| issue date = 06/03/2009 | | issue date = 06/03/2009 | ||
| title = | | title = TVA, Presentation Slides for Browns Ferry, Unit 1 | ||
| author name = Brown E | | author name = Brown E | ||
| author affiliation = NRC/NRR/DORL/LPLII-2 | | author affiliation = NRC/NRR/DORL/LPLII-2 | ||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:-- | {{#Wiki_filter:-- | ||
Z JJ | |||
- | () | ||
Revised January 28 meeting -NRC requested that the submittal schedule be reviewed to determine best possible dates Areva and TVA have agreed on approach improve schedule -Preliminary core design work will be eliminated | S:S: | ||
-Final core design has commenced using best available energy plan estimate for current cycle -TVA review time for selected reload inputs and analyses will be accelerated Revised Schedule | ~ | ||
* Areva will deliver all reload needed to support submittal by | CD | ||
-TVA will commit to a submittal date of 12/11/09 | ~ | ||
- | CD | ||
LAR | ('") | ||
~ | |||
* Will include the following reports: | ::r ::J | ||
-L to 0)1 I\\)~ | |||
* Will not submit the LOCA break spectrum report | 8~ | ||
* Will include the following Tech Spec related changes: | COeD 11- | ||
::J OJ | |||
* LAR will also address the eleven items requested by NRC in the draft Summary of Information Request Request NRC formally issue final as soon as possible RAI Reviews -LAR will address the prior BFN 2/3 fuel related EPU RAls Will also address the RAls from the Brunswick transition}} | ...., o | ||
:E | |||
::::J en | |||
::;i~ | |||
tu...., | |||
::::J en'< | |||
r-+ | |||
o >> | |||
::::J CD < | |||
tu 11 c:: | |||
CD | |||
(J) c 0 | |||
3 Q.)- | |||
""C Q.) | |||
("") | |||
Q.) " | |||
(Q CD 0 < | |||
CD ;: | |||
CD | |||
~ | |||
(J) | |||
C 0 | |||
3 Q.)- | |||
en | |||
("") | |||
::::r CD | |||
: a. | |||
c - | |||
CD C | |||
""C | |||
: a. | |||
Q.) | |||
CD CO> | |||
CD | |||
:::J | |||
: a. | |||
Q) | |||
en c | |||
cr 3 | |||
Ol en o | |||
::r. | |||
eo | |||
: a. | |||
c CD C | |||
-c | |||
: a. | |||
Ol eo | |||
Revised Schedule | |||
* January 28 meeting - NRC requested that the submittal schedule be reviewed to determine best possible dates | |||
* Areva and TVA have agreed on approach to improve schedule | |||
- Preliminary core design work will be eliminated | |||
- Final core design has commenced using best available energy plan estimate for current cycle | |||
- TVA review time for selected reload inputs and analyses will be accelerated | |||
Revised Schedule (cant) | |||
* Areva will deliver all reload documentation needed to support submittal by 10/23/09 | |||
* TVA will require time to prepare final submittal package and complete internal reviews and approvals | |||
- TVA will commit to a submittal date of 12/11/09 | |||
en c | |||
c 3 | |||
Dl | |||
-c Dl o | |||
=" | |||
Dl co CD o | |||
CD | |||
~ | |||
CD | |||
~ | |||
LAR Contents LAR will be a complete package No supplemental information planned to be submitted | |||
* Will include the following reports: | |||
Thermal Hydraulic Design Report Mechanical Design Report ANP-2637 (BWR Licensing Methodology Compendium) | |||
Fuel Cycle Design Report Reload Safety Report | |||
* Will not submit the LOCA break spectrum report Will provide justification as to unit 1 applicability | |||
* Will include the following Tech Spec related changes: | |||
SLMCPR Tech Spec (if required) | |||
Tech Spec 5.6.5 update to add Areva analytical methods Tech Spec Bases page changes | |||
LAR Contents (cant) | |||
* LAR will also address the eleven items requested by NRC in the draft Summary of Information Request | |||
- Request NRC formally issue final as soon as possible | |||
* RAI Reviews | |||
- LAR will address the prior BFN 2/3 fuel related EPU RAls | |||
- Will also address the RAls from the Brunswick transition}} | |||
Latest revision as of 12:47, 14 January 2025
| ML090770162 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 06/03/2009 |
| From: | Ellen Brown Plant Licensing Branch II |
| To: | |
| Brown E, NRR/DORL, 415-2315 | |
| Shared Package | |
| ML090770387 | List: |
| References | |
| TAC ME0438 | |
| Download: ML090770162 (8) | |
Text
--
Z JJ
()
S:S:
~
CD
~
CD
('")
~
- r ::J
-L to 0)1 I\\)~
8~
COeD 11-
- J OJ
...., o
- E
- J en
- i~
tu....,
- J en'<
r-+
o >>
- J CD <
tu 11 c::
CD
(J) c 0
3 Q.)-
""C Q.)
("")
Q.) "
(Q CD 0 <
CD ;:
CD
~
(J)
C 0
3 Q.)-
en
("")
- r CD
- a.
c -
CD C
""C
- a.
Q.)
CD CO>
CD
- J
- a.
Q)
en c
cr 3
Ol en o
- r.
eo
- a.
c CD C
-c
- a.
Ol eo
Revised Schedule
- January 28 meeting - NRC requested that the submittal schedule be reviewed to determine best possible dates
- Areva and TVA have agreed on approach to improve schedule
- Preliminary core design work will be eliminated
- Final core design has commenced using best available energy plan estimate for current cycle
- TVA review time for selected reload inputs and analyses will be accelerated
Revised Schedule (cant)
- Areva will deliver all reload documentation needed to support submittal by 10/23/09
- TVA will require time to prepare final submittal package and complete internal reviews and approvals
- TVA will commit to a submittal date of 12/11/09
en c
c 3
Dl
-c Dl o
="
Dl co CD o
CD
~
CD
~
LAR Contents LAR will be a complete package No supplemental information planned to be submitted
- Will include the following reports:
Thermal Hydraulic Design Report Mechanical Design Report ANP-2637 (BWR Licensing Methodology Compendium)
Fuel Cycle Design Report Reload Safety Report
- Will not submit the LOCA break spectrum report Will provide justification as to unit 1 applicability
- Will include the following Tech Spec related changes:
SLMCPR Tech Spec (if required)
Tech Spec 5.6.5 update to add Areva analytical methods Tech Spec Bases page changes
LAR Contents (cant)
- LAR will also address the eleven items requested by NRC in the draft Summary of Information Request
- Request NRC formally issue final as soon as possible
- RAI Reviews
- LAR will address the prior BFN 2/3 fuel related EPU RAls
- Will also address the RAls from the Brunswick transition