{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352 | ||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121) | SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121) | ||
==Dear Mr. Swank:== | ==Dear Mr. Swank:== | ||
Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations. | Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations. | ||
If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov. | If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov. | ||
Sincerely, rJlJ2ay~CJ~~~ | Sincerely, rJlJ2ay~CJ~~~ / | ||
rian E. Holian, Director Division of License Renewal | rian E. Holian, Director 0 | ||
Office of Nuclear Reactor Regulation Docket No. 50-397 | Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397 | ||
==Enclosure:== | ==Enclosure:== | ||
As stated cc w/encl: Listserv | |||
COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 1/19/10 1/20/10 Publish Federal Register Notice (FRN) - LRA availability 1/26/10 2/2110 Publish FRN - acceptancelrejection and opportunity for hearing 3/10/10 3/11/10 Publish FRN - Intent to conduct Environmental Scoping 3/10/10 3/11/10 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 4/6/10 4/6/10 Deadline for filing hearing requests and petitions for intervention 5/14/10 5/14/10 Environmental scoping period ends 5/14/10 5/14/10 Audit - Environmental 6/11/10 6/11/10 Issue draft supplemental environmental impact statement (SEIS) 8/2011 Public Meeting - draft SEIS meeting 9/2011 End of draft SEIS comment period 11/2011 Issue final SEIS 2/2012 ENCLOSURE | |||
COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestone | |||
June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352 | June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352 | ||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121) | SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121) | ||
==Dear Mr. Swank:== | ==Dear Mr. Swank:== | ||
Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations. | Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations. | ||
If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov. | If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov. | ||
Sincerely, IRA! | Sincerely, IRA! | ||
Brian | Brian Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397 | ||
==Enclosure:== | ==Enclosure:== | ||
As stated cc w/encl: Listserv DISTRIBUTION: | As stated cc w/encl: Listserv DISTRIBUTION: | ||
See next page ADAMS Accession Number: ML11151A222 | See next page ADAMS Accession Number: ML11151A222 | ||
*concurrence via email OFFICE LA: DLR* | |||
PM: DLR/RPB1 BC: DLR/RPB1 BPham NAME DDoyle 108/2011 06109/2011 06/10/2011 D:DLR OFFICIAL RECORD COpy | |||
Letter to David A. Swank from Brian H. Holian dated June 14, 2011 | Letter to David A. Swank from Brian H. Holian dated June 14, 2011 | ||
==SUBJECT:== | ==SUBJECT:== | ||
Latest revision as of 06:02, 13 January 2025
| ML11151A222 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 06/14/2011 |
| From: | Brian Holian Division of License Renewal |
| To: | Swank D Energy Northwest |
| Doyle D, 415-3748 | |
| References | |
| TAC ME3121 | |
| Download: ML11151A222 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121)
Dear Mr. Swank:
Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations.
If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov.
Sincerely, rJlJ2ay~CJ~~~ /
rian E. Holian, Director 0
Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
As stated cc w/encl: Listserv
COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 1/19/10 1/20/10 Publish Federal Register Notice (FRN) - LRA availability 1/26/10 2/2110 Publish FRN - acceptancelrejection and opportunity for hearing 3/10/10 3/11/10 Publish FRN - Intent to conduct Environmental Scoping 3/10/10 3/11/10 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 4/6/10 4/6/10 Deadline for filing hearing requests and petitions for intervention 5/14/10 5/14/10 Environmental scoping period ends 5/14/10 5/14/10 Audit - Environmental 6/11/10 6/11/10 Issue draft supplemental environmental impact statement (SEIS) 8/2011 Public Meeting - draft SEIS meeting 9/2011 End of draft SEIS comment period 11/2011 Issue final SEIS 2/2012 ENCLOSURE
June 14, 2011 Mr. David A. Swank Vice President, Engineering Columbia Generating Station Energy Northwest MD PE23 P.O. Box 968 Richland, WA 99352
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121)
Dear Mr. Swank:
Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staff's revised environmental review schedule for the Columbia Generating Station license renewal application. This revised schedule was established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. In developing the revised schedule, the NRC staff took several factors into consideration, including additional constraints on NRC staff resources affecting the environmental review and the previously extended review for severe accident mitigation alternatives. At this time, the staff does not anticipate that this change in the environmental review schedule will have an impact on the overall license renewal review schedule for Columbia Generating Station. The NRC staff will continue to follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations.
If you have any questions on the revised schedule, please contact Mr. Daniel Doyle, Project Manager for the review of the Columbia Generating Station license renewal environmental review, by telephone at 301-415-3748 or bye-mail at daniel.doyle@nrc.gov.
Sincerely, IRA!
Brian Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession Number: ML11151A222
- concurrence via email OFFICE LA: DLR*
PM: DLR/RPB1 BC: DLR/RPB1 BPham NAME DDoyle 108/2011 06109/2011 06/10/2011 D:DLR OFFICIAL RECORD COpy
Letter to David A. Swank from Brian H. Holian dated June 14, 2011
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE COLUMBIA GENERATING STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3121)
DISTRIBUTION:
HARD COPY:
DLR R/F PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource ACunanan Almboden LSubin,OGC MThadani, DORL ICouret,OPA VDricks, RIV BMaier, RIV WWalker, RIV NOkeefe, RIV GPick, RIV RCohen, RIV MHayes, RIV