{{#Wiki_filter:August 18, 2010  
{{#Wiki_filter:August 18, 2010  
 
  Mr. Ross T. Ridenoure Senior Vice President and   Chief Nuclear Officer Southern California Edison Company San Onofre Nuclear Generating Station  
P.O. Box 128 San Clemente, CA  92674-0128  
  SUBJECT: SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000362005) AND REQUEST FOR INFORMATION  
  Dear Mr.Ridenoure:  
Mr. Ross T. Ridenoure  
  From November 29 to December 10, 2010, reactor inspectors from the U.S. Nuclear Regulatory  
Senior Vice President and
Commission's (NRC) Region IV office will perform the baseline inservice inspection at San Onofre Nuclear Generating Station Unit 3, using NRC Inspection Procedure 71111.08, "Inservice Inspection Activities," and TI 2515/172, "Reactor Coolant System Dissimilar Metal Butt Welds." Experience has shown that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.  In order to minimize the impact to your onsite resources  
  Chief Nuclear Officer  
and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.  These documents have been divided into two groups.  The first group, due by September 1, 2010, (Section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.  The second group (Section B of the enclosure) identifies the information the inspectors will need upon arrival at the site.  It is  
Southern California Edison Company  
important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.  
San Onofre Nuclear Generating Station  
  We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. Dave Axeline of your licensing organization.  Our inspection dates are subject to change based on your updated schedule of  
P.O. Box 128  
outage activities.  If there are any questions about this inspection or the material requested, please contact the lead inspector Jim Drake, at (817) 276-6558 or (James.Drake@nrc.gov).  This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection  
San Clemente, CA  92674-0128  
requirements were approved by the Office of Management and Budget, Control UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125  
   
Southern California Edison Company - 2 -
SUBJECT:  
Number 3150 0011.  The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 - NOTIFICATION  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
OF INSPECTION (NRC INSPECTION REPORT 05000362005) AND REQUEST  
  Sincerely,    /RA/  Gregory E. Werner, Chief
FOR INFORMATION  
Plant Support Branch 2  Division of Reactor Safety
   
Docket:  50-362 License:  NPF-15
Dear Mr.Ridenoure:  
   
From November 29 to December 10, 2010, reactor inspectors from the U.S. Nuclear Regulatory  
Commissions (NRC) Region IV office will perform the baseline inservice inspection at San  
Onofre Nuclear Generating Station Unit 3, using NRC Inspection Procedure 71111.08,  
Inservice Inspection Activities, and TI 2515/172, Reactor Coolant System Dissimilar Metal  
Butt Welds.  Experience has shown that this inspection is a resource intensive inspection both  
for the NRC inspectors and your staff.  In order to minimize the impact to your onsite resources  
and to ensure a productive inspection, we have enclosed a request for documents needed for  
this inspection.  These documents have been divided into two groups.  The first group, due by  
September 1, 2010, (Section A of the enclosure) identifies information to be provided prior to the  
inspection to ensure that the inspectors are adequately prepared.  The second group (Section B  
of the enclosure) identifies the information the inspectors will need upon arrival at the site.  It is  
important that all of these documents are up to date and complete in order to minimize the  
number of additional documents requested during the preparation and/or the onsite portions of  
the inspection.  
   
We have discussed the schedule for these inspection activities with your staff and understand  
that our regulatory contact for this inspection will be Mr. Dave Axeline of your licensing  
organization.  Our inspection dates are subject to change based on your updated schedule of  
outage activities.  If there are any questions about this inspection or the material requested,  
please contact the lead inspector Jim Drake, at (817) 276-6558 or (James.Drake@nrc.gov).  
   
This letter does not contain new or amended information collection requirements subject to the  
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection  
requirements were approved by the Office of Management and Budget, Control  
UNITED STATES
NUCLEAR REGULATORY COMMISSION
R E GI ON  I V
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125


  Enclosure: Inservice Inspection Document Request  
Southern California Edison Company
  Chairman, Board of Supervisors  
- 2 -
County of San Diego 1600 Pacific Highway, Room 335 San Diego, CA  92101  
  Gary L. Nolff  
Number 3150 0011.  The NRC may not conduct or sponsor, and a person is not required to
Assistant Director-Resources City of Riverside 3900 Main Street Riverside, CA  92522  
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
  /RA/
Gregory E. Werner, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket:  50-362
License:  NPF-15
   
Enclosure:  
Inservice Inspection Document Request  
   
Chairman, Board of Supervisors  
County of San Diego  
1600 Pacific Highway, Room 335  
San Diego, CA  92101  
   
Gary L. Nolff  
Assistant Director-Resources  
City of Riverside
3900 Main Street
Riverside, CA  92522
Mark L. Parsons
Deputy City Attorney
City of Riverside  
3900 Main Street  
Riverside, CA  92522  
Gary H. Yamamoto, P.E., Chief
Division of Drinking Water and 
  Environmental Management 
1616 Capitol Avenue, MS 7400
P.O. Box 997377
Sacramento, CA  95899-7377
   
   
Mark L. Parsons Deputy City Attorney City of Riverside 3900 Main Street Riverside, CA  92522
Gary H. Yamamoto, P.E., Chief
Division of Drinking Water and    Environmental Management  1616 Capitol Avenue, MS 7400 P.O. Box 997377 Sacramento, CA  95899-7377


 
Southern California Edison Company  
Southern California Edison Company - 3 -  
- 3 -  
  Michael L. DeMarco San Onofre Liaison San Diego Gas & Electric Company 8315 Century Park Ct. CP21C  
   
Michael L. DeMarco  
San Onofre Liaison  
San Diego Gas & Electric Company  
8315 Century Park Ct. CP21C  
San Diego, CA  92123-1548  
San Diego, CA  92123-1548  
  Director, Radiological Health Branch State Department of Health Services P.O. Box 997414 (MS 7610)  
   
Director, Radiological Health Branch  
State Department of Health Services  
P.O. Box 997414 (MS 7610)  
Sacramento, CA  95899-7414
The Mayor of the City of San Clemente
100 Avenida Presidio
San Clemente, CA  92672
James D. Boyd, Commissioner
California Energy Commission
1516 Ninth Street (MS 34)
Sacramento, CA  95814
Douglas K. Porter, Esquire
Southern California Edison Company
2244 Walnut Grove Avenue
Rosemead, CA  91770
Albert R. Hochevar
Southern California Edison Company
San Onofre Nuclear Generating Station
P.O. Box 128
San Clemente, CA  92674-0128
Steve Hsu
Department of Health Services
Radiologic Health Branch
MS 7610, P.O. Box 997414
Sacramento, CA  95899-7414  
Sacramento, CA  95899-7414  
The Mayor of the City of San Clemente 100 Avenida Presidio San Clemente, CA  92672
James D. Boyd, Commissioner
California Energy Commission 1516 Ninth Street (MS 34) Sacramento, CA  95814
Douglas K. Porter, Esquire
Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA  91770
Albert R. Hochevar
Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA  92674-0128
   
   
Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA  95899-7414
R. St. Onge
Southern California Edison Company
San Onofre Nuclear Generating Station
P.O. Box 128
San Clemente, CA  92674-0128
Chief, Technological Hazards Branch
FEMA Region IX
1111 Broadway, Suite 1200
Oakland, CA  94607-4052


R. St. Onge Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128
Southern California Edison Company  
- 4 -
Institute of Nuclear Power Operations (INPO) 
Records Center
700 Galleria Parkway SE, Suite 100
Atlanta, GA  30339
   
   
   
Chief, Technological Hazards Branch FEMA Region IX 1111 Broadway, Suite 1200 Oakland, CA  94607-4052
 
Southern California Edison Company - 4 -
Institute of Nuclear Power Operations (INPO)  Records Center 700 Galleria Parkway SE, Suite 100 Atlanta, GA  30339


Southern California Edison Company
- 5 -
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
Acting DRP Director (Tony.Vegel@nrc.gov)
Acting DRP Deputy Director (Troy.Pruett@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
Acting DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Greg.Warnick@nrc.gov)
Resident Inspector (John.Reynoso@nrc.gov)
Branch Chief, DRP/D (Ryan.Lantz@nrc.gov)
Senior Project Engineer, DRP/D (Don.Allen@nrc.gov)
SONGS Administrative Assistant (Heather.Hutchinson@nrc.gov)
Project Engineer, DRP/D (Peter.Jayroe@nrc.gov)
Project Engineer, DRP/D (Zachary.Hollcraft@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Randy.Hall@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
Inspection Reports/MidCycle and EOC Letters to the following:
ROPreports
Only inspection reports to the following:
DRS/TSB STA (Dale.Powers@nrc.gov)
OEDO RIV Coordinator (Margie.Kotzalas@nrc.gov)
SUNSI Review Completed:  ___Y___
ADAMS:  7 Yes
  No        Initials: ___JFD_ 
7  Publicly Available        Non-Publicly Available        Sensitive
7  Non-Sensitive
R:_Reactors/_SONGS/2010/2010005-LTR-JFD.docx                      ML 
RI:EB1
C:PSB2
JDrake
GWerner
8/16/2010
8/18/2010
OFFICIAL RECORD COPY  T=Telephone       
    
    
Southern California Edison Company - 5 -  
E=E-mail 
  Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Chuck.Casto@nrc.gov) Acting DRP Director (Tony.Vegel@nrc.gov)
Acting DRP Deputy Director (Troy.Pruett@nrc.gov) DRS Director (Roy.Caniano@nrc.gov) Acting DRS Deputy Director (Jeff.Clark@nrc.gov) Senior Resident Inspector (Greg.Warnick@nrc.gov) Resident Inspector (John.Reynoso@nrc.gov)
        F=Fax
Branch Chief, DRP/D (Ryan.Lantz@nrc.gov) Senior Project Engineer, DRP/D (Don.Allen@nrc.gov) SONGS Administrative Assistant (Heather.Hutchinson@nrc.gov) Project Engineer, DRP/D (Peter.Jayroe@nrc.gov) Project Engineer, DRP/D (Zachary.Hollcraft@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov)
 
Project Manager (Randy.Hall@nrc.gov) Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
  Inspection Reports/MidCycle and EOC Letters to the following: ROPreports
   
- 1 -
Enclosure
INSERVICE INSPECTION DOCUMENT REQUEST
   
Inspection Dates:  
November 29 through December 10, 2010
   
   
Only inspection reports to the following: DRS/TSB STA (Dale.Powers@nrc.gov) OEDO RIV Coordinator (Margie.Kotzalas@nrc.gov)  
Inspection Procedures:  
 
IP 71111.08 Inservice Inspection (ISI) Activities
   
TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds
SUNSI Review Completed:  ___Y___ ADAMS:  Yes  No        Initials: ___JFD_
    Publicly Available        Non-Publicly Available        Sensitive    Non-Sensitive
R:_Reactors/_SONGS/2010/2010005-LTR-JFD.docx                      ML  RI:EB1 C:PSB2    JDrake GWerner   
    8/16/2010 8/18/2010    OFFICIAL RECORD COPY  T=Telephone            E=E-mail            F=Fax 
  - 1 - Enclosure INSERVICE INSPECTION DOCUMENT REQUEST
  Inspection Dates: November 29 through December 10, 2010
   
   
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds"
Inspectors:  
Inspectors: J. Drake, Senior Reactor Inspector (Lead Inspector - ISI) S. Makor, Reactor Inspector  
J. Drake, Senior Reactor Inspector (Lead Inspector - ISI)  
S. Makor, Reactor Inspector  
A. Fairbanks, Reactor Inspector  
A. Fairbanks, Reactor Inspector  
    A. Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com preferred), in care of Jim Drake, by September 1, 2010, to facilitate the selection of specific items that will be reviewed
during the onsite inspection week.  The inspectors will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure).  We ask that the specific items selected from the lists be available and ready for review on the first day of inspection.  *Please provide requested documentation electronically if possible.  If requested documents are large and only hard copy formats are available, please inform the inspectors, and provide subject documentation during the first day of the onsite inspection.  If you have any questions regarding this information request, please call the inspector as soon as possible.
   
   
A.1 ISI/Welding Programs and Schedule Information
  a) A detailed schedule (including preliminary dates) of:  
  i)  Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME, Section XI, Risk Informed (if applicable), and augmented ISI programs during the upcoming outage.  
  Provide a status summary of the NDE inspection activities vs. the  
A.  
required inspection period percentages for this interval by category per ASME, Section XI, IWX-2400 (Do not provide separately if other documentation requested contains this information).  
Information Requested for the In-Office Preparation Week
  ii)  Reactor pressure vessel head examinations planned for the upcoming outage.  iii) Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope (if applicable).  
 
The following information should be sent to the Region IV office in hard copy or
  - 2 - Enclosure iv) Examinations planned as part of your Boric Acid Corrosion Control Program (Mode 3 walkdowns, bolted connection walkdowns, etc.).  
electronic format (ims.certrec.com preferred), in care of Jim Drake, by
  v) Welding activities that are scheduled to be completed during the upcoming outage (ASME, Class 1, 2, or 3 structures, systems, or  
September 1, 2010, to facilitate the selection of specific items that will be reviewed
during the onsite inspection week.  The inspectors will select specific items from the
information requested below and then request from your staff additional documents
needed during the onsite inspection week (Section B of this enclosure).  We ask that the
specific items selected from the lists be available and ready for review on the first day of
inspection.  *Please provide requested documentation electronically if possible.  If
requested documents are large and only hard copy formats are available, please inform
the inspectors, and provide subject documentation during the first day of the onsite
inspection.  If you have any questions regarding this information request, please call the
inspector as soon as possible.
A.1
ISI/Welding Programs and Schedule Information  
a)  
A detailed schedule (including preliminary dates) of:  
   
i)   
Nondestructive examinations (NDEs) planned for Class 1 & 2 systems  
and containment, performed as part of your ASME, Section XI, Risk  
Informed (if applicable), and augmented ISI programs during the  
upcoming outage.  
   
Provide a status summary of the NDE inspection activities vs. the  
required inspection period percentages for this interval by category per  
ASME, Section XI, IWX-2400 (Do not provide separately if other  
documentation requested contains this information).  
   
ii)   
Reactor pressure vessel head examinations planned for the upcoming  
outage.  
   
iii)  
Examinations planned for Alloy 82/182/600 components that are not  
included in the Section XI scope (if applicable).  
 
- 2 -  
Enclosure  
iv)  
Examinations planned as part of your Boric Acid Corrosion Control  
Program (Mode 3 walkdowns, bolted connection walkdowns, etc.).  
   
v)  
Welding activities that are scheduled to be completed during the  
upcoming outage (ASME, Class 1, 2, or 3 structures, systems, or  
components (SSCs)).  
components (SSCs)).  
  b) A copy of ASME, Section XI, Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations identified above.   
   
  c) A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate, Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code Class 1 and 2 systems since the beginning of the last refueling outage.  This should include the previous Section XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.  Also, include in the list the NDE reports with relevant conditions in the reactor pressure vessel head penetration nozzles that have been accepted for continued service.   
b)  
The list of NDE reports should include a brief description of the SSC where the relevant condition was identified.  
A copy of ASME, Section XI, Code Relief Requests and associated NRC Safety  
  d) A list with a brief description (e.g., system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1 and 2 systems which have been  
Evaluations applicable to the examinations identified above.   
fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage.   
  e) If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to  
be examined and the extent of the planned examination.  Also provide reference numbers for applicable procedures that will be used to conduct these examinations.  
c)  
  f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.  
A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate,  
  g)  A list of any temporary noncode repairs in service (e.g., pinhole leaks).  
Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code  
  h) Please provide copies of the most recent self-assessments for the ISI, Welding, and Alloy 600 programs.   
Class 1 and 2 systems since the beginning of the last refueling outage.  This  
  A.2 Reactor Pressure Vessel Head  
should include the previous Section XI pressure test(s) conducted during start up  
  a)  Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the  
and any evaluations associated with the results of the pressure tests.  Also,  
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02 and NRC Order EA-03-009.  Also, include examination scope expansion criteria and planned expansion sample sizes if relevant conditions are identified (if applicable).   
include in the list the NDE reports with relevant conditions in the reactor pressure  
  - 3 - Enclosure  
vessel head penetration nozzles that have been accepted for continued service.   
  b)  A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g., the specific industry or procedural standards which will be used to evaluate potential leakage and/or flaw indications).  
The list of NDE reports should include a brief description of the SSC where the  
  A.3 Boric Acid Corrosion Control Program
relevant condition was identified.  
  a)  Copy of the procedures that govern the scope, equipment, and implementation of the inspections required to identify boric acid leakage, and the procedures for  
   
d)  
A list with a brief description (e.g., system, material, pipe size, weld number, and  
NDE performed) of the welds in Code Class 1 and 2 systems which have been  
fabricated due to component repair/replacement activities since the beginning of  
the last refueling outage, or are planned to be fabricated this refueling outage.   
   
e)  
If reactor vessel weld examinations required by the ASME Code are scheduled to  
occur during the upcoming outage, provide a detailed description of the welds to  
be examined and the extent of the planned examination.  Also provide reference  
numbers for applicable procedures that will be used to conduct these  
examinations.  
   
f)  
Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of  
Section XI of the ASME Code that have been identified since the beginning of the  
last refueling outage.  
   
g)   
A list of any temporary noncode repairs in service (e.g., pinhole leaks).  
   
h)  
Please provide copies of the most recent self-assessments for the ISI, Welding,  
and Alloy 600 programs.   
   
A.2  
Reactor Pressure Vessel Head
a)   
Provide the detailed scope of the planned NDE of the reactor vessel head which  
identifies the types of NDE methods to be used on each specific part of the  
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02  
and NRC Order EA-03-009.  Also, include examination scope expansion criteria  
and planned expansion sample sizes if relevant conditions are identified (if  
applicable).  
 
   
- 3 -  
Enclosure  
   
b)   
A list of the standards and/or requirements that will be used to evaluate  
indications identified during NDE of the reactor vessel head (e.g., the specific  
industry or procedural standards which will be used to evaluate potential leakage  
and/or flaw indications).  
   
A.3  
Boric Acid Corrosion Control Program  
a)   
Copy of the procedures that govern the scope, equipment, and implementation of  
the inspections required to identify boric acid leakage, and the procedures for  
boric acid leakage/corrosion evaluation.  
boric acid leakage/corrosion evaluation.  
  b) Provide a list of leaks (including Code class of the components) that have been identified since the last refueling outage and associated corrective action documentation.  If during the last cycle, the unit was shutdown, provide documentation of containment walkdown inspections performed as part of the Boric Acid Corrosion Control Program.  
   
  c) Provide a copy of the most recent self-assessment performed for the Boric Acid Corrosion Control Program.  
b)  
  A.4 Steam Generator Tube (SGT) Inspections
Provide a list of leaks (including Code class of the components) that have been  
  a) A detailed schedule of:  
identified since the last refueling outage and associated corrective action  
  i)  SGT inspection, data analyses, and repair activities for the upcoming outage (if occurring).  
documentation.  If during the last cycle, the unit was shutdown, provide  
  ii)  Steam Generator (SG) secondary side inspection activities for the upcoming outage (if occurring).  
documentation of containment walkdown inspections performed as part of the  
  b) Provide a copy of your SG ISI Inspection Program and Plan.  Please include a copy of the Operational Assessment from last outage and a copy of the following documents as they become available:   
Boric Acid Corrosion Control Program.  
  i) Degradation Assessment ii) Condition Monitoring Assessment   
   
  c) If you are planning on modifying your technical specifications such that they are consistent with Technical Specification Task Force-449, provide copies of your correspondence with the NRC regarding deviations from the standard technical specifications.  
c)  
  d) Copy of SG history documentation given to vendors performing Eddy Current (ET) testing of the SGs during the upcoming outage.  
Provide a copy of the most recent self-assessment performed for the Boric Acid  
 
Corrosion Control Program.  
  - 4 - Enclosure e) Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy Current Technique Specification Sheets (ETSS).  Additionally, provide a copy of EPRI, Appendix H, ETSS Qualification Records.  
   
  f) Identify and quantify any SGT leakage experienced during the previous operating cycle.  Also provide documentation identifying which SG was leaking and corrective actions completed or planned for this condition (If applicable).  
A.4  
  g)  Provide past history of the condition and issues pertaining to the secondary side of the SG (including items such as loose parts, fouling, top of tube sheet  
Steam Generator Tube (SGT) Inspections  
a)  
A detailed schedule of:  
   
i)   
SGT inspection, data analyses, and repair activities for the upcoming  
outage (if occurring).  
   
ii)   
Steam Generator (SG) secondary side inspection activities for the  
upcoming outage (if occurring).  
   
b)  
Provide a copy of your SG ISI Inspection Program and Plan.  Please include a  
copy of the Operational Assessment from last outage and a copy of the following  
documents as they become available:   
   
i)  
Degradation Assessment  
ii)  
Condition Monitoring Assessment   
   
c)  
If you are planning on modifying your technical specifications such that they are  
consistent with Technical Specification Task Force-449, provide copies of your  
correspondence with the NRC regarding deviations from the standard technical  
specifications.  
   
d)  
Copy of SG history documentation given to vendors performing Eddy Current  
(ET) testing of the SGs during the upcoming outage.  
 
- 4 -  
Enclosure  
e)  
Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy  
Current Technique Specification Sheets (ETSS).  Additionally, provide a copy of  
EPRI, Appendix H, ETSS Qualification Records.  
   
f)  
Identify and quantify any SGT leakage experienced during the previous operating  
cycle.  Also provide documentation identifying which SG was leaking and  
corrective actions completed or planned for this condition (If applicable).  
   
g)   
Provide past history of the condition and issues pertaining to the secondary side  
of the SG (including items such as loose parts, fouling, top of tube sheet  
condition, crud removal amounts, etc.).  
condition, crud removal amounts, etc.).  
h) Provide copies of your most recent self-assessments of the SG monitoring, loose parts monitoring, and secondary side water chemistry control programs.
i) Indicate where the primary, secondary, and resolution analyses are scheduled to take place.
j) Provide a summary of the scope of the SGT examinations, including examination methods such as bobbin, rotating pancake, or plus point, and the percentage of tubes to be examined.  *Do not provide these documents separately if already included in other information requested.  A.5 Materials Reliability Program (MRP-139) Activities
  a) A list of, with verification, that the baseline inspections of all applicable Dissimilar Metal Butt Welds (DMBWs) have been completed by July 31 2010.
b) Verification that baseline inspection of hot-leg and cold-leg temperature DMBWs have been included in the inspection program and that the schedules for the baseline inspections are consistent with the baseline schedules in MRP-139.
c) A list and schedule (examination dates) of all DMBW examinations planned for the upcoming refueling outage.  If none are scheduled, then data from previous examinations should be available for review.
d) A list and schedule for any welding to be performed on DMBWs in the upcoming outage.  If no welding will be performed then records of previous welding on DMBWs and post-weld NDE documentation.
e) A list and schedule of any stress improvement activities planned for the upcoming refueling outage.  If none are scheduled then have qualification reports for any stress improvements previously performed.
f) Documentation and description of how the baseline and ISI specifications in MRP-139 are satisfied at your facility.
 
  - 5 - Enclosure g) A list of weld locations controlled by MRP-139, which includes the MRP-139 weld category, pre-mitigation volumetric examination date, type of mitigation or stress improvement, post-mitigation volumetric examination date, and plans for future MRP-139 required examinations.
   
   
A.6 Additional information related to all ISI activities
h)
  a)  A list with a brief description of ISI, Boric Acid Corrosion Control Program, and SGT inspection related issues (e.g., condition reports) entered into your corrective action program since the beginning of the last refueling outage (for  
Provide copies of your most recent self-assessments of the SG monitoring, loose
Unit 2).  For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/SGT examinations.  
parts monitoring, and secondary side water chemistry control programs.
  b)  Provide names and phone numbers for the following program leads:  
  ISI contacts (examination, planning) Containment Examinations RPVH Examinations Snubbers and Supports Repair and Replacement Program Manager  
i)
Licensing Contact Site Welding Engineer Boric Acid Corrosion Control Program SG Inspection Activities (site lead and vendor contact)  
Indicate where the primary, secondary, and resolution analyses are scheduled to
take place.
j)
Provide a summary of the scope of the SGT examinations, including examination
methods such as bobbin, rotating pancake, or plus point, and the percentage of
tubes to be examined.  *Do not provide these documents separately if already
included in other information requested. 
A.5
Materials Reliability Program (MRP-139) Activities
a)
A list of, with verification, that the baseline inspections of all applicable Dissimilar
Metal Butt Welds (DMBWs) have been completed by July 31 2010.
b)
Verification that baseline inspection of hot-leg and cold-leg temperature DMBWs
have been included in the inspection program and that the schedules for the
baseline inspections are consistent with the baseline schedules in MRP-139.
c)
A list and schedule (examination dates) of all DMBW examinations planned for
the upcoming refueling outage.  If none are scheduled, then data from previous
examinations should be available for review.
d)
A list and schedule for any welding to be performed on DMBWs in the upcoming
outage.  If no welding will be performed then records of previous welding on
DMBWs and post-weld NDE documentation.
e)
A list and schedule of any stress improvement activities planned for the
upcoming refueling outage.  If none are scheduled then have qualification reports
for any stress improvements previously performed.
f)
Documentation and description of how the baseline and ISI specifications in
MRP-139 are satisfied at your facility.
 
- 5 -
Enclosure
g)
A list of weld locations controlled by MRP-139, which includes the MRP-139 weld
category, pre-mitigation volumetric examination date, type of mitigation or stress
improvement, post-mitigation volumetric examination date, and plans for future
MRP-139 required examinations.
A.6  
Additional information related to all ISI activities  
a)   
A list with a brief description of ISI, Boric Acid Corrosion Control Program, and  
SGT inspection related issues (e.g., condition reports) entered into your  
corrective action program since the beginning of the last refueling outage (for  
Unit 2).  For example, a list based upon data base searches using key words  
related to piping or SG tube degradation such as: ISI, ASME Code, Section XI,  
NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in  
piping/SGT examinations.  
   
b)   
Provide names and phone numbers for the following program leads:  
   
ISI contacts (examination, planning)  
Containment Examinations  
RPVH Examinations  
Snubbers and Supports  
Repair and Replacement Program Manager  
Licensing Contact  
Site Welding Engineer  
Boric Acid Corrosion Control Program  
SG Inspection Activities (site lead and vendor contact)  
B.
Information to be provided onsite to the inspector(s) at the entrance meeting
(November 29, 2010).
B.1
ISI / Welding Programs and Schedule Information
a)
Updated schedules for ISI/NDE activities, including SGT inspections, planned
welding activities, and schedule showing contingency repair plans, if available.
   
   
B. Information to be provided onsite to the inspector(s) at the entrance meeting (November 29, 2010).
b)  
B.1 ISI / Welding Programs and Schedule Information
For ASME, Code Class 1 and 2 welds selected by the inspector from the lists  
  a) Updated schedules for ISI/NDE activities, including SGT inspections, planned welding activities, and schedule showing contingency repair plans, if available.
provided from Section A of this enclosure, provide copies of the following  
b) For ASME, Code Class 1 and 2 welds selected by the inspector from the lists provided from Section A of this enclosure, provide copies of the following  
documentation for each subject weld:  
documentation for each subject weld:  
  i) Weld data sheet (traveler)  
   
  ii) Weld configuration and system location  
i)  
  iii) Applicable Code edition and addenda for weldment  
Weld data sheet (traveler)  
   
ii)  
Weld configuration and system location  
   
iii)  
Applicable Code edition and addenda for weldment  
iv)
Applicable Code edition and addenda for welding procedures
v)
Applicable weld procedures used to fabricate the welds


  iv) Applicable Code edition and addenda for welding procedures
   
  v) Applicable weld procedures used to fabricate the welds  
   
  - 6 - Enclosure  
   
  vi) Copies of procedure qualification records supporting the weld procedures from B.1.b.v vii) Copies of mechanical test reports identified in the procedure qualification records above  
- 6 -  
  viii) Copies of the nonconformance reports for the selected welds (If applicable)  
Enclosure  
  ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed)  
   
  x) Copies of the preservice examination records for the selected welds  
vi)  
  xi) Copies of welder performance qualifications records applicable to the selected welds, including documentation that welder maintained proficiency in the applicable welding processes specified in the weld  
Copies of procedure qualification records supporting the weld procedures  
from B.1.b.v  
vii)  
Copies of mechanical test reports identified in the procedure qualification  
records above  
   
viii)  
Copies of the nonconformance reports for the selected welds (If  
applicable)  
   
ix)  
Radiographs of the selected welds and access to equipment to allow  
viewing radiographs (If RT was performed)  
   
x)  
Copies of the preservice examination records for the selected welds  
   
xi)  
Copies of welder performance qualifications records applicable to the  
selected welds, including documentation that welder maintained  
proficiency in the applicable welding processes specified in the weld  
procedures (at least 6 months prior to the date of subject work)  
procedures (at least 6 months prior to the date of subject work)  
  xii) Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable  
   
  c) For the ISI related corrective action issues selected by the inspector(s) from Section A of this enclosure, provide a copy of the corrective actions and supporting documentation.  
xii)  
  d) For the NDE reports with relevant conditions on Code Class 1 & 2 systems selected by the inspectors from Section A above, provide a copy of the  
Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable  
examination records, examiner qualification records, and associated corrective action documents.  
   
  e) A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.   
c)  
  f) For the NDEs selected by the inspectors from Section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures).  For ultrasonic examination procedures qualified in accordance with ASME Code, Section XI,  
For the ISI related corrective action issues selected by the inspector(s) from  
Appendix VIII, provide documentation supporting the procedure qualification (e.g., the EPRI performance demonstration qualification summary sheets).  Also, include qualification documentation of the specific equipment to be used (e.g.,. ultrasonic unit, cables, and transducers including serial numbers) and NDE personnel qualification records.  
Section A of this enclosure, provide a copy of the corrective actions and  
  B.2 Reactor Pressure Vessel Head (RPVH)
supporting documentation.  
  a) Provide the NDE personnel qualification records for the examiners who will perform examinations of the reactor pressure vessel head
   
 
d)  
  - 7 - Enclosure b) Provide drawings showing the following: (If a visual examination is planned for the upcoming refueling outage).
For the NDE reports with relevant conditions on Code Class 1 & 2 systems  
i) RPVH and CRDM nozzle configurations  ii) RPVH insulation configuration  
selected by the inspectors from Section A above, provide a copy of the  
  The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable. 
examination records, examiner qualification records, and associated corrective  
c) Copy of NDE reports from the last RPVH examination.
action documents.  
   
e)  
A copy of (or ready access to) most current revision of the ISI Program Manual  
and Plan for the current Interval.   
   
f)  
For the NDEs selected by the inspectors from Section A of this enclosure,  
provide copy of the NDE procedures used to perform the examinations (including  
calibration and flaw characterization/sizing procedures).  For ultrasonic  
examination procedures qualified in accordance with ASME Code, Section XI,  
Appendix VIII, provide documentation supporting the procedure qualification  
(e.g., the EPRI performance demonstration qualification summary sheets).  Also,  
include qualification documentation of the specific equipment to be used  
(e.g.,. ultrasonic unit, cables, and transducers including serial numbers) and NDE  
personnel qualification records.  
   
B.2  
Reactor Pressure Vessel Head (RPVH)
a)  
Provide the NDE personnel qualification records for the examiners who will  
perform examinations of the reactor pressure vessel head   
   


  d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95 percent minimum coverage required by NRC Order EA-03-009 (If a visual examination is planned for the upcoming refueling outage).  
   
  e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH.  If no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.   
  f)  Provide a copy of the updated calculation of effective degradation years (EDY) for the RPVH susceptibility ranking.  
  g)  Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the NDE equipment used for the RPVH examinations.  Also, identify any changes in equipment configurations used for the RPVH examinations which  
- 7 -
Enclosure
b)
Provide drawings showing the following: (If a visual examination is planned for
the upcoming refueling outage).
i)
RPVH and CRDM nozzle configurations 
ii)
RPVH insulation configuration 
The drawings listed above should include fabrication drawings for the nozzle attachment
welds as applicable. 
c)
Copy of NDE reports from the last RPVH examination.
d)  
Copy of evaluation or calculation demonstrating that the scope of the visual  
examination of the upper head will meet the 95 percent minimum coverage  
required by NRC Order EA-03-009 (If a visual examination is planned for the  
upcoming refueling outage).  
   
e)  
Provide a copy of the procedures that will be used to identify the source of any  
boric acid deposits identified on the RPVH.  If no explicit procedures exist which  
govern this activity, provide a description of the process to be followed including  
personnel responsibilities and expectations.   
   
f)   
Provide a copy of the updated calculation of effective degradation years (EDY)  
for the RPVH susceptibility ranking.  
   
g)   
Provide copy of the vendor qualification report(s) that demonstrates the detection  
capability of the NDE equipment used for the RPVH examinations.  Also, identify  
any changes in equipment configurations used for the RPVH examinations which  
differ from that used in the vendor qualification report(s).  
differ from that used in the vendor qualification report(s).  
B.3 Boric Acid Corrosion Control Program
  a) Provide boric acid walkdown inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections. 
b) Provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage.  Please include a status of corrective
actions to repair and/or clean these boric acid leaks.  Please identify specifically which known leaks, if any, have remained in service or will remain in service as active leaks. 
B.4 SGT Inspections
  a) Copies of the Examination Technique Specification Sheets (ETSS) and associated justification for any revisions.
b) Copy of the guidance to be followed if a loose part or foreign material is identified in the SGs. 
  - 8 - Enclosure
c) Provide a copy of the ET procedures used to perform the SGT inspections (specifically calibration and flaw characterization/sizing procedures, etc.).  Also include documentation for the specific equipment to be used.
   
   
d) Provide copies of your responses to NRC and industry operating experience communications such as Generic Letters, Information Notices, etc. (as applicable to SGT inspections)  *Do not provide these documents separately if already included in other information requested such as the degradation assessment.   
B.3
e) List of corrective action documents generated by the vendor and/or site with respect to SG inspection activities.  
Boric Acid Corrosion Control Program 
  B.5 Codes and Standards
  a) Ready access to (i.e., copies provided to the inspector(s) for use during the inspection at the onsite inspection location, or room number and location where  
a)
Provide boric acid walkdown inspection results, an updated list of boric acid leaks
identified so far this outage, associated corrective action documentation, and
overall status of planned boric acid inspections. 
b)
Provide any engineering evaluations completed for boric acid leaks identified
since the end of the last refueling outage.  Please include a status of corrective
actions to repair and/or clean these boric acid leaks.  Please identify specifically
which known leaks, if any, have remained in service or will remain in service as
active leaks. 
B.4
SGT Inspections
a)
Copies of the Examination Technique Specification Sheets (ETSS) and
associated justification for any revisions.
b)
Copy of the guidance to be followed if a loose part or foreign material is identified
in the SGs.
 
- 8 -
Enclosure
c)
Provide a copy of the ET procedures used to perform the SGT inspections
(specifically calibration and flaw characterization/sizing procedures, etc.).  Also
include documentation for the specific equipment to be used.
d)  
Provide copies of your responses to NRC and industry operating experience  
communications such as Generic Letters, Information Notices, etc. (as applicable  
to SGT inspections)  *Do not provide these documents separately if already  
included in other information requested such as the degradation assessment.  
   
e)  
List of corrective action documents generated by the vendor and/or site with  
respect to SG inspection activities.  
B.5  
Codes and Standards  
a)  
Ready access to (i.e., copies provided to the inspector(s) for use during the  
inspection at the onsite inspection location, or room number and location where  
available):  
available):  
i)  Applicable Editions of the ASME Code, Sections V, IX and XI for the ISI program and the repair/replacement program. 
   
   
ii)  EPRI and industry standards referenced in the procedures used to perform the SGT Eddy Current examination.  
i) 
  Inspector Contact Information:  
Applicable Editions of the ASME Code, Sections V, IX and XI for the ISI
program and the repair/replacement program. 
ii)   
EPRI and industry standards referenced in the procedures used to  
perform the SGT Eddy Current examination.  
   
Inspector Contact Information:  
Jim Drake
Abin Fairbanks
Shiattin Makor 
Senior Reactor Inspector
Reactor Inspector
Reactor Inspector
817-276-6558
817-860-8158
817-276-6507
James.Drake@nrc.gov 
Abin.Fairbanks@nrc.gov
Shiattin.Makor@nrc.gov
   
   
Jim Drake Abin Fairbanks Shiattin Makor  Senior Reactor Inspector Reactor Inspector Reactor Inspector 817-276-6558 817-860-8158 817-276-6507 James.Drake@nrc.gov  Abin.Fairbanks@nrc.gov
Mailing Address:  
Shiattin.Makor@nrc.gov
US NRC Region IV  
 
Attn: Jim Drake  
Mailing Address: US NRC Region IV Attn: Jim Drake 612 E. Lamar Blvd, Suite 400 Arlington, TX 76011
612 E. Lamar Blvd, Suite 400  
Arlington, TX 76011
}}
}}

Latest revision as of 03:18, 14 January 2025

Notification of Inspection (NRC Inspection Report 05000362005) and Request for Information
ML102300672
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 08/18/2010
From: Greg Werner
NRC/RGN-IV/DRS/PSB-2
To: Ridenoure R
Southern California Edison Co
References
Download: ML102300672 (13)


See also: IR 05000036/2020005

Text

August 18, 2010

Mr. Ross T. Ridenoure

Senior Vice President and

Chief Nuclear Officer

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 - NOTIFICATION

OF INSPECTION (NRC INSPECTION REPORT 05000362005) AND REQUEST

FOR INFORMATION

Dear Mr.Ridenoure:

From November 29 to December 10, 2010, reactor inspectors from the U.S. Nuclear Regulatory

Commissions (NRC) Region IV office will perform the baseline inservice inspection at San

Onofre Nuclear Generating Station Unit 3, using NRC Inspection Procedure 71111.08,

Inservice Inspection Activities, and TI 2515/172, Reactor Coolant System Dissimilar Metal

Butt Welds. Experience has shown that this inspection is a resource intensive inspection both

for the NRC inspectors and your staff. In order to minimize the impact to your onsite resources

and to ensure a productive inspection, we have enclosed a request for documents needed for

this inspection. These documents have been divided into two groups. The first group, due by

September 1, 2010, (Section A of the enclosure) identifies information to be provided prior to the

inspection to ensure that the inspectors are adequately prepared. The second group (Section B

of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is

important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Mr. Dave Axeline of your licensing

organization. Our inspection dates are subject to change based on your updated schedule of

outage activities. If there are any questions about this inspection or the material requested,

please contact the lead inspector Jim Drake, at (817) 276-6558 or (James.Drake@nrc.gov).

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Southern California Edison Company

- 2 -

Number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Gregory E. Werner, Chief

Plant Support Branch 2

Division of Reactor Safety

Docket: 50-362

License: NPF-15

Enclosure:

Inservice Inspection Document Request

Chairman, Board of Supervisors

County of San Diego

1600 Pacific Highway, Room 335

San Diego, CA 92101

Gary L. Nolff

Assistant Director-Resources

City of Riverside

3900 Main Street

Riverside, CA 92522

Mark L. Parsons

Deputy City Attorney

City of Riverside

3900 Main Street

Riverside, CA 92522

Gary H. Yamamoto, P.E., Chief

Division of Drinking Water and

Environmental Management

1616 Capitol Avenue, MS 7400

P.O. Box 997377

Sacramento, CA 95899-7377

Southern California Edison Company

- 3 -

Michael L. DeMarco

San Onofre Liaison

San Diego Gas & Electric Company

8315 Century Park Ct. CP21C

San Diego, CA 92123-1548

Director, Radiological Health Branch

State Department of Health Services

P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414

The Mayor of the City of San Clemente

100 Avenida Presidio

San Clemente, CA 92672

James D. Boyd, Commissioner

California Energy Commission

1516 Ninth Street (MS 34)

Sacramento, CA 95814

Douglas K. Porter, Esquire

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, CA 91770

Albert R. Hochevar

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Steve Hsu

Department of Health Services

Radiologic Health Branch

MS 7610, P.O. Box 997414

Sacramento, CA 95899-7414

R. St. Onge

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Chief, Technological Hazards Branch

FEMA Region IX

1111 Broadway, Suite 1200

Oakland, CA 94607-4052

Southern California Edison Company

- 4 -

Institute of Nuclear Power Operations (INPO)

Records Center

700 Galleria Parkway SE, Suite 100

Atlanta, GA 30339

Southern California Edison Company

- 5 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

Acting DRP Director (Tony.Vegel@nrc.gov)

Acting DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

Acting DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Greg.Warnick@nrc.gov)

Resident Inspector (John.Reynoso@nrc.gov)

Branch Chief, DRP/D (Ryan.Lantz@nrc.gov)

Senior Project Engineer, DRP/D (Don.Allen@nrc.gov)

SONGS Administrative Assistant (Heather.Hutchinson@nrc.gov)

Project Engineer, DRP/D (Peter.Jayroe@nrc.gov)

Project Engineer, DRP/D (Zachary.Hollcraft@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Randy.Hall@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

Inspection Reports/MidCycle and EOC Letters to the following:

ROPreports

Only inspection reports to the following:

DRS/TSB STA (Dale.Powers@nrc.gov)

OEDO RIV Coordinator (Margie.Kotzalas@nrc.gov)

SUNSI Review Completed: ___Y___

ADAMS: 7 Yes

No Initials: ___JFD_

7 Publicly Available Non-Publicly Available Sensitive

7 Non-Sensitive

R:_Reactors/_SONGS/2010/2010005-LTR-JFD.docx ML

RI:EB1

C:PSB2

JDrake

GWerner

8/16/2010

8/18/2010

OFFICIAL RECORD COPY T=Telephone

E=E-mail

F=Fax

- 1 -

Enclosure

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates:

November 29 through December 10, 2010

Inspection Procedures:

IP 71111.08 Inservice Inspection (ISI) Activities

TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds

Inspectors:

J. Drake, Senior Reactor Inspector (Lead Inspector - ISI)

S. Makor, Reactor Inspector

A. Fairbanks, Reactor Inspector

A.

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or

electronic format (ims.certrec.com preferred), in care of Jim Drake, by

September 1, 2010, to facilitate the selection of specific items that will be reviewed

during the onsite inspection week. The inspectors will select specific items from the

information requested below and then request from your staff additional documents

needed during the onsite inspection week (Section B of this enclosure). We ask that the

specific items selected from the lists be available and ready for review on the first day of

inspection. *Please provide requested documentation electronically if possible. If

requested documents are large and only hard copy formats are available, please inform

the inspectors, and provide subject documentation during the first day of the onsite

inspection. If you have any questions regarding this information request, please call the

inspector as soon as possible.

A.1

ISI/Welding Programs and Schedule Information

a)

A detailed schedule (including preliminary dates) of:

i)

Nondestructive examinations (NDEs) planned for Class 1 & 2 systems

and containment, performed as part of your ASME,Section XI, Risk

Informed (if applicable), and augmented ISI programs during the

upcoming outage.

Provide a status summary of the NDE inspection activities vs. the

required inspection period percentages for this interval by category per

ASME,Section XI, IWX-2400 (Do not provide separately if other

documentation requested contains this information).

ii)

Reactor pressure vessel head examinations planned for the upcoming

outage.

iii)

Examinations planned for Alloy 82/182/600 components that are not

included in the Section XI scope (if applicable).

- 2 -

Enclosure

iv)

Examinations planned as part of your Boric Acid Corrosion Control

Program (Mode 3 walkdowns, bolted connection walkdowns, etc.).

v)

Welding activities that are scheduled to be completed during the

upcoming outage (ASME, Class 1, 2, or 3 structures, systems, or

components (SSCs)).

b)

A copy of ASME,Section XI, Code Relief Requests and associated NRC Safety

Evaluations applicable to the examinations identified above.

c)

A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate,

Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code

Class 1 and 2 systems since the beginning of the last refueling outage. This

should include the previousSection XI pressure test(s) conducted during start up

and any evaluations associated with the results of the pressure tests. Also,

include in the list the NDE reports with relevant conditions in the reactor pressure

vessel head penetration nozzles that have been accepted for continued service.

The list of NDE reports should include a brief description of the SSC where the

relevant condition was identified.

d)

A list with a brief description (e.g., system, material, pipe size, weld number, and

NDE performed) of the welds in Code Class 1 and 2 systems which have been

fabricated due to component repair/replacement activities since the beginning of

the last refueling outage, or are planned to be fabricated this refueling outage.

e)

If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to

be examined and the extent of the planned examination. Also provide reference

numbers for applicable procedures that will be used to conduct these

examinations.

f)

Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of

Section XI of the ASME Code that have been identified since the beginning of the

last refueling outage.

g)

A list of any temporary noncode repairs in service (e.g., pinhole leaks).

h)

Please provide copies of the most recent self-assessments for the ISI, Welding,

and Alloy 600 programs.

A.2

Reactor Pressure Vessel Head

a)

Provide the detailed scope of the planned NDE of the reactor vessel head which

identifies the types of NDE methods to be used on each specific part of the

vessel head to fulfill commitments made in response to NRC Bulletin 2002-02

and NRC Order EA-03-009. Also, include examination scope expansion criteria

and planned expansion sample sizes if relevant conditions are identified (if

applicable).

- 3 -

Enclosure

b)

A list of the standards and/or requirements that will be used to evaluate

indications identified during NDE of the reactor vessel head (e.g., the specific

industry or procedural standards which will be used to evaluate potential leakage

and/or flaw indications).

A.3

Boric Acid Corrosion Control Program

a)

Copy of the procedures that govern the scope, equipment, and implementation of

the inspections required to identify boric acid leakage, and the procedures for

boric acid leakage/corrosion evaluation.

b)

Provide a list of leaks (including Code class of the components) that have been

identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the unit was shutdown, provide

documentation of containment walkdown inspections performed as part of the

Boric Acid Corrosion Control Program.

c)

Provide a copy of the most recent self-assessment performed for the Boric Acid

Corrosion Control Program.

A.4

Steam Generator Tube (SGT) Inspections

a)

A detailed schedule of:

i)

SGT inspection, data analyses, and repair activities for the upcoming

outage (if occurring).

ii)

Steam Generator (SG) secondary side inspection activities for the

upcoming outage (if occurring).

b)

Provide a copy of your SG ISI Inspection Program and Plan. Please include a

copy of the Operational Assessment from last outage and a copy of the following

documents as they become available:

i)

Degradation Assessment

ii)

Condition Monitoring Assessment

c)

If you are planning on modifying your technical specifications such that they are

consistent with Technical Specification Task Force-449, provide copies of your

correspondence with the NRC regarding deviations from the standard technical

specifications.

d)

Copy of SG history documentation given to vendors performing Eddy Current

(ET) testing of the SGs during the upcoming outage.

- 4 -

Enclosure

e)

Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy

Current Technique Specification Sheets (ETSS). Additionally, provide a copy of

EPRI, Appendix H, ETSS Qualification Records.

f)

Identify and quantify any SGT leakage experienced during the previous operating

cycle. Also provide documentation identifying which SG was leaking and

corrective actions completed or planned for this condition (If applicable).

g)

Provide past history of the condition and issues pertaining to the secondary side

of the SG (including items such as loose parts, fouling, top of tube sheet

condition, crud removal amounts, etc.).

h)

Provide copies of your most recent self-assessments of the SG monitoring, loose

parts monitoring, and secondary side water chemistry control programs.

i)

Indicate where the primary, secondary, and resolution analyses are scheduled to

take place.

j)

Provide a summary of the scope of the SGT examinations, including examination

methods such as bobbin, rotating pancake, or plus point, and the percentage of

tubes to be examined. *Do not provide these documents separately if already

included in other information requested.

A.5

Materials Reliability Program (MRP-139) Activities

a)

A list of, with verification, that the baseline inspections of all applicable Dissimilar

Metal Butt Welds (DMBWs) have been completed by July 31 2010.

b)

Verification that baseline inspection of hot-leg and cold-leg temperature DMBWs

have been included in the inspection program and that the schedules for the

baseline inspections are consistent with the baseline schedules in MRP-139.

c)

A list and schedule (examination dates) of all DMBW examinations planned for

the upcoming refueling outage. If none are scheduled, then data from previous

examinations should be available for review.

d)

A list and schedule for any welding to be performed on DMBWs in the upcoming

outage. If no welding will be performed then records of previous welding on

DMBWs and post-weld NDE documentation.

e)

A list and schedule of any stress improvement activities planned for the

upcoming refueling outage. If none are scheduled then have qualification reports

for any stress improvements previously performed.

f)

Documentation and description of how the baseline and ISI specifications in

MRP-139 are satisfied at your facility.

- 5 -

Enclosure

g)

A list of weld locations controlled by MRP-139, which includes the MRP-139 weld

category, pre-mitigation volumetric examination date, type of mitigation or stress

improvement, post-mitigation volumetric examination date, and plans for future

MRP-139 required examinations.

A.6

Additional information related to all ISI activities

a)

A list with a brief description of ISI, Boric Acid Corrosion Control Program, and

SGT inspection related issues (e.g., condition reports) entered into your

corrective action program since the beginning of the last refueling outage (for

Unit 2). For example, a list based upon data base searches using key words

related to piping or SG tube degradation such as: ISI, ASME Code,Section XI,

NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in

piping/SGT examinations.

b)

Provide names and phone numbers for the following program leads:

ISI contacts (examination, planning)

Containment Examinations

RPVH Examinations

Snubbers and Supports

Repair and Replacement Program Manager

Licensing Contact

Site Welding Engineer

Boric Acid Corrosion Control Program

SG Inspection Activities (site lead and vendor contact)

B.

Information to be provided onsite to the inspector(s) at the entrance meeting

(November 29, 2010).

B.1

ISI / Welding Programs and Schedule Information

a)

Updated schedules for ISI/NDE activities, including SGT inspections, planned

welding activities, and schedule showing contingency repair plans, if available.

b)

For ASME, Code Class 1 and 2 welds selected by the inspector from the lists

provided from Section A of this enclosure, provide copies of the following

documentation for each subject weld:

i)

Weld data sheet (traveler)

ii)

Weld configuration and system location

iii)

Applicable Code edition and addenda for weldment

iv)

Applicable Code edition and addenda for welding procedures

v)

Applicable weld procedures used to fabricate the welds

- 6 -

Enclosure

vi)

Copies of procedure qualification records supporting the weld procedures

from B.1.b.v

vii)

Copies of mechanical test reports identified in the procedure qualification

records above

viii)

Copies of the nonconformance reports for the selected welds (If

applicable)

ix)

Radiographs of the selected welds and access to equipment to allow

viewing radiographs (If RT was performed)

x)

Copies of the preservice examination records for the selected welds

xi)

Copies of welder performance qualifications records applicable to the

selected welds, including documentation that welder maintained

proficiency in the applicable welding processes specified in the weld

procedures (at least 6 months prior to the date of subject work)

xii)

Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable

c)

For the ISI related corrective action issues selected by the inspector(s) from

Section A of this enclosure, provide a copy of the corrective actions and

supporting documentation.

d)

For the NDE reports with relevant conditions on Code Class 1 & 2 systems

selected by the inspectors from Section A above, provide a copy of the

examination records, examiner qualification records, and associated corrective

action documents.

e)

A copy of (or ready access to) most current revision of the ISI Program Manual

and Plan for the current Interval.

f)

For the NDEs selected by the inspectors from Section A of this enclosure,

provide copy of the NDE procedures used to perform the examinations (including

calibration and flaw characterization/sizing procedures). For ultrasonic

examination procedures qualified in accordance with ASME Code,Section XI,

Appendix VIII, provide documentation supporting the procedure qualification

(e.g., the EPRI performance demonstration qualification summary sheets). Also,

include qualification documentation of the specific equipment to be used

(e.g.,. ultrasonic unit, cables, and transducers including serial numbers) and NDE

personnel qualification records.

B.2

Reactor Pressure Vessel Head (RPVH)

a)

Provide the NDE personnel qualification records for the examiners who will

perform examinations of the reactor pressure vessel head

- 7 -

Enclosure

b)

Provide drawings showing the following: (If a visual examination is planned for

the upcoming refueling outage).

i)

RPVH and CRDM nozzle configurations

ii)

RPVH insulation configuration

The drawings listed above should include fabrication drawings for the nozzle attachment

welds as applicable.

c)

Copy of NDE reports from the last RPVH examination.

d)

Copy of evaluation or calculation demonstrating that the scope of the visual

examination of the upper head will meet the 95 percent minimum coverage

required by NRC Order EA-03-009 (If a visual examination is planned for the

upcoming refueling outage).

e)

Provide a copy of the procedures that will be used to identify the source of any

boric acid deposits identified on the RPVH. If no explicit procedures exist which

govern this activity, provide a description of the process to be followed including

personnel responsibilities and expectations.

f)

Provide a copy of the updated calculation of effective degradation years (EDY)

for the RPVH susceptibility ranking.

g)

Provide copy of the vendor qualification report(s) that demonstrates the detection

capability of the NDE equipment used for the RPVH examinations. Also, identify

any changes in equipment configurations used for the RPVH examinations which

differ from that used in the vendor qualification report(s).

B.3

Boric Acid Corrosion Control Program

a)

Provide boric acid walkdown inspection results, an updated list of boric acid leaks

identified so far this outage, associated corrective action documentation, and

overall status of planned boric acid inspections.

b)

Provide any engineering evaluations completed for boric acid leaks identified

since the end of the last refueling outage. Please include a status of corrective

actions to repair and/or clean these boric acid leaks. Please identify specifically

which known leaks, if any, have remained in service or will remain in service as

active leaks.

B.4

SGT Inspections

a)

Copies of the Examination Technique Specification Sheets (ETSS) and

associated justification for any revisions.

b)

Copy of the guidance to be followed if a loose part or foreign material is identified

in the SGs.

- 8 -

Enclosure

c)

Provide a copy of the ET procedures used to perform the SGT inspections

(specifically calibration and flaw characterization/sizing procedures, etc.). Also

include documentation for the specific equipment to be used.

d)

Provide copies of your responses to NRC and industry operating experience

communications such as Generic Letters, Information Notices, etc. (as applicable

to SGT inspections) *Do not provide these documents separately if already

included in other information requested such as the degradation assessment.

e)

List of corrective action documents generated by the vendor and/or site with

respect to SG inspection activities.

B.5

Codes and Standards

a)

Ready access to (i.e., copies provided to the inspector(s) for use during the

inspection at the onsite inspection location, or room number and location where

available):

i)

Applicable Editions of the ASME Code, Sections V, IX and XI for the ISI

program and the repair/replacement program.

ii)

EPRI and industry standards referenced in the procedures used to

perform the SGT Eddy Current examination.

Inspector Contact Information:

Jim Drake

Abin Fairbanks

Shiattin Makor

Senior Reactor Inspector

Reactor Inspector

Reactor Inspector

817-276-6558

817-860-8158

817-276-6507

James.Drake@nrc.gov

Abin.Fairbanks@nrc.gov

Shiattin.Makor@nrc.gov

Mailing Address:

US NRC Region IV

Attn: Jim Drake

612 E. Lamar Blvd, Suite 400

Arlington, TX 76011