IR 05000293/2011010: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (3 intermediate revisions by the same user not shown) | |||
| Line 3: | Line 3: | ||
| issue date = 06/10/2011 | | issue date = 06/10/2011 | ||
| title = IR 05000293/2011010; on 04/25/2011 - 04/29/2011; Pilgrim Nuclear Power Station; Review of License Renewal Activities | | title = IR 05000293/2011010; on 04/25/2011 - 04/29/2011; Pilgrim Nuclear Power Station; Review of License Renewal Activities | ||
| author name = Conte R | | author name = Conte R | ||
| author affiliation = NRC/RGN-I/DRS/EB1 | | author affiliation = NRC/RGN-I/DRS/EB1 | ||
| addressee name = Smith R | | addressee name = Smith R | ||
| addressee affiliation = Entergy Nuclear Operations, Inc | | addressee affiliation = Entergy Nuclear Operations, Inc | ||
| docket = 05000293 | | docket = 05000293 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:==SUBJECT:== | ||
PILGRIM NUCLEAR POWER 05000293/201 1010 | |||
SUBJECT: PILGRIM NUCLEAR | |||
==Dear Mr. Smith:== | ==Dear Mr. Smith:== | ||
UNITED STATES NUCLEAR REGULATORY COMMISSION | |||
==REGION I== | |||
475 ALLENDALE ROAD KING OF PRUSSIA. PA 19406-1415 June 10, 2011 STATION - NRC INSPECTION REPORT on April 29,2011, the U.S. Nuclear Regulatory commission (NRC) completed an inspection at the pilgrim Nuclear Power Station. The-encloied report documents the results of the inspection, which *"r" dir"rssed on April 29, 2011, with you and members of your staff' | |||
This inspection was an examination of license renewal activities under Temporary lnstruction (Tl) 2516/001, Review of License Renewal Activities. The inspection was directed toward those activities and facilities accessible during the refueling outage. The inspection also reviewed the completion of commitments made duririg the renewed license application process and compliance with the commission's rules-and regulations and the conditions of your operating license. Within these areas, the inspeciion invoived examination of selected procedures and representative records, observations of activities, and interviews with personnel' | |||
On the basis of the samples selected for review, there were no findings of significance identified during this inspection. tne NRC staff identified two instances of commitments which could not be considered completed at this time. Given the scheduled completion of June 8, 2012'for these commitments, we will incorporate a followup review as a part of our planned team inspection in this area prior to June 8,2012, to verify completion along with the completion of other commitments. ln accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.qov/readinq-rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, A*l*-['] e-}, | |||
NRC f nspection Report | Richard J. Conte, CMef Engineering Branchl Division of Reactor Safety Enclosure: | ||
NRC f nspection Report 0500029312011301 cc w/enclosure: Distribution via ListServ | |||
}} | }} | ||
Latest revision as of 05:54, 13 January 2025
| ML111610030 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 06/10/2011 |
| From: | Conte R Engineering Region 1 Branch 1 |
| To: | Rich Smith Entergy Nuclear Operations |
| References | |
| IR-11-010 | |
| Download: ML111610030 (12) | |
Text
SUBJECT:
PILGRIM NUCLEAR POWER 05000293/201 1010
Dear Mr. Smith:
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALE ROAD KING OF PRUSSIA. PA 19406-1415 June 10, 2011 STATION - NRC INSPECTION REPORT on April 29,2011, the U.S. Nuclear Regulatory commission (NRC) completed an inspection at the pilgrim Nuclear Power Station. The-encloied report documents the results of the inspection, which *"r" dir"rssed on April 29, 2011, with you and members of your staff'
This inspection was an examination of license renewal activities under Temporary lnstruction (Tl) 2516/001, Review of License Renewal Activities. The inspection was directed toward those activities and facilities accessible during the refueling outage. The inspection also reviewed the completion of commitments made duririg the renewed license application process and compliance with the commission's rules-and regulations and the conditions of your operating license. Within these areas, the inspeciion invoived examination of selected procedures and representative records, observations of activities, and interviews with personnel'
On the basis of the samples selected for review, there were no findings of significance identified during this inspection. tne NRC staff identified two instances of commitments which could not be considered completed at this time. Given the scheduled completion of June 8, 2012'for these commitments, we will incorporate a followup review as a part of our planned team inspection in this area prior to June 8,2012, to verify completion along with the completion of other commitments. ln accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.qov/readinq-rm/adams.html (the Public Electronic Reading Room).
Sincerely, A*l*-['] e-},
Richard J. Conte, CMef Engineering Branchl Division of Reactor Safety Enclosure:
NRC f nspection Report 0500029312011301 cc w/enclosure: Distribution via ListServ