| issue date = 05/26/2009
| issue date = 05/26/2009
| title = E-mail from J. White to M. Ferdas and R. Bellamy Re Timeline for Second Excavation
| title = E-mail from J. White to M. Ferdas and R. Bellamy Re Timeline for Second Excavation
| author name = White J R
| author name = White J
| author affiliation = NRC/RGN-I/DRS/PSB2
| author affiliation = NRC/RGN-I/DRS/PSB2
| addressee name = Bellamy R R, Ferdas M S
| addressee name = Bellamy R, Ferdas M
| addressee affiliation = NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6
| addressee affiliation = NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6
| docket = 05000219
| docket = 05000219
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Bellamy, Ronald From: John White.Sent: Tuesday, May 26, 2009 7:57 AM To: Marc Ferdas; Ronald Bellamy Cc: Ronald Nimitz; Harold Gray  
{{#Wiki_filter:Bellamy, Ronald From:
John White
.Sent:
Tuesday, May 26, 2009 7:57 AM To:
Marc Ferdas; Ronald Bellamy Cc:
Ronald Nimitz; Harold Gray


==Subject:==
==Subject:==
FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com  
FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com [mailto:James.Barstow@exeloncorp.com]
[mailto:James.Barstow@exeloncorp.com].Sent: Thursday, May 21, 2009 2:04 PM To: John White  
.Sent: Thursday, May 21, 2009 2:04 PM To: John White


==Subject:==
==Subject:==
Timeline for Second Excavation at Oyster Creek John, Below is the timeline that Project Management is utilizing for the inspection of the CS-38 line. This is a tentative schedule weather permitting.
Timeline for Second Excavation at Oyster Creek
Jim* Diving complete:
: John, Below is the timeline that Project Management is utilizing for the inspection of the CS-38 line. This is a tentative schedule weather permitting.
5/20/09* Area policed in preparation of MUA tour: 5/20/09-5/21/09
Jim Diving complete: 5/20/09 Area policed in preparation of MUA tour: 5/20/09-5/21/09 Repair of penetration at Turbine Building: 5/22/09 0
* Repair of penetration at Turbine Building:
Tour of trenching: 5/22/09 De-mob and clean-up of area: 5/26/09-5/29/09 Free release of material by R.P. 6/01/09-6/13/09 Backfill of trench: 6/1/09-6/5/09 Excavation of C.R.D. min flow line: 6/8/09-6/12/09 Inspection of pipe:6/15/09 Remove coating (contingent): 6/16/09 UT inspection (contingent): 6/17/09 Re-coat piping (contingent): 6/18/09-6/19/09 Backfill second excavation:6/22/09-6/26/09
5/22/09 0 Tour of trenching:
 
5/22/09* De-mob and clean-up of area: 5/26/09-5/29/09
Jim (Barstow Exelon Corporation TeamOysterCreek Oyster Creek Generating Station Regulatory Assurance Manager Office of the Site Vice President James. Barstow(ýexeloncorp.com Work - 609-971-4947 This e-mail and any of its attachments may contain Exelon Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Exelon Corporation family of Companies. This e-mail is intended solely for the use of the individual or entity to which it is addressed. If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or actionr taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful. If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout. Thank You.
* Free release of material by R.P. 6/01/09-6/13/09
* 2}}
* Backfill of trench: 6/1/09-6/5/09
* Excavation of C.R.D. min flow line: 6/8/09-6/12/09
* Inspection of pipe:6/15/09
* Remove coating (contingent):
6/16/09* UT inspection (contingent):
6/17/09* Re-coat piping (contingent):
6/18/09-6/19/09
* Backfill second excavation:6/22/09-6/26/09 Jim (Barstow Exelon Corporation TeamOysterCreek Oyster Creek Generating Station Regulatory Assurance Manager Office of the Site Vice President James. Barstow(ýexeloncorp.com Work -609-971-4947 This e-mail and any of its attachments may contain Exelon Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Exelon Corporation family of Companies.
This e-mail is intended solely for the use of the individual or entity to which it is addressed.
If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or actionr taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful.
If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout.
Thank You. *2}}

Latest revision as of 08:27, 14 January 2025

E-mail from J. White to M. Ferdas and R. Bellamy Re Timeline for Second Excavation
ML093080805
Person / Time
Site: Oyster Creek
Issue date: 05/26/2009
From: Jason White
NRC/RGN-I/DRS/PSB2
To: Ronald Bellamy, Marc Ferdas
NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6
References
FOIA/PA-2009-0214
Download: ML093080805 (2)


Text

Bellamy, Ronald From:

John White

.Sent:

Tuesday, May 26, 2009 7:57 AM To:

Marc Ferdas; Ronald Bellamy Cc:

Ronald Nimitz; Harold Gray

Subject:

FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com [1]

.Sent: Thursday, May 21, 2009 2:04 PM To: John White

Subject:

Timeline for Second Excavation at Oyster Creek

John, Below is the timeline that Project Management is utilizing for the inspection of the CS-38 line. This is a tentative schedule weather permitting.

Jim Diving complete: 5/20/09 Area policed in preparation of MUA tour: 5/20/09-5/21/09 Repair of penetration at Turbine Building: 5/22/09 0

Tour of trenching: 5/22/09 De-mob and clean-up of area: 5/26/09-5/29/09 Free release of material by R.P. 6/01/09-6/13/09 Backfill of trench: 6/1/09-6/5/09 Excavation of C.R.D. min flow line: 6/8/09-6/12/09 Inspection of pipe:6/15/09 Remove coating (contingent): 6/16/09 UT inspection (contingent): 6/17/09 Re-coat piping (contingent): 6/18/09-6/19/09 Backfill second excavation:6/22/09-6/26/09

Jim (Barstow Exelon Corporation TeamOysterCreek Oyster Creek Generating Station Regulatory Assurance Manager Office of the Site Vice President James. Barstow(ýexeloncorp.com Work - 609-971-4947 This e-mail and any of its attachments may contain Exelon Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Exelon Corporation family of Companies. This e-mail is intended solely for the use of the individual or entity to which it is addressed. If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or actionr taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful. If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout. Thank You.

  • 2