IR 05000133/2008003: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (3 intermediate revisions by the same user not shown) | |||
| Line 3: | Line 3: | ||
| issue date = 10/23/2008 | | issue date = 10/23/2008 | ||
| title = IR 05000133-08-003; Pacific Gas and Electric Company; 09/22-26/2008; Humboldt Bay Power Plant, NRC Inspection Report | | title = IR 05000133-08-003; Pacific Gas and Electric Company; 09/22-26/2008; Humboldt Bay Power Plant, NRC Inspection Report | ||
| author name = Whitten J | | author name = Whitten J | ||
| author affiliation = NRC/RGN-IV/DNMS/NMSBB | | author affiliation = NRC/RGN-IV/DNMS/NMSBB | ||
| addressee name = Conway J | | addressee name = Conway J | ||
| addressee affiliation = Pacific Gas & Electric Co | | addressee affiliation = Pacific Gas & Electric Co | ||
| docket = 05000133 | | docket = 05000133 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:October 23, 2008 | ||
==SUBJECT:== | |||
NRC INSPECTION REPORT 050-00133/08-003 | |||
==Dear Mr. Conway:== | |||
A Nuclear Regulatory Commission (NRC) inspection was conducted on September 22-26, 2008, at your Humboldt Bay Power Plant, Unit 3 facility. This inspection was an examination of activities conducted under your license as they relate to safety and compliance of the Commissions rules and regulations and with the conditions of your license. Within these areas, the inspection included reviews of your organization, management, and cost controls; safety reviews, design changes, and modifications; spent fuel pool safety; maintenance and surveillances; decommissioning status; occupational radiation exposure; and radioactive waste treatment, effluent and environmental monitoring. On September 26, 2008, at the conclusion of the onsite inspection, an exit interview was conducted with Mr. Mark Smith, Engineering Manager, and other members of your staff. The enclosed report presents the scope and results of that inspection. The inspection determined that you were conducting decommissioning activities in compliance with regulatory and license requirements. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, if you choose to provide one, will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction. | |||
Should you have any questions concerning this inspection, please contact Mr. Emilio Garcia, Health Physicist, at (530) 756-3910, or the undersigned at (817) 860-8197. | |||
Sincerely, | |||
/RA/ | |||
Jack E. Whitten, Chief | |||
Nuclear Materials Safety Branch B | |||
Docket No.: 050-00133 License No.: DPR-7 UNITED STATES NUCLEAR REGULATORY COMM ISSION R E GI ON I V 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125 | |||
Mr. John Enclosure: | |||
NRC Inspection Report 050-00133/08-003 | |||
cc w/enclosure: | |||
Donna Jacobs, Vice President Nuclear Services Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424 | |||
Antonio Fernandez, Esq. | |||
PG&E P.O. Box 7442 San Francisco, CA 94120 | |||
Loren Sharp, Director and Nuclear Plant Manager Humboldt Bay Power Plant, PG&E 1000 King Salmon Avenue Eureka, CA 95505 | |||
Chairman Humboldt County Board of Supervisors County Courthouse 825 Fifth Street Eureka, CA 95501 | |||
Law Office of Linda J. Brown, Esq. | |||
300 Drakes Landing Road, Suite 172 Greenbrae, CA 94904 | |||
Regional Radiation Representative U. S. Environmental Protection Agency Region IX Office 75 Hawthorne Street San Francisco, CA 94105 | |||
Dr. Richard Ferguson, Energy Chair Sierra Club California 1100 11th Street, Suite 311 Sacramento, CA 95814 | |||
Dr. James F. Davis, State Geologist Department of Conservation Division of Mines & Geology 801 K Street MS 12-30 Sacramento, CA 95814-3531 | |||
Mr. John | |||
}} | }} | ||
Latest revision as of 14:39, 14 January 2025
| ML082970815 | |
| Person / Time | |
|---|---|
| Site: | Humboldt Bay |
| Issue date: | 10/23/2008 |
| From: | Whitten J NRC/RGN-IV/DNMS/NMSBB |
| To: | Conway J Pacific Gas & Electric Co |
| References | |
| IR-08-003 | |
| Download: ML082970815 (19) | |
Text
October 23, 2008
SUBJECT:
NRC INSPECTION REPORT 050-00133/08-003
Dear Mr. Conway:
A Nuclear Regulatory Commission (NRC) inspection was conducted on September 22-26, 2008, at your Humboldt Bay Power Plant, Unit 3 facility. This inspection was an examination of activities conducted under your license as they relate to safety and compliance of the Commissions rules and regulations and with the conditions of your license. Within these areas, the inspection included reviews of your organization, management, and cost controls; safety reviews, design changes, and modifications; spent fuel pool safety; maintenance and surveillances; decommissioning status; occupational radiation exposure; and radioactive waste treatment, effluent and environmental monitoring. On September 26, 2008, at the conclusion of the onsite inspection, an exit interview was conducted with Mr. Mark Smith, Engineering Manager, and other members of your staff. The enclosed report presents the scope and results of that inspection. The inspection determined that you were conducting decommissioning activities in compliance with regulatory and license requirements.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, if you choose to provide one, will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
Should you have any questions concerning this inspection, please contact Mr. Emilio Garcia, Health Physicist, at (530) 756-3910, or the undersigned at (817) 860-8197.
Sincerely,
/RA/
Jack E. Whitten, Chief
Nuclear Materials Safety Branch B
Docket No.: 050-00133 License No.: DPR-7 UNITED STATES NUCLEAR REGULATORY COMM ISSION R E GI ON I V 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125
Mr. John Enclosure:
NRC Inspection Report 050-00133/08-003
cc w/enclosure:
Donna Jacobs, Vice President Nuclear Services Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424
Antonio Fernandez, Esq.
PG&E P.O. Box 7442 San Francisco, CA 94120
Loren Sharp, Director and Nuclear Plant Manager Humboldt Bay Power Plant, PG&E 1000 King Salmon Avenue Eureka, CA 95505
Chairman Humboldt County Board of Supervisors County Courthouse 825 Fifth Street Eureka, CA 95501
Law Office of Linda J. Brown, Esq.
300 Drakes Landing Road, Suite 172 Greenbrae, CA 94904
Regional Radiation Representative U. S. Environmental Protection Agency Region IX Office 75 Hawthorne Street San Francisco, CA 94105
Dr. Richard Ferguson, Energy Chair Sierra Club California 1100 11th Street, Suite 311 Sacramento, CA 95814
Dr. James F. Davis, State Geologist Department of Conservation Division of Mines & Geology 801 K Street MS 12-30 Sacramento, CA 95814-3531
Mr. John