IR 05000237/2008009: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:December 1, 2008 | ||
==SUBJECT:== | ==SUBJECT:== | ||
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000237/2008009(DRS); | DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 | ||
TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000237/2008009(DRS); | |||
05000249/2008009(DRS) | 05000249/2008009(DRS) | ||
| Line 36: | Line 38: | ||
Sincerely, | Sincerely, | ||
/RA/ | /RA/ | ||
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Nonpublic Enclosure: Inspection Report 05000237/2008009(DRS); | |||
05000249/2008009(DRS) | Hironori Peterson, Chief Operations Branch Division of Reactor Safety | ||
w/Attachment: Supplemental Information cc w/encl: C. Symonds, Security Director, Dresden J. Klinger, State Liaison Officer, Illinois Emergency Management Agency cc w/o encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Chairman, Illinois Commerce Commission | |||
Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 | |||
Nonpublic Enclosure: Inspection Report 05000237/2008009(DRS); | |||
05000249/2008009(DRS) | |||
w/Attachment: Supplemental Information | |||
cc w/encl: | |||
C. Symonds, Security Director, Dresden | |||
J. Klinger, State Liaison Officer, | |||
Illinois Emergency Management Agency | |||
cc w/o encl: | |||
Site Vice President - Dresden Nuclear Power Station | |||
Plant Manager - Dresden Nuclear Power Station | |||
Regulatory Assurance Manager - Dresden Nuclear Power Station | |||
Chief Operating Officer and Senior Vice President | |||
Senior Vice President - Midwest Operations | |||
Senior Vice President - Operations Support | |||
Vice President - Licensing and Regulatory Affairs | |||
Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities | |||
Associate General Counsel | |||
Document Control Desk - Licensing | |||
Assistant Attorney General | |||
Chairman, Illinois Commerce Commission | |||
}} | }} | ||
Latest revision as of 14:05, 14 January 2025
| ML083400486 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 12/01/2008 |
| From: | Hironori Peterson Operations Branch I |
| To: | Pardee C AmerGen Energy Co, Exelon Nuclear |
| References | |
| IR-08-009 | |
| Download: ML083400486 (4) | |
Text
December 1, 2008
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3
TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000237/2008009(DRS);
Dear Mr. Pardee:
On October 24, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Dresden Nuclear Power Station, Units 2 and 3. The enclosed report documents the results of the inspection, which were discussed on October 24, 2008, with Mr. Hanley and other members of your staff.
The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.
Based on the results of the inspection, there were no NRC-identified findings.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Enclosures Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety
Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Nonpublic Enclosure: Inspection Report 05000237/2008009(DRS);
w/Attachment: Supplemental Information
cc w/encl:
C. Symonds, Security Director, Dresden
J. Klinger, State Liaison Officer,
Illinois Emergency Management Agency
cc w/o encl:
Site Vice President - Dresden Nuclear Power Station
Plant Manager - Dresden Nuclear Power Station
Regulatory Assurance Manager - Dresden Nuclear Power Station
Chief Operating Officer and Senior Vice President
Senior Vice President - Midwest Operations
Senior Vice President - Operations Support
Vice President - Licensing and Regulatory Affairs
Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities
Associate General Counsel
Document Control Desk - Licensing
Assistant Attorney General
Chairman, Illinois Commerce Commission