IR 07200068/2008001: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:December 19, 2008  
{{#Wiki_filter:December 19, 2008


Mr. Charles President and Chief Nuclear Officer (CNO), Exelon Nuclear Chief Nuclear Officer, AmerGen Energy Company, LLC 4300 Winfield Road
==SUBJECT:==
 
BYRON POWER STATION NRC INSPECTION REPORT NO. 072-00068/08-01(DNMS)
Warrenville, IL 60555
 
SUBJECT: BYRON POWER STATION NRC INSPECTION REPORT NO. 072-00068/08-01(DNMS)


==Dear Mr. Pardee:==
==Dear Mr. Pardee:==
Line 32: Line 29:
The enclosed report presents the results of this inspection.
The enclosed report presents the results of this inspection.


The inspection was an examination of the dry fuel storage pad construction activities as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. Specifically, the inspectors observed placement of structural fill, reinforcement, and concrete for the storage pad and HI-STORM 100 overpacks. The inspectors also performed an in-office review of calculations related to the storage pad. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of selected examinations of procedures and representative records, observations of activities, and interviews with personnel.
The inspection was an examination of the dry fuel storage pad construction activities as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. Specifically, the inspectors observed placement of structural fill, reinforcement, and concrete for the storage pad and HI-STORM 100 overpacks. The inspectors also performed an in-office review of calculations related to the storage pad. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of selected examinations of procedures and representative records, observations of activities, and interviews with personnel.


Based on the results of these inspections, the inspectors did not identify violations of NRC requirements. The storage pad construction activities were conducted in accordance with applicable regulations and license conditions.
Based on the results of these inspections, the inspectors did not identify violations of NRC requirements. The storage pad construction activities were conducted in accordance with applicable regulations and license conditions.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
 
and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRC's document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.


Sincerely,
Sincerely,
/RA by William G. Snell, acting for/
/RA by William G. Snell, acting for/  
Christine A. Lipa, Chief Materials Control, ISFSI and


Decommissioning Branch Docket Nos. 72-068; 050-454; 50-455
Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch  


License Nos. NPF-37; NPF-66  
Docket Nos. 72-068; 050-454; 50-455 License Nos. NPF-37; NPF-66  


===Enclosure:===
===Enclosure:===
Line 52: Line 46:


REGION III==
REGION III==
Docket No.
072-00068
License Nos.
NPF-37; NPF-66
Report No.
072-00068/08-01(DNMS)
Licensee:
Exelon
Facility:
Byron Power Station
Location:
4450 North German Church Road
Byron, IL 61010
Inspection Dates:
Onsite: May 21, 2008; June 26, 2008, August 5, 2008, August 27, 2008; and September 18, 2008.
In-office review completed on December 11, 2008
Exit Teleconference: December 11, 2008


Docket No. 072-00068
Inspectors:


License Nos. NPF-37; NPF-66
Sarah Bakhsh, Reactor Inspector


Report No. 072-00068/08-01(DNMS)
Bruce Bartlett, Senior Resident Inspector


Licensee: Exelon
Matthew Learn, Reactor Engineer in training


Facility: Byron Power Station
Approved by:
Christine A. Lipa, Chief


Location: 4450 North German Church Road Byron, IL 61010
Materials Control, ISFSI and Decommissioning Branch


Inspection Dates: Onsite: May 21, 2008; June 26, 2008, August 5, 2008, August 27, 2008; and September 18, 2008.
Division of Nuclear Materials Safety


In-office review completed on December 11, 2008 Exit Teleconference: December 11, 2008
Enclosure


Inspectors: Sarah Bakhsh, Reactor Inspector Bruce Bartlett, Senior Resident Inspector Matthew Learn, Reactor Engineer in training
EXECUTIVE SUMMARY Byron Power Station NRC Inspection Report 072-00068/08-01(DNMS)


Approved by: Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch Division of Nuclear Materials Safety Enclosure 2 EXECUTIVE SUMMARY Byron Power Station NRC Inspection Report 072-00068/08-01(DNMS)
The purpose of the inspection was to observe and evaluate the licensees activities associated with construction of a new Independent Spent Fuel Storage Installation (ISFSI) pad. During this inspection period, the inspectors also reviewed the design of the new pad to ensure compliance with the regulations and the design specifications.
The purpose of the inspection was to observe and evaluate the licensee's activities associated with construction of a new Independent Spent Fuel Storage Installation (ISFSI) pad. During this inspection period, the inspectors also reviewed the design of the new pad to ensure compliance with the regulations and the design specifications.


Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design  
Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design  
* The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.
* The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.
 
(Section 1.1)


(Section 1.1)
Independent Spent Fuel Storage Pad Construction  
Independent Spent Fuel Storage Pad Construction
* The licensees engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications and industry standards. (Section 2.1)  
* The licensee's engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications and industry standards. (Section 2.1)  
* The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI)
* The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensee's approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI)
07200068/2008001, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008002, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies. (Section 2.2)  
07200068/2008001, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008002, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies. (Section 2.2)  


Enclosure 3 Report Details 1.0 Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design (IP 60856)
Enclosure  
1.1 Site Characterization and Design of the ISFSI Pad


a. Inspection Scope The inspectors evaluated the licensee's soil and engineering design evaluations in preparation for a new dry cask storage pad to verify the licensee's compliance with the Certificate of Compliance (CoC), 10 CFR Part 72 requirements, and industry standards.
Report Details


b. Observations and Findings Soil Analysis
1.0 Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design (IP 60856)


A total of six borings were drilled within the general vicinity of the ISFSI facility to determine the site subsurface conditions. The inspectors reviewed the licensee's report and the soil boring test results. Based on the soil sample analysis, the subsurface soil profile for the ISFSI consists of approximately 4 inches of asphalt followed by 12 inches of granular subbase or 2 to 3 inches of organic topsoil. Both were underlain by dense to very dense silty sand with crushed gravel. Bedrock was approximately 3 to 6 feet (ft.)
1.1 Site Characterization and Design of the ISFSI Pad


below the existing grade, with the existing grade at approximately 873.6 ft. Rock cores were taken to depths ranging from 13 to 16 ft. There was no groundwater collected within the borings prior to the addition of water to facilitate rock coring. The groundwater surface varied, but was at approximately 840 ft. at the plant site and 740 ft. one mile northeast of the site. Groundwater was at approximately 60 ft. to 75 ft. below the area of
a.


the ISFSI.
Inspection Scope


Soil Liquefaction Analysis The boring logs performed by the licensee's contractor indicated the presence of dense to very dense soils as demonstrated by the high Standard Penetration Test blow counts.
The inspectors evaluated the licensees soil and engineering design evaluations in preparation for a new dry cask storage pad to verify the licensees compliance with the Certificate of Compliance (CoC), 10 CFR Part 72 requirements, and industry standards.
 
b.
 
Observations and Findings
 
Soil Analysis
 
A total of six borings were drilled within the general vicinity of the ISFSI facility to determine the site subsurface conditions. The inspectors reviewed the licensees report and the soil boring test results. Based on the soil sample analysis, the subsurface soil profile for the ISFSI consists of approximately 4 inches of asphalt followed by 12 inches of granular subbase or 2 to 3 inches of organic topsoil. Both were underlain by dense to very dense silty sand with crushed gravel. Bedrock was approximately 3 to 6 feet (ft.)
 
below the existing grade, with the existing grade at approximately 873.6 ft. Rock cores were taken to depths ranging from 13 to 16 ft. There was no groundwater collected within the borings prior to the addition of water to facilitate rock coring. The groundwater surface varied, but was at approximately 840 ft. at the plant site and 740 ft. one mile northeast of the site. Groundwater was at approximately 60 ft. to 75 ft. below the area of the ISFSI.
 
Soil Liquefaction Analysis  
 
The boring logs performed by the licensees contractor indicated the presence of dense to very dense soils as demonstrated by the high Standard Penetration Test blow counts.


High blow counts are indicative of high resistance to liquefaction. In addition, at approximately 3 feet below grade, the soil strata was limestone rock which is not susceptible to liquefaction.
High blow counts are indicative of high resistance to liquefaction. In addition, at approximately 3 feet below grade, the soil strata was limestone rock which is not susceptible to liquefaction.
Line 104: Line 144:
To address any frost heave concerns during cold weather, the licensee placed a frost free granular material under the pad.
To address any frost heave concerns during cold weather, the licensee placed a frost free granular material under the pad.


Enclosure 4 c. Conclusion The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.
Enclosure  
 
c.
 
Conclusion  


2.0 Independent Spent Fuel Storage Pad Construction (IP 60853)
The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.


2.1 Excavation and Soil Compaction Activities
2.0 Independent Spent Fuel Storage Pad Construction (IP 60853)


a. Inspection Scope
2.1 Excavation and Soil Compaction Activities


The inspectors evaluated the licensee's site characterization, and observed soil compaction activities for the new dry cask storage pad to verify the licensee's compliance with its specifications, design drawings, and industry standards.
a.


b. Observations and Findings The licensee constructed a reinforced concrete ISFSI storage pad to the south of the plant. The ISFSI pad was designed to hold 96 dry fuel storage casks. The licensee excavated 3 feet of soil, ensuring removal of topsoil, organic, and all undesirable material until bedrock was reached. There was a lot of hard rock identified at very shallow depths and in order to ensure the required 3 ft. of engineered fill be placed, the licensee raised the final elevation of the top of the pad by 1 ft. 6 inches to approximately 875 ft.
Inspection Scope
 
The inspectors evaluated the licensees site characterization, and observed soil compaction activities for the new dry cask storage pad to verify the licensees compliance with its specifications, design drawings, and industry standards.
 
b.
 
Observations and Findings  
 
The licensee constructed a reinforced concrete ISFSI storage pad to the south of the plant. The ISFSI pad was designed to hold 96 dry fuel storage casks. The licensee excavated 3 feet of soil, ensuring removal of topsoil, organic, and all undesirable material until bedrock was reached. There was a lot of hard rock identified at very shallow depths and in order to ensure the required 3 ft. of engineered fill be placed, the licensee raised the final elevation of the top of the pad by 1 ft. 6 inches to approximately 875 ft.


Rolling of the underlying in-situ material ensured that a suitable subgrade existed under the pad area. Following receipt of satisfactory compaction results for the subgrade, the licensee backfilled the area with 3 ft. of non-frost susceptible granular base material (gravel/sand) and compacted the fill to a minimum of 95 percent of the maximum dry density as indicated in American Society for Testing and Materials (ASTM) D 1557. The inspectors observed the licensee place and compact the fill in layers of six inches.
Rolling of the underlying in-situ material ensured that a suitable subgrade existed under the pad area. Following receipt of satisfactory compaction results for the subgrade, the licensee backfilled the area with 3 ft. of non-frost susceptible granular base material (gravel/sand) and compacted the fill to a minimum of 95 percent of the maximum dry density as indicated in American Society for Testing and Materials (ASTM) D 1557. The inspectors observed the licensee place and compact the fill in layers of six inches.


The inspectors observed certified personnel perform field tests using a moisture density gauge to verify that each individual lift met the minimum compaction, maximum dry density and moisture content as specified in technical specifications and established during laboratory tests. The licensee's contractor obtained this data by performing field tests which included wet and dry density, moisture content, and lift thickness in accordance with the appropriate ASTM standards.
The inspectors observed certified personnel perform field tests using a moisture density gauge to verify that each individual lift met the minimum compaction, maximum dry density and moisture content as specified in technical specifications and established during laboratory tests. The licensees contractor obtained this data by performing field tests which included wet and dry density, moisture content, and lift thickness in accordance with the appropriate ASTM standards.


The licensee performed soil plate load tests for the engineered fill to determine the value of the Young's Modulus. This parameter measured the stiffness of the material and was calculated using field tests. There is both a lower and upper limit required to ensure the pad's structural qualifications are met. The lower limit of the Young's Modulus was the minimum required for the strength of the pad while the upper limit was to ensure that the deceleration values of the fuel assemblies do not exceed design requirements during a non-mechanistic tipover of the cask.
The licensee performed soil plate load tests for the engineered fill to determine the value of the Youngs Modulus. This parameter measured the stiffness of the material and was calculated using field tests. There is both a lower and upper limit required to ensure the pads structural qualifications are met. The lower limit of the Youngs Modulus was the minimum required for the strength of the pad while the upper limit was to ensure that the deceleration values of the fuel assemblies do not exceed design requirements during a non-mechanistic tipover of the cask.


Enclosure 5 The licensee committed to follow the ASTM D1194 standards in its Civil Construction Specification and Engineering Change package for the plate load tests which required the use of at least three test locations. However, the specification contradicted this by stating that "at least one Soil Plate Load Test shall be performed near the center of the pad location." The inspectors highlighted this discrepancy to the licensee. The licensee used three test locations and revised the specification to state "at least one Soil Plate Load Test shall be performed for the installation of each section of the ISFSI pad."
Enclosure  


The licensee and the designer of the proposed pad (Holtec) indicated that although they did plan to use three test locations, they were not required to do so because the standard was to be used as a guidance document. The inspectors explained the need for the licensee to emphasize adherence to codes and standards and the inspectors'
The licensee committed to follow the ASTM D1194 standards in its Civil Construction Specification and Engineering Change package for the plate load tests which required the use of at least three test locations. However, the specification contradicted this by stating that at least one Soil Plate Load Test shall be performed near the center of the pad location. The inspectors highlighted this discrepancy to the licensee. The licensee used three test locations and revised the specification to state at least one Soil Plate Load Test shall be performed for the installation of each section of the ISFSI pad.
understanding that there needs to be full compliance to documents that the licensee committed to in their design documents. The licensee modified its documents to better reflect their intent to use the standards as guidance documents. Discrepancies would be submitted to Owner's Engineering for evaluat ion and to obtain acceptance from Holtec prior to proceeding with construction.


The results for the three tests were forwarded to Holtec to determine the Young's modulus. The initial test results were outside the 7.5 kips per square inch (ksi) to 15 ksi range specified in the design documents. Since there is hard rock at very shallow depths and only 3 ft. of backfill, Holtec recommended changing the plate size used in the test from a 2x2 to a 1x1. Changing the plate size ensured that the data was representative of the engineered fill without significant contribution from the in-situ rock beneath the fill. The values for the Young's modulus were then within the specified range for the three test locations.
The licensee and the designer of the proposed pad (Holtec) indicated that although they did plan to use three test locations, they were not required to do so because the standard was to be used as a guidance document. The inspectors explained the need for the licensee to emphasize adherence to codes and standards and the inspectors understanding that there needs to be full compliance to documents that the licensee committed to in their design documents. The licensee modified its documents to better reflect their intent to use the standards as guidance documents. Discrepancies would be submitted to Owners Engineering for evaluation and to obtain acceptance from Holtec prior to proceeding with construction.


c. Conclusion The licensee's engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications
The results for the three tests were forwarded to Holtec to determine the Youngs modulus. The initial test results were outside the 7.5 kips per square inch (ksi) to 15 ksi range specified in the design documents. Since there is hard rock at very shallow depths and only 3 ft. of backfill, Holtec recommended changing the plate size used in the test from a 2x2 to a 1x1. Changing the plate size ensured that the data was representative of the engineered fill without significant contribution from the in-situ rock beneath the fill. The values for the Youngs modulus were then within the specified range for the three test locations.


and industry standards.
c.


2.2 Pad Construction Activities a. Inspection Scope
Conclusion


The inspectors evaluated whether construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensee's approved Engineering Change package, design drawings, Work Orders, and applicable industry standards. The inspectors also reviewed select material, and batch plant tickets.
The licensees engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications and industry standards.


b. Observations and Findings
2.2 Pad Construction Activities


The inspectors reviewed an approved Engineering Change package which provided specifications for the pad construction activities. The storage pad was designed to be a 198 ft. long, 116 ft. wide, and 2 ft. thick reinforced concrete slab. The storage pad was supported by a 6 inch thick concrete mat foundation set on top of 3 ft. of dense graded
a.


aggregate.
Inspection Scope


Enclosure 6 Placement of Reinforcing Steel
The inspectors evaluated whether construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Work Orders, and applicable industry standards.
 
The inspectors also reviewed select material, and batch plant tickets.
 
b.
 
Observations and Findings
 
The inspectors reviewed an approved Engineering Change package which provided specifications for the pad construction activities. The storage pad was designed to be a 198 ft. long, 116 ft. wide, and 2 ft. thick reinforced concrete slab. The storage pad was supported by a 6 inch thick concrete mat foundation set on top of 3 ft. of dense graded aggregate.
 
Enclosure  
 
Placement of Reinforcing Steel  


After placement and satisfactory compaction of the engineered fill, the licensee installed forms and placed reinforcement bars (rebar). The reinforced concrete was designed for a nominal compressive strength between 3,000 pounds per square inch (psi) and 4,200 psi at 28 days and the rebar conformed to ASTM A615 Grade 60 steel.
After placement and satisfactory compaction of the engineered fill, the licensee installed forms and placed reinforcement bars (rebar). The reinforced concrete was designed for a nominal compressive strength between 3,000 pounds per square inch (psi) and 4,200 psi at 28 days and the rebar conformed to ASTM A615 Grade 60 steel.


After placing the rebar and securing the forms, the licensee performed an inspection of the first third of the proposed pad prior to concrete placement. The inspectors reviewed the design drawings and performed an independent walk down of the proposed first third of the pad. The pad area was free of debris and excessive moisture. The rebar was placed in two upper and lower layers joined by U-shaped bars. The licensee placed the correct size of rebar. The inspectors measured the spacing between the rebar and identified some instances where the spacing was outside the allowed tolerance specified in the design drawing. The inspectors also identified instances in which the requirements for the concrete cover between the rebar and the forms as well as the top and bottom of the pad differed from design drawings. Thus a number of field changes were performed to address the existing field conditions which deviated from the prescribed drawings. Where it was not practical, the licensee obtained justification from Holtec to leave the rebar in the as built condition as documented in Holtec's September 2, 2008, letter to the licensee. The licensee entered this into its corrective action program as Action Request (AR) Report 00812028. The licensee will address these discrepancies in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements.
After placing the rebar and securing the forms, the licensee performed an inspection of the first third of the proposed pad prior to concrete placement. The inspectors reviewed the design drawings and performed an independent walk down of the proposed first third of the pad. The pad area was free of debris and excessive moisture. The rebar was placed in two upper and lower layers joined by U-shaped bars. The licensee placed the correct size of rebar. The inspectors measured the spacing between the rebar and identified some instances where the spacing was outside the allowed tolerance specified in the design drawing. The inspectors also identified instances in which the requirements for the concrete cover between the rebar and the forms as well as the top and bottom of the pad differed from design drawings. Thus a number of field changes were performed to address the existing field conditions which deviated from the prescribed drawings. Where it was not practical, the licensee obtained justification from Holtec to leave the rebar in the as built condition as documented in Holtecs September 2, 2008, letter to the licensee. The licensee entered this into its corrective action program as Action Request (AR) Report 00812028. The licensee will address these discrepancies in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements.


This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar  
This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar Discrepancies.


Discrepancies.
Placement of Concrete for Storage Pad


Placement of Concrete for Storage Pad The storage pad was designed in accordance with American Concrete Institute (ACI)
The storage pad was designed in accordance with American Concrete Institute (ACI)
318 and constructed in accordance with ACI 301. The inspectors observed concrete placement for the second third of the main storage pad. The licensee deposited concrete in this section in one continuous placement. The licensee checked the batch tickets for every truck to confirm that each concrete batch was mixed as specified in the mix design and the mixing time and number of drum revolutions satisfied code requirements to ensure the concrete was suitable for placement. The inspectors observed that the concrete was transported by conveyor belt and deposited in the areas of placement as indicated by the forms. The inspectors noted that the contractor staff maintained careful control of the discharge hose and ensured that concrete had an unrestricted vertical drop to the point of placement to prevent segregation of the aggregate. The contractor used a systematic pattern of vibration to ensure proper consolidation, thereby preventing voids in the concrete slab. The proposed ISFSI pad was constructed in three segments allowing three separate continuous placements of concrete. The licensee applied a broom finish as required by the design to the pad after placement in order to achieve the appropriate surface friction factor.
318 and constructed in accordance with ACI 301. The inspectors observed concrete placement for the second third of the main storage pad. The licensee deposited concrete in this section in one continuous placement. The licensee checked the batch tickets for every truck to confirm that each concrete batch was mixed as specified in the mix design and the mixing time and number of drum revolutions satisfied code requirements to ensure the concrete was suitable for placement. The inspectors observed that the concrete was transported by conveyor belt and deposited in the areas of placement as indicated by the forms. The inspectors noted that the contractor staff maintained careful control of the discharge hose and ensured that concrete had an unrestricted vertical drop to the point of placement to prevent segregation of the aggregate. The contractor used a systematic pattern of vibration to ensure proper consolidation, thereby preventing voids in the concrete slab. The proposed ISFSI pad was constructed in three segments allowing three separate continuous placements of concrete. The licensee applied a broom finish as required by the design to the pad after placement in order to achieve the appropriate surface friction factor.


Enclosure 7 Concrete Field Tests The licensee's contractor obtained concrete samples approximately every 50 cubic yards to test air content, temperature, and slump tests. The field tests were satisfactory and within the allowed acceptance criteria with a few exceptions. During placement of the first third of the proposed pad, the concrete from one of the trucks arriving from the batch plant had a nominal slump of 1.5 inches which was outside the 3 inches to 5.5 inches specified in the Civil Construction Specifications. The licensee added water to the concrete mix and performed high-speed mixing of the truck drum. After stopping the drum the counter displayed 347 revolutions which exceeded 300 specified in ASTM C94. However, engineering judgment could be used and if the concrete was placed within
Enclosure  


90 minutes of its stay time in the truck, the standard allowed for deviations from the 300 revolutions. The licensee placed the concrete approximately an hour after it was batched and with a final slump of 3 inches. The licensee entered this into its corrective action program as Issue Report No. 00817907. There were a few other trucks in which the concrete did not meet the requirements of slump. This was attributed to the rain that the batch plant received the night before. The licensee contacted the batch plant and
Concrete Field Tests


rejected trucks with the slumps outside tolerance and increased sampling to every truck until consistency and quality of concrete were within specifications after which every six trucks were sampled as required by the specifications. The licensee entered this issue into its corrective action program as AR 00816039.
The licensees contractor obtained concrete samples approximately every 50 cubic yards to test air content, temperature, and slump tests. The field tests were satisfactory and within the allowed acceptance criteria with a few exceptions. During placement of the first third of the proposed pad, the concrete from one of the trucks arriving from the batch plant had a nominal slump of 1.5 inches which was outside the 3 inches to 5.5 inches specified in the Civil Construction Specifications. The licensee added water to the concrete mix and performed high-speed mixing of the truck drum. After stopping the drum the counter displayed 347 revolutions which exceeded 300 specified in ASTM C94.
 
However, engineering judgment could be used and if the concrete was placed within 90 minutes of its stay time in the truck, the standard allowed for deviations from the 300 revolutions. The licensee placed the concrete approximately an hour after it was batched and with a final slump of 3 inches. The licensee entered this into its corrective action program as Issue Report No. 00817907. There were a few other trucks in which the concrete did not meet the requirements of slump. This was attributed to the rain that the batch plant received the night before. The licensee contacted the batch plant and rejected trucks with the slumps outside tolerance and increased sampling to every truck until consistency and quality of concrete were within specifications after which every six trucks were sampled as required by the specifications. The licensee entered this issue into its corrective action program as AR 00816039.


In addition to the field tests, the qualified individuals collected concrete samples in cylinders for the concrete strength tests. The cylinders were adequately stored in accordance with ACI and ASTM standards. The cylinders were cured and tested initially after 7 days and then after 28 days by an independent laboratory to measure the compressive strength of the concrete. The inspectors reviewed the 28-day concrete compressive strength test results taken from the storage pad to ensure they met the minimum strength of 3,000 psi and maximum of 4,200 psi as specified by the design requirements. There were several 28-day test results that exceeded the 4,200 psi maximum strength, the highest one being at 4310 psi. The licensee will address these discrepancies and acceptance of these test result deviations in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements. This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.
In addition to the field tests, the qualified individuals collected concrete samples in cylinders for the concrete strength tests. The cylinders were adequately stored in accordance with ACI and ASTM standards. The cylinders were cured and tested initially after 7 days and then after 28 days by an independent laboratory to measure the compressive strength of the concrete. The inspectors reviewed the 28-day concrete compressive strength test results taken from the storage pad to ensure they met the minimum strength of 3,000 psi and maximum of 4,200 psi as specified by the design requirements. There were several 28-day test results that exceeded the 4,200 psi maximum strength, the highest one being at 4310 psi. The licensee will address these discrepancies and acceptance of these test result deviations in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements. This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.
Line 166: Line 231:
In addition to field observations, the inspectors reviewed the rebar certification which could affect the quality of the concrete pad and its design function. The inspectors also reviewed documentation regarding the batch plant certification which was certified in accordance with the Illinois Department of Transportation.
In addition to field observations, the inspectors reviewed the rebar certification which could affect the quality of the concrete pad and its design function. The inspectors also reviewed documentation regarding the batch plant certification which was certified in accordance with the Illinois Department of Transportation.


Placement of Concrete for HI-STORM 100 Overpacks
Placement of Concrete for HI-STORM 100 Overpacks  


The inspectors attended the licensee's pre-job brief prior to construction of the overpacks. The project manager discussed the concrete placement procedures and safety precautions when placing concrete in the overpack shells. Holtec representatives had direct supervision over the work activities and the licensee provided additional  
The inspectors attended the licensees pre-job brief prior to construction of the overpacks. The project manager discussed the concrete placement procedures and safety precautions when placing concrete in the overpack shells. Holtec representatives had direct supervision over the work activities and the licensee provided additional oversight.


oversight.
Enclosure


Enclosure 8 The inspectors inspected three of the six fabricated HI-STORM 100 overpack shells to verify they were clean and free of debris. The inspectors observed that concrete was delivered in truck agitator units and discharged through a trunk that ensured an unrestricted vertical drop to prevent aggregate segregation. In addition, the vertical drop was minimized to prevent aggregate segregation and air entrainment. The staff placed the concrete in layers that were two ft. in elevation. After completion of each layer in the four quadrants of the circle, the workers used a vibrator to ensure proper consolidation of the concrete. During the placement of the concrete, personnel performed unit weight, temperature, and slump tests as specified by the applicable ACI standards. Selected tests were observed by the inspectors.
The inspectors inspected three of the six fabricated HI-STORM 100 overpack shells to verify they were clean and free of debris. The inspectors observed that concrete was delivered in truck agitator units and discharged through a trunk that ensured an unrestricted vertical drop to prevent aggregate segregation. In addition, the vertical drop was minimized to prevent aggregate segregation and air entrainment. The staff placed the concrete in layers that were two ft. in elevation. After completion of each layer in the four quadrants of the circle, the workers used a vibrator to ensure proper consolidation of the concrete. During the placement of the concrete, personnel performed unit weight, temperature, and slump tests as specified by the applicable ACI standards. Selected tests were observed by the inspectors.


c. Conclusion The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensee's approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.
c.


3.0 Exit Meeting Summary On December 11, 2008, the inspectors conducted an exit teleconference to present the results of the inspection. The licensee acknowledged the findings presented and did not identify any information discussed as being proprietary in nature.
Conclusion


Attachment: Supplemental Information
The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.


Attachment SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED  
3.0 Exit Meeting Summary
*Brad Adams Plant Manager *John Anderson Project Management Manager  
 
On December 11, 2008, the inspectors conducted an exit teleconference to present the results of the inspection. The licensee acknowledged the findings presented and did not identify any information discussed as being proprietary in nature.
 
Attachment:
Supplemental Information
 
Attachment SUPPLEMENTAL INFORMATION  
 
PARTIAL LIST OF PERSONS CONTACTED  
* Brad Adams Plant Manager  
*John Anderson Project Management Manager  
*Jerry Barger Project Manager  
*Jerry Barger Project Manager  
*Ed Blondin Design Engineering Mechanical  
*Ed Blondin  
*Terry Eckert Contract Project Manager *Bill Grundmann Regulatory Assurance Manager Harish Patel Lead project Engineer Dry Cask Storage Project  
 
Design Engineering Mechanical  
*Terry Eckert Contract Project Manager  
*Bill Grundmann Regulatory Assurance Manager Harish Patel  
 
Lead project Engineer Dry Cask Storage Project  
*Bill Perchiazzi Design Engineering Manager  
*Bill Perchiazzi Design Engineering Manager  
*Tim Spelde Exelon Project Mananger  
*Tim Spelde  
 
Exelon Project Mananger  
* Persons present during the December 11, 2008, exit teleconference.


* Persons present during the December 11, 2008, exit teleconference.
INSPECTION PROCEDURE USED


INSPECTION PROCEDURE USED IP 60853 Construction of an Independent Spent Fuel Storage Installation  
IP 60853 Construction of an Independent Spent Fuel Storage Installation  


IP 60856 Review of 10 CFR 72.212 (b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design ITEMS OPENED, CLOSED, AND DISCUSSED Opened Type Summary 07200068/2008-001-01 URI Change to Tip Over Analysis to Incorporate Rebar Discrepancies
IP 60856 Review of 10 CFR 72.212 (b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design  


07200068/2008-001-02 URI Change in Tip Over Analysis to Incorporate 28 day Concrete
ITEMS OPENED, CLOSED, AND DISCUSSED


Compressive Strength Test Discrepancies
Opened Type Summary


Closed None Discussed None
07200068/2008-001-01


Attachment LIST OF DOCUMENTS REVIEWED Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 0 Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 2  
URI
 
Change to Tip Over Analysis to Incorporate Rebar Discrepancies
 
07200068/2008-001-02 URI
 
Change in Tip Over Analysis to Incorporate 28 day Concrete Compressive Strength Test Discrepancies
 
Closed
 
None
 
Discussed
 
None
 
Attachment  
 
LIST OF DOCUMENTS REVIEWED  
 
Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 0  
 
Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 2  


Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 3  
Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 3  
Line 206: Line 311:
Drawing R1; ISFSI Foundation Plan; dated April 22, 2008  
Drawing R1; ISFSI Foundation Plan; dated April 22, 2008  


Drawing R2; Construction Pad Foundation Plan; dated May 5, 2008 Drawing No. S-2232; ISFSI Pad Plan, Details, and Sections; dated March 20, 2008  
Drawing R2; Construction Pad Foundation Plan; dated May 5, 2008  
 
Drawing No. S-2232; ISFSI Pad Plan, Details, and Sections; dated March 20, 2008  


Drawing No. S-2238; Dry Fuel Storage Project Cask Storage Pad Details; dated March 20, 2008  
Drawing No. S-2238; Dry Fuel Storage Project Cask Storage Pad Details; dated March 20, 2008  
Line 214: Line 321:
Engineering Change Number 367118; Dry Cask Storage Project Independent Spent Fuel Storage Installation (ISFSI) Pad; Revision 3  
Engineering Change Number 367118; Dry Cask Storage Project Independent Spent Fuel Storage Installation (ISFSI) Pad; Revision 3  


Gerdau Ameristeel Chemical and Physical Test Report Holtec International BYNPS ISFSI Pad Plate Load Tests Letter; Document ID 1676024; dated
Gerdau Ameristeel Chemical and Physical Test Report  


July 11, 2008  
Holtec International BYNPS ISFSI Pad Plate Load Tests Letter; Document ID 1676024; dated July 11, 2008  


Holtec International BYNPS ISFSI Pad Plate Load Tests Results Letter; Document ID 1676026; dated July 28, 2008  
Holtec International BYNPS ISFSI Pad Plate Load Tests Results Letter; Document ID 1676026; dated July 28, 2008  
Line 226: Line 333:
Terracon Concrete Compressive Strength Test; 7-day Test Reports for North Third of ISFSI Pad; dated September 17, 2008  
Terracon Concrete Compressive Strength Test; 7-day Test Reports for North Third of ISFSI Pad; dated September 17, 2008  


Terracon Concrete Compressive Strength Test; 7-day Test Reports for South Third of ISFSI Pad; dated September 26, 2008 Terracon Concrete Compressive Strength Test; 7-day Test Reports for Middle Third of ISFSI
Terracon Concrete Compressive Strength Test; 7-day Test Reports for South Third of ISFSI Pad; dated September 26, 2008  


Pad; dated October 2, 2008  
Terracon Concrete Compressive Strength Test; 7-day Test Reports for Middle Third of ISFSI Pad; dated October 2, 2008  


Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for North Third of ISFSI Pad, sample dated September 9, 2008 Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for South Third of ISFSI Pad, sample dated September 18, 2008  
Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for North Third of ISFSI Pad, sample dated September 9, 2008  


Attachment Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for Middle Third of ISFSI Pad, sample date September 24, 2008  
Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for South Third of ISFSI Pad, sample dated September 18, 2008
 
Attachment  
 
Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for Middle Third of ISFSI Pad, sample date September 24, 2008  


Terracon Report Number 19081017.0022; Dry Cask Storage-Byron; dated June 26, 2008  
Terracon Report Number 19081017.0022; Dry Cask Storage-Byron; dated June 26, 2008  


Terracon Plate Bearing Test Results-ASTM D 1194; dated July 23, 2008, July 24, 2008, and  
Terracon Plate Bearing Test Results-ASTM D 1194; dated July 23, 2008, July 24, 2008, and July 25, 2008  
 
July 25, 2008  


WR-BY-PF-10; Effect of Local Probable Maximum Precipitation (PMP) at Plant Site; EC 367118; Revision 4D  
WR-BY-PF-10; Effect of Local Probable Maximum Precipitation (PMP) at Plant Site; EC 367118; Revision 4D  
Line 244: Line 353:
LIST OF ACRONYMS USED  
LIST OF ACRONYMS USED  


ACI American Concrete Institute ADAMS Agencywide Documents Access Management System ASTM American Society for Testing and Materials AR Action Report CFR Code of Federal Regulations CoC Certificate of Compliance ft Feet ISFSI Independent Spent Fuel Storage Installation kips kilopounds ksi kips per square inch NRC Nuclear Regulatory Commission psi pounds per square inch URI Unresolved Item
ACI  
 
American Concrete Institute ADAMS Agencywide Documents Access Management System ASTM American Society for Testing and Materials AR  
 
Action Report CFR  
 
Code of Federal Regulations CoC  
 
Certificate of Compliance ft  
 
Feet ISFSI Independent Spent Fuel Storage Installation kips  
 
kilopounds ksi  
 
kips per square inch NRC  
 
Nuclear Regulatory Commission psi  
 
pounds per square inch URI  
 
Unresolved Item
}}
}}

Latest revision as of 13:54, 14 January 2025

IR 072000068-08-01 (Dnms), on 05/21/2008, 06/26/2008, 08/05/2008, 08/27/2008, 09/18/2008, and 12/11/2008, Byron Power Station
ML083540743
Person / Time
Site: Byron  Constellation icon.png
Issue date: 12/19/2008
From: Christine Lipa
NRC/RGN-III/DNMS/DB
To: Pardee C
AmerGen Energy Co, Exelon Nuclear
References
FOIA/PA-2010-0209 IR-08-001
Download: ML083540743 (14)


Text

December 19, 2008

SUBJECT:

BYRON POWER STATION NRC INSPECTION REPORT NO. 072-00068/08-01(DNMS)

Dear Mr. Pardee:

On December 11, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed its inspection of the dry cask storage pad construction activities at the Byron Power Station. The purpose of the inspection was to determine whether the dry cask storage pad design and construction activities were conducted safely and in accordance with NRC requirements and design specifications. At the conclusion of the inspection on December 11, 2008, during an exit teleconference, the inspectors discussed the inspection findings with members of your staff.

The enclosed report presents the results of this inspection.

The inspection was an examination of the dry fuel storage pad construction activities as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. Specifically, the inspectors observed placement of structural fill, reinforcement, and concrete for the storage pad and HI-STORM 100 overpacks. The inspectors also performed an in-office review of calculations related to the storage pad. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of selected examinations of procedures and representative records, observations of activities, and interviews with personnel.

Based on the results of these inspections, the inspectors did not identify violations of NRC requirements. The storage pad construction activities were conducted in accordance with applicable regulations and license conditions.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.

Sincerely,

/RA by William G. Snell, acting for/

Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch

Docket Nos.72-068; 050-454; 50-455 License Nos. NPF-37; NPF-66

Enclosure:

Inspection Report No. 072-00068/08-01(DNMS)

REGION III==

Docket No.

072-00068

License Nos.

NPF-37; NPF-66

Report No.

072-00068/08-01(DNMS)

Licensee:

Exelon

Facility:

Byron Power Station

Location:

4450 North German Church Road

Byron, IL 61010

Inspection Dates:

Onsite: May 21, 2008; June 26, 2008, August 5, 2008, August 27, 2008; and September 18, 2008.

In-office review completed on December 11, 2008

Exit Teleconference: December 11, 2008

Inspectors:

Sarah Bakhsh, Reactor Inspector

Bruce Bartlett, Senior Resident Inspector

Matthew Learn, Reactor Engineer in training

Approved by:

Christine A. Lipa, Chief

Materials Control, ISFSI and Decommissioning Branch

Division of Nuclear Materials Safety

Enclosure

EXECUTIVE SUMMARY Byron Power Station NRC Inspection Report 072-00068/08-01(DNMS)

The purpose of the inspection was to observe and evaluate the licensees activities associated with construction of a new Independent Spent Fuel Storage Installation (ISFSI) pad. During this inspection period, the inspectors also reviewed the design of the new pad to ensure compliance with the regulations and the design specifications.

Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design

  • The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.

(Section 1.1)

Independent Spent Fuel Storage Pad Construction

  • The licensees engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications and industry standards. (Section 2.1)
  • The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI)

07200068/2008001, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008002, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies. (Section 2.2)

Enclosure

Report Details

1.0 Review of 10 CFR 72.212(b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design (IP 60856)

1.1 Site Characterization and Design of the ISFSI Pad

a.

Inspection Scope

The inspectors evaluated the licensees soil and engineering design evaluations in preparation for a new dry cask storage pad to verify the licensees compliance with the Certificate of Compliance (CoC), 10 CFR Part 72 requirements, and industry standards.

b.

Observations and Findings

Soil Analysis

A total of six borings were drilled within the general vicinity of the ISFSI facility to determine the site subsurface conditions. The inspectors reviewed the licensees report and the soil boring test results. Based on the soil sample analysis, the subsurface soil profile for the ISFSI consists of approximately 4 inches of asphalt followed by 12 inches of granular subbase or 2 to 3 inches of organic topsoil. Both were underlain by dense to very dense silty sand with crushed gravel. Bedrock was approximately 3 to 6 feet (ft.)

below the existing grade, with the existing grade at approximately 873.6 ft. Rock cores were taken to depths ranging from 13 to 16 ft. There was no groundwater collected within the borings prior to the addition of water to facilitate rock coring. The groundwater surface varied, but was at approximately 840 ft. at the plant site and 740 ft. one mile northeast of the site. Groundwater was at approximately 60 ft. to 75 ft. below the area of the ISFSI.

Soil Liquefaction Analysis

The boring logs performed by the licensees contractor indicated the presence of dense to very dense soils as demonstrated by the high Standard Penetration Test blow counts.

High blow counts are indicative of high resistance to liquefaction. In addition, at approximately 3 feet below grade, the soil strata was limestone rock which is not susceptible to liquefaction.

Flooding Analysis The plant probable maximum precipitation was approximately 870.8 ft., which is the governing water elevation for the plant site. The ridge line of pad runs east to west. The lower edge of the pad (thickness of 2 ft.) was at elevation 875 ft. which sloped from the top elevation of 875 ft. 3 inches. Thus the pad was located on the upstream side of the flood path which can aid in lowering the flood water depth. The water drains from the east side (main road to the plant) to a ditch on the west side which drains to the river.

To address any frost heave concerns during cold weather, the licensee placed a frost free granular material under the pad.

Enclosure

c.

Conclusion

The inspectors concluded that the licensee adequately characterized the subsurface conditions for the new ISFSI site. The ISFSI pad was designed in accordance with the Certificate of Compliance, 10 CFR Part 72 requirements, and industry standards.

2.0 Independent Spent Fuel Storage Pad Construction (IP 60853)

2.1 Excavation and Soil Compaction Activities

a.

Inspection Scope

The inspectors evaluated the licensees site characterization, and observed soil compaction activities for the new dry cask storage pad to verify the licensees compliance with its specifications, design drawings, and industry standards.

b.

Observations and Findings

The licensee constructed a reinforced concrete ISFSI storage pad to the south of the plant. The ISFSI pad was designed to hold 96 dry fuel storage casks. The licensee excavated 3 feet of soil, ensuring removal of topsoil, organic, and all undesirable material until bedrock was reached. There was a lot of hard rock identified at very shallow depths and in order to ensure the required 3 ft. of engineered fill be placed, the licensee raised the final elevation of the top of the pad by 1 ft. 6 inches to approximately 875 ft.

Rolling of the underlying in-situ material ensured that a suitable subgrade existed under the pad area. Following receipt of satisfactory compaction results for the subgrade, the licensee backfilled the area with 3 ft. of non-frost susceptible granular base material (gravel/sand) and compacted the fill to a minimum of 95 percent of the maximum dry density as indicated in American Society for Testing and Materials (ASTM) D 1557. The inspectors observed the licensee place and compact the fill in layers of six inches.

The inspectors observed certified personnel perform field tests using a moisture density gauge to verify that each individual lift met the minimum compaction, maximum dry density and moisture content as specified in technical specifications and established during laboratory tests. The licensees contractor obtained this data by performing field tests which included wet and dry density, moisture content, and lift thickness in accordance with the appropriate ASTM standards.

The licensee performed soil plate load tests for the engineered fill to determine the value of the Youngs Modulus. This parameter measured the stiffness of the material and was calculated using field tests. There is both a lower and upper limit required to ensure the pads structural qualifications are met. The lower limit of the Youngs Modulus was the minimum required for the strength of the pad while the upper limit was to ensure that the deceleration values of the fuel assemblies do not exceed design requirements during a non-mechanistic tipover of the cask.

Enclosure

The licensee committed to follow the ASTM D1194 standards in its Civil Construction Specification and Engineering Change package for the plate load tests which required the use of at least three test locations. However, the specification contradicted this by stating that at least one Soil Plate Load Test shall be performed near the center of the pad location. The inspectors highlighted this discrepancy to the licensee. The licensee used three test locations and revised the specification to state at least one Soil Plate Load Test shall be performed for the installation of each section of the ISFSI pad.

The licensee and the designer of the proposed pad (Holtec) indicated that although they did plan to use three test locations, they were not required to do so because the standard was to be used as a guidance document. The inspectors explained the need for the licensee to emphasize adherence to codes and standards and the inspectors understanding that there needs to be full compliance to documents that the licensee committed to in their design documents. The licensee modified its documents to better reflect their intent to use the standards as guidance documents. Discrepancies would be submitted to Owners Engineering for evaluation and to obtain acceptance from Holtec prior to proceeding with construction.

The results for the three tests were forwarded to Holtec to determine the Youngs modulus. The initial test results were outside the 7.5 kips per square inch (ksi) to 15 ksi range specified in the design documents. Since there is hard rock at very shallow depths and only 3 ft. of backfill, Holtec recommended changing the plate size used in the test from a 2x2 to a 1x1. Changing the plate size ensured that the data was representative of the engineered fill without significant contribution from the in-situ rock beneath the fill. The values for the Youngs modulus were then within the specified range for the three test locations.

c.

Conclusion

The licensees engineering evaluation of the in-situ soil was adequate. The soil compaction activities were being performed in accordance with technical specifications and industry standards.

2.2 Pad Construction Activities

a.

Inspection Scope

The inspectors evaluated whether construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Work Orders, and applicable industry standards.

The inspectors also reviewed select material, and batch plant tickets.

b.

Observations and Findings

The inspectors reviewed an approved Engineering Change package which provided specifications for the pad construction activities. The storage pad was designed to be a 198 ft. long, 116 ft. wide, and 2 ft. thick reinforced concrete slab. The storage pad was supported by a 6 inch thick concrete mat foundation set on top of 3 ft. of dense graded aggregate.

Enclosure

Placement of Reinforcing Steel

After placement and satisfactory compaction of the engineered fill, the licensee installed forms and placed reinforcement bars (rebar). The reinforced concrete was designed for a nominal compressive strength between 3,000 pounds per square inch (psi) and 4,200 psi at 28 days and the rebar conformed to ASTM A615 Grade 60 steel.

After placing the rebar and securing the forms, the licensee performed an inspection of the first third of the proposed pad prior to concrete placement. The inspectors reviewed the design drawings and performed an independent walk down of the proposed first third of the pad. The pad area was free of debris and excessive moisture. The rebar was placed in two upper and lower layers joined by U-shaped bars. The licensee placed the correct size of rebar. The inspectors measured the spacing between the rebar and identified some instances where the spacing was outside the allowed tolerance specified in the design drawing. The inspectors also identified instances in which the requirements for the concrete cover between the rebar and the forms as well as the top and bottom of the pad differed from design drawings. Thus a number of field changes were performed to address the existing field conditions which deviated from the prescribed drawings. Where it was not practical, the licensee obtained justification from Holtec to leave the rebar in the as built condition as documented in Holtecs September 2, 2008, letter to the licensee. The licensee entered this into its corrective action program as Action Request (AR) Report 00812028. The licensee will address these discrepancies in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements.

This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar Discrepancies.

Placement of Concrete for Storage Pad

The storage pad was designed in accordance with American Concrete Institute (ACI)

318 and constructed in accordance with ACI 301. The inspectors observed concrete placement for the second third of the main storage pad. The licensee deposited concrete in this section in one continuous placement. The licensee checked the batch tickets for every truck to confirm that each concrete batch was mixed as specified in the mix design and the mixing time and number of drum revolutions satisfied code requirements to ensure the concrete was suitable for placement. The inspectors observed that the concrete was transported by conveyor belt and deposited in the areas of placement as indicated by the forms. The inspectors noted that the contractor staff maintained careful control of the discharge hose and ensured that concrete had an unrestricted vertical drop to the point of placement to prevent segregation of the aggregate. The contractor used a systematic pattern of vibration to ensure proper consolidation, thereby preventing voids in the concrete slab. The proposed ISFSI pad was constructed in three segments allowing three separate continuous placements of concrete. The licensee applied a broom finish as required by the design to the pad after placement in order to achieve the appropriate surface friction factor.

Enclosure

Concrete Field Tests

The licensees contractor obtained concrete samples approximately every 50 cubic yards to test air content, temperature, and slump tests. The field tests were satisfactory and within the allowed acceptance criteria with a few exceptions. During placement of the first third of the proposed pad, the concrete from one of the trucks arriving from the batch plant had a nominal slump of 1.5 inches which was outside the 3 inches to 5.5 inches specified in the Civil Construction Specifications. The licensee added water to the concrete mix and performed high-speed mixing of the truck drum. After stopping the drum the counter displayed 347 revolutions which exceeded 300 specified in ASTM C94.

However, engineering judgment could be used and if the concrete was placed within 90 minutes of its stay time in the truck, the standard allowed for deviations from the 300 revolutions. The licensee placed the concrete approximately an hour after it was batched and with a final slump of 3 inches. The licensee entered this into its corrective action program as Issue Report No. 00817907. There were a few other trucks in which the concrete did not meet the requirements of slump. This was attributed to the rain that the batch plant received the night before. The licensee contacted the batch plant and rejected trucks with the slumps outside tolerance and increased sampling to every truck until consistency and quality of concrete were within specifications after which every six trucks were sampled as required by the specifications. The licensee entered this issue into its corrective action program as AR 00816039.

In addition to the field tests, the qualified individuals collected concrete samples in cylinders for the concrete strength tests. The cylinders were adequately stored in accordance with ACI and ASTM standards. The cylinders were cured and tested initially after 7 days and then after 28 days by an independent laboratory to measure the compressive strength of the concrete. The inspectors reviewed the 28-day concrete compressive strength test results taken from the storage pad to ensure they met the minimum strength of 3,000 psi and maximum of 4,200 psi as specified by the design requirements. There were several 28-day test results that exceeded the 4,200 psi maximum strength, the highest one being at 4310 psi. The licensee will address these discrepancies and acceptance of these test result deviations in a calculation which is still pending completion. The inspector will review the calculation upon receipt to ensure adherence to the design requirements. This issue requires additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, this issue will be treated as URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.

In addition to field observations, the inspectors reviewed the rebar certification which could affect the quality of the concrete pad and its design function. The inspectors also reviewed documentation regarding the batch plant certification which was certified in accordance with the Illinois Department of Transportation.

Placement of Concrete for HI-STORM 100 Overpacks

The inspectors attended the licensees pre-job brief prior to construction of the overpacks. The project manager discussed the concrete placement procedures and safety precautions when placing concrete in the overpack shells. Holtec representatives had direct supervision over the work activities and the licensee provided additional oversight.

Enclosure

The inspectors inspected three of the six fabricated HI-STORM 100 overpack shells to verify they were clean and free of debris. The inspectors observed that concrete was delivered in truck agitator units and discharged through a trunk that ensured an unrestricted vertical drop to prevent aggregate segregation. In addition, the vertical drop was minimized to prevent aggregate segregation and air entrainment. The staff placed the concrete in layers that were two ft. in elevation. After completion of each layer in the four quadrants of the circle, the workers used a vibrator to ensure proper consolidation of the concrete. During the placement of the concrete, personnel performed unit weight, temperature, and slump tests as specified by the applicable ACI standards. Selected tests were observed by the inspectors.

c.

Conclusion

The inspectors concluded that most of the construction activities for the ISFSI concrete storage pad complied with specifications contained in the licensees approved Engineering Change package, design drawings, Civil Construction Specifications, Work Orders, and applicable industry standards. Two issues pertaining to the Tip Over Analysis required additional NRC evaluation and will remain unresolved pending further review. Pending resolution by the NRC, the issues will be treated as Unresolved Item (URI) 07200068/2008001-01, Change to Tip Over Analysis to Incorporate Rebar Discrepancies and URI 07200068/2008001-02, Change in Tip Over Analysis to Incorporate 28-day Concrete Compressive Strength Test Discrepancies.

3.0 Exit Meeting Summary

On December 11, 2008, the inspectors conducted an exit teleconference to present the results of the inspection. The licensee acknowledged the findings presented and did not identify any information discussed as being proprietary in nature.

Attachment:

Supplemental Information

Attachment SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

  • Brad Adams Plant Manager
  • John Anderson Project Management Manager
  • Jerry Barger Project Manager
  • Ed Blondin

Design Engineering Mechanical

  • Terry Eckert Contract Project Manager
  • Bill Grundmann Regulatory Assurance Manager Harish Patel

Lead project Engineer Dry Cask Storage Project

  • Bill Perchiazzi Design Engineering Manager
  • Tim Spelde

Exelon Project Mananger

  • Persons present during the December 11, 2008, exit teleconference.

INSPECTION PROCEDURE USED

IP 60853 Construction of an Independent Spent Fuel Storage Installation

IP 60856 Review of 10 CFR 72.212 (b) Evaluations, Appendix A, Review of ISFSI Storage Pad Design

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened Type Summary

07200068/2008-001-01

URI

Change to Tip Over Analysis to Incorporate Rebar Discrepancies

07200068/2008-001-02 URI

Change in Tip Over Analysis to Incorporate 28 day Concrete Compressive Strength Test Discrepancies

Closed

None

Discussed

None

Attachment

LIST OF DOCUMENTS REVIEWED

Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 0

Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 2

Byron Independent Spent Fuel Storage Installation Civil Construction Specification; Specification No. 127324-BYR-001; Revision 3

Drawing R1; ISFSI Foundation Plan; dated April 22, 2008

Drawing R2; Construction Pad Foundation Plan; dated May 5, 2008

Drawing No. S-2232; ISFSI Pad Plan, Details, and Sections; dated March 20, 2008

Drawing No. S-2238; Dry Fuel Storage Project Cask Storage Pad Details; dated March 20, 2008

Drawing No. S-2239; Dry Fuel Storage Project Grading Sections; dated February 22, 2008

Engineering Change Number 367118; Dry Cask Storage Project Independent Spent Fuel Storage Installation (ISFSI) Pad; Revision 3

Gerdau Ameristeel Chemical and Physical Test Report

Holtec International BYNPS ISFSI Pad Plate Load Tests Letter; Document ID 1676024; dated July 11, 2008

Holtec International BYNPS ISFSI Pad Plate Load Tests Results Letter; Document ID 1676026; dated July 28, 2008

PSI Geotechnical Engineering Services Report; dated November 16, 2007

PSI Geotechnical Engineering Services Report Letter; dated December 9, 2008

Terracon Concrete Compressive Strength Test; 7-day Test Reports for North Third of ISFSI Pad; dated September 17, 2008

Terracon Concrete Compressive Strength Test; 7-day Test Reports for South Third of ISFSI Pad; dated September 26, 2008

Terracon Concrete Compressive Strength Test; 7-day Test Reports for Middle Third of ISFSI Pad; dated October 2, 2008

Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for North Third of ISFSI Pad, sample dated September 9, 2008

Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for South Third of ISFSI Pad, sample dated September 18, 2008

Attachment

Terracon Concrete Compressive Strength Test Report; 28-Day Test Report for Middle Third of ISFSI Pad, sample date September 24, 2008

Terracon Report Number 19081017.0022; Dry Cask Storage-Byron; dated June 26, 2008

Terracon Plate Bearing Test Results-ASTM D 1194; dated July 23, 2008, July 24, 2008, and July 25, 2008

WR-BY-PF-10; Effect of Local Probable Maximum Precipitation (PMP) at Plant Site; EC 367118; Revision 4D

LIST OF ACRONYMS USED

ACI

American Concrete Institute ADAMS Agencywide Documents Access Management System ASTM American Society for Testing and Materials AR

Action Report CFR

Code of Federal Regulations CoC

Certificate of Compliance ft

Feet ISFSI Independent Spent Fuel Storage Installation kips

kilopounds ksi

kips per square inch NRC

Nuclear Regulatory Commission psi

pounds per square inch URI

Unresolved Item