ML103300217: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (3 intermediate revisions by the same user not shown) | |||
| Line 13: | Line 13: | ||
| page count = 6 | | page count = 6 | ||
}} | }} | ||
=Text= | =Text= | ||
{{#Wiki_filter:Tennessee | {{#Wiki_filter:Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 | ||
Valley Authority, Post Office Box 2000, Spring City, Tennessee | |||
37381-2000 | ==Subject:== | ||
10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory | Watts Bar Nuclear Plant Unit 2 - Reply to Notice of Violation 05000391/2010603 Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers | ||
Commission | |||
ATTN: Document Control Desk Washington, D.C. 20555-0001 | ==References:== | ||
Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 Subject: Watts Bar Nuclear Plant Unit 2 -Reply to Notice of Violation 05000391/2010603 | : 1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction - | ||
NRC Integrated Inspection Report 05000391/2010603 and Notice of Violation," dated August 5, 2010 (ML102170465) | |||
Evaluate and Qualify Molded Case Circuit Breakers References: | : 2. TVA letter to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers," | ||
1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction | dated September 7, 2010 (ML102520435) | ||
: 3. TVA letter to NRC, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - | |||
Inspection | Additional Information," dated October 15, 2010 (ML102880493) | ||
Report 05000391/2010603 | : 4. NRC letter to TVA, "Response to Disputed Notice of Violation (NOV) 05000391/2010603-08," dated October 19, 2010 (ML102920665) | ||
and Notice of Violation," dated August 5, 2010 ( | The purpose of this letter is to further respond to Notice of Violation 391/2010603-08, "Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a {{letter dated|date=August 5, 2010|text=letter dated August 5, 2010}} (Reference 1). TVA initially denied the violation in a {{letter dated|date=September 7, 2010|text=letter dated September 7, 2010}} (Reference 2), and provided additional information in a {{letter dated|date=October 15, 2010|text=letter dated October 15, 2010}} (Reference 3). NRC subsequently | ||
Evaluate and Qualify Molded Case Circuit Breakers," dated September | |||
7, 2010 ( | U.S. Nuclear Regulatory Commission Page 2 November 24, 2010 concluded that the violation occurred as stated in a {{letter dated|date=October 19, 2010|text=letter dated October 19, 2010}} (Reference 4). | ||
Evaluate and Qualify Molded Case Circuit Breakers -Additional | TVA admits that the violation occurred and provides its reply in Enclosure 1. provides the list of commitments made in this letter. | ||
Information," dated October 15, 2010 (ML102880493) | The schedule for submitting this reply was discussed between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004. | ||
4. NRC letter to TVA, "Response | I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 4 th day of November, 2010. | ||
to Disputed Notice of Violation (NOV)05000391/2010603-08," dated October 19, 2010 (ML102920665) | Sincerely,9/ | ||
The purpose of this letter is to further respond to Notice of Violation | Masoud stani Watts r | ||
391/2010603-08,"Failure to Adequately | nit 2 Vice President Encl ures | ||
Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a letter dated August 5, 2010 (Reference | : 1. | ||
1). TVA initially | TVA's Reply to the Notice of Violation 391/2010603-08 | ||
denied the violation | : 2. | ||
in a letter dated September | List of Commitments cc (Enclosures): | ||
7, 2010 (Reference | U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 | ||
2), and provided additional | |||
information | Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08" Description of the Violation "10 CFR 50, Appendix B, Criterion Ill, "Design Control, "states that measures shall be established for the review for suitability of application of materials, parts, and equipment that are essential to the safety-related functions of the structures, systems, and components (SSCs). The design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying or checking processes, it shall include suitable qualifications testing of a prototype unit under the most adverse design conditions. | ||
in a letter dated October 15, 2010 (Reference | Contrary to the above, measures used to review the suitability of application of materials, parts, and equipment essential to the safety-related functions of molded case circuit breakers and measures to provide for the verification of checking the adequacy of design, such as, calculational methods, performing a suitable test program, including qualifications testing of a prototype unit under the most adverse design conditions, were not adequate in that: | ||
3). NRC subsequently | Example I On October 5, 2009, the applicant installed molded case circuit breakers into the 120VAC vital instrument power boards; however, the test program used to seismically qualify a prototype circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition." | ||
U.S. Nuclear Regulatory | TVA Response: | ||
Commission | TVA admits that the violation occurred. | ||
Page 2 November 24, 2010 concluded | Reason For The Violation - Example 1: | ||
that the violation | The reason for this violation is that Calculation WCG-ACQ-1 004 failed to fully establish that (1) the 1992 test mounting represented a suitable mounting method and that (2) the 1992 test bounded the configuration of the breakers installed in 2009. The calculation should have identified that the method of support for breakers within the board was a rigid mounting system which would have justified the 1992 testing for replacement breakers. | ||
occurred as stated in a letter dated October 19, 2010 (Reference | Corrective Steps That Have Been Taken And The Results Achieved (Example 1): | ||
4).TVA admits that the violation | : 1. TVA performed Calculation WCG-ACQ-1301 to verify the rigidity of the panel assembly. | ||
occurred and provides its reply in Enclosure | Corrective Steps That Will Be Taken: | ||
1. | : 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing. | ||
E1-1 | |||
made in this letter.The schedule for submitting | |||
this reply was discussed | Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08" | ||
between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004.I declare under penalty of perjury that the foregoing | : 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on this review, TVA will determine the appropriate implementing documents to be revised. | ||
is true and correct. Executed on the 2 4 th day of November, 2010.Sincerely, 9/Masoud stani Watts r nit 2 Vice President Encl ures 1. TVA's Reply to the Notice of Violation | : 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers. | ||
391/2010603-08 | Date When Full Compliance Will Be Achieved. | ||
2. List of Commitments | TVA will be in full compliance by March 18, 2011. | ||
cc (Enclosures): | Example 2 "On September 3, 2009, the applicant failed to perform an adequate review for suitability of application parts and material used to modify dimensional critical characteristics in molded case circuit breakers; further, the applicant failed to verify the adequacy of design for the modification and the effects on essential safety related functions of the circuit breakers." | ||
U. S. Nuclear Regulatory | Reason For The Violation - Example 2: | ||
Commission | The reason for this violation is that the manufacturer made a production change to the breaker configuration but did not revise the model number or publish schematics to reflect a component change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting impact on device seismic qualification and functionality. Rather than performing a new equivalency evaluation, TVA applied a technical evaluation for the original breakers and concluded that the breakers were seismically and functionally qualified. | ||
Region II Marquis One Tower 245 Peachtree | Corrective Steps That Have Been Taken And The Results Achieved (Example 2): | ||
Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 | : 1. TVA performed an equivalency evaluation for the reconfigured Heinemann breakers that identifies the critical characteristics, addresses the role of the Micarta insulation board in restoring the needed mounting depth for contact between the rear angles and front-face panel, and addresses seismic qualification requirements. | ||
NRC Resident Inspector | : 2. A unique identifier (CATID) was established for the reconfigured breaker to be used for future purchases of reconfigured breakers for WBN Units 1 and 2. Use of a unique ID will distinguish the reconfigured breakers from the original breakers. | ||
Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee | E1-2 | ||
Enclosure | Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08" | ||
I Watts Bar Nuclear Plant (WBN) Unit 2"Response | : 3. As an enhancement, TVA updated both the TVA and Westinghouse drawings to ensure consistency between drawings and with the installed configuration. | ||
to Notice of Violation (NOV) 05000391/2010603-08" Description | Corrective Steps That Will Be Taken: | ||
of the Violation"10 CFR 50, Appendix B, Criterion | : 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past. | ||
Ill, "Design Control, "states that measures shall be established | : 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e., | ||
for the review for suitability | demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections). | ||
of application | Date When Full Compliance Will Be Achieved. | ||
of materials, parts, and equipment that are essential | TVA will be in full compliance by March 18, 2011. | ||
to the safety-related | E1-3 | ||
functions | |||
of the structures, systems, and components (SSCs). The design control measures shall provide for verifying | I ý List of Commitments Example 1 | ||
or checking the adequacy of design, such as by the performance | : 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing. | ||
of design reviews, by the use of alternate | : 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by the following: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on the above review, TVA will determine the appropriate implementing documents to be revised. | ||
or simplified | : 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers. | ||
calculational | Example 2 | ||
methods, or by the performance | : 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past. | ||
of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying | : 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e., | ||
or checking processes, it shall include suitable qualifications | demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections). | ||
testing of a prototype | Date When Full Compliance Will Be Achieved. | ||
unit under the most adverse design conditions. | TVA will be in full compliance by March 18, 2011. | ||
Contrary to the above, measures used to review the suitability | E2-1}} | ||
of application | |||
of materials, parts, and equipment | |||
essential | |||
to the safety-related | |||
functions | |||
of molded case circuit breakers and measures to provide for the verification | |||
of checking the adequacy of design, such as, calculational | |||
methods, performing | |||
a suitable test program, including qualifications | |||
testing of a prototype | |||
unit under the most adverse design conditions, were not adequate in that: Example I On October 5, 2009, the applicant | |||
installed | |||
molded case circuit breakers into the 120VAC vital instrument | |||
power boards; however, the test program used to seismically | |||
qualify a prototype | |||
circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition." TVA Response: TVA admits that the violation | |||
occurred.Reason For The Violation | |||
-Example 1: The reason for this violation | |||
is that Calculation | |||
WCG-ACQ-1 | |||
004 failed to fully establish that (1) the 1992 test mounting represented | |||
a suitable mounting method and that (2) the 1992 test bounded the configuration | |||
of the breakers installed | |||
in 2009. The calculation | |||
should have identified | |||
that the method of support for breakers within the board was a rigid mounting system which would have justified | |||
the 1992 testing for replacement | |||
breakers.Corrective | |||
Steps That Have Been Taken And The Results Achieved (Example 1): 1. TVA performed | |||
Calculation | |||
WCG-ACQ-1301 | |||
to verify the rigidity of the panel assembly.Corrective | |||
Steps That Will Be Taken: 1. TVA will revise calculation | |||
WCG-ACQ-1004 | |||
to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement | |||
breaker testing.E1-1 | |||
Enclosure | |||
I Watts Bar Nuclear Plant (WBN) Unit 2"Response | |||
to Notice of Violation (NOV) 05000391/2010603-08" 2. As an enhancement | |||
to address any potentially | |||
misaligned | |||
breakers, TVA will review WBN maintenance | |||
and Unit 2 refurbishment | |||
procedures | |||
to ensure that the design basis for the breakers is maintained | |||
by: 1) that the procedures | |||
provide sufficient | |||
guidance that the breakers make positive contact with the angles in the rear, and 2)that the breakers project appropriately | |||
through the front-face | |||
panel openings after any maintenance | |||
involving | |||
full or partial removal of the front-face | |||
panel. In addition, the review will determine | |||
whether directions | |||
are needed to avoid excessive | |||
clamping pressure and to implement | |||
simple checks to status and correct for minor irregularities | |||
in contact between the Micarta insulation | |||
board and rear angles. Based on this review, TVA will determine | |||
the appropriate | |||
implementing | |||
documents | |||
to be revised.3. TVA will evaluate the installed | |||
breakers to ensure breaker operation | |||
will not be affected by the applied clamping breakers.Date When Full Compliance | |||
Will Be Achieved.TVA will be in full compliance | |||
by March 18, 2011.Example 2"On September | |||
3, 2009, the applicant | |||
failed to perform an adequate review for suitability | |||
of application | |||
parts and material used to modify dimensional | |||
critical characteristics | |||
in molded case circuit breakers; | |||
further, the applicant | |||
failed to verify the adequacy of design for the modification | |||
and the effects on essential | |||
safety related functions | |||
of the circuit breakers." Reason For The Violation | |||
-Example 2: The reason for this violation | |||
is that the manufacturer | |||
made a production | |||
change to the breaker configuration | |||
but did not revise the model number or publish schematics | |||
to reflect a component | |||
change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting | |||
impact on device seismic qualification | |||
and functionality. | |||
Rather than performing | |||
a new equivalency | |||
evaluation, TVA applied a technical | |||
evaluation | |||
for the original breakers and concluded | |||
that the breakers were seismically | |||
and functionally | |||
qualified. | |||
Corrective | |||
Steps That Have Been Taken And The Results Achieved (Example 2): 1. TVA performed | |||
an equivalency | |||
evaluation | |||
for the reconfigured | |||
Heinemann | |||
breakers that identifies | |||
the critical characteristics, addresses | |||
the role of the Micarta insulation | |||
board in restoring | |||
the needed mounting depth for contact between the rear angles and front-face | |||
panel, and addresses | |||
seismic qualification | |||
requirements. | |||
2. A unique identifier (CATID) was established | |||
for the reconfigured | |||
breaker to be used for future purchases | |||
of reconfigured | |||
breakers for WBN Units 1 and 2. Use of a unique ID will distinguish | |||
the reconfigured | |||
breakers from the original breakers.E1-2 | |||
Enclosure | |||
I Watts Bar Nuclear Plant (WBN) Unit 2"Response | |||
to Notice of Violation (NOV) 05000391/2010603-08" 3. As an enhancement, TVA updated both the TVA and Westinghouse | |||
drawings to ensure consistency | |||
between drawings and with the installed | |||
configuration. | |||
Corrective | |||
Steps That Will Be Taken: 1. Instructions | |||
will be issued to procurement | |||
and engineering | |||
organizations | |||
providing the necessary | |||
direction | |||
to use the unique CATID described | |||
above which will distinguish | |||
the reconfigured | |||
breakers from the original breakers. | |||
The CATID for original breakers will be retained to support the existing qualification | |||
of replacement | |||
original breakers procured in the past.2. TVA will revise calculation | |||
WCG-ACQ-1004 | |||
to confirm the design basis performance | |||
of the reconfigured | |||
breaker in support of the equivalency | |||
evaluation (i.e., demonstrate | |||
the breaker will function as designed with the current configuration | |||
of breaker and spacer board attachment | |||
in the clamping arrangement | |||
of rear angles and front-face | |||
panel sections). | |||
Date When Full Compliance | |||
Will Be Achieved.TVA will be in full compliance | |||
by March 18, 2011.E1-3 | |||
I ý | |||
Example 1 1. TVA will revise calculation | |||
WCG-ACQ-1004 | |||
to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement | |||
breaker testing.2. As an enhancement | |||
to address any potentially | |||
misaligned | |||
breakers, TVA will review WBN maintenance | |||
and Unit 2 refurbishment | |||
procedures | |||
to ensure that the design basis for the breakers is maintained | |||
by the following: | |||
1) that the procedures | |||
provide sufficient | |||
guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately | |||
through the front-face | |||
panel openings after any maintenance | |||
involving | |||
full or partial removal of the front-face | |||
panel. In addition, the review will determine | |||
whether directions | |||
are needed to avoid excessive | |||
clamping pressure and to implement | |||
simple checks to status and correct for minor irregularities | |||
in contact between the Micarta insulation | |||
board and rear angles. Based on the above review, TVA will determine | |||
the appropriate | |||
implementing | |||
documents | |||
to be revised.3. TVA will evaluate the installed | |||
breakers to ensure breaker operation | |||
will not be affected by the applied clamping breakers.Example 2 1. Instructions | |||
will be issued to procurement | |||
and engineering | |||
organizations | |||
providing the necessary | |||
direction | |||
to use the unique CATID described | |||
above which will distinguish | |||
the reconfigured | |||
breakers from the original breakers. | |||
The CATID for original breakers will be retained to support the existing qualification | |||
of replacement | |||
original breakers procured in the past.2. TVA will revise calculation | |||
WCG-ACQ-1004 | |||
to confirm the design basis performance | |||
of the reconfigured | |||
breaker in support of the equivalency | |||
evaluation (i.e., demonstrate | |||
the breaker will function as designed with the current configuration | |||
of breaker and spacer board attachment | |||
in the clamping arrangement | |||
of rear angles and front-face | |||
panel sections). | |||
Date When Full Compliance | |||
Will Be Achieved.TVA will be in full compliance | |||
by March 18, 2011.E2-1 | |||
}} | |||
Latest revision as of 01:11, 14 January 2025
| ML103300217 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 11/24/2010 |
| From: | Bajestani M Tennessee Valley Authority |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| Download: ML103300217 (6) | |
Text
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant Unit 2 - Reply to Notice of Violation 05000391/2010603 Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers
References:
- 1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction -
NRC Integrated Inspection Report 05000391/2010603 and Notice of Violation," dated August 5, 2010 (ML102170465)
- 2. TVA letter to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV)05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers,"
dated September 7, 2010 (ML102520435)
- 3. TVA letter to NRC, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV)05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers -
Additional Information," dated October 15, 2010 (ML102880493)
- 4. NRC letter to TVA, "Response to Disputed Notice of Violation (NOV)05000391/2010603-08," dated October 19, 2010 (ML102920665)
The purpose of this letter is to further respond to Notice of Violation 391/2010603-08, "Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a letter dated August 5, 2010 (Reference 1). TVA initially denied the violation in a letter dated September 7, 2010 (Reference 2), and provided additional information in a letter dated October 15, 2010 (Reference 3). NRC subsequently
U.S. Nuclear Regulatory Commission Page 2 November 24, 2010 concluded that the violation occurred as stated in a letter dated October 19, 2010 (Reference 4).
TVA admits that the violation occurred and provides its reply in Enclosure 1. provides the list of commitments made in this letter.
The schedule for submitting this reply was discussed between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 4 th day of November, 2010.
Sincerely,9/
Masoud stani Watts r
nit 2 Vice President Encl ures
- 1.
TVA's Reply to the Notice of Violation 391/2010603-08
- 2.
List of Commitments cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08" Description of the Violation "10 CFR 50, Appendix B, Criterion Ill, "Design Control, "states that measures shall be established for the review for suitability of application of materials, parts, and equipment that are essential to the safety-related functions of the structures, systems, and components (SSCs). The design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying or checking processes, it shall include suitable qualifications testing of a prototype unit under the most adverse design conditions.
Contrary to the above, measures used to review the suitability of application of materials, parts, and equipment essential to the safety-related functions of molded case circuit breakers and measures to provide for the verification of checking the adequacy of design, such as, calculational methods, performing a suitable test program, including qualifications testing of a prototype unit under the most adverse design conditions, were not adequate in that:
Example I On October 5, 2009, the applicant installed molded case circuit breakers into the 120VAC vital instrument power boards; however, the test program used to seismically qualify a prototype circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition."
TVA Response:
TVA admits that the violation occurred.
Reason For The Violation - Example 1:
The reason for this violation is that Calculation WCG-ACQ-1 004 failed to fully establish that (1) the 1992 test mounting represented a suitable mounting method and that (2) the 1992 test bounded the configuration of the breakers installed in 2009. The calculation should have identified that the method of support for breakers within the board was a rigid mounting system which would have justified the 1992 testing for replacement breakers.
Corrective Steps That Have Been Taken And The Results Achieved (Example 1):
- 1. TVA performed Calculation WCG-ACQ-1301 to verify the rigidity of the panel assembly.
Corrective Steps That Will Be Taken:
- 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.
E1-1
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08"
- 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on this review, TVA will determine the appropriate implementing documents to be revised.
- 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.
Date When Full Compliance Will Be Achieved.
TVA will be in full compliance by March 18, 2011.
Example 2 "On September 3, 2009, the applicant failed to perform an adequate review for suitability of application parts and material used to modify dimensional critical characteristics in molded case circuit breakers; further, the applicant failed to verify the adequacy of design for the modification and the effects on essential safety related functions of the circuit breakers."
Reason For The Violation - Example 2:
The reason for this violation is that the manufacturer made a production change to the breaker configuration but did not revise the model number or publish schematics to reflect a component change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting impact on device seismic qualification and functionality. Rather than performing a new equivalency evaluation, TVA applied a technical evaluation for the original breakers and concluded that the breakers were seismically and functionally qualified.
Corrective Steps That Have Been Taken And The Results Achieved (Example 2):
- 1. TVA performed an equivalency evaluation for the reconfigured Heinemann breakers that identifies the critical characteristics, addresses the role of the Micarta insulation board in restoring the needed mounting depth for contact between the rear angles and front-face panel, and addresses seismic qualification requirements.
- 2. A unique identifier (CATID) was established for the reconfigured breaker to be used for future purchases of reconfigured breakers for WBN Units 1 and 2. Use of a unique ID will distinguish the reconfigured breakers from the original breakers.
E1-2
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08"
- 3. As an enhancement, TVA updated both the TVA and Westinghouse drawings to ensure consistency between drawings and with the installed configuration.
Corrective Steps That Will Be Taken:
- 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
- 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,
demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).
Date When Full Compliance Will Be Achieved.
TVA will be in full compliance by March 18, 2011.
E1-3
I ý List of Commitments Example 1
- 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.
- 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by the following: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on the above review, TVA will determine the appropriate implementing documents to be revised.
- 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.
Example 2
- 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
- 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,
demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).
Date When Full Compliance Will Be Achieved.
TVA will be in full compliance by March 18, 2011.
E2-1