{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:September 7, 2011  
                                  NU CLE AR RE G ULAT O RY CO M M I S S I O N
                                                    R E GI ON I V
                                          612 EAST LAMAR BLVD , SU ITE 400
Mr. Eric W. Olson  
                                          AR LIN GTON , TEXAS 76011-4125
Site Vice President  
                                        September 7, 2011
Entergy Operations, Inc.  
Mr. Eric W. Olson
River Bend Station  
Site Vice President
5485 US Highway 61N  
Entergy Operations, Inc.
St. Francisville, LA 70775  
River Bend Station
5485 US Highway 61N
SUBJECT: RIVER BEND STATION- NOTIFICATION OF INSPECTION (INSPECTION  
St. Francisville, LA 70775
REPORT 05000458/2011005) AND REQUEST FOR INFORMATION  
SUBJECT: RIVER BEND STATION- NOTIFICATION OF INSPECTION (INSPECTION
              REPORT 05000458/2011005) AND REQUEST FOR INFORMATION
Dear Mr. Olson:  
Dear Mr. Olson:
On November 14, 2011, the NRC will begin the on-site portion of the Gas Accumulation
On November 14, 2011, the NRC will begin the on-site portion of the Gas Accumulation  
Management in Emergency Core Cooling, Decay Heat Removal, and Containment Spray
Management in Emergency Core Cooling, Decay Heat Removal, and Containment Spray  
Systems Temporary Instruction at your River Bend Station. This inspection will be performed in
Systems Temporary Instruction at your River Bend Station. This inspection will be performed in  
accordance with NRC Temporary Instruction (TI) 2515/177.
accordance with NRC Temporary Instruction (TI) 2515/177.  
Experience has shown that this inspection is resource intensive, both for the NRC inspectors
and your staff. In order to minimize the impact to your on-site resources and to ensure a
Experience has shown that this inspection is resource intensive, both for the NRC inspectors  
productive inspection, we have enclosed a request for documents needed for this inspection.
and your staff. In order to minimize the impact to your on-site resources and to ensure a  
The documents have been divided into two groups.
productive inspection, we have enclosed a request for documents needed for this inspection.  
* The first group lists information necessary for our initial inspection scoping and in-office
The documents have been divided into two groups.  
  preparation activities. This information should be separated by information request number,
  especially if provided electronically (e.g., folder with the information request number). This
* The first group lists information necessary for our initial inspection scoping and in-office  
  information should be available to the inspector no later than October 31, 2011. Upon review
preparation activities. This information should be separated by information request number,  
  of these documents, the inspectors will select additional documentation for review upon
especially if provided electronically (e.g., folder with the information request number). This  
  arrival. By November 3, 2011, the inspector will communicate the initial selected samples.
information should be available to the inspector no later than October 31, 2011. Upon review  
* The second group of documents requested is needed to support our on-site inspection
of these documents, the inspectors will select additional documentation for review upon  
  activities. This set of documents should be available to the inspector on November 14, 2011.
arrival. By November 3, 2011, the inspector will communicate the initial selected samples.  
  It is also requested that corrective action documents and responses to questions developed
  during the inspection be provided to the inspector as the documents are generated.
* The second group of documents requested is needed to support our on-site inspection  
We have discussed the schedule for these inspection activities with your staff and understand
activities. This set of documents should be available to the inspector on November 14, 2011.
that our regulatory contact for this inspection will be Danny Williamson of your licensing
It is also requested that corrective action documents and responses to questions developed  
organization. If there are any questions about this inspection or the material requested, please
during the inspection be provided to the inspector as the documents are generated.  
contact the inspector, Matt Young, at 817-276-6545 or by email at matt.young@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
We have discussed the schedule for these inspection activities with your staff and understand  
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
that our regulatory contact for this inspection will be Danny Williamson of your licensing  
requirements were approved by the Office of Management and Budget, control
organization. If there are any questions about this inspection or the material requested, please  
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
contact the inspector, Matt Young, at 817-276-6545 or by email at matt.young@nrc.gov.  
respond to, a request for information or an information collection requirement unless the
This letter does not contain new or amended information collection requirements subject to the  
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection  
requirements were approved by the Office of Management and Budget, control  
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to  
respond to, a request for information or an information collection requirement unless the  
UNITED STATES
NUCLEAR REGULATORY COMMISSION
R E GI ON  I V
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125


Entergy Operations, Inc.                         -2-
Entergy Operations, Inc.  
requesting document displays a currently valid Office of Management and Budget control
- 2 -  
number.
In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of
requesting document displays a currently valid Office of Management and Budget control  
Practice, a copy of this letter and its enclosure will be available electronically for public
number.  
inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web
In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of  
site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Practice, a copy of this letter and its enclosure will be available electronically for public  
                                              Sincerely,
inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)  
                                              /RA/
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web  
                                              Thomas R. Farnholtz, Chief
site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
                                              Engineering Branch 1
                                              Division of Reactor Safety
Docket: 50-458
License: NPF-47
Enclosure:       Management of Gas Accumulation in Emergency Core Cooling, Decay Heat
                Removal, and Containment Spray Systems Temporary Instruction Document
                Request
cc w/encl:
Sincerely,
Distribution via ListServ for River Bend Station
/RA/  
Thomas R. Farnholtz, Chief  
Engineering Branch 1  
Division of Reactor Safety  
Docket: 50-458  
License: NPF-47  
Enclosure:  
Management of Gas Accumulation in Emergency Core Cooling, Decay Heat  
Removal, and Containment Spray Systems Temporary Instruction Document  
Request  
cc w/encl:  
Distribution via ListServ for River Bend Station  


Entergy Operations, Inc.                       -3-
Entergy Operations, Inc.  
Electronic distribution by RIV:
- 3 -  
Regional Administrator (Elmo.Collins@nrc.gov )
Deputy Regional Administrator (Art.Howell@nrc.gov )
Electronic distribution by RIV:  
DRP Director (Kriss.Kennedy@nrc.gov )
Regional Administrator (Elmo.Collins@nrc.gov )  
Acting DRP Deputy Director (Jeff.Clark@nrc.gov )
Deputy Regional Administrator (Art.Howell@nrc.gov )  
DRS Director (Anton.Vegel@nrc.gov )
DRP Director (Kriss.Kennedy@nrc.gov )  
DRS Deputy Director (Tom.Blount@nrc.gov )
Acting DRP Deputy Director (Jeff.Clark@nrc.gov )  
Senior Resident Inspector (Grant.Larkin@nrc.gov )
DRS Director (Anton.Vegel@nrc.gov )  
Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov )
DRS Deputy Director (Tom.Blount@nrc.gov )  
Resident Inspector (Andy.Barrett@nrc.gov )
Senior Resident Inspector (Grant.Larkin@nrc.gov )  
RBS Administrative Assistant (Lisa.Day@nrc.gov )
Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov )  
Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov )
Resident Inspector (Andy.Barrett@nrc.gov )  
Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov )
RBS Administrative Assistant (Lisa.Day@nrc.gov )  
Project Engineer, DRP/C (Jonathan.Braisted@nrc.gov )
Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov )  
Public Affairs Officer (Victor.Dricks@nrc.gov)
Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov )  
Public Affairs Officer (Lara.Uselding@nrc.gov )
Project Engineer, DRP/C (Jonathan.Braisted@nrc.gov )  
Project Manager (Alan.Wang@nrc.gov )
Public Affairs Officer (Victor.Dricks@nrc.gov)  
Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov )
Public Affairs Officer (Lara.Uselding@nrc.gov )  
RITS Coordinator (Marisa.Herrera@nrc.gov )
Project Manager (Alan.Wang@nrc.gov )  
Regional Counsel (Karla.Fuller@nrc.gov )
Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov )  
Congressional Affairs Officer (Jenny.Weil@nrc.gov )
RITS Coordinator (Marisa.Herrera@nrc.gov )  
OEMail Resource
Regional Counsel (Karla.Fuller@nrc.gov )  
  S:\DRS\REPORTS\RB TI-177 RFI-MRY                                     ML
Congressional Affairs Officer (Jenny.Weil@nrc.gov )  
  ADAMS          No Yes  SUNSI Review Complete                   Reviewer Initials: MRY
OEMail Resource  
Category B.1       Publicly Available               Non-sensitive
   
Category A             Non-publicly Available         Sensitive
KEYWORD: A.X                         Sensitive - XXX
RIV:DRS\RI                                                                 C:EB1
M. Young                                                                   T. Farnholtz
/RA/                                                                       /RA/
S:\\DRS\\REPORTS\\RB TI-177 RFI-MRY                                                           ML      
9/7/11                                                                     9/7/11
ADAMS
OFFICIAL RECORD COPY                                 T=Telephone       E=E-mail     F=Fax
  No  
  Yes  
  SUNSI Review Complete  
Reviewer Initials: MRY  
Category B.1  
  Publicly Available  
  Non-sensitive  
Category A  
  Non-publicly Available  
  Sensitive  
KEYWORD: A.X  
Sensitive - XXX  
RIV:DRS\\RI  
C:EB1  
M. Young  
T. Farnholtz  
/RA/  
/RA/  
9/7/11  
9/7/11  
OFFICIAL RECORD COPY
T=Telephone           E=E-mail       F=Fax


    MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY
MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY  
  HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION
HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION  
                                      DOCUMENT REQUEST
DOCUMENT REQUEST  
Inspection Report:               05000458/2011005
Inspection Dates:               November 14-17, 2011
- 1 -
Inspection Procedure:           TI 2515/177, Management of Gas Accumulation in Emergency
Enclosure
                                Core Cooling, Decay Heat Removal, and Containment Spray
                                Systems
Inspection Report:
Inspectors:                     Matthew Young, Reactor Inspector
05000458/2011005  
                                (817) 276-6545
Inspection Dates:  
                                matt.young@nrc.gov
The following information should be sent to the Region IV office in hard copy or electronic
November 14-17, 2011  
format (ims.certrec.com or compact disc, preferred), in care of Matt Young, to facilitate the
Inspection Procedure:  
selection of specific items that will be reviewed during the on-site inspection week. The
TI 2515/177, Management of Gas Accumulation in Emergency  
inspector will select specific items from the information requested below and then request from
Core Cooling, Decay Heat Removal, and Containment Spray  
your staff additional documents needed during the on-site inspection weeks. Also, we request
Systems  
that you categorize the documents in your response with the numbered list below. Please
Inspectors:  
provide requested documentation electronically if possible. If requested documents are large
and only hard copy formats are available, please inform the inspector(s), and provide subject
documentation during the first day of the on-site inspection. If you have any questions
Matthew Young, Reactor Inspector  
regarding this information request, please call the inspector as soon as possible.
I. Information Requested By October 31, 2011
    1. List of corrective action program documents (with a short description) associated with
        GL 2008-01, voids in piping, and pressure transients for the previous three years.
    2. List of changes (with a short description and tracking number) to the final safety analysis
        report (FSAR), technical specifications, technical specification bases, and technical
(817) 276-6545  
        requirements manual associated with the resolution of GL 2008-01.
    3. List of calculations associated with GL 2008-01, including calculations that have been
        changed or created in response to GL 2008-01 (with a short description of the
        calculation and the change).
    4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the
        affected system locations (e.g. identify the source, conditions, and expected void
matt.young@nrc.gov
        locations). Also include a short description of how each gas intrusion mechanism has
        been addressed (eg. plant hardware modification, procedure change).
                                              -1-                                        Enclosure
The following information should be sent to the Region IV office in hard copy or electronic  
format (ims.certrec.com or compact disc, preferred), in care of Matt Young, to facilitate the  
selection of specific items that will be reviewed during the on-site inspection week. The  
inspector will select specific items from the information requested below and then request from  
your staff additional documents needed during the on-site inspection weeks. Also, we request  
that you categorize the documents in your response with the numbered list below. Please  
provide requested documentation electronically if possible. If requested documents are large  
and only hard copy formats are available, please inform the inspector(s), and provide subject  
documentation during the first day of the on-site inspection. If you have any questions  
regarding this information request, please call the inspector as soon as possible.  
I. Information Requested By October 31, 2011  
1. List of corrective action program documents (with a short description) associated with  
GL 2008-01, voids in piping, and pressure transients for the previous three years.  
2. List of changes (with a short description and tracking number) to the final safety analysis  
report (FSAR), technical specifications, technical specification bases, and technical  
requirements manual associated with the resolution of GL 2008-01.  
3. List of calculations associated with GL 2008-01, including calculations that have been  
changed or created in response to GL 2008-01 (with a short description of the  
calculation and the change).  
4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the  
affected system locations (e.g. identify the source, conditions, and expected void  
locations). Also include a short description of how each gas intrusion mechanism has  
been addressed (eg. plant hardware modification, procedure change).  


MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY
MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY  
HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION
HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION  
                                    DOCUMENT REQUEST
DOCUMENT REQUEST  
  5. List of the suction piping sections identified as susceptible to gas accumulation (the list
   
    should identify the corresponding system).
- 2 -
  6. List of the discharge piping sections identified as susceptible to gas accumulation (the
Enclosure
    list should identify the corresponding system).
5. List of the suction piping sections identified as susceptible to gas accumulation (the list  
  7. Copies of isometric drawings of the plant systems within scope of GL 2008-01 (hard-
should identify the corresponding system).  
    copies are preferred).
   
  8. Copies of piping and instrumentation diagrams (P&IDs) of the plant systems within
6. List of the discharge piping sections identified as susceptible to gas accumulation (the  
    scope of GL 2008-01 (hard-copies are preferred). Please highlight any components that
list should identify the corresponding system).  
    were part of hardware modifications installed as part of the resolution of GL 2008-01 and
   
    all high point vents that are monitored during void surveillances.
7. Copies of isometric drawings of the plant systems within scope of GL 2008-01 (hard-
  9. Copies of program documents and procedures developed to implement the resolution of
copies are preferred).  
    GL 2008-01.
   
  10. List of actions that were completed in response to GL 2008-01.
8. Copies of piping and instrumentation diagrams (P&IDs) of the plant systems within  
  11. Copies of the modification packages for hardware modifications as part of the resolution
scope of GL 2008-01 (hard-copies are preferred). Please highlight any components that  
    of GL 2008-01.
were part of hardware modifications installed as part of the resolution of GL 2008-01 and  
  12. Design basis documents of the plant systems within scope of GL 2008-01.
all high point vents that are monitored during void surveillances.  
  13. Design basis documents of keep-full systems of the plant systems within scope of
   
    GL 2008-01.
9. Copies of program documents and procedures developed to implement the resolution of  
  14. System walkdown reports associated with the resolution of GL 2008-01.
GL 2008-01.  
15. If applicable, provide a list of inaccessible locations where plant walkdowns of the plant
   
    systems within scope of GL 2008-01 have not been completed. Include an explanation
10. List of actions that were completed in response to GL 2008-01.  
    of why each area is considered inaccessible.
   
  16. Copies of surveillance procedures associated with the resolution of GL 2008-01 and the
11. Copies of the modification packages for hardware modifications as part of the resolution  
    results of the last two surveillances for the plant systems within scope of GL 2008-01.
of GL 2008-01.  
  17. Copies of procedures used for filling and venting.
   
  18. Copies of trends of periodic venting results.
12. Design basis documents of the plant systems within scope of GL 2008-01.  
  19. Copies of the engineering evaluations performed for all identified voids.
   
  20. Basis for the void acceptance criteria (e.g. calculation). If applicable, provide the
13. Design basis documents of keep-full systems of the plant systems within scope of
    justification for any deviation from the void acceptance criteria established by the Office
GL 2008-01.  
    of Nuclear Reactor Regulation (NRR).
   
                                            -2-                                          Enclosure
14. System walkdown reports associated with the resolution of GL 2008-01.  
 
15. If applicable, provide a list of inaccessible locations where plant walkdowns of the plant  
systems within scope of GL 2008-01 have not been completed. Include an explanation  
of why each area is considered inaccessible.  
   
16. Copies of surveillance procedures associated with the resolution of GL 2008-01 and the  
results of the last two surveillances for the plant systems within scope of GL 2008-01.  
   
17. Copies of procedures used for filling and venting.  
   
18. Copies of trends of periodic venting results.  
   
19. Copies of the engineering evaluations performed for all identified voids.  
   
20. Basis for the void acceptance criteria (e.g. calculation). If applicable, provide the  
justification for any deviation from the void acceptance criteria established by the Office  
of Nuclear Reactor Regulation (NRR).  


    MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY
MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY  
    HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION
HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION  
                                        DOCUMENT REQUEST
DOCUMENT REQUEST  
    21. Copies of any void transport analyses.
    22. Copies of vortexing calculations associated with systems under the scope of GL 2008-
- 3 -
        01.
Enclosure
    23. Copies of self-assessments associated with the implementation of the GL 2008-01
21. Copies of any void transport analyses.  
        program.
II. Information Requested By November 14, 2011
22. Copies of vortexing calculations associated with systems under the scope of GL 2008-
    24. Copies of the selected corrective action program documents.
01.  
    25. Copies of the selected licensing and design basis document changes.
    26. Copies of the selected calculations.
23. Copies of self-assessments associated with the implementation of the GL 2008-01  
    27. Copies of training modules and attendance records that ensure that personnel are aware
program.  
        of gas-related concerns.
    28. Copies of corrective action program implementing procedures.
    29. Electronic copies of the current technical specifications, technical specification bases,
II. Information Requested By November 14, 2011  
        final safety analysis report, and technical requirements manual.
Inspector Contact Information:
24. Copies of the selected corrective action program documents.  
US NRC Region IV
Attn: Matt Young
25. Copies of the selected licensing and design basis document changes.  
612 E. Lamar Blvd., Suite 400
Arlington, TX 76011-4125
26. Copies of the selected calculations.  
                                              -3-                                          Enclosure
27. Copies of training modules and attendance records that ensure that personnel are aware  
of gas-related concerns.  
28. Copies of corrective action program implementing procedures.  
29. Electronic copies of the current technical specifications, technical specification bases,  
final safety analysis report, and technical requirements manual.  
Inspector Contact Information:  
US NRC Region IV  
Attn: Matt Young  
612 E. Lamar Blvd., Suite 400  
Arlington, TX 76011-4125
}}
}}

Latest revision as of 02:12, 13 January 2025

IR 05000458-11-005, on 11/14/2011, River Bend Station - Notification of Inspection and Request for Information
ML11250A063
Person / Time
Site: River Bend Entergy icon.png
Issue date: 09/07/2011
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Olson E
Entergy Operations
References
IR-11-005
Download: ML11250A063 (6)


See also: IR 05000458/2011005

Text

September 7, 2011

Mr. Eric W. Olson

Site Vice President

Entergy Operations, Inc.

River Bend Station

5485 US Highway 61N

St. Francisville, LA 70775

SUBJECT: RIVER BEND STATION- NOTIFICATION OF INSPECTION (INSPECTION

REPORT 05000458/2011005) AND REQUEST FOR INFORMATION

Dear Mr. Olson:

On November 14, 2011, the NRC will begin the on-site portion of the Gas Accumulation

Management in Emergency Core Cooling, Decay Heat Removal, and Containment Spray

Systems Temporary Instruction at your River Bend Station. This inspection will be performed in

accordance with NRC Temporary Instruction (TI) 2515/177.

Experience has shown that this inspection is resource intensive, both for the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

The documents have been divided into two groups.

  • The first group lists information necessary for our initial inspection scoping and in-office

preparation activities. This information should be separated by information request number,

especially if provided electronically (e.g., folder with the information request number). This

information should be available to the inspector no later than October 31, 2011. Upon review

of these documents, the inspectors will select additional documentation for review upon

arrival. By November 3, 2011, the inspector will communicate the initial selected samples.

  • The second group of documents requested is needed to support our on-site inspection

activities. This set of documents should be available to the inspector on November 14, 2011.

It is also requested that corrective action documents and responses to questions developed

during the inspection be provided to the inspector as the documents are generated.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Danny Williamson of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the inspector, Matt Young, at 817-276-6545 or by email at matt.young@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Entergy Operations, Inc.

- 2 -

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of

Practice, a copy of this letter and its enclosure will be available electronically for public

inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web

site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket: 50-458

License: NPF-47

Enclosure:

Management of Gas Accumulation in Emergency Core Cooling, Decay Heat

Removal, and Containment Spray Systems Temporary Instruction Document

Request

cc w/encl:

Distribution via ListServ for River Bend Station

Entergy Operations, Inc.

- 3 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov )

Deputy Regional Administrator (Art.Howell@nrc.gov )

DRP Director (Kriss.Kennedy@nrc.gov )

Acting DRP Deputy Director (Jeff.Clark@nrc.gov )

DRS Director (Anton.Vegel@nrc.gov )

DRS Deputy Director (Tom.Blount@nrc.gov )

Senior Resident Inspector (Grant.Larkin@nrc.gov )

Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov )

Resident Inspector (Andy.Barrett@nrc.gov )

RBS Administrative Assistant (Lisa.Day@nrc.gov )

Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov )

Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov )

Project Engineer, DRP/C (Jonathan.Braisted@nrc.gov )

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov )

Project Manager (Alan.Wang@nrc.gov )

Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov )

RITS Coordinator (Marisa.Herrera@nrc.gov )

Regional Counsel (Karla.Fuller@nrc.gov )

Congressional Affairs Officer (Jenny.Weil@nrc.gov )

OEMail Resource

S:\\DRS\\REPORTS\\RB TI-177 RFI-MRY ML

ADAMS

No

Yes

SUNSI Review Complete

Reviewer Initials: MRY

Category B.1

Publicly Available

Non-sensitive

Category A

Non-publicly Available

Sensitive

KEYWORD: A.X

Sensitive - XXX

RIV:DRS\\RI

C:EB1

M. Young

T. Farnholtz

/RA/

/RA/

9/7/11

9/7/11

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY

HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION

DOCUMENT REQUEST

- 1 -

Enclosure

Inspection Report: 05000458/2011005

Inspection Dates:

November 14-17, 2011

Inspection Procedure:

TI 2515/177, Management of Gas Accumulation in Emergency

Core Cooling, Decay Heat Removal, and Containment Spray

Systems

Inspectors:

Matthew Young, Reactor Inspector

(817) 276-6545

matt.young@nrc.gov

The following information should be sent to the Region IV office in hard copy or electronic

format (ims.certrec.com or compact disc, preferred), in care of Matt Young, to facilitate the

selection of specific items that will be reviewed during the on-site inspection week. The

inspector will select specific items from the information requested below and then request from

your staff additional documents needed during the on-site inspection weeks. Also, we request

that you categorize the documents in your response with the numbered list below. Please

provide requested documentation electronically if possible. If requested documents are large

and only hard copy formats are available, please inform the inspector(s), and provide subject

documentation during the first day of the on-site inspection. If you have any questions

regarding this information request, please call the inspector as soon as possible.

I. Information Requested By October 31, 2011

1. List of corrective action program documents (with a short description) associated with

GL 2008-01, voids in piping, and pressure transients for the previous three years.

2. List of changes (with a short description and tracking number) to the final safety analysis

report (FSAR), technical specifications, technical specification bases, and technical

requirements manual associated with the resolution of GL 2008-01.

3. List of calculations associated with GL 2008-01, including calculations that have been

changed or created in response to GL 2008-01 (with a short description of the

calculation and the change).

4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the

affected system locations (e.g. identify the source, conditions, and expected void

locations). Also include a short description of how each gas intrusion mechanism has

been addressed (eg. plant hardware modification, procedure change).

MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY

HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION

DOCUMENT REQUEST

- 2 -

Enclosure

5. List of the suction piping sections identified as susceptible to gas accumulation (the list

should identify the corresponding system).

6. List of the discharge piping sections identified as susceptible to gas accumulation (the

list should identify the corresponding system).

7. Copies of isometric drawings of the plant systems within scope of GL 2008-01 (hard-

copies are preferred).

8. Copies of piping and instrumentation diagrams (P&IDs) of the plant systems within

scope of GL 2008-01 (hard-copies are preferred). Please highlight any components that

were part of hardware modifications installed as part of the resolution of GL 2008-01 and

all high point vents that are monitored during void surveillances.

9. Copies of program documents and procedures developed to implement the resolution of

GL 2008-01.

10. List of actions that were completed in response to GL 2008-01.

11. Copies of the modification packages for hardware modifications as part of the resolution

of GL 2008-01.

12. Design basis documents of the plant systems within scope of GL 2008-01.

13. Design basis documents of keep-full systems of the plant systems within scope of

GL 2008-01.

14. System walkdown reports associated with the resolution of GL 2008-01.

15. If applicable, provide a list of inaccessible locations where plant walkdowns of the plant

systems within scope of GL 2008-01 have not been completed. Include an explanation

of why each area is considered inaccessible.

16. Copies of surveillance procedures associated with the resolution of GL 2008-01 and the

results of the last two surveillances for the plant systems within scope of GL 2008-01.

17. Copies of procedures used for filling and venting.

18. Copies of trends of periodic venting results.

19. Copies of the engineering evaluations performed for all identified voids.

20. Basis for the void acceptance criteria (e.g. calculation). If applicable, provide the

justification for any deviation from the void acceptance criteria established by the Office

of Nuclear Reactor Regulation (NRR).

MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY

HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSPECTION

DOCUMENT REQUEST

- 3 -

Enclosure

21. Copies of any void transport analyses.

22. Copies of vortexing calculations associated with systems under the scope of GL 2008-

01.

23. Copies of self-assessments associated with the implementation of the GL 2008-01

program.

II. Information Requested By November 14, 2011

24. Copies of the selected corrective action program documents.

25. Copies of the selected licensing and design basis document changes.

26. Copies of the selected calculations.

27. Copies of training modules and attendance records that ensure that personnel are aware

of gas-related concerns.

28. Copies of corrective action program implementing procedures.

29. Electronic copies of the current technical specifications, technical specification bases,

final safety analysis report, and technical requirements manual.

Inspector Contact Information:

US NRC Region IV

Attn: Matt Young

612 E. Lamar Blvd., Suite 400

Arlington, TX 76011-4125