{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES  
                              NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION  
                                              REGION III
REGION III  
                                2443 WARRENVILLE ROAD, SUITE 210
2443 WARRENVILLE ROAD, SUITE 210  
                                        LISLE, IL 60532-4352
LISLE, IL 60532-4352  
                                            June 30, 2010
Mr. Christopher R. Costanzo
Vice President
June 30, 2010  
NextEra Energy Duane Arnold, LLC
3277 DAEC Road
Mr. Christopher R. Costanzo  
Palo, IA 52324-9785
Vice President  
SUBJECT:         DUANE ARNOLD ENERGY CENTER INFORMATION REQUEST FOR AN NRC
NextEra Energy Duane Arnold, LLC  
                TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59 (MOD/50.59)
3277 DAEC Road  
                BASELINE INSPECTION 05000331/2010-007(DRS)
Palo, IA 52324-9785  
Dear Mr. Costanzo:
SUBJECT:  
On September 13, 2010, the Nuclear Regulatory Commission (NRC) will begin a Permanent
DUANE ARNOLD ENERGY CENTER INFORMATION REQUEST FOR AN NRC  
Plant Modifications 10 CFR 50.59 (MOD/50.59) baseline inspection at your Duane Arnold
TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59 (MOD/50.59)  
Energy Center. This inspection will be performed in accordance with the NRC baseline
BASELINE INSPECTION 05000331/2010-007(DRS)  
Inspection Procedure IP 71111.17. The on-site portion of the inspection will take place on
Dear Mr. Costanzo:  
September 13 - 17, 2010, and September 27 - October 1, 2010.
On September 13, 2010, the Nuclear Regulatory Commission (NRC) will begin a Permanent  
Experience has shown that these baseline inspections are resource intensive, both for the NRC
Plant Modifications 10 CFR 50.59 (MOD/50.59) baseline inspection at your Duane Arnold  
inspectors and the licensee staff. In order to minimize the inspection impact on the site and to
Energy Center. This inspection will be performed in accordance with the NRC baseline  
ensure a productive inspection for both parties, we have enclosed a request for documents
Inspection Procedure IP 71111.17. The on-site portion of the inspection will take place on  
needed for the inspection. These documents have been divided into three groups. The first
September 13 - 17, 2010, and September 27 - October 1, 2010.  
group is necessary to ensure that the inspection team is adequately prepared for the inspection.
Experience has shown that these baseline inspections are resource intensive, both for the NRC  
This information should be made available via compact disc to the Regional Office no later than
inspectors and the licensee staff. In order to minimize the inspection impact on the site and to  
August 13, 2010. The inspection team will review this information and, by August 20, 2010, will
ensure a productive inspection for both parties, we have enclosed a request for documents  
request specific items (second group of documents requested) that should be available for
needed for the inspection. These documents have been divided into three groups. The first  
review by September 3, 2010. The third group lists information that should be available by the
group is necessary to ensure that the inspection team is adequately prepared for the inspection.
first day of the on-site inspection and/or is necessary to aid the inspection team in tracking
This information should be made available via compact disc to the Regional Office no later than  
issues identified as a result of the inspection. It is important that all of these documents are up
August 13, 2010. The inspection team will review this information and, by August 20, 2010, will  
to date and complete in order to minimize the number of additional documents requested during
request specific items (second group of documents requested) that should be available for  
the preparation and/or the on-site portions of the inspection.
review by September 3, 2010. The third group lists information that should be available by the  
The lead inspector for this inspection is Ms. Caroline Tilton. We understand that our regulatory
first day of the on-site inspection and/or is necessary to aid the inspection team in tracking  
contact for this inspection is Mr. B. Murell of your organization. If there are any questions about
issues identified as a result of the inspection. It is important that all of these documents are up  
the inspection or the material requested, please contact the lead inspector at (630) 829-9718 or
to date and complete in order to minimize the number of additional documents requested during  
the preparation and/or the on-site portions of the inspection.  
The lead inspector for this inspection is Ms. Caroline Tilton. We understand that our regulatory  
contact for this inspection is Mr. B. Murell of your organization. If there are any questions about  
the inspection or the material requested, please contact the lead inspector at (630) 829-9718 or  
via e-mail at caroline.tilton@nrc.gov.
via e-mail at caroline.tilton@nrc.gov.


C. Costanzo       -2-
C. Costanzo     -2-  
This letter does not contain new or amended information collection requirements subject to the
This letter does not contain new or amended information collection requirements subject to the  
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection  
requirements were approved by the Office of Management and Budget, control number 3150-
requirements were approved by the Office of Management and Budget, control number 3150-
0011.
0011.  
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for  
information or an information collection requirement unless the requesting document displays a
information or an information collection requirement unless the requesting document displays a  
currently valid Office of Management and Budget control number.
currently valid Office of Management and Budget control number.  
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and  
its enclosure will be available electronically for public inspection in the NRC Public Document
its enclosure will be available electronically for public inspection in the NRC Public Document  
Room or from the Publicly Available Records (PARS) component of NRC's document system
Room or from the Publicly Available Records (PARS) component of NRC's document system  
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
rm/adams.html (the Public Electronic Reading Room).  
                                                Sincerely,
Sincerely,  
                                                /RA/
                                                Robert C. Daley, Chief
/RA/  
                                                Engineering Branch 3
                                                Division of Reactor Safety
Robert C. Daley, Chief  
Docket No. 50-331
Engineering Branch 3  
License No. DPR-49
Division of Reactor Safety  
Enclosure:     Initial Document Request Modifications and 50.59 Inspection Document Request
Docket No. 50-331  
cc w/encl:     Distribution via ListServ
License No. DPR-49  
Enclosure:  
Initial Document Request Modifications and 50.59 Inspection Document Request  
cc w/encl:  
Distribution via ListServ  


        INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST
INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST  
Inspection Report:             05000331/2010007(DRS)
Inspection Dates:               September 13 - 17, 2010 and September 27 - October 1, 2010
Inspection Procedures:         IP 71111.17, Evaluation of Changes, Tests, or Experiments and
Enclosure
                                Permanent Plant Modifications
1
Lead Inspector:                 Caroline Tilton
Inspection Report:
                                (630) 829-9718
05000331/2010007(DRS)  
I.     Information Requested for In-Office Preparation Week
Inspection Dates:  
      The following information is requested by August 13, 2010, or sooner, to facilitate the
      selection of specific items that will be reviewed during the on-site inspection week. The
September 13 - 17, 2010 and September 27 - October 1, 2010  
      team will select specific items from the information requested below and submit a list to
Inspection Procedures:  
      your staff by August 20, 2010. We will request that certain items be made available to
IP 71111.17, Evaluation of Changes, Tests, or Experiments and  
      the regional office prior to the inspection by September 3, 2010. We request that the
Permanent Plant Modifications  
      remaining items selected from the lists be available and ready for review on the first day
Lead Inspector:
      of inspection. All requested information should cover the time frame from the receipt of
Caroline Tilton  
      information for the last Permanent Modification inspection on June 25, 2007, to the
(630) 829-9718  
      present. If you have any questions regarding this information, please call the lead
I.  
      inspector as soon as possible.
Information Requested for In-Office Preparation Week  
      (1)     List of permanent plant modifications to systems, structures, or components
The following information is requested by August 13, 2010, or sooner, to facilitate the  
              that are field work complete. (For the purpose of this inspection, permanent plant
selection of specific items that will be reviewed during the on-site inspection week. The  
              modifications include permanent: plant changes, design changes, set point
team will select specific items from the information requested below and submit a list to  
              changes, equivalency evaluations, suitability analyses, and commercial grade
your staff by August 20, 2010. We will request that certain items be made available to  
              dedications.)
the regional office prior to the inspection by September 3, 2010. We request that the  
              The list should contain the number of each document, the title, the revision (or
remaining items selected from the lists be available and ready for review on the first day  
              date), and the affected system. In addition to the list, please provide a
of inspection. All requested information should cover the time frame from the receipt of  
              description of each modification and a list of associated calculations and affected
information for the last Permanent Modification inspection on June 25, 2007, to the  
              procedures.
present. If you have any questions regarding this information, please call the lead  
      (2)     List of all 10 CFR 50.59 completed evaluations involving: (a) calculations;
inspector as soon as possible.  
              (b) procedure revisions; (c) changes to the facility (modifications); (d) non-routine
(1)  
              operating configurations; or (e) departures in methods of analyses. This list
List of permanent plant modifications to systems, structures, or components  
              should include 50.59 evaluations for the following:
that are field work complete. (For the purpose of this inspection, permanent plant  
                                                  1                                        Enclosure
modifications include permanent: plant changes, design changes, set point  
changes, equivalency evaluations, suitability analyses, and commercial grade  
dedications.)  
The list should contain the number of each document, the title, the revision (or  
date), and the affected system. In addition to the list, please provide a  
description of each modification and a list of associated calculations and affected  
procedures.
(2)  
List of all 10 CFR 50.59 completed evaluations involving: (a) calculations;
(b) procedure revisions; (c) changes to the facility (modifications); (d) non-routine  
operating configurations; or (e) departures in methods of analyses. This list  
should include 50.59 evaluations for the following:


    INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST
INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST  
      a.     Changes that have been made under the provisions of 10 CFR 50.59 that have
              been updated in accordance with 10 CFR 50.71(e)(4) since June 25, 2007;
      b.     Modifications that are field work complete; and
Enclosure
      c.     Changes to calculations (or initiation of new calculations) that have been
2
              issued.
a.  
              The list should contain the number and title of each document, a brief
Changes that have been made under the provisions of 10 CFR 50.59 that have  
              description of the change, and the corresponding number and type of the
been updated in accordance with 10 CFR 50.71(e)(4) since June 25, 2007;  
              affected document (i.e., the modification or procedure to which the evaluation
b.  
              applies). The list should NOT include any evaluations in which prior NRC
Modifications that are field work complete; and  
              approval was sought and obtained.
c.  
(3)   List of all 10 CFR 50.59 changes that have been screened out as not requiring a full
Changes to calculations (or initiation of new calculations) that have been  
      evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to the
issued.
      facility (modifications); (d) non-routine operating configurations; or (e) departures in
The list should contain the number and title of each document, a brief  
      methods of analyses.
description of the change, and the corresponding number and type of the  
      The list should contain the number and title of each document, a brief description of
affected document (i.e., the modification or procedure to which the evaluation  
      the change, and the corresponding number and type of the affected document (i.e.,
applies). The list should NOT include any evaluations in which prior NRC  
      the modification or procedure to which the evaluation applies).
approval was sought and obtained.  
(4)   List of any modifications, procedure revisions, or UFSAR changes where it was
(3)
      determined that 10 CFR 50.59 did not apply.
List of all 10 CFR 50.59 changes that have been screened out as not requiring a full  
(5)   List of calculation changes that have been issued for use.
evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to the  
(6)   List of corrective action documents (open and closed) that address plant permanent
facility (modifications); (d) non-routine operating configurations; or (e) departures in  
      modification or 10 CFR 50.59 issues, concerns, or processes. These documents
methods of analyses.  
      should also include corrective action documents associated with modification and
The list should contain the number and title of each document, a brief description of  
      MOD 50.59 change implementation.
the change, and the corresponding number and type of the affected document (i.e.,  
      The list should contain the number, title and revision (or date) of each document, the
the modification or procedure to which the evaluation applies).  
      affected system and corresponding documentation (if applicable), and should be
(4)
      sorted in order of significance,
List of any modifications, procedure revisions, or UFSAR changes where it was  
(7)   Copies of procedures addressing the following: modifications, design changes, set
determined that 10 CFR 50.59 did not apply.  
      point changes, equivalency evaluations or suitability analyses, commercial grade
(5)
      dedications, post-modification testing, 10 CFR 50.59 evaluation and screenings, and
List of calculation changes that have been issued for use.  
      UFSAR updates.
(6)
(8)   UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies
List of corrective action documents (open and closed) that address plant permanent  
      of the complete submittal.
modification or 10 CFR 50.59 issues, concerns, or processes. These documents  
(9)   Copy of the UFSAR change log (or a synopsis of changes). This should include
should also include corrective action documents associated with modification and  
      all of the changes made to the UFSAR that were incorporated in the last
MOD 50.59 change implementation.  
      10 CFR 50.71(e)(4) submittal.
(10)   Name(s) and phone numbers for the regulatory and technical contacts.
The list should contain the number, title and revision (or date) of each document, the  
                                              2                                      Enclosure
affected system and corresponding documentation (if applicable), and should be  
sorted in order of significance,
(7)
Copies of procedures addressing the following: modifications, design changes, set  
point changes, equivalency evaluations or suitability analyses, commercial grade  
dedications, post-modification testing, 10 CFR 50.59 evaluation and screenings, and  
UFSAR updates.  
(8)
UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies  
of the complete submittal.  
(9)
Copy of the UFSAR change log (or a synopsis of changes). This should include  
all of the changes made to the UFSAR that were incorporated in the last  
10 CFR 50.71(e)(4) submittal.  
(10)  
Name(s) and phone numbers for the regulatory and technical contacts.


          INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST
INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST  
    (11)   Current management and engineering organizational chart.
II.   Information Requested to be Provided Prior to Inspection. Request will be made by
      August 20, 2010 for availability of documents by September 3, 2010
Enclosure
      (1)   Copies of all selected items from Section I. This includes copies of associated
3
            documents such as calculations, post-modification test packages, 10 CFR 50.59
(11)  
            evaluations, or screenings, and any corrective action documents (need in Regional
Current management and engineering organizational chart.  
            Office by September 3, 2010).
II.  
III. Information Requested to be provided on the first day of on-site inspection
Information Requested to be Provided Prior to Inspection. Request will be made by  
      (September 13, 2010) and/or throughout the inspection
August 20, 2010 for availability of documents by September 3, 2010
      (1)   Copies of these documents do not need to be solely available to the team as long as
(1)
            the inspectors have easy and unrestrained access to them.
Copies of all selected items from Section I. This includes copies of associated  
            a.   Updated Final Safety Analysis Report;
documents such as calculations, post-modification test packages, 10 CFR 50.59  
            b.   Original FSAR Volumes;
evaluations, or screenings, and any corrective action documents (need in Regional  
            c.   Original SER and Supplements;
Office by September 3, 2010).  
            d.   FSAR Question and Answers;
III. Information Requested to be provided on the first day of on-site inspection  
            e.   Quality Assurance Plan;
(September 13, 2010) and/or throughout the inspection  
            f. Technical     Specifications;
(1)  
            g.   Latest IPE/PRA Report;
Copies of these documents do not need to be solely available to the team as long as  
            h.   Vendor Manuals; and
the inspectors have easy and unrestrained access to them.  
            i.   The Latest 10 CFR 50.59 FSAR Update Submittal.
a.  
    (2)     Please ensure that other supporting documents for the selected items have been
Updated Final Safety Analysis Report;  
            located and are readily retrievable as the team will likely be requesting these
b.  
            documents during the inspections. Examples of supporting documents are:
Original FSAR Volumes;  
            a.   Drawings supporting the modifications;
c.  
            b.   Procedures affected by the modifications; and
Original SER and Supplements;  
            c.   UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
d.  
    (3)     Assessment and Corrective Actions:
FSAR Question and Answers;  
            a.   The most recent modification (MOD)/50.59 Quality Assurance (QA) audit
e.  
                  and/or self-assessment; and
Quality Assurance Plan;  
            b.   Corrective action documents (e.g., condition reports, including status of
f. Technical  
                  corrective actions) generate as a result of the most recent MOD/50.59 Quality
Specifications;  
                  Assurance (QA) audit and/or self-assessment.
g.  
                                                3                                        Enclosure
Latest IPE/PRA Report;  
h.  
Vendor Manuals; and  
i.  
The Latest 10 CFR 50.59 FSAR Update Submittal.  
(2)
Please ensure that other supporting documents for the selected items have been  
located and are readily retrievable as the team will likely be requesting these  
documents during the inspections. Examples of supporting documents are:  
a.  
Drawings supporting the modifications;  
b.  
Procedures affected by the modifications; and  
c.  
UFSAR change papers generated due to a 10 CFR 50.59 evaluation.  
(3)  
Assessment and Corrective Actions:  
a.  
The most recent modification (MOD)/50.59 Quality Assurance (QA) audit  
and/or self-assessment; and  
b.  
Corrective action documents (e.g., condition reports, including status of  
corrective actions) generate as a result of the most recent MOD/50.59 Quality  
Assurance (QA) audit and/or self-assessment.  


              INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST
INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST  
    It is requested that the following two items be provided to the lead inspector as the information
    is generated during the inspection.
          (4)   Copies of any corrective action documents generated as a result of the teams
Enclosure
                questions or queries during this inspection.
4
          (5)   Copies of the list of questions submitted by the team members and the
It is requested that the following two items be provided to the lead inspector as the information  
                status/resolution of the information requested (provide daily during the inspection to
is generated during the inspection.  
                each team member).
(4)  
If you have questions regarding the information requested, please contact the lead inspector.
Copies of any corrective action documents generated as a result of the teams  
                                                      4                                      Enclosure
questions or queries during this inspection.  
(5)  
Copies of the list of questions submitted by the team members and the  
status/resolution of the information requested (provide daily during the inspection to  
each team member).  
If you have questions regarding the information requested, please contact the lead inspector.  


C. Costanzo                   -2-
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
C. Costanzo  
requirements were approved by the Office of Management and Budget, control number 3150-0011.
    -2-
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
information or an information collection requirement unless the requesting document displays a currently
This letter does not contain new or amended information collection requirements subject to  
valid Office of Management and Budget control number.
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection  
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure
requirements were approved by the Office of Management and Budget, control number 3150-0011.  
will be available electronically for public inspection in the NRC Public Document Room or from the
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for  
Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is
information or an information collection requirement unless the requesting document displays a currently  
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic
valid Office of Management and Budget control number.  
Reading Room).
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure  
                                                                                Sincerely,
will be available electronically for public inspection in the NRC Public Document Room or from the  
                                                                                /RA/
Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is  
                                                                                Robert C. Daley, Chief
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic  
                                                                                Engineering Branch 3
Reading Room).  
                                                                                Division of Reactor Safety
Sincerely,  
Docket No. 50-331
License No. DPR-49
/RA/  
Enclosure:                 Initial Document Request Modifications and 50.59 Inspection Document Request
Robert C. Daley, Chief  
cc w/encl:                 Distribution via ListServ
Engineering Branch 3  
DISTRIBUTION:
Division of Reactor Safety  
Susan Bagley
Docket No. 50-331  
RidsNrrDorlLpl3-1 Resource
License No. DPR-49  
RidsNrrPMDuaneArnold Resource
Enclosure:  
RidsNrrDirsIrib Resource
Initial Document Request Modifications and 50.59 Inspection Document Request  
Cynthia Pederson
cc w/encl:  
Steven Orth
Distribution via ListServ  
Jared Heck
DISTRIBUTION:  
Allan Barker
Susan Bagley  
Carole Ariano
RidsNrrDorlLpl3-1 Resource  
Linda Linn
RidsNrrPMDuaneArnold Resource  
DRPIII
RidsNrrDirsIrib Resource  
DRSIII
Cynthia Pederson  
Patricia Buckley
Steven Orth  
Tammy Tomczak
Jared Heck  
ROPreports Resource
Allan Barker  
DOCUMENT NAME: G:\DRS\WIP\Ltr. 06__10 Duane Arnold MOD 50.59 RFI CET.docx
Carole Ariano  
9 Publicly Available                     9 Non-Publicly Available                       9 Sensitive               9 Non-Sensitive
Linda Linn  
To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy
DRPIII  
OFFICE                             RIII                               RIII
DRSIII  
NAME                               CTilton:ls                         RCDaley
Patricia Buckley  
DATE                               06/25/10                           06/30/10
Tammy Tomczak  
                                                              OFFICIAL RECORD COPY
ROPreports Resource  
DOCUMENT NAME: G:\\DRS\\WIP\\Ltr. 06__10 Duane Arnold MOD 50.59 RFI CET.docx  
9 Publicly Available  
9 Non-Publicly Available       9 Sensitive       9   Non-Sensitive  
To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy  
OFFICE  
RIII  
RIII  
NAME  
CTilton:ls  
RCDaley  
DATE  
06/25/10  
06/30/10  
OFFICIAL RECORD COPY
}}
}}

Latest revision as of 04:20, 14 January 2025

Letter Duane Arnold Energy Center Information Requests for an NRC Triennal Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection 05000331-10-007(DRS)
ML101810132
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 06/30/2010
From: Robert Daley
Engineering Branch 3
To: Costanzo C
NextEra Energy Duane Arnold
References
IR-10-007
Download: ML101810132 (7)


See also: IR 05000331/2010007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

June 30, 2010

Mr. Christopher R. Costanzo

Vice President

NextEra Energy Duane Arnold, LLC

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT:

DUANE ARNOLD ENERGY CENTER INFORMATION REQUEST FOR AN NRC

TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59 (MOD/50.59)

BASELINE INSPECTION 05000331/2010-007(DRS)

Dear Mr. Costanzo:

On September 13, 2010, the Nuclear Regulatory Commission (NRC) will begin a Permanent

Plant Modifications 10 CFR 50.59 (MOD/50.59) baseline inspection at your Duane Arnold

Energy Center. This inspection will be performed in accordance with the NRC baseline

Inspection Procedure IP 71111.17. The on-site portion of the inspection will take place on

September 13 - 17, 2010, and September 27 - October 1, 2010.

Experience has shown that these baseline inspections are resource intensive, both for the NRC

inspectors and the licensee staff. In order to minimize the inspection impact on the site and to

ensure a productive inspection for both parties, we have enclosed a request for documents

needed for the inspection. These documents have been divided into three groups. The first

group is necessary to ensure that the inspection team is adequately prepared for the inspection.

This information should be made available via compact disc to the Regional Office no later than

August 13, 2010. The inspection team will review this information and, by August 20, 2010, will

request specific items (second group of documents requested) that should be available for

review by September 3, 2010. The third group lists information that should be available by the

first day of the on-site inspection and/or is necessary to aid the inspection team in tracking

issues identified as a result of the inspection. It is important that all of these documents are up

to date and complete in order to minimize the number of additional documents requested during

the preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Ms. Caroline Tilton. We understand that our regulatory

contact for this inspection is Mr. B. Murell of your organization. If there are any questions about

the inspection or the material requested, please contact the lead inspector at (630) 829-9718 or

via e-mail at caroline.tilton@nrc.gov.

C. Costanzo -2-

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011.

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a

currently valid Office of Management and Budget control number.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure:

Initial Document Request Modifications and 50.59 Inspection Document Request

cc w/encl:

Distribution via ListServ

INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST

Enclosure

1

Inspection Report: 05000331/2010007(DRS)

Inspection Dates:

September 13 - 17, 2010 and September 27 - October 1, 2010

Inspection Procedures:

IP 71111.17, Evaluation of Changes, Tests, or Experiments and

Permanent Plant Modifications

Lead Inspector:

Caroline Tilton

(630) 829-9718

I.

Information Requested for In-Office Preparation Week

The following information is requested by August 13, 2010, or sooner, to facilitate the

selection of specific items that will be reviewed during the on-site inspection week. The

team will select specific items from the information requested below and submit a list to

your staff by August 20, 2010. We will request that certain items be made available to

the regional office prior to the inspection by September 3, 2010. We request that the

remaining items selected from the lists be available and ready for review on the first day

of inspection. All requested information should cover the time frame from the receipt of

information for the last Permanent Modification inspection on June 25, 2007, to the

present. If you have any questions regarding this information, please call the lead

inspector as soon as possible.

(1)

List of permanent plant modifications to systems, structures, or components

that are field work complete. (For the purpose of this inspection, permanent plant

modifications include permanent: plant changes, design changes, set point

changes, equivalency evaluations, suitability analyses, and commercial grade

dedications.)

The list should contain the number of each document, the title, the revision (or

date), and the affected system. In addition to the list, please provide a

description of each modification and a list of associated calculations and affected

procedures.

(2)

List of all 10 CFR 50.59 completed evaluations involving: (a) calculations;

(b) procedure revisions; (c) changes to the facility (modifications); (d) non-routine

operating configurations; or (e) departures in methods of analyses. This list

should include 50.59 evaluations for the following:

INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST

Enclosure

2

a.

Changes that have been made under the provisions of 10 CFR 50.59 that have

been updated in accordance with 10 CFR 50.71(e)(4) since June 25, 2007;

b.

Modifications that are field work complete; and

c.

Changes to calculations (or initiation of new calculations) that have been

issued.

The list should contain the number and title of each document, a brief

description of the change, and the corresponding number and type of the

affected document (i.e., the modification or procedure to which the evaluation

applies). The list should NOT include any evaluations in which prior NRC

approval was sought and obtained.

(3)

List of all 10 CFR 50.59 changes that have been screened out as not requiring a full

evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to the

facility (modifications); (d) non-routine operating configurations; or (e) departures in

methods of analyses.

The list should contain the number and title of each document, a brief description of

the change, and the corresponding number and type of the affected document (i.e.,

the modification or procedure to which the evaluation applies).

(4)

List of any modifications, procedure revisions, or UFSAR changes where it was

determined that 10 CFR 50.59 did not apply.

(5)

List of calculation changes that have been issued for use.

(6)

List of corrective action documents (open and closed) that address plant permanent

modification or 10 CFR 50.59 issues, concerns, or processes. These documents

should also include corrective action documents associated with modification and

MOD 50.59 change implementation.

The list should contain the number, title and revision (or date) of each document, the

affected system and corresponding documentation (if applicable), and should be

sorted in order of significance,

(7)

Copies of procedures addressing the following: modifications, design changes, set

point changes, equivalency evaluations or suitability analyses, commercial grade

dedications, post-modification testing, 10 CFR 50.59 evaluation and screenings, and

UFSAR updates.

(8)

UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies

of the complete submittal.

(9)

Copy of the UFSAR change log (or a synopsis of changes). This should include

all of the changes made to the UFSAR that were incorporated in the last

10 CFR 50.71(e)(4) submittal.

(10)

Name(s) and phone numbers for the regulatory and technical contacts.

INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST

Enclosure

3

(11)

Current management and engineering organizational chart.

II.

Information Requested to be Provided Prior to Inspection. Request will be made by

August 20, 2010 for availability of documents by September 3, 2010

(1)

Copies of all selected items from Section I. This includes copies of associated

documents such as calculations, post-modification test packages, 10 CFR 50.59

evaluations, or screenings, and any corrective action documents (need in Regional

Office by September 3, 2010).

III. Information Requested to be provided on the first day of on-site inspection

(September 13, 2010) and/or throughout the inspection

(1)

Copies of these documents do not need to be solely available to the team as long as

the inspectors have easy and unrestrained access to them.

a.

Updated Final Safety Analysis Report;

b.

Original FSAR Volumes;

c.

Original SER and Supplements;

d.

FSAR Question and Answers;

e.

Quality Assurance Plan;

f. Technical

Specifications;

g.

Latest IPE/PRA Report;

h.

Vendor Manuals; and

i.

The Latest 10 CFR 50.59 FSAR Update Submittal.

(2)

Please ensure that other supporting documents for the selected items have been

located and are readily retrievable as the team will likely be requesting these

documents during the inspections. Examples of supporting documents are:

a.

Drawings supporting the modifications;

b.

Procedures affected by the modifications; and

c.

UFSAR change papers generated due to a 10 CFR 50.59 evaluation.

(3)

Assessment and Corrective Actions:

a.

The most recent modification (MOD)/50.59 Quality Assurance (QA) audit

and/or self-assessment; and

b.

Corrective action documents (e.g., condition reports, including status of

corrective actions) generate as a result of the most recent MOD/50.59 Quality

Assurance (QA) audit and/or self-assessment.

INITIAL MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST

Enclosure

4

It is requested that the following two items be provided to the lead inspector as the information

is generated during the inspection.

(4)

Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

(5)

Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection to

each team member).

If you have questions regarding the information requested, please contact the lead inspector.

C. Costanzo

-2-

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-0011.

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a currently

valid Office of Management and Budget control number.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure

will be available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic

Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure:

Initial Document Request Modifications and 50.59 Inspection Document Request

cc w/encl:

Distribution via ListServ

DISTRIBUTION:

Susan Bagley

RidsNrrDorlLpl3-1 Resource

RidsNrrPMDuaneArnold Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak

ROPreports Resource

DOCUMENT NAME: G:\\DRS\\WIP\\Ltr. 06__10 Duane Arnold MOD 50.59 RFI CET.docx

9 Publicly Available

9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive

To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy

OFFICE

RIII

RIII

NAME

CTilton:ls

RCDaley

DATE

06/25/10

06/30/10

OFFICIAL RECORD COPY