| issue date = 11/19/2009 | | issue date = 11/19/2009 | ||
| title = IR 05000400-09-201, on 04/03/2009, for Shearon Harris Nuclear Power Plant - Cover Letter | | title = IR 05000400-09-201, on 04/03/2009, for Shearon Harris Nuclear Power Plant - Cover Letter | ||
| author name = Shannon M | | author name = Shannon M | ||
| author affiliation = NRC/NSIR/DSO | | author affiliation = NRC/NSIR/DSO | ||
| addressee name = Burton C | | addressee name = Burton C | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter | {{#Wiki_filter:November 19, 2009 | ||
==SUBJECT:== | |||
SHEARON HARRIS NUCLEAR POWER PLANT-NRC SECURITY INSPECTION REPORT 05000400/2009201 | |||
SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT- NRC SECURITY INSPECTION REPORT 05000400/2009201 | |||
==Dear Mr. Burton:== | ==Dear Mr. Burton:== | ||
| Line 30: | Line 28: | ||
The enclosed inspection report documents the inspection results, which were discussed on November 19, 2009, with you and other members of your staff. | The enclosed inspection report documents the inspection results, which were discussed on November 19, 2009, with you and other members of your staff. | ||
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license | The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. | ||
Based on the results of this inspection, three findings, which are of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process (PPDSP) were identified. One finding has an associated cross-cutting area in Problem Identification and Resolution, within the area of Corrective Action Program under P1.c, | The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. | ||
Based on the results of this inspection, three findings, which are of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process (PPDSP) were identified. One finding has an associated cross-cutting area in Problem Identification and Resolution, within the area of Corrective Action Program under P1.c, Evaluates Problems because your staff failed to conduct an adequate review of the extent of condition affecting systems effectiveness to ensure regulatory compliance was met. Each of the three deficiencies were identified by the NRC. The deficiencies were promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site. | |||
However, because of the very low security significance and because they were entered into your corrective action program, the NRC is treating these violations as non-cited violations consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator Region I; Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector at the Shearon Harris Nuclear Power Plant. | However, because of the very low security significance and because they were entered into your corrective action program, the NRC is treating these violations as non-cited violations consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator Region I; Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector at the Shearon Harris Nuclear Power Plant. | ||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System | In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System | ||
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the | Enclosure contains Safeguards Information. Upon removal, this letter is decontrolled (PARS) component of NRC's Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. | ||
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide and acceptable response, please provide the level of protection described in 10 CFR 73.21. | |||
Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1). | |||
Should you have any questions concerning this inspection, we will be pleased to discuss them with you. | Should you have any questions concerning this inspection, we will be pleased to discuss them with you. | ||
Sincerely,/RA/ | Sincerely, | ||
/RA/ | |||
Michael P. Shannon, Chief, Acting Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response | |||
Docket No.: 50-400 License No.: NPF-63 | |||
Supplemental Information cc w/Encl: | |||
Enclosure: NRC Inspection Report No. 05000400/2009201(SGI) | |||
w/ Attachment: Supplemental Information | |||
cc w/Encl: | |||
R. J. Duncan, II Vice President Nuclear Operations Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 | R. J. Duncan, II Vice President Nuclear Operations Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 | ||
| Line 55: | Line 63: | ||
Shearon Harris Nuclear Power Plant P.O Box 165, Mail Zone 1 New Hill, NC 27562-0165 (PARS) component of NRC's Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. | Shearon Harris Nuclear Power Plant P.O Box 165, Mail Zone 1 New Hill, NC 27562-0165 (PARS) component of NRC's Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. | ||
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the | In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide and acceptable response, please provide the level of protection described in 10 CFR 73.21. | ||
Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1). | |||
Should you have any questions concerning this inspection, we will be pleased to discuss them with you. | Should you have any questions concerning this inspection, we will be pleased to discuss them with you. | ||
Sincerely,/RA/ Michael P. Shannon, Chief, Acting Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket No.: 50-400 License No.: NPF-63 | Sincerely, | ||
/RA/ | |||
Michael P. Shannon, Chief, Acting Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response | |||
Docket No.: 50-400 License No.: NPF-63 | |||
Enclosure: NRC Inspection Report No. 05000400/2009201(SGI) | |||
w/ Attachment: Supplemental Information | |||
Distribution w/encl: | |||
D. Brady, STSB M. Ernstes, R-II/DRS/PSB2 J. Austin, SRI Shearon Harris J. Curry, DDSO/DSO | |||
Distribution w/o encl: | |||
M Vaaler - NRR C. Adkison, PMDA | |||
Accession No. ML093240383 OFFICE TL:DSO/NSIR | |||
BC:RII | |||
SRI:Harris | |||
BC:DSO/NSIR | |||
NAME J. Willis M.Ernstes via e-mail | |||
J. Austin, via phone M. Shannon, Acting DATE 11/16/2009 11/18/2009 | |||
11/18/2009 11/19/2009 | |||
}} | }} | ||
Latest revision as of 08:10, 14 January 2025
| ML093240383 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 11/19/2009 |
| From: | Shannon M Division of Security Operations |
| To: | Burton C Carolina Power & Light Co |
| References | |
| IR-09-201 | |
| Download: ML093240383 (3) | |
Text
November 19, 2009
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT-NRC SECURITY INSPECTION REPORT 05000400/2009201
Dear Mr. Burton:
On April 3, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at the Shearon Harris Nuclear Power Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process.
The enclosed inspection report documents the inspection results, which were discussed on November 19, 2009, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, three findings, which are of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process (PPDSP) were identified. One finding has an associated cross-cutting area in Problem Identification and Resolution, within the area of Corrective Action Program under P1.c, Evaluates Problems because your staff failed to conduct an adequate review of the extent of condition affecting systems effectiveness to ensure regulatory compliance was met. Each of the three deficiencies were identified by the NRC. The deficiencies were promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site.
However, because of the very low security significance and because they were entered into your corrective action program, the NRC is treating these violations as non-cited violations consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator Region I; Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector at the Shearon Harris Nuclear Power Plant.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System
Enclosure contains Safeguards Information. Upon removal, this letter is decontrolled (PARS) component of NRC's Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide and acceptable response, please provide the level of protection described in 10 CFR 73.21.
Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/
Michael P. Shannon, Chief, Acting Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response
Docket No.: 50-400 License No.: NPF-63
Enclosure: NRC Inspection Report No. 05000400/2009201(SGI)
w/ Attachment: Supplemental Information
cc w/Encl:
R. J. Duncan, II Vice President Nuclear Operations Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
John C. Warner Manager Support Services Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant P.O Box 165, Mail Zone 1 New Hill, NC 27562-0165 (PARS) component of NRC's Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Reading Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide and acceptable response, please provide the level of protection described in 10 CFR 73.21.
Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/
Michael P. Shannon, Chief, Acting Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response
Docket No.: 50-400 License No.: NPF-63
Enclosure: NRC Inspection Report No. 05000400/2009201(SGI)
w/ Attachment: Supplemental Information
Distribution w/encl:
D. Brady, STSB M. Ernstes, R-II/DRS/PSB2 J. Austin, SRI Shearon Harris J. Curry, DDSO/DSO
Distribution w/o encl:
M Vaaler - NRR C. Adkison, PMDA
Accession No. ML093240383 OFFICE TL:DSO/NSIR
BC:RII
SRI:Harris
BC:DSO/NSIR
NAME J. Willis M.Ernstes via e-mail
J. Austin, via phone M. Shannon, Acting DATE 11/16/2009 11/18/2009
11/18/2009 11/19/2009