tree shown in Figure 2 in the Attachment.
Table 4 documents the final split fractions used in quantifying this event tree.
Using the event tree in Figure 2 and the split fractions in Table 4, the analyst calculated
a combined non-recovery probability of 7.9 x 10-2.  The licensees combined non-
recovery probability was 4.0 x 10-3.  The licensee used a similar approach to quantify this
value.  However, the licensee assumed that operators would always shut the safety-
relief valves upon determining that reactor pressure vessel water level was decreasing. 
The analyst assumed that some percentage of operators would continue to follow the
procedure and attempt to recover from the failed RHR valve or try alternate methods of
low-pressure injection.  In addition, the analyst identified the following issues that
impacted the licensees analysis:
*
The inspectors determined that it would require 112 ft-lbs of force to manually
open Valve RHR-MO-25B.  The analyst determined that this affected the
ergonomics of this recovery.  Some operators may assume that the valve is on
the backseat when large forces are required to open it.  Some operators might
be incapable of applying this force to a 2-foot diameter hand wheel. 
*
The analyst noted that the following valves would be potential reasons for lack
of injection flow and/or may distract operators from diagnosis that
Valve RHR-MO-025B is closed:
*
RHR-81B, RHR Loop B Injection Shutoff Valve, could be closed.
*
RHR-27CV, RHR Loop B Injection Line Testable Check Valve,
could be stuck closed.
Table 4
Split Fractions for RECOVERY-PATH
Top Event
How Assessed
Failure Probability
LEVEL-DOWN
SPAR-H (Diagnosis Only)
1.0 x 10-3
SRV-STATUS
Best Estimate of Fraction
1.0 x 10-1
CLOSE-SRVS
SPAR-H (Action Only)
5.0 x 10-4
RESTORE-HPCI
SPAR-H (Combined)
5.1 x 10-3
OPEN-MO-25B-3
SPAR-H (Combined) 
5.0 x 10-1
OPEN-MO-25B-5/7
SPAR-H (Combined) 
5.5 x 10-2
 
Enclosure 2
E2-14
*
RHR-MO-274B, Injection Line Testable Check Valve Bypass
Valve, could be opened as an alternative.
*
Operators could search for an alternate flow path.
*
The licensees evaluation did not include sequences involving the failure of the
HPCI system shortly after main control room evacuation in their risk evaluation. 
These sequences represented approximately 26 percent of the CDF as
calculated by the analyst.  These sequences are important for the following
reasons:
*
Failure of HPCI leads to the need for operators to rapidly
depressurize the reactor to establish alternate shutdown cooling. 
Decay heat will be much higher than for sequences involving early
HPCI success.  Also, depressurization under high decay heat and
high temperature result in greater water mass loss.  This will
significantly reduce the time available for recovery actions.
*
HPCI success sequences provide long time frames available with
HPCI operating.  This reduces decay heat, increases time for
recovery, and permits the establishment of an emergency
response organization.  Those factors are not applicable to early
HPCI failure sequences.
*
The basis for operating HPCI was not well documented by the licensee.  During
many of the extended sequences, suppression pool temperature went well
above the operating limits for HPCI cooling and remained high for extended
periods of time.  The following facts were determined through inspection:
*
The design temperature for operating HPCI is 140°F  based on
process flow providing oil cooling.
*
General Electric provided a transient operating temperature of
170°F for up to 2 hours.
*
*
In the licensees best case evaluation of the performance
deficiency, the suppression pool would remain above 150°F for
10.6 hours.
*
The licensee used a case-specific combined recovery in assessing the risk of
this performance deficiency.  Most of the recoveries discussed by the licensee
would have been available with or without the performance deficiency. 
Therefore, these should be in the baseline model and portions of the
sequences subtracted from the case evaluation.  This is the approach used by
the analyst in the linked event trees model.
 
Enclosure 2
E2-15
*
The licensee stated during the regulatory conference that credit should
be given for diesel-driven fire water pump injection.  This is one of the
licensees alternate strategies.  However, the inspectors determined, and the
licensee concurred, that this alternate method of injection requires that
Valve RHR-MO-25B be open.  Therefore, no credit was given for this alternate
strategy.
Conclusions:
The analyst concluded that the subject performance deficiency was of low to moderate
significance (White).  As documented in Table 1, for a period of exposure of 1 year, the analyst
determined a best estimate CDF for fire scenarios that did not require evacuation of the main
control room of 7.8 x 10-7 using both quantitative and qualitative techniques.  Additionally, using
the linked event tree model described in Assumption 4, for a period of exposure of 1 year, the
analyst calculated the CDF to be 7.3 x 10-6 for postulated fires leading to the abandonment of
the main control room.  This resulted in a total best estimate CDF of 8.1 x 10-6.
 
Y
0  
Y
~
Y
C
I
Y
Y
~
0
0
0
0
0
0
0
--________  
n
0
-  
T-  
T
m  
J
T  
Y
0 -  
0  
T-  
x
n
n
n
n
0
0
0
0
0
2  
J
m
?  
I
I
m
?
Figure 1
Figure 1
                                            T                  I  I
A-1
                                                                                    A-1
Attachment


                                                                  Attachment
cn  
                cn
W k 2  
                W
'? n  
                k
z  
                2
W  
                '?
0  
                n
c-'
                z     Y      Y  n  Y        n    Y  n  n
m 9  
                W     0      0  0  0        0    0  0  0
0  
                                      d-       In          al
Z
                m
W
                9
7  
                0
8
                7
a
                Z
W
                W
U
                8
cn
          0
W !I
          c-'
T
                a
P
                T
cn
                W
>
                U
U
                Pcn
W  
cn
0
'?
I?
Y
Y
n
0
0
0
Y
n
0
0  
d-  
In
I
I
Y
0
n
0
n
0
al
Figure 2
Figure 2
                W
A-2
                !I                                              A-2
Attachment
                cn
                >
                U
                '?
                W        I                I
                cn
                I?
                0


                                  SUPPLEMENTAL INFORMATION
                                        Summary of Findings
IR 05000298/2008008; 03/19/08 - 06/13/08; Cooper Nuclear Station: Triennial Fire Protection
Follow-up Inspection
Enclosure 3
The report covered a 3-month period of inspection follow-up and significance determination
E3-1
efforts by region-based inspectors and a senior risk analyst. One finding with an associated
SUPPLEMENTAL INFORMATION  
violation was determined to have White safety significance. The significance of most findings is
indicated by its color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609,
Summary of Findings  
"Significance Determination Process." Findings for which the significance determination
process does not apply may be green or be assigned a severity level after NRC management
IR 05000298/2008008; 03/19/08 - 06/13/08; Cooper Nuclear Station: Triennial Fire Protection  
review. The NRC's program for overseeing the safe operation of commercial nuclear power
Follow-up Inspection  
reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July
2000.
The report covered a 3-month period of inspection follow-up and significance determination  
A.     NRC-Identified and Self-Revealing Findings
efforts by region-based inspectors and a senior risk analyst. One finding with an associated  
        White. A violation of 10 CFR Part 50, Appendix B, Criterion V, was identified for failure
violation was determined to have White safety significance. The significance of most findings is  
        to ensure that some steps contained in emergency procedures at Cooper Nuclear
indicated by its color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609,  
        Station would work as written. Inspectors identified that steps in Emergency
"Significance Determination Process." Findings for which the significance determination  
        Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire
process does not apply may be green or be assigned a severity level after NRC management  
        Induced Shutdown From Outside Control Room, intended to reposition motor-operated
review. The NRC's program for overseeing the safe operation of commercial nuclear power  
        valves locally, would not have worked as written because the steps were not appropriate
reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July  
        for the configuration of the motor-starter circuits. This condition existed between 2004
2000.  
        and June, 2007. Appendix B to 10 CRF 50, Criterion V, was not met because these
        quality-related procedures would not work to allow operators to bring the plant to a safe
        shutdown condition in the event of certain fires. This finding had a cross-cutting aspect
A.  
        in Problem Identification and Resolution, under the Corrective Action Program attribute,
NRC-Identified and Self-Revealing Findings  
        because the licensee did not thoroughly evaluate the 2004 NRC violation to address
        causes and extent of condition (P.1.c -Evaluations).
White. A violation of 10 CFR Part 50, Appendix B, Criterion V, was identified for failure  
        This finding is of greater than minor safety significance because it impacted the
to ensure that some steps contained in emergency procedures at Cooper Nuclear  
        Mitigating Systems cornerstone objective to ensure the availability, reliability, and
Station would work as written. Inspectors identified that steps in Emergency  
        capability of systems that respond to initiating events to prevent undesirable
Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire  
        consequences. This finding affected both the procedure quality and protection against
Induced Shutdown From Outside Control Room, intended to reposition motor-operated  
        external factors (fires) attributes of this cornerstone objective. This finding was
valves locally, would not have worked as written because the steps were not appropriate  
        determined to have a White safety significance during a Phase 3 evaluation. The
for the configuration of the motor-starter circuits. This condition existed between 2004  
        scenarios of concern involve larger fires in specific areas of the plant which trigger
and June, 2007. Appendix B to 10 CRF 50, Criterion V, was not met because these  
        operators to implement fire response procedures to place the plant in a safe shutdown
quality-related procedures would not work to allow operators to bring the plant to a safe  
        condition. Since some of those actions could not be completed using the procedures as
shutdown condition in the event of certain fires. This finding had a cross-cutting aspect  
        written, this would challenge the operators ability to establish adequate core cooling.
in Problem Identification and Resolution, under the Corrective Action Program attribute,  
                                                  E3-1                                  Enclosure 3
because the licensee did not thoroughly evaluate the 2004 NRC violation to address  
causes and extent of condition (P.1.c -Evaluations).  
This finding is of greater than minor safety significance because it impacted the  
Mitigating Systems cornerstone objective to ensure the availability, reliability, and  
capability of systems that respond to initiating events to prevent undesirable  
consequences. This finding affected both the procedure quality and protection against  
external factors (fires) attributes of this cornerstone objective. This finding was  
determined to have a White safety significance during a Phase 3 evaluation. The  
scenarios of concern involve larger fires in specific areas of the plant which trigger  
operators to implement fire response procedures to place the plant in a safe shutdown  
condition. Since some of those actions could not be completed using the procedures as  
written, this would challenge the operators ability to establish adequate core cooling.  


                                    KEY POINTS OF CONTACT
Licensee
K. Billesbach, Quality Assurance Manager
M. Colomb, General Manager of Plant Operations
Enclosure 3
J. Flaherty, Senior Staff Licensing Engineer
E3-2
P. Fleming, Director of Nuclear Safety Assurance
KEY POINTS OF CONTACT  
V. Furr, Risk Management Engineer
G. Kline, Director of Engineering
Licensee  
G. Mace, Nuclear Assessment Manager
S. Minahan, Vice-President-Nuclear and Chief Nuclear Officer
K. Billesbach, Quality Assurance Manager  
S. Nelson, Risk Management Engineer
M. Colomb, General Manager of Plant Operations  
T. Shudak, Fire Protection Program Engineer
J. Flaherty, Senior Staff Licensing Engineer  
R. Stephan, Risk Assessment Engineer
P. Fleming, Director of Nuclear Safety Assurance  
K. Sutton, Risk Management Supervisor
V. Furr, Risk Management Engineer  
D. VanDerKamp, Licensing Supervisor
G. Kline, Director of Engineering  
NRC
G. Mace, Nuclear Assessment Manager  
J. Bongara, Senior Human Factors Specialist, Office of New Reactors
S. Minahan, Vice-President-Nuclear and Chief Nuclear Officer  
M. Chambers, Resident Inspector
S. Nelson, Risk Management Engineer  
J. Circle, Senior Reliability and Risk Analyst, Office of Nuclear Reactor Regulation
T. Shudak, Fire Protection Program Engineer  
N. Salgado, Chief, Operator Licensing and Human Performance Branch, Office of Nuclear
R. Stephan, Risk Assessment Engineer  
    Reactor Regulation
K. Sutton, Risk Management Supervisor  
N. Taylor, Senior Resident Inspector
D. VanDerKamp, Licensing Supervisor  
                    LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Discussed
05000298/2008007-01                   VIO               Two Inadequate Post-Fire Safe
NRC  
                                                          Shutdown Procedures
                                                E3-2                                  Enclosure 3
J. Bongara, Senior Human Factors Specialist, Office of New Reactors  
M. Chambers, Resident Inspector  
J. Circle, Senior Reliability and Risk Analyst, Office of Nuclear Reactor Regulation  
N. Salgado, Chief, Operator Licensing and Human Performance Branch, Office of Nuclear  
    Reactor Regulation  
N. Taylor, Senior Resident Inspector  
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED  
Discussed  
05000298/2008007-01  
VIO  
Two Inadequate Post-Fire Safe  
Shutdown Procedures  


                            LIST OF DOCUMENTS REVIEWED
PROCEDURES
              Number                                   Title             Revision
Administrative Procedure 0.1           Procedure Use and Adherence           31
Enclosure 3
Administrative Procedure 0.4A           Procedure Change Process           various
E3-3
                                        Supplement
LIST OF DOCUMENTS REVIEWED  
Administrative Procedure 2.0.1.2       Operations Procedure Policy           27
Administrative Procedure 2.0.3         Conduct of Operations                 58
PROCEDURES  
Emergency Procedure 5.4 Fire           General Fire Procedure               14
Emergency Procedure 5.4 Post-Fire       Post-Fire Operational Information 12 & 13
Number  
Emergency Procedure 5.4 Fire-S/D       Fire Induced Shutdown From         14 & 15
Title  
                                        Outside Control Room
Revision  
SELF-ASSESSMENTS AND AUDITS
Administrative Procedure 0.1
QA Audit 07-01         Fire Protection Program                             02/2007
Procedure Use and Adherence  
Self-assessment         Manual Action Feasibility - Review of Cooper       05/18/07
31  
                        Nuclear Station Post-Fire Manual Actions With NRC
Administrative Procedure 0.4A  
                        Inspection Manual Post-Fire Manual Action
Procedure Change Process  
                        Feasibility Criteria
Supplement  
Procedure Change       Emergency Procedure 5.4 POST-FIRE, Post Fire     Revision 4
Request                Operational Information
various
Alarm Response         HPCI Turbine Oil Cooler Temperature High          Revision 17
Administrative Procedure 2.0.1.2  
Procedure 2.3_9-3-2,
Operations Procedure Policy  
Panel 9-3-2/D-1
27  
CONDITION REPORTS
Administrative Procedure 2.0.3  
2007-04155
Conduct of Operations  
2004-03034
58  
2004-03081
Emergency Procedure 5.4 Fire  
2003-05433
General Fire Procedure  
                                              E3-3                          Enclosure 3
14  
Emergency Procedure 5.4 Post-Fire  
Post-Fire Operational Information  
12 & 13  
Emergency Procedure 5.4 Fire-S/D  
Fire Induced Shutdown From  
Outside Control Room
14 & 15  
SELF-ASSESSMENTS AND AUDITS  
QA Audit 07-01  
Fire Protection Program  
02/2007  
Self-assessment  
Manual Action Feasibility - Review of Cooper  
Nuclear Station Post-Fire Manual Actions With NRC  
Inspection Manual Post-Fire Manual Action  
Feasibility Criteria  
05/18/07
Procedure Change  
Request
Emergency Procedure 5.4 POST-FIRE, Post Fire  
Operational Information  
Revision 4
Alarm Response  
Procedure 2.3_9-3-2,  
Panel 9-3-2/D-1  
HPCI Turbine Oil Cooler Temperature High
Revision 17
CONDITION REPORTS  
2007-04155  
2004-03034  
2004-03081  
2003-05433  


CALCULATIONS
Enclosure 3
E3-4
CALCULATIONS  
Fauske Review of Cooper Nuclear Station Calculation NEDC 08-035, Suppression Pool Heat-
Fauske Review of Cooper Nuclear Station Calculation NEDC 08-035, Suppression Pool Heat-
up Response for Appendix R Event with 24 Hour HPCI Operation.
up Response for Appendix R Event with 24 Hour HPCI Operation.  
Calculation NEDC 08-035, Suppression Pool Heat-up Response for Appendix R Event with
24 Hour HPCI Operation, Revision 0.
Calculation NEDC 08-035, Suppression Pool Heat-up Response for Appendix R Event with  
Calculation NEDC 08-041, Main Control Room Forced Abandonment Fire Scenario Analysis,
24 Hour HPCI Operation, Revision 0.  
Revision 0.
EPM Calculation P1906-07-011b-001, Main Control Room Forced Abandonment Fire Scenario
Calculation NEDC 08-041, Main Control Room Forced Abandonment Fire Scenario Analysis,  
Analysis,5/2008.
Revision 0.  
Calculation ES-091, Detailed PSA Study of Fire Protection Triennial Inspection, Revision 0.
Calculation NEDC 08-032, EPM Calculation 1906-07-06, Fire Ignition Frequencies, Revision 0.
EPM Calculation P1906-07-011b-001, Main Control Room Forced Abandonment Fire Scenario  
MISCELLANEOUS
Analysis,5/2008.  
White paper discussion on SRV circuit operation from the alternate shutdown panel
dated 5/19/2008.
Calculation ES-091, Detailed PSA Study of Fire Protection Triennial Inspection, Revision 0.  
GE Service Information Letter 615, ADS/HPCI Functional Redundancy, dated 3/4/1998.
NUREG 2258, Fire Risk Analysis for Nuclear Power Plants.
Calculation NEDC 08-032, EPM Calculation 1906-07-06, Fire Ignition Frequencies, Revision 0.  
NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities.
NPPD Letter NLS2008044, Additional Information for Consideration in Addressing Inspection
Finding, dated 5/8/2008.
MISCELLANEOUS  
Generic Letter 82-21, Technical Specifications for Fire Protection Audits.
NRC Inspection Report 05000317/2007009 and 05000318/2007009.
White paper discussion on SRV circuit operation from the alternate shutdown panel  
NRC Inspection Report 05000282/2006009 and 05000306/2006009.
dated 5/19/2008.  
NRC Inspection Report 05000261/2007007.
Additional documents reviewed as part of inspecting this finding are documented in NRC
GE Service Information Letter 615, ADS/HPCI Functional Redundancy, dated 3/4/1998.  
NUREG 2258, Fire Risk Analysis for Nuclear Power Plants.  
NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities.  
NPPD Letter NLS2008044, Additional Information for Consideration in Addressing Inspection  
Finding, dated 5/8/2008.  
Generic Letter 82-21, Technical Specifications for Fire Protection Audits.  
NRC Inspection Report 05000317/2007009 and 05000318/2007009.  
NRC Inspection Report 05000282/2006009 and 05000306/2006009.  
NRC Inspection Report 05000261/2007007.  
Additional documents reviewed as part of inspecting this finding are documented in NRC  
Inspection Report 05000298/2008007.
Inspection Report 05000298/2008007.
                                              E3-4                                  Enclosure 3
}}
}}

Latest revision as of 16:22, 14 January 2025

IR 05000298-08-008, on 03/19/2008 - 06/13/2008, for Cooper, Triennial Fire Protection Follow-up Inspection
ML081650090
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/13/2008
From: Caniano R
Division of Reactor Safety IV
To: Minahan S
Nebraska Public Power District (NPPD)
References
EA-07-204 IR-08-008
Download: ML081650090 (29)


See also: IR 05000298/2008008

Text

June 13, 2008

EA 07-204

Stewart B. Minahan

Vice President-Nuclear and CNO

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

SUBJECT:

FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND

NOTICE OF VIOLATION, NRC INSPECTION REPORT 05000298/2008008,

COOPER NUCLEAR STATION

Dear Mr. Minahan:

The purpose of this letter is to provide you the final results of our significance determination of

the preliminary Greater than Green finding identified in the Nuclear Regulatory Commission

(NRC) Inspection Report 05000298/2008007. The inspection finding was assessed using the

significance determination process and was preliminarily characterized as a finding of greater

than very low safety significance resulting in the need for further evaluation to determine the

significance and, therefore, the need for additional NRC action.

Our preliminary finding was discussed with your staff during an exit meeting on March 18, 2008.

The finding involved two procedures used by operators to bring the plant to a safe shutdown

condition in the event of certain postulated fire scenarios. The procedures could not be

performed as written. This performance deficiency involved the failure to properly verify and

validate these infrequently used procedures.

The NRCs preliminary assessment of the safety significance of this inspection finding was a

modified bounding analysis based upon the best available information. This simplified analysis

demonstrated that this finding did not have high importance to safety, but that additional

information and analyses would be needed to determine the final significance. Therefore, the

finding was issued with a preliminary safety significance of Greater than Green.

At the request of Nebraska Public Power District, a regulatory conference was held on May 13,

2008, to further discuss your views on this issue. A copy of the handout you provided is

attached to the regulatory conference meeting summary (ML081550102). During the regulatory

conference, your staff described your assessment of the significance of the finding and your

views on the applicability of the Interim Enforcement Discretion Policy.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Nebraska Public Power District

- 2 -

After considering the information developed during this inspection, the additional information

you provided in your letter dated May 8, 2008 (ML081540362), and the information your staff

provided at the regulatory conference, the NRC has concluded that the inspection finding is

appropriately characterized as White, an issue with low to moderate increased importance to

safety, which may require additional NRC inspections.

The final significance determination, described in Enclosure 2, was based on the significance

determination process Phase 3 analysis performed by the NRC staff using multiple risk tools

including, a standardized plant analysis risk model simulation of the potential fires that would

impact this finding, hand calculations, and a linked event tree model of the Cooper Nuclear

Station's remote shutdown capabilities developed by NRC analysts. This evaluation considered

insights and values provided by your staff. The results of your analyses and fire modeling

provided important information needed for our staff to complete our significance determination

process evaluation. Our final assessment of the change in risk due to this performance

deficiency has dropped an order of magnitude. For fire areas that would not have the potential

to cause a control room evacuation, the NRC results closely match your results. However, for

cases with the potential to cause control room evacuation, which dominated the safety impact,

our results indicated greater safety significance than your results. The areas where the two

analyses differed significantly included the frequency with which operators would abandon the

main control room, and the assessment of the human reliability associated with the expected

recovery actions. Your analysis did not adequately model the impact of spurious operations due

to fire damage in alternate shutdown fire areas or treat them consistent with the plant operating

procedure, which would be expected to result in a higher evacuation frequency. In addition,

your evaluation did not include core damage sequences that involved the failure of the high

pressure coolant injection system early in the event. These sequences represented about

one fourth of the risk in our evaluation. We estimated the change in core damage frequency

associated with this finding to be 8.1 x 10-6, as discussed in Enclosure 2 to this letter, compared

to your final significance of 8.6 x 10-8.

You have 30 calendar days from the date of this letter to appeal the staffs determination of

significance for the identified White finding. Such appeals will be considered to have merit only

if they meet the criteria given in NRC Inspection Manual Chapter 0609, Significance

Determination Process, Attachment 2, Process for Appealing NRC Characterization of

Inspection Findings (Significance Determination Process Appeal Process).

The NRC has also determined that the two examples of inadequate fire response operating

procedures involved a violation of NRC requirements as cited in the enclosed Notice of

Violation (Notice). The circumstances surrounding the violation are described in detail in NRC

Inspection Report 05000298/2008007. This violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings involved steps contained in Emergency

Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire

Induced Shutdown From Outside Control Room. Certain steps in the procedures intended to

reposition motor-operated valves locally, would not have worked as written because the steps

were not appropriate for the configuration of the motor-starter circuits. As a consequence of this

violation, these quality-related procedures would have challenged the operators ability to bring

the plant to a safe shutdown condition in the event of certain fires. In accordance with the NRC

Enforcement Policy, the Notice is considered escalated enforcement action because it is

associated with a White finding.

Nebraska Public Power District

- 3 -

Because plant performance for this issue has been determined to be in the regulatory response

band, we will use the NRC Action Matrix, as described in NRC Inspection Manual Chapter 0305,

Operating Reactor Assessment Program, to determine the most appropriate NRC response

and any increase in NRC oversight. We will notify you by separate correspondence of that

determination.

The staff has reviewed the position provided in your March 10, 2008, letter (ML080740507)

concerning the circumstances surrounding this violation and how the Interim Enforcement Policy

Regarding Enforcement Discretion for Certain Fire Protection Issues related to this violation.

During the regulatory conference, your presentation reiterated the position stated in your letter.

Our review has concluded that your letter and regulatory conference presentation provided no

new information. Therefore, we maintain that all of the requirements of the Interim Enforcement

Policy Regarding Enforcement Discretion for Certain Fire Protection Issues were not satisfied

and enforcement discretion will not be granted for this violation.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure(s), and your response, if you choose to provide one, will be made available

electronically for public inspection in the NRC Public Document Room or from the NRCs

document system (ADAMS), accessible from the NRC website at www.nrc.gov/reading-

rm/pdr.html or www.nrc.gov/reading-rm/adams.html. To the extent possible, your response

should not include any personal privacy, proprietary, or safeguards information so that it can be

made available to the Public without redaction.

Sincerely,

/RA/

Roy J. Caniano, Director

Division of Reactor Safety

Docket: 50-298

License: DPR-46

Enclosures:

1. Notice of Violation

2. Final Significance Determination

3. Supplemental Information

cc w/enclosures:

Gene Mace

Nuclear Asset Manager

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

Nebraska Public Power District

- 4 -

John C. McClure, Vice President

and General Counsel

Nebraska Public Power District

P.O. Box 499

Columbus, NE 68602-0499

David Van Der Kamp

Licensing Manager

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

Michael J. Linder, Director

Nebraska Department of

Environmental Quality

P.O. Box 98922

Lincoln, NE 68509-8922

Chairman

Nemaha County Board of Commissioners

Nemaha County Courthouse

1824 N Street

Auburn, NE 68305

Julia Schmitt, Manager

Radiation Control Program

Nebraska Health & Human Services

Dept. of Regulation & Licensing

Division of Public Health Assurance

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

H. Floyd Gilzow

Deputy Director for Policy

Missouri Department of Natural Resources

P. O. Box 176

Jefferson City, MO 65102-0176

Director, Missouri State Emergency

Management Agency

P.O. Box 116

Jefferson City, MO 65102-0116

Nebraska Public Power District

- 5 -

Chief, Radiation and Asbestos

Control Section

Kansas Department of Health

and Environment

Bureau of Air and Radiation

1000 SW Jackson, Suite 310

Topeka, KS 66612-1366

Melanie Rasmussen, State Liaison Officer/

Radiation Control Program Director

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

John F. McCann, Director, Licensing

Entergy Nuclear Northeast

Entergy Nuclear Operations, Inc.

440 Hamilton Avenue

White Plains, NY 10601-1813

Keith G. Henke, Planner

Division of Community and Public Health

Office of Emergency Coordination

930 Wildwood, P.O. Box 570

Jefferson City, MO 65102

Ronald L. McCabe, Chief

Technological Hazards Branch

National Preparedness Division

DHS/FEMA

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

Daniel K. McGhee, State Liaison Officer

Bureau of Radiological Health

Iowa Department of Public Health

Lucas State Office Building, 5th Floor

321 East 12th Street

Des Moines, IA 50319

Ronald D. Asche, President

and Chief Executive Officer

Nebraska Public Power District

1414 15th Street

Columbus, NE 68601

Nebraska Public Power District

- 6 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov

DRS Director (Roy.Caniano@nrc.gov )

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (Nick.Taylor@nrc.gov)

Branch Chief, DRP/C (Rick.Deese@nrc.gov)

Senior Project Engineer, DRP/C (Wayne.Walker@nrc.gov )

Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )

RITS Coordinator (Marisa.Herrera@nrc.gov )

DRS STA (Dale.Powers@nrc.gov )

J. Adams, OEDO RIV Coordinator (John.Adams@nrc.gov)

P. Lougheed, OEDO RIV Coordinator (Patricia.Lougheed@nrc.gov )

ROPreports

CNS Site Secretary (Sue.Farmer@nrc.gov)

OEMail.Resource@nrc.gov

OEWeb.Resource@nrc.gov

Doug.Starkey@nrc.gov

Maryann.Ashley@nrc.gov

Michael.Vasquez@nrc.gov

Victor.Dricks@nrc.gov

Bill.Maier@nrc.gov

Linda.Smith@nrc.gov

Neil.OKeefe@nrc.gov

John.Mateychick@nrc.gov

Karla.Fuller@nrc.gov

Nick.Taylor@nrc.gov

Michael.Cheok@nrc.gov

John.Grobe@nrc.gov

Mark.Cunningham@nrc.gov

Alexander.Klein@nrc.gov

Michael.Franovich@nrc.gov

Jeff.Circle@nrc.gov

Joseph.Anderson@nrc.gov

Tim.Kobetz@nrc.gov

Thomas.Hiltz@nrc.gov

Carl.Lyon@nrc.gov

Undine.Shoop@nrc.gov

Richard.borchardt@nrc.gov

Melissa.Wyatt@nrc.gov

Paul.Lain@nrc.gov

Bruce.Boger@nrc.gov

Harold.Barrett@nrc.gov

Frederick.Brown@nrc.gov

Christine.Tucci@nrc.gov

Amy.Powell@nrc.gov

Christi.Maier@nrc.gov

SUNSI Review Completed: LJS ADAMS:

Yes

No Initials: __________

Publicly Available Non-Publicly Available Sensitive

Non-Sensitive

S:\\DRS\\REPORTS\\CN 2008008 Final Significance ltr - NFO

SRI/EB2

SRI/EB2

C:DRS/EB2

SRA/DRS

ACES

C:DRP/C

D:DRS

JMMateychick

NFOKeefe

LJSmith

DLoveless

CMaier

DChamberlain

RJCaniano

E /RA/

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

6/7/08

6/5/08

6/5/08

6/5/08

6/5/08

6/5/08

6/13/08

OFFICIAL RECORD COPY

T=Telephone

E=E-mail

F=Fax

E1-1

Enclosure 1

NOTICE OF VIOLATION

Nebraska Public Power District

Docket No. 50-298

Cooper Nuclear Station

License No. DPR-46

EA-07-204

During an NRC inspection completed on March 18, 2008, a violation of NRC requirements was

identified. In accordance with the NRC Enforcement policy, the violation is listed below:

Appendix B to 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings,

requires, in part, that activities affecting quality shall be prescribed by documented

instructions, procedures, or drawings, of a type appropriate to the circumstances and

shall be accomplished in accordance with these instructions, procedures, or drawings.

Procedure 0.4A, Procedure Change Process Supplement, Revision 0, implements

measures to ensure the procedure quality required by Criterion V for procedures

designated as quality-related. Attachment 2 to this procedure requires verification and

validation to be performed periodically, when writing a new procedure, when significant

changes are made to sequencing of complex steps in existing procedures, and when

infrequently used procedures are written or changed. Verification and validation efforts

are defined in this procedure as actions to confirm that the procedure steps: (1) are

usable; (2) are accurate; (3) contain the appropriate level of detail; (3) use equipment

nomenclature that corresponds to the actual hardware; and (4) satisfy plant design and

licensing basis. Procedure 0.4A applies to changes to Emergency Procedures

5.4POST-FIRE and 5.4FIRE-S/D.

Contrary to the above, between 1997 and June, 2007, the licensee failed to ensure that

two emergency operating procedures which controlled activities affecting quality were

appropriate to the circumstances. Specifically, the licensee changed Emergency

Procedures 5.4POST-FIRE and 5.4FIRE-S/D in 1997 to add steps that were

inappropriate to the circumstances because they would not work as written. Additionally,

the licensee failed to properly verify and validate procedure steps to ensure that they

would work to accomplish the necessary actions.

This violation is associated with a White significance determination process finding.

The NRC has concluded that information regarding the reason for the violation, the corrective

actions taken and planned to correct the violation and prevent recurrence and the date when full

compliance was achieved is already adequately addressed on the docket in NRC Inspection

Reports 05000298/2007008, 05000298/2008007, and Licensee Event Report 05000298/2007005-00. However, you are required to submit a written statement or explanation

pursuant to 10 CFR 2.201 if the description therein does not accurately reflect your corrective

actions or your position. In that case, or if you choose to respond, clearly mark your response

as a "Reply to a Notice of Violation," include the EA number, and send it to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a

copy to the Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the

facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this

Notice of Violation (Notice).

E1-2

Enclosure 1

If you choose to respond, your response will be made available electronically for public

inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),

accessible from the NRC website at www.nrc.gov/reading-rm/pdr.html or www.nrc.gov/reading-

rm/adams.html. Therefore, to the extent possible, the response should not include any personal

privacy, proprietary, or safeguards information so that it can be made available to the Public

without redaction.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis of your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Dated this 13th day of June 2008

E2-1

Enclosure 2

FINAL SIGNIFICANCE DETERMINATION SUMMARY

Significance Determination Basis

a.

Phase 1 Screening Logic, Results, and Assumptions

In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue

Screening," the issue was determined to be more than minor because it was associated

with the equipment performance attribute and affected the mitigating systems

cornerstone objective to ensure the availability, reliability, or function of a system or train

in a mitigating system in that 10 motor-operated valves would not have functioned

following a postulated fire in multiple fire zones. The following summarizes the valves

and fire areas affected:

Valves Affected

HPCI-MO-14

Steam Supply to High Pressure Coolant Injection (HPCI)

Turbine Valve

HPCI-MO-16

Steam Supply to HPCI Turbine Outboard Isolation Valve

RHR-MO-17

Shutdown Cooling Suction Valve

RHR-MO-25A

Residual Heat Removal (RHR) A Inboard Injection Valve

RHR-MO-25B

RHR B Inboard Injection Valve

RHR-MO-67

RHR Discharge to Radwaste Inboard Valve

RHR-MO-921

Augmented Offgas Steam Supply Valve

RWCU-MO-18

Outboard Reactor Water Cleanup Isolation Valve

MS-MO-77

Outboard Main Steam Drain Line Isolation Valve

RR-MO-53A

Reactor Recirculation Pump A Discharge Valve

Fire Areas Affected

CB-A

Control Building Reactor Protection System Room 1A, Seal Water

Pump Area, and Hallway

CB-A-1

Control Building Division 1 Switchgear Room and Battery Room

CB-B

Control Building Division 2 Switchgear Room and Battery Room

CB-C

Control Building Reactor Protection System Room 1B

CB-D

Control Room, Cable Spreading Room, Cable Expansion Room,

and Auxiliary Relay Room

RB-CF

Reactor Building North/Northwest 903, Northwest Quad 889 and

859, and RHR Heat Exchanger Room A

RB-DI (SW)

Reactor Building South/Southwest 903, Southwest Quad 889 and

859, and RHR Heat Exchanger Room B

RB-DI (SE)

Reactor Building RHR Pump B/HPCI Pump Room

RB-J

Reactor Building Critical Switchgear Room 1F

RB-K

Reactor Building Critical Switchgear Room 1G

RB-M

Reactor Building North/Northwest 931 and RHR Heat Exchanger

Room A

E2-2

Enclosure 2

RB-N

Reactor Building South/Southwest 931 and RHR Heat Exchanger

Room B

RB-FN

Reactor Building 903, Northeast Corner

TB-A

Turbine Building (multiple areas)

The significance determination process (SDP) Phase 1 Screening Worksheet (Manual

Chapter 0609, Attachment 4), Table 3b directs the user to Manual Chapter 0609,

Appendix F, Fire Protection Significance Determination Process, because it affected

fire protection defense-in-depth strategies involving post fire safe shutdown systems.

However, Manual Chapter 0308, Attachment 3, Appendix F, Technical Basis for Fire

Protection Significance Determination Process for at Power Operations, states that

Manual Chapter 0609, Appendix F, does not include explicit treatment of fires in the

main control room. The Phase 2 process can be utilized in the treatment of main control

room fires, but it is recommended that additional guidance be sought in the conduct of

such an analysis.

b.

Phase 2 Risk Estimation

Based on the complexity and scope of the subject finding and the significance of the

finding to main control room fires, the analyst determined that a Phase 2 estimation was

not appropriate.

c.

Phase 3 Analysis

In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3

analysis using input from the Nebraska Public Power District, Individual Plant

Examination for External Events (IPEEE) Report - 10 CFR 50.54(f) Cooper Nuclear

Station, NRC Docket No. 50-298, License No. DPR-46, dated October 30, 1996, the

Standardized Plant Analysis Risk (SPAR) Model for Cooper, Revision 3.31, dated

September 2007, licensee input (see documents reviewed list in Enclosure 3), a

probabilistic risk assessment using a linked event tree model created by the analyst for

evaluating main control room evacuation scenarios, and appropriate hand calculations.

Assumptions:

Following the regulatory conference, the analysts revised the Phase 3 analysis. To

evaluate the change in risk caused by this performance deficiency, the analyst made the

following assumptions:

1. For fire zones that do not have the possibility for a fire to require the main

control room to be abandoned, the ignition frequency identified in the IPEEE

is an appropriate value.

2. The fire ignition frequency for the main control room (PFIF) is best quantified

by the licensees revised value of 6.88 x 10-3/yr.

3. Of the original 64 fire scenarios evaluated, 18 were determined to be

redundant and were eliminated, 41 of the remaining (documented in Table 1)

E2-3

Enclosure 2

were identified as the predominant sequences associated with fires that did

not result in control room abandonment.

4. The baseline conditional core damage probability for a control room

evacuation at the Cooper Nuclear Station is best represented by the creation

of a new probabilistic risk assessment tool created by the analyst using a

linked event tree method. The primary event tree used in this model is

displayed as Figure 1 in the Attachment. The baseline conditional core

damage probability as calculated by the linked event tree model was

1.14 x 10-1, which is similar to the generic industry value of 0.1.

5. The analyst used an event tree, RECOVERY-PATH, shown in Figure 2 in the

Attachment, to evaluate the likelihood of operator recovery via either

restoration of HPCI or manually opening Valve RHR-MO-25B. The resulting

non-recovery probability was 7.9 x 10-2.

6. The risk related to a failure of Valve RHR-MO-25B to open following an

evacuation of the main control room was evaluated using the analysts linked

event tree model. The conditional core damage probability calculated by the

linked event tree model was 2.4 x 10-1.

7. Any fire in the main control room that is large enough to grow and that goes

unsuppressed for 20 minutes will lead to a control room evacuation.

8. Any fire that is unsuppressed by automatic or manual means in the auxiliary

relay room, the cable spreading room, the cable expansion room or

Area RB-FN will result in a main control room evacuation.

9. The Cooper SPAR model, Revision 3.31, represents an appropriate tool for

evaluation of the core damage probabilities associated with postulated fires

that do not result in main control room evacuation.

10. All postulated fires in this analysis resulted in a reactor scram. In addition,

the postulated fire in Fire Area RB-K resulted in a loss-of-offsite power.

11. Valves RHR-MO-25A and RHR-MO-25B are low pressure coolant injection

system isolation valves. These valves can prevent one method of decay heat

removal in the shutdown cooling mode of operation.

12. For Valves RHR-MO-25A and RHR-MO-25B, the subject performance

deficiency only applies to the portion of the post fire procedures that direct the

transition into shutdown cooling. Therefore, the low pressure injection

function is not affected.

13. Valve RHR-MO-25B must open from the motor-control center for operators to

initiate alternate shutdown cooling from the alternate shutdown panel

following a main control room evacuation.

E2-4

Enclosure 2

14. Valve RHR-MO-17 is one of two RHR system shutdown cooling cold-leg

suction isolation valves. These valves can prevent decay heat removal in the

shutdown cooling mode of operation.

15. Valve RWCU-MO-18 is the outboard isolation valve for the reactor water

cleanup system. The system is a closed-loop system outside containment

with piping rated at 1250 psig and 575°F. The isol ation of this system is

designed to protect the system demineralizer resins and as an isolation for a

piping break outside containment. The success or failure of the resins will not

affect the likelihood of core damage. The failure of the system piping without

isolation would contribute to an intersystem loss-of-coolant accident.

However, the likelihood that the system piping fails and an automatic isolation

is not generated would be very low.

16. Valve MS-MO-77 is a 3-inch main steam line drain. The valve isolates a high

pressure drain line heading back to the main condenser. The licensee stated

that the failure to isolate this line would not result in a high enough loss-of-

reactor coolant to affect the core damage frequency. However, the failure to

close this valve could result in a transient that would not have otherwise been

caused by the postulated fire scenario.

17. Valve RR-MO-53A is the discharge isolation valve for Reactor Recirculation

Pump 1-A. The failure to close either this valve or Valve RR-MO-43A would

result in a short circuit of the shutdown cooling flow to the reactor vessel.

The performance deficiency did not apply to Valve RR-MO-43A.

18. Valve RHR-MO-921 provides isolation of a 3-inch steam line heading to the

augmented offgas system. Just downstream of the valve the piping reduces

to a 1-inch diameter line. This line taps off the HPCI pump steam line and

terminates in the main condenser high pressure drain header. Because this

is a 1-inch line, the valve does not contribute to the large-early release

frequency except for postulated seismic events. Additionally, inventory

losses would be minimal and not affect mitigating systems necessary

following the subject fire initiation. Finally, the line would be automatically

isolated upon the isolation of the HPCI pump steam line. However, the failure

to close this valve could result in a transient that would not have otherwise

been caused by the postulated fire scenario.

19. Valve HPCI-MO-14 provides isolation of the HPCI system from the reactor

coolant system. The failure to isolate this valve, when required, would result

in reactor vessel level increasing in an uncontrolled manner, filling the steam

lines and suppressing the steam to all steam-driven equipment. This

increases the core damage probability because it results in the loss of all high

pressure systems.

20. Valve HPCI-MO-16 provides isolation of the HPCI system from the reactor

coolant system. The failure to isolate this valve, when required, would result

in reactor vessel level increasing in an uncontrolled manner, filling the steam

E2-5

Enclosure 2

lines and suppressing the steam to all steam-driven equipment. This

increases the core damage probability because it results in the loss of all high

pressure systems.

21. Valve RHR-MO-67 provides isolation of the RHR system from radwaste.

Post-fire instructions affecting this valve are to assist in placing shutdown

cooling in service. Failure of this valve would delay placing shutdown cooling

in service and act as a distraction to operators placing the plant in a safe

shutdown condition.

22. The exposure time used for evaluating this finding should be determined in

accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2,

Site Specific Risk-Informed Inspection Notebook Usage Rules. Given that

the performance deficiency was known to have existed for many years, the

analyst used the 1-year of the current assessment cycle as the exposure

period.

23. Based on fire damage and/or procedures, equipment affected by a postulated

fire in a given fire zone is unavailable for use as safe shutdown equipment.

24. The performance deficiency would have resulted in each of the demanded

valves failing to respond following a postulated fire.

25. In accordance with the requirements of Procedure 5.4POST-FIRE, operators

would perform the post-fire actions directed by the procedure following a fire

in an applicable fire zone. Therefore, the size and duration of the fire would

not be relevant to the failures caused by the performance deficiency.

26. Given Assumption 25, severity factors and probabilities of non-

suppression were not addressed for postulated fires that did not result in

main control room evacuation.

Postulated Fires Not Involving Main Control Room Evacuation:

The senior reactor analyst used the SPAR model for Cooper Nuclear Station to estimate

the change in risk, associated with fires in each of the associated fire scenarios (Table 1,

Items 1 - 41) that was caused by the finding. Average unavailability for test and

maintenance of modeled equipment was assumed, and a cutset truncation of

1.0 x 10-13 was used. For each fire zone, the analyst calculated a baseline conditional

core damage probability consistent with Assumptions 9, 10, 25 and 26.

For areas where the postulated fire resulted in a reactor scram, the frequency of the

transient initiator, IE-TRANS, was set to 1.0. All other initiators were set to the house

event FALSE, indicating that these events would not occur at the same time as a

reactor scram. Likewise, for Fire Area RB-K, the frequency of the loss-of-offsite power

initiator, IE-LOOP, was set to 1.0 while other initiators were set to the house event

FALSE.

E2-6

Enclosure 2

With input from the detailed IPEEE notebooks, maintained by the licensee, the analyst

was able to better assess the fire damage in each zone. This resulted in a more realistic

evaluation of the baseline fire risk for the zone, and lowering the change in risk for each

example.

Consistent with guidance in the Reactor Accident Sequence Precursor Handbook,

including NRC document, "Common-Cause Failure Analysis in Event Assessment,

(June 2007)," the baseline established for the fire zone, and Assumptions 22 through 26,

the analyst modeled the resulting condition following a postulated fire in each fire zone

by adjusting the appropriate basic events in the SPAR model. Both the baseline and

conditional values for each fire zone are documented in Table 1.

As shown in Table 1, the analyst calculated a change in core damage frequency (CDF)

associated with these 41 fire scenarios of 2.9 x 10-6/yr.

The analyst evaluated the licensees qualitative reviews of the 13 fire scenarios that

were impacted by the failure of the HPCI turbine to trip. In these scenarios, HPCI floods

the steam lines and prevents further injection by either HPCI or reactor core isolation

cooling system. Qualitatively, not all fires will grow to a size that causes a loss of the trip

function due to spatial separation. Additionally, not all unsuppressed fires would cause a

failure of the HPCI trip function. Finally, no operator recovery was credited in these

evaluations.

Given that these qualitative factors would all tend to decrease the significance of the

finding, the analyst believed that the total change in risk would be significantly lower than

the 2.9 x 10-6/yr documented above. Based on analyst judgment and an assessment of

the evidence provided by the licensee, an occurrence factor of 0.1 was applied to

the13 fire scenarios. This resulted in a total CDF of 7.8 x 10-7/yr. Therefore, the

analyst determined that this value was the best estimate of the safety significance for

these 41 fire scenarios.

E2-7

Enclosure 2

Table 1

Postulated Fires Not Involving Main Control Room Evacuation

Fire Area/

Shutdown

Strategy

Area/

Zone

Scenario

Number

Scenario

Description

Ignition

Frequency

Base

CCDP

Case

CCDP

Estimated

delta-CDF

Contribution

Function Affected

1C

1

RHR A

Pump Room

2.94E-03

8.82E-07

8.15E-05

2.37E-07

2

MCC K

3.02E-03

2.76E-05

1.28E-04

3.03E-07

3

MCC Q

3.93E-03

2.76E-05

1.28E-04

3.95E-07

4

MCC R

3.43E-03

2.76E-05

1.28E-04

3.44E-07

5

MCC RB

1.62E-03

1.12E-03

1.21E-03

1.46E-07

6

MCC S

2.23E-03

1.12E-03

1.21E-03

2.01E-07

7

MCC Y

3.83E-03

1.12E-03

1.21E-03

3.45E-07

8

Panel AA3

9.98E-04

2.76E-05

1.28E-04

1.00E-07

9

Panel BB3

9.98E-04

1.12E-03

1.21E-03

8.98E-08

10

RCIC Starter

Rack

1.32E-03

5.27E-06

8.27E-05

1.02E-07

11

250V Div 1

Rack

5.10E-04

2.76E-05

1.28E-04

5.12E-08

12

250V Div 2

Rack

2.09E-04

1.12E-03

1.21E-03

1.88E-08

RB-CF

2A/2C

13

ASD Panels

3.02E-04

1.12E-03

1.21E-03

2.72E-08

Shut HPCI-MO-14,

HPCI-MO-16,

RHR-MO-921,

RWCU-MO-18 and

MS-MO-77

7A

14

6.74E-03

7.64E-04

7.64E-04

0.00E+00

7B

15

1.36E-03

2.61E-06

2.61E-06

0.00E+00

8C

16

RPS Room

1A

4.15E-03

1.75E-07

1.75E-07

0.00E+00

8D

17

2.42E-03

3.57E-04

3.58E-04

4.84E-10

CB-A

10B

18

Hallway

(used CB

corridor)

1.09E-02

2.05E-05

2.85E-05

8.74E-08

Open RHR-MO-25B

and RHR-MO-67

E2-8

Enclosure 2

8H

19

DC

Switchgear

Room 1A

4.27E-03

3.49E-04

3.49E-04

1.28E-09

CB-A-1

8E

20

Battery

Room 1A

2.25E-03

8.74E-06

1.03E-05

3.51E-09

Open RHR-MO-17,

RHR-MO-25B, and

RHR-MO-67

8G

21

DC

Switchgear

Room 1B

4.27E-03

1.82E-03

1.83E-03

3.42E-08

CB-B

8F

22

Battery

Room 1B

2.25E-03

4.81E-06

5.73E-06

2.07E-09

Open RHR-MO-25A

8B

23

4.15E-03

1.75E-07

1.77E-07

5.81E-12

CB-C

8C

24

RPS Room

1A

4.15E-03

1.75E-07

1.77E-07

5.81E-12

Open RHR-MO-17,

RHR-MO-25A, and

RHR-MO-67

RB-DI (SW)

2D

25

RHR Heat

Exchanger

Room B

6.70E-04

8.66E-05

8.68E-05

1.27E-10

Shut HPCI-MO-14

and RR-MO-53A.

RB-DI (SE)

1D/1E

26

RHR B/HPCI

Pump Room

4.28E-03

6.48E-05

1.44E-04

3.37E-07

Shut HPCI-MO-14

and RR-MO-53A.

RB-J

3A

27

Switchgear

Room 1F

3.71E-03

5.28E-05

5.28E-05

0.00E+00

Open RHR-MO-17,

RHR-MO-25B, and

RHR-MO-67

RB-K

3B

28

Switchgear

Room 1G

3.71E-03

1.77E-02

1.77E-02

0.00E+00

Open RHR-MO-25A

3C/3D

/3E

29

RB Elevation

932

1.13E-02

7.06E-06

8.99E-06

2.18E-08

RB-M

2B

30

RHR Hx

Rm A

6.70E-04

7.06E-06

8.99E-06

1.29E-09

Open RHR-MO-17

and RHR-MO-25B

E2-9

Enclosure 2

3C/3D

/3E

31

Reactor

Building

Elevation

932

1.13E-02

1.22E-05

1.38E-05

1.81E-08

RB-N

2D

32

RHR Heat

Exchanger

Room B

6.70E-04

1.22E-05

1.38E-05

1.07E-09

Open RHR-MO-25A

11D

33

Condenser

Pit Area

3.10E-03

4.83E-06

6.20E-06

4.25E-09

11E

34

Reactor

Feedwater

Pump Area

6.25E-03

4.83E-06

6.20E-06

8.56E-09

11L

35

Pipe Chase

6.70E-04

4.83E-06

6.20E-06

9.18E-10

12C

36

Condenser

and Heater

Bay Area

3.27E-03

4.83E-06

6.20E-06

4.48E-09

12D

37

TB Floor 903

3.45E-03

4.83E-06

6.20E-06

4.73E-09

13A

38

Turbine

Operating

Floor

5.76E-03

4.83E-06

6.20E-06

7.89E-09

13B

39

Non-critical

Switchgear

Room

3.79E-03

4.83E-06

6.20E-06

5.19E-09

13C

40

Electric Shop

8.56E-04

4.83E-06

6.20E-06

1.17E-09

TB-A

13D

41

I&C Shop

8.90E-04

4.83E-06

6.20E-06

1.22E-09

Open RHR-MO-17,

RHR-MO-25A, and

RHR-MO-67

Total Estimated CDF for 41 Postulated Fire Scenarios:

2.91E-06

Enclosure 2

E2-10

Post-Fire Remote Shutdown Calculations:

As documented in Assumptions 4, 5, and 6, the analyst created a linked event tree

model, using the Systems Analysis Programs for Hand-on Integrated Reliability

Evaluation (SAPHIRE) software provided by the Idaho National Laboratory, to evaluate

the risks related to fire-induced main control room abandonment at the Cooper Nuclear

Station. This linked event tree was used to evaluate the increased risk from the subject

performance deficiency during the response to postulated fires in the main control room,

the auxiliary relay room, the cable spreading room, the cable expansion room or Fire

Area RB-FN. The primary event tree used in this model is displayed as Figure 1 in the

Attachment.

As documented in Assumption 5, the analyst used an event tree to evaluate the

likelihood of operator recovery via either restoration of HPCI or manually opening

Valve RHR-MO-25B. The resulting non-recovery probability was 7.9 x 10-2.

Using the linked event tree model described in Assumption 4, the analyst calculated the

CDF to be 7.3 x 10-6/yr. The dominant cutsets are shown below in Table 2.

Table 2

Main Control Room Abandonment Cutsets

Postulated Fire

Sequence

Mitigating Functions

Results

Auxiliary Relay Room

4-01-03

Failure to Reestablish HPCI

Failure to Open MO-25B

1.7 x 10-6/yr

Main Control Room

3-01-03

Failure to Reestablish HPCI

Failure to Open MO-25B

4.5 x 10-7/yr

Auxiliary Relay Room

4-01-12

Early HPCI Failure

Failure to Open MO-25B

4.1 x 10-7/yr

Auxiliary Relay Room

4-01-12

HPCI Out of Service

Failure to Open MO-25B

2.7 x 10-7/yr

Main Control Room

4-01-12

Early HPCI Failure

Failure to Open MO-25B

1.1 x 10-7/yr

Control Room Abandonment Frequency

NUREG/CR-2258, Fire Risk Analysis for Nuclear Power Plants, provides that control

room evacuation would be required because of thick smoke if a fire went unsuppressed

for 20 minutes. Given Assumption 6 and assuming that a fire takes 2 minutes to be

detected by automatic detection and/or by the operators, there are 18 minutes remaining

in which to suppress the fire prior to main control room evacuation being required. NRC

Inspection Manual Chapter 0609, Appendix F, Table 2.7.1, Non-suppression Probability

Values for Manual Fire Fighting Based on Fire Duration (Time to Damage after

Detection) and Fire Type Category, provides a manual non-suppression probability

(PNS) for the control room of 1.3 x 10-2 given 18 minutes from time of detection until time

of equipment damage. This is a reasonable approach, although fire modeling performed

by the licensee indicated that 16 minutes was the expected time to abandon the main

control room based on habitability.

Enclosure 2

E2-11

In accordance with Inspection Manual Chapter 0609, Appendix F, Task 2.3.2, the

analyst used a severity factor of 0.1 for determining the probability that a postulated fire

would be self sustaining and grow to a size that could affect plant equipment.

Given these values, the analyst calculated the main control room evacuation frequency

for fires in the main control room (FEVAC) as follows:

FEVAC = PFIF * SF * PNS

= 6.88 x 10-3/yr * 0.1 * 1.3 x 10-2

= 8.94 x 10-6/yr

In accordance with Procedure 5.4FIRE-S/D, operators are directed to evacuate the main

control room and conduct a remote shutdown, if a fire in the main control room or any of

the four areas documented in Assumption 8, if plant equipment spuriously actuates/de-

energizes equipment, or if instrumentation becomes unreliable. Therefore, for all

scenarios except a postulated fire in the main control room, the probability of non-

suppression by automatic or manual means are documented in Table 3, below.

Table 3

Control Room Abandonment Frequency

Fire Area

Ignition

Frequency

(per year)

Severity

Automatic

Suppression

Manual

Suppression

Abandonment

Frequency

(per year)

Main Control

Room

6.88 x 10-3

0.1

none

1.3 x 10-2

8.94 x 10-6

Auxiliary Relay

Room

1.42 x 10-3

0.1

none

0.24

3.41 x 10-5

Cable Expansion

Room

1.69 x 10-4

0.1

2 x 10-2

0.24

8.11 x 10-8

Cable Spreading

Room

4.27 x 10-3

0.1

5 x 10-2

0.24

5.12 x 10-6

Reactor Building

903 (RB-FN)

1.43 x 10-3

0.1

2 x 10-2

0.24

6.86 x 10-7

Total MCR Abandonment:

4.89 x 10-5

Enclosure 2

E2-12

The licensees total control room abandonment frequency was 1.75 x 10-5. For the main

control room fire, the licensees calculations were more in-depth than the analysts. The

remaining fire areas were assessed by the licensee using IPEEE data. However, the

following issues were noted with the licensees assessment:

Kitchen fires were not included in licensees evaluation

This would tend to increase the ignition frequency

This might add more heat input than the electrical cabinet fires

modeled by the licensee

Habitability Forced Abandonment

Non-suppression probability did not account for fire brigade

response time or the expected time to damage.

Reduced risk based on 3 specific cabinets causing a loss of

ventilation early, when it should have increased the risk. Fire

modeling showed that fires in these cabinets could damage

nearby cables and cause ventilation damper(s) to close.

Risk Assessment Calculation ES-91 uses an abandonment value

of 9.93 x 10-7. However, the supporting calculation performed by

EPM used 3.02 x 10-6.

Equipment Failure Control Room Abandonment

Criteria for leaving the control room did not accurately reflect the

guidance that was proceduralized.

The evaluation of the Cable Expansion Room stated that the only

fire source was self-ignition of cables. This was modeled as a hot

work fire, and it included a probability that administrative controls

for hot work and fire watches would prevent such fires from getting

large enough to require control room abandonment. This is

inappropriate for self-ignition of cables, since there would not

really be any fire watch present. Adjusting for this would increase

the risk in this area by two orders of magnitude.

The licensee concluded that fires in equipment in the four

alternate shutdown fire areas outside the main control room (see

Assumption 8) would not result in control room abandonment

without providing a technical basis. The licensees Appendix R

analysis concluded that fire damage in these rooms require main

control room evacuation to prevent core damage.

Enclosure 2

E2-13

The analyst used the main control room abandonment frequencies documented in

Table 3. In addition, sensitivities were run using the licensees values.

Recovery Following Failure of Valve RHR-MO-25B

As documented in Assumption 5, the analyst calculated a combined non-recovery

probability using the event tree shown in Figure 2 in the Attachment.

Table 4 documents the final split fractions used in quantifying this event tree.

Using the event tree in Figure 2 and the split fractions in Table 4, the analyst calculated

a combined non-recovery probability of 7.9 x 10-2. The licensees combined non-

recovery probability was 4.0 x 10-3. The licensee used a similar approach to quantify this

value. However, the licensee assumed that operators would always shut the safety-

relief valves upon determining that reactor pressure vessel water level was decreasing.

The analyst assumed that some percentage of operators would continue to follow the

procedure and attempt to recover from the failed RHR valve or try alternate methods of

low-pressure injection. In addition, the analyst identified the following issues that

impacted the licensees analysis:

The inspectors determined that it would require 112 ft-lbs of force to manually

open Valve RHR-MO-25B. The analyst determined that this affected the

ergonomics of this recovery. Some operators may assume that the valve is on

the backseat when large forces are required to open it. Some operators might

be incapable of applying this force to a 2-foot diameter hand wheel.

The analyst noted that the following valves would be potential reasons for lack

of injection flow and/or may distract operators from diagnosis that

Valve RHR-MO-025B is closed:

RHR-81B, RHR Loop B Injection Shutoff Valve, could be closed.

RHR-27CV, RHR Loop B Injection Line Testable Check Valve,

could be stuck closed.

Table 4

Split Fractions for RECOVERY-PATH

Top Event

How Assessed

Failure Probability

LEVEL-DOWN

SPAR-H (Diagnosis Only)

1.0 x 10-3

SRV-STATUS

Best Estimate of Fraction

1.0 x 10-1

CLOSE-SRVS

SPAR-H (Action Only)

5.0 x 10-4

RESTORE-HPCI

SPAR-H (Combined)

5.1 x 10-3

OPEN-MO-25B-3

SPAR-H (Combined)

5.0 x 10-1

OPEN-MO-25B-5/7

SPAR-H (Combined)

5.5 x 10-2

Enclosure 2

E2-14

RHR-MO-274B, Injection Line Testable Check Valve Bypass

Valve, could be opened as an alternative.

Operators could search for an alternate flow path.

The licensees evaluation did not include sequences involving the failure of the

HPCI system shortly after main control room evacuation in their risk evaluation.

These sequences represented approximately 26 percent of the CDF as

calculated by the analyst. These sequences are important for the following

reasons:

Failure of HPCI leads to the need for operators to rapidly

depressurize the reactor to establish alternate shutdown cooling.

Decay heat will be much higher than for sequences involving early

HPCI success. Also, depressurization under high decay heat and

high temperature result in greater water mass loss. This will

significantly reduce the time available for recovery actions.

HPCI success sequences provide long time frames available with

HPCI operating. This reduces decay heat, increases time for

recovery, and permits the establishment of an emergency

response organization. Those factors are not applicable to early

HPCI failure sequences.

The basis for operating HPCI was not well documented by the licensee. During

many of the extended sequences, suppression pool temperature went well

above the operating limits for HPCI cooling and remained high for extended

periods of time. The following facts were determined through inspection:

The design temperature for operating HPCI is 140°F based on

process flow providing oil cooling.

General Electric provided a transient operating temperature of

170°F for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

In the licensees best case evaluation of the performance

deficiency, the suppression pool would remain above 150°F for

10.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

The licensee used a case-specific combined recovery in assessing the risk of

this performance deficiency. Most of the recoveries discussed by the licensee

would have been available with or without the performance deficiency.

Therefore, these should be in the baseline model and portions of the

sequences subtracted from the case evaluation. This is the approach used by

the analyst in the linked event trees model.

Enclosure 2

E2-15

The licensee stated during the regulatory conference that credit should

be given for diesel-driven fire water pump injection. This is one of the

licensees alternate strategies. However, the inspectors determined, and the

licensee concurred, that this alternate method of injection requires that

Valve RHR-MO-25B be open. Therefore, no credit was given for this alternate

strategy.

Conclusions:

The analyst concluded that the subject performance deficiency was of low to moderate

significance (White). As documented in Table 1, for a period of exposure of 1 year, the analyst

determined a best estimate CDF for fire scenarios that did not require evacuation of the main

control room of 7.8 x 10-7 using both quantitative and qualitative techniques. Additionally, using

the linked event tree model described in Assumption 4, for a period of exposure of 1 year, the

analyst calculated the CDF to be 7.3 x 10-6 for postulated fires leading to the abandonment of

the main control room. This resulted in a total best estimate CDF of 8.1 x 10-6.

Y

0

Y

~

Y

C

I

Y

Y

~

0

0

0

0

0

0

0

--________

n

0

-

T-

T

m

J

T

Y

0 -

0

T-

x

n

n

n

n

0

0

0

0

0

2

J

m

?

I

I

m

?

Figure 1

A-1

Attachment

cn

W k 2

'? n

z

W

0

c-'

m 9

0

Z

W

7

8

a

W

U

cn

W !I

T

P

cn

>

U

W

cn

0

'?

I?

Y

Y

n

0

0

0

Y

n

0

0

d-

In

I

I

Y

0

n

0

n

0

al

Figure 2

A-2

Attachment

Enclosure 3

E3-1

SUPPLEMENTAL INFORMATION

Summary of Findings

IR 05000298/2008008; 03/19/08 - 06/13/08; Cooper Nuclear Station: Triennial Fire Protection

Follow-up Inspection

The report covered a 3-month period of inspection follow-up and significance determination

efforts by region-based inspectors and a senior risk analyst. One finding with an associated

violation was determined to have White safety significance. The significance of most findings is

indicated by its color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609,

"Significance Determination Process." Findings for which the significance determination

process does not apply may be green or be assigned a severity level after NRC management

review. The NRC's program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July

2000.

A.

NRC-Identified and Self-Revealing Findings

White. A violation of 10 CFR Part 50, Appendix B, Criterion V, was identified for failure

to ensure that some steps contained in emergency procedures at Cooper Nuclear

Station would work as written. Inspectors identified that steps in Emergency

Procedures 5.4POST-FIRE, Post-Fire Operational Information, and 5.4FIRE-S/D, Fire

Induced Shutdown From Outside Control Room, intended to reposition motor-operated

valves locally, would not have worked as written because the steps were not appropriate

for the configuration of the motor-starter circuits. This condition existed between 2004

and June, 2007. Appendix B to 10 CRF 50, Criterion V, was not met because these

quality-related procedures would not work to allow operators to bring the plant to a safe

shutdown condition in the event of certain fires. This finding had a cross-cutting aspect

in Problem Identification and Resolution, under the Corrective Action Program attribute,

because the licensee did not thoroughly evaluate the 2004 NRC violation to address

causes and extent of condition (P.1.c -Evaluations).

This finding is of greater than minor safety significance because it impacted the

Mitigating Systems cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. This finding affected both the procedure quality and protection against

external factors (fires) attributes of this cornerstone objective. This finding was

determined to have a White safety significance during a Phase 3 evaluation. The

scenarios of concern involve larger fires in specific areas of the plant which trigger

operators to implement fire response procedures to place the plant in a safe shutdown

condition. Since some of those actions could not be completed using the procedures as

written, this would challenge the operators ability to establish adequate core cooling.

Enclosure 3

E3-2

KEY POINTS OF CONTACT

Licensee

K. Billesbach, Quality Assurance Manager

M. Colomb, General Manager of Plant Operations

J. Flaherty, Senior Staff Licensing Engineer

P. Fleming, Director of Nuclear Safety Assurance

V. Furr, Risk Management Engineer

G. Kline, Director of Engineering

G. Mace, Nuclear Assessment Manager

S. Minahan, Vice-President-Nuclear and Chief Nuclear Officer

S. Nelson, Risk Management Engineer

T. Shudak, Fire Protection Program Engineer

R. Stephan, Risk Assessment Engineer

K. Sutton, Risk Management Supervisor

D. VanDerKamp, Licensing Supervisor

NRC

J. Bongara, Senior Human Factors Specialist, Office of New Reactors

M. Chambers, Resident Inspector

J. Circle, Senior Reliability and Risk Analyst, Office of Nuclear Reactor Regulation

N. Salgado, Chief, Operator Licensing and Human Performance Branch, Office of Nuclear

Reactor Regulation

N. Taylor, Senior Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Discussed 05000298/2008007-01

VIO

Two Inadequate Post-Fire Safe

Shutdown Procedures

Enclosure 3

E3-3

LIST OF DOCUMENTS REVIEWED

PROCEDURES

Number

Title

Revision

Administrative Procedure 0.1

Procedure Use and Adherence

31

Administrative Procedure 0.4A

Procedure Change Process

Supplement

various

Administrative Procedure 2.0.1.2

Operations Procedure Policy

27

Administrative Procedure 2.0.3

Conduct of Operations

58

Emergency Procedure 5.4 Fire

General Fire Procedure

14

Emergency Procedure 5.4 Post-Fire

Post-Fire Operational Information

12 & 13

Emergency Procedure 5.4 Fire-S/D

Fire Induced Shutdown From

Outside Control Room

14 & 15

SELF-ASSESSMENTS AND AUDITS

QA Audit 07-01

Fire Protection Program

02/2007

Self-assessment

Manual Action Feasibility - Review of Cooper

Nuclear Station Post-Fire Manual Actions With NRC

Inspection Manual Post-Fire Manual Action

Feasibility Criteria

05/18/07

Procedure Change

Request

Emergency Procedure 5.4 POST-FIRE, Post Fire

Operational Information

Revision 4

Alarm Response

Procedure 2.3_9-3-2,

Panel 9-3-2/D-1

HPCI Turbine Oil Cooler Temperature High

Revision 17

CONDITION REPORTS

2007-04155

2004-03034

2004-03081

2003-05433

Enclosure 3

E3-4

CALCULATIONS

Fauske Review of Cooper Nuclear Station Calculation NEDC 08-035, Suppression Pool Heat-

up Response for Appendix R Event with 24 Hour HPCI Operation.

Calculation NEDC 08-035, Suppression Pool Heat-up Response for Appendix R Event with

24 Hour HPCI Operation, Revision 0.

Calculation NEDC 08-041, Main Control Room Forced Abandonment Fire Scenario Analysis,

Revision 0.

EPM Calculation P1906-07-011b-001, Main Control Room Forced Abandonment Fire Scenario

Analysis,5/2008.

Calculation ES-091, Detailed PSA Study of Fire Protection Triennial Inspection, Revision 0.

Calculation NEDC 08-032, EPM Calculation 1906-07-06, Fire Ignition Frequencies, Revision 0.

MISCELLANEOUS

White paper discussion on SRV circuit operation from the alternate shutdown panel

dated 5/19/2008.

GE Service Information Letter 615, ADS/HPCI Functional Redundancy, dated 3/4/1998.

NUREG 2258, Fire Risk Analysis for Nuclear Power Plants.

NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities.

NPPD Letter NLS2008044, Additional Information for Consideration in Addressing Inspection

Finding, dated 5/8/2008.

Generic Letter 82-21, Technical Specifications for Fire Protection Audits.

NRC Inspection Report 05000317/2007009 and 05000318/2007009.

NRC Inspection Report 05000282/2006009 and 05000306/2006009.

NRC Inspection Report 05000261/2007007.

Additional documents reviewed as part of inspecting this finding are documented in NRC

Inspection Report 05000298/2008007.